{"document":{"slug":"rec-20261116-5105","title":"Tariff Revisions to Address Commission's EL26-71 Order to Show Cause","issued":"2026-11-16","accession":"20261116-5105","docket":"ER27-499-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"Citizens Sunrise Transmission LLC","kind":"tariff filing","file":"sources/filings/text/20261116-5105_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5105","tier":"record","sha256":"837ee55209e15cd1f765f54083b5dd14e8837dd364af53c58aaae77b9ddb7d21","pages":5,"tokens":1369,"emptyPages":[],"textThemes":["study"]},"pages":[{"page":1,"startToken":0,"endToken":215,"text":"Duncan \n&Allen LLP \n \n1730 Rhode Island Avenue, Northwest \nWashington, D.C. 20036 \nTelephone (202) 289-8400 \nFAX (202) 289-8450 \n \nCOUNSELLORS AT LAW \n \n \nNovember 16, 2026 \n \n \nVIA ELECTRONIC FILING \n \nDebbie-Anne A. Reese \n Secretary \nFederal Energy Regulatory Commission \n888 First Street, NW \nWashington, DC 20426 \n \nRe:  \nCitizens Sunrise Transmission LLC Tariff Revisions to \nAddress Commission’s Docket No. EL26-71 Order to Show \nCause, Docket No. ER27-___-000 \n \n \nDear Secretary Reese: \n \nOn June 18, 2026 the Commission issued its Order Instituting \nProceeding Under Section 206 of the Federal Power Act (“Show Cause \nOrder”),1 requiring each Participating Transmission Owner (“PTO”) within \nthe California Independent System Operator’s (“CAISO”) system to address \nissues associated with serving large load and co-location arrangements.  In \nthis filing, pursuant to Section 205 of the Federal Power Act, Citizens \nSunrise Transmission LLC (“Citizens Sunrise”) files proposed revisions to its \nTransmission Owner Tariff (“TO Tariff”) to address the issues raised in the \nShow Cause Order.  Citizens Sunrise respectfully requests that the \nCommission accept these TO Tariff revisions to become effective January 15, \n2027, which is sixty (60) days from the date of this filing. \n \n \nI. \nBACKGROUND ON CITIZENS SUNRISE \n \nCitizens Sunrise is a wholly owned subsidiary of Citizens Energy \nCorporation, a non-profit organization dedicated to making life’s basic needs \n \n1  \nCAISO et al., 195 FERC ¶61,214 (2026)."},{"page":2,"startToken":215,"endToken":544,"text":"Duncan \n& Allen LLP \n- 2 - \n \nmore affordable through successful business ventures.  To date, Citizens \nEnergy Corporation has donated more than $600 million to programs \nsupporting the most vulnerable in our communities.   \n \nIn 2012, Citizens Sunrise invested approximately $86 million with San \nDiego Gas & Electric Company (“SDG&E”) in the Sunrise Powerlink Project \n(“Sunrise Project”) in exchange for a 30-year leasehold interest in \napproximately 50% interest in a specific segment of the Sunrise Project.2  \nCitizens Sunrise does not own any of the actual facilities.  SDG&E retains \nownership and operation and maintenance responsibilities.  Citizens Sunrise \nbecame a CAISO PTO, turned its interest in the Sunrise Project over to the \nCAISO’s operational control and recovers its costs through its TO Tariff.  As \nreflected in its TO Tariff, Citizens Sunrise is a “Non-Load-Serving \nParticipating TO and has no End-Use Customers.”3 \n \nAs part of Citizens Energy Corporation’s charitable mission, Citizens \nSunrise is contractually committed to dedicate 50% of its net after-tax cash \nflows from the Sunrise Project to programs assisting low-income families in \nImperial County.  To date, the Sunrise Project has generated $20 million in \ncharitable donations, which are currently being used to support the country’s \nlargest community solar project which is saving low-income ratepayers in the \nImperial Valley an average of $350 a year on their electric bills.  Citizens \nSunrise estimates its involvement in the Sunrise Project will generate \napproximately $45 million in charitable assistance over the term of the lease. \n \n \nII. \nRESPONSE TO SHOW CAUSE ORDER \n \n \nThe Commission’s Show Cause Order determined that the TO Tariffs \nof the CAISO PTOs, including Citizens Sunrise, “lack provisions that \naddress, with sufficient clarity and consistency” how each PTO “will timely \nstudy…the provision of transmission service to Eligible Customers on behalf \nof large loads.”4  The Commission directed each PTO to either justify why its \n \n2  \nSunrise TO Tariff Section 3.70 definition of “Project”. \n3  \nSunrise TO Tariff Section 1 “Preamble”. \n4  \nShow Cause Order, 195 FERC ¶61,214 at P 38."},{"page":3,"startToken":544,"endToken":890,"text":"Duncan \n& Allen LLP \n- 3 - \n \nTO Tariff remained just and reasonable, or to provide TO Tariff revisions \nnecessary to remedy the Commission’s concerns.   \n \nAs discussed in more detail below, Citizens Sunrise has a limited, \nleasehold interest in only a portion of the overall Sunrise Project \ntransmission line.  Ownership of the transmission line, as well as \nresponsibility for operating and maintaining the line, remains with SDG&E.  \nFor these reasons, Citizens Sunrise proposes revisions to its TO Tariff to \nmake clear that any study, planning, interconnection or expansion requests \nrelated to Citizens Sunrise’s interest in the Sunrise Project will be governed \nby the relevant provisions of the SDG&E TO Tariff. \n \nA. \nRelevant Existing TO Tariff Provisions \n \nCitizens Sunrise’s current TO Tariff recognizes the limited nature of \nits interest in the Sunrise Project.  Section 16.12 of Citizens Sunrise’ current \nTO Tariff states that for so long as the Transfer Capability Lease between \nCitizens Sunrise and SDG&E is in effect, Sections 8 (“Obligation to \nInterconnect or Construct Transmission Expansions and Facility Upgrades”), \n9 (“Expansion Process”), and 10 (“Interconnection Process”) of the Citizens \nSunrise Tariff will be “superseded by the corresponding sections of the TO \nTariff of San Diego Gas & Electric.”5  Article III of the Transfer Capability \nLease, which is included at Appendix II to the Sunrise TO Tariff, outlines the \ndivision of responsibility between SDG&E and Citizens Sunrise, with \nSDG&E retaining all responsibility for operation and maintenance6 and to \nact as the interconnection agent for the Sunrise Project.7   \n \nThese existing provisions illustrate that any responsibility for studying \nor serving large load customers or addressing the needs of co-located \narrangements is beyond the scope of Citizens Sunrise’s limited authority as a \nnon-load serving PTO with no end-use customers and a limited interest in a \nportion of a single transmission line segment within SDG&E’s system. \n \n5  \nSunrise TO Tariff Section 16.12. \n6  \nSection 3.2 of the Transfer Capability Lease, Appendix II to the Sunrise TO \nTariff. \n7  \nSection 3.6 of the Transfer Capability Lease, Appendix II to the Sunrise TO \nTariff."},{"page":4,"startToken":890,"endToken":1193,"text":"Duncan \n& Allen LLP \n- 4 - \n \n \nB. \nProposed TO Tariff Provision Revisions \n \nIn response to the Show Cause Order, Citizens Sunrise is proposing a \nseries of revisions to its TO Tariff to ensure it is clear that when it comes to \nall interconnection matters, including interconnection and service of large \nload customers or co-located arrangements, the appropriate TO Tariff \nprovisions are those of SDG&E.  These revisions include the following: \n \n• Revisions to the definitions of Expedited Interconnection Agreement, \nFacilities Study Agreement, Facility or Facilities Study, \nInterconnection, Interconnection Agreement, Interconnection \nApplication, Reliability Upgrade, Requests for Expedited \nInterconnection Procedures, System Impact Study, and System Impact \nStudy Agreement, each to clarify that SDG&E’s TO Tariff provisions \nwill govern. \n \n• Added new language to Section 8, Obligations to Interconnect or \nConstruct Transmission and Expansions and Facility Upgrades, to \nconfirm that all conduct that falls under Section 8 will be governed by \nSDG&E’s TO Tariff. \n \n• Added new language to Section 9, Expansion Process, to confirm that \nall conduct that falls under Section 9 will be governed by SDG&E’s TO \nTariff. \n \n• Added new language to Section 10, Interconnection Process, to confirm \nthat all conduct that falls under Section 10 will be governed by \nSDG&E’s TO Tariff. \n \n• Citizens Sunrise additionally makes a series of administrative \nrevisions to address typos, update addresses, and similar type changes \nwith this filing. \n \nEach of these revisions is shown in redline in Attachment B to this filing, \nwhich is a redline of the Citizens Sunrise TO Tariff.  A clean version of the \nrevised TO Tariff is included as Attachment A. \n \nCitizens Sunrise respectfully submits that these revisions address the \nconcerns raised in the Show Cause Order within the bounds of Citizens \nSunrise’s limited interest in, and control over, the Sunrise Project.  Put \nsimply, Citizens Sunrise is bound by the terms of its Transfer Capability"},{"page":5,"startToken":1193,"endToken":1369,"text":"Duncan \n& Allen LLP \n- 5 - \n \nLease with SDG&E, and that agreement makes it clear that SDG&E, as the \nowner and operator of the Sunrise Project, has the authority and \nresponsibility for all operational and interconnection related matters. \n \n \nTo the extent that the CAISO or SDG&E propose TO Tariff revisions \nthat impact the revisions Citizens Sunrise proposes in this filing, Citizens \nSunrise commits to making a compliance filing to ensure its TO Tariff \nremains consistent. \n  \n \nIII. \nREQUESTED EFFECTIVE DATE \n \nCitizens Sunrise requests an effective date for the revised TO Tariff of \nJanuary 15, 2027. \n \nVIII. CONCLUSION \n \n \nCitizens Sunrise respectfully requests that the Commission accept \nthese proposed tariff revision effective as of January 15, 2027, and determine \nthat Citizens Sunrise has satisfied the concerns the Commission identified in \nits Show Cause Order. \n \n \n \n \n \n \n \n \nRespectfully submitted, \n \n \n \n \n \n \n \n \n/s/ Ashley M. Bond \n \n \n \n \n \n \n \n \nAshley M. Bond \n \n \n \n \n \n \nAmy E. McDonnell \nDuncan & Allen LLP \n1730 Rhode Island Ave. N.W. \nSuite 700 \nWashington, D.C.  20036 \n(202) 289-8400 \namb@duncanallen.com \naem@duncanallen.com \n \nCounsel for Citizens Sunrise \nTransmission LLC  \n \nNovember 16, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1293,"startToken":0,"endToken":181},{"p":1,"at":1293,"title":"I. BACKGROUND ON CITIZENS SUNRISE","method":"printed heading","endPage":2,"endAt":1639,"startToken":181,"endToken":454},{"p":2,"at":1639,"title":"II. RESPONSE TO SHOW CAUSE ORDER","method":"printed heading","endPage":3,"endAt":725,"startToken":454,"endToken":653},{"p":3,"at":725,"title":"A. Relevant Existing TO Tariff Provisions","method":"printed heading","endPage":4,"endAt":32,"startToken":653,"endToken":894},{"p":4,"at":32,"title":"B. Proposed TO Tariff Provision Revisions","method":"printed heading","endPage":5,"endAt":487,"startToken":894,"endToken":1269},{"p":5,"at":487,"title":"III. REQUESTED EFFECTIVE DATE","method":"printed heading","endPage":5,"endAt":616,"startToken":1269,"endToken":1288},{"p":5,"at":616,"title":"VIII. CONCLUSION","method":"printed heading","endPage":5,"endAt":1239,"startToken":1288,"endToken":1369}]}