{"document":{"slug":"rec-20261116-5210-3","title":"SCE TO Tariff Revisions_Sect205-OSC LL_MARKED","issued":"2026-11-16","accession":"20261116-5210","docket":"ER27-508-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"Southern California Edison Company","kind":"attachment","file":"sources/filings/text/20261116-5210_003.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5210","tier":"record","parent":"rec-20261116-5210","sha256":"c9feea20cfafe47f17304810831585e52fdb9fe8f6062b8ee3d0e021107ad052","pages":58,"tokens":14309,"emptyPages":[],"textThemes":["study","cost","flex"]},"pages":[{"page":1,"startToken":0,"endToken":13,"text":"ATTACHMENT B \n \nRedlined TO Tariff Sheets \nSections 1, 3, 4, 7-10, and 13"},{"page":2,"startToken":13,"endToken":278,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n \nTABLE OF CONTENTS \n \n \n1.  PREAMBLE ...............................................................................................................................  \n1.1  Transmission Access for Participating TOs ................................................................  \n1.2  Transmission Access for Wheeling Customers ..........................................................  \n1.3  Transmission Access for End-Users ...........................................................................  \n2.  EFFECTIVE DATE ....................................................................................................................  \n3.  TO DEFINITIONS ......................................................................................................................  \n4.  ELIGIBILITY ..............................................................................................................................  \n5.  ACCESS CHARGES AND TRANSMISSION RATES...............................................................  \n5.1  Low Voltage Access Charge .........................................................................................  \n5.2  Wheeling Access Charge ..............................................................................................  \n5.3  End-User Transmission Rates ......................................................................................  \n5.4  Transmission Revenue Requirement ...........................................................................  \n5.5  Transmission Revenue Balancing Account Adjustment (TRBAA). ...........................  \n5.6  Transmission Access Charge Balancing Account Adjustment (TRBAA). ................  \n6.  ANCILLARY SERVICES - APPLICABILITY AND CHARGES .................................................  \n7.  BILLING AND PAYMENT .........................................................................................................  \n7.1  End-Users .......................................................................................................................  \n7.2  Low Voltage Access Charge Revenues .......................................................................  \n    7.2.1  Billing Procedure ....................................................................................................  \n    7.2.2  Interest on Unpaid Balances ..................................................................................  \n    7.2.3  Default ......................................................................................................................  \n7.3  Wheeling and Usage Charge Revenues .......................................................................  \n8.  OBLIGATION TO INTERCONNECT OR CONSTRUCT TRANSMISSION EXPANSIONS & \nFACILITY UPGRADES ..................................................................................................................  \n8.1  Participating TO Obligation to Interconnect ................................................................  \n    8.1.1  Interconnection to Transmission System .............................................................  \n        8.1.1.1  Letter Agreement .............................................................................................  \n    8.1.2  Costs Associated with Interconnection ................................................................  \n    8.1.3  Interconnection Agreement ...................................................................................  \n    8.1.4  Due Diligence to Construct ....................................................................................  \n    8.1.5  Energization .............................................................................................................  \n    8.1.6  Coordination with ISO on Interconnection Requests ..........................................  \n8.2  Participating TO Obligation to Construct Transmission Expansions or Facility \nUpgrades ................................................................................................................................  \n    8.2.1  Obligation to Construct ..........................................................................................  \n    8.2.2  Local Furnishing Participating TO Obligation to Construct ...............................  \n8.3  Request for FERC Deference Regarding Need Determination ..................................  \n9.  EXPANSION PROCESS ...........................................................................................................  \n9.1  Determination of Facilities ............................................................................................  \n    9.1.1  Payment of Facilities Study’s Cost .......................................................................  \n \n \n         Tariff Record Proposed Effective Date: 06/15/202102/16/27 \n \n \n \n \n                       Version Number: 18.0.0 \n \n \n \n \n \n \n \n \n \n \n             Option Code:  A"},{"page":3,"startToken":278,"endToken":592,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n    9.1.1.1  Market Participant to Pay for Facilities Study ...............................................  \n    9.1.1.2  Project Sponsor or Project Proponent to Pay for Facilities Study ..............  \n    9.1.1.3  Principal Beneficiaries to Pay for Facilities Study ........................................  \n    9.1.2  Payment Procedure ................................................................................................  \n    9.1.3  Facilities Study Procedures ...................................................................................  \n9.2  Obligation to Build .........................................................................................................  \n    9.2.1  Due Diligence to Construct ....................................................................................  \n    9.2.2  Delay in Construction or Expansion .....................................................................  \n    9.2.2.1  Alternatives to the Original Facility Additions .............................................. \n    9.2.2.2  Refund Obligation for Unfinished Facility Additions ....................................  \n9.3  Provisions Relating To Transmission Construction On the Systems Of Other \nTOs .........................................................................................................................................  \n    9.3.1  Responsibility for Third Party Additions ..............................................................  \n    9.3.2  Coordination of Third-Party System Additions ....................................................  \n    9.3.3  Expansion by “Local Furnishing Participating TOs” ...........................................  \n10.  INTERCONNECTION PROCESS ...........................................................................................  \n10.1  Applicability ..................................................................................................................  \n10.2  Applications ..................................................................................................................  \n10.3  Interconnection Application ........................................................................................  \n10.4  Review of Completed Interconnection Application ..................................................  \n10.5  Notice of Need for System Impact Study ...................................................................  \n10.6  System Impact Study Cost Reimbursement ..............................................................  \n    10.6.1  Cost Reimbursement ............................................................................................  \n    10.6.2  Multiple Parties ......................................................................................................  \n10.7  System Impact Study Procedures ..............................................................................  \n    10.7.1  Procedures Upon Completion of System Impact Study ....................................  \n10.8   Notice of Need for Facilities Study ............................................................................  \n10.9  Facilities Study Procedures ........................................................................................  \n    10.9.1  Execution of Interconnection Agreement ...........................................................  \n10.10  Partial Interim Service ...............................................................................................  \n10.11  Expedited Interconnection Procedures ...................................................................  \n11.  UNCONTROLLABLE FORCES AND INDEMNIFICATION ....................................................  \n11.1  Procedures To Follow if Uncontrollable Force Occurs ............................................  \n11.2  Indemnification .............................................................................................................  \n12.  REGULATORY FILINGS .........................................................................................................  \n12.1  Open Access ................................................................................................................  \n        12.2  STRANDED COST RECOVERY ...................................................................................  \n13.  CREDITWORTHINESS ...........................................................................................................  \n13.1  UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low \nVoltage Transmission Facilities ..........................................................................................  \n13.2  End-Users .....................................................................................................................  \n14.  DISPUTES ...............................................................................................................................  \n15.  RECOVERY OF RELIABILITY SERVICES COSTS ...............................................................  \n16.  MISCELLANEOUS ..................................................................................................................  \n16.1  Notices ..........................................................................................................................  \n16.2  Waiver ...........................................................................................................................  \n16.3  Confidentiality ..............................................................................................................  \n    16.3.1  Maintaining Confidentiality If Not for Public Disclosure ...................................  \n    16.3.2  Disclosure of Confidential Information ..............................................................."},{"page":4,"startToken":592,"endToken":748,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n16.4  TO Tariff Supersedes Existing Tariffs ........................................................................  \n16.5  Titles ..............................................................................................................................  \n16.6  Severability ...................................................................................................................  \n16.7  Preservation of Obligations ........................................................................................  \n16.8  Governing Law .............................................................................................................  \n16.9  Appendices Incorporated ............................................................................................  \n16.10  Conflict With ISO Tariff ..............................................................................................  \n16.11  Conflicting Operating Instructions ...........................................................................  \n16.12  Self Provision of Ancillary Services .........................................................................  \n \n \nAPPENDIX I - TRANSMISSION REVENUE REQUIREMENT .......................................................  \nAPPENDIX II - CHARGES FOR WHOLESALE TRANSMISSION SERVICES .............................  \nAPPENDIX III – TRANSMISSION RATES FOR END-USE SERVICE ..........................................  \nAPPENDIX IV – RATES FOR CERTAIN ANCILLARY SERVICE BIDS .......................................  \nAPPENDIX V - NOTICES ...............................................................................................................  \nAPPENDIX VI - RELIABILITY SERVICES RATE SCHEDULE .....................................................  \nAPPENDIX VII - INTERCONNECTION PROCEDURES IN EFFECT PRIOR TO JULY 1, 2005 ...  \nAPPENDIX VIII – NOT USED .........................................................................................................  \nAPPENDIX IX – FORMULA RATE ................................................................................................  \nAPPENDIX X – RATE SCHEDULE FOR RECOVERY OF COSTS ASSOCIATED WITH \nFACILITIES INSTALLED PURSUANT TO INTERCONNECTION AGREEMENTS.…………….. \nAPPENDIX XI – TRANSMISSION MAINTENANCE AND COMPLIANCE REVIEW .....................  \nAPPENDIX XII – STAKEHOLDER REVIEW PROCESS ...............................................................  \nAPPENDIX XIII – LETTER AGREEMENT .....................................................................................  \nAPPENDIX XIV -  WEST OF DEVERS FORMULA RATE……………………………….................. \nAPPENDIX XV – LARGE LOAD INTERCONNECTION PROCEDURES………………………….."},{"page":5,"startToken":748,"endToken":990,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n1.  Preamble.  \nThe Participating TO's revenue requirements and applicable rates and charges for \ntransmission access over the ISO Controlled Grid and the terms and conditions for \ntransmission expansion and interconnection are set forth in this TO Tariff and the ISO \nTariff. \n1.1  Transmission Access for Participating TOs. \nParticipating TOs are able to participate in the ISO and utilize the entire ISO Controlled \nGrid to serve their End-Use Customers.  The applicable High Voltage Access Charges \nand Transition Charges shall be paid by Participating TOs to the ISO pursuant to the \nISO Tariff.  If a Participating TO utilizes the Low Voltage Transmission Facilities of \nanother Participating TO, such Participating TO shall also pay the Low Voltage Access \nCharge of the other Participating TO.  \n1.2  Transmission Access for Wheeling Customers. \nWheeling allows Scheduling Coordinators to deliver Energy through or out of the ISO \nControlled Grid to serve a load located outside the transmission or Distribution System \nof a Participating TO.  Wheeling Access Charges shall be paid by Scheduling \nCoordinators to the ISO pursuant to the ISO Tariff. \n1.3  Transmission Access for End-Users.   \nEnd-Users receive transmission service over the ISO Controlled Grid through the Utility \nDistribution Company, Small Utility Distribution Company, or MSS OperatorParticipating \nTO to whose transmission or distribution facilities the End-User is directly connected.  \nCharges to End-Users for access to the ISO Controlled Grid  shall be paid to the"},{"page":6,"startToken":990,"endToken":1025,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \napplicable Utility Distribution Company, Small Utility Distribution Company, or MSS \nOperatorParticipating TO to whose transmission or distribution facilities the End-User is \ndirectly connected."},{"page":7,"startToken":1025,"endToken":1280,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n3.  TO Definitions. \nCapitalized terms used in this TO Tariff shall have the meanings set out below or in \nAppendix XV unless otherwise stated.  Capitalized terms used in this tariff and not \ndefined below or in Appendix XV shall have the meanings set out in the ISO Tariff. \n3.1 \nAccess Charge.  A charge paid by all UDCs, MSSs and, in certain cases, \nScheduling Coordinators, delivering Energy to Gross Load, as set forth in Section 26.1 \nof the ISO Tariff.  The Access Charge includes the High Voltage Access Charge, the \nTransition Charge, and the Low Voltage Access Charge. \n3.2 \nAutomatic Generation Control (AGC).  Generation equipment that \nautomatically responds to signals from the ISO’s EMS control in real time to control the \npower output of electric generators within a prescribed area in response to a change in \nsystem frequency, tieline loading, or the relation of these to each other, so as to \nmaintain the target system frequency and/or the established interchange with other \nareas within the predetermined limits. \n3.3 \nAncillary Services.  Regulation, Spinning Reserve, Non-Spinning Reserve, \nVoltage Support and Black Start together with such other interconnected operation \nservices as the ISO may develop in cooperation with Market Participants to support the \ntransmission of Energy from Generation resources to Loads while maintaining reliable \noperation of the ISO Controlled Grid in accordance with Good Utility Practice. \n \n \n                        Tariff Record Proposed Effective Date: 05/01/2026 \n \n  \n \n                           Version Number: 16.0.0 \n \n \n \n \n \n \n \n \n \n \n \nOption Code:  A"},{"page":8,"startToken":1280,"endToken":1486,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n3.4 \nApplicable Reliability Criteria.  The reliability standards established by NERC, \nWECC, and Local Reliability Criteria as amended from time to time, including any \nrequirements of the Nuclear Regulatory Commission. \n3.5 \nAvailable Transfer Capacity.  For a given transmission path, the capacity rating \nin MW of the path established consistent with ISO and WECC transmission capacity \nrating guidelines, less any reserved uses applicable to the path. \n3.6 \nBase Transmission Revenue Requirement.  The Transmission Revenue \nRequirement before deducting the Transmission Revenue Balancing Account \nAdjustment (TRBAA) and, for wholesale purposes, before deducting Standby \nTransmission Revenues. \n3.7 \nBlack Start.  The procedure by which a Generating Unit self-starts without an \nexternal source of electricity thereby restoring power to the ISO Controlled Grid \nfollowing system or local area blackouts. \n3.8 \nBusiness Day.  Monday through Friday, excluding federal holidays and the day \nafter Thanksgiving Day. \n3.9 \n(Omitted) \n3.10 Completed Application Date.  The date on which a party submits an \nInterconnection Application that satisfies the requirements of a Completed \nInterconnection Application.  \n3.11 Completed Interconnection Application.  An Interconnection Application that \nsatisfies all of the information and other requirements of Section 10.3 of this TO Tariff."},{"page":9,"startToken":1486,"endToken":1755,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.12 Congestion.  A condition that occurs when there is insufficient Available \nTransfer Capacity to implement all Preferred Schedules simultaneously or, in real time, \nto serve all Generation and Demand.  “Congested” shall be construed accordingly. \n3.13 Congestion Management.  The alleviation of Congestion in accordance with \napplicable ISO Protocols and Good Utility Practice. \n3.14 Converted Rights.  Those transmission service rights as defined in Section \n4.3.1.6 of the ISO Tariff. \n3.15 CPUC.  The California Public Utilities Commission, or its successor. \n3.16 (Omitted) \n3.17 Demand.  The rate at which Energy is delivered to Loads and Scheduling Points \nby Generation, transmission or distribution facilities.  It is the product of voltage and the \nin-phase component of alternating current measured in units of watts or standard \nmultiples thereof, e.g., 1,000W = 1kW, 1,000kW = 1MW, etc. \n3.18 Direct Assignment Facilities.  Facilities or portions of facilities that are owned \nby the Participating TO necessary to physically and electrically interconnect a particular \nparty requesting Interconnection under this TO Tariff to the ISO Controlled Grid at the \npoint of interconnection.  Direct Assignment Facilities shall be specified in the \nInterconnection Agreement that governs Interconnection service to such party and shall \nbe subject to FERC approval.  \n3.19 Dispatch.  The operating control of an integrated electric system to: i) assign \nspecific Generating Units and other sources of supply to effect the supply to meet the \nrelevant area Demand taken as Load rises or falls; ii) control operations and \nmaintenance of high voltage lines, substations, and equipment, including administration"},{"page":10,"startToken":1755,"endToken":2052,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nof safety procedures; iii) operate interconnections; iv) manage Energy transactions with \nother interconnected Control Areas; and v) curtail Demand.   \n3.20 Distribution System.  The distribution assets of a TO, UDC, or MSS.   \n3.21 Eligible Customer.  (i) Any utility (including Participating TOs, Market \nParticipants and any power marketer), Federal power marketing agency, or any person \ngenerating Energy for sale or resale; Energy sold or produced by such entity may be \nEnergy produced in the United States, Canada or Mexico; however, such entity is not \neligible for transmission service that would be prohibited by Section 212(h)(2) of the \nFederal Power Act; and (ii) any retail customer taking unbundled transmission service \npursuant to a state retail access program or pursuant to a voluntary offer of unbundled \nretail transmission service by the Participating TO. \n3.22 Encumbrance.  A legal restriction or covenant binding on the Participating TO \nthat affects the operation of any transmission lines or associated facilities and which the \nISO needs to take into account in exercising Operational Control over such transmission \nlines or associated facilities if the Participating TO is not to risk incurring significant \nliability.  Encumbrances shall include Existing Contracts and may include:  (1) other \nlegal restrictions or covenants meeting the definition of Encumbrance and arising under \nother arrangements entered into before the ISO Operations Date, if any; and (2) legal \nrestrictions or covenants meeting the definition of Encumbrance and arising under a \ncontract or other arrangement entered into after the ISO Operations Date.  \n3.23 End-Use Customer or End-User.  A purchaser of electric power who purchases \nsuch power to satisfy a Load directly connected to the ISO Controlled Grid or to a \nDistribution System and who does not resell the power."},{"page":11,"startToken":2052,"endToken":2316,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.24 Energy.  The electrical energy produced, flowing or supplied by generation, \ntransmission or distribution facilities, being the integral with respect to time of the \ninstantaneous power, measured in units of watt-hours or standard multiples thereof, \ne.g., 1,000 Wh = 1kWh, 1,000 kWh = 1MWh, etc. \n3.25 Entitlements.  The right of the Participating TO obtained through contract or \nother means to use another entity's transmission facilities for the transmission of \nEnergy.  \n3.26 Existing Contracts.  The contracts which grant transmission service rights in \nexistence on the ISO Operations Date (including any contracts entered into pursuant to \nsuch contracts) as may be amended in accordance with their terms or by agreement \nbetween the parties thereto from time to time. \n3.27 Existing Rights.  The transmission service rights and obligations of non-\nParticipating TOs under Existing Contracts, including all terms, conditions, and rates of \nthe Existing Contracts, as they may change from time to time under the terms of the \nExisting Contracts. \n3.28 Expedited Interconnection Agreement.  A contract between a party which has \nsubmitted a Request for Expedited Interconnection Procedures and the Participating TO \nunder which the Participating TO agrees to process, on an expedited basis, the \nCompleted Interconnection Application of such party and which sets forth the terms, \nconditions, and cost responsibilities for such interconnection.   \n3.29 Facilities Study Agreement.  An agreement between a Participating TO and \neither a party requesting Interconnection to the ISO Controlled Grid, Market Participant, \nProject Sponsor, or identified principal beneficiaries pursuant to which the party"},{"page":12,"startToken":2316,"endToken":2593,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nrequesting such Interconnection, Market Participants, Project Sponsor, or identified \nprincipal beneficiaries agrees to reimburse the Participating TO for the cost of \nperforming or reviewing a Facilities Study. \n3.30 Facility or Facilities Study.  An engineering study conducted to determine \nrequired modifications to the Participating TO’s transmission system, including the \nestimated cost and scheduled completion date for such modifications that will be \nrequired to provide needed services. \n3.31 FERC.  The Federal Energy Regulatory Commission or its successor.  \n3.32 FPA.  Parts II and III of the Federal Power Act, 16 U.S.C. § 824 et seq., as they \nmay be amended from time to time. \n3.33 FTR (Firm Transmission Right).  A contractual right, subject to the terms and \nconditions of the ISO Tariff, that entitles the FTR Holder to receive, for each hour of the \nterm of the FTR, a portion of the Usage Charges received by the ISO for transportation \nof energy from a specific originating Zone to a specific receiving Zone and, in the event \nof an uneconomic curtailment to manage Day-Ahead congestion, to a Day-Ahead \nscheduling priority higher than that of a schedule using Converted Rights capacity that \ndoes not have an FTR.  \n3.34 FTR Holder.  The owner of an FTR, as registered with the ISO.  \n3.35 Generating Unit.  An individual electric generator and its associated plant and \napparatus whose electrical output is capable of being separately identified and metered \nor a Physical Scheduling Plant that, in either case, is: (a) located within the ISO Control \nArea; (b) connected to the ISO Controlled Grid, either directly or via interconnected"},{"page":13,"startToken":2593,"endToken":2906,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ntransmission, or distribution facilities; and (c) that is capable of producing and delivering \nnet Energy (Energy in excess of a generating station’s internal power requirements). \n3.36 Generation.  Energy delivered from a Generating Unit. \n3.37 Good Utility Practice.  Any of the practices, methods, and acts engaged in or \napproved by a significant portion of the electric utility industry during the relevant time \nperiod, or any of the practices, methods, and acts which, in the exercise of reasonable \njudgment in light of the facts known at the time the decision was made, could have been \nexpected to accomplish the desired result at a reasonable cost consistent with good \nbusiness practices, reliability, safety, and expedition.  Good Utility Practice is not \nintended to be any one of a number of the optimum practices, methods, or acts to the \nexclusion of all others, but rather to be acceptable practices, methods, or acts generally \naccepted in the region. \n3.38 Gross Load.  Gross Load is all Energy (adjusted for distribution losses) \ndelivered for the supply of End-User Loads directly connected to the transmission \nfacilities or Distribution System of the Participating TO.  Gross Load shall exclude the \nportion of the Load of an individual End-Use Customer of the Participating TO that is \nserved by a Generating Unit that: (a) is located on the customer's site or provides \nservice to the customer's site through over-the-fence arrangements as authorized by \nSection 218 of the California Public Utilities Code; (b) is a qualifying small power \nproduction facility or qualifying cogeneration facility, as those terms are defined in the \nFERC's regulations implementing Section 201 of the Public Utility Regulatory Policies \nAct of 1978; (c) was serving the customer's Load on or before March 31, 2000; and (d) \nsecured Standby Service from the Participating TO under terms approved by a Local"},{"page":14,"startToken":2906,"endToken":3183,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nRegulatory Authority or FERC, as applicable, as of March 31, 2000 and continues to \nsecure Standby Service from the Participating TO or can be curtailed concurrently with \nan outage of the Generating Unit serving the Load. \n3.39 High Voltage Access Charge.  A component of the Access Charge determined \nby the ISO and assessed to the Participating TO under Section 26.1 of the ISO Tariff. \n3.40 High Voltage Existing Contracts Access Charge.  A charge for access to the \nISO Controlled Grid under certain specified Existing Contracts to be paid by the Existing \nContract holder to the Participating TO.  Such rate shall be calculated by dividing the \nHigh Voltage Transmission Revenue Requirement applicable to wholesale customers \nby the sum of Edison’s twelve monthly retail system peak demands measured at the \nISO Controlled Grid level, consistent with such revenue requirement.    \n3.41 High Voltage Transmission Facility.  A transmission facility under the \noperational control of the ISO that is owned by the Participating TO or to which the \nParticipating TO has an Entitlement that is represented by a Converted Right and that \noperates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs \nof which are not directly assigned to one or more specific customers. \n3.42 High Voltage Transmission Revenue Requirement.  The portion of the \nParticipating TO's TRR associated with and allocable to the Participating TO's High \nVoltage Transmission Facilities and Converted Rights associated with High Voltage \nTransmission Facilities.  \n3.43 High Voltage Utility-Specific Rate.  The Participating TO's High Voltage \nTransmission Revenue Requirement divided by the Participating TO's forecasted Gross \nLoad."},{"page":15,"startToken":3183,"endToken":3441,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.44 High Voltage Wheeling Access Charge.  The Wheeling Access Charge \nassessed by the ISO associated with the recovery of the Participating TOs' High \nVoltage Transmission Revenue Requirements in accordance with Section 26.1 of the \nISO Tariff. \n3.45 (Omitted) \n3.46 Interconnection.  Transmission facilities, other than additions or replacements \nto existing facilities that: i) connect one system to another system where the facilities \nemerge from one and only one substation of the two systems and are functionally \nseparate from the ISO Controlled Grid facilities such that the facilities are, or can be, \noperated and planned as a single facility; or ii) are identified as radial transmission lines \npursuant to contract; or iii) produce Generation at a single point on the ISO Controlled \nGrid; provided that such interconnection does not include facilities that, if not owned by \nthe Participating TO, would result in a reduction in the ISO’s Operational Control of the \nParticipating TO’s portion of the ISO Controlled Grid. \n3.47 Interconnection Agreement.  A contract between a party requesting \nInterconnection and the Participating TO that owns the transmission facility with which \nthe requesting party wishes to interconnect. \n3.48 Interconnection Application.   An application that requests Interconnection to \nthe ISO Controlled Grid. \n3.49 Interest.  Interest shall be calculated in accordance with the methodology \nspecified for interest on refunds in the regulations of FERC at 18 C.F.R. \n§35.19(a)(2)(iii)(1996).  Interest on delinquent amounts shall be calculated from the due"},{"page":16,"startToken":3441,"endToken":3691,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ndate of the bill to the date of payment.  When payments are made by mail, bills shall be \nconsidered as having been paid on the date of receipt. \n3.50 Independent System Operator (“ISO”).  The California Independent System \nOperator Corporation, a state chartered, nonprofit corporation that controls the \ntransmission facilities of all Participating TOs and dispatches certain Generating Units \nand Loads. \n3.51 ISO ADR Procedures.  The procedures for resolution of disputes or differences \nset out in Section 13 of the ISO Tariff, as amended from time to time. \n3.52 ISO Controlled Grid.  The system of transmission lines and associated facilities \nof the Participating TOs that have been placed under the ISO’s Operational Control.  \n3.53 ISO Protocols.  The rules, protocols, procedures and standards promulgated by \nthe ISO (as amended from time to time) to be complied with by the ISO Scheduling \nCoordinators, Participating TOs and all other Market Participants in relation to the \noperation of the ISO Controlled Grid and the participation in the markets for Energy and \nAncillary Services in accordance with the ISO Tariff. \n3.54 ISO Tariff.  The California Independent System Operator Agreement and Tariff, \ndated March 31, 1997, as it may be modified from time to time. \n3.55 Load.  An end-use device of an End-Use Customer that consumes power.  Load \nshould not be confused with Demand, which is the measure of power that a Load \nreceives or requires. \n3.56 (Omitted)"},{"page":17,"startToken":3691,"endToken":3955,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.57 Local Furnishing Bond.  Tax-exempt bonds utilized to finance facilities for the \nlocal furnishing of electric energy, as described in section 142(f) of the Internal Revenue \nCode, 26 U.S.C. § 142(f). \n3.58 Local Furnishing Participating TO.  Any Tax-Exempt Participating TO that \nowns facilities financed by Local Furnishing Bonds. \n3.59 Local Publicly Owned Electric Utilities.  A municipality or municipal \ncorporation operating as a public utility furnishing electric service, a municipal utility \ndistrict furnishing electric service, a public utility district furnishing electric services, an \nirrigation district furnishing electric services, or a joint powers authority that includes one \nor more of these agencies and that owns Generation or transmission facilities, or \nfurnishes electric services over its own or its members’ electric Distribution System. \n3.60 Local Regulatory Authority.  The state or local governmental authority \nresponsible for the regulation or oversight of a utility.  \n3.61 Local Reliability Criteria.  Reliability criteria established at the ISO Operations \nDate, unique to the transmission systems of each of the Participating TOs. \n3.62 Low Voltage Access Charge.  The Access Charge applicable under Section \n26.1 of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement \nof the Participating TO. \n3.63 Low Voltage Existing Contracts Access Charge.  A charge for access to the \nISO Controlled Grid under certain specified Existing Contracts to be paid by the Existing \nContract holder to the Participating TO.  Such rate shall be calculated by dividing the \nLow Voltage Transmission Revenue Requirement applicable to wholesale customers by"},{"page":18,"startToken":3955,"endToken":4225,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nthe sum of Edison’s twelve monthly retail system peak demands measured at the ISO \nControlled Grid level, consistent with such revenue requirement.    \n3.64 Low Voltage Transmission Facility.  A transmission facility under the \noperational control of the ISO owned by the Participating TO or to which the \nParticipating TO has an Entitlement that is represented by a Converted Right, which is \nnot a High Voltage Transmission Facility, and supporting facilities, and the costs of \nwhich are not directly assigned to one or more specific customers. \n3.65 Low Voltage Transmission Revenue Requirement.  The portion of the \nParticipating TO's TRR associated with and allocable to the Participating TO's Low \nVoltage Transmission Facilities and Converted Rights associated with Low Voltage \nTransmission Facilities. \n3.66 Low Voltage Wheeling Access Charge.  The Wheeling Access Charge \nassociated with the recovery of the Participating TO's Low Voltage Transmission \nRevenue Requirement in accordance with Section 26.1 of the ISO Tariff. \n3.67 Market Participant.  An entity, including a Scheduling Coordinator, who \nparticipates in the Energy marketplace through the buying, selling, transmission, or \ndistribution of Energy or Ancillary Services into, out of, or through the ISO Controlled \nGrid.  \n3.68 MSS (Metered Subsystem).  A geographically contiguous system located within \na single zone which has been operating as an electric utility for a number of years prior \nto the ISO Operations Date as a municipal utility, water district, irrigation district, State \nagency or Federal power administration subsumed within the ISO Control Area and \nencompassed by ISO certified revenue quality meters at each interface point with the"},{"page":19,"startToken":4225,"endToken":4481,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nISO Controlled Grid and ISO certified revenue quality meters on all Generating Units or, \nif aggregated, each individual resource and Participating Load internal to the system, \nwhich is operated in accordance with a MSS agreement described in Section 4.9.1 of \nthe ISO Tariff. \n3.69 NERC.  The North American Electric Reliability Council or its successor. \n3.70 (Omitted) \n3.71 (Omitted) \n3.72 New High Voltage Transmission Facility.  A High Voltage Transmission \nFacility of the Participating TO that enters service after the beginning of the transition \nperiod described in Section 4 of Schedule 3 of Appendix F of the ISO Tariff, or a capital \naddition made after the beginning of the transition period described in Section 4.2 of \nSchedule 3 of Appendix F of the ISO Tariff to an Existing High Voltage Transmission \nFacility. \n3.73 New Participating TO.  A Participating TO that is not an Original Participating \nTO. \n3.74 Non-Participating TO.  A TO that is not a party to the TCA or for the purposes of \nSection 16.1 of the ISO Tariff the holder of transmission service rights under an Existing \nContract that is not a Participating TO. \n3.75 Non-Spinning Reserve.   The portion of off-line generating capacity that is \ncapable of being synchronized and ramping to a specified load in ten minutes (or load \nthat is capable of being interrupted in ten minutes) and that is capable of running (or \nbeing interrupted) for at least two hours."},{"page":20,"startToken":4481,"endToken":4788,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.76 Operational Control.  The rights of the ISO under the Transmission Control \nAgreement and the ISO Tariff to direct Participating TOs how to operate their \ntransmission lines and facilities and other electric plant affecting the reliability of those \nlines and facilities for the purpose of affording comparable non-discriminatory \ntransmission access and meeting Applicable Reliability Criteria. \n3.77 Original Participating TO.  A Participating TO that was a Participating TO as of \nJanuary 1, 2000.  The Original Participating TOs are Pacific Gas and Electric Company, \nSouthern California Edison Company, and San Diego Gas & Electric Company. \n3.78 Participating TO.  A party to the TCA whose application under Section 2.2 of the \nTCA has been accepted and who has placed its transmission assets and Entitlements \nunder the ISO’s Operational Control in accordance with the TCA.  A Participating TO \nmay be an Original Participating TO or a New Participating TO.  For purposes of this TO \nTariff, the Participating TO is Southern California Edison Company.  \n3.79 Participation Agreement.  An agreement between a Participating TO and a \nProject Sponsor that specifies the terms and conditions under which the Participating \nTO will construct a transmission addition or upgrade on behalf of the Project Sponsor. \n3.80 Physical Scheduling Plant.  A group of two or more related Generating Units, \neach of which is individually capable of producing Energy, but which either by physical \nnecessity or operational design must be operated as if they were a single Generating \nUnit and any Generating Unit or Units containing related multiple generating \ncomponents which meet one or more of the following criteria: i) multiple generating \ncomponents are related by a common flow of fuel which cannot be interrupted without a \nsubstantial loss of efficiency of the combined output of all components; ii) the Energy"},{"page":21,"startToken":4788,"endToken":5058,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nproduction from one component necessarily causes Energy production from other \ncomponents; iii) the operational arrangement of related multiple generating components \ndetermines the overall physical efficiency of the combined output of all components; iv) \nthe level of coordination required to schedule individual generating components would \ncause the ISO to incur scheduling costs far in excess of the benefits of having \nscheduled such individual components separately; or v) metered output is available only \nfor the combined output of related multiple generating components and separate \ngenerating component metering is either impractical or economically inefficient. \n3.81 (Omitted)  \n3.82 Project Proponent.  A Market Participant or group of Market Participants that: (i) \nadvocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the \nproposed transmission addition and upgrade, and thus is not a Project Sponsor; and (iii) \ninitiates proceedings under the ISO ADR Procedures to determine the need for the \nproposed transmission addition or upgrade. \n3.83 Project Sponsor.  A Market Participant or group of Market Participants or a \nParticipating TO that proposes the construction of a transmission addition or upgrade in \naccordance with Section 24 of the ISO Tariff. \n3.84 Regional Transmission Group (“RTG”).  A voluntary organization approved by \nFERC and composed of transmission owners, transmission users, and other entities, \norganized to efficiently coordinate the planning, expansion and use of transmission on a \nregional and inter-regional basis. \n3.85 Regulation.  The service provided either by Generating Units certified by the ISO \nas equipped and capable of responding to the ISO’s direct digital control (AGC) signals,"},{"page":22,"startToken":5058,"endToken":5351,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nor by System Resources that have been certified by the ISO as capable of delivering \nsuch service to the ISO Balancing Authority Area, in an upward and downward direction \nto match, on a Real-Time basis, Demand and resources, consistent with established \nApplicable Reliability Criteria.  Regulation is used to control the power output of electric \ngenerators within a prescribed area in response to a change in system frequency, tieline \nloading, or the relation of these to each other so as to maintain the target system \nfrequency and/or the established Interchange with other Balancing Authority Areas \nwithin the predetermined Regulation Limits.  Regulation includes both the increase of \noutput by a Generating Unit or System Resource (Regulation Up) and the decrease in \noutput by a Generating Unit or System Resource (Regulation Down).  Regulation Up \nand Regulation Down are distinct capacity products, with separately stated \nrequirements and ASMPs in each Settlement Period.  \n3.86 Reliability Criteria.  Pre-established criteria that are to be followed in order to \nmaintain desired performance of the ISO Controlled Grid under contingency or steady \nstate conditions. \n3.87 Reliability Services.  Those services provided by the ISO:  1) that are deemed \nby the ISO as necessary to maintain reliable electric service in the ISO Control Area; \nand 2) whose costs are billed by the ISO to the Participating TO pursuant to the ISO \nTariff.  Reliability Services include services obtained from:  Reliability Must-Run units; \nand generators committed pursuant to the ISO’s Exceptional Dispatch authority, which \nincludes any costs of Exceptional Dispatches as well as any default costs allocated to \nthe Participating TO resulting from its incurrence of Exceptional Dispatch costs pursuant \nto Section 11.29.17.2.1 of the CAISO Tariff."},{"page":23,"startToken":5351,"endToken":5583,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.88 Reliability Upgrade.  The transmission facilities, other than Direct Assignment \nFacilities, beyond the first point of Interconnection necessary to interconnect a \nwholesale load safely and reliably to the ISO Controlled Grid, which would not have \nbeen necessary but for the Interconnection of a wholesale load, including network \nupgrades necessary to remedy short circuit or stability problems resulting from the \ninterconnection of a wholesale load to the ISO Controlled Grid.  Reliability Upgrades \nalso include, consistent with WECC practice, the facilities necessary to mitigate any \nadverse impact a wholesale load’s interconnection may have on a path’s WECC path \nrating.  Reliability Upgrades shall be specified in the Interconnection Agreement that \ngoverns Interconnection service to the wholesale load and shall be subject to FERC \napproval.   \n3.89 (Omitted).   \n3.90 Request for Expedited Interconnection Procedures.  A written request by \nwhich an applicant for Interconnection can request expedited processing of its \nInterconnection Application. \n3.91 Scheduling Coordinator.  An entity certified by the ISO for the purposes of \nundertaking the functions specified in Section 4.5.3 of the ISO Tariff. \n3.92 Scheduling Point.  A location at which the ISO Controlled Grid is connected, by \na group of transmission paths for which a physical, non-simultaneous transmission \ncapacity rating has been established for Congestion Management, to transmission \nfacilities that are outside the ISO’s Operational Control."},{"page":24,"startToken":5583,"endToken":5852,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.93 Spinning Reserve.  The portion of unloaded synchronized generating capacity \nthat is immediately responsive to system frequency and that is capable of being loaded \nin ten minutes, and that is capable of running for at least two hours. \n3.94 Standby Rate.  A rate assessed a Standby Service Customer by the \nParticipating TO, as approved by the Local Regulatory Authority, or FERC, as \napplicable, for Standby Service which compensates the Participating TO, among other \nthings, for costs of High Voltage Transmission Facilities. \n3.95 Standby Service.  Service provided by the Participating TO which allows a \nStandby Service Customer, among other things, access to High Voltage Transmission \nFacilities for the delivery of backup power on an instantaneous basis to ensure that \nEnergy may be reliably delivered to the Standby Service Customer in the event of an \noutage of a Generating Unit serving the customer's Load. \n3.96 Standby Service Customer.  A retail End-Use Customer of the Participating TO \nthat receives Standby Service and pays a Standby Rate. \n3.97 Standby Transmission Revenue.  The transmission rate revenues associated \nwith Standby Service collected by the Participating TO from those Standby Service \nCustomers who are not billed for Standby Service on a Gross Load basis.   \n3.98 System Impact Study.  An engineering study conducted to determine whether a \nrequest for Interconnection to the ISO Controlled Grid would require new transmission \nadditions, upgrades, or other mitigation measures.  \n3.99 System Impact Study Agreement.  An agreement between a Participating TO \nand an entity that has requested Interconnection to the Participating TO’s transmission"},{"page":25,"startToken":5852,"endToken":6123,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nsystem pursuant to which the entity requesting Interconnection agrees to reimburse the \nParticipating TO for the cost of performing or reviewing a System Impact Study. \n3.100 TO Tariff.  This Transmission Owner Tariff, as it may be amended or \nsuperseded. \n3.101 Transition Charge.  A component of the Access Charge determined by the ISO \nand assessed the Participating TO along with the High Voltage Access Charge in \naccordance with Section 5.7 of Appendix F, Schedule 3 of the ISO Tariff. \n3.102 Transmission Access Charge Balancing Account Adjustment (\"TACBAA\").  \nA mechanism established by the Participating TO which will ensure that the difference \nbetween (i) the actual charges by the ISO pursuant to Section 26.1.2 of the ISO Tariff \nfor the High Voltage Access Charge and Transition Charge and (ii) the revenues \ndisbursed by the ISO pursuant to Section 26.1.3 of the ISO Tariff are recovered from \nthe Participating TO's End-Use Customers. \n3.103 Transmission Control Agreement (“TCA”).  The agreement between the ISO \nand Participating TOs establishing the terms and conditions under which TOs will \nbecome Participating TOs and how the ISO and each Participating TO will discharge \ntheir respective duties and responsibilities, as may be modified from time to time. \n3.104 Transmission Owner (“TO”).  An entity owning transmission facilities or having \nfirm contractual rights to use transmission facilities.  \n3.105 Transmission Revenue Balancing Account Adjustment (“TRBAA”).  A \nmechanism established by the Participating TO which will ensure that all Transmission \nRevenue Credits and other credits specified in Sections 6 and 8 of Appendix F,"},{"page":26,"startToken":6123,"endToken":6392,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nSchedule 3 of the ISO Tariff, flow through to ISO Tariff and TO Tariff transmission \ncustomers. \n3.106 Transmission Revenue Credit.  The sum of:  1) the revenues received by the \nParticipating TO from the ISO for Wheeling service, including EDAM Recoverable \nRevenue; (2) the difference between the costs incurred by the Participating TO \nassociated with Existing Rights and the amount of such costs recovered by the \nParticipating TO from the Existing Rights customers (“ETC Cost Differentials”); and (3) \nany additional appropriate amounts included in the ISO Tariff definition of Transmission \nRevenue Credit set forth in Appendix A of the CAISO Tariff ; and (4) any remaining \nInterconnection Financial Security under the TSRA that has been drawn down by \nParticipating TO. \n3.107 Transmission Revenue Requirement (“TRR”).  The TRR is the total annual \nauthorized revenue requirements associated with transmission facilities and \nEntitlements turned over to the Operational Control of the ISO by the Participating TO, \nincluding the Projects under construction identified in Appendix VIII that are to be turned \nover to the Operational Control of the ISO upon completion.  The costs of any \ntransmission facility turned over to the Operational Control of the ISO, including the \ncosts of the Projects under construction identified in Appendix VIII that are to be turned \nover to the Operational Control of the ISO upon completion, shall be fully included in the \nParticipating TO's TRR.  The TRR includes the costs of transmission facilities and \nEntitlements and deducts Transmission Revenue Credits; for wholesale purposes, \ncredits for Standby Transmission Revenue; and the transmission revenue expected to"},{"page":27,"startToken":6392,"endToken":6640,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nbe actually received by the Participating TO for Existing Rights and Converted Rights.  \nThe TRR is shown in Appendix I. \n3.108 Uncontrollable Force.  Any act of God, labor disturbance, act of the public \nenemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, \norder, regulation or restriction imposed by governmental, military or lawfully established \ncivilian authorities or any other cause beyond the reasonable control of the ISO or \nMarket Participant which could not be avoided through the exercise of Good Utility \nPractice. \n3.109 Usage Charge.  The amount of money, per 1 kW of scheduled flow, that the ISO \ncharges a Scheduling Coordinator for use of a specific congested Inter-Zonal Interface \nduring a given hour. \n3.110 Utility Distribution Company (“UDC”).  An entity that owns a Distribution \nSystem for the delivery of Energy to and from the ISO Controlled Grid, and that provides \nregulated retail electric service to Eligible Customers, as well as regulated procurement \nservice to those End-Use Customers who are not yet eligible for direct access, or who \nchoose not to arrange services through another retailer. \n3.111 Voltage Support.  Services provided by Generating Units or other equipment \nsuch as shunt capacitors, static var compensators, or synchronous condensers that are \nrequired to maintain established grid voltage criteria.  This service is required under \nnormal or system emergency conditions. \n3.112 Western Electricity Coordinating Council (“WECC”).  The Western Systems \nCoordinating Council or its successor."},{"page":28,"startToken":6640,"endToken":6881,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.113 Wheeling Access Charge.  The charge assessed by the ISO that is paid by a \nScheduling Coordinator for Wheeling in accordance with Section 26.1 of the ISO Tariff.  \nWheeling Access Charges shall not apply for Wheeling under a bundled non-economy \nEnergy coordination agreement of a Participating TO executed prior to July 9, 1996.  \nThe Wheeling Access Charge may consist of a High Voltage Wheeling Access Charge \nand a Low Voltage Wheeling Access Charge. \n3.114 Wheeling Out.  Except for Existing Rights exercised under an Existing Contract \nin accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for \nthe transmission of Energy from a Generating Unit located within the ISO Controlled \nGrid to serve a Load located outside the transmission and Distribution System of a \nParticipating TO. \n3.115 Wheeling Through.  Except for Existing Rights exercised under an Existing \nContract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled \nGrid for the transmission of Energy from a resource located outside the ISO Controlled \nGrid to serve a Load located outside the transmission and Distribution System of a \nParticipating TO. \n3.116 Wheeling.  Wheeling Out or Wheeling Through. \n3.117 Wholesale Customer.  A person wishing to purchase Energy and Ancillary \nServices at a Bulk Supply Point or a Scheduling Point for resale. \n3.118 Omitted."},{"page":29,"startToken":6881,"endToken":6968,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n4.  Eligibility.   \nWholesale tTransmission service over a Participating TO’s system shall be provided \nonly to Eligible Customers who qualify for transmission service under the ISO Tariff.  \nAny dispute as to whether a customer is eligible for wholesale transmission service shall \nbe resolved by FERC and any dispute as to whether an End-Use Customer is eligible \nfor retail transmission service or retail interconnection service under this TO Tariff shall \nbe resolved by the Local Regulatory Authority."},{"page":30,"startToken":6968,"endToken":7215,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n7.  Billing and Payment. \n7.1  End-Users.   \nBilling and payment rules applicable to End-Users shall be pursuant to the then-current \nrules of the applicable Local Regulatory Authority and, as applicable, Appendix XV. \n7.2  Wholesale Customers.   \n7.2.1 Billing Procedure.  \n7.2.1.1  Low Voltage Access Charge Revenues.  Within a reasonable time after the \nParticipating TO receives from the ISO the monthly kilowatt-hours to which the Low \nVoltage Access Charge applies, the Participating TO shall submit an invoice to the \napplicable UDC, MSS or Scheduling Coordinator for the Low Voltage Access Charge \nbilling.  The invoice shall be paid by the UDC, MSS, or Scheduling Coordinator within \ntwenty days of receipt.  All payments shall be made in immediately available funds \npayable to the Participating TO, or by wire transfer to a bank named by the Participating \nTO.   \n7.2.1.2  Reliability Services Revenues.  The Participating TO shall submit an invoice \nto applicable Wheeling customers for billings under the Reliability Services Rate \nSchedule.  The invoice shall be paid by the Wheeling Customer within twenty days of \nreceipt.  All payments shall be made in immediately available funds payable to the \nParticipating TO, or by wire transfer to a bank named by the Participating TO. \n7.2.2  Interest on Unpaid Balances.   \nInterest on any unpaid amounts (including amounts placed in escrow) shall be \ncalculated in accordance with the methodology specified for interest on refunds in"},{"page":31,"startToken":7215,"endToken":7516,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nFERC’s regulations at 18 C.F.R. Section 35.19a(a)(2)(iii).  Interest on delinquent \namounts shall be calculated from the due date of the bill to the date of payment.  When \npayments are made by mail, bills shall be considered as having been paid on the date \nof receipt by the Participating TO. \n7.2.3  Default.  \nIn the event the UDC, MSS, Scheduling Coordinator, or Wheeling Customer fails, for \nany reason other than a billing dispute as described below, to make payment to the \nParticipating TO on or before the due date as described above, and such failure of \npayment is not corrected within 30 calendar days after the Participating TO notifies the \napplicable UDC, MSS, Scheduling Coordinator, or Wheeling Customer to cure such \nfailure, a default by the UDC, MSS, Scheduling Coordinator, or Wheeling Customer \nshall be deemed to exist.  Upon the occurrence of a default, the Participating TO may \ninitiate a proceeding with FERC (or the Local Regulatory Authority for a Local Publicly \nOwned Electric Utility) to terminate service but shall not terminate service until FERC, or \nthe Local Regulatory Authority, as applicable, so approves any such request.  In the \nevent of a billing dispute between the Participating TO and the UDC, MSS, Scheduling \nCoordinator, or Wheeling Customer, the Participating TO will continue to provide service \nunder this TO Tariff as long as the applicable UDC, MSS, Scheduling Coordinator, or \nWheeling Customer:  (i) continues to make all payments not in dispute, and (ii) pays into \nan independent escrow account the portion of the invoice in dispute, pending resolution \nof such dispute.  If the UDC, MSS, Scheduling Coordinator, or Wheeling Customer fails \nto meet these two requirements for continuation of service, then the Participating TO"},{"page":32,"startToken":7516,"endToken":7587,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nmay provide notice to the UDC, MSS, Scheduling Coordinator, or Wheeling Customer of \nits intention to suspend service in sixty days, in accordance with FERC policy. \n7.3  Wheeling and Usage Charge Revenues.   \nThe ISO, pursuant to the ISO Tariff, shall pay to Participating TOs all Wheeling and \nUsage Charge revenues, excluding Usage Charge revenues payable to FTR Holders."},{"page":33,"startToken":7587,"endToken":7844,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n8.  Obligation to Interconnect or Construct Transmission Expansions & Facility \nUpgrades.  \n8.1  Participating TO Obligation to Interconnect.   \nThe Participating TO shall, at the request of a third party pursuant to Section 10, \ninterconnect its system to the wholesale generation or wholesale load of such third \nparty, or modify an existing wholesale Interconnection.  Interconnections under this TO \nTariff shall be available to entities eligible to request Interconnection consistent with the \nprovisions of Section 210(a) of the FPA.  Interconnections requested by entities or \nindividuals that are not so eligible shall be governed by the Local Regulatory Authority.  \nThe procedures for Interconnections of wholesale generation to the ISO Controlled Grid \nshall be governed by the ISO Tariff, and if applicable, Appendix VII to the TO Tariff. \nInterconnections of Large Loads are governed by Appendix XV to the TO Tariff. \n8.1.1  Interconnection to Transmission System.   \nInterconnection must be consistent with Good Utility Practice, in conformance with all \nApplicable Reliability Criteria, all applicable statutes, regulations, and ISO reliability \ncriteria for the ISO Controlled Grid.  The Participating TO will not accommodate the \nInterconnection if doing so would impair system reliability, or would otherwise adversely \naffect the ability of the Participating TO to honor its Encumbrances existing as of the \ntime a party submits its Interconnection Application.  The Participating TO shall identify \nany such adverse effect on its Encumbrances in the System Impact Study performed \npursuant to Section 10.7.  To the extent the Participating TO determines that the"},{"page":34,"startToken":7844,"endToken":8136,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nInterconnection will have an adverse effect on Encumbrances, the party requesting \nInterconnection shall mitigate such adverse effect.   \n8.1.1.1  Letter Agreement. \nPursuant to Section 12 of Appendix DD of the ISO Tariff, prior to executing an \nInterconnection Agreement, a party seeking Interconnection may, in order to advance \nthe implementation of its Interconnection, request, and the Participating TO shall offer \nthe party, a Letter Agreement, a pro forma version of which is set forth in Appendix XIII \nto the TO Tariff, that authorizes the Participating TO to begin engineering, design, and \nprocurement of long lead-time items, or construction necessary for the establishment of \nthe Interconnection.  However, Participating TO shall not be obligated to offer a Letter \nAgreement if the party seeking Interconnection is in Dispute Resolution as a result of an \nallegation that the party seeking Interconnection has failed to meet any milestones or \ncomply with any prerequisites specified in the ISO Tariff.  The Letter Agreement is an \noptional procedure.  The Letter Agreement shall provide for the party seeking \nInterconnection to pay the cost of all activities authorized by the party and to make \nadvance payments or provide other satisfactory security for such costs. \nFollowing a party seeking Interconnection’s request for a Letter Agreement, the \nParticipating TO shall prepare and tender to the party seeking Interconnection a draft \nLetter Agreement in the form of the Participating TO’s FERC-approved Letter \nAgreement as set forth in Appendix XIII to the TO Tariff, including draft exhibits that \ninclude the proposed scope of work, estimated costs, payments, financial security and \nmilestones, as applicable.  The party seeking Interconnection shall provide written \ncomments, or notification of no comments, to the draft exhibits within thirty (30)"},{"page":35,"startToken":8136,"endToken":8439,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nCalendar Days.  The Participating TO and the party seeking Interconnection shall \nnegotiate concerning any disputed provisions of the exhibits to the draft Letter \nAgreement for not more than ninety (90) Calendar Days after the Participating TO \ntenders the draft Letter Agreement to the party seeking Interconnection.  If the party \nseeking Interconnection determines that negotiations are at an impasse, it may request \ntermination of the negotiations at any time after tender of the draft Letter Agreement and \nrequest submission of the unexecuted Letter Agreement with FERC or initiate dispute \nresolution procedures pursuant to Section 14 of this TO Tariff.  If the party seeking \nInterconnection requests termination of the negotiations, but within ninety (90) Calendar \nDays after the Participating TO tenders the draft Letter Agreement to the party seeking \nInterconnection, fails to request either the filing of the unexecuted Letter Agreement or \ninitiate dispute resolution procedures, it shall be deemed to have withdrawn its request \nfor a Letter Agreement and the Participating TO shall have no further obligation to enter \ninto a Letter Agreement, unless an extension is mutually agreed to by the parties.  The \nParticipating TO shall provide to the party seeking Interconnection a final Letter \nAgreement within fifteen (15) Business Days after the completion of the negotiation \nprocess. \nFollowing submission of the final Letter Agreement to the party seeking Interconnection, \nthe party shall either: (i) execute two originals of the tendered Letter Agreement and \nreturn them to the Participating TO; or (ii) request in writing that the Participating TO file \nwith FERC a Letter Agreement in unexecuted form.  As soon as practicable, but not \nlater than ten (10) Business Days after receiving either the two executed originals of the \ntendered Letter Agreement (if it does not conform with a FERC-approved Letter"},{"page":36,"startToken":8439,"endToken":8695,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nAgreement) or the request to file an unexecuted Letter Agreement, the Participating TO \nshall file the Letter Agreement with FERC, together with its explanation of any matters \nas to which the party seeking Interconnection and the Participating TO disagree and \nsupport for the costs that the Participating TO proposes to charge to the party seeking \nInterconnection under the Letter Agreement.  An unexecuted Letter Agreement should \ncontain terms and conditions deemed appropriate by the Participating TO for the \nInterconnection request.  \nIf the party seeking Interconnection executes the final Letter Agreement, the \nParticipating TO and the party seeking Interconnection shall perform their respective \nobligations in accordance with the terms of the Letter Agreement, subject to \nmodification by FERC.  Upon submission of an unexecuted Letter Agreement, the party \nseeking Interconnection and the Participating TO shall promptly comply with the \nunexecuted Letter Agreement, subject to modification by FERC.8.1.2  Costs Associated \nwith Interconnection. \nEach party requesting Interconnection shall pay the costs of planning, installing, owning, \noperating, and maintaining any Direct Assignment Facilities and, if applicable, any \nReliability Upgrades required to provide the requested Interconnection.  In addition, \nsuch party shall implement all existing operating procedures necessary to safely and \nreliably interconnect such party’s wholesale load to the facilities of the Participating TO \nand to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning \nCriteria, and shall bear all costs of implementing such operating procedures.  Any \nadditional costs associated with accommodating the Interconnection shall be allocated"},{"page":37,"startToken":8695,"endToken":8974,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nin accordance with the cost responsibility methodology set forth in the ISO Tariff for \ntransmission expansions or upgrades.   \n8.1.3  Interconnection Agreement. \nPursuant to Section 10.4, 10.7.1, or 10.9.1, a party requesting Interconnection shall \nrequest in writing that the Participating TO tender to such party an Interconnection \nAgreement that will be filed with FERC, or the Local Regulatory Authority, in the case of \na Local Publicly Owned Electric Utility.  The Interconnection Agreement will include, \nwithout limitation, cost responsibilities and payment provisions for any engineering, \nequipment, construction, ownership, operation and maintenance costs for any Direct \nAssignment Facilities, any Reliability Upgrades, and for any other mitigation measures.  \nFor an Interconnection request to remain a Completed Interconnection Application, the \nparty requesting the Interconnection shall execute the Interconnection Agreement and \nreturn it to the Participating TO within thirty (30) Business Days of receipt.  Alternatively, \nif an Eligible Customer requesting the Interconnection requests the Participating TO to \nfile an unexecuted Interconnection Agreement and commits to abide by the terms, \nconditions, and cost assignments determined to be just and reasonable under the ISO \nADR Procedures, including any determination by FERC or on appeal of a FERC \ndetermination in accordance with that process, the Participating TO shall promptly file \nan unexecuted Interconnection Agreement.  Provided, however, that if the ISO ADR \nProcedures concerns whether the requesting entity is an Eligible Customer, the \nParticipating TO shall not be obligated to file an unexecuted Interconnection Agreement \nor commence construction of the Interconnection facilities or incur other costs under the \nInterconnection Agreement until a final order determining the just and reasonable rates,"},{"page":38,"startToken":8974,"endToken":9249,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nterms, and conditions for such Interconnection Agreement has been issued by the \napplicable court or regulatory authority.  The Interconnection Agreement will set forth a \npayment schedule that enables the Participating TO to recover its costs.  If the applicant \nelects not to execute the Interconnection Agreement and does not request the \nParticipating TO to file an unexecuted Interconnection Agreement, its Completed \nInterconnection Application shall be deemed withdrawn, and the applicant shall \nreimburse to the Participating TO all costs reasonably incurred in processing the \napplication not covered by any System Impact Study Agreement or Facilities Study \nAgreement.   \n8.1.4 Due Diligence to Construct.  \nThe Participating TO shall use due diligence to construct, within a reasonable time, any \nDirect Assignment Facilities and any Reliability Upgrades that it is obligated to construct \npursuant to this TO Tariff.  The Participating TO’s obligation to build will be subject to:  \n1) its ability, after making a good faith effort, to obtain any necessary approvals and \nproperty rights under applicable federal, state, and local laws; 2) the presence of a cost \nrecovery mechanism with cost responsibility assigned in accordance with the ISO Tariff \nor applicable FERC precedent; and 3) a signed Interconnection Agreement or a signed \nExpedited Interconnection Agreement or, by mutual agreement of the parties, FERC \nacceptance for filing of an unexecuted Interconnection Agreement. \n8.1.5  Energization.   \nThe Participating TO shall not be obligated to energize, nor shall the wholesale load be \nentitled to have its interconnection to the ISO Controlled Grid energized, unless and \nuntil an Interconnection Agreement has been executed, or filed at FERC pursuant to"},{"page":39,"startToken":9249,"endToken":9502,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nSection 8.1.3, and becomes effective and such wholesale load has demonstrated to the \nISO's reasonable satisfaction that it has complied with all of the requirements of the ISO \nTariff and the requirements of this TO Tariff. \n8.1.6  Coordination with ISO on Interconnection Requests.   \nThe Participating TO shall coordinate with the ISO, pursuant to the provisions of the \nTCA, in developing Interconnection standards and guidelines for processing \nInterconnection requests under this TO Tariff. \n8.2  Participating TO Obligation to Construct Transmission Expansions or Facility \nUpgrades. \nThe Participating TO shall be obligated to:  (1) perform System Impact or Facility \nStudies where the Project Sponsor or the ISO agrees to pay the study cost and \nspecifies the project objectives to be achieved, and (2) build transmission additions and \nfacility upgrades where the Participating TO is obligated to construct or expand facilities \nin accordance with and subject to the limitations of Section 24 of the ISO Tariff and this \nTO Tariff. \n8.2.1  Obligation to Construct. \nA Participating TO shall not be obligated to construct or expand transmission facilities or \nsystem upgrades unless and until the conditions stated in Section 9.2.1 hereof have \nbeen satisfied.  \n8.2.2  Local Furnishing Participating TO Obligation to Construct.   \nA Local Furnishing Participating TO shall not be obligated to construct or expand \ntransmission facilities or system upgrades unless and until the conditions stated in \nSection 9.3.3 hereof have been satisfied."},{"page":40,"startToken":9502,"endToken":9572,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n8.3  Request for FERC Deference Regarding Need Determination.  \nIt is intended that FERC grant substantial deference to the factual determinations of the \nISO, (including the ISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated \nplanning processes as to the need for or construction of a facility, the need for full cost \nrecovery, and the allocation of costs."},{"page":41,"startToken":9572,"endToken":9853,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n9.  Expansion Process. \n9.1  Determination of Facilities.  \nA Participating TO shall perform a Facilities Study in accordance with this Section \nwhere (1) the Participating TO is obligated to construct or expand facilities in \naccordance with Section 24 of the ISO Tariff and this TO Tariff; (2) a Market Participant \nagrees to pay the costs of the Facilities Study and specifies the project objectives to be \nachieved in terms of increased capacity or reduced congestion; or (3) the Participating \nTO is required to perform a Facilities Study pursuant to the ISO Tariff. Eligible \nexpansions on behalf of Large Loads are not governed by this Section 9 but are instead \ngoverned by Appendix XV to the TO Tariff. \n9.1.1  Payment of Facilities Study’s Cost. \n9.1.1.1  Market Participant to Pay for Facilities Study.  \nWhere a Market Participant requests a Facilities Study and the need for the \ntransmission addition or upgrade has not yet been established in accordance with the \nprocedures established herein and the ISO Tariff, the Market Participant shall pay the \ncost of the Facilities Study. \n9.1.1.2  Project Sponsor or Project Proponent to Pay for Facilities Study.  \nWhere the facilities to be added or upgraded have been determined to be needed in \naccordance with the procedures established herein and the ISO Tariff, the Project \nSponsor, Project Proponent, or the ISO requesting the study shall pay the reasonable \ncost of the Facilities Study.  When the Participating TO is the Project Sponsor in \naccordance with the ISO Tariff, the costs of the Facilities Study shall be recovered \nthrough the Access Charges and transmission rates."},{"page":42,"startToken":9853,"endToken":10147,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n9.1.1.3  Principal Beneficiaries to Pay for Facilities Study. \nWhere the facilities to be added or upgraded have been determined to be needed and \nthe principal beneficiaries have been identified by the ISO or ISO ADR Procedures in \naccordance with the ISO Tariff, the Project Sponsor and the identified principal \nbeneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as \nmay be agreed, or, failing agreement, as determined in accordance with the ISO ADR \nProcedures. \n9.1.2  Payment Procedure.   \nWhere a Facilities Study is being conducted pursuant to this TO Tariff, the Participating \nTO shall, within thirty days of the receipt of all reasonably required information, tender to \nthe Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal \nbeneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, \ncontent, assumptions, and terms of reference for such study, the estimated time \nrequired to complete it, and such other provisions as the parties may reasonably require \nand pursuant to which such Market Participant, Project Sponsor, Project Proponent, the \nISO, or identified principal beneficiaries agree to reimburse the Participating TO the \nreasonable cost of performing the required Facilities Study.  If the Market Participant, \nProject Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the \ncase may be, agree to the terms of the Facilities Study Agreement, they shall execute \nthe Facilities Study Agreement and return it to the Participating TO within ten Business \nDays.  Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the \nISO, or identified principal beneficiaries, as the case may be, request the Participating \nTO to proceed with the Facilities Study and commit to abide by the terms, conditions,"},{"page":43,"startToken":10147,"endToken":10448,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nand cost assignments ultimately determined under the ISO ADR Procedures, including \nany determination by FERC or appeal of a FERC determination in accordance with that \nprocess, the Participating TO shall promptly proceed with the Facilities Study, and the \nparties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. \n9.1.3  Facilities Study Procedures.   \nUpon receipt of an executed Facilities Study Agreement or alternative request to \nproceed as provided for in Section 9.1.2, a copy of which has been provided to the ISO \nby the party requesting the Facilities Study, the Participating TO will use due diligence \nto complete the required Facilities Study within a sixty (60) day period.  If the \nParticipating TO is unable to complete the Facilities Study in the allotted time period, the \nParticipating TO shall notify the Market Participant and provide an estimate of the time \nneeded to reach a final determination along with an explanation of the reasons that \nadditional time is required to complete the study.  If additional time is required, the \nParticipating TO will use best efforts to complete the study within 10 months, provided \nadequate information is provided by all the parties. \n9.2  Obligation to Build. \n9.2.1  Due Diligence to Construct.   \nSubject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to \nconstruct, within a reasonable time, additions or upgrades to its transmission system \nthat it is obligated to construct pursuant to the ISO Tariff and this TO Tariff.  \nAlternatively, if a Market Participant requests the Participating TO to file an unexecuted \nParticipation Agreement and commits to abide by the terms, conditions, and cost \nassignments determined to be just and reasonable under the ISO ADR Procedures,"},{"page":44,"startToken":10448,"endToken":10754,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nincluding any determination by FERC or on appeal of a FERC determination in \naccordance with that process, the Participating TO shall promptly file an unexecuted \nParticipation Agreement.  Provided, however, that if the ISO ADR Procedures concerns \nwhether the requesting entity is an Eligible Customer, the Participating TO shall not be \nobligated to file an unexecuted Participation Agreement or commence construction of \nthe additions or upgrades or incur other costs under the Participation Agreement until a \nfinal order determining the just and reasonable rates, terms, and conditions for such \nParticipation Agreement has been issued by the applicable court or regulatory authority.  \nThe Participating TO’s obligation to build will be subject to:  1) its ability, after making a \ngood faith effort, to obtain the necessary approvals and property rights under applicable \nfederal, state, and local laws; 2) the presence of a cost recovery mechanism with cost \nresponsibility assigned in accordance with the ISO Tariff; and 3) a signed Participation \nAgreement.  The Participating TO will not construct or expand its existing or planned \ntransmission system, if doing so would impair system reliability as determined through \nsystems analysis based on the Applicable Reliability Criteria. \n9.2.2  Delay in Construction or Expansion.   \nIf any event occurs that will materially affect the time for completion of new facilities, or \nthe ability to complete them, the Participating TO shall promptly notify:  (1) the Project \nSponsor with regard to facilities determined to be needed; (2) the Parties to the \nParticipation Agreement with regard to facilities determined to be needed pursuant to \nthe ISO Tariff where principal beneficiaries were identified; and (3) the ISO.  In such \ncircumstances, the Participating TO shall, within thirty days of notifying such Project \nSponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a"},{"page":45,"startToken":10754,"endToken":11069,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ntechnical meeting with such Project Sponsor, Parties to the Participation Agreement, \nand the ISO to discuss the circumstances which have arisen and evaluate any options \navailable.  The Participating TO also shall make available to such Project Sponsor, \nParties to the Participation Agreement, and the ISO, as the case may be, studies and \nwork papers related to the cause and extent of the delay and the Participating TO’s \nability to complete the new facilities, including all information that is in the possession of \nthe Participating TO that is reasonably needed to evaluate the alternatives. \n9.2.2.1  Alternatives to the Original Facility Additions.   \nIf the review process of Section 9.2.2 determines that one or more alternatives exist to \nthe originally planned construction project, the Participating TO shall present such \nalternatives for consideration to the Project Sponsor, Parties to the Participation \nAgreement, and the ISO, as the case may be.  If upon review of any alternatives, such \nProject Sponsor, the ISO, or Parties to the Participation Agreement wish to evaluate or \nto proceed with one of the alternative additions or upgrades, such Project Sponsor, the \nISO, or Parties to the Participation Agreement may request that the Participating TO \nprepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO \nTariff.  In the event the Participating TO concludes that no reasonable alternative exists \nto the originally planned addition or upgrade and the Project Sponsor or Parties to the \nParticipation Agreement or the ISO disagree, the dispute shall be resolved pursuant to \nthe ISO ADR Procedure. \n9.2.2.2  Refund Obligation for Unfinished Facility Additions. \nIf the Participating TO and the Project Sponsor, the ISO, or Parties to the Participation \nAgreement, as the case may be, mutually agree that no other reasonable alternatives"},{"page":46,"startToken":11069,"endToken":11337,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nexist, the obligation to construct the requested additions or upgrades shall terminate \nand any deposit not yet applied toward the expended project costs shall be returned \nwith interest pursuant to FERC Regulation 35.19(a)(2)(iii).  However, the Project \nSponsor and any identified principal beneficiaries, as the case may be, shall be \nresponsible for all costs prudently incurred by the Participating TO through the time the \nconstruction was suspended.   \n9.3  Provisions Relating To Transmission Construction On the Systems Of Other \nTOs. \n9.3.1  Responsibility for Third Party Additions.  \nA Participating TO shall not be responsible for making arrangements for any \nengineering, permitting, and construction of transmission or distribution facilities on the \nsystem(s) of any other entity or for obtaining any regulatory approval for such facilities.  \nThe Participating TO will undertake reasonable efforts through the coordinated planning \nprocess to assist in making such arrangements, including, without limitation, providing \nany information or data required by such other electric system pursuant to Good Utility \nPractice. \n9.3.2  Coordination of Third-Party System Additions.  \nWhere transmission additions or upgrades being built pursuant to the ISO Tariff require \nadditions or upgrades on other systems, to the extent consistent with Section 9.3.3 of \nthis TO Tariff, the Participating TO shall coordinate construction on its own system with \nthe construction required by others.  The Participating TO, after consultation with the \nISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may \nbe, may defer construction if the new transmission facilities on another system cannot"},{"page":47,"startToken":11337,"endToken":11637,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nbe completed in a timely manner.  The Participating TO shall notify such Project \nSponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for \nany decision to defer construction and the specific problems which must be resolved \nbefore it will initiate or resume construction of the new facilities.  Within forty Business \nDays of receiving written notification by the Participating TO of its intent to defer \nconstruction pursuant to this section, such Project Sponsor, Parties to the Participation \nAgreement, or the ISO may challenge the decision in accordance with the ISO ADR \nProcedure. \n9.3.3  Expansion by “Local Furnishing Participating TOs”.   \nNotwithstanding any other provision of this TO Tariff, prior to requesting that a Local \nFurnishing Participating TO construct or expand facilities, the ISO or Project Sponsor \nshall tender (or cause to be tendered) an application under Section 211 of the FPA \nrequesting FERC to issue an order directing the Local Furnishing Participating TO to \nconstruct or expand facilities as necessary to provide transmission service as \ndetermined pursuant to the ISO Tariff.  Such Local Furnishing Participating TO shall \nthereafter, within ten Business Days of receiving a copy of the Section 211 application, \nwaive its right to a request for service under Section 213(a) of the FPA and to the \nissuance of a proposed order under Section 212(c) of the FPA.  Upon receipt of a final \norder from FERC under Section 211 of the FPA that is no longer subject to rehearing or \nappeal, such Local Furnishing Participating TO shall construct or expand facilities to \ncomply with that FERC order and shall transfer to the ISO Operational Control over the \nLocal Furnishing Participating TO’s expanded transmission facilities in accordance with \nthe ISO Tariff."},{"page":48,"startToken":11637,"endToken":11879,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.  Interconnection Process. \n10.1  Applicability.  \nAll requests for Interconnection of wholesale load directly to the ISO Controlled Grid from \nparties eligible to request such Interconnection consistent with Section 210(a) of the FPA \nshall be processed pursuant to the provisions of this Section 10., except requests for \ninterconnection on behalf of Large Loads to be located in the ISO BAA shall be subject \nto the procedures in Appendix XV of the TO Tariff.  All requests for Interconnection of \nwholesale generation directly to the ISO Controlled Grid shall be processed pursuant to \nthe provisions of the ISO Tariff, and if applicable, Appendix VII of the TO Tariff. Requests \nfor interconnection on behalf of Large Loads by retail transmission customers of \nParticipating TO shall be subject to the procedures in Appendix XV of the TO Tariff and \nthe Local Regulatory Authority, as applicable. \n10.2  Applications.   \nA party requesting Interconnection shall submit a written Interconnection Application \nwhich provides the information required in Section 10.3 to the Participating TO and shall \nsend a copy of the application to the ISO.  The Participating TO shall time-stamp the \napplication to establish study priority. \n10.3  Interconnection Application.   \nAn Interconnection Application shall provide all of the information listed in 18 CFR § \n2.20, including, but not limited to, the following: \n(i)  The identity, address, telephone number, and facsimile number of the party \nrequesting Interconnection;"},{"page":49,"startToken":11879,"endToken":12121,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n(ii)  The Interconnection point(s) to the ISO Controlled Grid contemplated by the \napplicant; \n(iii)  The resultant (or new) maximum amount of Interconnection capacity; \n(iv)  The proposed date for energizing the Interconnection and the term of the \nInterconnection service; \n(v)  Such other information as the Participating TO reasonably requires to process the \napplication. \nIn addition to the information specified above, the following information may also be \nprovided in order to properly evaluate system conditions: \n(vi)  The electrical location of the source of the power (if known) to be transmitted \npursuant to the applicant’s request for Interconnection.  If the source of the power is not \nknown, a system purchase will be assumed. \nWithin ten (10) Business Days after receipt of an Interconnection Application, the \nParticipating TO shall determine whether the application is complete (“Completed \nInterconnection Application”).  Wherever possible, the Participating TO will attempt to \nremedy deficiencies in the Interconnection Application through informal communications \nwith the applicant.  If such efforts are unsuccessful, the Participating TO shall return the \nInterconnection Application to the applicant.  The Participating TO will treat the \ninformation provided in the Interconnection Application, including the applicant’s identity, \nas confidential at the request of the applicant except to the extent that disclosure of this \ninformation is required by this TO Tariff, by regulatory or judicial order, for reliability \npurposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission"},{"page":50,"startToken":12121,"endToken":12402,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ninformation sharing agreements.  The Participating TO shall treat this information \nconsistent with the standards of conduct contained in Part 37 of FERC’s regulations. \n10.4  Review of Completed Interconnection Application.   \nAfter receiving a Completed Interconnection Application, the Participating TO will \ndetermine on a non-discriminatory basis whether a System Impact Study is required.  \nWhenever the Participating TO determines that a System Impact Study is not required \nand that neither Reliability Upgrades nor changes in existing operating procedures are \nrequired, the Participating TO shall notify the applicant within fifteen (15) Business Days \nof the Completed Application Date.  If the Interconnection can be accommodated \nwithout any Direct Assignment Facilities, then within thirty (30) Business Days of such \nnotice from the Participating TO, the applicant shall request the Participating TO to \ntender to the applicant an Interconnection Agreement within thirty (30) Business Days of \nsuch request.  The Participating TO shall tender to the applicant an Interconnection \nAgreement as provided in Section 8.1.3.  If the Participating TO determines, upon the \nreview of the Completed Interconnection Application, that Direct Assignment Facilities \nare required, the Participating TO shall tender to the applicant a Facilities Study \nAgreement within twenty (20) Business Days of the Completed Application Date and \ncontinue the interconnection process pursuant to Section 10.8.   \n10.5  Notice of Need for System Impact Study.   \nIf the Participating TO determines that a System Impact Study is necessary to \naccommodate the requested Interconnection, the Participating TO shall so inform the \napplicant, as soon as practicable.  In such cases, the Participating TO shall within \ntwenty (20) Business Days of receipt of a Completed Interconnection Application, tender"},{"page":51,"startToken":12402,"endToken":12692,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \na System Impact Study Agreement that defines the scope, content, assumptions and \nterms of reference for such study to be completed by the Participating TO; the \nestimated time required to complete it; and such other provisions as the parties may \nreasonably require, and pursuant to which the applicant shall agree to reimburse the \nParticipating TO for the reasonable actual costs of performing the required System \nImpact Study.  A description of the Participating TO’s transmission assessment \npractices for completing a System Impact Study is provided in the Participating TO’s \nFERC Form 715.  For an Interconnection request to remain a Completed \nInterconnection Application, the applicant shall execute the System Impact Study \nAgreement and return it to the Participating TO within ten (10) Business Days together \nwith payment for the reasonable estimated cost of performing the System Impact Study.  \nAlternatively, if the applicant requests the Participating TO to proceed with the System \nImpact Study and commits to abide by the terms, conditions, and cost assignments \nultimately determined under the ISO ADR Procedures, including any determination by \nFERC or appeal of a FERC determination in accordance with that process, the \nParticipating TO shall promptly proceed with the System Impact Study provided that \nsuch request is accompanied by payment for the reasonable estimated cost of the \nSystem Impact Study, and the parties shall submit the disputed terms for resolution \nunder the ISO’s ADR Procedures.  If the applicant elects not to execute a System \nImpact Study Agreement, and does not request that the Participating TO proceed with \nthe System Impact Study, its application shall be deemed withdrawn, and the applicant \nshall reimburse to the Participating TO all costs reasonably incurred in processing the \napplication."},{"page":52,"startToken":12692,"endToken":12955,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.6  System Impact Study Cost Reimbursement and Agreement \n10.6.1  Cost Reimbursement. \nThe System Impact Study Agreement shall clearly specify the charge, based on the \nParticipating TO’s estimate of the cost and time for completion of the System Impact \nStudy.  The charge shall not exceed the reasonable actual cost of the study.  In \nperforming the System Impact Study, the Participating TO shall rely, to the extent \nreasonably practicable, on existing transmission planning studies.  The applicant will not \nbe assessed a charge for such existing studies; however, the applicant will be \nresponsible for the reasonable charges associated with any modifications to existing \nplanning studies that are reasonably necessary to evaluate the impact of the applicant’s \nrequest. \n10.6.2  Multiple Parties.   \nIf multiple parties request Interconnection at the same location, the Participating TO \nmay conduct a single System Impact Study.  The costs of that study shall be pro-rated \namong the parties requesting Interconnection. \n10.7  System Impact Study Procedures.  \nUpon receipt of an executed System Impact Study Agreement or initiation of the ISO \nADR Procedures and receipt of payment for estimated study costs, the Participating TO \nwill use due diligence to complete the required System Impact Study within a sixty (60) \ncalendar day period.  The System Impact Study will identify whether any Direct \nAssignment Facilities or Reliability Upgrades are necessary, as well as whether any \ntransmission additions or upgrades are necessary to serve a wholesale load.  The \nSystem Impact Study will also identify any adverse impact on Encumbrances existing as"},{"page":53,"startToken":12955,"endToken":13236,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nof the applicant’s Completed Application Date.  In the event that the Participating TO is \nunable to complete the required System Impact Study within such time period, it shall so \nnotify the applicant, in writing, and provide an estimated completion date along with an \nexplanation of the reasons why additional time is required to complete the required \nstudies.  A copy of the completed System Impact Study and related work papers shall \nbe made available to the applicant and the ISO.  The Participating TO will use the same \ndue diligence in completing the System Impact Study for others as it uses when \ncompleting studies for its affiliated UDC load.  The Participating TO shall notify the \napplicant immediately upon completion of the System Impact Study. \n10.7.1  Procedures Upon Completion of System Impact Study.   \nWithin fifteen (15) Business Days of completion of the System Impact Study, the \nParticipating TO shall notify the applicant whether the transmission system will be \nadequate to accommodate all of a request for Interconnection.  If no costs are likely to \nbe incurred for any Direct Assignment Facilities, any Reliability Upgrades, or \nimplementing any operating procedures, then within thirty (30) Business Days of receipt \nof the completed System Impact Study, the applicant shall request the Participating TO \nto tender an Interconnection Agreement within thirty (30) Business Days of such \nrequest.  The Participating TO shall tender to the applicant an Interconnection \nAgreement as provided in Section 8.1.3.  If costs are likely to be incurred to \naccommodate a request for Interconnection, the Participating TO shall tender to the \napplicant a Facilities Study Agreement pursuant to Section 10.8."},{"page":54,"startToken":13236,"endToken":13536,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.8  Notice of Need for Facilities Study.   \nIf a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid \nare needed to satisfy an applicant’s request for Interconnection, the Participating TO \nshall, within fifteen (15) Business Days of the completion date of the System Impact \nStudy tender to the applicant a Facilities Study Agreement that defines the scope, \ncontent, assumptions and terms of reference for such study; the estimated time required \nto complete the required study; and such other provisions as the parties may \nreasonably require, and pursuant to which the applicant agrees to reimburse the \nParticipating TO for the reasonable actual costs of performing the required Facilities \nStudy.   For an Interconnection request to remain a Completed Interconnection \nApplication, the applicant shall execute the Facilities Study Agreement and return it to \nthe Participating TO within ten (10) Business Days together with payment for the \nreasonable estimated cost of performing the Facilities Study.  Alternatively, if the \napplicant requests the Participating TO to proceed with the Facilities Study and commits \nto abide by the terms, conditions, and cost assignments ultimately determined under the \nISO ADR Procedures, including any determination by FERC or appeal of a FERC \ndetermination in accordance with that process, the Participating TO shall promptly \nproceed with the Facilities Study provided that such request is accompanied by \npayment for the reasonable estimated cost of the Facilities Study, and the parties shall \nsubmit the disputed terms for resolution under the ISO ADR Procedures.  If the \napplicant elects not to execute a Facilities Study Agreement and does not request that \nthe Participating TO proceed with the Facilities Study, its application shall be deemed \nwithdrawn and the applicant shall reimburse to the Participating TO all costs reasonably"},{"page":55,"startToken":13536,"endToken":13807,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nincurred in processing the application not covered by the System Impact Study \nAgreement. \n10.9  Facilities Study Procedures.  \nUpon receipt of an executed Facilities Study Agreement or initiation of the ISO ADR \nProcedures and receipt of payment for the estimated study costs, the Participating TO \nwill use due diligence to complete the required Facilities Study within a sixty (60) \ncalendar day period.  In the event that the Participating TO is unable to complete the \nrequired Facilities Study within such time period, it shall so notify the applicant, in \nwriting, and provide an estimated completion date along with an explanation of the \nreasons why additional time is required to complete the required studies.  A copy of the \ncompleted Facilities Study shall be made available to the applicant.   \n10.9.1  Execution of Interconnection Agreement.  \nWithin thirty (30) Business Days of receipt of the completed Facilities Study, the \napplicant shall request the Participating TO to tender an Interconnection Agreement \nwithin thirty (30) Business Days of such request.  The Participating TO shall tender to \nthe applicant an Interconnection Agreement as provided in Section 8.1.3.  \n10.10  Partial Interim Service.   \nIf the Participating TO determines that there will not be adequate transmission capability \nto satisfy the full amount requested in a Completed Interconnection Application, the \nParticipating TO nonetheless shall be obligated to offer and provide the portion of the \nrequested Interconnection that can be accommodated without any additional Direct \nAssignment Facilities or Reliability Upgrades.  However, the Participating TO shall not \nbe obligated to provide the incremental amount of requested Interconnection that"},{"page":56,"startToken":13807,"endToken":14082,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nrequires such additional facilities or upgrades until such facilities or upgrades have been \nplaced in service. \n10.11  Expedited Interconnection Procedures.   \nIn lieu of the procedures set forth above, the applicant shall have the option to expedite \nthe processing of its Completed Interconnection Application.  In order to exercise this \noption, the applicant shall submit in writing a Request for Expedited Interconnection \nProcedures to the Participating TO within ten (10) Business Days after receiving a copy \nof the System Impact Study for the proposed Interconnection.  Within ten (10) Business \nDays after receiving a Request for Expedited Procedures, the Participating TO shall \ntender an Expedited Interconnection Agreement that requires the applicant to \ncompensate the Participating TO for all costs reasonably incurred pursuant to the terms \nof this TO Tariff for processing the Completed Interconnection Application and providing \nthe requested Interconnection.  While the Participating TO agrees to provide the \napplicant with its best estimate of the costs of any needed Direct Assignment Facilities \nand, if applicable, Reliability Upgrades and other charges that may be incurred, unless \notherwise agreed by the parties, such estimate shall not be binding and the applicant \nmust agree in writing to compensate the Participating TO for all actual Interconnection \ncosts reasonably incurred pursuant to the provisions of this TO Tariff.  The applicant \nshall execute and return such Expedited Interconnection Agreement within ten (10) \nBusiness Days of its receipt or the applicant's request for Interconnection will cease to \nbe a Completed Interconnection Application and will be deemed terminated and \nwithdrawn.  In that event, the applicant shall reimburse the Participating TO for all costs"},{"page":57,"startToken":14082,"endToken":14111,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nreasonably incurred in processing the application not covered by the terms of the \nSystem Impact Study Agreement."},{"page":58,"startToken":14111,"endToken":14309,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n13.  Creditworthiness. \n13.1  UDCs, MSSs, and Scheduling Coordinators Using the Participating TO's Low \nVoltage Transmission Facilities.  \nFor the purpose of determining the ability of a UDC, MSS, and Scheduling Coordinator \nto meet its obligations related to service using the Participating TO's Low Voltage \nTransmission Facilities hereunder, the Participating TO may require reasonable credit \nreview procedures for the UDC, MSS, or Scheduling Coordinator.  This review shall be \nmade in accordance with standard commercial practices.  In addition, the Participating \nTO may require the UDC, MSS, or Scheduling Coordinator to provide and maintain in \neffect during the term of the service, an unconditional and irrevocable letter of credit as \nsecurity to meet its responsibilities and obligations under this TO Tariff, or an alternative \nform of security proposed by the UDC, MSS, or Scheduling Coordinator and acceptable \nto the Participating TO, and consistent with commercial practices established by the \nUniform Commercial Code, that protect the Participating TO against the risk of non-\npayment. \n13.2  End-Users.   \nCreditworthiness rules applicable to End-Users shall be pursuant to the then-current \nrules of the applicable Local Regulatory Authority. and, as applicable, Appendix XV."}],"sections":[{"p":1,"at":0,"title":"ATTACHMENT B","method":"printed heading","endPage":2,"endAt":108,"startToken":0,"endToken":25},{"p":2,"at":108,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":58,"endAt":1401,"startToken":25,"endToken":14309}]}