{"document":{"slug":"rec-20261116-5210","title":"SCE OSC - Large Load, TOT Revisions","issued":"2026-11-16","accession":"20261116-5210","docket":"ER27-508-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"Southern California Edison Company","kind":"tariff filing","file":"sources/filings/text/20261116-5210_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5210","tier":"record","sha256":"f5d7ac378d4dff75714cebbca3d204e03c8dc84d535d093491e178972e5b4777","pages":294,"tokens":86427,"emptyPages":[],"textThemes":["study","cost","colo","flex"]},"pages":[{"page":1,"startToken":0,"endToken":251,"text":"Jeffrey Nelson \nDirector, FERC Rates & \nMarket Integration \n \n \n \nP.O. Box 800 \n \n2244 Walnut Grove Ave. \nRosemead, CA 91770 \n \nNovember 16, 2026 \n \nThe Honorable Debbie-Anne A. Reese  \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC 20426 \n \n \nRe: \nSouthern California Edison Company Docket No. ER27-___-000 –   \nDear Secretary Reese: \nOn June 18, 2026, the Commission issued an Order Instituting Proceeding Under Section \n206 of the Federal Power Act (“FPA”) (“Order to Show Cause” or “Order”) regarding \ninterconnections and transmission service for large loads.  The Order directed the California \nIndependent System Operator (“CAISO”) and the Participating Transmission Owners (“PTOs”) \nto (1) show cause as to why their respective Tariffs remain just and reasonable and not unduly \ndiscriminatory or preferential; or (2) explain what changes to their respective Tariffs they believe \nwould remedy the concerns if the Commission were to determine that the Tariff has in fact \nbecome unjust and unreasonable or unduly discriminatory or preferential and, therefore, \nproceeds to establish a replacement Tariff.   \nSouthern California Edison Company (“SCE”) supports the Commission’s efforts to \nensure that large loads can be integrated into our transmission system in a manner that does not \nshift costs or cause harm to smaller customers.  In fact, if done properly, the integration of new \nload has the potential to both provide transmission cost relief and to enhance reliability to \neveryone on the grid.  SCE’s proposals herein set the groundwork to realize these benefits, while \nat the same time providing transparency and reasonable rules for integrating new large loads."},{"page":2,"startToken":251,"endToken":561,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 2 \nNovember 16, 2026  \n \n2 \nSCE, as a PTO, hereby submits this filing under FPA Section 205 with proposed changes \nto its Transmission Owner Tariff (“TO Tariff”) to address items identified in the Order.  This \nTransmittal Letter also addresses the Commission’s Briefing Questions at Section IV of the \nOrder.  \nI. \nBACKGROUND \nAs SCE stated in its Request for Abeyance, many of the Commission’s identified \nconcerns can only be resolved with complementary or, at a minimum, non-conflicting tariff \nprovisions among the CAISO Tariff and the various TO Tariffs.  In order to respond to the \ndeficiencies raised in the Order to Show Cause, SCE has had robust coordination with other \nCalifornia PTOs and the CAISO while developing the tariff changes described herein.    \nShortly after the Commission issued the Order to Show Cause, SCE began engaging with \nthe CAISO and other stakeholders to coordinate its response.  SCE actively participated in the \nCAISO stakeholder process that produced the CAISO’s Large Loads Enhancements proposal.  \nSCE attended the CAISO’s stakeholder meetings on its Straw Proposal and the CAISO Draft \nFinal Proposal and submitted written comments on each, including comments on the definition \nof Large Load, the large load application process and interconnection study procedures, \noperational requirements, service agreements, and the CAISO’s draft tariff language.  SCE also \ncontinuously coordinated with the other PTOs, including Pacific Gas and Electric Company \n(“PG&E”) and San Diego Gas & Electric Company (“SDG&E”), and with the CAISO \nthroughout the process to promote a fair and compatible application of requirements and \nprocedures across the CAISO system, and to identify where the PTOs and the CAISO are aligned \nand where their positions differ.  \nUltimately, the CAISO has decided to defer to the various PTOs to adopt and implement \nTO Tariff changes to their load interconnection processes to respond to most of the deficiencies"},{"page":3,"startToken":561,"endToken":968,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 3 \nNovember 16, 2026  \n \n3 \npreliminarily identified in the Order to Show Cause.1  This approach requires each PTO to \ndevelop their TO Tariff provisions on critical issues, including the application and study process; \nflexible transmission service; and cost-shifting mitigation.  SCE appreciates that the ISOs/RTOs \nhave significant regional differences that must be recognized.  In light of the existing division of \nresponsibilities between PTOs and the CAISO, SCE understands that the CAISO’s approach \nmay be unique amongst ISOs/RTOs subject to the Commission’s Orders to Show Cause2 in \nhaving the PTOs address these issues in their own TO Tariffs.  In the absence of CAISO \ndirection or tariff changes applicable to Eligible Customers taking transmission service on behalf \nof large load, SCE understands that there will likely be some diversity as to the details and \nsubstance of the various TO Tariff filings in response to the Order to Show Cause.  Each PTO \nstarts with a unique tariff, and thus changes must necessarily conform to the unique features of \neach PTO tariff.  Despite this necessary diversity among TO Tariffs, the Commission’s goals in \nissuing the Order nevertheless can and should be reached.  As such, and particularly given the \ncompressed timeline for responses to the Order to Show Cause, SCE believes uniformity in the \nPTOs’ tariffs should not be expected.  Nonetheless, SCE understands it is aligned with PG&E, \nSDG&E, and LS Power in requiring security or upfront payments for network upgrades triggered \nby large loads, as well as exit fees, to help protect against cost shifting due to speculative or \ndeparting loads.  SCE also understands that it and other PTOs are also implementing similar \nflexible interim interconnection proposals.  Moreover, SCE has reached agreement with the \nCAISO and other PTOs on the foundational issue of the definition of Large Load.     \n \n1 \nCAISO Large Load Enhancements, Draft Final Proposal (“CAISO Draft Final Proposal”) (Sept. 24, \n2026).  Due to SCE submitting its compliance filing on the same day as the CAISO, SCE is basing its \nunderstanding of the CAISO’s expected filing on the CAISO Draft Final Proposal, which were \naccepted by the CAISO Board at its October 28, 2026 meeting, as well as the CAISO’s draft tariff \nlanguage provided on October 30, 2026.  See \nhttps://stakeholdercenter.caiso.com/StakeholderInitiatives/Large-loads. \n2  \nSCE has reviewed stakeholder postings as well as Section 205 and 206 filings already submitted by \nother ISOs and RTOs."},{"page":4,"startToken":968,"endToken":1213,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 4 \nNovember 16, 2026  \n \n4 \nII. \nRESPONSE TO SHOW CAUSE ORDER \nIn the Order to Show Cause, the Commission found that CAISO’s existing CAISO Tariff \nand/or the TO Tariffs preliminarily appear to be unjust, unreasonable, or unduly discriminatory \nor preferential.3  CAISO and the PTOs were directed to either file revised tariff language, or \nshow cause as to why their tariffs remain just and reasonable and not unduly discriminatory or \npreferential without provisions addressing:  \n(a) the application process, study procedures, and ongoing operational \nrequirements that apply to Eligible Customers seeking transmission service on \nbehalf of large loads; \n(b) additional transparency concerning the network upgrade costs to \nprovide transmission service to Eligible Customers on behalf of large loads; and a \npro forma cost recovery agreement between CAISO, the relevant transmission \nowner, and Eligible Customer taking transmission service on behalf of the large \nload to mitigate the risk of cost shifting among transmission customers, and a \nmechanism to ensure such payments are appropriately credited toward \ntransmission owners’ transmission revenue requirements consistent with the \nCommission’s cost-of-service regulations;  \n(c) the rates, terms, and conditions of service that apply to co-location \narrangements;  \n(d) transmission services that reflect Eligible Customers taking \ntransmission service on behalf of co-located loads, load with behind the meter \ngeneration, and flexible large loads that are willing and able to limit their use of \nthe transmission system under certain conditions; and \n \n3  Order at P 3."},{"page":5,"startToken":1213,"endToken":1515,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 5 \nNovember 16, 2026  \n \n5 \n(e) the rates, terms, and conditions of service applicable to interconnection \ncustomers serving electrically proximate large load or co-located load[.] \nIn this filing, SCE proposes revisions to its TO Tariff in response to the concerns \nidentified in the Order to Show Cause that are not being fully addressed by the CAISO in its own \nCAISO Tariff revisions.  In coordination with the CAISO’s expected revisions to its own CAISO \nTariff, SCE’s tariff revisions will connect large loads to the grid more efficiently, while also \nhelping to shield existing ratepayers throughout the CAISO region from transmission costs \nlinked to those large loads.  \nCurrently, SCE’s TO Tariff governs the interconnection of certain loads to SCE’s \ntransmission facilities that are under the operational control of the CAISO.  Specifically, SCE’s \nTO Tariff was drafted in order to facilitate the interconnection of other transmission owners’ \nfacilities to SCE’s transmission system as well as the interconnection of Load-Serving Entities’ \n(“LSEs”) transmission facilities to SCE’s facilities.  In this filing, the body of SCE’s existing TO \nTariff regarding Eligible Customer interconnections remains largely unchanged.  Instead, SCE \nproposes to create a new Appendix titled the Large Load Interconnection Procedures (“LLIP”) to \naugment existing TO Tariff interconnection and cost responsibility sections with new provisions \nspecifically tailored to the transmission interconnection of both Eligible Customers serving \nLarge Loads and Large Loads that obtain their retail transmission service from SCE.  The new \nLLIP will be used when such entities seek to interconnect to SCE’s transmission system; for all \nother interconnections under the TO Tariff, SCE’s existing TO Tariff provisions will apply.   In \ndeveloping the LLIP, SCE used Commission-approved Wholesale Distribution Access Tariff \n(“WDAT”) generator interconnection procedures as a starting point and revised the procedures \nwhere necessary to accommodate load requests."},{"page":6,"startToken":1515,"endToken":1836,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 6 \nNovember 16, 2026  \n \n6 \nA.  APPLICATION PROCESS, STUDY PROCEDURES, AND ONGOING \n OPERATIONAL REQUIREMENTS \nOrder to Show Cause Section A (“Transmission Service to Eligible Customers on Behalf \nof Large Loads”) preliminarily found that CAISO’s Tariff and/or the TO Tariffs appear to be \nunjust and unreasonable because they lack provisions that address, with sufficient clarity and \nconsistency, how CAISO and/or the Participating Transmission Owners will timely study (i.e., \nwithin 60-90 days of receiving the request) the provision of transmission service to Eligible \nCustomers on behalf of large loads.4  Regarding the definition of large load, the Order \npreliminarily found that the CAISO’s Tariff and/or the TO Tariffs appear to be unjust and \nunreasonable because they lack a definition of large load, as a new category of load, including a \nload size and interconnection voltage threshold, which should be based on the characteristics of \nCAISO’s transmission system.  The Commission ordered CAISO and/or the PTOs to explain \nwhether their tariffs remain just and reasonable without such a definition or propose tariff \nrevisions establishing their own definition of large load.5  The Commission was also concerned \nthat CAISO’s existing Tariff and/or the TO Tariffs fail to deter speculative or duplicative \nrequests for transmission service.6  Finally, the Commission suggested that a pro forma \nagreement to memorialize certain operational terms to support transmission system reliability, \nincluding the terms of any flexible transmission service arrangement, would be appropriate for \ninclusion in the CAISO Tariff and/or PTO Tariffs.7 \n1. \nTariff Changes to Incorporate a Definition of Large Load \nIn Paragraph 57 of the Order, the Commission found that the CAISO and TO Tariffs lack \na definition of large load and directed that an appropriate definition, including a load size and \n \n4  Id. at P 38. \n5  Id. at P 57. \n6 \nId. at P 55. \n7 \nId. at P 64."},{"page":7,"startToken":1836,"endToken":2205,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 7 \nNovember 16, 2026  \n \n7 \ninterconnection voltage threshold, be based on the characteristics of CAISO’s transmission \nsystem.  The Commission suggested that it would be reasonable to define a large load as a new \ncommercial or industrial customer, located at a single site behind one or more points of \ninterconnection, that has a peak load of 50 MW or greater, interconnects to the transmission \nsystem at a voltage level greater than 69 kV, and is not part of a co-location arrangement. \nTo satisfy this directive, SCE proposes to incorporate the CAISO’s definition of “Large \nLoad” into its TO Tariff.  (See TO Tariff Section 3, stating that capitalized terms not defined in \nthe TO Tariff shall be defined in the CAISO Tariff).  Under the CAISO’s proposed tariff \nlanguage, a “Large Load” is “[a]n End User located at a single site behind one or more points of \ninterconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater.”  \nSCE participated in the CAISO’s stakeholder process and supports this definition. \nThe CAISO’s proposed definition as incorporated into SCE’S TO Tariff is just and \nreasonable and responsive to the Order for three reasons.  First, it adopts the 50 MW peak load \nthreshold suggested by the Commission, which the CAISO adopted and which the other PTOs \nnow support.  Second, because the definition applies to an End User located at a single site \nbehind one or more points of interconnection to the CAISO Controlled Grid, it is based on the \ncharacteristics of CAISO’s transmission system, and it applies only to loads that interconnect to \nthe transmission facilities placed under the CAISO’s Operational Control and governed by the \nTO Tariff.  Loads interconnected to SCE’s distribution and sub-transmission systems are subject \nto the jurisdiction of the California Public Utilities Commission and are therefore outside the \nscope of the definition.  Third, a uniform definition across the CAISO Tariff and the TO Tariffs \nwill provide clarity and consistency and avoid conflicting definitions of the same term.  The \nLarge Load Interconnection Procedures, the Large Load Study Process Agreement, and the \nTransmission Security and Reliability Agreement described below apply to Large Loads as so \ndefined."},{"page":8,"startToken":2205,"endToken":2529,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 8 \nNovember 16, 2026  \n \n8 \nSCE notes that the CAISO has stated that it may refine the definition as NERC develops \nsimilar terms for computational loads.  In the event the CAISO changes its definition in the \nfuture, SCE expects to conform its definition to maintain consistency across the tariffs. \n2. \nTariff Changes to Update Application Process \nConsistent with the CAISO’s position, SCE proposes to continue to utilize the current \nframework of shared responsibilities among the CAISO and the PTOs for the interconnection of \nlarge loads to SCE’s transmission system.  Under that framework, SCE is largely responsible for \nprocessing applications and studying new large loads, while the CAISO remains responsible for \nreviewing those studies and ensuring alignment with transmission planning activities. \nThe Order preliminarily found that the TO Tariffs lack provisions that address, with \nsufficient clarity and consistency, how the PTOs will timely study (i.e., within 60-90 days of \nreceiving the request) the provision of transmission service to Eligible Customers on behalf of \nlarge loads.  SCE’s proposed Large Load Interconnection Procedures (“LLIP”), a new Appendix \nXV to the TO Tariff, address this concern by establishing a defined, time-bound application and \nstudy process for Large Loads.  Although technically an “interconnection process,” the study \nprocess adopted ensures that power can be delivered to the Large Load under the CAISO’s \nunique transmission regime. \nCritical to the LLIP are its eligibility criteria.  The CAISO has expressed concern that \nexisting provisions in the TO Tariffs apply only to a subset of Eligible Customers.8  SCE \nunderstands this language to acknowledge that not all transmission interconnections proceed \nthrough an Eligible Customer.  Specifically, when SCE interconnects large loads that SCE will \nserve at retail, the TO Tariff does not require SCE to apply for an interconnection to itself as an \nEligible Customer under the TO Tariff.  A plain reading of the Order could suggest that SCE’s \n \n8 \nId. at P 83."},{"page":9,"startToken":2529,"endToken":2869,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 9 \nNovember 16, 2026  \n \n9 \nown retail transmission customers should be excluded from obligations under the Order since \nSCE is not its own Eligible Customer.  However, SCE does not believe that the Commission \nmeant to exclude SCE’s own transmission-connected retail transmission customers from \nrequirements that are within FERC’s jurisdiction and that concern the FERC-jurisdictional \ntransmission system.  For instance, SCE believes that it should be obligated to engage in the \nsame study requirements and timelines regardless of whether the Large Load is SCE’s own retail \ntransmission customer or whether the Large Load is provided retail transmission service \n(including bundled service) by another Eligible Customer, such as a Utility Distribution \nCompany or MSS Operator.  SCE’s LLIP thus applies the same transmission-related \nrequirements to SCE’s own Large Load retail transmission customers as it does to Eligible \nCustomers seeking to interconnect on behalf of Large Loads, subject to exceptions based on \nareas such as the evaluation of distribution upgrades for SCE’s own retail transmission \ncustomers that are exclusively within state law jurisdiction.   \nAccordingly, SCE has defined the Large Load Interconnection Customer to whom the \nLLIP applies as “an Eligible Customer that proposes to interconnect and sell retail transmission \nservice to a Large Load except for when the Large Load Owner seeking to interconnect the \nLarge Load with the Participating TO’s Transmission System will be a retail transmission \ncustomer of the Participating TO, in which case the Large Load Owner shall be the Large Load \nInterconnection Customer.”  (LLIP Section 2.)  To preserve jurisdictional boundaries, Large \nLoad Owners who are retail transmission customers of SCE will still seek interconnection under \nthe Local Regulatory Authority.  However, the FERC-jurisdictional transmission-related \nprocedures and obligations in the LLIP will also apply to those Large Loads that are SCE’s retail \ntransmission customers.  In response to the Commission’s Briefing Question at P 123, SCE notes \nthat the LLIP also preserves existing commercial arrangements because it is only applicable to \nnew Large Load requests for interconnection submitted after the Commission approves the TO"},{"page":10,"startToken":2869,"endToken":3237,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 10 \nNovember 16, 2026  \n \n10 \nTariff changes.  (LLIP Section 1.2, “This LLIP applies to all Large Loads seeking \ninterconnection to Participating TO’s transmission system after the effective date of this \nAppendix XV to the TO Tariff.”)      \nUnder the LLIP, a Large Load Interconnection Customer begins the process by \nsubmitting an Interconnection Request using the form included as Attachment 1 to the LLIP, \ntogether with an Interconnection Study Deposit of $250,000, a Commercial Readiness Deposit \nequal to two times the study deposit, the technical data required by Appendix A to Attachment 1, \nand a demonstration of Site Control (LLIP Section 4.2.1).  Within 10 Business Days of receipt, \nSCE, as the Participating TO, notifies the customer whether the request is valid, and a customer \nwith a deficient request must cure it within the time provided in LLIP Section 4.3.2 (LLIP \nSections 4.3.1 and 4.3.2).  The Participating TO may defer the start of the study where higher-\nqueued projects must be studied first, in which case it must notify the customer and provide \nmonthly status updates (LLIP Section 4.4).  Within 15 Business Days after the request is deemed \nvalid, the Participating TO schedules a Scoping Meeting with the customer and, if applicable, the \nCAISO, to discuss Service Commencement Dates and interconnection options and to determine \nthe Point of Interconnection (LLIP Section 4.5).  Within 5 Business Days after the Scoping \nMeeting, the Participating TO provides the Large Load Study Process Agreement, which is \nincluded as Attachment 2 to the LLIP, and the customer must execute it within 30 Calendar Days \nafter the Scoping Meeting or its Interconnection Request will be deemed withdrawn (LLIP \nSection 4.5).  The agreement outlines the scope of the study (through the assumptions in its \nAppendix A), provides a non-binding good faith estimate of the study cost, and memorializes the \ncustomer’s obligation to pay the actual costs of the Interconnection Studies and to increase its \nCommercial Readiness Deposit after the final study report.  It also permits the Participating TO \nto share study results with the CAISO, any Affected System Operator, and the Western \nElectricity Coordinating Council."},{"page":11,"startToken":3237,"endToken":3596,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 11 \nNovember 16, 2026  \n \n11 \nThe Participating TO then performs a serial Large Load Interconnection Study, which \nconsists of a short circuit analysis, a power flow analysis, an electromagnetic transient (“EMT”) \nscreening. The study identifies a non-binding good faith estimate of the scope and cost of the \nParticipating TO’s Interconnection Facilities, Distribution Upgrades, and Large Load Network \nUpgrades, as applicable, that are required as a result of the Interconnection Request, and will also \nidentify the need for any additional studies (LLIP Section 4.6.1.1).  Where the Large Load will \nbe a retail transmission customer of the Participating TO, the study evaluates the impact of the \nproposed interconnection on the safety and reliability of the Participating TO’s Transmission \nSystem and, if applicable, any Affected System, and does not evaluate Distribution Upgrades, \nwhich are governed by the Local Regulatory Authority.  The study will also consider the use of \nalternative transmission technologies, including dynamic line ratings, advanced power flow \ncontrol devices, advanced conductors, and transmission switching when evaluating transmission \nsolutions (LLIP Section 4.6.1.1).  The Participating TO shares the study results with the CAISO \nfor review and concurrence under Section 25.7 of the CAISO Tariff, consistent with the \nCAISO’s role in reviewing those studies and ensuring alignment with transmission planning, as \ndescribed above (LLIP Sections 4.6 and 4.6.1.2).  If the Participating TO identifies a need for \nadditional studies to comply with Applicable Reliability Standards, such as stability, variable \nload impact, or EMT analysis, they are performed as part of the scope of work under a new pro \nforma Transmission Security and Reliability Agreement (“TSRA”) at the customer’s cost (LLIP \nSection 4.6.3). \nThe LLIP provides firm timelines that are responsive to the Commission’s 60–90-day \nexpectation.  The Participating TO will use Reasonable Efforts to complete the Large Load \nInterconnection Study within 90 Calendar Days after execution of the Large Load Study Process \nAgreement (LLIP Section 4.6.1.2).  A Report Meeting among the Participating TO, the CAISO \n(if applicable), and the Large Load Interconnection Customer must be held within 10 Business"},{"page":12,"startToken":3596,"endToken":3945,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 12 \nNovember 16, 2026  \n \n12 \nDays after the study report is provided to the customer to discuss the results, including assigned \ncost responsibility (LLIP Section 4.6.1.3).  If the Participating TO will not meet the required \ntimeframe, it must notify the customer of the schedule status and provide an estimated \ncompletion date with an explanation of why additional time is required (LLIP Section 4.6.1.2).  \nAfter the Report Meeting, the customer may submit written comments, and the Participating TO \nwill determine whether a revised study report is necessary and issue any revised report within 15 \nBusiness Days after the Report Meeting (LLIP Section 4.6.1.2). \nThe LLIP also includes provisions to ensure that Participating TO study resources are \ndirected to commercially viable projects, which is discussed in Section II.A.3 below.  Within 30 \nCalendar Days after receiving the final study report, the customer must increase its Commercial \nReadiness Deposit to 20% of its Large Load Network Upgrade cost assignment identified in the \nstudy, or its Interconnection Request will be deemed withdrawn (LLIP Section 4.6.1.4). \nWhere the study shows that the full amount of a Large Load’s request cannot be \naccommodated until network upgrades are completed, the LLIP allows the customer to request \nan optional Flexible Interim Large Load Interconnection (“FILI”) Study after the Large Load \nInterconnection Study, to determine whether the Large Load may interconnect on a limited basis \nin the interim (LLIP Section 4.6.2).  If the customer elects a FILI Study, the Participating TO \nwill complete within 60 Calendar Days.  This option is discussed in Section II.C below. \nFinally, NERC is still developing operational standards and study requirements that may \naffect the studies SCE needs to conduct. Further refinement of the LLIP may be required to \nconform with NERC standards. \n3. \nTariff Changes to Deter Speculative Large Load \nThe Order directed the CAISO and PTOs to address how their tariffs deter speculative or \nduplicative large load interconnection requests, which can consume study resources and create"},{"page":13,"startToken":3945,"endToken":4327,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 13 \nNovember 16, 2026  \n \n13 \nuncertainty in transmission planning.  The LLIP addresses this concern by requiring each Large \nLoad Interconnection Customer to demonstrate commercial readiness and financial commitment \nat each stage of the process, and by imposing financial consequences on customers that withdraw \nafter study resources have been committed. \nFirst, to be deemed valid, an Interconnection Request must be accompanied by an \nInterconnection Study Deposit of $250,000 and a Commercial Readiness Deposit equal to two \ntimes the study deposit, in the form of an irrevocable letter of credit, cash, a surety bond, or other \nsecurity reasonably acceptable to the Participating TO (LLIP Sections 4.2.1 and 4.7.1).  The \nInterconnection Study Deposit is applied to the prudent costs incurred by the Participating TO, \nthe CAISO, or third parties to perform and administer the study (LLIP Section 4.2.1.1).  The \nCommercial Readiness Deposit is refundable in accordance with LLIP Section 3.10.1, although \nthe Participating TO may hold it until the Service Commencement Date, and it is retained as \nfinancial security for any Withdrawal Penalty.  Within 30 Calendar Days after receiving the final \nstudy report, the customer must increase its Commercial Readiness Deposit to 20% of its Large \nLoad Network Upgrade cost assignment identified in the study, or its Interconnection Request is \ndeemed withdrawn (LLIP Section 4.6.1.4).  As a result, the financial commitment required of a \ncustomer increases as the study identifies the upgrades the customer’s load would require. \nSecond, the LLIP requires the customer to demonstrate Site Control at the time of its \nInterconnection Request (LLIP Section 4.2.1).  Site Control means the exclusive land right to \ndevelop, construct, operate, and maintain the Large Load over the term of its expected operation, \nwhich may be shown by ownership of, a leasehold interest in, or a right to develop a site of \nsufficient size; an option to purchase or acquire a leasehold on such a site; or other \ndocumentation that clearly demonstrates the customer’s right to exclusively occupy such a site \n(LLIP Section 2).  Requiring evidence of control over the site where the load will be located \nscreens out requests from customers that have no realistic ability to build the project, and helps"},{"page":14,"startToken":4327,"endToken":4721,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 14 \nNovember 16, 2026  \n \n14 \nprevent multiple, duplicative requests for the same site.  In addition, a customer that proposes a \nService Commencement Date more than seven years after its request must demonstrate that the \nrequired engineering, permitting, and construction will take longer than seven years (LLIP \nSection 3.7.1). \nThird, the LLIP imposes a Withdrawal Penalty that increases as the process advances \n(LLIP Section 3.10).  A customer that withdraws its Interconnection Request, or is deemed \nwithdrawn, before the Large Load Interconnection Study begins is not subject to a Withdrawal \nPenalty.  If the customer withdraws, is deemed withdrawn, or otherwise does not achieve its \nService Commencement Date at any point after the study begins, its Withdrawal Penalty will be \nthe greater of (1) its $250,000 study deposit or (2) an amount determined by the stage at which \nthe withdrawal occurs: (a) two times the actual cost of the study, if the customer withdraws or is \ndeemed withdrawn during the study or after receipt of the study report; (b) 10% of its estimated \nLarge Load Network Upgrade costs, if it withdraws or is deemed withdrawn after receipt of the \ndraft TSRA but before it executes the TSRA or requests that the TSRA be filed unexecuted; or \n(c) once it has executed the TSRA or requested that the TSRA be filed unexecuted, the amount \ncalculated under the TSRA, which, before the Service Commencement Date, is the greater of \n20% of its estimated Large Load Network Upgrade costs or the actual cost of any abandoned \nLarge Load Network Upgrade facilities (LLIP Section 3.10.1(c); TSRA Appendix B).  The \npenalty does not apply if the withdrawal has no material impact on the cost or timing of any \nequal or later queued request, or if the customer withdraws after receiving a study report in \nwhich its assigned Large Load Network Upgrade costs have increased by more than 25% over its \npreceding study report or by more than 100% over its initial Large Load Interconnection Study \nreport (LLIP Section 3.10).  A customer also is not subject to the penalty if it withdraws within \n30 Calendar Days after an additional study increases those costs by more than 25% (LLIP \nSection 4.6.3).  Once service begins, the customer is instead subject to the Exit Fee and"},{"page":15,"startToken":4721,"endToken":5026,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 15 \nNovember 16, 2026  \n \n15 \nMinimum Annual Revenue Obligation provisions of the TSRA, as described in Section II.B \nbelow. \nTogether, these provisions ensure that customers requesting study resources commit \ncapital, provide evidence that the Large Load Owner controls the proposed site where the Large \nLoad will be located, and bear the cost of withdrawing, which discourages speculative or \nduplicative requests. \n4. \nTariff Changes to Create a New Pro Forma Transmission Security and \nReliability Agreement \nThe Order directed the CAISO and PTOs to address the ongoing operational \nrequirements that apply to Eligible Customers taking transmission service on behalf of large \nloads, and to consider an agreement that memorializes the terms on which such service is \nprovided.  SCE proposes to address these requirements through the new pro forma TSRA, \nincluded as Attachment 3 to the LLIP.  The TSRA is a standard-form agreement between the \nLarge Load Interconnection Customer and SCE, as the Participating TO, that SCE tenders, \ntogether with draft appendices, after the Large Load Interconnection Study is complete (LLIP \nSection 5.1).  It consolidates in one agreement the facilities, operational, reliability, and financial \nsecurity terms applicable to the Large Load.  The TSRA is executed only by the customer and \nSCE; the CAISO’s role in SCE’s new flexible interim interconnection service, FILI is reflected \nthrough a new Operating Conditions Agreement for Flexible Load Interconnection (“FILI \nAgreement”) among the customer, SCE, and the CAISO (LLIP Attachment 4), discussed below \nand in Section II.C.  The TSRA has a term of 15 years from its effective date (TSRA Article \n2.2).  It consists of twenty-nine Articles, covering, among other things, term and termination \n(Article 2), regulatory filings (Article 3), scope of service (Article 4), engineering, procurement, \nand construction (Article 5), testing and inspection (Article 6), metering (Article 7),"},{"page":16,"startToken":5026,"endToken":5379,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 16 \nNovember 16, 2026  \n \n16 \ncommunications (Article 8), operations (Article 9), maintenance (Article 10), performance \nobligations and financial security (Article 11), invoices (Article 12), emergencies (Article 13), \ndefault (Article 17), indemnity and insurance (Article 18), confidentiality (Article 22), \ninformation requirements and audit rights (Articles 24 and 25), and disputes (Article 27), and of \nseven appendices (Appendices A through G). \nThe TSRA addresses ongoing operational and reliability requirements in several respects.  \nIt requires each party to comply with Applicable Reliability Standards and Electric Reliability \nOrganization requirements and to share the information reasonably required for the other party to \ndo so (TSRA Article 9.1).  It requires the Participating TO and the CAISO to operate and control \nthe Participating TO’s Transmission System in a safe and reliable manner, and it allows the \nParticipating TO and the CAISO to provide operating instructions to the Large Load \nInterconnection Customer consistent with the TSRA and applicable operating protocols (TSRA \nArticle 9.3).  It requires the customer to operate the Large Load in a safe and reliable manner and \nin accordance with the requirements of its Balancing Authority Area, as set forth in Appendix D, \nand prohibits the customer from operating the Large Load in parallel with the Participating TO’s \nTransmission System without the Participating TO’s prior written approval (TSRA Article 9.3).  \nThe customer must also comply with the Participating TO’s Interconnection Handbook (TSRA \nArticle 5.6.4); install a Remote Terminal Unit and provide telemetry before the Service \nCommencement Date (TSRA Article 8); design the Large Load to maintain a power factor \nbetween 0.99 leading and 0.97 lagging at the Point of Interconnection (TSRA Article 9.5.1); \nprovide frequency and voltage ride-through capability (TSRA Article 9.6.1); and install system \nprotection facilities and other protective devices (TSRA Article 9.6.3).  The TSRA also provides \nfor the exchange of switching and tagging rules and of disturbance analysis data, including \noscillography, protective relay targets, breaker operations, and sequence of events records \n(TSRA Article 9); sets maintenance obligations for both parties (TSRA Article 10); and"},{"page":17,"startToken":5379,"endToken":5729,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 17 \nNovember 16, 2026  \n \n17 \naddresses Emergency Conditions, including the Participating TO’s authority to reduce service to, \nor disconnect, the Large Load (TSRA Article 13).   \nThe TSRA also provides for the design, procurement, and construction of facilities \nneeded to serve the Large Load (TSRA Article 5).  The Participating TO uses Reasonable Efforts \nto complete its Interconnection Facilities, Distribution Upgrades, and Large Load Network \nUpgrades by the dates in Appendix C (Article 5.1).  Design and procurement begin once the \nInterconnection Studies are complete, the Participating TO has received the customer’s written \nauthorization to proceed by the date specified in Appendix C, and the customer has provided the \nrequired security (Article 5.2).  Construction begins once any required regulatory approvals and \nreal property rights have been obtained and the customer has given its written authorization to \nproceed with construction (Article 5.3).  That said, the (generally applicable) seven-year limit \nfrom service request to Service Commencement Date means that the customer must provide such \nwritten authorization at such a time that leaves sufficient time to complete facilities before this \nseven-year period runs out.  The TSRA also requires the customer to provide specifications for \nits own interconnection facilities, initially at least 180 Calendar Days, and in final form at least \n90 Calendar Days, before the Service Commencement Date, so that the Participating TO can \nconfirm they are compatible with the Transmission System (Article 5.6.1). \nFor customers that elect FILI, TSRA Article 9.7 provides that the conditions and \nlimitations applicable to FILI service, including curtailments, are specified in Appendix E to the \nTSRA.  In addition, such customers must execute the FILI Agreement included as Attachment 4 \nto the LLIP with SCE and the CAISO before the Service Commencement Date (LLIP Section \n4.6.2.1).  That agreement describes the circumstances in which the CAISO or SCE may \ntemporarily curtail the Large Load, and the mechanism that will be used to do so, consistent with \nSection 25.7.2 of the CAISO Tariff.  FILI is discussed further in Section II.C below."},{"page":18,"startToken":5729,"endToken":6051,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 18 \nNovember 16, 2026  \n \n18 \nThe TSRA includes seven appendices (Appendices A through G) that are completed for \neach Large Load Interconnection Customer.  Under LLIP Section 5.1, within 30 Calendar Days \nafter the Report Meeting for the final Large Load Interconnection Study report (or the final FILI \nStudy report, if applicable), the Participating TO tenders a draft TSRA together with draft \nappendices, and the customer has 30 Calendar Days to provide written comments or notify the \nParticipating TO that it has none.  The parties may negotiate the appendices for up to 60 \nCalendar Days after the final study report; the customer must then execute the TSRA, request \nthat it be filed unexecuted, or initiate dispute resolution, or its Interconnection Request is deemed \nwithdrawn, and the Participating TO may declare an impasse and file the TSRA unexecuted with \nthe Commission within 21 Calendar Days (LLIP Sections 5.2 and 5.3).  The appendices are \ndescribed below. \nAppendix A (Description of Participating TO’s Interconnection Facilities, Large Load \nNetwork Upgrades, Distribution Upgrades, Costs, Payments and Interconnection Financial \nSecurity) describes the scope of work for the Large Load Interconnection Customer’s \nInterconnection Facilities and for the Participating TO’s Interconnection Facilities, Distribution \nUpgrades, and Large Load Network Upgrades identified in the Large Load Interconnection \nStudy, together with the associated cost estimates, payments, and security.  The LLIP also \ndefines the Point of Interconnection and the Point of Change of Ownership by reference to \nAppendix A.   \nAppendix B (Requirements for Mitigation of Potential Cost Shifting Related to New \nTransmission Facilities) is the central cost-shifting protection in the TSRA, as described in \nSection II.B below, and it is the appendix to which TSRA Articles 11.3, 11.4.2.1, and 11.4.2.3 \nrefer.   \nAppendix C (Milestones) sets the dates for the design, procurement, and construction of \nthe Participating TO’s Interconnection Facilities, Distribution Upgrades, and Large Load"},{"page":19,"startToken":6051,"endToken":6330,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 19 \nNovember 16, 2026  \n \n19 \nNetwork Upgrades, against which the Participating TO uses Reasonable Efforts to complete its \nwork (TSRA Article 5.1).  It also sets the dates by which the customer must provide written \nauthorization to proceed with design, procurement, and construction and post the required \nInterconnection Financial Security (TSRA Articles 5.2, 5.3, and 11.4).  If the Participating TO \nreasonably expects that it will not meet a milestone date, it must promptly notify the customer in \nwriting. \nAppendix D (Interconnection Details) sets out the interconnection details and operating \nrequirements with which the customer must operate the Large Load, which are updated as those \nrequirements change (TSRA Article 9.3).   \nAppendix E (Flexible Interim Load Interconnection Conditions) applies only to \ncustomers that elect FILI.  It is where the conditions and limitations of the interim service, \nincluding curtailments, are specified under TSRA Section 9.8, and it is used together with the \nFILI Agreement in Attachment 4 to the LLIP.   \nAppendix F (Security Arrangements Details) addresses the infrastructure security of the \nParticipating TO’s Transmission System and Distribution System equipment and its operations \nand control hardware and software.  It states the expectation that the CAISO, transmission \nproviders, market participants, and Large Load Interconnection Customers interconnected to the \nParticipating TO’s Transmission System will comply with infrastructure-protection \nrecommendations and best practices, including physical, operational, and cyber-security \npractices. \nB.  COST SHIFTING MITIGATION \nOrder Section B (“Cost Shifting Risk Among Transmission Customers”) preliminarily \nfound that CAISO’s Tariff and/or the TO Tariffs appear to be unjust and unreasonable because \nthey lack adequate mechanisms to mitigate the risk of cost shifting among transmission"},{"page":20,"startToken":6330,"endToken":6673,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 20 \nNovember 16, 2026  \n \n20 \ncustomers, which may result in unjust and unreasonable rates for transmission service.9  In \nparticular, the Commission was concerned about the apparent lack of (1) transparency regarding \nthe assignment of network upgrades, and their associated costs, that are needed to provide \ntransmission service to Eligible Customers on behalf of large loads; and (2) a pro forma cost \nrecovery agreement to help ensure that Eligible Customers bear the risk and are ultimately \nresponsible for costs incurred to provide transmission service, including the cost of network \nupgrades.10 \nThe Order directed the CAISO and the PTOs to explain whether the tariffs remain just \nand reasonable without (1) robust, accurate, and systematic provision of data on CAISO’s \nwebsite in a single location, and in an easily accessible format that is searchable and allows users \nto filter the data, regarding the cost for network upgrades needed to provide transmission service \nto Eligible Customers on behalf of large loads; and (2) a pro forma cost recovery agreement \nbetween CAISO, the relevant transmission owner, and the Eligible Customer taking transmission \nservice on behalf of a large load, or to propose tariff revisions to provide additional transparency \nand establish such a pro forma cost recovery agreement.11 \nIn response to the Order, the CAISO is not proposing changes to its Tariff to address cost \nshifting risk among transmission customers.  Instead, as stated in the CAISO Draft Final \nProposal, it believes it is prudent for cost allocation rules to be set forth in the PTO tariffs rather \nthan the CAISO tariff.12   In the absence of CAISO tariff changes, changes to each PTO’s tariff \nwill be required in order to mitigate cost shifting.  Accordingly, SCE is proposing revisions to its \nTO Tariff to mitigate cost shifting risks associated with the interconnection of large loads to \nSCE’s transmission system. SCE understand the general framework and Large Load obligations \n \n9  Id. at P 65. \n10  Id. \n11  Id. at P 66. \n12  CAISO Draft Final Proposal, p. 44."},{"page":21,"startToken":6673,"endToken":7007,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 21 \nNovember 16, 2026  \n \n21 \nof SCE’s proposal are aligned with PG&E’s proposal.  Each Large Load Interconnection \nCustomer will be subject to these cost obligations. \n1. \nTariff Changes to Mitigate the Risk of Cost Shifting for Transmission \nFacilities to Serve Large Load \nThe cost obligation provisions of SCE’s proposal are found in the LLIP and in the pro \nforma Transmission Security and Reliability Agreement (“TSRA”) (Attachment 3 to the LLIP).  \nAs discussed above in Section II.A.2, SCE understands that the Commission’s intent was not to \nexclude SCE’s own retail transmission customers from new FERC-jurisdictional, transmission-\nrelated obligations associated with transmission service to large loads (including obligations \nrelated to the avoidance of cost shifting).  SCE’s LLIP transmission security requirements thus \napply to either an Eligible Customer seeking to interconnect a Large Load, or where the Large \nLoad Owner is SCE’s retail transmission customer, the Large Load Owner.   \nObligating Large Load Owners who are SCE’s retail transmission customers to comply \nwith cost shifting mitigation requirements is necessary in order to achieve the Commission’s \ngoals of reducing the risk of cost shifting among transmission customers.  As noted above in \nSection II.A.2, SCE does not interconnect to its own TO Tariff as an Eligible Customer of itself \nwhen interconnecting its own transmission retail customers to SCE’s transmission system.  Even \nif SCE were, hypothetically, determined to be an Eligible Customer of itself, any cost obligations \nresulting from the construction of new SCE transmission facilities that are assigned to SCE \nwould flow into SCE’s Formula Rate and thus, into the Transmission Access Charge (“TAC”) \npaid by all CAISO participants.  Thus, obligating only SCE (as a fictional Eligible Customer) to \npay transmission network upgrade costs would not satisfy the requirements of the Order to Show \nCause to help prevent cost shifts among transmission customers since all of those costs would \nend up in the TAC regardless.  In the absence of any state law obligation or voluntary"},{"page":22,"startToken":7007,"endToken":7334,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 22 \nNovember 16, 2026  \n \n22 \nagreement,13 SCE believes that obligating the Large Load Owner who is SCE’s retail \ntransmission customer to provide cost shift mitigation security is thus required to comply with \nthe Commission’s Order. \nSCE’s proposal does not impermissibly invade the Local Regulatory Authority’s \njurisdiction over retail customers, as it is clear that the Commission retains jurisdiction over the \nallocation of certain transmission costs.  For instance, the Commission determines transmission \nrates for SCE’s retail rate classes in ruling on SCE’s Formula Rate, which is part of SCE’s TO \nTariff.  As discussed in Section II.A.2 above, SCE’s proposed tariff revisions align with \njurisdictional boundaries, given that the Large Load Owners who are SCE’s retail transmission \ncustomers still seek interconnection through state law tariffs.  The TSRA does not supplant those \nstate law tariffs, but layers in additional cost provisions that are solely directed at FERC-\njurisdictional costs for transmission system upgrades.  Allocation for distribution system costs \nand distribution retail rates remains exclusively with the Local Regulatory Authority.       \nThe TSRA mitigates cost shifting for network upgrades through provisions located in \nTSRA Article 11 and Appendix B in three ways: (1) security for Large Load Network Upgrades \ntriggered by the Large Load Interconnection Customer, and as applicable, any additional \nupgrades identified by the CAISO; (2) a 15-year minimum transmission revenue obligation \nbacked by 5 years of security, which is meant to protect against stranded asset costs of broader \nnetwork upgrades; and (3) exit fees for early termination.  Collectively, these provisions help \nmitigate the potential for cost shifts to other transmission customers arising out of the \ninterconnection of large loads where the large load does not materialize as planned or is not \ndeveloped at all.14  \n \n13 Currently no state law tariff requires SCE’s retail transmission customers to provide security or \npayments for transmission network upgrades that are necessary to serve their load.  \n14 Order at P 82."},{"page":23,"startToken":7334,"endToken":7665,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 23 \nNovember 16, 2026  \n \n23 \nFirst, the Large Load Interconnection Customer must provide Interconnection Financial \nSecurity at least 30 Calendar Days before work begins on the Large Load Network Upgrades \nattributable to it (TSRA Section 11.4.2.1).  Large Load Network Upgrades are defined as “the \nadditions, modifications, and upgrades to the CAISO Controlled Grid at or beyond the Point of \nInterconnection necessary to serve one or more Large Loads safely and reliably that are \nidentified through the Large Load Interconnection Study and sent to the CAISO for concurrence \npursuant to ISO Tariff Section 25.7.”  (LLIP Section 2).  That security equals the estimated cost \nof the upgrades, including engineering, procurement, construction, and overhead, and increases if \nthe scope changes.  In recognition of the reduced need for security to protect against cost shifting \nonce the large load customer begins paying transmission rates, once retail service begins, the \nLarge Load Interconnection Customer may reduce its associated security annually by 75% of the \namount of MWh counted as Gross Load of the Large Load Interconnection Customer associated \nwith withdrawals by the Large Load multiplied by the Regional Access Charge.  Any balance \nremaining after fifteen years is drawn down and credited under SCE’s Formula Rate via the \nTransmission Revenue Balancing Account Adjustment (TO Tariff Article 3.106).  Likewise, \nwhere the CAISO determines that additional cost-shifting protection is needed concerning shared \nnetwork upgrade costs, the costs for such upgrades will be included in the security requirement.  \n(TSRA Section 2, defining “ISO-Identified Network Upgrades.”)  In the case where the Large \nLoad Interconnection Customer is expected to drive significant additional transmission costs, the \nidentification of ISO-Identified Network Upgrades will allow for additional cost-shifting \nprotection.   \nSecond, Appendix B imposes a Minimum Annual Revenue Obligation (“MARO”) so that \nthe Large Load contributes to the transmission revenue requirement even if it does not ramp as \nplanned.  Each year’s MARO equals the Minimum Obligation Capacity (in MW) for that year,"},{"page":24,"startToken":7665,"endToken":8023,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 24 \nNovember 16, 2026  \n \n24 \ntimes the hours in the year, times 80% and 75%,15 times the Regional Access Charge.  The rates \nare fixed for fifteen years, and a fifteen-year Minimum Capacity Schedule, reaching the \ncustomer’s Requested Maximum Load by Year 5, sets the capacity.  A delay in the load’s ramp \ndoes not postpone scheduled increases.  The MARO is intended to cover at least some of the \ntransmission network costs associated with transmission service to the Large Load \nInterconnection Customer that are not identified as Large Load Network Upgrades.  Such costs \nwould include, for instance, shared network upgrades included in the CAISO’s TPP process to \nserve data center load growth, which could result in cost shifting to other transmission customers \nif the Large Load Interconnection Customer’s load does not materialize as expected.  SCE \nreconciles the MARO annually.  If the customer’s retail transmission revenues exceed the \nMARO, nothing further is due.  Otherwise, SCE invoices the shortfall, payable within 30 \nCalendar Days, and the payment is treated as revenue providing a Transmission Revenue Credit \nin SCE’s Formula Rate process, which reduces the risk of transmission cost shifting to other \ntransmission customers.  The customer must also post security for the MARO equal to five years \nof the MARO at full capacity.  If a shortfall goes unpaid for 60 Calendar Days, SCE may draw \non that security, and the customer must replenish it within 30 Calendar Days. \nThird, the customer bears the cost of prematurely terminating service through exit fees.  \nBefore service begins, a customer that fails to take service owes a Withdrawal Penalty equal to \nthe greater of 20% of its estimated Large Load Network Upgrade costs or the actual cost of \nabandoned facilities (TSRA Appendix B; LLIP Section 3.10.1(c)).  After service begins, early \ntermination triggers an Exit Fee equal to all remaining required security, including the MARO \nsecurity, due within 30 Business Days, and SCE may draw on the security if it is not paid.   \n \n15 The 80% multiplier approximates the capacity factor of the Large Load, and the 75% multiplier \nrepresents the minimum payment threshold."},{"page":25,"startToken":8023,"endToken":8362,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 25 \nNovember 16, 2026  \n \n25 \nFinally, in order to avoid creating duplicative credit support requirements, Section \n11.4.2.4 provides that Large Load Interconnection Customer may avoid duplicative credit \nrequirements by demonstrating to Participating TO that security or payments provided pursuant \nto a retail agreement with the Large Load Owner satisfies some portion of Large Load \nInterconnection Customer’s obligations.16 \nIn the absence of CAISO direction on cost-shifting mitigation, SCE believes that it is \nimportant for the various PTOs to align, to the extent possible, on the approach to mitigation in \norder to ensure consistency across the CAISO territory.  As noted, SCE understands that its cost \nshifting mitigation proposal shares key features with those of other PTOs. PG&E in particular is \nproposing substantively similar cost-shifting mitigation measures in its own tariff revisions, \nincluding an additional minimum revenue obligation intended to cover broader network upgrades \nabove and beyond those Large Load Network Upgrades triggered by the Large Load.  In \nresponse to the Commission’s Briefing Question at P 125, SCE believes that its proposed \napproach provides the appropriate structure and minimum level of protection to prevent unjust \nand unreasonable cost shifts among transmission customers related to network upgrade costs \nrequired for large loads at this time.  SCE also supports the CAISO’s commitment to explore \nadditional cost-shifting protection for non-FERC-jurisdictional PTOs in a future stakeholder \nprocess.17 \n \n16 Order at P 82 (“We preliminarily find that an Eligible Customer may include a credit support or other \nfinancial security posted by a large load as part of a retail agreement to avoid creating duplicative \ncredit support requirements.”) \n17 CAISO Draft Final Proposal, p. 42 (“The CAISO additionally recognizes the ultimate need to bring \nnon-FERC jurisdictional PTOs into alignment with the cost allocation framework of the FERC-\njurisdictional PTOs.  The CAISO proposes to address this framework in a future CAISO stakeholder \ninitiative and filing, once greater certainty exists around the mechanisms the PTOs propose to adopt \nto prevent cost-shifting under this Order.”)"},{"page":26,"startToken":8362,"endToken":8669,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 26 \nNovember 16, 2026  \n \n26 \nC.  FLEXIBLE SERVICE \nIn Section D of the Order (“Extending New Transmission Services to Eligible Customers \nTaking Service on Behalf of Flexible Large Loads”), the Commission preliminarily found that \nthe CAISO tariff may be unjust and unreasonable because it does not include transmission \nservices that reflect Eligible Customers taking transmission service on behalf of flexible large \nloads that are willing and able to limit their use of the transmission system under certain \nconditions.18  The Order directed the CAISO to explain whether its Tariff remains just and \nreasonable without the transmission services described by the Commission in the PJM Co-\nLocation Order, with regional variation as appropriate, being available to Eligible Customers \ntaking transmission service on behalf of flexible large loads, or propose appropriate Tariff \nrevisions.   \nAs stated in the CAISO Draft Final Proposal, the CAISO is not proposing to create new \n“transmission services” or create more responsibilities around Eligible Customers, which would \nrequire redesigning transmission and interconnection service entirely.19  The CAISO does not \nbelieve such a redesign is warranted, and the Commission expressly invited the CAISO to \nexplain alternative service frameworks that may enable similar flexibility.  Instead, the CAISO \nproposes to create new, flexible interim interconnection service options that will enable large \nloads and co-located loads to limit their energy withdrawals or injections until the needed \nnetwork upgrades are complete.  The CAISO’s proposed name for this service is Flexible Interim \nLoad Interconnection.  The CAISO Draft Final Proposal indicated that PTOs will have the \nprimary role in defining and implementing this interconnection service offering.20  For instance, \nCAISO has not proposed a pro forma FILI agreement as part of its tariff revisions.  Instead, the \n \n18  Order at P 104. \n19  CAISO Draft Final Proposal, p. 67. \n20  Id. at p. 66."},{"page":27,"startToken":8669,"endToken":8997,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 27 \nNovember 16, 2026  \n \n27 \nCAISO tariff revisions indicate that each PTO will have its own pro forma agreement to \nmemorialize the terms of any FILI arrangement.   \nIn the CAISO Draft Final Proposal, the CAISO indicated that it sees value in \ndevelopment of permanent flexible service approach but defers the permanent offering to a \nfuture initiative.21  SCE concurs that there is value to developing a permanent flexible service \nand agrees that the CAISO will need to play a lead role in the development of that proposal.  \nSCE continues to see customer benefits in flexibility and will actively participate in the CAISO’s \nfuture stakeholder process to develop that permanent flexible service.  \nAlthough the Order did not direct SCE, as a PTO, to provide an interim flexible service \nfor large loads, SCE is supporting the CAISO’s proposed FILI in this filing, including by \nproposing its own pro forma FILI agreement.   \n1. \nTariff Changes to Implement New Flexible Interim Interconnection Service \nSCE proposes tariff changes to implement FILI, which the LLIP defines as curtailable, \ninterim transmission interconnection service for a Large Load, provided by the CAISO and the \nParticipating TO, that enables the Large Load to interconnect before completion of specified \nLarge Load Network Upgrades, Distribution Upgrades, or the Participating TO’s Interconnection \nFacilities.  Specifically, SCE proposes to offer FILI through Sections 4.6.2 and 4.6.2.1 of the \nLLIP, Section 9.7 and Appendix E of the TSRA, and the new FILI Agreement. \nTo obtain FILI, a large load would first request interconnection under the LLIP.  If the \n90-day Large Load Interconnection Study finds that the full amount of the large load’s \ninterconnection request cannot be accommodated without transmission network upgrades, the \nlarge load may request a FILI Study to determine (i) whether the Large Load may interconnect \nand begin receiving limited service before all upgrades are completed; (ii) the conditions and \n \n21  Id. at p. 68."},{"page":28,"startToken":8997,"endToken":9345,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 28 \nNovember 16, 2026  \n \n28 \nlimitations of such service; (iii) the upgrades and the associated cost; and (iv) the estimated \nduration required to provide the limited service (LLIP Section 4.6.2). \nThe Large Load Interconnection Customer may request a FILI Study after the Large \nLoad Interconnection Study.  If the customer elects to proceed with a FILI Study, the \nParticipating TO will complete the study within 60 Calendar Days (LLIP Section 4.6.2).  The \nParticipating TO will perform the FILI Study, and the Large Load Interconnection Customer will \nbe responsible for the actual costs of the study.  If at any time the Participating TO determines \nthat it will not meet the required time frame for completing the FILI Study, it shall notify the \ncustomer of the schedule status and provide an estimated completion date with an explanation of \nthe reasons why additional time is required.  The Participating TO will share the results with the \nCAISO for review and concurrence, and if the customer requests it within 10 Business Days after \nthe FILI Study report is issued, the Participating TO, the CAISO, and the customer will hold a \nReport Meeting (LLIP Section 4.6.2).   \nAs detailed in Section 9.8 and Appendix E of the TSRA and in the FILI Agreement \n(Attachment 4 to the LLIP), large loads with FILI will be subject to the operational requirements \nto ensure that they do not cause reliability impacts on the grid, including potential curtailment.  \nOnce transmission network upgrades are completed, the Large Load will be able to have its full \nload served (i.e., receive firm service). \nSCE understands other PTOs are also presenting similar FILI proposals in their tariff \nrevisions. \nD.  PROXIMATE LARGE LOAD AND CO-LOCATED LOAD \nIn Section E (“Interconnection Customers Serving Electrically Proximate Large Load and \nCo-Located Load”), the Order found that that the CAISO tariff appears to be unjust and \nunreasonable because it does not contain provisions allowing an interconnection customer to \nseek the generator interconnection service(s) that reflects the operational dynamics of serving"},{"page":29,"startToken":9345,"endToken":9705,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 29 \nNovember 16, 2026  \n \n29 \neither: (1) an electrically proximate large load; or (2) a co-located load, as defined in the Order, \nthat has a high peak load (i.e., large co-located loads that are 50 MW or greater).22 The \nCommission defined an “electrically proximate large load” as a large load “sufficiently \nelectrically close to the interconnection customer’s requested point of interconnection, such that \nthe impact on the transmission system of the combination of the generating facility and the load, \nwith the exception of the transmission facilities between the two, will be effectively the same as \nif they were located at the same substation (e.g., large load that is located no more than two \nsubstations from the generating facility).”23  The Order did not direct SCE, as a PTO, to take any \naction regarding proximate large loads. \nIn the CAISO Draft Final Proposal, the CAISO proposes considering provisions for \ninterconnection customers to serve electrically proximate large loads in a future stakeholder \ninitiative.24  The CAISO stated that it intends to prioritize the more common stand-alone and co-\nlocated load and generator interconnections with this proposal and filing and will focus on \nproximate load and generation arrangements once the process for co-location is underway.  SCE \nsupports the CAISO’s proposal to consider provision regarding proximate load in a future \nstakeholder initiative.   \nIn Section C (“Co-Location Arrangements and Load with Behind the Meter Generation”), \nthe Commission preliminarily found the CAISO tariff to be deficient as it does not currently \naddress the rates, terms, and conditions that apply to co-location arrangements.25  SCE supports \nthe CAISO proposal to clarify how co-located large loads and generation may interconnect to \nand operate within the CAISO-controlled grid and will work with the CAISO to implement this \nproposal.  SCE agrees with CAISO that the PTOs will continue to govern and study all load \n \n22  Order at P 113. \n23  Id. at P 112. \n24  CAISO Draft Final Proposal, p. 69.  The term interconnection customer is lower-cased and undefined, \nbut presumably refers to a generator or a combination of generation and storage. \n25 Order at P 93."},{"page":30,"startToken":9705,"endToken":10022,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 30 \nNovember 16, 2026  \n \n30 \ninterconnection requests pursuant to their tariffs, and the CAISO will continue to govern and \nstudy wholesale generation interconnection requests of exporting generators.  SCE also supports \nthe CAISO proposal that new or existing large loads seeking to co-locate with new generation \nthat may export energy to the transmission grid will require a CAISO interconnection study \nunder the CAISO’s Resource Interconnection Standards, Appendix KK to the CAISO Tariff. \nThe Commission also posed several Briefing Questions regarding co-located and \nproximate loads.  In response to the Commission’s Briefing Question at P 124 regarding the \nimpacts of new transmission services, SCE emphasizes that neither the CAISO nor SCE are \nproposing any new transmission services.  Because no new transmission services are being \nproposed, there will be no impact of the introduction of new transmission services on \ntransmission planning in the CAISO.  Of note, neither the CAISO nor the PTOs are proposing \n“permanent flexibility” at this time.  The CAISO has committed to an additional stakeholder \nprocess to explore the details on what “permanent flexibility” could encompass.26  SCE supports \nfurther exploration of permanent flexibility that has the potential to provide customer benefits \nincluding reduced transmission costs (for both the interconnecting customer and likely other \ntransmission customers), as well as potential reliability benefits.  Implementation of permanent \nflexibility is likely to impact multiple aspects of the transmission process, including \ninterconnection, operations and planning.  However, until the CAISO concludes this future \nprocess, it is premature to describe its impacts on the transmission planning process. \nWith respect to the Briefing Questions at P 127 concerning co-located and proximate \ngenerators’ participation in the energy and ancillary services market and considerations \nregarding resource adequacy, SCE notes that the CAISO Tariff governs both participation in the \nCAISO’s energy and ancillary services market and how generating facilities count for the \n \n26 CAISO Draft Final Proposal, p. 68."},{"page":31,"startToken":10022,"endToken":10287,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 31 \nNovember 16, 2026  \n \n31 \npurposes of resource adequacy.  Accordingly, SCE believes that these questions are best \npositioned for a response by CAISO. \n1. \nTariff Changes to Address Co-Located Load \nAs discussed above in Section II.A, all new Large Loads will be required to comply with \nthe application and study procedures in the LLIP, as well as the operational requirements in the \nTSRA.  This will include any Large Loads with non-exporting co-located generation.  \nAdditionally, SCE has incorporated specific provisions to address the Commission’s concerns \nabout co-located loads, including:  \n• Scope of LLIP study for non-exporting co-located generation. Co-\nlocated generation serving a Large Load that will not export to the CAISO \nControlled Grid is evaluated for impacts on SCE’s Transmission System \nas part of the LLIP study process, provided it is included in the \nInterconnection Request (LLIP Section 3.1).  The Large Load \nInterconnection Study identifies the impacts of the Large Load and the \nincremental impacts of non-exporting co-located generation that is not \nsubject to short circuit duty dependence (LLIP Section 4.6.1.1). \n• Exporting co-located generation. Co-located generation that will export \nto the CAISO Controlled Grid must submit a separate generator \ninterconnection request to the CAISO under Section 25.7.6 and Appendix \nKK of the CAISO Tariff, while the Large Load itself is evaluated under \nthe LLIP (LLIP Section 3.1; LLIP Attachment 1). \n• Interconnection Request form.  LLIP Attachment 1 (Interconnection \nRequest form)  requires a description of any co-located generation, \nincluding whether it will export, its proposed date of initial operation, and"},{"page":32,"startToken":10287,"endToken":10531,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 32 \nNovember 16, 2026  \n \n32 \ngross Large Load and gross co-located generation reported separately (not \nnetted); maximum net withdrawal with the generation online; the largest \nco-located unit or storage device that could trip; and firm and curtailable \nwithdrawal requested when the generation is unavailable (which cannot \nexceed the requested maximum load).  It also requires non-export control \ninformation, including ride-through capability and protection settings, the \nexpected response of the generation and load to a sudden loss of either, \nprotection coordination, and disturbance monitoring. \n• Technical data. Large Loads co-locating with non-exporting generation \nmust complete the applicable generator data in Appendix A to LLIP \nAttachment 1 (synchronous, induction, wind, or inverter-based), including \npower flow, dynamic and, if required, EMT models. \n• Inverter standards. New LLIP Section 3.11 requires inverters in co-\nlocated generating facilities, including storage that later injects electricity, \nto meet UL-1741 and UL-1741 Supplement B certification. \n• Study base case. The Base Case used for the Interconnection Studies may \ninclude Large Loads and any co-located generation (LLIP Section 2). \n• Cost responsibility and security. Under TSRA Sections 11.3.1 and \n11.4.2.2, the customer bears the full actual cost of, and must post security \nat least 30 Calendar Days before work begins on, Large Load Network \nUpgrades attributable to non-export co-located generation.  Where the \ncustomer is SCE’s retail transmission customer, cost assignment and \nsecurity follow SCE’s retail tariffs, subject to the Local Regulatory \nAuthority."},{"page":33,"startToken":10531,"endToken":10835,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 33 \nNovember 16, 2026  \n \n33 \n• Construction, testing and operation. The TSRA extends to co-located \ngeneration, where applicable, the as-built drawing and data requirements \n(Section 5.6.3); pre- and post-service testing, parallel-operation approval \nand right to observe testing (Sections 6.1–6.3); operation and maintenance \nobligations and coordination (Sections 9.4, 10.2, 10.3); synchronization \n(Section 9.5); and system protection and fault-removal requirements \n(Sections 9.7.4.1 and 9.7.5).  The customer may not operate the co-located \ngeneration in parallel with SCE’s system without SCE’s prior written \napproval. \n• Metering and changes in data. “Metering Equipment” includes metering \nat co-located generation, and the customer may not energize or operate the \nLarge Load or co-located generation until SCE completes studies when the \ncustomer’s actual data differs materially from that originally provided \n(TSRA Article 24.3). \nE.  SUMMARY OF OTHER PROPOSED TARIFF CHANGES \nIn addition to the proposed changes described above, SCE is proposing revisions to the \nbody of its TO Tariff that are necessary to incorporate the new LLIP and clarify certain \nprovisions.  These changes are summarized below. \ni. \nThe Table of Contents has been revised to add a new appendix, Appendix XV (Large \nLoad Interconnection Procedures) and its Attachments 1 through 4. \nii. \nSections 1 and 1.3 have been modified to clarify the entities that provide retail \ntransmission service that may apply for Large Loads interconnections.  \niii. \nThe introduction of Section 3 has been revised to account for defined terms in \nAppendix XV.  SCE has also revised the definition of a Transmission Revenue Credit \nto confirm that any remaining Interconnection Financial Security under the TSRA \nthat has been drawn down by Participating TO will be included as a Transmission \nRevenue Credit in calculating SCE’s Transmission Revenue Balancing Account \nAdjustment."},{"page":34,"startToken":10835,"endToken":11164,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 34 \nNovember 16, 2026  \n \n34 \niv. \nSection 4 has been revised to clarify Eligible Customers who qualify for transmission \nservice under the CAISO Tariff.  \nv. \nSection 7.1 has been revised to incorporate Appendix XV. \nvi. \nSection 8.1 has been revised to incorporate the interconnection of Large Loads as a \nParticipating TO obligation as governed by Appendix XV. \nvii. \nSection 9.1 has been revised to indicate that expansions on behalf of Large Loads are \ngoverned by Appendix XV.   \nviii. \nSection 10.1 has been revised to indicate that requests for interconnection on behalf \nof Large Loads are governed by Appendix XV rather than the existing wholesale load \nprocedures. \nix. \nSection 13.2 has been revised to reference Appendix XV, as applicable.    \nIII. \nEFFECTIVE DATE  \nSCE requests that the Commission accept the tariff revisions submitted in this \ncompliance filing effective as of February 16, 2027, 92 days after the date of this filing. \nIV. \nCONTENTS OF FILING \nBesides this transmittal letter, this filing includes these attachments: \nAtt. A  \nClean TO Tariff sheets incorporating this compliance filing \nAtt. B  \nRed-lined document showing the revisions in this compliance filing \nThe Marked Tariff Attachment includes TO Tariff Sections 1, 3, 4, 7-10, and 13.  SCE \nseeks a waiver of the need to redline TO Tariff Appendix XV, which is a brand new Appendix.  \nV. \nOTHER FILING REQUIREMENTS \nNo expenses or costs included in the rates tendered herein have been  \nalleged or judged in any administrative or judicial proceeding to be illegal, duplicative, or \nunnecessary costs that are demonstrably the product of discriminatory employment practices. \nSCE believes that the data contained in this letter and the attachments provide sufficient \ninformation upon which to approve this filing; however, to the extent necessary, SCE further \nrequests that the Commission waive its filing requirements contained in Sections 35.5 and 35.13 \nof the Commission’s regulations (18 C.F.R. §§ 35.5 and 35.13)."},{"page":35,"startToken":11164,"endToken":11357,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 35 \nNovember 16, 2026  \n \n35 \nSCE believes that this filing conforms to any rule of general applicability and to any \nCommission order specifically applicable to SCE and, upon request, will make this letter and all \nenclosures available for public inspection in SCE’s principal office located in Rosemead, \nCalifornia. SCE has served copies of this transmittal to those persons whose names appear on the \nmailing list enclosed. \nVI. \nCORRESPONDENCE  \nPursuant to Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, SCE \nrequests that all correspondence, pleadings, and other communications regarding the filing \nshould be directed to the following:   \n \n \n \n \n \nEllen Kenney  \n \n \n \n \n \nSenior Attorney \n \n \n \n \n \nSouthern California Edison Company  \n \n \n \n \n \nP.O. Box 800 \n \n \n \n \n \nRosemead, CA 91770 \n \n \n \n \n \nTel (626) 949-3825 \n \n \n \n \n \nEmail: Ellen.Kenney@sce.com \nWith a copy to:  \nJeffrey Nelson  \n \n \n \n \n \nDirector, FERC Rates & Market Integration \n \n \n \n \n \nSouthern California Edison Company  \n \n \n \n \n \nP.O. Box 800 \n \n \n \n \n \nRosemead, CA 91770 \n \n \n \n \n \nTel (626) 302-4834 \n \n \n \n \n \nEmail: Jeffrey.Nelson@sce.com \nVII. NOTICE \nIn addition to serving the California Public Utilities Commission, SCE is serving notice \nof these proposed tariff revisions on all parties to EL26-71-000 and SCE’s TO Tariff customers."},{"page":36,"startToken":11357,"endToken":11422,"text":"Ms. Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \nPage 36 \nNovember 16, 2026  \n \n36 \nVIII. CONCLUSION  \nFor the reasons set forth above, SCE respectfully requests that the Commission accept \nSCE’s proposed tariff revisions as filed, and rescind the Order to Show Cause as to SCE’s TO \nTariff. \n \n \nVery truly yours,  \n \n \n/s/ Jeffrey Nelson \n \n \nJeffrey Nelson \nSouthern California Edison Company  \nDirector, FERC Rates & Market Integration"},{"page":37,"startToken":11422,"endToken":11428,"text":"ATTACHMENT A \n \nClean TO Tariff Sheets"},{"page":38,"startToken":11428,"endToken":11691,"text":"Southern California Edison Company   \nFERC Electric Tariff, Third Revised Volume No. 6 \nTABLE OF CONTENTS \n1.  PREAMBLE ............................................................................................................................... \n1.1  Transmission Access for Participating TOs ................................................................  \n1.2  Transmission Access for Wheeling Customers ..........................................................  \n1.3  Transmission Access for End-Users ...........................................................................  \n2.  EFFECTIVE DATE .................................................................................................................... \n3.  TO DEFINITIONS ...................................................................................................................... \n4.  ELIGIBILITY .............................................................................................................................. \n5.  ACCESS CHARGES AND TRANSMISSION RATES...............................................................  \n5.1  Low Voltage Access Charge .........................................................................................  \n5.2  Wheeling Access Charge ..............................................................................................  \n5.3  End-User Transmission Rates ......................................................................................  \n5.4  Transmission Revenue Requirement ...........................................................................  \n5.5  Transmission Revenue Balancing Account Adjustment (TRBAA). ...........................  \n5.6  Transmission Access Charge Balancing Account Adjustment (TRBAA). ................  \n6.  ANCILLARY SERVICES - APPLICABILITY AND CHARGES .................................................  \n7.  BILLING AND PAYMENT ......................................................................................................... \n7.1  End-Users ....................................................................................................................... \n7.2  Low Voltage Access Charge Revenues .......................................................................  \n    7.2.1  Billing Procedure .................................................................................................... \n    7.2.2  Interest on Unpaid Balances ..................................................................................  \n    7.2.3  Default ...................................................................................................................... \n7.3  Wheeling and Usage Charge Revenues .......................................................................  \n8. OBLIGATION TO INTERCONNECT OR CONSTRUCT TRANSMISSION EXPANSIONS &\nFACILITY UPGRADES .................................................................................................................. \n8.1  Participating TO Obligation to Interconnect ................................................................  \n    8.1.1  Interconnection to Transmission System .............................................................  \n        8.1.1.1  Letter Agreement .............................................................................................  \n    8.1.2  Costs Associated with Interconnection ................................................................  \n    8.1.3  Interconnection Agreement ...................................................................................  \n    8.1.4  Due Diligence to Construct ....................................................................................  \n    8.1.5  Energization ............................................................................................................. \n    8.1.6  Coordination with ISO on Interconnection Requests ..........................................  \n8.2  Participating TO Obligation to Construct Transmission Expansions or Facility \nUpgrades ................................................................................................................................ \n    8.2.1  Obligation to Construct ..........................................................................................  \n    8.2.2  Local Furnishing Participating TO Obligation to Construct ...............................  \n8.3  Request for FERC Deference Regarding Need Determination ..................................  \n9.  EXPANSION PROCESS ........................................................................................................... \n9.1  Determination of Facilities ............................................................................................  \n    9.1.1  Payment of Facilities Study’s Cost .......................................................................  \n Tariff Record Proposed Effective Date: 02/16/27 \n Version Number: 19.0.0 \n       Option Code:  A"},{"page":39,"startToken":11691,"endToken":12005,"text":"Southern California Edison Company   \nFERC Electric Tariff, Third Revised Volume No. 6 \n    9.1.1.1  Market Participant to Pay for Facilities Study ...............................................  \n    9.1.1.2  Project Sponsor or Project Proponent to Pay for Facilities Study ..............  \n    9.1.1.3  Principal Beneficiaries to Pay for Facilities Study ........................................  \n    9.1.2  Payment Procedure ................................................................................................  \n    9.1.3  Facilities Study Procedures ...................................................................................  \n9.2  Obligation to Build ......................................................................................................... \n    9.2.1  Due Diligence to Construct ....................................................................................  \n    9.2.2  Delay in Construction or Expansion .....................................................................  \n    9.2.2.1  Alternatives to the Original Facility Additions ..............................................  \n    9.2.2.2  Refund Obligation for Unfinished Facility Additions ....................................  \n9.3  Provisions Relating To Transmission Construction On the Systems Of Other \nTOs ......................................................................................................................................... \n    9.3.1  Responsibility for Third Party Additions ..............................................................  \n    9.3.2  Coordination of Third-Party System Additions ....................................................  \n    9.3.3  Expansion by “Local Furnishing Participating TOs” ...........................................  \n10.  INTERCONNECTION PROCESS ...........................................................................................  \n10.1  Applicability .................................................................................................................. \n10.2  Applications .................................................................................................................. \n10.3  Interconnection Application ........................................................................................  \n10.4  Review of Completed Interconnection Application ..................................................  \n10.5  Notice of Need for System Impact Study ...................................................................  \n10.6  System Impact Study Cost Reimbursement ..............................................................  \n    10.6.1  Cost Reimbursement ............................................................................................  \n    10.6.2  Multiple Parties ...................................................................................................... \n10.7  System Impact Study Procedures ..............................................................................  \n    10.7.1  Procedures Upon Completion of System Impact Study ....................................  \n10.8   Notice of Need for Facilities Study ............................................................................  \n10.9  Facilities Study Procedures ........................................................................................  \n    10.9.1  Execution of Interconnection Agreement ...........................................................  \n10.10  Partial Interim Service ...............................................................................................  \n10.11  Expedited Interconnection Procedures ...................................................................  \n11.  UNCONTROLLABLE FORCES AND INDEMNIFICATION ....................................................  \n11.1  Procedures To Follow if Uncontrollable Force Occurs ............................................  \n11.2  Indemnification ............................................................................................................. \n12.  REGULATORY FILINGS ......................................................................................................... \n12.1  Open Access ................................................................................................................ \n        12.2  STRANDED COST RECOVERY ...................................................................................  \n13.  CREDITWORTHINESS ........................................................................................................... \n13.1  UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low \nVoltage Transmission Facilities ..........................................................................................  \n13.2  End-Users ..................................................................................................................... \n14.  DISPUTES ............................................................................................................................... \n15.  RECOVERY OF RELIABILITY SERVICES COSTS ...............................................................  \n16.  MISCELLANEOUS .................................................................................................................. \n16.1  Notices .......................................................................................................................... \n16.2  Waiver ........................................................................................................................... \n16.3  Confidentiality .............................................................................................................. \n    16.3.1  Maintaining Confidentiality If Not for Public Disclosure ...................................  \n    16.3.2  Disclosure of Confidential Information ..............................................................."},{"page":40,"startToken":12005,"endToken":12161,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n16.4  TO Tariff Supersedes Existing Tariffs ........................................................................  \n16.5  Titles .............................................................................................................................. \n16.6  Severability ................................................................................................................... \n16.7  Preservation of Obligations ........................................................................................  \n16.8  Governing Law ............................................................................................................. \n16.9  Appendices Incorporated ............................................................................................  \n16.10  Conflict With ISO Tariff ..............................................................................................  \n16.11  Conflicting Operating Instructions ...........................................................................  \n16.12  Self Provision of Ancillary Services .........................................................................  \n \n \nAPPENDIX I - TRANSMISSION REVENUE REQUIREMENT .......................................................  \nAPPENDIX II - CHARGES FOR WHOLESALE TRANSMISSION SERVICES .............................  \nAPPENDIX III – TRANSMISSION RATES FOR END-USE SERVICE ..........................................  \nAPPENDIX IV – RATES FOR CERTAIN ANCILLARY SERVICE BIDS .......................................  \nAPPENDIX V - NOTICES ............................................................................................................... \nAPPENDIX VI - RELIABILITY SERVICES RATE SCHEDULE .....................................................  \nAPPENDIX VII - INTERCONNECTION PROCEDURES IN EFFECT PRIOR TO JULY 1, 2005 ...  \nAPPENDIX VIII – NOT USED ......................................................................................................... \nAPPENDIX IX – FORMULA RATE ................................................................................................  \nAPPENDIX X – RATE SCHEDULE FOR RECOVERY OF COSTS ASSOCIATED WITH \nFACILITIES INSTALLED PURSUANT TO INTERCONNECTION AGREEMENTS.…………….. \nAPPENDIX XI – TRANSMISSION MAINTENANCE AND COMPLIANCE REVIEW .....................  \nAPPENDIX XII – STAKEHOLDER REVIEW PROCESS ...............................................................  \nAPPENDIX XIII – LETTER AGREEMENT .....................................................................................  \nAPPENDIX XIV -  WEST OF DEVERS FORMULA RATE……………………………….................. \nAPPENDIX XV – LARGE LOAD INTERCONNECTION PROCEDURES………………………….."},{"page":41,"startToken":12161,"endToken":12404,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n1.  Preamble.  \nThe Participating TO's revenue requirements and applicable rates and charges for \ntransmission access over the ISO Controlled Grid and the terms and conditions for \ntransmission expansion and interconnection are set forth in this TO Tariff and the ISO \nTariff. \n1.1  Transmission Access for Participating TOs. \nParticipating TOs are able to participate in the ISO and utilize the entire ISO Controlled \nGrid to serve their End-Use Customers.  The applicable High Voltage Access Charges \nand Transition Charges shall be paid by Participating TOs to the ISO pursuant to the \nISO Tariff.  If a Participating TO utilizes the Low Voltage Transmission Facilities of \nanother Participating TO, such Participating TO shall also pay the Low Voltage Access \nCharge of the other Participating TO.  \n1.2  Transmission Access for Wheeling Customers. \nWheeling allows Scheduling Coordinators to deliver Energy through or out of the ISO \nControlled Grid to serve a load located outside the transmission or Distribution System \nof a Participating TO.  Wheeling Access Charges shall be paid by Scheduling \nCoordinators to the ISO pursuant to the ISO Tariff. \n1.3  Transmission Access for End-Users.   \nEnd-Users receive transmission service over the ISO Controlled Grid through the Utility \nDistribution Company, Small Utility Distribution Company, or MSS Operator to whose \ntransmission or distribution facilities the End-User is directly connected.  Charges to \nEnd-Users for access to the ISO Controlled Grid shall be paid to the applicable Utility"},{"page":42,"startToken":12404,"endToken":12436,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nDistribution Company, Small Utility Distribution Company, or MSS Operator to whose \ntransmission or distribution facilities the End-User is directly connected."},{"page":43,"startToken":12436,"endToken":12691,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n3.  TO Definitions. \nCapitalized terms used in this TO Tariff shall have the meanings set out below or in \nAppendix XV unless otherwise stated.  Capitalized terms used in this tariff and not \ndefined below or in Appendix XV shall have the meanings set out in the ISO Tariff. \n3.1 \nAccess Charge.  A charge paid by all UDCs, MSSs and, in certain cases, \nScheduling Coordinators, delivering Energy to Gross Load, as set forth in Section 26.1 \nof the ISO Tariff.  The Access Charge includes the High Voltage Access Charge, the \nTransition Charge, and the Low Voltage Access Charge. \n3.2 \nAutomatic Generation Control (AGC).  Generation equipment that \nautomatically responds to signals from the ISO’s EMS control in real time to control the \npower output of electric generators within a prescribed area in response to a change in \nsystem frequency, tieline loading, or the relation of these to each other, so as to \nmaintain the target system frequency and/or the established interchange with other \nareas within the predetermined limits. \n3.3 \nAncillary Services.  Regulation, Spinning Reserve, Non-Spinning Reserve, \nVoltage Support and Black Start together with such other interconnected operation \nservices as the ISO may develop in cooperation with Market Participants to support the \ntransmission of Energy from Generation resources to Loads while maintaining reliable \noperation of the ISO Controlled Grid in accordance with Good Utility Practice. \n \n \n                        Tariff Record Proposed Effective Date: 05/01/2026 \n \n  \n \n                           Version Number: 16.0.0 \n \n \n \n \n \n \n \n \n \n \n \nOption Code:  A"},{"page":44,"startToken":12691,"endToken":12897,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n3.4 \nApplicable Reliability Criteria.  The reliability standards established by NERC, \nWECC, and Local Reliability Criteria as amended from time to time, including any \nrequirements of the Nuclear Regulatory Commission. \n3.5 \nAvailable Transfer Capacity.  For a given transmission path, the capacity rating \nin MW of the path established consistent with ISO and WECC transmission capacity \nrating guidelines, less any reserved uses applicable to the path. \n3.6 \nBase Transmission Revenue Requirement.  The Transmission Revenue \nRequirement before deducting the Transmission Revenue Balancing Account \nAdjustment (TRBAA) and, for wholesale purposes, before deducting Standby \nTransmission Revenues. \n3.7 \nBlack Start.  The procedure by which a Generating Unit self-starts without an \nexternal source of electricity thereby restoring power to the ISO Controlled Grid \nfollowing system or local area blackouts. \n3.8 \nBusiness Day.  Monday through Friday, excluding federal holidays and the day \nafter Thanksgiving Day. \n3.9 \n(Omitted) \n3.10 Completed Application Date.  The date on which a party submits an \nInterconnection Application that satisfies the requirements of a Completed \nInterconnection Application.  \n3.11 Completed Interconnection Application.  An Interconnection Application that \nsatisfies all of the information and other requirements of Section 10.3 of this TO Tariff."},{"page":45,"startToken":12897,"endToken":13166,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.12 Congestion.  A condition that occurs when there is insufficient Available \nTransfer Capacity to implement all Preferred Schedules simultaneously or, in real time, \nto serve all Generation and Demand.  “Congested” shall be construed accordingly. \n3.13 Congestion Management.  The alleviation of Congestion in accordance with \napplicable ISO Protocols and Good Utility Practice. \n3.14 Converted Rights.  Those transmission service rights as defined in Section \n4.3.1.6 of the ISO Tariff. \n3.15 CPUC.  The California Public Utilities Commission, or its successor. \n3.16 (Omitted) \n3.17 Demand.  The rate at which Energy is delivered to Loads and Scheduling Points \nby Generation, transmission or distribution facilities.  It is the product of voltage and the \nin-phase component of alternating current measured in units of watts or standard \nmultiples thereof, e.g., 1,000W = 1kW, 1,000kW = 1MW, etc. \n3.18 Direct Assignment Facilities.  Facilities or portions of facilities that are owned \nby the Participating TO necessary to physically and electrically interconnect a particular \nparty requesting Interconnection under this TO Tariff to the ISO Controlled Grid at the \npoint of interconnection.  Direct Assignment Facilities shall be specified in the \nInterconnection Agreement that governs Interconnection service to such party and shall \nbe subject to FERC approval.  \n3.19 Dispatch.  The operating control of an integrated electric system to: i) assign \nspecific Generating Units and other sources of supply to effect the supply to meet the \nrelevant area Demand taken as Load rises or falls; ii) control operations and \nmaintenance of high voltage lines, substations, and equipment, including administration"},{"page":46,"startToken":13166,"endToken":13463,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nof safety procedures; iii) operate interconnections; iv) manage Energy transactions with \nother interconnected Control Areas; and v) curtail Demand.   \n3.20 Distribution System.  The distribution assets of a TO, UDC, or MSS.   \n3.21 Eligible Customer.  (i) Any utility (including Participating TOs, Market \nParticipants and any power marketer), Federal power marketing agency, or any person \ngenerating Energy for sale or resale; Energy sold or produced by such entity may be \nEnergy produced in the United States, Canada or Mexico; however, such entity is not \neligible for transmission service that would be prohibited by Section 212(h)(2) of the \nFederal Power Act; and (ii) any retail customer taking unbundled transmission service \npursuant to a state retail access program or pursuant to a voluntary offer of unbundled \nretail transmission service by the Participating TO. \n3.22 Encumbrance.  A legal restriction or covenant binding on the Participating TO \nthat affects the operation of any transmission lines or associated facilities and which the \nISO needs to take into account in exercising Operational Control over such transmission \nlines or associated facilities if the Participating TO is not to risk incurring significant \nliability.  Encumbrances shall include Existing Contracts and may include:  (1) other \nlegal restrictions or covenants meeting the definition of Encumbrance and arising under \nother arrangements entered into before the ISO Operations Date, if any; and (2) legal \nrestrictions or covenants meeting the definition of Encumbrance and arising under a \ncontract or other arrangement entered into after the ISO Operations Date.  \n3.23 End-Use Customer or End-User.  A purchaser of electric power who purchases \nsuch power to satisfy a Load directly connected to the ISO Controlled Grid or to a \nDistribution System and who does not resell the power."},{"page":47,"startToken":13463,"endToken":13727,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.24 Energy.  The electrical energy produced, flowing or supplied by generation, \ntransmission or distribution facilities, being the integral with respect to time of the \ninstantaneous power, measured in units of watt-hours or standard multiples thereof, \ne.g., 1,000 Wh = 1kWh, 1,000 kWh = 1MWh, etc. \n3.25 Entitlements.  The right of the Participating TO obtained through contract or \nother means to use another entity's transmission facilities for the transmission of \nEnergy.  \n3.26 Existing Contracts.  The contracts which grant transmission service rights in \nexistence on the ISO Operations Date (including any contracts entered into pursuant to \nsuch contracts) as may be amended in accordance with their terms or by agreement \nbetween the parties thereto from time to time. \n3.27 Existing Rights.  The transmission service rights and obligations of non-\nParticipating TOs under Existing Contracts, including all terms, conditions, and rates of \nthe Existing Contracts, as they may change from time to time under the terms of the \nExisting Contracts. \n3.28 Expedited Interconnection Agreement.  A contract between a party which has \nsubmitted a Request for Expedited Interconnection Procedures and the Participating TO \nunder which the Participating TO agrees to process, on an expedited basis, the \nCompleted Interconnection Application of such party and which sets forth the terms, \nconditions, and cost responsibilities for such interconnection.   \n3.29 Facilities Study Agreement.  An agreement between a Participating TO and \neither a party requesting Interconnection to the ISO Controlled Grid, Market Participant, \nProject Sponsor, or identified principal beneficiaries pursuant to which the party"},{"page":48,"startToken":13727,"endToken":14004,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nrequesting such Interconnection, Market Participants, Project Sponsor, or identified \nprincipal beneficiaries agrees to reimburse the Participating TO for the cost of \nperforming or reviewing a Facilities Study. \n3.30 Facility or Facilities Study.  An engineering study conducted to determine \nrequired modifications to the Participating TO’s transmission system, including the \nestimated cost and scheduled completion date for such modifications that will be \nrequired to provide needed services. \n3.31 FERC.  The Federal Energy Regulatory Commission or its successor.  \n3.32 FPA.  Parts II and III of the Federal Power Act, 16 U.S.C. § 824 et seq., as they \nmay be amended from time to time. \n3.33 FTR (Firm Transmission Right).  A contractual right, subject to the terms and \nconditions of the ISO Tariff, that entitles the FTR Holder to receive, for each hour of the \nterm of the FTR, a portion of the Usage Charges received by the ISO for transportation \nof energy from a specific originating Zone to a specific receiving Zone and, in the event \nof an uneconomic curtailment to manage Day-Ahead congestion, to a Day-Ahead \nscheduling priority higher than that of a schedule using Converted Rights capacity that \ndoes not have an FTR.  \n3.34 FTR Holder.  The owner of an FTR, as registered with the ISO.  \n3.35 Generating Unit.  An individual electric generator and its associated plant and \napparatus whose electrical output is capable of being separately identified and metered \nor a Physical Scheduling Plant that, in either case, is: (a) located within the ISO Control \nArea; (b) connected to the ISO Controlled Grid, either directly or via interconnected"},{"page":49,"startToken":14004,"endToken":14317,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ntransmission, or distribution facilities; and (c) that is capable of producing and delivering \nnet Energy (Energy in excess of a generating station’s internal power requirements). \n3.36 Generation.  Energy delivered from a Generating Unit. \n3.37 Good Utility Practice.  Any of the practices, methods, and acts engaged in or \napproved by a significant portion of the electric utility industry during the relevant time \nperiod, or any of the practices, methods, and acts which, in the exercise of reasonable \njudgment in light of the facts known at the time the decision was made, could have been \nexpected to accomplish the desired result at a reasonable cost consistent with good \nbusiness practices, reliability, safety, and expedition.  Good Utility Practice is not \nintended to be any one of a number of the optimum practices, methods, or acts to the \nexclusion of all others, but rather to be acceptable practices, methods, or acts generally \naccepted in the region. \n3.38 Gross Load.  Gross Load is all Energy (adjusted for distribution losses) \ndelivered for the supply of End-User Loads directly connected to the transmission \nfacilities or Distribution System of the Participating TO.  Gross Load shall exclude the \nportion of the Load of an individual End-Use Customer of the Participating TO that is \nserved by a Generating Unit that: (a) is located on the customer's site or provides \nservice to the customer's site through over-the-fence arrangements as authorized by \nSection 218 of the California Public Utilities Code; (b) is a qualifying small power \nproduction facility or qualifying cogeneration facility, as those terms are defined in the \nFERC's regulations implementing Section 201 of the Public Utility Regulatory Policies \nAct of 1978; (c) was serving the customer's Load on or before March 31, 2000; and (d) \nsecured Standby Service from the Participating TO under terms approved by a Local"},{"page":50,"startToken":14317,"endToken":14594,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nRegulatory Authority or FERC, as applicable, as of March 31, 2000 and continues to \nsecure Standby Service from the Participating TO or can be curtailed concurrently with \nan outage of the Generating Unit serving the Load. \n3.39 High Voltage Access Charge.  A component of the Access Charge determined \nby the ISO and assessed to the Participating TO under Section 26.1 of the ISO Tariff. \n3.40 High Voltage Existing Contracts Access Charge.  A charge for access to the \nISO Controlled Grid under certain specified Existing Contracts to be paid by the Existing \nContract holder to the Participating TO.  Such rate shall be calculated by dividing the \nHigh Voltage Transmission Revenue Requirement applicable to wholesale customers \nby the sum of Edison’s twelve monthly retail system peak demands measured at the \nISO Controlled Grid level, consistent with such revenue requirement.    \n3.41 High Voltage Transmission Facility.  A transmission facility under the \noperational control of the ISO that is owned by the Participating TO or to which the \nParticipating TO has an Entitlement that is represented by a Converted Right and that \noperates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs \nof which are not directly assigned to one or more specific customers. \n3.42 High Voltage Transmission Revenue Requirement.  The portion of the \nParticipating TO's TRR associated with and allocable to the Participating TO's High \nVoltage Transmission Facilities and Converted Rights associated with High Voltage \nTransmission Facilities.  \n3.43 High Voltage Utility-Specific Rate.  The Participating TO's High Voltage \nTransmission Revenue Requirement divided by the Participating TO's forecasted Gross \nLoad."},{"page":51,"startToken":14594,"endToken":14852,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.44 High Voltage Wheeling Access Charge.  The Wheeling Access Charge \nassessed by the ISO associated with the recovery of the Participating TOs' High \nVoltage Transmission Revenue Requirements in accordance with Section 26.1 of the \nISO Tariff. \n3.45 (Omitted) \n3.46 Interconnection.  Transmission facilities, other than additions or replacements \nto existing facilities that: i) connect one system to another system where the facilities \nemerge from one and only one substation of the two systems and are functionally \nseparate from the ISO Controlled Grid facilities such that the facilities are, or can be, \noperated and planned as a single facility; or ii) are identified as radial transmission lines \npursuant to contract; or iii) produce Generation at a single point on the ISO Controlled \nGrid; provided that such interconnection does not include facilities that, if not owned by \nthe Participating TO, would result in a reduction in the ISO’s Operational Control of the \nParticipating TO’s portion of the ISO Controlled Grid. \n3.47 Interconnection Agreement.  A contract between a party requesting \nInterconnection and the Participating TO that owns the transmission facility with which \nthe requesting party wishes to interconnect. \n3.48 Interconnection Application.   An application that requests Interconnection to \nthe ISO Controlled Grid. \n3.49 Interest.  Interest shall be calculated in accordance with the methodology \nspecified for interest on refunds in the regulations of FERC at 18 C.F.R. \n§35.19(a)(2)(iii)(1996).  Interest on delinquent amounts shall be calculated from the due"},{"page":52,"startToken":14852,"endToken":15102,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ndate of the bill to the date of payment.  When payments are made by mail, bills shall be \nconsidered as having been paid on the date of receipt. \n3.50 Independent System Operator (“ISO”).  The California Independent System \nOperator Corporation, a state chartered, nonprofit corporation that controls the \ntransmission facilities of all Participating TOs and dispatches certain Generating Units \nand Loads. \n3.51 ISO ADR Procedures.  The procedures for resolution of disputes or differences \nset out in Section 13 of the ISO Tariff, as amended from time to time. \n3.52 ISO Controlled Grid.  The system of transmission lines and associated facilities \nof the Participating TOs that have been placed under the ISO’s Operational Control.  \n3.53 ISO Protocols.  The rules, protocols, procedures and standards promulgated by \nthe ISO (as amended from time to time) to be complied with by the ISO Scheduling \nCoordinators, Participating TOs and all other Market Participants in relation to the \noperation of the ISO Controlled Grid and the participation in the markets for Energy and \nAncillary Services in accordance with the ISO Tariff. \n3.54 ISO Tariff.  The California Independent System Operator Agreement and Tariff, \ndated March 31, 1997, as it may be modified from time to time. \n3.55 Load.  An end-use device of an End-Use Customer that consumes power.  Load \nshould not be confused with Demand, which is the measure of power that a Load \nreceives or requires. \n3.56 (Omitted)"},{"page":53,"startToken":15102,"endToken":15366,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.57 Local Furnishing Bond.  Tax-exempt bonds utilized to finance facilities for the \nlocal furnishing of electric energy, as described in section 142(f) of the Internal Revenue \nCode, 26 U.S.C. § 142(f). \n3.58 Local Furnishing Participating TO.  Any Tax-Exempt Participating TO that \nowns facilities financed by Local Furnishing Bonds. \n3.59 Local Publicly Owned Electric Utilities.  A municipality or municipal \ncorporation operating as a public utility furnishing electric service, a municipal utility \ndistrict furnishing electric service, a public utility district furnishing electric services, an \nirrigation district furnishing electric services, or a joint powers authority that includes one \nor more of these agencies and that owns Generation or transmission facilities, or \nfurnishes electric services over its own or its members’ electric Distribution System. \n3.60 Local Regulatory Authority.  The state or local governmental authority \nresponsible for the regulation or oversight of a utility.  \n3.61 Local Reliability Criteria.  Reliability criteria established at the ISO Operations \nDate, unique to the transmission systems of each of the Participating TOs. \n3.62 Low Voltage Access Charge.  The Access Charge applicable under Section \n26.1 of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement \nof the Participating TO. \n3.63 Low Voltage Existing Contracts Access Charge.  A charge for access to the \nISO Controlled Grid under certain specified Existing Contracts to be paid by the Existing \nContract holder to the Participating TO.  Such rate shall be calculated by dividing the \nLow Voltage Transmission Revenue Requirement applicable to wholesale customers by"},{"page":54,"startToken":15366,"endToken":15636,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nthe sum of Edison’s twelve monthly retail system peak demands measured at the ISO \nControlled Grid level, consistent with such revenue requirement.    \n3.64 Low Voltage Transmission Facility.  A transmission facility under the \noperational control of the ISO owned by the Participating TO or to which the \nParticipating TO has an Entitlement that is represented by a Converted Right, which is \nnot a High Voltage Transmission Facility, and supporting facilities, and the costs of \nwhich are not directly assigned to one or more specific customers. \n3.65 Low Voltage Transmission Revenue Requirement.  The portion of the \nParticipating TO's TRR associated with and allocable to the Participating TO's Low \nVoltage Transmission Facilities and Converted Rights associated with Low Voltage \nTransmission Facilities. \n3.66 Low Voltage Wheeling Access Charge.  The Wheeling Access Charge \nassociated with the recovery of the Participating TO's Low Voltage Transmission \nRevenue Requirement in accordance with Section 26.1 of the ISO Tariff. \n3.67 Market Participant.  An entity, including a Scheduling Coordinator, who \nparticipates in the Energy marketplace through the buying, selling, transmission, or \ndistribution of Energy or Ancillary Services into, out of, or through the ISO Controlled \nGrid.  \n3.68 MSS (Metered Subsystem).  A geographically contiguous system located within \na single zone which has been operating as an electric utility for a number of years prior \nto the ISO Operations Date as a municipal utility, water district, irrigation district, State \nagency or Federal power administration subsumed within the ISO Control Area and \nencompassed by ISO certified revenue quality meters at each interface point with the"},{"page":55,"startToken":15636,"endToken":15892,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nISO Controlled Grid and ISO certified revenue quality meters on all Generating Units or, \nif aggregated, each individual resource and Participating Load internal to the system, \nwhich is operated in accordance with a MSS agreement described in Section 4.9.1 of \nthe ISO Tariff. \n3.69 NERC.  The North American Electric Reliability Council or its successor. \n3.70 (Omitted) \n3.71 (Omitted) \n3.72 New High Voltage Transmission Facility.  A High Voltage Transmission \nFacility of the Participating TO that enters service after the beginning of the transition \nperiod described in Section 4 of Schedule 3 of Appendix F of the ISO Tariff, or a capital \naddition made after the beginning of the transition period described in Section 4.2 of \nSchedule 3 of Appendix F of the ISO Tariff to an Existing High Voltage Transmission \nFacility. \n3.73 New Participating TO.  A Participating TO that is not an Original Participating \nTO. \n3.74 Non-Participating TO.  A TO that is not a party to the TCA or for the purposes of \nSection 16.1 of the ISO Tariff the holder of transmission service rights under an Existing \nContract that is not a Participating TO. \n3.75 Non-Spinning Reserve.   The portion of off-line generating capacity that is \ncapable of being synchronized and ramping to a specified load in ten minutes (or load \nthat is capable of being interrupted in ten minutes) and that is capable of running (or \nbeing interrupted) for at least two hours."},{"page":56,"startToken":15892,"endToken":16199,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.76 Operational Control.  The rights of the ISO under the Transmission Control \nAgreement and the ISO Tariff to direct Participating TOs how to operate their \ntransmission lines and facilities and other electric plant affecting the reliability of those \nlines and facilities for the purpose of affording comparable non-discriminatory \ntransmission access and meeting Applicable Reliability Criteria. \n3.77 Original Participating TO.  A Participating TO that was a Participating TO as of \nJanuary 1, 2000.  The Original Participating TOs are Pacific Gas and Electric Company, \nSouthern California Edison Company, and San Diego Gas & Electric Company. \n3.78 Participating TO.  A party to the TCA whose application under Section 2.2 of the \nTCA has been accepted and who has placed its transmission assets and Entitlements \nunder the ISO’s Operational Control in accordance with the TCA.  A Participating TO \nmay be an Original Participating TO or a New Participating TO.  For purposes of this TO \nTariff, the Participating TO is Southern California Edison Company.  \n3.79 Participation Agreement.  An agreement between a Participating TO and a \nProject Sponsor that specifies the terms and conditions under which the Participating \nTO will construct a transmission addition or upgrade on behalf of the Project Sponsor. \n3.80 Physical Scheduling Plant.  A group of two or more related Generating Units, \neach of which is individually capable of producing Energy, but which either by physical \nnecessity or operational design must be operated as if they were a single Generating \nUnit and any Generating Unit or Units containing related multiple generating \ncomponents which meet one or more of the following criteria: i) multiple generating \ncomponents are related by a common flow of fuel which cannot be interrupted without a \nsubstantial loss of efficiency of the combined output of all components; ii) the Energy"},{"page":57,"startToken":16199,"endToken":16469,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nproduction from one component necessarily causes Energy production from other \ncomponents; iii) the operational arrangement of related multiple generating components \ndetermines the overall physical efficiency of the combined output of all components; iv) \nthe level of coordination required to schedule individual generating components would \ncause the ISO to incur scheduling costs far in excess of the benefits of having \nscheduled such individual components separately; or v) metered output is available only \nfor the combined output of related multiple generating components and separate \ngenerating component metering is either impractical or economically inefficient. \n3.81 (Omitted)  \n3.82 Project Proponent.  A Market Participant or group of Market Participants that: (i) \nadvocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the \nproposed transmission addition and upgrade, and thus is not a Project Sponsor; and (iii) \ninitiates proceedings under the ISO ADR Procedures to determine the need for the \nproposed transmission addition or upgrade. \n3.83 Project Sponsor.  A Market Participant or group of Market Participants or a \nParticipating TO that proposes the construction of a transmission addition or upgrade in \naccordance with Section 24 of the ISO Tariff. \n3.84 Regional Transmission Group (“RTG”).  A voluntary organization approved by \nFERC and composed of transmission owners, transmission users, and other entities, \norganized to efficiently coordinate the planning, expansion and use of transmission on a \nregional and inter-regional basis. \n3.85 Regulation.  The service provided either by Generating Units certified by the ISO \nas equipped and capable of responding to the ISO’s direct digital control (AGC) signals,"},{"page":58,"startToken":16469,"endToken":16762,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nor by System Resources that have been certified by the ISO as capable of delivering \nsuch service to the ISO Balancing Authority Area, in an upward and downward direction \nto match, on a Real-Time basis, Demand and resources, consistent with established \nApplicable Reliability Criteria.  Regulation is used to control the power output of electric \ngenerators within a prescribed area in response to a change in system frequency, tieline \nloading, or the relation of these to each other so as to maintain the target system \nfrequency and/or the established Interchange with other Balancing Authority Areas \nwithin the predetermined Regulation Limits.  Regulation includes both the increase of \noutput by a Generating Unit or System Resource (Regulation Up) and the decrease in \noutput by a Generating Unit or System Resource (Regulation Down).  Regulation Up \nand Regulation Down are distinct capacity products, with separately stated \nrequirements and ASMPs in each Settlement Period.  \n3.86 Reliability Criteria.  Pre-established criteria that are to be followed in order to \nmaintain desired performance of the ISO Controlled Grid under contingency or steady \nstate conditions. \n3.87 Reliability Services.  Those services provided by the ISO:  1) that are deemed \nby the ISO as necessary to maintain reliable electric service in the ISO Control Area; \nand 2) whose costs are billed by the ISO to the Participating TO pursuant to the ISO \nTariff.  Reliability Services include services obtained from:  Reliability Must-Run units; \nand generators committed pursuant to the ISO’s Exceptional Dispatch authority, which \nincludes any costs of Exceptional Dispatches as well as any default costs allocated to \nthe Participating TO resulting from its incurrence of Exceptional Dispatch costs pursuant \nto Section 11.29.17.2.1 of the CAISO Tariff."},{"page":59,"startToken":16762,"endToken":16994,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.88 Reliability Upgrade.  The transmission facilities, other than Direct Assignment \nFacilities, beyond the first point of Interconnection necessary to interconnect a \nwholesale load safely and reliably to the ISO Controlled Grid, which would not have \nbeen necessary but for the Interconnection of a wholesale load, including network \nupgrades necessary to remedy short circuit or stability problems resulting from the \ninterconnection of a wholesale load to the ISO Controlled Grid.  Reliability Upgrades \nalso include, consistent with WECC practice, the facilities necessary to mitigate any \nadverse impact a wholesale load’s interconnection may have on a path’s WECC path \nrating.  Reliability Upgrades shall be specified in the Interconnection Agreement that \ngoverns Interconnection service to the wholesale load and shall be subject to FERC \napproval.   \n3.89 (Omitted).   \n3.90 Request for Expedited Interconnection Procedures.  A written request by \nwhich an applicant for Interconnection can request expedited processing of its \nInterconnection Application. \n3.91 Scheduling Coordinator.  An entity certified by the ISO for the purposes of \nundertaking the functions specified in Section 4.5.3 of the ISO Tariff. \n3.92 Scheduling Point.  A location at which the ISO Controlled Grid is connected, by \na group of transmission paths for which a physical, non-simultaneous transmission \ncapacity rating has been established for Congestion Management, to transmission \nfacilities that are outside the ISO’s Operational Control."},{"page":60,"startToken":16994,"endToken":17263,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.93 Spinning Reserve.  The portion of unloaded synchronized generating capacity \nthat is immediately responsive to system frequency and that is capable of being loaded \nin ten minutes, and that is capable of running for at least two hours. \n3.94 Standby Rate.  A rate assessed a Standby Service Customer by the \nParticipating TO, as approved by the Local Regulatory Authority, or FERC, as \napplicable, for Standby Service which compensates the Participating TO, among other \nthings, for costs of High Voltage Transmission Facilities. \n3.95 Standby Service.  Service provided by the Participating TO which allows a \nStandby Service Customer, among other things, access to High Voltage Transmission \nFacilities for the delivery of backup power on an instantaneous basis to ensure that \nEnergy may be reliably delivered to the Standby Service Customer in the event of an \noutage of a Generating Unit serving the customer's Load. \n3.96 Standby Service Customer.  A retail End-Use Customer of the Participating TO \nthat receives Standby Service and pays a Standby Rate. \n3.97 Standby Transmission Revenue.  The transmission rate revenues associated \nwith Standby Service collected by the Participating TO from those Standby Service \nCustomers who are not billed for Standby Service on a Gross Load basis.   \n3.98 System Impact Study.  An engineering study conducted to determine whether a \nrequest for Interconnection to the ISO Controlled Grid would require new transmission \nadditions, upgrades, or other mitigation measures.  \n3.99 System Impact Study Agreement.  An agreement between a Participating TO \nand an entity that has requested Interconnection to the Participating TO’s transmission"},{"page":61,"startToken":17263,"endToken":17534,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nsystem pursuant to which the entity requesting Interconnection agrees to reimburse the \nParticipating TO for the cost of performing or reviewing a System Impact Study. \n3.100 TO Tariff.  This Transmission Owner Tariff, as it may be amended or \nsuperseded. \n3.101 Transition Charge.  A component of the Access Charge determined by the ISO \nand assessed the Participating TO along with the High Voltage Access Charge in \naccordance with Section 5.7 of Appendix F, Schedule 3 of the ISO Tariff. \n3.102 Transmission Access Charge Balancing Account Adjustment (\"TACBAA\").  \nA mechanism established by the Participating TO which will ensure that the difference \nbetween (i) the actual charges by the ISO pursuant to Section 26.1.2 of the ISO Tariff \nfor the High Voltage Access Charge and Transition Charge and (ii) the revenues \ndisbursed by the ISO pursuant to Section 26.1.3 of the ISO Tariff are recovered from \nthe Participating TO's End-Use Customers. \n3.103 Transmission Control Agreement (“TCA”).  The agreement between the ISO \nand Participating TOs establishing the terms and conditions under which TOs will \nbecome Participating TOs and how the ISO and each Participating TO will discharge \ntheir respective duties and responsibilities, as may be modified from time to time. \n3.104 Transmission Owner (“TO”).  An entity owning transmission facilities or having \nfirm contractual rights to use transmission facilities.  \n3.105 Transmission Revenue Balancing Account Adjustment (“TRBAA”).  A \nmechanism established by the Participating TO which will ensure that all Transmission \nRevenue Credits and other credits specified in Sections 6 and 8 of Appendix F,"},{"page":62,"startToken":17534,"endToken":17802,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nSchedule 3 of the ISO Tariff, flow through to ISO Tariff and TO Tariff transmission \ncustomers. \n3.106 Transmission Revenue Credit.  The sum of:  1) the revenues received by the \nParticipating TO from the ISO for Wheeling service, including EDAM Recoverable \nRevenue; (2) the difference between the costs incurred by the Participating TO \nassociated with Existing Rights and the amount of such costs recovered by the \nParticipating TO from the Existing Rights customers (“ETC Cost Differentials”); (3) any \nadditional appropriate amounts included in the ISO Tariff definition of Transmission \nRevenue Credit set forth in Appendix A of the CAISO Tariff ; and (4) any remaining \nInterconnection Financial Security under the TSRA that has been drawn down by \nParticipating TO. \n3.107 Transmission Revenue Requirement (“TRR”).  The TRR is the total annual \nauthorized revenue requirements associated with transmission facilities and \nEntitlements turned over to the Operational Control of the ISO by the Participating TO, \nincluding the Projects under construction identified in Appendix VIII that are to be turned \nover to the Operational Control of the ISO upon completion.  The costs of any \ntransmission facility turned over to the Operational Control of the ISO, including the \ncosts of the Projects under construction identified in Appendix VIII that are to be turned \nover to the Operational Control of the ISO upon completion, shall be fully included in the \nParticipating TO's TRR.  The TRR includes the costs of transmission facilities and \nEntitlements and deducts Transmission Revenue Credits; for wholesale purposes, \ncredits for Standby Transmission Revenue; and the transmission revenue expected to"},{"page":63,"startToken":17802,"endToken":18050,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nbe actually received by the Participating TO for Existing Rights and Converted Rights.  \nThe TRR is shown in Appendix I. \n3.108 Uncontrollable Force.  Any act of God, labor disturbance, act of the public \nenemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, \norder, regulation or restriction imposed by governmental, military or lawfully established \ncivilian authorities or any other cause beyond the reasonable control of the ISO or \nMarket Participant which could not be avoided through the exercise of Good Utility \nPractice. \n3.109 Usage Charge.  The amount of money, per 1 kW of scheduled flow, that the ISO \ncharges a Scheduling Coordinator for use of a specific congested Inter-Zonal Interface \nduring a given hour. \n3.110 Utility Distribution Company (“UDC”).  An entity that owns a Distribution \nSystem for the delivery of Energy to and from the ISO Controlled Grid, and that provides \nregulated retail electric service to Eligible Customers, as well as regulated procurement \nservice to those End-Use Customers who are not yet eligible for direct access, or who \nchoose not to arrange services through another retailer. \n3.111 Voltage Support.  Services provided by Generating Units or other equipment \nsuch as shunt capacitors, static var compensators, or synchronous condensers that are \nrequired to maintain established grid voltage criteria.  This service is required under \nnormal or system emergency conditions. \n3.112 Western Electricity Coordinating Council (“WECC”).  The Western Systems \nCoordinating Council or its successor."},{"page":64,"startToken":18050,"endToken":18291,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.113 Wheeling Access Charge.  The charge assessed by the ISO that is paid by a \nScheduling Coordinator for Wheeling in accordance with Section 26.1 of the ISO Tariff.  \nWheeling Access Charges shall not apply for Wheeling under a bundled non-economy \nEnergy coordination agreement of a Participating TO executed prior to July 9, 1996.  \nThe Wheeling Access Charge may consist of a High Voltage Wheeling Access Charge \nand a Low Voltage Wheeling Access Charge. \n3.114 Wheeling Out.  Except for Existing Rights exercised under an Existing Contract \nin accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for \nthe transmission of Energy from a Generating Unit located within the ISO Controlled \nGrid to serve a Load located outside the transmission and Distribution System of a \nParticipating TO. \n3.115 Wheeling Through.  Except for Existing Rights exercised under an Existing \nContract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled \nGrid for the transmission of Energy from a resource located outside the ISO Controlled \nGrid to serve a Load located outside the transmission and Distribution System of a \nParticipating TO. \n3.116 Wheeling.  Wheeling Out or Wheeling Through. \n3.117 Wholesale Customer.  A person wishing to purchase Energy and Ancillary \nServices at a Bulk Supply Point or a Scheduling Point for resale. \n3.118 Omitted."},{"page":65,"startToken":18291,"endToken":18378,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n4.  Eligibility.   \nWholesale transmission service over a Participating TO’s system shall be provided only \nto Eligible Customers who qualify for transmission service under the ISO Tariff.  Any \ndispute as to whether a customer is eligible for wholesale transmission service shall be \nresolved by FERC and any dispute as to whether an End-Use Customer is eligible for \nretail transmission service or retail interconnection service under this TO Tariff shall be \nresolved by the Local Regulatory Authority."},{"page":66,"startToken":18378,"endToken":18625,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n7.  Billing and Payment. \n7.1  End-Users.   \nBilling and payment rules applicable to End-Users shall be pursuant to the then-current \nrules of the applicable Local Regulatory Authority and, as applicable, Appendix XV. \n7.2  Wholesale Customers.   \n7.2.1 Billing Procedure.  \n7.2.1.1  Low Voltage Access Charge Revenues.  Within a reasonable time after the \nParticipating TO receives from the ISO the monthly kilowatt-hours to which the Low \nVoltage Access Charge applies, the Participating TO shall submit an invoice to the \napplicable UDC, MSS or Scheduling Coordinator for the Low Voltage Access Charge \nbilling.  The invoice shall be paid by the UDC, MSS, or Scheduling Coordinator within \ntwenty days of receipt.  All payments shall be made in immediately available funds \npayable to the Participating TO, or by wire transfer to a bank named by the Participating \nTO.   \n7.2.1.2  Reliability Services Revenues.  The Participating TO shall submit an invoice \nto applicable Wheeling customers for billings under the Reliability Services Rate \nSchedule.  The invoice shall be paid by the Wheeling Customer within twenty days of \nreceipt.  All payments shall be made in immediately available funds payable to the \nParticipating TO, or by wire transfer to a bank named by the Participating TO. \n7.2.2  Interest on Unpaid Balances.   \nInterest on any unpaid amounts (including amounts placed in escrow) shall be \ncalculated in accordance with the methodology specified for interest on refunds in"},{"page":67,"startToken":18625,"endToken":18926,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nFERC’s regulations at 18 C.F.R. Section 35.19a(a)(2)(iii).  Interest on delinquent \namounts shall be calculated from the due date of the bill to the date of payment.  When \npayments are made by mail, bills shall be considered as having been paid on the date \nof receipt by the Participating TO. \n7.2.3  Default.  \nIn the event the UDC, MSS, Scheduling Coordinator, or Wheeling Customer fails, for \nany reason other than a billing dispute as described below, to make payment to the \nParticipating TO on or before the due date as described above, and such failure of \npayment is not corrected within 30 calendar days after the Participating TO notifies the \napplicable UDC, MSS, Scheduling Coordinator, or Wheeling Customer to cure such \nfailure, a default by the UDC, MSS, Scheduling Coordinator, or Wheeling Customer \nshall be deemed to exist.  Upon the occurrence of a default, the Participating TO may \ninitiate a proceeding with FERC (or the Local Regulatory Authority for a Local Publicly \nOwned Electric Utility) to terminate service but shall not terminate service until FERC, or \nthe Local Regulatory Authority, as applicable, so approves any such request.  In the \nevent of a billing dispute between the Participating TO and the UDC, MSS, Scheduling \nCoordinator, or Wheeling Customer, the Participating TO will continue to provide service \nunder this TO Tariff as long as the applicable UDC, MSS, Scheduling Coordinator, or \nWheeling Customer:  (i) continues to make all payments not in dispute, and (ii) pays into \nan independent escrow account the portion of the invoice in dispute, pending resolution \nof such dispute.  If the UDC, MSS, Scheduling Coordinator, or Wheeling Customer fails \nto meet these two requirements for continuation of service, then the Participating TO"},{"page":68,"startToken":18926,"endToken":18997,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nmay provide notice to the UDC, MSS, Scheduling Coordinator, or Wheeling Customer of \nits intention to suspend service in sixty days, in accordance with FERC policy. \n7.3  Wheeling and Usage Charge Revenues.   \nThe ISO, pursuant to the ISO Tariff, shall pay to Participating TOs all Wheeling and \nUsage Charge revenues, excluding Usage Charge revenues payable to FTR Holders."},{"page":69,"startToken":18997,"endToken":19254,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n8.  Obligation to Interconnect or Construct Transmission Expansions & Facility \nUpgrades.  \n8.1  Participating TO Obligation to Interconnect.   \nThe Participating TO shall, at the request of a third party pursuant to Section 10, \ninterconnect its system to the wholesale generation or wholesale load of such third \nparty, or modify an existing wholesale Interconnection.  Interconnections under this TO \nTariff shall be available to entities eligible to request Interconnection consistent with the \nprovisions of Section 210(a) of the FPA.  Interconnections requested by entities or \nindividuals that are not so eligible shall be governed by the Local Regulatory Authority.  \nThe procedures for Interconnections of wholesale generation to the ISO Controlled Grid \nshall be governed by the ISO Tariff, and if applicable, Appendix VII to the TO Tariff. \nInterconnections of Large Loads are governed by Appendix XV to the TO Tariff. \n8.1.1  Interconnection to Transmission System.   \nInterconnection must be consistent with Good Utility Practice, in conformance with all \nApplicable Reliability Criteria, all applicable statutes, regulations, and ISO reliability \ncriteria for the ISO Controlled Grid.  The Participating TO will not accommodate the \nInterconnection if doing so would impair system reliability, or would otherwise adversely \naffect the ability of the Participating TO to honor its Encumbrances existing as of the \ntime a party submits its Interconnection Application.  The Participating TO shall identify \nany such adverse effect on its Encumbrances in the System Impact Study performed \npursuant to Section 10.7.  To the extent the Participating TO determines that the"},{"page":70,"startToken":19254,"endToken":19546,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nInterconnection will have an adverse effect on Encumbrances, the party requesting \nInterconnection shall mitigate such adverse effect.   \n8.1.1.1  Letter Agreement. \nPursuant to Section 12 of Appendix DD of the ISO Tariff, prior to executing an \nInterconnection Agreement, a party seeking Interconnection may, in order to advance \nthe implementation of its Interconnection, request, and the Participating TO shall offer \nthe party, a Letter Agreement, a pro forma version of which is set forth in Appendix XIII \nto the TO Tariff, that authorizes the Participating TO to begin engineering, design, and \nprocurement of long lead-time items, or construction necessary for the establishment of \nthe Interconnection.  However, Participating TO shall not be obligated to offer a Letter \nAgreement if the party seeking Interconnection is in Dispute Resolution as a result of an \nallegation that the party seeking Interconnection has failed to meet any milestones or \ncomply with any prerequisites specified in the ISO Tariff.  The Letter Agreement is an \noptional procedure.  The Letter Agreement shall provide for the party seeking \nInterconnection to pay the cost of all activities authorized by the party and to make \nadvance payments or provide other satisfactory security for such costs. \nFollowing a party seeking Interconnection’s request for a Letter Agreement, the \nParticipating TO shall prepare and tender to the party seeking Interconnection a draft \nLetter Agreement in the form of the Participating TO’s FERC-approved Letter \nAgreement as set forth in Appendix XIII to the TO Tariff, including draft exhibits that \ninclude the proposed scope of work, estimated costs, payments, financial security and \nmilestones, as applicable.  The party seeking Interconnection shall provide written \ncomments, or notification of no comments, to the draft exhibits within thirty (30)"},{"page":71,"startToken":19546,"endToken":19849,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nCalendar Days.  The Participating TO and the party seeking Interconnection shall \nnegotiate concerning any disputed provisions of the exhibits to the draft Letter \nAgreement for not more than ninety (90) Calendar Days after the Participating TO \ntenders the draft Letter Agreement to the party seeking Interconnection.  If the party \nseeking Interconnection determines that negotiations are at an impasse, it may request \ntermination of the negotiations at any time after tender of the draft Letter Agreement and \nrequest submission of the unexecuted Letter Agreement with FERC or initiate dispute \nresolution procedures pursuant to Section 14 of this TO Tariff.  If the party seeking \nInterconnection requests termination of the negotiations, but within ninety (90) Calendar \nDays after the Participating TO tenders the draft Letter Agreement to the party seeking \nInterconnection, fails to request either the filing of the unexecuted Letter Agreement or \ninitiate dispute resolution procedures, it shall be deemed to have withdrawn its request \nfor a Letter Agreement and the Participating TO shall have no further obligation to enter \ninto a Letter Agreement, unless an extension is mutually agreed to by the parties.  The \nParticipating TO shall provide to the party seeking Interconnection a final Letter \nAgreement within fifteen (15) Business Days after the completion of the negotiation \nprocess. \nFollowing submission of the final Letter Agreement to the party seeking Interconnection, \nthe party shall either: (i) execute two originals of the tendered Letter Agreement and \nreturn them to the Participating TO; or (ii) request in writing that the Participating TO file \nwith FERC a Letter Agreement in unexecuted form.  As soon as practicable, but not \nlater than ten (10) Business Days after receiving either the two executed originals of the \ntendered Letter Agreement (if it does not conform with a FERC-approved Letter"},{"page":72,"startToken":19849,"endToken":20105,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nAgreement) or the request to file an unexecuted Letter Agreement, the Participating TO \nshall file the Letter Agreement with FERC, together with its explanation of any matters \nas to which the party seeking Interconnection and the Participating TO disagree and \nsupport for the costs that the Participating TO proposes to charge to the party seeking \nInterconnection under the Letter Agreement.  An unexecuted Letter Agreement should \ncontain terms and conditions deemed appropriate by the Participating TO for the \nInterconnection request.  \nIf the party seeking Interconnection executes the final Letter Agreement, the \nParticipating TO and the party seeking Interconnection shall perform their respective \nobligations in accordance with the terms of the Letter Agreement, subject to \nmodification by FERC.  Upon submission of an unexecuted Letter Agreement, the party \nseeking Interconnection and the Participating TO shall promptly comply with the \nunexecuted Letter Agreement, subject to modification by FERC.8.1.2  Costs Associated \nwith Interconnection. \nEach party requesting Interconnection shall pay the costs of planning, installing, owning, \noperating, and maintaining any Direct Assignment Facilities and, if applicable, any \nReliability Upgrades required to provide the requested Interconnection.  In addition, \nsuch party shall implement all existing operating procedures necessary to safely and \nreliably interconnect such party’s wholesale load to the facilities of the Participating TO \nand to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning \nCriteria, and shall bear all costs of implementing such operating procedures.  Any \nadditional costs associated with accommodating the Interconnection shall be allocated"},{"page":73,"startToken":20105,"endToken":20384,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nin accordance with the cost responsibility methodology set forth in the ISO Tariff for \ntransmission expansions or upgrades.   \n8.1.3  Interconnection Agreement. \nPursuant to Section 10.4, 10.7.1, or 10.9.1, a party requesting Interconnection shall \nrequest in writing that the Participating TO tender to such party an Interconnection \nAgreement that will be filed with FERC, or the Local Regulatory Authority, in the case of \na Local Publicly Owned Electric Utility.  The Interconnection Agreement will include, \nwithout limitation, cost responsibilities and payment provisions for any engineering, \nequipment, construction, ownership, operation and maintenance costs for any Direct \nAssignment Facilities, any Reliability Upgrades, and for any other mitigation measures.  \nFor an Interconnection request to remain a Completed Interconnection Application, the \nparty requesting the Interconnection shall execute the Interconnection Agreement and \nreturn it to the Participating TO within thirty (30) Business Days of receipt.  Alternatively, \nif an Eligible Customer requesting the Interconnection requests the Participating TO to \nfile an unexecuted Interconnection Agreement and commits to abide by the terms, \nconditions, and cost assignments determined to be just and reasonable under the ISO \nADR Procedures, including any determination by FERC or on appeal of a FERC \ndetermination in accordance with that process, the Participating TO shall promptly file \nan unexecuted Interconnection Agreement.  Provided, however, that if the ISO ADR \nProcedures concerns whether the requesting entity is an Eligible Customer, the \nParticipating TO shall not be obligated to file an unexecuted Interconnection Agreement \nor commence construction of the Interconnection facilities or incur other costs under the \nInterconnection Agreement until a final order determining the just and reasonable rates,"},{"page":74,"startToken":20384,"endToken":20659,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nterms, and conditions for such Interconnection Agreement has been issued by the \napplicable court or regulatory authority.  The Interconnection Agreement will set forth a \npayment schedule that enables the Participating TO to recover its costs.  If the applicant \nelects not to execute the Interconnection Agreement and does not request the \nParticipating TO to file an unexecuted Interconnection Agreement, its Completed \nInterconnection Application shall be deemed withdrawn, and the applicant shall \nreimburse to the Participating TO all costs reasonably incurred in processing the \napplication not covered by any System Impact Study Agreement or Facilities Study \nAgreement.   \n8.1.4 Due Diligence to Construct.  \nThe Participating TO shall use due diligence to construct, within a reasonable time, any \nDirect Assignment Facilities and any Reliability Upgrades that it is obligated to construct \npursuant to this TO Tariff.  The Participating TO’s obligation to build will be subject to:  \n1) its ability, after making a good faith effort, to obtain any necessary approvals and \nproperty rights under applicable federal, state, and local laws; 2) the presence of a cost \nrecovery mechanism with cost responsibility assigned in accordance with the ISO Tariff \nor applicable FERC precedent; and 3) a signed Interconnection Agreement or a signed \nExpedited Interconnection Agreement or, by mutual agreement of the parties, FERC \nacceptance for filing of an unexecuted Interconnection Agreement. \n8.1.5  Energization.   \nThe Participating TO shall not be obligated to energize, nor shall the wholesale load be \nentitled to have its interconnection to the ISO Controlled Grid energized, unless and \nuntil an Interconnection Agreement has been executed, or filed at FERC pursuant to"},{"page":75,"startToken":20659,"endToken":20912,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nSection 8.1.3, and becomes effective and such wholesale load has demonstrated to the \nISO's reasonable satisfaction that it has complied with all of the requirements of the ISO \nTariff and the requirements of this TO Tariff. \n8.1.6  Coordination with ISO on Interconnection Requests.   \nThe Participating TO shall coordinate with the ISO, pursuant to the provisions of the \nTCA, in developing Interconnection standards and guidelines for processing \nInterconnection requests under this TO Tariff. \n8.2  Participating TO Obligation to Construct Transmission Expansions or Facility \nUpgrades. \nThe Participating TO shall be obligated to:  (1) perform System Impact or Facility \nStudies where the Project Sponsor or the ISO agrees to pay the study cost and \nspecifies the project objectives to be achieved, and (2) build transmission additions and \nfacility upgrades where the Participating TO is obligated to construct or expand facilities \nin accordance with and subject to the limitations of Section 24 of the ISO Tariff and this \nTO Tariff. \n8.2.1  Obligation to Construct. \nA Participating TO shall not be obligated to construct or expand transmission facilities or \nsystem upgrades unless and until the conditions stated in Section 9.2.1 hereof have \nbeen satisfied.  \n8.2.2  Local Furnishing Participating TO Obligation to Construct.   \nA Local Furnishing Participating TO shall not be obligated to construct or expand \ntransmission facilities or system upgrades unless and until the conditions stated in \nSection 9.3.3 hereof have been satisfied."},{"page":76,"startToken":20912,"endToken":20982,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n8.3  Request for FERC Deference Regarding Need Determination.  \nIt is intended that FERC grant substantial deference to the factual determinations of the \nISO, (including the ISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated \nplanning processes as to the need for or construction of a facility, the need for full cost \nrecovery, and the allocation of costs."},{"page":77,"startToken":20982,"endToken":21263,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n9.  Expansion Process. \n9.1  Determination of Facilities.  \nA Participating TO shall perform a Facilities Study in accordance with this Section \nwhere (1) the Participating TO is obligated to construct or expand facilities in \naccordance with Section 24 of the ISO Tariff and this TO Tariff; (2) a Market Participant \nagrees to pay the costs of the Facilities Study and specifies the project objectives to be \nachieved in terms of increased capacity or reduced congestion; or (3) the Participating \nTO is required to perform a Facilities Study pursuant to the ISO Tariff. Eligible \nexpansions on behalf of Large Loads are not governed by this Section 9 but are instead \ngoverned by Appendix XV to the TO Tariff. \n9.1.1  Payment of Facilities Study’s Cost. \n9.1.1.1  Market Participant to Pay for Facilities Study.  \nWhere a Market Participant requests a Facilities Study and the need for the \ntransmission addition or upgrade has not yet been established in accordance with the \nprocedures established herein and the ISO Tariff, the Market Participant shall pay the \ncost of the Facilities Study. \n9.1.1.2  Project Sponsor or Project Proponent to Pay for Facilities Study.  \nWhere the facilities to be added or upgraded have been determined to be needed in \naccordance with the procedures established herein and the ISO Tariff, the Project \nSponsor, Project Proponent, or the ISO requesting the study shall pay the reasonable \ncost of the Facilities Study.  When the Participating TO is the Project Sponsor in \naccordance with the ISO Tariff, the costs of the Facilities Study shall be recovered \nthrough the Access Charges and transmission rates."},{"page":78,"startToken":21263,"endToken":21557,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n9.1.1.3  Principal Beneficiaries to Pay for Facilities Study. \nWhere the facilities to be added or upgraded have been determined to be needed and \nthe principal beneficiaries have been identified by the ISO or ISO ADR Procedures in \naccordance with the ISO Tariff, the Project Sponsor and the identified principal \nbeneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as \nmay be agreed, or, failing agreement, as determined in accordance with the ISO ADR \nProcedures. \n9.1.2  Payment Procedure.   \nWhere a Facilities Study is being conducted pursuant to this TO Tariff, the Participating \nTO shall, within thirty days of the receipt of all reasonably required information, tender to \nthe Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal \nbeneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, \ncontent, assumptions, and terms of reference for such study, the estimated time \nrequired to complete it, and such other provisions as the parties may reasonably require \nand pursuant to which such Market Participant, Project Sponsor, Project Proponent, the \nISO, or identified principal beneficiaries agree to reimburse the Participating TO the \nreasonable cost of performing the required Facilities Study.  If the Market Participant, \nProject Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the \ncase may be, agree to the terms of the Facilities Study Agreement, they shall execute \nthe Facilities Study Agreement and return it to the Participating TO within ten Business \nDays.  Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the \nISO, or identified principal beneficiaries, as the case may be, request the Participating \nTO to proceed with the Facilities Study and commit to abide by the terms, conditions,"},{"page":79,"startToken":21557,"endToken":21858,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nand cost assignments ultimately determined under the ISO ADR Procedures, including \nany determination by FERC or appeal of a FERC determination in accordance with that \nprocess, the Participating TO shall promptly proceed with the Facilities Study, and the \nparties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. \n9.1.3  Facilities Study Procedures.   \nUpon receipt of an executed Facilities Study Agreement or alternative request to \nproceed as provided for in Section 9.1.2, a copy of which has been provided to the ISO \nby the party requesting the Facilities Study, the Participating TO will use due diligence \nto complete the required Facilities Study within a sixty (60) day period.  If the \nParticipating TO is unable to complete the Facilities Study in the allotted time period, the \nParticipating TO shall notify the Market Participant and provide an estimate of the time \nneeded to reach a final determination along with an explanation of the reasons that \nadditional time is required to complete the study.  If additional time is required, the \nParticipating TO will use best efforts to complete the study within 10 months, provided \nadequate information is provided by all the parties. \n9.2  Obligation to Build. \n9.2.1  Due Diligence to Construct.   \nSubject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to \nconstruct, within a reasonable time, additions or upgrades to its transmission system \nthat it is obligated to construct pursuant to the ISO Tariff and this TO Tariff.  \nAlternatively, if a Market Participant requests the Participating TO to file an unexecuted \nParticipation Agreement and commits to abide by the terms, conditions, and cost \nassignments determined to be just and reasonable under the ISO ADR Procedures,"},{"page":80,"startToken":21858,"endToken":22164,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nincluding any determination by FERC or on appeal of a FERC determination in \naccordance with that process, the Participating TO shall promptly file an unexecuted \nParticipation Agreement.  Provided, however, that if the ISO ADR Procedures concerns \nwhether the requesting entity is an Eligible Customer, the Participating TO shall not be \nobligated to file an unexecuted Participation Agreement or commence construction of \nthe additions or upgrades or incur other costs under the Participation Agreement until a \nfinal order determining the just and reasonable rates, terms, and conditions for such \nParticipation Agreement has been issued by the applicable court or regulatory authority.  \nThe Participating TO’s obligation to build will be subject to:  1) its ability, after making a \ngood faith effort, to obtain the necessary approvals and property rights under applicable \nfederal, state, and local laws; 2) the presence of a cost recovery mechanism with cost \nresponsibility assigned in accordance with the ISO Tariff; and 3) a signed Participation \nAgreement.  The Participating TO will not construct or expand its existing or planned \ntransmission system, if doing so would impair system reliability as determined through \nsystems analysis based on the Applicable Reliability Criteria. \n9.2.2  Delay in Construction or Expansion.   \nIf any event occurs that will materially affect the time for completion of new facilities, or \nthe ability to complete them, the Participating TO shall promptly notify:  (1) the Project \nSponsor with regard to facilities determined to be needed; (2) the Parties to the \nParticipation Agreement with regard to facilities determined to be needed pursuant to \nthe ISO Tariff where principal beneficiaries were identified; and (3) the ISO.  In such \ncircumstances, the Participating TO shall, within thirty days of notifying such Project \nSponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a"},{"page":81,"startToken":22164,"endToken":22479,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ntechnical meeting with such Project Sponsor, Parties to the Participation Agreement, \nand the ISO to discuss the circumstances which have arisen and evaluate any options \navailable.  The Participating TO also shall make available to such Project Sponsor, \nParties to the Participation Agreement, and the ISO, as the case may be, studies and \nwork papers related to the cause and extent of the delay and the Participating TO’s \nability to complete the new facilities, including all information that is in the possession of \nthe Participating TO that is reasonably needed to evaluate the alternatives. \n9.2.2.1  Alternatives to the Original Facility Additions.   \nIf the review process of Section 9.2.2 determines that one or more alternatives exist to \nthe originally planned construction project, the Participating TO shall present such \nalternatives for consideration to the Project Sponsor, Parties to the Participation \nAgreement, and the ISO, as the case may be.  If upon review of any alternatives, such \nProject Sponsor, the ISO, or Parties to the Participation Agreement wish to evaluate or \nto proceed with one of the alternative additions or upgrades, such Project Sponsor, the \nISO, or Parties to the Participation Agreement may request that the Participating TO \nprepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO \nTariff.  In the event the Participating TO concludes that no reasonable alternative exists \nto the originally planned addition or upgrade and the Project Sponsor or Parties to the \nParticipation Agreement or the ISO disagree, the dispute shall be resolved pursuant to \nthe ISO ADR Procedure. \n9.2.2.2  Refund Obligation for Unfinished Facility Additions. \nIf the Participating TO and the Project Sponsor, the ISO, or Parties to the Participation \nAgreement, as the case may be, mutually agree that no other reasonable alternatives"},{"page":82,"startToken":22479,"endToken":22747,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nexist, the obligation to construct the requested additions or upgrades shall terminate \nand any deposit not yet applied toward the expended project costs shall be returned \nwith interest pursuant to FERC Regulation 35.19(a)(2)(iii).  However, the Project \nSponsor and any identified principal beneficiaries, as the case may be, shall be \nresponsible for all costs prudently incurred by the Participating TO through the time the \nconstruction was suspended.   \n9.3  Provisions Relating To Transmission Construction On the Systems Of Other \nTOs. \n9.3.1  Responsibility for Third Party Additions.  \nA Participating TO shall not be responsible for making arrangements for any \nengineering, permitting, and construction of transmission or distribution facilities on the \nsystem(s) of any other entity or for obtaining any regulatory approval for such facilities.  \nThe Participating TO will undertake reasonable efforts through the coordinated planning \nprocess to assist in making such arrangements, including, without limitation, providing \nany information or data required by such other electric system pursuant to Good Utility \nPractice. \n9.3.2  Coordination of Third-Party System Additions.  \nWhere transmission additions or upgrades being built pursuant to the ISO Tariff require \nadditions or upgrades on other systems, to the extent consistent with Section 9.3.3 of \nthis TO Tariff, the Participating TO shall coordinate construction on its own system with \nthe construction required by others.  The Participating TO, after consultation with the \nISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may \nbe, may defer construction if the new transmission facilities on another system cannot"},{"page":83,"startToken":22747,"endToken":23047,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nbe completed in a timely manner.  The Participating TO shall notify such Project \nSponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for \nany decision to defer construction and the specific problems which must be resolved \nbefore it will initiate or resume construction of the new facilities.  Within forty Business \nDays of receiving written notification by the Participating TO of its intent to defer \nconstruction pursuant to this section, such Project Sponsor, Parties to the Participation \nAgreement, or the ISO may challenge the decision in accordance with the ISO ADR \nProcedure. \n9.3.3  Expansion by “Local Furnishing Participating TOs”.   \nNotwithstanding any other provision of this TO Tariff, prior to requesting that a Local \nFurnishing Participating TO construct or expand facilities, the ISO or Project Sponsor \nshall tender (or cause to be tendered) an application under Section 211 of the FPA \nrequesting FERC to issue an order directing the Local Furnishing Participating TO to \nconstruct or expand facilities as necessary to provide transmission service as \ndetermined pursuant to the ISO Tariff.  Such Local Furnishing Participating TO shall \nthereafter, within ten Business Days of receiving a copy of the Section 211 application, \nwaive its right to a request for service under Section 213(a) of the FPA and to the \nissuance of a proposed order under Section 212(c) of the FPA.  Upon receipt of a final \norder from FERC under Section 211 of the FPA that is no longer subject to rehearing or \nappeal, such Local Furnishing Participating TO shall construct or expand facilities to \ncomply with that FERC order and shall transfer to the ISO Operational Control over the \nLocal Furnishing Participating TO’s expanded transmission facilities in accordance with \nthe ISO Tariff."},{"page":84,"startToken":23047,"endToken":23289,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.  Interconnection Process. \n10.1  Applicability.  \nAll requests for Interconnection of wholesale load directly to the ISO Controlled Grid from \nparties eligible to request such Interconnection consistent with Section 210(a) of the FPA \nshall be processed pursuant to the provisions of this Section 10, except requests for \ninterconnection on behalf of Large Loads to be located in the ISO BAA shall be subject \nto the procedures in Appendix XV of the TO Tariff.  All requests for Interconnection of \nwholesale generation directly to the ISO Controlled Grid shall be processed pursuant to \nthe provisions of the ISO Tariff, and if applicable, Appendix VII of the TO Tariff. Requests \nfor interconnection on behalf of Large Loads by retail transmission customers of \nParticipating TO shall be subject to the procedures in Appendix XV of the TO Tariff and \nthe Local Regulatory Authority, as applicable. \n10.2  Applications.   \nA party requesting Interconnection shall submit a written Interconnection Application \nwhich provides the information required in Section 10.3 to the Participating TO and shall \nsend a copy of the application to the ISO.  The Participating TO shall time-stamp the \napplication to establish study priority. \n10.3  Interconnection Application.   \nAn Interconnection Application shall provide all of the information listed in 18 CFR § \n2.20, including, but not limited to, the following: \n(i)  The identity, address, telephone number, and facsimile number of the party \nrequesting Interconnection;"},{"page":85,"startToken":23289,"endToken":23531,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n(ii)  The Interconnection point(s) to the ISO Controlled Grid contemplated by the \napplicant; \n(iii)  The resultant (or new) maximum amount of Interconnection capacity; \n(iv)  The proposed date for energizing the Interconnection and the term of the \nInterconnection service; \n(v)  Such other information as the Participating TO reasonably requires to process the \napplication. \nIn addition to the information specified above, the following information may also be \nprovided in order to properly evaluate system conditions: \n(vi)  The electrical location of the source of the power (if known) to be transmitted \npursuant to the applicant’s request for Interconnection.  If the source of the power is not \nknown, a system purchase will be assumed. \nWithin ten (10) Business Days after receipt of an Interconnection Application, the \nParticipating TO shall determine whether the application is complete (“Completed \nInterconnection Application”).  Wherever possible, the Participating TO will attempt to \nremedy deficiencies in the Interconnection Application through informal communications \nwith the applicant.  If such efforts are unsuccessful, the Participating TO shall return the \nInterconnection Application to the applicant.  The Participating TO will treat the \ninformation provided in the Interconnection Application, including the applicant’s identity, \nas confidential at the request of the applicant except to the extent that disclosure of this \ninformation is required by this TO Tariff, by regulatory or judicial order, for reliability \npurposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission"},{"page":86,"startToken":23531,"endToken":23812,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ninformation sharing agreements.  The Participating TO shall treat this information \nconsistent with the standards of conduct contained in Part 37 of FERC’s regulations. \n10.4  Review of Completed Interconnection Application.   \nAfter receiving a Completed Interconnection Application, the Participating TO will \ndetermine on a non-discriminatory basis whether a System Impact Study is required.  \nWhenever the Participating TO determines that a System Impact Study is not required \nand that neither Reliability Upgrades nor changes in existing operating procedures are \nrequired, the Participating TO shall notify the applicant within fifteen (15) Business Days \nof the Completed Application Date.  If the Interconnection can be accommodated \nwithout any Direct Assignment Facilities, then within thirty (30) Business Days of such \nnotice from the Participating TO, the applicant shall request the Participating TO to \ntender to the applicant an Interconnection Agreement within thirty (30) Business Days of \nsuch request.  The Participating TO shall tender to the applicant an Interconnection \nAgreement as provided in Section 8.1.3.  If the Participating TO determines, upon the \nreview of the Completed Interconnection Application, that Direct Assignment Facilities \nare required, the Participating TO shall tender to the applicant a Facilities Study \nAgreement within twenty (20) Business Days of the Completed Application Date and \ncontinue the interconnection process pursuant to Section 10.8.   \n10.5  Notice of Need for System Impact Study.   \nIf the Participating TO determines that a System Impact Study is necessary to \naccommodate the requested Interconnection, the Participating TO shall so inform the \napplicant, as soon as practicable.  In such cases, the Participating TO shall within \ntwenty (20) Business Days of receipt of a Completed Interconnection Application, tender"},{"page":87,"startToken":23812,"endToken":24102,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \na System Impact Study Agreement that defines the scope, content, assumptions and \nterms of reference for such study to be completed by the Participating TO; the \nestimated time required to complete it; and such other provisions as the parties may \nreasonably require, and pursuant to which the applicant shall agree to reimburse the \nParticipating TO for the reasonable actual costs of performing the required System \nImpact Study.  A description of the Participating TO’s transmission assessment \npractices for completing a System Impact Study is provided in the Participating TO’s \nFERC Form 715.  For an Interconnection request to remain a Completed \nInterconnection Application, the applicant shall execute the System Impact Study \nAgreement and return it to the Participating TO within ten (10) Business Days together \nwith payment for the reasonable estimated cost of performing the System Impact Study.  \nAlternatively, if the applicant requests the Participating TO to proceed with the System \nImpact Study and commits to abide by the terms, conditions, and cost assignments \nultimately determined under the ISO ADR Procedures, including any determination by \nFERC or appeal of a FERC determination in accordance with that process, the \nParticipating TO shall promptly proceed with the System Impact Study provided that \nsuch request is accompanied by payment for the reasonable estimated cost of the \nSystem Impact Study, and the parties shall submit the disputed terms for resolution \nunder the ISO’s ADR Procedures.  If the applicant elects not to execute a System \nImpact Study Agreement, and does not request that the Participating TO proceed with \nthe System Impact Study, its application shall be deemed withdrawn, and the applicant \nshall reimburse to the Participating TO all costs reasonably incurred in processing the \napplication."},{"page":88,"startToken":24102,"endToken":24365,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.6  System Impact Study Cost Reimbursement and Agreement \n10.6.1  Cost Reimbursement. \nThe System Impact Study Agreement shall clearly specify the charge, based on the \nParticipating TO’s estimate of the cost and time for completion of the System Impact \nStudy.  The charge shall not exceed the reasonable actual cost of the study.  In \nperforming the System Impact Study, the Participating TO shall rely, to the extent \nreasonably practicable, on existing transmission planning studies.  The applicant will not \nbe assessed a charge for such existing studies; however, the applicant will be \nresponsible for the reasonable charges associated with any modifications to existing \nplanning studies that are reasonably necessary to evaluate the impact of the applicant’s \nrequest. \n10.6.2  Multiple Parties.   \nIf multiple parties request Interconnection at the same location, the Participating TO \nmay conduct a single System Impact Study.  The costs of that study shall be pro-rated \namong the parties requesting Interconnection. \n10.7  System Impact Study Procedures.  \nUpon receipt of an executed System Impact Study Agreement or initiation of the ISO \nADR Procedures and receipt of payment for estimated study costs, the Participating TO \nwill use due diligence to complete the required System Impact Study within a sixty (60) \ncalendar day period.  The System Impact Study will identify whether any Direct \nAssignment Facilities or Reliability Upgrades are necessary, as well as whether any \ntransmission additions or upgrades are necessary to serve a wholesale load.  The \nSystem Impact Study will also identify any adverse impact on Encumbrances existing as"},{"page":89,"startToken":24365,"endToken":24646,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nof the applicant’s Completed Application Date.  In the event that the Participating TO is \nunable to complete the required System Impact Study within such time period, it shall so \nnotify the applicant, in writing, and provide an estimated completion date along with an \nexplanation of the reasons why additional time is required to complete the required \nstudies.  A copy of the completed System Impact Study and related work papers shall \nbe made available to the applicant and the ISO.  The Participating TO will use the same \ndue diligence in completing the System Impact Study for others as it uses when \ncompleting studies for its affiliated UDC load.  The Participating TO shall notify the \napplicant immediately upon completion of the System Impact Study. \n10.7.1  Procedures Upon Completion of System Impact Study.   \nWithin fifteen (15) Business Days of completion of the System Impact Study, the \nParticipating TO shall notify the applicant whether the transmission system will be \nadequate to accommodate all of a request for Interconnection.  If no costs are likely to \nbe incurred for any Direct Assignment Facilities, any Reliability Upgrades, or \nimplementing any operating procedures, then within thirty (30) Business Days of receipt \nof the completed System Impact Study, the applicant shall request the Participating TO \nto tender an Interconnection Agreement within thirty (30) Business Days of such \nrequest.  The Participating TO shall tender to the applicant an Interconnection \nAgreement as provided in Section 8.1.3.  If costs are likely to be incurred to \naccommodate a request for Interconnection, the Participating TO shall tender to the \napplicant a Facilities Study Agreement pursuant to Section 10.8."},{"page":90,"startToken":24646,"endToken":24946,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.8  Notice of Need for Facilities Study.   \nIf a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid \nare needed to satisfy an applicant’s request for Interconnection, the Participating TO \nshall, within fifteen (15) Business Days of the completion date of the System Impact \nStudy tender to the applicant a Facilities Study Agreement that defines the scope, \ncontent, assumptions and terms of reference for such study; the estimated time required \nto complete the required study; and such other provisions as the parties may \nreasonably require, and pursuant to which the applicant agrees to reimburse the \nParticipating TO for the reasonable actual costs of performing the required Facilities \nStudy.   For an Interconnection request to remain a Completed Interconnection \nApplication, the applicant shall execute the Facilities Study Agreement and return it to \nthe Participating TO within ten (10) Business Days together with payment for the \nreasonable estimated cost of performing the Facilities Study.  Alternatively, if the \napplicant requests the Participating TO to proceed with the Facilities Study and commits \nto abide by the terms, conditions, and cost assignments ultimately determined under the \nISO ADR Procedures, including any determination by FERC or appeal of a FERC \ndetermination in accordance with that process, the Participating TO shall promptly \nproceed with the Facilities Study provided that such request is accompanied by \npayment for the reasonable estimated cost of the Facilities Study, and the parties shall \nsubmit the disputed terms for resolution under the ISO ADR Procedures.  If the \napplicant elects not to execute a Facilities Study Agreement and does not request that \nthe Participating TO proceed with the Facilities Study, its application shall be deemed \nwithdrawn and the applicant shall reimburse to the Participating TO all costs reasonably"},{"page":91,"startToken":24946,"endToken":25217,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nincurred in processing the application not covered by the System Impact Study \nAgreement. \n10.9  Facilities Study Procedures.  \nUpon receipt of an executed Facilities Study Agreement or initiation of the ISO ADR \nProcedures and receipt of payment for the estimated study costs, the Participating TO \nwill use due diligence to complete the required Facilities Study within a sixty (60) \ncalendar day period.  In the event that the Participating TO is unable to complete the \nrequired Facilities Study within such time period, it shall so notify the applicant, in \nwriting, and provide an estimated completion date along with an explanation of the \nreasons why additional time is required to complete the required studies.  A copy of the \ncompleted Facilities Study shall be made available to the applicant.   \n10.9.1  Execution of Interconnection Agreement.  \nWithin thirty (30) Business Days of receipt of the completed Facilities Study, the \napplicant shall request the Participating TO to tender an Interconnection Agreement \nwithin thirty (30) Business Days of such request.  The Participating TO shall tender to \nthe applicant an Interconnection Agreement as provided in Section 8.1.3.  \n10.10  Partial Interim Service.   \nIf the Participating TO determines that there will not be adequate transmission capability \nto satisfy the full amount requested in a Completed Interconnection Application, the \nParticipating TO nonetheless shall be obligated to offer and provide the portion of the \nrequested Interconnection that can be accommodated without any additional Direct \nAssignment Facilities or Reliability Upgrades.  However, the Participating TO shall not \nbe obligated to provide the incremental amount of requested Interconnection that"},{"page":92,"startToken":25217,"endToken":25492,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nrequires such additional facilities or upgrades until such facilities or upgrades have been \nplaced in service. \n10.11  Expedited Interconnection Procedures.   \nIn lieu of the procedures set forth above, the applicant shall have the option to expedite \nthe processing of its Completed Interconnection Application.  In order to exercise this \noption, the applicant shall submit in writing a Request for Expedited Interconnection \nProcedures to the Participating TO within ten (10) Business Days after receiving a copy \nof the System Impact Study for the proposed Interconnection.  Within ten (10) Business \nDays after receiving a Request for Expedited Procedures, the Participating TO shall \ntender an Expedited Interconnection Agreement that requires the applicant to \ncompensate the Participating TO for all costs reasonably incurred pursuant to the terms \nof this TO Tariff for processing the Completed Interconnection Application and providing \nthe requested Interconnection.  While the Participating TO agrees to provide the \napplicant with its best estimate of the costs of any needed Direct Assignment Facilities \nand, if applicable, Reliability Upgrades and other charges that may be incurred, unless \notherwise agreed by the parties, such estimate shall not be binding and the applicant \nmust agree in writing to compensate the Participating TO for all actual Interconnection \ncosts reasonably incurred pursuant to the provisions of this TO Tariff.  The applicant \nshall execute and return such Expedited Interconnection Agreement within ten (10) \nBusiness Days of its receipt or the applicant's request for Interconnection will cease to \nbe a Completed Interconnection Application and will be deemed terminated and \nwithdrawn.  In that event, the applicant shall reimburse the Participating TO for all costs"},{"page":93,"startToken":25492,"endToken":25521,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nreasonably incurred in processing the application not covered by the terms of the \nSystem Impact Study Agreement."},{"page":94,"startToken":25521,"endToken":25719,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n13.  Creditworthiness. \n13.1  UDCs, MSSs, and Scheduling Coordinators Using the Participating TO's Low \nVoltage Transmission Facilities.  \nFor the purpose of determining the ability of a UDC, MSS, and Scheduling Coordinator \nto meet its obligations related to service using the Participating TO's Low Voltage \nTransmission Facilities hereunder, the Participating TO may require reasonable credit \nreview procedures for the UDC, MSS, or Scheduling Coordinator.  This review shall be \nmade in accordance with standard commercial practices.  In addition, the Participating \nTO may require the UDC, MSS, or Scheduling Coordinator to provide and maintain in \neffect during the term of the service, an unconditional and irrevocable letter of credit as \nsecurity to meet its responsibilities and obligations under this TO Tariff, or an alternative \nform of security proposed by the UDC, MSS, or Scheduling Coordinator and acceptable \nto the Participating TO, and consistent with commercial practices established by the \nUniform Commercial Code, that protect the Participating TO against the risk of non-\npayment. \n13.2  End-Users.   \nCreditworthiness rules applicable to End-Users shall be pursuant to the then-current \nrules of the applicable Local Regulatory Authority and, as applicable, Appendix XV."},{"page":95,"startToken":25719,"endToken":25754,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \nAPPENDIX XV \n \n \n \nLARGE LOAD  \n \nINTERCONNECTION PROCEDURES (LLIP) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n                Tariff Record Proposed Effective Date: 02/16/27 \n \n \n    \n \n \n             Version Number: 0.0.0  \nOption Code:  A"},{"page":96,"startToken":25754,"endToken":26021,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nTABLE OF CONTENTS  \n \n \n           \nSection 1.  Objectives and Applicability .....................................................  \n1.1 Objectives……………………………………………………………... \n \n1.2 Applicability……………………………………………………………. \n \nSection 2. Definitions ..................................................................................  \n \nSection 3. General Provisions Applicable to All Interconnection Requests  \n3.1 Interconnection Requests  \n3.2 Transmission Interconnection Service ....................................  \n3.2.1 \nThe Product ..................................................................  \n3.2.2 \nNo Applicability to Transmission Service ..................   \n3.2.3 \nRoles and Responsibilities..........................................  \n3.3 Comparability.............................................................................  \n3.4 Base Case Data ..........................................................................  \n3.5 Coordination with Affected Systems .......................................  \n3.6  Capacity of the Large Load.......................................................  \n3.7  Proposed Service Commencement Date .................................  \n \n3.7.1 \nInterconnection Request .............................................  \n \n3.7.2 \n \nAfter Start of the Large Load Interconnection Study  ....................  \n3.8   Queue Position \n3.9 Withdrawal .................................................................................  \n3.10 Withdrawal Penalty \n        3.10.1  Calculation of the Withdrawal Penalty \n3.11 Standards for Co-located Inverter Based Generating Facilities \n \n \nSection 4. Large Load Study Process ........................................................  \n4.1 Timing for Submitting Interconnection Requests ..................   \n4.2 Processing of Interconnection Request ..................................  \n4.2.1 \nInitiating an Interconnection Request ........................  \n4.2.1.1 Use of Interconnection Study Deposit .....................  \n4.3 Validation of Interconnection Request ....................................  \n4.3.1 \nAcknowledgment of Interconnection Request ..........  \n4.3.2 \nDeficiencies in Interconnection Request ...................  \n4.4   Potential Deferral of the Interconnection Studies \n4.5 Scoping Meeting ........................................................................  \n4.6 Interconnection Studies ............................................................  \n4.6.1 \nLarge Load Interconnection Study .............................  \n4.6.1.1  Scope of the Large Load Study ................................  \n4.6.1.2  Timing of the Large Load Interconnection Study Results \n \n4.6.1.3  Large Load Interconnection Study Report Meeting  \n4.6.1.4  Increase in the Commercial Readiness Deposit…… \n4.6.1.5  Restudy…………………………………………………… \n4.6.1.6  Modifications .............................................................."},{"page":97,"startToken":26021,"endToken":26263,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n4.6.2     Optional Flexible Interim Load Interconnection (FILI) Study \n4.6.2.1   FILI Agreement with Participating TO and ISO…… \n4.6.3     Additional Studies ........................................................  \n4.6.4     Financing of Participating TO’s Interconnection Facilities, \nDistribution Upgrades, and Large Load Network Upgrades \n4.7 Interconnection Financial Security ..........................................  \n4.7.1 \nTypes of Interconnection Financial Security .............  \n \n \nSection 5. Transmission Security and Reliability Agreement .................  \n5.1 Tender  .......................................................................................   \n5.2   Negotiation .................................................................................  \n5.3 Execution and Filing  \n5.4   Commencement of Interconnection Activities ........................  \n5.5 Large Load Interconnection Customer To Meet Requirements of the \n \nParticipating TO’s Interconnection Handbook ........................  \n \nSection 6. Construction of Participating TO’s Interconnection Facilities, \n \nDistribution Upgrades, and Large Load Network Upgrades ..  \n6.1 Schedule ....................................................................................   \n6.2 Construction Sequencing .........................................................  \n6.2.1 \nGeneral ..........................................................................  \n6.2.2 \nAdvancing Construction of Distribution Upgrades and \nLarge Load Network Upgrades that are Part of an Expansion Plan of \nthe Participating TO ..................................................................  \n6.3 Special Provisions for Affected Systems ................................  \n \nSection 7. Miscellaneous ............................................................................  \n7.1 Confidentiality ............................................................................  \n7.1.1 \nScope ............................................................................  \n7.1.2 \nRelease of Confidential Information ...........................  \n7.1.3 \nRights ............................................................................  \n7.1.4 \nNo Warranties ...............................................................  \n7.1.5 \nStandard of Care ..........................................................  \n7.1.6 \nOrder of Disclosure ......................................................  \n7.1.7 \nRemedies ......................................................................  \n7.1.8 \nDisclosure to FERC, its Staff, or a State ....................  \n7.2 Disputes  ....................................................................................    \n7.2.1 \nSubmission ...................................................................  \n \nAttachment 1 – Interconnection Request Form \n \nAttachment 2 – Large Load Study Process Agreement  \n \nAttachment 3 – Transmission Security and Reliability Agreement"},{"page":98,"startToken":26263,"endToken":26611,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nAttachment 4 – Operating Conditions Agreement for Flexible Interim Load \nInterconnection (FILI)  \n \nLARGE LOAD INTERCONNECTION PROCEDURES (LLIP) \n \n \nSection 1. Objectives and Applicability  \n1.1 Objectives \n \nThe objective of this LLIP is to implement requirements for Large Load interconnections \nto the Participating TO’s Transmission System pursuant to the TO Tariff.  In addition to \nall applicable requirements under the Local Regulatory Authority, the requirements of \nthe LLIP also apply to a Large Load that will be a retail transmission customer of the \nParticipating TO.   \n \n1.2 Applicability  \n \nThe LLIP is applicable to a Large Load Interconnection Customer that is either (1) \nproposing to interconnect a Large Load to Participating TO’s transmission system; (2) \nseeking to increase the capacity of an existing Large Load processed under the LLIP; or \n(3) with respect to an existing Participating TO transmission-interconnected load not \nprocessed under the LLIP, is seeking an increase of 50 MW or greater.  This LLIP \napplies to all Large Loads seeking interconnection to Participating TO’s transmission \nsystem after the effective date of this Appendix XV to the TO Tariff.  \n \n \nSection 2. Definitions  \n \nTerms used in this LLIP with initial capitalization shall have the meanings set forth \nbelow.  The singular of any definition shall include the plural and the plural shall include \nthe singular.  If a term with initial capitalization used herein is not defined, such term \nshall have the meanings ascribed to such term in Section 3 of the TO Tariff.   \n \n \nAffected System shall mean an electric system other than the Participating TO’s \nTransmission System and Distribution System that may be affected by the proposed \ninterconnection.   \n \n \nAffected System Operator shall mean the entity that operates an Affected System.   \n \n \n \n \nApplicable Laws and Regulations shall mean all duly promulgated applicable \nfederal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, \ndirectives, or judicial or administrative orders, permits and other duly authorized actions \nof any Governmental Authority \n \n  \nBase Case shall mean data including, but not limited to, base power flow, short \ncircuit and stability data bases, underlying load, generation, and transmission facility"},{"page":99,"startToken":26611,"endToken":27007,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nassumptions, contingency lists, including relevant remedial action schemes, and \ntransmission diagrams used to perform the Interconnection Studies.  The Base Case \nmay include Critical Energy Infrastructure Information (as that term is defined by FERC).  \nThe Base Case may include transmission facilities as approved by the Participating TO \nor ISO, as applicable, Large Load Network Upgrades that are included in a signed \ninterconnection agreement, Distribution Upgrades, Large Load Network Upgrades, \nLarge Loads and any co-located generation, and load forecast. The Base Case may \nalso include generation facilities that (i) are directly interconnected to the Distribution \nSystem or ISO Controlled Grid; (ii) are interconnected to Affected Systems and may \nhave an impact on the Interconnection Request; (iii) have a pending request to \ninterconnect to the Distribution System or an Affected System; or (iv) are not \ninterconnected to the Distribution System or ISO Controlled Grid, but are subject to the \nterms and conditions of a fully executed interconnection agreement (or its equivalent \npredecessor agreement) or for which an unexecuted interconnection agreement (or its \nequivalent predecessor agreement) has been requested to be filed with FERC.   \n \n \nBusiness Day shall mean Monday through Friday, excluding Federal Holidays. \n \n \nCalendar Day shall mean any day including Saturday, Sunday or a Federal \nHoliday.   \n \nCommercial Readiness Deposit shall mean a deposit paid as set forth in LLIP \nSections 4.2.1 and 4.6.1.4. \n \n \nConfidential Information shall mean any confidential, proprietary or trade secret \ninformation of a plan, specification, pattern, procedure, design, device, list, concept, \npolicy or compilation relating to the present or planned business of a Party, which is \ndesignated as confidential by the Party supplying the information, whether conveyed \norally, electronically, in writing, through inspection, or otherwise. \n \n \nDispute Resolution shall mean the applicable procedure for resolution of a dispute \nbetween the Parties as described in TO Tariff Section 14.  \n \n \nFlexible Interim Load Interconnection (FILI) shall mean curtailable, interim \ntransmission interconnection service for a Large Load provided by the ISO and \nParticipating TO, enabling the Large Load to interconnect prior to completion of the \nLarge Load’s Large Load Network Upgrades, Distribution Upgrades, or Participating \nTO’s Interconnection Facilities. \n \n \nInterconnection Financial Security shall mean any of the financial instruments \nlisted in LLIP Section 4.7.1 provided by the Large Load Interconnection Customer to \ncomply with its obligations under the LLIP or the TSRA."},{"page":100,"startToken":27007,"endToken":27407,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nInterconnection Handbook shall mean a handbook, developed by the \nParticipating TO and posted on the Participating TO’s website or otherwise made \navailable by the Participating TO, describing the technical and operational requirements \nfor wholesale generators and loads connected to the Participating TO’s Transmission \nSystem, as such handbook may be modified or superseded from time to time.  \nParticipating TO’s standards contained in the Interconnection Handbook shall be \ndeemed consistent with Good Utility Practice and Applicable Reliability Standards.  In \nthe event of a conflict between the terms of the LLIP and the terms of the Participating \nTO’s Interconnection Handbook, the terms in the LLIP shall govern. \n \n \nInterconnection Request shall mean an Interconnection Application in the form of \nAttachment 1 to Appendix XV to the TO Tariff, to interconnect a new Large Load, or to \nincrease the capacity of, or make a Material Modification to the operating characteristics \nof, an existing Large Load that is interconnected with the Participating TO’s \nTransmission System. \n \n \nInterconnection Study shall mean any of the following studies: the Large Load \nInterconnection Study, the FILI Study, restudies, and any additional studies performed \npursuant to LLIP Section 4.6.3. \n \n \nInterconnection Study Deposit shall mean the cash deposit provided to the \nParticipating TO under LLIP Section 4.2.1 as a requirement of a valid Interconnection \nRequest to be used to offset the cost of the Interconnection Studies. \n \nLarge Load Capacity shall mean the maximum capacity of the Large Load at the \nPoint of Interconnection.  \n \nLarge Load Interconnection Customer shall mean an Eligible Customer that \nproposes to interconnect and sell retail transmission service to a Large Load except for \nwhen the Large Load Owner seeking to interconnect the Large Load with the \nParticipating TO’s Transmission System will be a retail transmission customer of the \nParticipating TO, in which case the Large Load Owner shall be the Large Load \nInterconnection Customer. \n \nLarge Load Interconnection Customer Interconnection Facilities shall mean all \nfacilities and equipment owned, controlled, or operated by the Large Load \nInterconnection Customer or the Large Load Owner up to the Point of Change of \nOwnership as identified in Appendix A to the TSRA, including any modifications, \nadditions or upgrades to such facilities and equipment.   \n \nLarge Load Interconnection Procedures (LLIP) shall mean the interconnection \nprocedures applicable to an Interconnection Request set forth in this Appendix XV to \nthe TO Tariff."},{"page":101,"startToken":27407,"endToken":27880,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nLarge Load Interconnection Study shall mean an engineering study conducted by \nthe Participating TO for a Large Load Interconnection Customer under the LLIP that \nevaluates the impact of the proposed interconnection on the safety and reliability of \nParticipating TO’s Transmission System and Distribution System and, if applicable, an \nAffected System. The Large Load Interconnection Study will also determine a list of \nfacilities (including Participating TO’s Interconnection Facilities, Distribution Upgrades, \nand Large Load Network Upgrades), the cost of those facilities, and the time required to \ninterconnect the Large Load Facility with the Participating TO’s Transmission System. \nWhen the Large Load will be a retail transmission customer of the Participating TO, the \nLarge Load Interconnection Study will only evaluate the impact of the proposed \ninterconnection on the safety and reliability of Participating TO’s Transmission System \nand, if applicable, an Affected System, and will not evaluate any Distribution Upgrades, \nwhich are governed by the Local Regulatory Authority. The scope of the study is defined \nin LLIP Section 4.6.1.1. \n \nLarge Load Owner shall mean the legal entity that owns, controls, and operates \nthe Large Load. \n \nLarge Load Study Process Agreement shall mean the agreement entered into by \nthe Large Load Interconnection Customer and the Participating TO which sets forth the \nParties’ agreement to perform Interconnection Studies under the LLIP, a pro forma \nversion of which is set forth in Attachment 2 to the LLIP. \n \n \nMaterial Modification shall mean those modifications that have a material impact \non the cost or timing of any Interconnection Request, or any other valid interconnection \nrequest to the Participating TO or the ISO, with a equal or later Queue Position date.  \n \n \nLarge Load Network Upgrades shall mean the additions, modifications, and \nupgrades to the ISO Controlled Grid at or beyond the Point of Interconnection \nnecessary to serve one or more Large Loads safely and reliably that are identified \nthrough the Large Load Interconnection Study and sent to the ISO for concurrence \npursuant to ISO Tariff Section 25.7. Large Load Network Upgrades do not include \nDistribution Upgrades or Participating TO’s Interconnection Facilities.  \n \nParticipating TO’s Interconnection Facilities shall mean all facilities and \nequipment owned, controlled, or operated by the Participating TO from the Point of \nChange of Ownership to the Point of Interconnection as identified in Appendix A to the \nTSRA, including any modifications, additions or upgrades to such facilities and \nequipment.  Participating TO’s Interconnection Facilities are transmission facilities but \nare not controlled by the ISO.  Participating TO’s Interconnection Facilities are sole use \nfacilities and shall not include Distribution Upgrades or Large Load Network Upgrades.  \n \nParticipating TO’s Transmission System shall mean the facilities owned and \noperated by the Participating TO and that have been placed under the ISO’s \nOperational Control, which facilities form part of the ISO Controlled Grid."},{"page":102,"startToken":27880,"endToken":28320,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nPoint of Change of Ownership shall mean the point, as set forth in Appendix A to \nthe TSRA, where the Large Load Interconnection Customer's interconnection facilities \nconnect to the Participating TO’s Interconnection Facilities. \n \n \nPoint of Interconnection shall mean the point, as set forth in Appendix A to the \nTSRA, where the Participating TO’s Interconnection Facilities connect to the \nParticipating TO’s Transmission System. \n \n  \nQueue Position shall mean the order of a valid Interconnection Request, relative to \nall other pending valid Interconnection Requests, established pursuant to LLIP Section \n3.10. \n \n \nReasonable Efforts shall mean, with respect to an action required to be attempted \nor taken by a Party under the LLIP or the TSRA, efforts that are timely and consistent \nwith Good Utility Practice and are otherwise substantially equivalent to those a Party \nwould use to protect its own interests. \n \nReport Meeting shall mean the meeting among the Participating TO, the Large \nLoad Interconnection Customer, and if applicable, the ISO and other Affected System \nOperators to discuss the results of the Interconnection Studies as set forth in the LLIP.  \n \nScoping Meeting shall mean the meeting between representatives of the Large \nLoad Interconnection Customer and Participating TO, and if applicable, the ISO, \nconducted for the purpose of discussing alternative interconnection options, to \nexchange information including any transmission data and earlier study evaluations that \nwould be reasonably expected to impact such interconnection options, to analyze such \ninformation, and to determine the potential feasible Points of Interconnection.  \n \nService Commencement Date shall mean the date the Large Load is initially \noperated in parallel with the Participating TO’s Transmission System and transmission \ninterconnection service is provided to the Large Load Interconnection Customer \npursuant to the terms of an executed TSRA.  \n \nSite Control shall mean the exclusive land right to develop, construct, operate, and \nmaintain the Large Load over the term of expected operation of the Large Load. Site \nControl may be demonstrated by documentation establishing: (1) ownership of, a \nleasehold interest in, or a right to develop a site of sufficient size to construct and \noperate the Large Load; (2) an option to purchase or acquire a leasehold site of \nsufficient size to construct and operate the Large Load for such purpose; or (3) any \nother documentation that clearly demonstrates the right of Large Load Interconnection \nCustomer or Large Load Owner, as applicable, to exclusively occupy a site of sufficient \nsize to construct and operate the Large Load.  \n \nSystem Protection Facilities shall mean the equipment, including necessary \nprotection signal communications equipment, that protects (1) the Participating TO’s \nTransmission System, Participating TO’s Interconnection Facilities, Distribution System,"},{"page":103,"startToken":28320,"endToken":28732,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nISO Controlled Grid, and Affected Systems from faults or other electrical disturbances \noccurring at the Large Load and (2) the Large Load from faults or other electrical \nsystem disturbances occurring on the ISO Controlled Grid, Participating TO’s \nInterconnection Facilities, and Affected Systems or on other delivery systems or other \ngenerating systems to which the ISO Controlled Grid is directly connected. \n \nTransmission Interconnection Service shall mean the service provided by the \nParticipating TO associated with interconnecting the Large Load to the Participating \nTO’s Transmission System and enabling the Large Load Interconnection Customer to \nreceive electric energy at the Point of Interconnection, pursuant to the terms of the \nTSRA and the TO Tariff. \n \nTransmission Security and Reliability Agreement (TSRA) shall mean the form of \nagreement applicable to an Interconnection Application pertaining to a Large Load \nprocessed pursuant to the LLIP, a pro forma version of which is set forth in Attachment \n3 to Appendix XV of the TO Tariff.   \n \nWithdrawal Penalty shall mean the penalty assessed by Participating TO to a \nLarge Load Interconnection Customer that chooses to withdraw or is deemed withdrawn \nfrom Participating TO’s interconnection queue or whose Large Load does not otherwise \nreach its Service Commencement Date. The calculation of the Withdrawal Penalty is set \nforth in LLIP Section 3.10.1.1. \n \nSection 3. \nGeneral Provisions Applicable to All Interconnection Requests \n \n \n3.1 \nInterconnection Requests \nA Large Load Interconnection Customer shall submit to Participating TO \nan Interconnection Request in the form of Attachment 1 to this LLIP for \nprocessing under the LLIP.  The Participating TO will forward a copy of the \nInterconnection Request to the ISO, as applicable.   \n \nAn Interconnection Request for the expansion of capacity of an existing \nLarge Load shall be treated the same as an Interconnection Request for a \nnew Large Load pursuant to this LLIP.  \n \nCo-located generation serving a Large Load that will not export to the ISO \nControlled Grid will be evaluated for impacts to the Participating TO’s \nTransmission System as part of the LLIP study process, provided the co-\nlocated generation is included in the Interconnection Request. Co-located \ngeneration that will export to the ISO Controlled Grid is required to submit \na generator interconnection request to the ISO in accordance with Section \n25.7.6 of the ISO Tariff for evaluation of the proposed generator \ninterconnection and the Large Load will be evaluated pursuant to the LLIP. \n \n3.2 \nTransmission Interconnection Service"},{"page":104,"startToken":28732,"endToken":29077,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n3.2.1 The Product.  Transmission Interconnection Service allows Large \nLoad Interconnection Customer to connect the Large Load to the \nParticipating TO’s Transmission System and be eligible to receive \nelectric energy and capacity from the ISO Controlled Grid. \n \n3.2.2 No Applicability to Transmission Service.  Nothing in this LLIP \nshall constitute a request for transmission service or confer upon a \nLarge Load Interconnection Customer any right to receive \ntransmission service.   \n \n3.2.3 Roles and Responsibilities. \n \n3.2.3.1 \nEach Interconnection Request will be subject to the \ndirection and oversight of the Participating TO.  The \nParticipating TO will conduct or cause to be performed the \nrequired Interconnection Studies and any additional studies \nthe Participating TO determines to be reasonably necessary.  \nThe analysis of impacts on, and upgrades required to, the \nParticipating TO’s Transmission System will be performed by \nthe Participating TO and will be subject to review and \nconcurrence by the ISO.  The Participating TO will perform \nall required studies related to the Participating TO’s \nTransmission System and will coordinate with Affected \nSystem Operators in accordance with LLIP Section 3.5. \n \n3.2.3.2 The Participating TO will complete or cause to be \ncompleted all studies as required within the timelines \nprovided in this LLIP. \n \n3.2.3.3 \nEach Large Load Interconnection Customer shall pay \nthe actual costs of all Interconnection Studies, and any \nadditional studies the Participating TO determines to be \nreasonably necessary in response to the Interconnection \nRequest.  The Participating TO shall reimburse the ISO for \nthe actual cost of any portion of the Interconnection Studies \nthat the ISO performs related to the ISO Controlled Grid, as \napplicable.  \n \n3.2.3.3.1 The Participating TO shall issue invoices for \nInterconnection Studies that shall include a detailed \nand itemized accounting of the cost of each \nInterconnection Study.  Whenever the actual cost of \nperforming the Interconnection Studies exceeds the \nInterconnection Study Deposit, the Large Load \nInterconnection Customer shall pay the undisputed \ndifference in accordance with the Participating TO"},{"page":105,"startToken":29077,"endToken":29452,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nissued invoice within thirty (30) Calendar Days.  The \nParticipating TO shall not be obligated to continue to \nhave any studies conducted unless the Large Load \nInterconnection Customer has paid all undisputed \namounts in compliance herewith. \n \n3.3 \nComparability \nParticipating TO shall receive, process and analyze all Interconnection \nRequests in a timely manner as set forth in this LLIP.  Participating TO will \nuse the same Reasonable Efforts in processing and analyzing \nInterconnection Requests from all Large Load Interconnection Customers, \nwhether the Large Load is owned by Participating TO and its Affiliates or \nby a third party.   \n \n3.4 \nBase Case Data \nParticipating TO shall provide Base Case data to a Large Load \nInterconnection Customer upon request subject to confidentiality \nprovisions in LLIP Section 7.1. Participating TO shall provide base power \nflow, short circuit databases, including all underlying assumptions, and \ncontingency list used in the Large Load Interconnection Customer’s \nInterconnection Studies.  Participating TO is permitted to require that the \nLarge Load Interconnection Customer sign a confidentiality agreement \nbefore the release of commercially sensitive information or Critical Energy \nInfrastructure Information in the Base Case data.  Such Base Cases may \ninclude all (i) Large Loads, (ii) generation projects, and (iii) transmission \nprojects, including merchant transmission projects that are proposed for \nthe Transmission System for which a transmission expansion plan has \nbeen submitted and approved by the applicable authority. \n \n \n3.5 \nCoordination with Affected Systems \nThe Participating TO will notify the Affected System Operators that are \npotentially affected by a Large Load Interconnection Customer’s \nInterconnection Request.  The Participating TO will coordinate the conduct \nof any studies required to determine the impact of the Interconnection \nRequest on Affected Systems with Affected System Operators and, if \npossible, include those results (if available) in its applicable \nInterconnection Study within the time frame specified in this LLIP.  \nParticipating TO will include such Affected System Operators in all \nmeetings held with Large Load Interconnection Customer as required by \nthis LLIP.  Large Load Interconnection Customer will cooperate with \nParticipating TO in all matters related to the conduct of studies and the \ndetermination of modifications to Affected Systems.  If an Affected System \nOperator, that has been informed its system is an Affected System refuses"},{"page":106,"startToken":29452,"endToken":29886,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nto cooperate with the Participating TO with whom interconnection has \nbeen requested in all matters related to the conduct of studies and the \ndetermination of whether modifications to its Affected System are \nnecessary to avoid adverse impacts, it waives any right in any fora that the \nParticipating TO’s provision of service has adversely impacted such \nAffected System Operator. \n \n3.6 \nCapacity of the Large Load  \n \nThe Interconnection Request shall be evaluated using the maximum \ncapacity requested by the Large Load Interconnection Customer.  \nHowever, if the maximum capacity that the Large Load is capable of \nreceiving is greater than the maximum capacity requested by the Large \nLoad Interconnection Customer, the Large Load Interconnection Customer \nwill be required to limit the Large Load capacity to no greater than the \namount requested (e.g., through use of a control system, power relay(s), \nor other similar device settings or adjustments), and the Large Load \nInterconnection Customer must obtain the Participating TO’s agreement, \nwith such agreement not to be unreasonably withheld, that the manner in \nwhich the Large Load Interconnection Customer proposes to implement \nsuch a limit will not adversely affect the safety and reliability of the \nParticipating TO’s Transmission System.  If the Participating TO does not \nso agree, then the Interconnection Request must be withdrawn or revised \nto specify the maximum capacity that the Large Load is capable of \nreceiving.    Furthermore, nothing in this section shall prevent a \nParticipating TO from considering a capacity higher than the limited \ncapacity, if appropriate, when evaluating system protection impacts. \n \n3.7 \nProposed Service Commencement Date \nThe  proposed Service Commencement Date of the new Large Load or \nincrease in capacity of the existing Large Load shall not exceed seven \nyears from the date the Interconnection Request is received by \nParticipating TO for those Interconnection Requests studied in accordance \nwith the Large Load Interconnection Procedures, unless Large Load \nInterconnection Customer demonstrates and the Participating TO agrees, \nsuch agreement not to be unreasonably withheld, that engineering, \npermitting and construction of the new Large Load or increase in capacity \nof the existing Large Load will take longer than the seven year period.    \n \n3.7.1 Interconnection Request.  If the proposed Service Commencement \nDate in the Interconnection Request is more than seven years from the \ndate the Interconnection Request is received by the Participating TO, the \nLarge Load Interconnection Customer must demonstrate, subject to the \nParticipating TO’s agreement, such agreement not to be unreasonably \nwithheld, that the required engineering, permitting and construction of the \nLarge Load will take longer than the seven-year period."},{"page":107,"startToken":29886,"endToken":30247,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n3.7.2 After Start of the Large Load Interconnection Study.  Any \nrequest to extend the Service Commencement Date after commencement \nof the Large Load Interconnection Study under the LLIP, or following \nexecution of a TSRA, shall be subject to the following: \n \n(i) Requested extension does not exceed seven years from Service \nCommencement Date in the original Interconnection Request.  A \nrequest to extend the Service Commencement Date that does not \nexceed seven years from the Service Commencement Date in the \noriginal Interconnection Request is subject to the modification \nassessment process specified in LLIP Section 4.6.1.6.  \n \n(ii) Requested extension exceeds seven years from Service \nCommencement Date in the original Interconnection Request.  A \nrequest to extend the Service Commencement Date that exceeds \nseven years from the Service Commencement Date in the original \nInterconnection Request shall (a) demonstrate, subject to the \nParticipating TO’s agreement, such agreement not to be \nunreasonably withheld, that engineering, permitting and \nconstruction of the new Large Load or increase in capacity of the \nexisting Large Load will take longer than the seven-year period, \nand (b) be subject to the modification assessment process \nspecified in LLIP Section 4.6.1.6. \n \n3.8   Queue Position \n \n           3.8.1 Assignment of Queue Position. \nParticipating TO shall assign a Queue Position as follows: the \nQueue Position shall be assigned based upon the date and time of \nreceipt of all items required pursuant to the provisions of LLIP \nSection 4.2.1.   \n \n3.8.2 Higher Queue Position.  \nA higher Queue Position assigned to an Interconnection Request is \none that has been placed “earlier” in the queue in relation to \nanother Interconnection Request that is assigned a lower Queue \nPosition.  \n \n \n3.9 \nWithdrawal \nLarge Load Interconnection Customer may withdraw its Interconnection \nRequest at any time by written notice of such withdrawal to Participating \nTO, and the Participating TO will notify the ISO and Affected System \nOperators, if any, within three (3) Business Days of receipt of such a \nnotice.  In addition, after confirmation by the Participating TO of a valid \nInterconnection Request, if the Large Load Interconnection Customer fails"},{"page":108,"startToken":30247,"endToken":30662,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nto adhere to all requirements of this LLIP, except as provided in LLIP \nSection 7.2 (Disputes), Participating TO shall deem the Interconnection \nRequest to be withdrawn and shall provide written notice to Large Load \nInterconnection Customer of the deemed withdrawal within five (5) \nBusiness Days and an explanation of the reasons for such deemed \nwithdrawal.  Upon receipt of such written notice, Large Load \nInterconnection Customer shall have five (5) Business Days in which to \neither respond with information or action that either cures the deficiency or \nsupports its position that the deemed withdrawal was erroneous and \nnotifies the Participating TO of its intent to pursue Dispute Resolution. \n \nFor an Interconnection Request under the LLIP, withdrawal shall result in \nthe removal of the Interconnection Request from the Interconnection \nStudies.  If a Large Load Interconnection Customer disputes the \nwithdrawal and removal from the Interconnection Studies and has elected \nto pursue Dispute Resolution, Large Load Interconnection Customer's \nInterconnection Request will not be considered in any ongoing \nInterconnection Study during the Dispute Resolution process. \n \nIn the event of such withdrawal, Participating TO, subject to the provisions \nin LLIP Section 7.1, as applicable, shall provide, at Large Load \nInterconnection Customer's request, all information that Participating TO \ndeveloped for any completed study conducted up to the date of withdrawal \nof the Interconnection Request. \n \n3.10 \nWithdrawal Penalty \nA Large Load Interconnection Customer with an Interconnection Request \nbeing processed under the LLIP will be subject to a Withdrawal Penalty if \nit withdraws its Interconnection Request or is deemed withdrawn, or the \nLarge Load does not otherwise achieve its Service Commencement Date, \nwhich date may be modified if the necessary Participating TO-owned \nfacilities cannot be constructed on a timeline that meets such date, unless: \n(1) the withdrawal does not have a material impact on the cost or timing of \nany equal or later queued interconnection request; (2) Large Load \nInterconnection Customer withdraws after receiving Large Load \nInterconnection Customer’s most recent Interconnection Study report and \nthe Large Load Network Upgrade costs assigned to the Interconnection \nRequest identified in that report have increased by more than twenty-five \npercent (25%) compared to costs identified in Large Load Interconnection \nCustomer’s preceding Interconnection Study report; or (3) Large Load \nInterconnection Customer withdraws after receiving an Interconnection \nStudy report issued after completion of the initial Large Load \nInterconnection Study and the Large Load Network Upgrade costs \nassigned to the Interconnection Request identified in such Interconnection"},{"page":109,"startToken":30662,"endToken":31014,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nStudy report have increased by more than one hundred percent (100%) \ncompared to costs identified in the initial Large Load Interconnection \nStudy report. \n \n3.10.1 Calculation of the Withdrawal Penalty \nIf the Large Load Interconnection Customer withdraws its \nInterconnection Request or is deemed withdrawn prior to the \ncommencement of the Large Load Interconnection Study, Large \nLoad Interconnection Customer will not be subject to a Withdrawal \nPenalty.  If Large Load Interconnection Customer withdraws, is \ndeemed withdrawn, or otherwise does not achieve its Service \nCommencement Date at any point after the commencement of the \nLarge Load Interconnection Study, that Large Load Interconnection \nCustomer’s Withdrawal Penalty will be the greater of: (1) the Large \nLoad Interconnection Customer’s study deposit required under LLIP \nSection 4.2.1; or (2) as follows in (a)–(d): \n \n(a) If Large Load Interconnection Customer withdraws or is \ndeemed withdrawn during the Large Load Interconnection Study \nor after receipt of a Large Load Interconnection Study report, \nLarge Load Interconnection Customer will be charged two (2) \ntimes the actual cost of the Large Load Interconnection Study \nperformed for the Large Load Interconnection Customer. \n \n(b) If Large Load Interconnection Customer withdraws or is \ndeemed withdrawn after receipt of the draft TSRA but before \nLarge Load Interconnection Customer has executed a TSRA or \nhas requested that its TSRA be filed unexecuted, Large Load \nInterconnection Customer will be charged ten percent (10%) its \nestimated Large Load Network Upgrade costs as reflected in \nthe most recently completed Interconnection Study.   \n \n(c) If Large Load Interconnection Customer has executed a \nTSRA or has requested that its TSRA be filed unexecuted and \nsubsequently withdraws its Interconnection Request, the Large \nLoad Interconnection Customer’s Withdrawal Penalty will \ncalculated as described in the TSRA.   \n \nThe Commercial Readiness Deposit shall be retained as financial \nsecurity for the Withdrawal Penalty (if applicable) and other than as \ndescribed in the TSRA, any security not applied to the Withdrawal \nPenalty will be released to the Interconnection Customer following \nwithdrawal or the Service Commencement Date. \n \n3.11 Standards for Co-located Inverter Based Generating Facilities"},{"page":110,"startToken":31014,"endToken":31370,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \nInverters used for the production, and/or later injection from storage, of \nelectricity shall meet the inverter certification standards of UL-1741 and \nUL-1741 Supplement B. \n \nSection 4.  Large Load Study Process \n \n4.1 \nTiming For Submitting Interconnection Requests \nA Large Load Interconnection Customer may submit an Interconnection \nRequest for processing under the LLIP at any time during the year. The \nParticipating TO, in coordination with the ISO, as applicable, will study the \nInterconnection Request.   \n \n4.2 Processing of Interconnection Request \n \n4.2.1 \nInitiating an Interconnection Request.  To initiate an \nInterconnection Request under the LLIP, Large Load \nInterconnection Customer must submit all of the following: (i) an \nInterconnection Study Deposit of $250,000; (ii) a completed \nInterconnection Request in the form of Attachment 1 to the LLIP, \nincluding preferred Point of Interconnection and voltage level, and \nall other technical data; (iii) a Commercial Readiness Deposit equal \nto two times the study deposit described in this Section 4.2.1 in the \nform of an irrevocable letter of credit, cash, a surety bond, or other \nform of security that is reasonably acceptable to Participating TO, in \naccordance with LLIP Section 4.7.1. This Commercial Readiness \nDeposit is refunded to Large Load Interconnection Customer \naccording to LLIP Section 3.10.1; however, the Participating TO \nshall be entitled to hold the Commercial Readiness Deposit until the \nLarge Load Interconnection Customer’s Generating Facility \nachieves its Service Commencement Date; and (iv) demonstration \nof Site Control.   \n \n4.2.1.1 Use of Interconnection Study Deposit.  The \nInterconnection Study Deposit shall be applied to pay for \nprudent costs incurred by the Participating TO, the ISO, or \nthird parties at the direction of the Participating TO or ISO, \nas applicable, to perform and administer the Interconnection \nStudies.   \n \nIn the event a Large Load Interconnection Customer \nwithdraws its Interconnection Request prior to the \ncommencement of the Large Load Interconnection Study, \nLarge Load Interconnection Customer must pay Participating \nTO the actual costs of processing its Interconnection \nRequest. In the event a Large Load Interconnection \nCustomer withdraws after commencement of the Large Load"},{"page":111,"startToken":31370,"endToken":31736,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nInterconnection Study, Participating TO shall charge and \nLarge Load Interconnection Customer shall pay the actual \ncosts of the Interconnection Studies.  \n \nAny difference between the study deposit and the actual cost \nof the Interconnection Studies shall be paid by or refunded to \nthe Large Load Interconnection Customer. Any invoices for \nInterconnection Studies shall include a detailed and itemized \naccounting of the cost of each Interconnection Study. Large \nLoad Interconnection Customers shall pay any such \nundisputed costs within thirty (30) Calendar Days of receipt \nof an invoice. If Large Load Interconnection Customer fails to \npay such undisputed costs within the time allotted, its \nInterconnection Request shall be deemed withdrawn and will \nbe subject to Withdrawal Penalties pursuant to LLIP Section \n3.10.1. \n \nThe Participating TO will reimburse the ISO or third parties, \nas applicable, for all work performed on behalf of the \nwithdrawn Interconnection Request at the Participating TO’s \ndirection. The Large Load Interconnection Customer must \npay all monies due before it is allowed to obtain any \nInterconnection Study data or results. \n \n4.3 \nValidation of Interconnection Request \n \n4.3.1 Acknowledgment of Interconnection Request.  Participating TO \nshall notify the Large Load Interconnection Customer within ten \n(10) Business Days of receipt of the Interconnection Request, \nwhich notice shall state whether the Interconnection Request is \ndeemed valid.   \n \n4.3.2 Deficiencies in Interconnection Request.  An Interconnection \nRequest will not be considered to be a valid request until all items \nin LLIP Section 4.2.1 have been received by Participating TO and \ndeemed valid by the Participating TO.  If an Interconnection \nRequest fails to meet the requirements set forth in LLIP Section \n4.2.1, Participating TO shall include in its notification to the Large \nLoad Interconnection Customer under LLIP Section 4.3.1 the \nreasons for such failure and that the Interconnection Request does \nnot constitute a valid request.  Large Load Interconnection \nCustomer shall provide Participating TO the additional requested \ninformation needed to constitute a valid request.  Whenever the \nadditional requested information is provided by the Large Load \nInterconnection Customer, the Participating TO shall notify the \nLarge Load Interconnection Customer within five (5) Business Days"},{"page":112,"startToken":31736,"endToken":32150,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nof receipt of the additional requested information whether the \nInterconnection Request is valid.  If the Interconnection Request \ncontinues to fail to meet the requirements set forth in LLIP Section \n4.2.1, the Participating TO shall include in its notification to the \nLarge Load Interconnection Customer the reasons for such failure.  \nIf an Interconnection Request has not been deemed valid, the \nLarge Load Interconnection Customer must submit all information \nnecessary to meet the requirements of LLIP Section 4.2.1 no later \nthan twenty (20) Business Days after the date the original \nInterconnection Request was submitted, or ten (10) Business Days \nafter the Participating TO first provided notice that the \nInterconnection Request was not valid, whichever is later.  \nInterconnection Requests that have not met the requirements of \nLLIP Section 4.2.1 within twenty (20) Business Days after the date \nthe original Interconnection Request was submitted or ten (10) \nBusiness Days after the Participating TO first provided notice that \nthe Interconnection Request was not valid, whichever is later, will \nbe deemed invalid and will not be included in the LLIP.  \n \nInterconnection Requests deemed invalid under this LLIP Section \n4.3.2 are not subject to LLIP Section 3.9.  Large Load \nInterconnection Customers with invalid Interconnection Requests \nunder this LLIP Section 4.3.2 may seek relief under LLIP Section \n7.2 by notifying the Participating TO within two (2) Business Days \nof the notice of invalidity. \n \n4.4      Potential Deferral of the Interconnection Studies \n           The Participating TO may defer commencement of the Large Load \nInterconnection Study when it determines, using Good Utility Practice and \nreasonable engineering judgment, that the Interconnection Request \ncannot be studied meaningfully until other pending study results for \nhigher-queued projects are available. \n \n         Within ten (10) Business Days after deeming an Interconnection Request \nvalid under Section 4.3.1, the Participating TO will notify the Large Load \nInterconnection Customer in writing if it is deferring the start of the \nInterconnection Studies. The notice will include: (i) information regarding \nthe pending studies; and (ii) the estimated start date of the Large Load \nInterconnection Study.  During the period of deferral, the Participating TO \nwill provide a monthly status update to the Interconnection Customer. \n \n4.5 \nScoping Meeting \nWithin fifteen (15) Business Days after the Participating TO notifies the \nLarge Load Interconnection Customer that the Interconnection Request \nhas been deemed valid as set forth in LLIP Section 4.3.2, the Participating"},{"page":113,"startToken":32150,"endToken":32555,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nTO shall establish a date agreeable to the Large Load Interconnection \nCustomer, and the ISO, if applicable, for the Scoping Meeting.   \n \nThe purpose of the Scoping Meeting shall be to discuss reasonable \nService Commencement Dates and alternative interconnection options, to \nexchange information including any transmission data that would \nreasonably be expected to impact such interconnection options, to \nanalyze such information and to determine the potential feasible Points of \nInterconnection and eliminate alternatives given resources and available \ninformation. The Scoping Meeting shall also include discussion of a \ndeferral of the Interconnection Studies in accordance with LLIP Section \n4.4.     \n \nThe Participating TO will bring to the meeting, as reasonably necessary to \naccomplish its purpose, such already available technical data, including, \nbut not limited to, (i) general facility loadings, (ii) general instability issues, \n(iii) general short circuit issues, (iv) general voltage issues, and (v) general \nreliability issues.    \n \nThe Large Load Interconnection Customer will bring to the Scoping \nMeeting, in addition to the technical data in Appendix A to LLIP \nAttachment 1, any system studies previously performed.  The Participating \nTO, the ISO, if applicable, and the Large Load Interconnection Customer \nwill also bring to the meeting personnel and other resources as may be \nreasonably required to accomplish the purpose of the meeting in the time \nallocated for the meeting.  On the basis of the meeting, the Large Load \nInterconnection Customer shall designate its Point of Interconnection.  \nThe duration of the meeting shall be sufficient to accomplish its purpose. \n \nWithin five (5) Business Days after the Scoping Meeting, the Participating \nTO  shall provide the Large Load Interconnection Customer with a Large \nLoad Study Process Agreement in the form set forth in LLIP Attachment 2, \nwhich shall contain an outline of the scope of the Large Load \nInterconnection Study, contain a non-binding good faith estimate of the \ncost to perform such study, and shall specify that the Large Load \nInterconnection Customer is responsible for the actual cost of the \nInterconnection Studies, including reasonable administrative costs.  The \nLarge Load Interconnection Customer shall execute and deliver to the \nParticipating TO the Large Load Study Process Agreement no later than \nthirty (30) Calendar Days after the Scoping Meeting, or the \nInterconnection Request shall be deemed withdrawn. \n \n4.6 \nInterconnection Studies \nThe Interconnection Studies shall consist of a Large Load Interconnection \nStudy and any additional studies, including but not limited to those"},{"page":114,"startToken":32555,"endToken":32933,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nidentified in LLIP Section 4.6.3 required for interconnection of the Large \nLoad, and co-located generation not exporting to the ISO Controlled Grid, \nto the Participating TO’s Transmission System.  The analysis of impacts \non, and upgrades required to, the Participating TO’s Transmission System \nwill be performed by the Participating TO and will be subject to the review \nand concurrence of the ISO in accordance with Section 25.7 of the ISO \nTariff. The Interconnection Studies will identify Interconnection Facilities, \nDistribution Upgrades and required Large Load Network Upgrades \nnecessary to mitigate thermal overloads and voltage violations, and \naddress short circuit, stability, and reliability issues associated with the \nrequested Transmission Interconnection Service. When a Large Load \nOwner is the Large Load Interconnection Customer, the Interconnection \nStudies will be limited to the identification of Large Load Network \nUpgrades necessary to mitigate thermal overloads and voltage violations, \nand address short circuit, stability, and reliability issues associated with \nthe requested Transmission Interconnection Service.  \n \nAll cost estimates for Participating TO’s Interconnection Facilities, \nDistribution Upgrades, and Large Load Network Upgrades, as applicable, \ncontained in the Interconnection Studies will be set forth in the \nInterconnection Study report in present dollar costs as well as time-\nadjusted dollar costs, adjusted to the estimated year of construction of the \ncomponents being constructed.   \n \nThe Participating TO will prepare an Interconnection Study report to \ndocument the results of the Interconnection Studies.   \n \n4.6.1 Large Load Interconnection Study.  \n \n \n4.6.1.1  Scope of the Large Load Interconnection Study.  The \nLarge Load Interconnection Study will consist of a short \ncircuit analysis, a power flow analysis, an electromagnetic \ntransient (“EMT”) screening, a non-binding good faith \nestimate of the scope and cost of the Participating TO’s \nInterconnection Facilities, Distribution Upgrades and Large \nLoad Network Upgrades, and any other studies that are \ndeemed necessary. The Large Load Interconnection Study \nwill also identify the need for any additional studies (e.g., \nstability analysis, EMT study, etc.) to be performed as part of \nthe scope of the TSRA pursuant to LLIP Section 4.6.3.  \nWhen there is co-located generation not exporting to the ISO \nControlled Grid and not subject to electrical short circuit duty \ndependence, the Large Load Interconnection Study will"},{"page":115,"startToken":32933,"endToken":33247,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nidentify the impacts associated with the Large Load and any \nincremental impacts of the co-located generation.       \nThe Large Load Interconnection Study will consider the use \nof alternative transmission technologies including dynamic \nline ratings, advanced power flow control devices, advanced \nconductors, and transmission switching, when evaluating \ntransmission solutions to accommodate new Large Loads \nand their associated transmission system impacts.  \nThe Large Load Interconnection Study shall state the \nassumptions upon which it is based, state the results of the \nanalyses, and provide the requirement or potential \nimpediments to providing the requested Transmission \nInterconnection Service, including an estimate of the cost \nand length of time that would be necessary to correct any \nproblems identified in those analyses and implement the \nInterconnection.   \n \nThe Large Load Interconnection Study shall provide a list of \nParticipating TO’s Interconnection Facilities, Distribution \nUpgrades, and Large Load Network Upgrades, as \napplicable, that are required as a result of the \nInterconnection Request. \n \n4.6.1.2 Timing of the Large Load Interconnection Study \nResults.  The Participating TO shall use Reasonable Efforts \nto complete the Large Load Interconnection Study within \nninety (90) Calendar Days after the execution of a Large \nLoad Study Process Agreement.  The Participating TO will \nissue a Large Load Interconnection Study report to the Large \nLoad Interconnection Customer. The Participating TO will \nshare study results with the ISO for review and concurrence.   \n \nAt any time the Participating TO determines that it will not \nmeet the required time frame for completing the Large Load \nInterconnection Study, Participating TO shall notify the Large \nLoad Interconnection Customer as to the schedule status of \nthe Large Load Interconnection Study and provide an \nestimated completion date with an explanation of the \nreasons why additional time is required. \n \nUpon request, the Participating TO shall provide the Large \nLoad Interconnection Customer all supporting \ndocumentation, workpapers and relevant pre-Interconnection"},{"page":116,"startToken":33247,"endToken":33616,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nRequest and post-Interconnection Request power flow and \nshort circuit databases for the Large Load Interconnection \nStudy, subject to confidentiality arrangements consistent \nwith LLIP Section 7.1. \n \nShould the Large Load Interconnection Customer provide \nwritten comments on the Large Load Interconnection Study \nreport at least five (5) Business Days before the Report \nMeeting conducted to discuss the report, the Participating \nTO will address the written comments in the Large Load \nInterconnection Study Report Meeting.  Should the Large \nLoad Interconnection Customer provide comments at any \nlater time (up to the time of the Report Meeting), then such \ncomments shall be considered informal inquiries to which the \nParticipating TO will provide informal, informational \nresponses at the Report Meeting, to the extent possible.  \n \nThe Large Load Interconnection Customer may submit, in \nwriting, additional comments on the final Large Load \nInterconnection Study report up to (3) Business Days \nfollowing the Report Meeting.  Based on any discussion at \nthe Report Meeting and any comments received from the \nLarge Load Interconnection Customer or the ISO, the \nParticipating TO will determine whether it is necessary to \nfollow the Large Load Interconnection Study report with a \nrevised study report.  The Participating TO will issue any \nsuch revised report to the Large Load Interconnection \nCustomer no later than fifteen (15) Business Days following \nthe Report Meeting. If the ISO has not completed its review \nof the Large Load Interconnection Study report, the \nParticipating TO shall delay its determination of whether a \nrevised study report is required until that review is complete. \n \n4.6.1.3 Large Load Interconnection Study Report Meeting.  A \nReport Meeting shall be held among the Participating TO, \nthe ISO, if applicable, and the Large Load Interconnection \nCustomer to discuss the results of the Large Load \nInterconnection Study, including assigned cost responsibility.  \nA Report Meeting will be held within ten (10) Business Days \nof the date the Large Load Interconnection Study report is \nprovided to the Large Load Interconnection Customer.  \n \n4.6.1.4 Increase in the Commercial Readiness Deposit.  The \nLarge Load Interconnection Customer shall submit an \nadditional deposit that brings the total Commercial \nReadiness Deposit to twenty percent (20%) of Large Load"},{"page":117,"startToken":33616,"endToken":33979,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nInterconnection Customer’s Large Load Network Upgrade \ncost assignment identified in the Large Load Interconnection \nStudy, within thirty (30) Calendar Days after being provided \nwith the final Large Load Interconnection Study report, or its \nInterconnection Request shall be deemed withdrawn.   \n \n \nShould the Large Load Interconnection Study report be \nrevised as the result of ISO review, in accordance with LLIP \nSection 4.6.1.2, the increase in the Commercial Readiness \nDeposit shall be adjusted to reflect twenty percent (20%) of \nthe assigned Large Load Network Upgrades in the revised \nreport within thirty (30) Calendar Days of issuance of the \nfinal report. \n   \n4.6.1.5 Restudy. If restudy of the Large Load Interconnection \nStudy is required due to a higher queued project dropping \nout of the queue, or a modification of a higher queued \nproject subject to Section 4.6.1.6, Participating TO shall \nnotify Large Load Interconnection Customer in writing. Such \nrestudy shall take no longer than forty-five (45) Calendar \nDays from the date of notice. Any cost of restudy shall be \nborne by the Large Load Interconnection Customer. \n \n4.6.1.6 Modifications.  At any time during the course of the \nInterconnection Studies, the Large Load Interconnection \nCustomer, the Participating TO, or the ISO, as applicable, \nmay identify changes to the planned interconnection that \nmay improve the costs and benefits (including reliability) of \nthe interconnection, and the ability of the proposed change \nto accommodate the Interconnection Request.  To the extent \nthe identified changes are acceptable to the Participating \nTO, the ISO, as applicable, and Large Load Interconnection \nCustomer, such acceptance not to be unreasonably \nwithheld, Participating TO shall modify the configuration in \naccordance with such changes without altering the \nInterconnection Request’s eligibility for participating in \nInterconnection Studies.          \n \n4.6.1.6.1 For any modifications other than those agreed \nupon under LLIP Section 4.6.1.6, the Interconnection \nCustomer must first request that Participating TO \nevaluate whether such modification is a Material \nModification.  In response to Interconnection \nCustomer's request, Participating TO, in coordination \nwith the ISO, if applicable, shall evaluate the \nproposed modifications prior to making them and"},{"page":118,"startToken":33979,"endToken":34317,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \ninform Interconnection Customer in writing of whether \nthe modifications would constitute a Material \nModification.  The Participating TO may, at its option, \nengage the services of the ISO to assist in the \nassessment of the modification.  Any change to the \nPoint of Interconnection shall constitute a Material \nModification.   \n \n \n \nThe Large Load Interconnection Customer shall \nprovide the Participating TO a $30,000 deposit for the \nmodification assessment at the time the request is \nsubmitted.  Except as provided below, any \nmodification assessment will be concluded, and a \nresponse provided to the Large Load Interconnection \nCustomer in writing, within forty-five (45) Calendar \nDays from the date the Participating TO receives all of \nthe following: 1) the Large Load Interconnection \nCustomer’s written notice to modify the project; 2) a \nnarrative description of the requested modification; 3) \ntechnical data required to assess the request, \nincluding an updated Appendix A to the \nInterconnection Request Form (LLIP Attachment 1), if \nrequested by the Participating TO; 4) any additional \ninformation requested by Participating TO; and 5) \npayment of the $30,000 deposit.  If applicable, the \nParticipating TO shall coordinate the modification \nrequest with the ISO.  If the modification assessment \ncannot be completed within that time period, the \nParticipating TO shall notify the Large Load \nInterconnection Customer and provide an estimated \ncompletion date with an explanation of the reasons \nwhy additional time is required.  The Large Load \nInterconnection Customer will be responsible for the \nactual costs incurred by the Participating TO and, if \napplicable, the ISO in conducting the modification \nassessment.  If the actual costs of the modification \nassessment are less than the deposit provided by the \nLarge Load Interconnection Customer, the Large \nLoad Interconnection Customer will be refunded the \nbalance within thirty (30) Calendar Days of being \ninvoiced.  If the actual costs of the modification \nassessment are greater than the deposit provided by \nthe Large Load Interconnection Customer, the Large \nLoad Interconnection Customer shall pay the balance \nwithin thirty (30) Calendar Days of being invoiced."},{"page":119,"startToken":34317,"endToken":34655,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nIf the proposed modification is determined to be a \nMaterial Modification by the Participating TO pursuant \nto the modification assessment described above, the \nLarge Load Interconnection Customer shall then \neither:  \n \n(i) \nwithdraw the proposed modification, or  \n \n(ii) \nwithdraw the proposed modification and submit a \nnew Interconnection Request reflecting such \nmodification. \n \n4.6.2    Optional Flexible Interim Load Interconnection (FILI) Study \nand Agreement. Based on the results of the Large Load \nInterconnection Study, the Large Load Interconnection Customer \nmay elect to have a FILI Study performed when the estimated \ncompletion date of the PTO’s Interconnection Facilities, \nDistribution Upgrades, or Large Load Network Upgrades identified \nin the Large Load Interconnection Study is beyond the Large Load \nInterconnection Customer’s requested Service Commencement \nDate.  \n \n \nThe Large Load Interconnection Customer’s election to proceed \nwith the FILI Study must be made by written notification to the \nParticipating TO within fifteen (15) Business Days of the Large \nLoad Interconnection Study Report Meeting.  \n \nThe Participating TO will perform the FILI Study within sixty (60) \nCalendar Days of receipt of the Large Load Interconnection \nCustomer’s written notification. The Large Load Interconnection \nCustomer will be responsible for the actual costs of the Study. At \nany time Participating TO determines that it will not meet the \nrequired time frame for completing the FILI Study, Participating TO \nshall notify the Large Load Interconnection Customer as to the \nschedule status of the FILI Study and provide an estimated \ncompletion date with an explanation of the reasons why additional \ntime is required. \n \nThe FILI study will determine: (i) whether a Large Load \nInterconnection Customer is eligible to receive non-firm limited \nload capacity; (ii) the conditions and limitations of such service; (iii) \nthe upgrades and the associated cost, and (iv) the estimated \nduration required to provide the limited service. The Participating \nTO will share study results with the ISO for review and \nconcurrence.  If requested by the Large Load Interconnection \nCustomer within ten (10) Business Days of the date of the"},{"page":120,"startToken":34655,"endToken":35015,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nissuance of the FILI Study report, a Report Meeting shall be \nscheduled among the Participating TO, the ISO, and the Large \nLoad Interconnection Customer. \n \n \n \nThe Large Load Interconnection Customer should note the \nfollowing considerations: \na) \nTemporary limits may be adjusted if unforeseen conditions \narise. \nb) \nAdvance notice of non-firm load curtailment may not be \npossible. \nc) \nNon-firm load may be curtailed during planned or repair \noutages, which may last longer than 6 months. \nd) \nISO may have additional operational requirements. \ne) \nParticipating TO is not obligated to provide flexibility beyond \nwhat it can, in its sole judgment, manage operationally. \nf) \nInterconnection Facilities costs for interim interconnection \nservice will be directly assigned to the Large Load \nInterconnection Customer. \ng) \nLarge Load Interconnection Customers not adhering to the \ncontractual agreement and conditions may be curtailed \nindefinitely.  \n \n4.6.2.1 FILI Agreement with Participating TO and ISO. If the \nLarge Load Interconnection Customer has elected Flexible \nInterim Load Interconnection (FILI), as reflected in the \nTSRA, the Large Load Interconnection Customer will be \nrequired to execute an agreement with the Participating TO \nand ISO, in the form of agreement included in Attachment 4 \nto LLIP, prior to the Service Commencement Date, in \naccordance with ISO Tariff Section 25.7.2. The agreement \nshall describe the circumstances in which the ISO or \nParticipating TO may temporarily curtail the Large Load \nreceiving FILI, and the mechanism the ISO or Participation \nTO will use to perform the curtailment. The ISO will post \nsuch FILI agreements on the ISO Website.  \n \n4.6.3   Additional Studies. The Participating TO may identify the need for \nadditional studies to comply with Applicable Reliability Standards. \nThese additional studies may include, but not limited to, the \nfollowing: stability analysis, variable load impact analysis, and EMT \nanalysis.  The associated new scope will be identified in the Large \nLoad Interconnection Study pursuant to LLIP Section 4.6.1.1. The \nadditional studies will be performed by the Participating TO as part \nof the scope of work set forth in the Transmission Security and \nReliability Agreement (“TSRA”). The additional studies may result in"},{"page":121,"startToken":35015,"endToken":35394,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nthe identification of additional facilities scope and cost, and may \nrequire a revision to the schedule set forth in the TSRA. The Large \nLoad Interconnection Customer will be responsible for providing the \nnecessary technical information and/or models requested by the \nParticipating TO to conduct the additional studies. The Large Load \nInterconnection Customer will be responsible for the costs of such \nstudies.            \n \nIf an additional study results in the need to revise the scope of work \nof the Large Load Network Upgrades identified in the Large Load \nInterconnection Study and the updated assigned costs have \nincreased by more than twenty-five percent (25%) compared to \ncosts identified in the Large Load Interconnection Study Report, the \nLarge Load Interconnection Customer shall not be subject to a \nWithdrawal Penalty under LLIP Section 3.10.1 if the Interconnection \nRequest is withdrawn within thirty (30) Calendar Days of receipt of \nthe additional study report.  If the Large Load Interconnection \nCustomer elects to continue with its Interconnection Request, the \nTSRA will be amended to reflect the results of the additional study. \n \n4.6.4   Financing of Participating TO’s Interconnection Facilities, \nDistribution Upgrades and Large Load Network Upgrades.  The \nresponsibility to finance Participating TO’s Interconnection Facilities \nand Distribution Upgrades shall be assigned solely to the Large \nLoad Interconnection Customer, except where the Large Load will \nbe a retail transmission customer of Participating TO, in which case \nthe local regulatory authority will determine any financing \nresponsibilities for Distribution Upgrades. The Participating TO will \nbe responsible for financing Large Load Network Upgrades in \naccordance with the TSRA.   \n \n4.7 \nInterconnection Financial Security   \n \n4.7.1 Types of Interconnection Financial Security.  The \nInterconnection Financial Security posted by a Large Load \nInterconnection Customer may be any combination of the following \ntypes of Interconnection Financial Security provided in favor of the \nParticipating TO: \n \n(a) \nan irrevocable and unconditional letter of credit issued by a \nbank or financial institution that has a credit rating of A or \nbetter by Standard and Poor’s or A2 or better by Moody’s;  \n \n(b) \nan irrevocable and unconditional surety bond issued by an \ninsurance company that has a credit rating of A or better by \nStandard and Poor’s or A2 or better by Moody’s;"},{"page":122,"startToken":35394,"endToken":35757,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n(c) \nan unconditional and irrevocable guaranty issued by a \ncompany has a credit rating of A or better by Standard and \nPoor’s or A2 or better by Moody’s; \n \n(d) \na cash deposit standing to the credit of the Participating TO \nand in an interest-bearing escrow account maintained at a \nbank or financial institution that is reasonably acceptable to \nthe Participating TO; \n \n(e) \na certificate of deposit in the name of the Participating TO \nissued by a bank or financial institution that has a credit \nrating of A or better by Standard and Poor’s or A2 or better \nby Moody’s; or  \n \n(f) \na payment bond certificate in the name of the Participating \nTO issued by a bank or financial institution that has a credit \nrating of A or better by Standard and Poor’s or A2 or better \nby Moody’s.  \n \nInterconnection Financial Security instruments as listed above shall \nbe in such form as the Participating TO may reasonably require \nfrom time to time by notice to Large Load Interconnection \nCustomers, or in such other form as has been evaluated and \napproved as reasonably acceptable by the Participating TO.     \n \nThe Participating TO shall require the use of standardized forms of \nInterconnection Financial Security to the greatest extent possible.  \nIf at any time the guarantor of the Interconnection Financial \nSecurity fails to maintain the credit rating required by this LLIP \nSection 4.7.1, the Large Load Interconnection Customer shall \nprovide to the Participating TO replacement Interconnection \nFinancial Security meeting the requirements of this LLIP Section \n4.7.1 within five (5) Business Days of the change in credit rating.  \n \nInterest on a cash deposit standing to the credit of the Participating \nTO in an interest-bearing escrow account under subpart (d) of this \nLLIP Section 4.7.1 will accrue to the Large Load Interconnection \nCustomer’s benefit.  \n \nExecution and filing of the TSRA at FERC are addressed in LLIP \nSection 5. \n \nSection 5. \nTransmission Security and Reliability Agreement  \n \n5.1 \nTender.  Within thirty (30) Calendar Days after the Report Meeting for the final \nLarge Load Interconnection Study report, or the final FILI Study report, if"},{"page":123,"startToken":35757,"endToken":36235,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \napplicable, the Participating TO shall tender a draft TSRA, together with \ndraft appendices.  The draft TSRA shall be in the form of Participating \nTO's FERC-approved form of TSRA, which is in Attachment 3 to the LLIP.  \nThe Large Load Interconnection Customer shall provide written \ncomments, or notification of no comments, to the draft appendices within \nthirty (30) Calendar Days. \n \n5.2 \nNegotiation.  Notwithstanding LLIP Section 5.1, at the request of Large Load \nInterconnection Customer Participating TO shall begin negotiations with \nLarge Load Interconnection Customer concerning the appendices to the \nTSRA at any time after the Participating TO provides the Large Load \nInterconnection Customer with the final Large Load Interconnection Study \nreport, or the final FILI Study report, if applicable.  Participating TO and \nLarge Load Interconnection Customer shall negotiate concerning any \ndisputed provisions of the appendices to the draft TSRA for not more than \nsixty (60) Calendar Days after the Participating TO provides the Large \nLoad Interconnection Customer with the final Large Load Interconnection \nStudy report or the final FILI Study report if applicable.  If Large Load \nInterconnection Customer determines that negotiations are at an impasse, \nit may request termination of the negotiations at any time after tender of \nthe draft TSRA pursuant to LLIP Section 5.1 and request submission of \nthe unexecuted TSRA with FERC or initiate Dispute Resolution \nprocedures pursuant to LLIP Section 7.2.  If Large Load Interconnection \nCustomer requests termination of the negotiations, but within sixty (60) \nCalendar Days after issuance of the final Large Load Interconnection \nStudy report, or the final FILI Study report if applicable, fails to request \neither the filing of the unexecuted TSRA or initiate Dispute Resolution, it \nshall be deemed to have withdrawn its Interconnection Request.  Unless \notherwise agreed by the Parties, if Large Load Interconnection Customer \nhas not executed the TSRA, requested filing of an unexecuted TSRA, or \ninitiated Dispute Resolution procedures pursuant to LLIP Section 7.2 \nwithin sixty (60) Calendar Days after issuance of the final Large Load \nInterconnection Study report, or the final FILI Study report if applicable, it \nshall be deemed to have withdrawn its Interconnection Request.  \nParticipating TO shall provide to Large Load Interconnection Customer a \nfinal TSRA within fifteen (15) Business Days after the completion of the \nnegotiation process. \n \n \nThe Participating TO may declare an impasse upon sixty (60) Calendar \nDays after issuance of the final Large Load Interconnection Study report, \nor the final FILI Study report if applicable, or at anytime following sixty (60) \nCalendar Days after issuance of the final Large Load Interconnection \nStudy report, or the final FILI Study report if applicable, if the Parties have \nagreed to extend negotiation of the TSRA.  If the Participating TO declares \nan impasse, the Participating TO will file the TSRA unexecuted with FERC \nwithin twenty one (21) Calendar Days."},{"page":124,"startToken":36235,"endToken":36615,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n5.3 \nExecution and Filing \nLarge Load Interconnection Customer shall either: (i) execute two originals \nof the tendered TSRA and return them to Participating TO; or (ii) request \nin writing that Participating TO file with FERC a TSRA in unexecuted form.  \nAs soon as practicable, but not later than ten (10) Business Days after \nreceiving either the two executed originals of the tendered TSRA (if either \ndoes not conform with a FERC-approved standard form of TSRA) or the \nrequest to file an unexecuted TSRA, Participating TO shall file the TSRA \nwith FERC, together with its explanation of any matters as to which Large \nLoad Interconnection Customer and Participating TO disagree and \nsupport for the costs that Participating TO proposes to charge to Large \nLoad Interconnection Customer under the TSRA.  An unexecuted TSRA \nshould contain terms and conditions deemed appropriate by Participating \nTO for the Interconnection Request.  If the Parties agree to proceed with \ndesign, procurement, and construction of facilities and upgrades under the \nagreed-upon terms of the unexecuted TSRA, they may proceed pending \nFERC action. \n \n \n5.4 \nCommencement of Interconnection Activities \nIf Large Load Interconnection Customer executes the final TSRA, \nParticipating TO and Large Load Interconnection Customer shall perform \ntheir respective obligations in accordance with the terms of the TSRA, \nsubject to modification by FERC.  Upon submission of an unexecuted \nTSRA, Large Load Interconnection Customer and Participating TO shall \npromptly comply with the unexecuted TSRA, if agreed to by the Parties \npursuant to LLIP Section 5.2, subject to modification by FERC. \n \n5.5 \nLarge Load Interconnection Customer To Meet Requirements of the \nParticipating TO’s Interconnection Handbook   \nThe Large Load Interconnection Customer’s Interconnection Facilities \nshall be designed, constructed, operated and maintained in accordance \nwith the Participating TO’s Interconnection Handbook.  In the event of a \nconflict between the terms of the LLIP and the terms of the Participating \nTO’s Interconnection Handbook, the terms in the LLIP shall govern.  \n \nSection 6. \nConstruction of Participating TO's Interconnection Facilities, \nDistribution Upgrades, and Large Load Network Upgrades  \n \n \n6.1 \nSchedule \nParticipating TO and Large Load Interconnection Customer shall negotiate \nin good faith concerning a schedule for the Participating TO’s construction \nof Participating TO's Interconnection Facilities, Distribution Upgrades, and \nthe Large Load Network Upgrades."},{"page":125,"startToken":36615,"endToken":36944,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n6.2 \nConstruction Sequencing \n \n6.2.1 General.  In general, the Service Commencement Date will \ndetermine the sequence of construction of Distribution Upgrades \nand Large Load Network Upgrades. \n \n6.2.2 Advancing Construction of Distribution Upgrades and Large \nLoad Network Upgrades that are Part of an Expansion Plan of \nthe Participating TO.  A Large Load Interconnection Customer \nwith a TSRA, in order to maintain its Service Commencement Date, \nmay request that Participating TO advance to the extent necessary \nthe completion of Distribution Upgrades and Large Load Network \nUpgrades that:  (i) are necessary to support such Service \nCommencement Date and (ii) would otherwise not be completed, \npursuant to an expansion plan of Participating TO or approved ISO \nTransmission Plan covering the Participating TO’s service territory, \nin time to support such Service Commencement Date.  Upon such \nrequest, Participating TO will use Reasonable Efforts to advance \nthe construction of such Distribution Upgrades and Large Load \nNetwork Upgrades to accommodate such request; provided that \nLarge Load Interconnection Customer commits to pay Participating \nTO any associated expediting costs.   \n \n6.3 \nSpecial Provisions for Affected Systems   \nThe Large Load Interconnection Customer shall enter into an agreement \nwith the Affected System Operator, as applicable.  The agreement shall \nspecify the terms governing payments to be made by the Large Load \nInterconnection Customer to the Affected System Operator.   \n \nSection 7. \nMiscellaneous \n \n7.1 \nConfidentiality \n \nFor the purposes of this LLIP Section 7.1, “Party” or “Parties” shall mean \nthe Participating TO, Large Load Interconnection Customer, ISO, or any \ncombination of the Participating TO, Large Load Interconnection \nCustomer, or ISO.  \n \nConfidential Information shall include, without limitation, all information \nrelating to a Party's technology, research and development, business \naffairs, and pricing. \n \nInformation is Confidential Information only if it is clearly designated or \nmarked in writing as confidential on the face of the document, or, if the \ninformation is conveyed orally or by inspection, if the Party providing the"},{"page":126,"startToken":36944,"endToken":37361,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \ninformation orally informs the Party receiving the information that the \ninformation is confidential. \n \nIf requested by either Party, the other Party shall provide in writing, the \nbasis for asserting that the information referred to in this Article warrants \nconfidential treatment, and the requesting Party may disclose such writing \nto the appropriate Governmental Authority.  Each Party shall be \nresponsible for the costs associated with affording confidential treatment \nto its information. \n \n \n \n7.1.1 Scope.  Confidential Information shall not include information that \nthe receiving Party can demonstrate: (1) is generally available to \nthe public other than as a result of a disclosure by the receiving \nParty; (2) was in the lawful possession of the receiving Party on a \nnon-confidential basis before receiving it from the disclosing Party; \n(3) was supplied to the receiving Party without restriction by a third \nparty, who, to the knowledge of the receiving Party after due \ninquiry, was under no obligation to the disclosing Party to keep \nsuch information confidential; (4) was independently developed by \nthe receiving Party without reference to Confidential Information of \nthe disclosing Party; (5) is, or becomes, publicly known, through no \nwrongful act or omission of the receiving Party or Breach of the \nTSRA; or (6) is required, in accordance with LLIP Section 7.1.6, \nOrder of Disclosure, to be disclosed by any Governmental Authority \nor is otherwise required to be disclosed by law or subpoena, or is \nnecessary in any legal proceeding establishing rights and \nobligations under the TSRA. Information designated as Confidential \nInformation will no longer be deemed confidential if the Party that \ndesignated the information as confidential notifies the other Party \nthat it no longer is confidential. \n \n7.1.2  Release of Confidential Information.  Neither Party shall release \nor disclose Confidential Information to any other person, except to \nits Affiliates (limited by the Standards of Conduct requirements), \nemployees, consultants, Affected System Operators, or to parties \nwho may be or considering providing financing to or equity \nparticipation with Large Load Interconnection Customer, or to \npotential purchasers or assignees of Large Load Interconnection \nCustomer, on a need-to-know basis in connection with these \nprocedures, unless such person has first been advised of the \nconfidentiality provisions of this LLIP Section 7.1 and has agreed to \ncomply with such provisions.  Notwithstanding the foregoing, a \nParty providing Confidential Information to any person shall remain \nprimarily responsible for any release of Confidential Information in \ncontravention of this LLIP Section 7.1."},{"page":127,"startToken":37361,"endToken":37794,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n7.1.3 Rights.  Each Party retains all rights, title, and interest in the \nConfidential Information that each Party discloses to the other \nParty.  The disclosure by each Party to the other Party of \nConfidential Information shall not be deemed a waiver by either \nParty or any other person or entity of the right to protect the \nConfidential Information from public disclosure. \n \n7.1.4 No Warranties.  By providing Confidential Information, neither \nParty makes any warranties or representations as to its accuracy or \ncompleteness.  In addition, by supplying Confidential Information, \nneither Party obligates itself to provide any particular information or \nConfidential Information to the other Party nor to enter into any \nfurther agreements or proceed with any other relationship or joint \nventure. \n \n7.1.5 Standard of Care.  Each Party shall use at least the same \nstandard of care to protect Confidential Information it receives as it \nuses to protect its own Confidential Information from unauthorized \ndisclosure, publication or dissemination.  Each Party may use \nConfidential Information solely to fulfill its obligations to the other \nParty under these procedures or its regulatory requirements. \n \n7.1.6 Order of Disclosure.  If a court or a Government Authority or entity \nwith the right, power, and apparent authority to do so requests or \nrequires either Party, by subpoena, oral deposition, interrogatories, \nrequests for production of documents, administrative order, or \notherwise, to disclose Confidential Information, that Party shall \nprovide the other Party with prompt notice of such request(s) or \nrequirement(s) so that the other Party may seek an appropriate \nprotective order or waive compliance with the terms of these \nconfidentiality provisions. Notwithstanding the absence of a \nprotective order or waiver, the Party may disclose such Confidential \nInformation which, in the opinion of its counsel, the Party is legally \ncompelled to disclose.  Each Party will use Reasonable Efforts to \nobtain reliable assurance that confidential treatment will be \naccorded any Confidential Information so furnished. \n \n7.1.7 Remedies.  The Parties agree that monetary damages would be \ninadequate to compensate a Party for the other Party's Breach of \nits obligations under this LLIP Section 7.1.  Each Party accordingly \nagrees that the other Party shall be entitled to equitable relief, by \nway of injunction or otherwise, if the first Party Breaches or \nthreatens to Breach its obligations under this LLIP Section 7.1, \nwhich equitable relief shall be granted without bond or proof of \ndamages, and the receiving Party shall not plead in defense that \nthere would be an adequate remedy at law.  Such remedy shall not"},{"page":128,"startToken":37794,"endToken":38279,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nbe deemed an exclusive remedy for the Breach of this LLIP Section \n7.1 but shall be in addition to all other remedies available at law or \nin equity.  The Parties further acknowledge and agree that the \ncovenants contained herein are necessary for the protection of \nlegitimate business interests and are reasonable in scope.  No \nParty, however, shall be liable for indirect, incidental, or \nconsequential or punitive damages of any nature or kind resulting \nfrom or arising in connection with this LLIP Section 7.1. \n \n7.1.8 Disclosure to FERC, its Staff, or a State.  Notwithstanding \nanything in this LLIP Section 7.1 to the contrary, and pursuant to 18 \nCFR section 1b.20, if FERC or its staff, during the course of an \ninvestigation or otherwise, requests information from one of the \nParties that is otherwise required to be maintained in confidence \npursuant to the LLIP, the Party shall provide the requested \ninformation to FERC or its staff, within the time provided for in the \nrequest for information.  In providing the information to FERC or its \nstaff, the Party must, consistent with 18 CFR section 388.112, \nrequest that the information be treated as confidential and non-\npublic by FERC and its staff and that the information be withheld \nfrom public disclosure.  Parties are prohibited from notifying the \nother Party prior to the release of the Confidential Information to \nFERC or its staff.  The Party shall notify the other Party to the \nTSRA when it is notified by FERC or its staff that a request to \nrelease Confidential Information has been received by FERC, at \nwhich time either of the Parties may respond before such \ninformation would be made public, pursuant to 18 CFR section \n388.112.  Requests from a state regulatory body conducting a \nconfidential investigation shall be treated in a similar manner, \nconsistent with applicable state rules and regulations. \n \n7.1.9 Subject to the exception in LLIP Section 7.1.8, any information that \na Party claims is competitively sensitive, commercial or financial \ninformation (\"Confidential Information\") shall not be disclosed by \nthe other Party to any person not employed or retained by the other \nParty, except to the extent disclosure is (i) required by law; (ii) \nreasonably deemed by the disclosing Party to be required to be \ndisclosed in connection with a dispute between or among the \nParties, or the defense of litigation or dispute; (iii) otherwise \npermitted by consent of the other Party, such consent not to be \nunreasonably withheld;  or (iv) necessary to fulfill its obligations \nunder this LLIP or as a transmission service provider or a Balancing \nAuthority Area operator including disclosing the Confidential \nInformation to an RTO or ISO or to a subregional, regional or \nnational reliability organization or planning group.  The Party \nasserting confidentiality shall notify the other Party in writing of the"},{"page":129,"startToken":38279,"endToken":38514,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \ninformation it claims is confidential.  Prior to any disclosures of the \nother Party's Confidential Information under this subparagraph, or if \nany third party or Governmental Authority makes any request or \ndemand for any of the information described in this subparagraph, \nthe disclosing Party agrees to promptly notify the other Party in \nwriting and agrees to assert confidentiality and cooperate with the \nother Party in seeking to protect the Confidential Information from \npublic disclosure by confidentiality agreement, protective order or \nother reasonable measures. \n \n7.1.10 This provision shall not apply to any information that was or is \nhereafter in the public domain (except as a result of a Breach of this \nprovision). \n \n7.1.11 Participating TO shall, at Large Load Interconnection Customer's \nelection, destroy, in a confidential manner, or return the \nConfidential Information provided at the time of Confidential \nInformation is no longer needed. \n \n \n7.2 \nDisputes  \n \n \n \n7.2.1  Submission.  In the event either Party has a dispute, or asserts a \nclaim, that arises out of or in connection with the TSRA, the LLIP, \nor their performance, such Party (the \"disputing Party\") shall \nprovide the other Party with written notice of the dispute or claim \n(\"Notice of Dispute\").  Such dispute or claim shall be resolved in \naccordance with the Dispute Resolution Procedures set forth in \nSection 14 of the TO Tariff."},{"page":130,"startToken":38514,"endToken":38729,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \nATTACHMENT 1 to LLIP \n \nTRANSMISSION OWNER TARIFF \nINTERCONNECTION REQUEST FOR A \nLARGE LOAD  \n \n \nSubmittal and Payment Instructions \n \n The Interconnection Request may be submitted via email at \ngrid.interconnections@sce.com or mail to: \n  \nSouthern California Edison Company \nGrid Interconnection & Contract Development \nP.O. Box 800 \n2244 Walnut Grove Avenue \nRosemead, CA  91770 \n \nThe required deposit may be submitted via mail at: \n \nSouthern California Edison Company \nAttention: Accounts Receivable (GCM) \nP.O. Box 800 \nRosemead, CA 91771-0001 \n \n \nThe undersigned Large Load Interconnection Customer submits this request to \ninterconnect its Large Load with Participating TO’s Transmission System \npursuant to Appendix XV of the TO Tariff. \n \n \nWhere Large Load Owner will be a retail transmission customer of Participating \nTO, requests for interconnection of non-exporting generation will be governed by \nthe Local Regulatory Authority. \n \n1. \nThis Interconnection Request is for (check only one): \n \n \n \nA proposed new Large Load. \n \nA proposed new Large Load and co-located generation \n \n \nAn increase in the capacity, or a Material Modification of an existing Large \nLoad.  \n \n \n2. \nLarge Load Interconnection Customer provides the following information: \n \n \na. \nAddress or location, including the county, of the proposed new Large Load \nsite (to the extent known) or, in the case of an existing Large Load, the"},{"page":131,"startToken":38729,"endToken":38936,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nname and specific location, including the county, of the existing Large \nLoad; \n \n \n \nProject Name: \n      \n \nProject Location:  \nStreet Address: \n      \nCity, State: \n      \nCounty:  \n      \n \n \n \nZip Code: \n \n \n \nGPS Coordinates: \n \n \n \nAssessor’s Parcel Numbers (if available): \n \n \nb. \nMaximum rated load and the requested maximum load of the proposed \nnew Large Load or the amount of increase in the load of an existing Large \nLoad; \n \nMaximum rated load (MW): ________ \nRequested maximum load (MW): ________    or \nIncrease in the load (MW):     ________  \n  \nProvide five (5) year forecast of monthly load requirements beginning with \nthe first year after service is scheduled to commence. \n \nc. \nType of Large Load and general description of the equipment \nconfiguration (if more than one type is chosen, include net MW for each); \n \n \nComputational loads \n___ AI/machine-learning training data center                         _____ MW \n___ Cloud, enterprise, colocation or AI inference data center _____ MW \n___ Cryptocurrency mining \n                                              _____ MW \n___ Non-IT Load \n                                              _____ MW \n \nElectrochemical and industrial process loads \n___ Hydrogen electrolyzer \n                                            _____ MW \n___ Electric arc furnace or induction furnace \n_____  MW \n___ Other manufacturing or process industry (e.g., semiconductor fab, \nchemicals, cement) \n                                            _____ MW \n___ Other (please describe):                                                  ____  MW \n \nd. \nDescription of co-located generation resource(s) (if applicable) \n \n \nRated capacity (MW): ________ \n \nWill the co-located generation export to the ISO Controlled Grid (Yes or \nNo)?"},{"page":132,"startToken":38936,"endToken":39127,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \nCo-located generation exporting to the ISO Controlled Grid will be \nevaluated under the ISO Tariff and the Interconnection Customer is \nrequired to submit a separate Interconnection Request pursuant to \nAppendix KK of the ISO Tariff. \n \nCAISO queue number (if applicable): ___________ \n \ne. \nProposed Service Commencement Date, and Other Key Dates \n(Day/Month/Year)  \n  \n  \nProposed Service Commencement Date: \n      /       /  \nProposed Date of Initial Operation of co-located generation (if  \napplicable)          /      /      \nProposed Term of Service (years): ______________ \n \n      \n \n \n \nf.  \nName, address, telephone number, and e-mail address of Large Load \nInterconnection Customer's contact person (primary person who will be \ncontacted); \n \nName: \n      \nTitle: \n      \nCompany Name: \n      \nStreet Address:       \nCity, State: \n      \nZip Code: \n      \nPhone Number:       \n \n      \nEmail Address:       \nLarge Load Interconnection Customer’s DUNS Number: \n      \n \n \ng.  \nPoint of Interconnection: \n \nTransmission Substation (Name and voltage level): \n______________________, or \nTransmission Line: ______________________, or \n \nApproximate location of the proposed Point of Interconnection \n_______________ (i.e., specify transmission facility interconnection point \nname, voltage level, and the location of interconnection);  \n \n \nh.  \nLarge Load Interconnection Customer Data (set forth in Appendix A) \n \nThe Large Load Interconnection Customer shall provide to the \nDistribution Provider the technical data called for in Appendix A."},{"page":133,"startToken":39127,"endToken":39310,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n3. \nApplicable Interconnection Study Deposit amount as specified in LLIP Section \n4.2.1 made payable to Southern California Edison Company.  Send check to \nParticipating TO along with: \n \n1. A completed Interconnection Request form for processing. \n2. A completed Appendix A (Transmission Owner Tariff Large Load \nData). \n \n4. \nCommercial Readiness Deposit (CRD) equal to two times the Study Deposit \namount in the form of a security instrument in accordance with LLIP Section \n4.9.1.  A draft security instrument may be submitted with the Interconnection \nRequest but must be finalized within ten (10) Business Days. \n \n5. \nEvidence of Site Control as specified in LLIP Section 4.2.1 and name(s), \naddress(es) and contact information of site owner(s).  (Attach documentation) \n \n \n6. \nRepresentative of Large Load Interconnection Customer to contact: \n \n \n \n[To be completed by Large Load Interconnection Customer] \nName: \n      \nTitle: \n      \nCompany Name: \n      \nStreet Address:       \nCity, State: \n      \nZip Code: \n      \nPhone Number:     \nEmail Address: \n \n                  \n7. \nThis Interconnection Request is submitted by: \n \n \nLegal name of Large Load Interconnection Customer:  ___________________ \n \n \nBy: ____________________________  \n \n \nName: _________________________ \n \nTitle: __________________________ \n \n \nDate: __________________________"},{"page":134,"startToken":39310,"endToken":39616,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nAppendix A to  \nInterconnection Request \n \nTRANSMISSION OWNER TARIFF \nLARGE LOAD DATA \n \n \nEach Large Load Interconnection Customer will complete Sections 1 and 2 of this \nAppendix A. Each Large Load Interconnection Customer colocating with non-exporting \ngenerating facilities will complete the applicable data in Sections 3 through 8 of this \nAttachment A based on the type of generating facility(ies) requesting interconnection.  \n(Section 5 for synchronous generators, Section 6 for induction generators, Section 7 for \nwind turbine generators, and Section 8 for inverter-based generators). \n \nEach Large Load Interconnection Customer will complete Sections 9 through 13, as \napplicable. At any time, Participating TO may require Large Load Interconnection \nCustomer to provide additional technical data, or additional documentation supporting \nthe technical data provided, as deemed necessary by the Participating TO to perform \nInterconnection Studies, other studies, or evaluations as set forth under the LLIP. \n \n1.  \nProvide the following: \n \nA. \nSite drawing showing Large Load location and Point of Interconnection \nwith the Participating TO’s Transmission System. \nB. \nSingle-line diagram showing applicable equipment such as large load \ncomponents, generating units (if applicable), step-up transformers, \nauxiliary transformers, switches/disconnects of the proposed \ninterconnection, including the required protection devices and circuit \nbreakers. This one-line drawing must be signed and stamped by a \nlicensed Professional Engineer. \n \n2. Large Load Information: \nProvide the following information for the Large Load: \n \nA.    Rated total MW consumption and power factor of the Large Load, including \nIT equipment, power distribution, and cooling: \nTotal MW: _______________ \nPower factor: _______________ \nB.    Percentage of the total MW consumption of the Large Load for each of the \nfollowing load components: \nComputing/server load: _____ % \nLighting load: _____ % \nPower distribution losses: _____ % \nCooling: _____ % \nOther: _____ % (describe if applicable): _______________ \nDoes the percentage change during different seasons and different \ntimes of the day? (Yes/No): _____ If yes, provide a gross estimate"},{"page":135,"startToken":39616,"endToken":39925,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n(e.g., Summer Day / Summer Night and Winter Day / Winter Night): \n_______________ \nC.    If the Large Loadhas some form of forced cooling system, indicate what it is \ncomprised of (check all that apply and add details if needed): \n___ Computer Room Air Conditioners (CRACs) with internal \ncompressors: _______________ \n___ Computer Room Air Handlers (CRAHs) supplied with chilled \nwater: _______________ \n___ Air-Handling Units (AHUs) dedicated to the data center space: \n_______________ \n___ Other (please describe): _______________ \nD.    Motor-driven components of the cooling systems are driven by (check all \nthat apply and add details if needed): \n___ Single-speed motors operated across the line (motors \nconnected directly to the AC supply): _______________ \n___ Motors controlled by variable/adjustable speed drives or \nelectronically commutated motors (ECMs): _______________ \n___ Other methods (please specify): _______________ \nE.    Voltage sag levels and durations below which the components within the \ndata center disconnect from the grid: \n(1)   Computing/server load: _______________ \n(2)   Cooling load: _______________ \n(3)   Are voltage sags sensed per phase or on a three-phase basis \nfor the disconnection action? _______________ \n(4)   Does any load disconnect after a given number of voltage sag \nevents (Yes/No)? If yes, specify: _______________ \n(5)   Any other protection scheme related to voltage sag that may \ndisconnect load: _______________ \nF.    Voltage swell levels and durations above which the components within the \ndata center disconnect from the grid: \n(1)   Computing/server load: _______________ \n(2)   Cooling load: _______________ \n(3)   Are voltage swells sensed per phase or on a three-phase basis \nfor the disconnection action? _______________ \n(4)   Does any load disconnect after a given number of voltage \nswell events (Yes/No)? If yes, specify: _______________ \n(5)   Any other protection scheme related to voltage swell that may \ndisconnect load: _______________ \nG.   Frequency thresholds above and below which any computing/server load \nmay disconnect from the grid: \nAbove: _______________ \nBelow: _______________ \nH.   Reconnection of load after voltage and frequency recover (check all that \napply and specify): \n___ Reconnects immediately; voltage and frequency levels: \n_______________"},{"page":136,"startToken":39925,"endToken":40190,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n___ Reconnects after a time delay; voltage and frequency levels \nand delay: _______________ \n___ Reconnects manually \n___ Reconnects on a ramp; ramp rate: _______________ \nI.   Emergency generation and battery energy storage: \n(1)   Size (MW) and duration: _______________ \n(2)   Can the emergency generation and storage be dispatched to \nsupport all or part of the load during system events (Yes/No)? \n_______________ \n(3)   Can the facility island on emergency generation and storage \n(Yes/No)? _______________ \n(4)   Can the facility participate in demand-side management during \na grid emergency or as an ancillary service (Yes/No)? \n_______________ \n(5)   Amount, if any, of server farm load that could be redistributed \nto redundant server capacity: _______________ \n(6)   Amount, if any, of load that would transfer if the facility were \ntripped offline: _______________ \n(7)   How fast the load transfer can be performed: \n_______________ \n(8)   Is the transfer closed transition (make before break) or open \ntransition (break before make)? _______________ \n   \nJ.        Details of existing protection and control schemes that affect the response \nof the facility: _______________________________________________ \nK.        Acceptable duration of outage (seconds or minutes): _______________ \nL.        Any additional information about the project: ______________________ \n \n3. Co-Located Generation Information (if applicable): \n \nInclude all on-site generation and storage, including emergency backup \ngeneration, and complete (1) - (9) below. Report load and generation as \ngross values (do not net co-located generation against the Large Load). \nProvide technical data for the co-located generation resources in \nAppendix A as applicable. \n \nA. \nArrangement and operating mode: \n(1) \nArrangement (check one):  \n___ Co-located generation serving the Large Load on the \ngenerator side of the Point of Interconnection    \n___ Behind-the-meter generation at the Large Load’s retail \nmeter   \n___ Other (describe): _______________"},{"page":137,"startToken":40190,"endToken":40419,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n(2)   \nOperating mode (check all that apply):  \n___ Emergency backup only (no parallel operation with the \nPTO’s Transmission System)    \n___ Continuous parallel operation    \n___ Islanding capable   ___ Peak shaving or load following \n \n(3)  \nNew or existing generation; in-service date relative to the \nLarge Load phases in Item 2.b: __________________________ \n \nB.      Technology and ratings (aggregate nameplate MVA and MW for each \ntechnology): \n____ Combustion turbine or reciprocating engine: ____MVA \n/  ____MW       Fuel: __________ \n           ____ Solar photovoltaic: _____ MVA / _____ MW \n____ Battery energy storage: _____ MVA / _____ MW /                 \n____ MWh   \nCharges from the ISO Controlled Grid (Y/N): ___ \n           ____ Fuel cell: _____ MVA / _____ MW   Fuel: _________ \n____ Other (describe): ________________  \n           MVA / _____    MW___ \n \nVoltage (kV) at the common point where the co-located \ngeneration connects (e.g., high side of the generator step-up \ntransformer or collector system): _______________ \n \nC.      Gross and net withdrawal and requested service: \n \n(1)   Gross Large Load (MW) and gross co-located generation \n(MW), reported separately: _______ / _______ \n(2) Maximum net withdrawal from the ISO Controlled Grid with co-\nlocated generation online (MW): _______________ \n(3)   Largest single co-located generating unit or storage device that \ncould trip (MW): _______________ \n(4)   Withdrawal requested when co-located generation is \nunavailable (MW): _______    \n \nD.      Non-export controls (for non-exporting co-located generation): \n(1)   Method used to prevent export (e.g., reverse-power relay, \nexport-limiting controls, power control system): _______________ \n \n_____________________________________________________ \n \nE.      Ride-through, protection, and disturbance behavior: \n(1)   Voltage and frequency ride-through capability and protection \nsettings of the co-located generation (attach curves and settings):"},{"page":138,"startToken":40419,"endToken":40708,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n____________________________________________________ \n(2)   Expected response of the co-located generation to a sudden \nloss or reduction of the Large Load, and of the Large Load to a trip \nof the co-located generation, including the resulting change in flow \nat the Point of Interconnection (MW): _______________ \n(3)   Transfer scheme (open or closed transition) and maximum \nduration of parallel operation: _______________ \n(4)   Anti-islanding protection and time to separate from the \nTransmission System during a disturbance: _____________ \n(5)   Protection coordination at the Point of Interconnection and \ndisturbance monitoring equipment covering the co-located \ngeneration: _______________ \n \nF.       Models and data: \n(1)   Power flow and dynamic models of the co-located generation \nand an electromagnetic transient (EMT) model if required. \n(2)   Evidence of model verification (e.g., manufacturer attestation, \ntest data, or commissioning measurements), with as-built model \nupdates provided before the Service Commencement Date. \n \n \nG.      NERC registration: \n(1)   Co-located generation (check one):  \n                     ___    Bulk Electric System generation (BES Inclusion I2, I3, or \nI4): Category 1 Generator Owner / Generator Operator \n    \n                             ___    Non-BES inverter-based resources with aggregate \nnameplate capacity of 20 MVA or more connected at 60 kV or \nabove: Category 2 Generator Owner / Generator Operator \n    \n                      ___    Excluded (e.g., BES Exclusion E1 or E2) or below \nregistration thresholds; explain: _______________ \n \n(2)   Does the Large Load expect to register as a Computational \nLoad Owner or Computational Load Operator (Y/N)? _________ \n \n \n4.         Generating Facility General Information (if applicable): \nA. \nTotal Generating Facility rated output (MW): \n_______________ \nA1. \nMaximum Generating Facility operating capacity (MW): _______________ \n \n(applicable if the Generating Facility output will be limited to less than \nrated capacity) \nB. \nGenerating Facility auxiliary load (MW): _______________ \nC. \nNet Generating Facility capacity at generator/inverter terminals (MW): \n_______________ (A-B) or (A1-B) \nD. \nCollector system losses (MW): _______________ (insert “n/a” if not \napplicable or negligible)"},{"page":139,"startToken":40708,"endToken":40994,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nE. \nMain step-up transformer losses (MW): _______________ (insert “n/a” if \nnot applicable or negligible) \nF. \nNet Generating Facility capacity at high-side of main step-up transformer \n(MW): _______________ (C-D-E) \nG. \nGen-tie loss to Point of Interconnection (MW): _______________ (insert \n“n/a” if not applicable or negligible) \nH. \nNet Generating Facility capacity at Point of Interconnection (MW): \n_______________ (F-G) \nH1. \nMaximum export capacity at Point of Interconnection (MW): \n_______________ \n \n(applicable if the requested export capacity at the Point of Interconnection \nis less than the Net Generating Facility capacity at the Point of \nInterconnection.  If so, please indicate the reason (e.g., serving host load, \netc.))  ___________________ \nI. \nStandby Load when Generating Facility is off-line (MW):\n \n_______________ \nJ. \nNumber of Generating Units: ___________________ \n \n(Please repeat the following items for each generator) \nK. \nIndividual generator rated output (MW for each unit): _______________ \nL. \nManufacturer of the Generating Units:  __________________________ \nM. \nYear Manufactured: ____________ \nN. \nNominal Terminal Voltage (kV): ________________________________ \nO. \nRated Power Factor (%): _____________ \nP. \nType (induction, synchronous, D.C. with inverter): _________________ \n \nQ. \nPhase (3 phase or single phase): _______ \nR.  \nConnection (Delta, Grounded WYE, Ungrounded WYE, impedance \ngrounded): ________________________________________________  \nS.  \nGenerator Voltage Regulation Range (+/- %): _____________________  \nT.  \nGenerator Power Factor Regulation Range: ______________________  \nU.  \nFor combined cycle plants, specify the plant net output capacity (MW) for \nan outage of the steam turbine or an outage of a single combustion \nturbine______________  \n \n5. \nSynchronous Generator –Information: \n \n5A \nGenerator Information: \n(Please repeat the following for each generator) \n \nA. \nRated Generator speed (rpm): ____________ \nB. \nRated MVA: _______________ \nC. \nRated Generator Power Factor: ____________ \nD. \nGenerator Efficiency at Rated Load (%): ____________ \nE. \nMoment of Inertia (including prime mover): ____________ \nF. \nInertia Time Constant (on machine base) H: ____________ sec or \nMJ/MVA \nG. \nSCR (Short-Circuit Ratio - the ratio of the field current required for"},{"page":140,"startToken":40994,"endToken":41300,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nrated open-circuit voltage to the field current required for rated \nshort-circuit current): \n___________________________________________ \nH. \nPlease attach generator reactive capability curves. \nI. \nRated Hydrogen Cooling Pressure in psig (Steam Units only): \n________________________________________________ \nJ. \nPlease attach a plot of generator terminal voltage versus field \ncurrent that shows the air gap line, the open-circuit saturation \ncurve, and the saturation curve at full load and rated power factor. \n \n5B \nExcitation System Information: \n(Please repeat the following for each generator) \n \nA. \nIndicate the Manufacturer ____________________ and Type \n_____________of excitation system used for the generator.  For \nexciter type, please choose from 1 to 9 below or describe the \nspecific excitation system. \n(1) \nRotating DC commutator exciter with continuously acting \nregulator.  The regulator power source is independent of the \ngenerator terminal voltage and current. \n(2) \nRotating DC commentator exciter with continuously acting \nregulator.  The regulator power source is bus fed from the \ngenerator terminal voltage. \n(3) \nRotating DC commutator exciter with non-continuously \nacting regulator (i.e., regulator adjustments are made in \ndiscrete increments). \n(4) \nRotating AC Alternator Exciter with non-controlled (diode) \nrectifiers.  The regulator power source is independent of the \ngenerator terminal voltage and current (not bus-fed). \n(5) \nRotating AC Alternator Exciter with controlled (thyristor) \nrectifiers.  The regulator power source is fed from the exciter \noutput voltage. \n(6) \nRotating AC Alternator Exciter with controlled (thyristor) \nrectifiers. \n(7) \nStatic Exciter with controlled (thyristor) rectifiers.  The \nregulator power source is bus-fed from the generator \nterminal voltage. \n(8) \nStatic Exciter with controlled (thyristor) rectifiers.  The \nregulator power source is bus-fed from a combination of \ngenerator terminal voltage and current (compound-source \ncontrolled rectifiers system. \n(9) \nOther (specify): \n_______________________________________ \nB. \nAttach a copy of the block diagram of the excitation system from its \ninstruction manual.  The diagram should show the input, output, \nand all feedback loops of the excitation system."},{"page":141,"startToken":41300,"endToken":41551,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nC.  \nExcitation system response ratio (ASA): ______________ \nD.  \nFull load rated exciter output voltage: ___________ \nE.  \nMaximum exciter output voltage (ceiling voltage): ___________ \nF. \nOther comments regarding the excitation system? \n_____________________________________________________\n_____________________________________________________ \n \n5C \nPower System Stabilizer (“PSS”) Information: \n(Please repeat the following for each generator model. All new generators \nare required to install PSS unless an exemption has been obtained from \nWECC. Such an exemption can be obtained for units that do not have \nsuitable excitation systems.) \n \nA. \nManufacturer: \n_____________________________________________ \nB. \nIs the PSS digital or analog? \n__________________________________ \nC. \nNote the input signal source for the PSS? \n_____ Bus frequency   _____ Shaft speed   _____  \nBus Voltage _____________________   Other (specify source) \nD. \nPlease attach a copy of a block diagram of the PSS from the PSS \nInstruction Manual and the correspondence between dial settings \nand the time constants or PSS gain. \nE. \nOther comments regarding the PSS? \n_____________________________________________________ \n_____________________________________________________ \n_____________________________________________________ \n \n5D \nTurbine-Governor Information: \n \n(Please repeat the following for each generator model.) \n \nPlease complete Part A for steam, gas or combined-cycle turbines, Part B \nfor hydro turbines, and Part C for both. \n \nA. \nSteam, gas or combined-cycle turbines: \n \n(1) \nList type of unit (Steam, Gas, or Combined-\ncycle):__________ \n(2) \nIf steam or combined-cycle, does the turbine system have a \nreheat process (i.e., both high and low pressure turbines)? \n_______ \n(3) \nIf steam with reheat process, or if combined-cycle, indicate \nin the space provided, the percent of full load power \nproduced by each turbine: \nLow pressure turbine or gas turbine:______% \nHigh pressure turbine or steam turbine:______%"},{"page":142,"startToken":41551,"endToken":41760,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n(4)  \nFor combined cycle plants, specify the plant net output \ncapacity (MW) for an outage of the steam turbine or an \noutage of a single combustion \nturbine:_____________________________________ \n \nB. \nHydro turbines: \n \n(1) \nTurbine efficiency at rated load: _______% \n(2) \nLength of penstock: ______ft \n(3) \nAverage cross-sectional area of the penstock: _______ft2 \n(4) \nTypical maximum head (vertical distance from the bottom of \nthe penstock, at the gate, to the water level): ______ft \n(5) \nIs the water supply run-of-the-river or reservoir: \n___________ \n(6) \nWater flow rate at the typical maximum head: \n_________ft3/sec \n(7) \nAverage energy rate: _________kW-hrs/acre-ft \n(8) \nEstimated yearly energy production: ________kW-hrs \n \nC. \nComplete this section for each machine, independent of the turbine \ntype. \n \n(1) \nTurbine manufacturer: _______________ \n(2) \nMaximum turbine power output: _______________MW \n(3) \nMinimum turbine power output (while on line): \n_________MW \n(4) \nGovernor information: \n(a) \nDroop setting (speed regulation): _____________ \n(b) \nIs the governor mechanical-hydraulic or electro-\nhydraulic (Electro-hydraulic governors have an \nelectronic speed sensor and transducer.)? \n_________________ \n(c) \nOther comments regarding the turbine governor     \nsystem? \n___________________________________________ \n___________________________________________ \n___________________________________________ \n___________________________________________ \n \n5E \nShort Circuit Duty Information: \nFor each generator, provide the following reactances expressed in p.u. on \nthe generator base: \n \n• Xd – Direct Axis Synchronous Reactance: _____ p.u. \n• X’d – Direct Axis Transient Reactance: _____ p.u."},{"page":143,"startToken":41760,"endToken":41975,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n• X”d – Direct Axis Subtransient Reactance: _____ p.u. \n• X2 – Negative Sequence Reactance: _____ p.u. \n• X0 – Zero Sequence Reactance: _____ p.u. \n \nGenerator Grounding (select one for each model): \n \nA. \n_____ Solidly grounded \nB. \n_____ Grounded through an impedance \n \n(Impedance value in p.u. on generator base.\n \nR:_____________p.u. \n \nX:_____________p.u.) \nC. \n_____ Ungrounded \n \n \n6. \nInduction Generator Information:  \n(Please repeat the following for each generator) \n \nA. \nMotoring Power (kW): ______________ \nB.  \nI22t or K (Heating Time Constant): ______________ \nC.  \nRotor Resistance, Rr: ______________ \nD.  \nStator Resistance, Rs:  ______________  \nE.  \nStator Reactance, Xs: ______________ \nF.  \nRotor Reactance, Xr:  ______________   \nG.  \nMagnetizing Reactance, Xm: ______________ \nH.  \nShort Circuit Reactance, Xd'': ______________ \nI.  \nExciting Current: ______________ \nJ.  \nTemperature Rise: ______________ \nK.  \nFrame Size:  ______________  \nL.  \nDesign Letter: ______________ \nM.  \nReactive Power Required In Vars (No Load): ______________ \nN.  \nReactive Power Required In Vars (Full Load): ______________ \nO.  \nTotal Rotating Inertia, H: _____________   Per Unit on kVA Base \n \n7. \nWind Turbine Generator (WTG) Information: \n \n(Proposed projects may include one or more WTG types.  Please repeat the \nfollowing for each type of WTG). \n \nA. Number of generators to be interconnected pursuant to this \nInterconnection Request: _____  \nB. Average Site Elevation: ______ Single Phase _____ Three Phase_____  \nC. Field Volts: _________________  \nD. Field Amperes: ______________  \nE. Motoring Power (MW): _______  \nF. Neutral Grounding Resistor (If Applicable): ____________  \nG. I22t or K (Heating Time Constant): ____________"},{"page":144,"startToken":41975,"endToken":42263,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nH. Rotor Resistance: ____________  \nI. Stator Resistance: ____________  \nJ. Stator Reactance: ____________  \nK. Rotor Reactance: ____________  \nL. Magnetizing Reactance: ___________  \nM. Short Circuit Reactance: ___________  \nN. Exciting Current: ________________  \nO. Temperature Rise: ________________  \nP. Frame Size: _______________  \nQ. Design Letter: _____________  \nR. Reactive Power Required In Vars (No Load):________  \nS. Reactive Power Required In Vars (Full Load):________  \nT. Total Rotating Inertia, H: ________ Per Unit on 100 MVA Base  \n \nNote: A completed General Electric Company Power Systems Load Flow \n(PSLF) data sheet must be supplied with the Interconnection Request. If \nother data sheets are more appropriate to the proposed device then they \nshall be provided and discussed at Scoping Meeting.  \n \nDistribution Provider may require testing verification of voltage and harmonic \nperformance during commissioning test of WTG based generation projects. \n \n8. \nInverter Based Generation Systems Information:  \n \n(Proposed inverter based generation projects may include one or more types of \ninverters.  Please repeat the following for each type of inverter). \n \nA.  \nInverter Manufacturer and Model: _________________________ \nB.  \nNumber of Inverters: ___________________ \nC.  \nNameplate Rating (AC, each inverter):   _______/_______ kW \nD.  \nNameplate Voltage Rating (AC):   _______ kV \nE.  \nMaximum AC line current:   _______ Amps \nF.  \nNameplate Power Factor Rating (AC):   _______  \nG.  \nPlease attach capability curve describing reactive power or power factor \nrange from no output to full rated output   \nH.  \nInverter control mode (e.g. voltage, power factor, reactive power):   _____  \nI. \nShort Circuit Characteristics: Applicant to provide technical data related to \nthe short circuit characteristics of proposed inverter based generation \nsystems.  For example, the applicant can provide a sinusoidal waveform \ntest data showing faulted condition at the AC side of the inverter for a \nthree phase and single-line-to-ground fault.   \nJ.  \nHarmonics Characteristics: \n(1)  \nInverter switching frequency: _______ \n \n(2)  \nHarmonic characteristics for each unit up to switching frequency: \n___________________________________________________"},{"page":145,"startToken":42263,"endToken":42377,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n(3)  \nHarmonic characteristics for aggregate generation facility: _______ \nK. \nInverter disconnection characteristics:  Applicant to provide voltage \nsinusoidal waveform test data which shows the voltage characteristics \nduring disconnection of inverter system from distribution system at 100% \nand at 50% of rated output.     \nL. \nProvide documentation demonstrating compliance with the Smart Inverter \nrequirements specified in Section 3.13 of the LLIP. \n \nDistribution Provider may require testing verification of voltage and harmonic \nperformance during commissioning test of the inverter based generation \nsystems. \n \n9. \nStep-Up Transformer Data: \n \nFor each step-up transformer (e.g. main step-up transformers, padmount \ntransformers), fill out the data form provided in Table 1."},{"page":146,"startToken":42377,"endToken":42470,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \nTABLE 1 \n \nTRANSFORMER DATA \n(Provide for each level of transformation) \n \nUNIT*_____________________________________ \n \nNUMBER OF TRANSFORMERS_________   PHASE _______ \n \nRATING \nH Winding \nX Winding \nY Winding \n \nRated MVA \n \nConnection (Delta, Wye, Gnd.) \n \nCooling Type (OA,OA/FA, etc) :    \n \nTemperature Rise Rating  \n \nRated Voltage \n \nBIL \n \nAvailable Taps (% of rating) \n \nLoad Tap Changer? (Y or N) \n \nTap Settings \n \n \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \n__________ \nIMPEDANCE \nH-X \nH-Y \nX-Y \n \nPercent \n \nMVA Base \n \nTested Taps \n \nWINDING RESISTANCE \n \nOhms \n \n __________ \n \n__________ \n \n__________ \n \nH \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \nX \n \n__________ \n \n__________ \n \n__________ \n \n__________ \n \nY \n \n__________ \n \n \nCURRENT TRANSFORMER RATIOS \n \nH_____________ \nX______________ \nY______________ \nN_____________ \n \nPERCENT EXCITING CURRENT 100 % Voltage; _________ 110% Voltage________"},{"page":147,"startToken":42470,"endToken":42747,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nSupply copy of nameplate and manufacturer’s test report when available.  \n \n* For Generating Facilities with multiple step-up transformers, identify the transformer datasheet \nunit number with that of the single line. \n \n10. \nInterconnection Facilities Line Data:  \n \nFor transmission lines that are to be planned by the generation developer, please \nprovide the following information: \n \nNominal Voltage: _______________ kV \nLine Length (miles): ___________________ \nLine termination Points: ___________________ \nConductor Type: ______   Size: ________  \nIf bundled.  Number per phase: ______, Bundle spacing: _____in. \nPhase Configuration. Vertical: _______, Horizontal: _______ \nPhase Spacing (ft): A-B: ______, B-C: _______, C-A: ________ \nDistance of lowest conductor to Ground at full load and 40°C: _________ft \nGround Wire Type: ________ Size: _______ Distance to Ground: ______ft \nAttach Tower Configuration Diagram \nSummer line ratings in amperes (normal and emergency) _________________ \nPositive Sequence Resistance ( R ):  \n__________ p.u.** (for entire line \nlength) \nPositive Sequence Reactance: ( X ):  \n__________ p.u.** (for entire line \nlength) \nZero Sequence Resistance ( R0 ):  \n__________ p.u.** (for entire line \nlength) \nZero Sequence Reactance: ( X0 ):  \n__________ p.u.**  (for entire line \nlength) \nLine Charging (B/2):  \n__________ p.u.** \n** On 100-MVA and nominal line voltage (kV) Base \n \n11. \nFor Wind/Photovoltaic Plants, provide Collector System Equivalence \nImpedance Data (if applicable): \n \nProvide values for each equivalence collector circuit at all voltage levels. \n \n \nNominal Voltage: _______________ kV \n \nSummer line ratings in amperes (normal and emergency): _______________ \n \nPositive Sequence Resistance ( R ): _____ p.u.** (for entire line length of each \ncollector circuit) \n \nPositive Sequence Reactance: ( X ): _____ p.u.** (for entire line length of each \ncollector circuit) \n \nZero Sequence Resistance ( R0 ): _____ p.u.** (for entire line length of each \ncollector circuit) \n \nZero Sequence Reactance: ( X0 ): _____ p.u.** (for entire line length of each \ncollector circuit) \n \nLine Charging (B/2): ______ p.u.**"},{"page":148,"startToken":42747,"endToken":43003,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n** On 100-MVA and nominal line voltage (kV) Base \n \n12. \nPlant-Level Reactive Power Compensation Data: \nProvide the following information for plant-level reactive power compensation, if \napplicable:  \n \nA.  \nNumber of individual shunt capacitor banks: _____________ \nB.  \nIndividual shunt capacitor bank rated voltage (kV): _____________ \nC.  \nIndividual shunt capacitor bank size (kVAR at rated voltage): \n_____________ \nD. \nPlanned dynamic reactive control devices (SVC, STATCOM): \n_____________ \nE.  \nControl range: _____________ kVAR (lead) _____________ kVAR (lag)   \nF.  \nControl mode (e.g. voltage, power factor, reactive power): \n_____________ \nG.  \nPlease provide the overall plant reactive power control strategy \n \n13. \nStorage System Information: \n \nDescription of the intended use of the storage system (e.g., export to the grid, \npeak shaving, load shifting, etc.): \n___________________________________________ \n \nProvide the following information for each type of storage device: \n \nA. \nManufacturer and model: ____________________________________  \nB. \nSource Functions  \n(1) \nTotal storage capability:  ___________________ MWh \n(2) \nRated storage discharging power:  ___________________ MW \n(3) \nMaximum storage discharging power:  ________________ MW \n \nIf the maximum storage discharging power is less than the rated \nstorage discharging power, specify the device(s) used to limit the \ndischarge (e.g., inverters, storage control, etc.): \n_____________________ \n(4) \nDischarge duration under rated power:  ____ Hours \n(5) \nDischarge duration under maximum power: ____ Hours \nC. \nCharging Functions \n(1) \nRated storage charging power:  ___________________ MW \n(2) \nMaximum storage charging power:  ________________ MW \n \nIf the maximum storage charging power is less than the rated \nstorage charging power, specify the device(s) used to limit the \ncharging (e.g., inverters, storage control, etc.): \n_____________________ \n(3) \nCharge duration under rated power: ____ Hours \n(4) \nCharge duration under maximum power: ____ Hours"},{"page":149,"startToken":43003,"endToken":43416,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n(5) \nWill the Distribution System be used to charge the storage device \n(Yes/No):  _______ \n \nIf No, specify the device(s) used to prevent charging from the \nDistribution System (e.g., inverters, storage control, etc.): \n_____________________ \n \nD.   Primary frequency response operating range for electric storage  resources             \n(xx % of the upper charging limit of each storage component) \n \n(1) \nMinimum State of Charge:  _____________ \n \n(2) \nMaximum State of Charge: _____________ \n \n14. \nLoad Flow and Dynamic Models: \n \nThe WECC Data Preparation Manual for Power Flow Base Cases and Dynamic Stability \nData has established power flow and dynamic modeling requirements for generation \nprojects in WECC base cases.  In general, if the aggregate sum of generation on a bus \nexceeds 10 MVA, it should not be netted.  Furthermore, the total netted generation in an \narea should not exceed five percent of the area’s total generation.  Based on current \nWECC modeling requirements, the following information will be required for all \ngeneration projects whose net capacity is greater than 10 MVA.  The following \ninformation may also be required for generation projects less than 10 MVA on a case-\nby-case basis, based on the amount of generation in the area of the requested Point of \nInterconnection.  Each Large Load shall provide the load flow and dynamic model data \nspecified in Item C of this section, in addition to the information in Items A and B for any \nco-located generation. \n \nA.   \nProvide load flow model for the generating plant and its interconnection \nfacilities in GE PSLF *.epc format, including new buses, generators, \ntransformers, interconnection facilities. An equivalent model is required for \nthe plant with generation collector systems.  This data should reflect the \ntechnical data provided in this Attachment A. \n \nB. \nFor each generator, governor, exciter, power system stabilizer, WTG, or \ninverter based generator, select the appropriate dynamic models from the \nGeneral Electric PSLF Program Manual and provide the required input \ndata. Include any user written *.p EPCL files to simulate inverter based \nplants’ dynamic responses (typically needed for inverter based PV/wind \nplants).  Provide a completed *.dyd file that contains the information \nspecified in this section.   \n \nC.   For Large Loads, the Large Load Interconnection Customer shall provide a \nvalidated user-defined root mean squared (RMS) positive sequence \ndynamics model and an appropriately parameterized generic library RMS \npositive sequence dynamics model, including model block diagram of the \ninverter control and plant control systems, as defined by a model \napproved by the Western Electricity Coordinating Council, that"},{"page":150,"startToken":43416,"endToken":43827,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \ncorresponds to Large Load Interconnection Customer’s Generating \nFacility. Refer to the PSLF User Manual and available NERC \ndocumentation on the use and parameterization of model parameters. \nEnter “N/A” for any field that is not applicable (e.g., distributed generation \ndata). If multiple motors or Type 1 loads need to be represented, copy the \nrelevant fields and identify the applicable parameters. \n \nThe GE PSLF manual is available upon request from GE.  There are links within the GE \nPSLF User’s Manual to detailed descriptions of specific models, a definition of each \nparameter, a list of the output channels, explanatory notes, and a control system block \ndiagram.  In addition, GE PSLF modeling information and various modeling guidelines \ndocuments have been prepared by the WECC Modeling and Validation Work Group.  \nThis information is available on the WECC website (www.wecc.org).  \n \nIf you require assistance in developing the models, we suggest you contact GE \nVernova. Accurate models are important to obtain accurate study results. Costs \nassociated with any changes in facility requirements that are due to differences between \nmodel data provided by the generation developer and the actual generator test data, \nmay be the responsibility of the generation developer. \n \n15.       MODELS FOR NON-SYNCHRONOUS GENERATORS \nFor a non-synchronous Generating Facility, Large Load Interconnection Customer shall \nprovide (1) a validated user-defined root mean squared (RMS) positive sequence \ndynamics model; (2) an appropriately parameterized generic library RMS positive \nsequence dynamics model, including model block diagram of the inverter control and \nplant control systems, as defined by a model approved by the Western Electricity \nCoordinating Council, that corresponds to Large Load Interconnection Customer’s \nGenerating Facility; and (3) if applicable, a validated electromagnetic transient model if \nDistribution Provider performs an electromagnetic transient study as part of the \ninterconnection study process.  A user-defined model is a set of programming code \ncreated by equipment manufacturers or developers that captures the latest features of \ncontrollers that are mainly software based and represents the entities’ control strategies \nbut does not necessarily correspond to any generic library model.  Large Load \nInterconnection Customer must also demonstrate that the model is validated by \nproviding evidence that the equipment behavior is consistent with the model behavior \n(e.g., an attestation from Large Load Interconnection Customer that the model \naccurately represents the entire Generating Facility; attestations from each equipment \nmanufacturer that the user defined model accurately represents the component of the \nGenerating Facility; or test data)."},{"page":151,"startToken":43827,"endToken":44108,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \nATTACHMENT 2 to LLIP \n \nLARGE LOAD STUDY PROCESS  AGREEMENT \n \n \n \nTHIS LARGE LOAD STUDY PROCESS  AGREEMENT (“AGREEMENT”) is \nmade and entered into                               by and \nbetween                                                    , a                                      organized and \nexisting under the laws of the State of                                    , (\"Large Load \nInterconnection Customer\") and _________________________ a                                   \nexisting under the laws of the State of____________, (\"Participating TO\").  Large Load \nInterconnection Customer and Participating TO each may be referred to as a \"Party,\" or \ncollectively as the \"Parties.\" \n \nRECITALS \n \n \nWHEREAS, Large Load Interconnection Customer is proposing to develop a \nLarge Load or  capacity addition to an existing Large Load consistent with the \nInterconnection Request submitted by Large Load Interconnection Customer dated \n____                    ; and \n \n \nWHEREAS, Large Load Interconnection Customer desires to interconnect the \nLarge Load  with the Participating TO’s Transmission System pursuant to the LLIP; and \n \nWHEREAS, the Large Load Interconnection Customer has requested \nParticipating TO to perform Interconnection Studies to assess the system impact of \ninterconnecting the Large Load to the Participating TO’s Transmission System, and any \nAffected Systems and to specify and estimate the cost of the equipment, engineering, \nprocurement and construction work needed on the Participating TO’s electric system to \nphysically and electrically connect the Large Load to the Participating TO’s \nTransmission System in accordance with Good Utility Practice; \n \n \nNOW, THEREFORE, in consideration of and subject to the mutual covenants \ncontained herein the Parties agree as follows: \n \n \n1.0 \nWhen used in this Agreement, with initial capitalization, the terms \nspecified shall have the meanings indicated in Participating TO’s FERC \napproved LLIP. \n \n \n2.0 \nLarge Load Interconnection Customer elects and Participating TO shall \ncause to be performed Interconnection Studies consistent with Section 4 \nof the LLIP."},{"page":152,"startToken":44108,"endToken":44509,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n3.0 \nThe scope of the Interconnection Studies shall be subject to the \nassumptions set forth in Appendix A to this Agreement. \n \n \n4.0 \nThe Interconnection Studies will be based upon the technical information \nprovided by Large Load Interconnection Customer in the Interconnection \nRequest, as may be modified as the result of the Scoping Meeting, subject \nto any modifications in accordance with LLIP Section 4.6.1.6.  \nParticipating TO reserves the right to request additional technical \ninformation from Large Load Interconnection Customer as may reasonably \nbecome necessary consistent with Good Utility Practice during the course \nof the Interconnection Studies.  If Large Load Interconnection Customer \nmodifies its designated Point of Interconnection, Interconnection Request, \nor the technical information provided therein is modified, the \nInterconnection Studies may be modified as specified in the LLIP. \n \n \n5.0 \nThe Interconnection Study report for each Interconnection Study shall \nprovide the information specified in the LLIP. \n \n6.0 \nLarge Load Interconnection Customer shall increase the Commercial \nReadiness Deposit after issuance of the final Large Load Interconnection  \nStudy report in accordance with LLIP Section 4.6.1.4.  \n \n \n7.0 \nUpon completion of the Interconnection Studies, Participating TO shall \ncharge and Large Load Interconnection Customer shall pay the actual \ncosts of the Interconnection Studies pursuant to LLIP Section 3.2.3.3. \n \n8. 0     The Participating TO may provide copies of the Interconnection Studies \nresults to the ISO, an Affected System Operator and the Western \nElectricity Coordinating Council.  Requests for review and input from any \nAffected System Operators or the Western Electricity Coordinating Council \nmay arrive at any time prior to interconnection. \n \n9.0 \nSubstantial portions of technical data and assumptions used to perform \nthe Interconnection Studies, such as system conditions, existing and \nplanned generation, and unit modeling, may change after the Participating \nTO provides the Interconnection Studies results to the Large Load \nInterconnection Customer.  Interconnection Studies results will reflect \navailable data at the time the Participating TO provides the \nInterconnection Study reports to the Large Load Interconnection \nCustomer.  The Participating TO shall not be responsible for any \nadditional costs for Participating TO’s  Interconnection Facilities, \nDistribution Upgrades and Large Load Network Upgrades, including, \nwithout limitation, costs of new or additional facilities, system upgrades, or \nschedule changes, that may be incurred by the Large Load \nInterconnection Customer as a result of changes in such data and \nassumptions."},{"page":153,"startToken":44509,"endToken":44897,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n10.0 The Participating TO shall maintain records and accounts of all costs \nincurred in performing the Interconnection Studies in sufficient detail to \nallow verification of all costs incurred, including associated overheads.  \nThe Large Load Interconnection Customer shall have the right, upon \nreasonable notice, within a reasonable time at the Participating TO’s \noffices and at its own expense, to audit the Participating TO’s records as \nnecessary and as appropriate in order to verify costs incurred by the \nParticipating TO.  Any audit requested by the Large Load Interconnection \nCustomer shall be completed, and written notice of any audit dispute \nprovided to the Participating TO, within one hundred eighty (180) Calendar \nDays following receipt by the Large Load Interconnection Customer of the \nParticipating TO’s  notification of the final costs of the Interconnection \nStudies. \n \n11.0 In accordance with LLIP Section 3.11, the Large Load Interconnection \nCustomer may withdraw its Interconnection Request at any time by written \nnotice to the Participating TO.  Upon receipt of such notice, this \nAgreement shall terminate, subject to the requirements of LLIP Sections \n4.2.1.1 and 7.1. \n \n12.0 This Agreement shall become effective upon the date the fully executed \nAgreement is received by the Participating TO.  If the Participating TO \ndoes not receive the fully executed Agreement pursuant to LLIP Section \n4.4, then the Interconnection Request will be deemed withdrawn upon the \nLarge Load Interconnection Customer’s receipt of written notice by the \nDistribution Provider pursuant to LLIP Section 3.11. \n \n \n13.0 Miscellaneous.   \n \n \n13.1 Dispute Resolution.   \n \n \n13.1.1 Submission.  In the event either Party has a dispute, or asserts a claim, \nthat arises out of or in connection with the TSRA, the LLIP, or their \nperformance, such Party (the \"disputing Party\") shall provide the other \nParty with written notice of the dispute or claim (\"Notice of Dispute\").  \nSuch dispute or claim shall be resolved in accordance with the Dispute \nResolution Procedures set forth in Section 14 of the TO Tariff. \n \n13.2 Confidentiality.  Confidential Information shall be treated in accordance \nwith LLIP Section 7.1. \n \n13.3 Binding Effect.  This Agreement and the rights and obligations hereof, \nshall be binding upon and shall inure to the benefit of the successors and \nassigns of the Parties hereto."},{"page":154,"startToken":44897,"endToken":45363,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n13.4 Conflicts.  In the event of a conflict between the body of this Agreement \nand any attachment, appendices or exhibits hereto, the terms and \nprovisions of the body of this Agreement shall prevail and be deemed the \nfinal intent of the Parties.   \n \n13.5 Rules of Interpretation.  This Agreement, unless a clear contrary intention \nappears, shall be construed and interpreted as follows:  (1) the singular \nnumber includes the plural number and vice versa;  (2) reference to any \nperson includes such person’s successors and assigns but, in the case of \na Party, only if such successors and assigns are permitted by this \nAgreement, and reference to a person in a particular capacity excludes \nsuch person in any other capacity or individually; (3) reference to any \nagreement (including this Agreement), document, instrument or tariff \nmeans such agreement, document, instrument, or tariff as amended or \nmodified and in effect from time to time in accordance with the terms \nthereof and, if applicable, the terms hereof; (4) reference to any applicable \nlaws and regulations means such applicable laws and regulations as \namended, modified, codified, or reenacted, in whole or in part, and in \neffect from time to time, including, if applicable, rules and regulations \npromulgated thereunder; (5) unless expressly stated otherwise, reference \nto any Article, Section or Appendix means such Article or Section of this \nAgreement or such Appendix to this Agreement, or such Section of the \nLLIP or such Attachment to the LLIP, as the case may be; (6) “hereunder”, \n“hereof”, “herein”, “hereto” and words of similar import shall be deemed \nreferences to this Agreement as a whole and not to any particular Article \nSection, or other provision hereof or thereof; (7) “including” (and with \ncorrelative meaning “include”) means including without limiting the \ngenerality of any description preceding such term; and (8) relative to the \ndetermination of any period of time, “from” means “from and including”, \n“to” means “to but excluding” and “through” means “through and \nincluding”.   \n \n13.6 Entire Agreement.  This Agreement, including all Appendices and \nSchedules attached hereto, constitutes the entire agreement between the \nParties with reference to the subject matter hereof, and supersedes all \nprior and contemporaneous understandings or agreements, oral or written, \nbetween the Parties with respect to the subject matter of this Agreement.  \nThere are no other agreements, representations, warranties, or covenants \nwhich constitute any part of the consideration for, or any condition to, any \nParty’s compliance with its obligations under this Agreement.  \n \n13.7 No Third Party Beneficiaries.  This Agreement is not intended to and does \nnot create rights, remedies, or benefits of any character whatsoever in \nfavor of any persons, corporations, associations, or entities other than the \nParties, and the obligations herein assumed are solely for the use and"},{"page":155,"startToken":45363,"endToken":45787,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nbenefit of the Parties, their successors in interest and, where permitted, \ntheir assigns. \n \n13.8 Waiver.  The failure of a Party to this Agreement to insist, on any \noccasion, upon strict performance of any provision of this Agreement will \nnot be considered a waiver of any obligation, right, or duty of, or imposed \nupon, such Party.  \n \nAny waiver at any time by either Party of its rights with respect to this \nAgreement shall not be deemed a continuing waiver or a waiver with \nrespect to any other failure to comply with any other obligation, right, or \nduty of this Agreement.  Termination or default of this Agreement for any \nreason by the Large Load Interconnection Customer shall not constitute a \nwaiver of the Large Load Interconnection Customer's legal rights to obtain \nan interconnection from the Participating TO.  Any waiver of this \nAgreement shall, if requested, be provided in writing. \n \n13.9 Headings.  The descriptive headings of the various Articles and Sections \nof this Agreement have been inserted for convenience of reference only \nand are of no significance in the interpretation or construction of this \nAgreement   \n \n13.10 Multiple Counterparts.  This Agreement may be executed in two or more \ncounterparts, each of which is deemed an original but all constitute one \nand the same instrument.  \n \n13.11 Amendment.  The Parties may by mutual agreement amend this \nAgreement by a written instrument duly executed by both of the Parties. \n \n13.12 Modification by the Parties.  The Parties may by mutual agreement amend \nthe Appendices to this Agreement by a written instrument duly executed \nby both of the Parties.  Such amendment shall become effective and a \npart of this Agreement upon satisfaction of all applicable laws and \nregulations. \n \n13.13 Reservation of Rights.  The Participating TO shall have the right to make a \nunilateral filing with FERC to modify this Agreement with respect to any \nrates, terms and conditions, charges, classifications of service, rule or \nregulation under section 205 or any other applicable provision of the \nFederal Power Act and FERC’s rules and regulations thereunder, and \nLarge Load Interconnection Customer shall have the right to make a \nunilateral filing with FERC to modify this Agreement pursuant to section \n206 or any other applicable provision of the Federal Power Act and \nFERC’s rules and regulations thereunder; provided that each Party shall \nhave the right to protest any such filing by another Party and to participate \nfully in any proceeding before FERC in which such modifications may be"},{"page":156,"startToken":45787,"endToken":46142,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \nconsidered.  Nothing in this Agreement shall limit the rights of the Parties \nor of FERC under sections 205 or 206 of the Federal Power Act and \nFERC’s rules and regulations thereunder, except to the extent that the \nParties otherwise mutually agree as provided herein.  \n \n13.14 No Partnership.  This Agreement shall not be interpreted or construed to \ncreate an association, joint venture, agency relationship, or partnership \nbetween the Parties or to impose any partnership obligation or partnership \nliability upon any Party.  No Party shall have any right, power or authority \nto enter into any agreement or undertaking for, or act on behalf of, or to \nact as or be an agent or representative of, or to otherwise bind, another \nParty.   \n \n13.15 Assignment.  This Agreement may be assigned by a Party only with the \nwritten consent of the other Party; and provided further that the Large \nLoad Interconnection Customer shall have the right to assign this \nAgreement, without the consent of the other Party, for collateral security \npurposes to aid in providing financing for the Large Load, provided that the \nLarge Load Interconnection Customer will require any secured party, \ntrustee or mortgagee to notify the other Party of any such assignment.  \nAny financing arrangement entered into by the Large Load Interconnection \nCustomer pursuant to this Section will provide that prior to or upon the \nexercise of the secured party’s, trustee’s or mortgagee’s assignment rights \npursuant to said arrangement, the secured creditor, the trustee or \nmortgagee will notify the other Party of the date and particulars of any \nsuch exercise of assignment right(s).  Any attempted assignment that \nviolates this Section is void and ineffective.  Any assignment under this \nAgreement shall not relieve a Party of its obligations, nor shall a Party’s \nobligations be enlarged, in whole or in part, by reason thereof.  Where \nrequired, consent to assignment will not be unreasonably withheld, \nconditioned or delayed. \n \n \nIN WITNESS THEREOF, the Parties have caused this Agreement to be duly \nexecuted by their duly authorized officers or agents on the day and year first above \nwritten."},{"page":157,"startToken":46142,"endToken":46174,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n[Insert name of Participating TO] \n \nBy: \n                                                       \n \n \n \nName: ___________________________ \n \n \nTitle:                                                        \n \n  \n  \nDate:                                                         \n \n \n \n[Insert name of Large Load Interconnection Customer] \n \n \nBy: \n                                                       \n \n \nName:  __________________________ \n \nTitle:                                                        \n \n \nDate:  ___________________________"},{"page":158,"startToken":46174,"endToken":46268,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \nAppendix A  \nLarge Load Study Process \n Agreement \n \n \nASSUMPTIONS USED IN CONDUCTING THE  \nLARGE LOAD INTERCONNECTION STUDY \n \n \n \nThe Interconnection System Impact Study will be based upon the information set \nforth in the Interconnection Request and agreed upon in the Scoping Meeting held \non_________, subject to any modifications in accordance with LLIP Section 4.6.1.6, \nand the following assumptions: \n \n1. \nDesignation of Point of Interconnection and configuration to be studied. \n \n2. \nScope of the Study. \n \n3. \nOther Assumptions. \n \n4. \nNon-Binding Cost Estimate."},{"page":159,"startToken":46268,"endToken":46303,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \nATTACHMENT 3 to LLIP \n \n \n \n \nTRANSMISSION SECURITY AND RELIABILITY AGREEMENT (TSRA)  \nFOR A LARGE LOAD INTERCONNECTION CUSTOMER \nSUBJECT TO THE LARGE LOAD INTERCONNECTION PROCEDURES"},{"page":160,"startToken":46303,"endToken":46499,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nTABLE OF CONTENTS \n \n \n \n  \nRecitals .......................................................................................  \nArticle 1. Definitions ..................................................................................  \n \nArticle 2. Effective Date, Term, and Termination ....................................  \n2.1 Effective Date .............................................................................  \n2.2 Term of Agreement ....................................................................  \n2.3 Termination Procedures ...........................................................  \n2.3.1 Written Notice .................................................................  \n2.3.2 Default..............................................................................  \n2.3.3  ..........................................................................................  \n2.4 Termination Costs .....................................................................     \n2.5 Disconnection ............................................................................  \n2.6 Survival ......................................................................................  \n \nArticle 3. Regulatory Filings .....................................................................  \n3.1 Filing ...........................................................................................  \n \nArticle 4. Scope of Service ........................................................................  \n4.1 Transmission Interconnection Service ....................................  \n4.1.1 Transmission Service Implications ...............................  \n4.2 Provision of Service ..................................................................  \n4.3 Performance Standards ............................................................  \n4.4 No Transmission Service ..........................................................  \nArticle 5. Interconnection Facilities Engineering, Procurement, and \n \nConstruction ..............................................................................  \n5.1   …………………………………………………………………………. \n5.2 Equipment Procurement ...........................................................  \n5.3 Construction Commencement .................................................  \n5.4 Work Progress ...........................................................................  \n5.5 Information Exchange ...............................................................  \n5.6 Large Load Interconnection Customer’s Interconnection Facilities  \n \n5.6.1 Large Load Interconnection Customer’s Interconnection  \nFacility Specifications ...............................................................  \n5.6.2 Participating TO’s Review ..............................................  \n5.6.3   Large Load Interconnection Customer’s Interconnection \nFacilities Construction \n5.6.4 Large Load Interconnection Customer to Meet Requirements  \nof the Participating TO’s Interconnection Handbook .............  \n5.7 Participating TO’s Interconnection Facilities Construction...  \n5.8 Access Rights ............................................................................  \n5.9 Permits .......................................................................................  \n5.10 Early Construction of Base Case Facilities ............................."},{"page":161,"startToken":46499,"endToken":46749,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n5.11 Taxes  ..........................................................................................  \n5.11.1 Large Load Interconnection Customer Payments Taxable  \n5.11.2 Tax Gross-Up Amount ....................................................  \n5.11.3 Private Letter Ruling or Change or Clarification of Law \n \n5.11.4 Refund .............................................................................  \n5.11.5 Taxes Other Than Income Taxes ...................................  \n5.12 Tax Status ..................................................................................  \n5.13 Modification ...............................................................................  \n5.13.1 General ............................................................................  \n5.13.2 Standards ........................................................................  \n5.13.3 Modification Costs ..........................................................  \n \nArticle 6. Testing and Inspection .............................................................  \n6.1 Pre-Service Commencement Date Testing and Modifications \n \n6.2 Post-Service Commencement Date Testing and Modifications \n \n6.3 Right to Observe Testing ..........................................................  \n6.4 Right to Inspect .........................................................................  \n \nArticle 7. Metering .....................................................................................  \n7.1 General .......................................................................................  \n7.2 Check Meters .............................................................................  \n7.3 Participating TO Retail Metering ..............................................  \n \nArticle 8. Communications .......................................................................  \n8.1 Large Load Interconnection Customer Obligations ...............  \n8.2 Remote Terminal Unit ...............................................................  \n8.3 No Annexation ...........................................................................  \n \nArticle 9. Operations .................................................................................  \n9.1 General .......................................................................................  \n9.2 Participating TO Obligations ....................................................  \n9.3 Large Load Interconnection Customer Obligations ...............  \n9.4 Start-Up and Synchronization ..................................................  \n9.5 Reactive Power ..........................................................................  \n9.5.1 Power Factor Design Criteria .........................................  \n9.6 Outages and Performance Requirements ...............................  \n9.6.1 Outage Coordination \n9.6.2   Ride Through Capability and Performance ..................  \n9.6.3 System Protection and Other Control Requirements ..  \n9.6.3.1 \nSystem Protection Facilities ..................................  \n9.6.4 Requirements for Protection .........................................  \n9.6.5 Power Quality ..................................................................  \n9.7   Operating Limitations Related to FILI \n9.8 Switching and Tagging Rules ...................................................  \n9.9 Disturbance Analysis Data Exchange .....................................  \n9.10 Compliance with ISO Tariff on Large Load Interconnections"},{"page":162,"startToken":46749,"endToken":46944,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nArticle 10. Maintenance ...............................................................................  \n10.1 Participating TO Obligations ....................................................  \n10.2 Large Load Interconnection Customer Obligations ...............  \n10.3 Coordination ..............................................................................  \n10.4 Secondary Systems ..................................................................  \n10.5 Operating and Maintenance Expenses ....................................  \n \nArticle 11. Performance Obligations ..........................................................  \n11.1 Large Load Interconnection Customer Interconnection Facilities  \n11.2 Participating TO’s Interconnection Facilities and Distribution  \n        Upgrades  \n11.3 Large Load Network Upgrades .................................................  \n        11.3.1 Non-Export Co-Located Generation Large Load Network \n         Upgrades……………………………………………………………. \n11.4 Provision of Interconnection Financial Security ....................  \n11.4.1 Participating TO’s Interconnection Facilities and Distribution \nUpgrades…………………………………………………………….. \n11.4.2 Security Requirements \n \nArticle 12. Invoice \n ..................................................................................  \n12.1 General \n ..................................................................................  \n12.2 Final Invoice ...............................................................................  \n12.3 Payment \n ..................................................................................  \n12.4 Disputes  ..................................................................................  \n \nArticle 13. Emergencies ..............................................................................  \n13.1 Definition  ..................................................................................  \n13.2 Obligations .................................................................................  \n \n13.3 Notice \n ..................................................................................  \n \n13.4 Immediate Action .......................................................................  \n13.5 Participating TO Authority ........................................................  \n13.5.1 General ............................................................................  \n13.5.2 Reduction and Disconnection .......................................  \n13.6 Large Load Interconnection Customer Authority ...................  \n13.7 Limited Liability .........................................................................  \n \nArticle 14. Regulatory Requirements and Governing Law .......................  \n14.1 Regulatory Requirements .........................................................  \n14.2 Governing Law ...........................................................................  \n \nArticle 15. Notices \n ..................................................................................  \n15.1 General \n ..................................................................................  \n15.2 Billings and Payments ..............................................................  \n15.3 Alternative Forms of Notice ......................................................  \n15.4 Operations and Maintenance Notice ........................................"},{"page":163,"startToken":46944,"endToken":47122,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nArticle 16. Uncontrollable Force .................................................................  \n16.1 Uncontrollable Force .................................................................  \n \nArticle 17. Default \n ..................................................................................  \n17.1 Default \n ..................................................................................  \n17.1.1 General ............................................................................  \n17.1.2 Right to Terminate ..........................................................  \n \nArticle 18. Indemnity, Consequential Damages and Insurance ...............  \n18.1 Indemnity  ..................................................................................  \n18.1.1 Indemnified Person ........................................................  \n18.1.2 Indemnifying Party .........................................................  \n18.1.3 Indemnity Procedures ....................................................  \n18.2 Consequential Damages ...........................................................  \n18.3 Insurance  ..................................................................................  \n \nArticle 19. Assignment ................................................................................  \n \n19.1 Assignment ................................................................................  \n \n \nArticle 20. Severability ................................................................................  \n \n20.1 Severability ................................................................................  \n \n \nArticle 21. Comparability.............................................................................  \n21.1 Comparability.............................................................................  \n \nArticle 22. Confidentiality ............................................................................  \n22.1 Confidentiality ............................................................................  \n22.1.1 Term .................................................................................  \n22.1.2 Scope ...............................................................................  \n22.1.3 Release of Confidential Information..............................  \n22.1.4 Rights...............................................................................  \n22.1.5 No Warranties .................................................................  \n22.1.6 Standard of Care .............................................................  \n22.1.7 Order of Disclosure ........................................................  \n22.1.8 Termination of Agreement .............................................  \n22.1.9 Remedies .........................................................................  \n22.1.10 Disclosure to FERC, its Staff, or a State .....................  \n \nArticle 23. Environmental Releases ...........................................................  \n \nArticle 24. Information Requirements ........................................................  \n24.1 Information Acquisition ............................................................  \n24.2 Information Submission by Participating TO ..........................  \n24.3 Updated Information Submission by Large Load Interconnection \nCustomer……………………………………………………………………"},{"page":164,"startToken":47122,"endToken":47330,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n24.4 Information Supplementation ...................................................  \n \nArticle 25. Information Access and Audit Rights ......................................  \n25.1 Information Access ...................................................................  \n25.2 Reporting of Non-Uncontrollable Force Events ......................  \n25.3 Audit Rights ...............................................................................  \n25.4 Audit Rights Periods .................................................................  \n25.4.1 Audit Rights Period for Construction-Related Accounts \n \nand Records ....................................................................  \n25.4.2 Audit Rights Period for All Other Accounts and Records \n \n25.5 Audit Results .............................................................................  \n \nArticle 26. Subcontractors ..........................................................................  \n26.1 General \n ..................................................................................  \n26.2 Responsibility of Principal .......................................................  \n26.3 No Limitation by Insurance ......................................................  \n \nArticle 27. Disputes  ..................................................................................  \n27.1 Submission ................................................................................  \n \n \nArticle 28. Representations, Warranties, and Covenants ........................  \n28.1 General \n ..................................................................................  \n28.1.1 Good Standing ................................................................  \n28.1.2 Authority ..........................................................................  \n28.1.3 No Conflict .......................................................................  \n28.1.4 Consent and Approval....................................................  \n \nArticle 29. Miscellaneous ............................................................................  \n29.1 Binding Effect ............................................................................  \n29.2 Conflicts  ..................................................................................  \n29.3 Rules of Interpretation ..............................................................  \n29.4 Entire Agreement .......................................................................  \n29.5 No Third Party Beneficiaries.....................................................  \n29.6 Waiver \n ..................................................................................  \n29.7 Headings  ..................................................................................  \n29.8 Multiple Counterparts ...............................................................  \n29.9 Amendment ................................................................................  \n29.10 Modification by the Parties .....................................................  \n29.11 Reservation of Rights ..............................................................  \n29.12 No Partnership .........................................................................  \n \nAppendix A – Description of Participating TO’s Interconnection Facilities, Large Load \nNetwork Upgrades, Distribution Upgrades, Costs, Payments and Financial Security \n \nAppendix B – Requirements for Mitigation of Potential Cost Shifting Related to New \nTransmission Facilities"},{"page":165,"startToken":47330,"endToken":47371,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nAppendix C – Milestones \n \nAppendix D – Interconnection Details \n \nAppendix E – Flexible Interim Load Interconnection (FILI) Conditions \n \nAppendix F – Security Arrangements Details  \n \nAppendix G – Addresses for Delivery of Notices and Billings"},{"page":166,"startToken":47371,"endToken":47700,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nTRANSMISSION SECURITY AND RELIABILITY AGREEMENT \n \n \n \nTHIS TRANSMISSION SECURITY AND RELIABILITY AGREEMENT (“TSRA” \nor “Agreement”) is made and entered into ______________, by and between \n_______________________, a ____________________________ organized and \nexisting under the laws of the State/Commonwealth of ________________ (“Large \nLoad Interconnection Customer” with a Large Load), and Southern California Edison \nCompany, a corporation organized and existing under the laws of the State of California \n(“Participating TO”).  Large Load Interconnection Customer and Participating TO each \nmay be referred to as a “Party” or collectively as the “Parties.” \n \nRecitals \n \n \nWHEREAS, Participating TO owns the Participating TO’s Transmission System; \nand  \n \n \nWHEREAS, Large Load Interconnection Customer and Participating TO have \nagreed to enter into this Agreement for the purpose of defining certain transmission \nsecurity and reliability terms necessary to interconnect the Large Load with the \nParticipating TO’s Transmission System; \n \n \nNOW, THEREFORE, in consideration of and subject to the mutual covenants \ncontained herein, it is agreed: \n \nArticle 1. \nDefinitions \n \nTerms used in this TSRA with initial capitalization shall have the meanings set forth \nbelow.  The singular of any definition shall include the plural and the plural shall include \nthe singular.  If a term with initial capitalization used herein is not defined, such term \nshall have the meanings ascribed to such term in the LLIP and Section 3 of the TO \nTariff. \n \n \n \nAffiliate shall mean, with respect to a corporation, partnership or other entity, \neach such other corporation, partnership or other entity that directly or indirectly, \nthrough one or more intermediaries, controls, is controlled by, or is under common \ncontrol with, such corporation, partnership or other entity. \n \n \nAncillary Services shall mean those services that are necessary to support the \ntransmission of capacity and energy from resources to loads while maintaining reliable \noperation of the Participating TO’s Transmission System and Distribution System in \naccordance with Good Utility Practice. \n \n \nBreach shall mean the failure of a Party to perform or observe any material term \nor condition of the TSRA."},{"page":167,"startToken":47700,"endToken":48154,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nBreaching Party shall mean a Party that is in Breach of the TSRA. \n \n \nCustomer-Financed Monthly Rate for Non-ISO-Controlled Facilities shall \nhave the meaning as defined in Appendix X of the Transmission Owner Tariff.  The \ncurrently effective Customer-Financed Monthly Rate for Non-ISO-Controlled Facilities is \nas provided in Appendix X of the Transmission Owner Tariff. \n \n \nDefault shall mean the failure of a Breaching Party to cure its Breach in \naccordance with Article 17 of the TSRA. \n \n \nDistribution Upgrades Charge shall mean the monthly charge to the Large \nLoad Interconnection Customer to recover the revenue requirements for the \nParticipating TO’s Distribution Upgrades, calculated as the product of the Customer-\nFinanced Monthly Rate for Non-ISO-Controlled Facilities and the Distribution Upgrades \nCost.  The Distribution Upgrades Charge is provided in Section 5 of Appendix A to the \nTSRA.  The Distribution Upgrades Charge is not applicable to Large Load \nInterconnection Customers who are retail transmission customers of Participating TO.  \n \n \nDistribution Upgrades Completion Date shall mean the date upon which the \nconstruction of the Distribution Upgrades is complete and such facilities are successfully \ntested and ready for service. \n \n \nDistribution Upgrades Cost shall mean the Large Load Interconnection \nCustomer’s allocated share of all costs, excluding One-Time Cost, determined by the \nParticipating TO to be associated with the design, engineering, procurement, \nconstruction and installation of the Distribution Upgrades.  The Distribution Upgrades \nCost is provided in Section 5 of Appendix A to the TSRA. \n \nEmergency Condition shall mean a condition or situation: (1) that in the \njudgment of the Party making the claim is imminently likely to endanger life or property; \nor (2) that, in the case of the ISO, is imminently likely (as determined in a non-\ndiscriminatory manner) to cause a material adverse effect on the security of, or damage \nto, the ISO Controlled Grid or the electric systems of others to which the ISO Controlled \nGrid is directly connected; (3) that, in the case of the Participating TO, is imminently \nlikely (as determined in a non-discriminatory manner) to cause a material adverse effect \non the security of, or damage to, the Participating TO’s Transmission System, \nParticipating TO’s Interconnection Facilities, Distribution System, or the electric systems \nof others to which the Participating TO’s electric system is directly connected; or (4) \nthat, in the case of the Large Load Interconnection Customer, is imminently likely (as \ndetermined in a non-discriminatory manner) to cause a material adverse effect on the \nsecurity of, or damage to, the Large Load or Large Load Interconnection Customer’s \nInterconnection Facilities.  System restoration shall be considered an Emergency \nCondition. \n \n \nHazardous Substances shall mean any chemicals, materials or substances \ndefined as or included in the definition of “hazardous substances,” “hazardous wastes,”"},{"page":168,"startToken":48154,"endToken":48516,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n“hazardous materials,” “hazardous constituents,” “restricted hazardous materials,” \n“extremely hazardous substances,” “toxic substances,” “radioactive substances,” \n“contaminants,” “pollutants,” “toxic pollutants” or words of similar meaning and \nregulatory effect under any applicable Environmental Law, or any other chemical, \nmaterial or substance, exposure to which is prohibited, limited or regulated by any \napplicable Environmental Law. \n \n \nInterconnection Facilities Charge shall mean the monthly charge to the Large \nLoad Interconnection Customer to recover the revenue requirements for the \nParticipating TO’s Interconnection Facilities, calculated as the product of the Customer-\nFinanced Monthly Rate for Non-ISO-Controlled Facilities and the Interconnection \nFacilities Cost.  The Interconnection Facilities Charge is provided in Appendix A to the \nTSRA. \n \nIRS shall mean the Internal Revenue Service. \n \nISO-Identified Network Upgrades shall mean the identified dollar amount \ndetermined by the ISO and identified in Appendix B, where the ISO determines that \nadditional cost-shifting protection is needed concerning shared network upgrade costs. \n \n \nITCC (Income Tax Component of Contribution) shall have the meaning \nassigned to it in Appendix X to the TO Tariff. \n \n \nMetering Equipment shall mean all metering equipment installed or to be \ninstalled at the Large Load and co-located generation, if applicable, pursuant to the \nTSRA at the metering points, including but not limited to instrument transformers, MWh-\nmeters, data acquisition equipment, transducers, remote terminal unit, communications \nequipment, phone lines, and fiber optics. \n \n \nOne-Time Cost shall mean all costs determined by the Participating TO to be \nassociated with the installation of the Participating TO’s Interconnection Facilities and \nDistribution Upgrades which are not capitalized.  The One-Time Cost is provided in \nAppendix A to the TSRA. \n \nParty or Parties shall mean Participating TO, Large Load Interconnection \nCustomer or any combination of the above. \n \n \nRemedial Action Scheme (RAS) shall mean a scheme designed to detect \npredetermined system conditions and automatically take corrective actions that may \ninclude, but are not limited to, adjusting or tripping load or generation. \n \n \nService Commencement Date shall mean the date the Large Load is initially \noperated in parallel with the Participating TO’s Transmission System and transmission \ninterconnection service is provided to the Large Load Interconnection Customer \npursuant to the terms of an executed TSRA."},{"page":169,"startToken":48516,"endToken":48947,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nUncontrollable Force shall mean any act of God, labor disturbance, act of the \npublic enemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, breakage \nor accident to machinery or equipment, any curtailment, order, regulation or restriction \nimposed by governmental, military or lawfully established civilian authorities, or any \nother cause beyond the reasonable control of the Participating TO or Large Load \nInterconnection Customer which could not be avoided through the exercise of Good \nUtility Practice.  An Uncontrollable Force event does not include acts of negligence or \nintentional wrongdoing by the Party claiming Uncontrollable Force. \n \nArticle 2. \nEffective Date, Term, and Termination \n \n2.1 \nEffective Date.  This TSRA shall become effective upon execution by the Parties \nsubject to acceptance by FERC (if applicable), or if filed unexecuted, upon the \ndate specified by FERC.  Participating TO shall promptly file this TSRA with \nFERC upon execution in accordance with Article 3.1, if required. \n \n2.2 \nTerm of Agreement.  Subject to the provisions of Article 2.3, this TSRA shall \nremain in effect for a period of fifteen (15) years from the Effective Date. \n \n2.3 \nTermination Procedures. \n \n \n2.3.1 Written Notice.  This TSRA may be terminated by Large Load \nInterconnection Customer after giving Participating TO ninety (90) \nCalendar Days advance written notice, or by Participating TO notifying \nFERC after the Large Load permanently ceases operation. \n \n \n2.3.2 Default.  Either Party may terminate this TSRA in accordance with Article \n17. \n \n2.3.3 Notwithstanding Articles 2.3.1 and 2.3.2, no termination shall become \neffective until the Parties have complied with all Applicable Laws and \nRegulations applicable to such termination, including the filing with FERC \nof a notice of termination of this TSRA, which notice has been accepted \nfor filing by FERC, and the Large Load Interconnection Customer has \nfulfilled its termination cost obligations under Article 2.4. \n  \n2.4 \nTermination Costs.  If a Party elects to terminate this Agreement pursuant to \nArticle 2.3 above, each Party shall pay all costs incurred (including any cancellation \ncosts relating to orders or contracts for Interconnection Facilities and equipment) or \ncharges assessed by the other Party, as of the date of the other Party’s receipt of such \nnotice of termination, that are the responsibility of the Terminating Party under this \nTSRA.  In the event of termination by a Party, the Parties shall use commercially \nReasonable Efforts to mitigate the costs, damages and charges arising as a \nconsequence of termination.  Upon termination of this TSRA, unless otherwise ordered \nor approved by FERC:"},{"page":170,"startToken":48947,"endToken":49367,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n2.4.1 With respect to any portion of Participating TO’s Interconnection Facilities \nthat have not yet been constructed or installed, Participating TO shall to \nthe extent possible and with Large Load Interconnection Customer’s \nauthorization cancel any pending orders of, or return, any materials or \nequipment for, or contracts for construction of, such facilities; provided that \nin the event Large Load Interconnection Customer elects not to authorize \nsuch cancellation, Large Load Interconnection Customer shall assume all \npayment obligations with respect to such materials, equipment, and \ncontracts, and Participating TO shall deliver such material and equipment, \nand, if necessary, assign such contracts, to Large Load Interconnection \nCustomer as soon as practicable, at Large Load Interconnection \nCustomer’s expense.  To the extent that Large Load Interconnection \nCustomer has already paid Participating TO for any or all such costs of \nmaterials or equipment not taken by Large Load Interconnection \nCustomer, Participating TO shall promptly refund such amounts to Large \nLoad Interconnection Customer, less any costs, including penalties \nincurred by Participating TO to cancel any pending orders of or return \nsuch materials, equipment, or contracts. \n \nIf a Large Load Interconnection Customer terminates this TSRA, it shall be \nresponsible for all costs incurred in association with that Large Load \nInterconnection Customer’s interconnection, including any cancellation \ncosts relating to orders or contracts for Interconnection Facilities and \nequipment, and other expenses including any Distribution Upgrades and \nLarge Load Network Upgrades for which Participating TO has incurred \nexpenses and has not been reimbursed by Large Load Interconnection \nCustomer. \n \n \n2.4.2 Participating TO may, at its option, retain any portion of such materials, \nequipment, or facilities that Large Load Interconnection Customer chooses \nnot to accept delivery of, in which case Participating TO shall be \nresponsible for all costs associated with procuring such materials, \nequipment, or facilities. \n \n \n2.4.3 With respect to any portion of the Interconnection Facilities, and any other \nfacilities already installed or constructed pursuant to the terms of this \nTSRA, Large Load Interconnection Customer shall be responsible for all \ncosts associated with the removal, relocation or other disposition or \nretirement of such materials, equipment, or facilities. \n \n \n2.4.4 Large Load Interconnection Customer will also be responsible for any \nWithdrawal Fee or Exit Fee under Appendix B to this TSRA. \n \n2.5 \nDisconnection.  Upon termination of this TSRA, the Parties will take all \nappropriate steps to disconnect the Large Load from the Participating TO’s \nTransmission System.  All costs required to effectuate such disconnection shall"},{"page":171,"startToken":49367,"endToken":49775,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nbe borne by the terminating Party, unless such termination resulted from the non-\nterminating Party’s Default of this TSRA or such non-terminating Party otherwise \nis responsible for these costs under this TSRA. \n \n2.6 \nSurvival.  This TSRA shall continue in effect after termination to the extent \nnecessary to provide for final billings and payments and for costs incurred \nhereunder, including billings and payments pursuant to this TSRA; to permit the \ndetermination and enforcement of liability and indemnification obligations arising \nfrom acts or events that occurred while this TSRA was in effect; and to permit \neach Party to have access to the lands of the other Party pursuant to this TSRA \nor other applicable agreements, to disconnect, remove or salvage its own \nfacilities and equipment. \n \nArticle 3. \nRegulatory Filings \n \n3.1 \nFiling.  Participating TO shall file this TSRA (and any amendment hereto) with \nFERC and any other appropriate Governmental Authority, if required.  Large \nLoad Interconnection Customer may request that any information provided be \nsubject to the confidentiality provisions of Article 22.  If Large Load \nInterconnection Customer has executed this TSRA, or any amendment thereto, \nLarge Load Interconnection Customer shall reasonably cooperate with \nParticipating TO with respect to such filing and to provide any information \nreasonably requested by Participating TO needed to comply with applicable \nregulatory requirements. \n \nArticle 4. \nScope of Service \n \n4.1 \nTransmission Interconnection Service.  Transmission Interconnection Service \nallows Large Load Interconnection Customer to connect the Large Load to the \nParticipating TO’s Transmission System and be eligible to receive power from \nthe ISO Grid, using the capacity of the ISO Controlled Grid.  To the extent Large \nLoad Interconnection Customer wants to receive Transmission Interconnection \nService, Participating TO shall construct facilities identified in Appendices A and \nD that the Participating TO is responsible to construct. \n \n4.1.1 Transmission Service Implications. Transmission Interconnection \nService does not necessarily provide Large Load Interconnection \nCustomer with the capability to physically receive power from the ISO \nControlled Grid without incurring congestion costs.  In the event of \ntransmission constraints on the ISO Controlled Grid, the Large Load \nInterconnection Customer shall be subject to the applicable congestion \nmanagement procedures in the ISO Tariff in the same manner as all other \nLarge Loads.  The Large Load Interconnection Customer shall be solely \nresponsible for completing all of the necessary arrangements required \nunder the ISO Tariff to be eligible to schedule the power required for the"},{"page":172,"startToken":49775,"endToken":50179,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nLarge Load, except when the Large Load will be a retail transmission \ncustomer of the Participating TO. \n \n4.2 \nProvision of Service.  Participating TO shall provide Transmission \nInterconnection Service for the Large Load at the Point of Interconnection. \n \n4.3 \nPerformance Standards.  Each Party shall perform all of its obligations under \nthis TSRA in accordance with Applicable Laws and Regulations, Applicable \nReliability Standards, and Good Utility Practice, and to the extent a Party is \nrequired or prevented or limited in taking any action by such regulations and \nstandards, such Party shall not be deemed to be in Breach of this TSRA for its \ncompliance therewith.  If such Party is a Participating TO, then that Party shall \namend the TSRA and submit the amendment to FERC for approval. \n \n4.4 \nNo Transmission Service.  The execution of this TSRA does not entitle the \nLarge Load Interconnection Customer to transmission service under the ISO \nTariff and does not convey any right to the Large Load Interconnection Customer \nto receive electricity using the ISO Controlled Grid.   \n \nArticle 5. \nInterconnection Facilities Engineering, Procurement, and \nConstruction \n \n5.1 \nParticipating TO shall design, procure, and construct Participating TO’s \nInterconnection Facilities, Distribution Upgrades, and Large Load Network \nUpgrades, using Reasonable Efforts to complete Participating TO’s \nInterconnection Facilities, Distribution Upgrades, and Large Load Network \nUpgrades by the dates set forth in Appendix C.  Participating TO shall not be \nrequired to undertake any action which is inconsistent with its standard safety \npractices, its material and equipment specifications, its design criteria and \nconstruction procedures, its labor agreements, and Applicable Laws and \nRegulations.  In the event Participating TO reasonably expects that it will not be \nable to complete Participating TO’s Interconnection Facilities, Distribution \nUpgrades, and Large Load Network Upgrades by the specified dates, \nParticipating TO shall promptly provide written notice to Large Load \nInterconnection Customer and shall undertake Reasonable Efforts to meet the \nearliest dates thereafter.  \n \n5.2 \nEquipment Procurement.  The Participating TO shall commence design of \nParticipating TO’s Interconnection Facilities, Distribution Upgrades, or Large \nLoad Network Upgrades and procure necessary equipment as soon as \npracticable after all of the following conditions are satisfied, unless the Parties \notherwise agree in writing: \n \n \n5.2.1 Participating TO has completed the Interconnection Studies pursuant to \nthe LLIP, except for any additional studies performed pursuant to this \nTSRA and in accordance with LLIP Section 4.6.3;"},{"page":173,"startToken":50179,"endToken":50533,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n5.2.2 Participating TO has received written authorization to proceed with design \nand procurement from Large Load Interconnection Customer by the date \nspecified in Appendix C; and \n \n \n5.2.3 Large Load Interconnection Customer has provided security to \nParticipating TO in accordance with Article 11.4 by the dates specified in \nAppendix C. \n \n5.3 \nConstruction Commencement.  Participating TO shall commence construction \nof Participating TO’s Interconnection Facilities, Distribution Upgrades, and Large \nLoad Network Upgrades for which it is responsible as soon as practicable after \nthe following additional conditions are satisfied: \n \n \n5.3.1 Approval of the appropriate Governmental Authority has been obtained for \nany facilities requiring regulatory approval;  \n \n \n5.3.2 Necessary real property rights and rights-of-way have been obtained, to \nthe extent required for the construction of a discrete aspect of Participating \nTO’s Interconnection Facilities, Distribution Upgrades, and Large Load \nNetwork Upgrades; \n \n \n5.3.3 Participating TO has received written authorization to proceed with \nconstruction from Large Load Interconnection Customer by the date \nspecified in Appendix C; and \n \n \n5.3.4 Large Load Interconnection Customer has provided security to \nParticipating TO in accordance with Article 11.4 by the dates specified in \nAppendix C. \n \n5.4 \nWork Progress.  The Parties will keep each other advised periodically as to the \nprogress of their respective design, procurement and construction efforts.  Either \nParty may, at any time, request a progress report from the other Party.  If, at any \ntime, Large Load Interconnection Customer determines that the completion of \nParticipating TO’s Interconnection Facilities will not be required until after the \nspecified Service Commencement Date, Large Load Interconnection Customer \nwill provide written notice to Participating TO of such later date upon which the \ncompletion of Participating TO’s Interconnection Facilities will be required. \n \n5.5 \nInformation Exchange.  As soon as reasonably practicable after the Effective \nDate, the Parties shall exchange information regarding the design and \ncompatibility of the Parties’ Interconnection Facilities and compatibility of the \nInterconnection Facilities with Participating TO’s Transmission System, and shall \nwork diligently and in good faith to make any necessary design changes."},{"page":174,"startToken":50533,"endToken":50928,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n5.6 \nLarge Load Interconnection Customer’s Interconnection Facilities.  Large \nLoad Interconnection Customer shall, at its expense, design, procure, construct, \nown and install the Large Load Interconnection Customer’s Interconnection \nFacilities, as set forth in Appendix A. \n \n \n5.6.1 Large Load Interconnection Customer’s Interconnection Facility \nSpecifications.  Large Load Interconnection Customer shall submit initial \nspecifications for the Large Load Interconnection Customer’s \nInterconnection Facilities, including System Protection Facilities, to \nParticipating TO at least one hundred eighty (180) Calendar Days prior to \nthe Service Commencement Date; and final specifications for review and \ncomment at least ninety (90) Calendar Days prior to the Service \nCommencement Date.  Participating TO shall review such specifications \nto ensure that the Large Load Interconnection Customer’s Interconnection \nFacilities are compatible with the technical specifications, operational \ncontrol, and safety requirements of Participating TO and comment on such \nspecifications within thirty (30) Calendar Days of Large Load \nInterconnection Customer’s submission.  All specifications provided \nhereunder shall be deemed confidential. \n \n \n5.6.2 Participating TO’s Review.  Participating TO’s review of Large Load \nInterconnection Customer’s final specifications shall not be construed as \nconfirming, endorsing, or providing a warranty as to the design, fitness, \nsafety, durability or reliability of the Large Load, or the Large Load \nInterconnection Customer’s Interconnection Facilities.  Large Load \nInterconnection Customer shall make such changes to the Large Load \nInterconnection Customer’s Interconnection Facilities as may reasonably \nbe required by Participating TO, in accordance with Good Utility Practice, \nto ensure that the Large Load Interconnection Customer’s Interconnection \nFacilities are compatible with the technical specifications, operational \ncontrol, and safety requirements of Participating TO. \n \n \n5.6.3 Large Load Interconnection Customer’s Interconnection Facilities \nConstruction.  The Large Load Interconnection Customer’s \nInterconnection Facilities shall be designed and constructed in accordance \nwith Good Utility Practice.  Within one hundred twenty (120) Calendar \nDays after the Service Commencement Date, unless the Parties agree on \nanother mutually acceptable deadline, Large Load Interconnection \nCustomer shall deliver to Participating TO “as-built” drawings, information \nand documents for the Large Load Interconnection Customer’s \nInterconnection Facilities and Large Load, such as: a one-line diagram, a \nsite plan showing the Large Load, co-located generation, if applicable, and \nthe Large Load Interconnection Customer’s Interconnection Facilities, plan \nand elevation drawings showing the layout of the Large Load \nInterconnection Customer’s Interconnection Facilities, a relay functional \ndiagram, relaying AC and DC schematic wiring diagrams and relay"},{"page":175,"startToken":50928,"endToken":51345,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nsettings for all facilities associated with Large Load Interconnection \nCustomer’s transformers, the facilities connecting the Large Load and co-\nlocated generation, if applicable, to the  transformers and the Large Load \nInterconnection Customer’s Interconnection Facilities, and the \nimpedances (determined by factory tests) for the associated transformers \nand the Large Load and co-located generation, if applicable.  The Large \nLoad Interconnection Customer shall provide Participating TO \nspecifications for the excitation system, automatic voltage regulator, Large \nLoad and co-located generation, if applicable, control and protection \nsettings, transformer tap settings, and communications, if applicable. \n \n5.6.4   Large Load Interconnection Customer to Meet Requirements of the \nParticipating TO’s Interconnection Handbook.  The Large Load \nInterconnection Customer shall comply with the Participating TO’s \nInterconnection Handbook.  In the event of a conflict between the terms of \nthis TSRA and the terms of the Participating TO’s Interconnection \nHandbook, the terms in this TSRA shall govern.  \n \n5.7 \nParticipating TO’s Interconnection Facilities Construction.  Participating \nTO’s Interconnection Facilities shall be designed and constructed in accordance \nwith Good Utility Practice.   \n \n5.8 \nAccess Rights.  Upon reasonable notice and supervision by a Party, and \nsubject to any required or necessary regulatory approvals, a Party (“Granting \nParty”) shall furnish at no cost to the other Party (“Access Party”) any rights of \nuse, licenses, rights of way and easements with respect to lands owned or \ncontrolled by the Granting Party, its agents (if allowed under the applicable \nagency agreement), or any Affiliate, that are necessary to enable the Access \nParty to obtain ingress and egress to construct, operate, maintain, repair, test (or \nwitness testing), inspect, replace or remove facilities and equipment to: (i) \ninterconnect the Large Load with the Participating TO’s Transmission System; (ii) \noperate and maintain the Large Load, the Interconnection Facilities and the \nParticipating TO’s Transmission System; and (iii) disconnect or remove the \nAccess Party’s facilities and equipment upon termination of this TSRA.  In \nexercising such licenses, rights of way and easements, the Access Party shall \nnot unreasonably disrupt or interfere with normal operation of the Granting \nParty’s business and shall adhere to the safety rules and procedures established \nin advance, as may be changed from time to time, by the Granting Party and \nprovided to the Access Party.   \n \n5.9 \nPermits.  Participating TO and Large Load Interconnection Customer shall \ncooperate with each other in good faith in obtaining all permits, licenses and \nauthorizations that are necessary to accomplish the interconnection in \ncompliance with Applicable Laws and Regulations."},{"page":176,"startToken":51345,"endToken":51810,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n5.10 Early Construction of Base Case Facilities.  The Large Load Interconnection \nCustomer, in order to maintain its Service Commencement Date, may request \nthat Participating TO construct all or any portion of any Distribution Upgrades or \nLarge Load Network Upgrades required for Large Load Interconnection \nCustomer to be interconnected to the Participating TO’s Transmission System \nwhich are included in the Base Case of the Large Load Interconnection Study for \nLarge Load Interconnection Customer, and which also are required to be \nconstructed for another project, but where such construction is not scheduled to \nbe completed in time to achieve Large Load Interconnection Customer’s Service \nCommencement Date. Upon such request, Participating TO will use Reasonable \nEfforts to advance the construction of such Distribution Upgrades and Large \nLoad Network Upgrades to accommodate such request, provided that Large \nLoad Interconnection Customer commits to pay Participating TO any associated \nexpediting costs.   \n \n5.11 Taxes. \n \n \n5.11.1 Large Load Interconnection Customer Payments Taxable.  The \nParties acknowledge and agree that all payments or property transfers \nmade by Large Load Interconnection Customer to Participating TO for the \ninstallation of Participating TO’s Interconnection Facilities, Distribution \nUpgrades, and, if applicable, Large Load Network Upgrades will be \ntaxable to the Participating TO under the Internal Revenue Code and \napplicable state income tax laws. Participating TO will include in the \namounts charged to Large Load Interconnection Customer a gross-up for \nthe income tax cost consequences of such payments or property \ntransfers, calculated in accordance with Article 5.11.2 (Tax Gross-Up \nAmount) and subject to Article 5.11.3 (Private Letter Ruling or Change or \nClarification of Law) and Article 5.11.4 (Refund).   \n \n \n5.11.2 Tax Gross-Up Amount.  Participating TO will include in the amounts it \ncharges Large Load Interconnection Customer a gross-up for the income \ntax cost consequences of the payments and property the former receives \nfrom the latter. Large Load Interconnection Customer’s liability for the \nincome tax cost consequences of such payments or property transfers \nunder this Article 5.11 shall be calculated on a fully grossed-up basis.  \nExcept as may otherwise be agreed to by the parties, this means that \nLarge Load Interconnection Customer will pay Participating TO, in addition \nto the amount paid for the Interconnection Facilities, Distribution \nUpgrades, and Large Load Network Upgrades, an amount equal to (1) the \ncurrent taxes imposed on Participating TO (“Current Taxes”) on the \nexcess of (a) the gross income realized by Participating TO as a result of \npayments or property transfers made by Large Load Interconnection \nCustomer to Participating TO under this TSRA (without regard to any \npayments under this Article 5.11) (the “Gross Income Amount”) over (b) \nthe present value of future tax deductions for depreciation that will be"},{"page":177,"startToken":51810,"endToken":52249,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \navailable as a result of such payments or property transfers (the “Present \nValue Depreciation Amount”), plus (2) an additional amount sufficient to \npermit Participating TO to receive and retain, after the payment of all \nCurrent Taxes, an amount equal to the net amount described in clause \n(1). \n \nFor this purpose, (i) Current Taxes shall be computed based on \nParticipating TO’s composite federal and state tax rates at the time the \npayments or property transfers are received and Participating TO will be \ntreated as being subject to tax at the highest marginal rates in effect at \nthat time (the “Current Tax Rate”), and (ii) the Present Value Depreciation \nAmount shall be computed by discounting Participating TO’s anticipated \ntax depreciation deductions as a result of such payments or property \ntransfers by Participating TO’s current weighted average cost of capital.  \nThus, the formula for calculating Large Load Interconnection Customer’s \nliability to Participating TO pursuant to this Article 5.11.2 can be expressed \nas follows: (Current Tax Rate x (Gross Income Amount – Present Value of \nTax Depreciation))/(1-Current Tax Rate).  Large Load Interconnection \nCustomer’s estimated tax liability in the event taxes are imposed shall be \nstated in Appendix A. \n \n \n5.11.3 Private Letter Ruling or Change or Clarification of Law.  At Large Load \nInterconnection Customer’s request and expense, Participating TO shall \nfile with the IRS a request for a private letter ruling as to whether any \nproperty transferred or sums paid, or to be paid, by Large Load \nInterconnection Customer to Participating TO under this TSRA are subject \nto federal income taxation.  Large Load Interconnection Customer will \nprepare the initial draft of the request for a private letter ruling, and will \ncertify under penalties of perjury that all facts represented in such request \nare true and accurate to the best of Large Load Interconnection \nCustomer’s knowledge.  Participating TO and Large Load Interconnection \nCustomer shall cooperate in good faith with respect to the submission of \nsuch request. \n \nParticipating TO shall keep Large Load Interconnection Customer fully \ninformed of the status of such request for a private letter ruling and shall \nexecute either a privacy act waiver or a limited power of attorney, in a form \nacceptable to the IRS, that authorizes Large Load Interconnection \nCustomer to participate in all discussions with the IRS regarding such \nrequest for a private letter ruling.  Participating TO shall allow Large Load \nInterconnection Customer to attend all meetings with IRS officials about \nthe request and shall permit Large Load Interconnection Customer to \nprepare the initial drafts of any follow-up letters in connection with the \nrequest."},{"page":178,"startToken":52249,"endToken":52670,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n5.11.4 Refund.  In the event that (a) a private letter ruling is issued to \nParticipating TO which holds that any amount paid or the value of any \nproperty transferred by Large Load Interconnection Customer to \nParticipating TO under the terms of this TSRA is not subject to federal \nincome taxation, (b) any legislative change or administrative \nannouncement, notice, ruling or other determination makes it reasonably \nclear to Participating TO in good faith that any amount paid or the value of \nany property transferred by Large Load Interconnection Customer to \nParticipating TO under the terms of this TSRA is not taxable to \nParticipating TO, (c) any abatement, appeal, protest, or other contest \nresults in a determination that any payments or transfers made by Large \nLoad Interconnection Customer to Participating TO are not subject to \nfederal income tax, or (d) if Participating TO receives a refund from any \ntaxing authority for any overpayment of tax attributable to any payment or \nproperty transfer made by Large Load Interconnection Customer to \nParticipating TO pursuant to this TSRA, Participating TO shall promptly \nrefund to Large Load Interconnection Customer the following: \n \n(i) any payment made by Large Load Interconnection Customer \nunder this Article 5.11 for taxes that is attributable to the amount \ndetermined to be non-taxable, together with interest thereon, \n \n(ii) interest on any amounts paid by Large Load Interconnection \nCustomer to Participating TO for such taxes which Participating TO \ndid not submit to the taxing authority, calculated in accordance with \nthe methodology set forth in FERC’s regulations at 18 CFR \n§35.19a(a)(2)(iii) from the date payment was made by Large Load \nInterconnection Customer to the date Participating TO refunds such \npayment to Large Load Interconnection Customer, and \n \n(iii) with respect to any such taxes paid by Participating TO, any \nrefund or credit Participating TO receives or to which it may be \nentitled from any Governmental Authority, interest (or that portion \nthereof attributable to the payment described in clause (i), above) \nowed to Participating TO for such overpayment of taxes (including \nany reduction in interest otherwise payable by Participating TO to \nany Governmental Authority resulting from an offset or credit); \nprovided, however, that Participating TO will remit such amount \npromptly to Large Load Interconnection Customer only after and to \nthe extent that Participating TO has received a tax refund, credit or \noffset from any Governmental Authority for any applicable \noverpayment of income tax related to Participating TO’s \nInterconnection Facilities."},{"page":179,"startToken":52670,"endToken":53126,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nThe intent of this provision is to leave the Parties, to the extent practicable, \nin the event that no taxes are due with respect to any payment for \nInterconnection Facilities, Distribution Upgrades, and Large Load Network \nUpgrades hereunder, in the same position they would have been in had \nno such tax payments been made. \n \n \n5.11.5 Taxes Other Than Income Taxes.  Upon the timely request by Large \nLoad Interconnection Customer, and at Large Load Interconnection \nCustomer’s sole expense, Participating TO may appeal, protest, seek \nabatement of, or otherwise contest any tax (other than federal or state \nincome tax) asserted or assessed against Participating TO for which \nLarge Load Interconnection Customer may be required to reimburse \nParticipating TO under the terms of this TSRA.  Large Load \nInterconnection Customer shall pay to Participating TO on a periodic \nbasis, as invoiced by Participating TO, Participating TO’s documented \nreasonable costs of prosecuting such appeal, protest, abatement, or other \ncontest.  Large Load Interconnection Customer and Participating TO shall \ncooperate in good faith with respect to any such contest.  Unless the \npayment of such taxes is a prerequisite to an appeal or abatement or \ncannot be deferred, no amount shall be payable by Large Load \nInterconnection Customer to Participating TO for such taxes until they are \nassessed by a final, non-appealable order by any court or agency of \ncompetent jurisdiction.  In the event that a tax payment is withheld and \nultimately due and payable after appeal, Large Load Interconnection \nCustomer will be responsible for all taxes, interest and penalties, other \nthan penalties attributable to any delay caused by Participating TO. \n \n5.12 Tax Status.  Each Party shall cooperate with the other to maintain the other \nParty’s tax status.  Nothing in this TSRA is intended to adversely affect any \nParticipating TO’s tax exempt status with respect to the issuance of bonds.  \n \n5.13 Modification. \n \n \n5.13.1 General.  Either Party may undertake modifications to its facilities.  If a \nParty plans to undertake a modification that reasonably may be expected \nto affect the other Party’s facilities, that Party shall provide to the other \nParty sufficient information regarding such modification so that the other \nParty may evaluate the potential impact of such modification prior to \ncommencement of the work.  Such information shall be deemed to be \nconfidential hereunder and shall include information concerning the timing \nof such modifications and whether such modifications are expected to \ninterrupt the flow of electricity to the Large Load.  The Party desiring to \nperform such work shall provide the relevant drawings, plans, and \nspecifications to the other Party at least ninety (90) Calendar Days in \nadvance of the commencement of the work or such shorter period upon"},{"page":180,"startToken":53126,"endToken":53541,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nwhich the Parties may agree, which agreement shall not unreasonably be \nwithheld, conditioned or delayed. \n \nIn the case of Large Load modifications that do not require Large Load \nInterconnection Customer to submit an Interconnection Request, the \nproposed modification shall be evaluated in accordance with LLIP Section \n4.6.1.6. If the proposed modification is determined not to be a Material \nModification, the Participating TO shall provide, within forty-five (45) \nCalendar Days (or such other time as the Parties may agree), an estimate \nof any additional modifications to the Transmission System, Participating \nTO’s Interconnection Facilities, Distribution Upgrades, or Large Load \nNetwork Upgrades necessitated by such Large Load Interconnection \nCustomer modification and a good faith estimate of the costs thereof. \n \n \n5.13.2 Standards.  Any additions, modifications, or replacements made to a \nParty’s facilities shall be designed, constructed and operated in \naccordance with this TSRA and Good Utility Practice. \n \n \n5.13.3 Modification Costs.  Large Load Interconnection Customer shall not be \ndirectly assigned for the costs of any additions, modifications, or \nreplacements that Participating TO makes to Participating TO’s \nInterconnection Facilities or the Participating TO’s Transmission System to \nfacilitate the interconnection of a third party to Participating TO’s \nInterconnection Facilities or the Participating TO’s Transmission System, \nor to provide transmission interconnection service to a third party under \nthe TO Tariff.  Large Load Interconnection Customer shall be responsible \nfor the costs of any additions, modifications, or replacements to Large \nLoad Interconnection Customer’s Interconnection Facilities that may be \nnecessary to maintain or upgrade such Large Load Interconnection \nCustomer’s Interconnection Facilities consistent with Applicable Laws and \nRegulations, Applicable Reliability Standards or Good Utility Practice. \n \nArticle 6. \nTesting and Inspection \n \n6.1 \nPre-Service Commencement Date Testing and Modifications.  Prior to the \nService Commencement Date, Participating TO shall test Participating TO’s \nInterconnection Facilities, Distribution Upgrades, and Large Load Network \nUpgrades and Large Load Interconnection Customer shall test the Large Load \nand co-located generation (if applicable) and Large Load Interconnection \nCustomer’s Interconnection Facilities to ensure their safe and reliable operation.  \nEach Party shall make any modifications to its facilities that are found to be \nnecessary as a result of such testing.  Large Load Interconnection Customer \nshall bear the cost of all such testing and modifications.  The Large Load \nInterconnection Customer shall not commence initial parallel operation of the \nLarge Load and co-located generation (if applicable) with the Participating TO’s \nTransmission System until the Participating TO provides prior written approval as"},{"page":181,"startToken":53541,"endToken":54023,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nset forth in Appendix C, which approval shall not be unreasonably withheld, for \noperation of such Large Load and co-located generation (if applicable).  Large \nLoad Interconnection Customer shall receive test energy at the Large Load only \nif it has arranged for the receipt of such test energy. \n \n6.2 \nPost-Service Commencement Operation Date Testing and Modifications.  \nEach Party shall at its own expense perform routine inspection and testing of its \nfacilities and equipment in accordance with Good Utility Practice as may be \nnecessary to ensure the continued interconnection of the Large Load and co-\nlocated generation (if applicable) with the Participating TO’s Transmission \nSystem in a safe and reliable manner.  Each Party shall have the right, upon \nadvance written notice, to require reasonable additional testing of the other \nParty’s facilities, at the requesting Party’s expense, as may be in accordance \nwith Good Utility Practice. \n \n6.3 \nRight to Observe Testing.  Each Party shall notify the other Party in advance of \nits performance of tests of its Interconnection Facilities, the Large Load and co-\nlocated generation (if applicable).  The other Party has the right, at its own \nexpense, to observe such testing. \n \n6.4 \nRight to Inspect.  Each Party shall have the right, but shall have no obligation \nto: (i) observe the other Party’s tests and/or inspection of any of its System \nProtection Facilities and other protective equipment; (ii) review the settings of the \nother Party’s System Protection Facilities and other protective equipment; and \n(iii) review the other Party’s maintenance records relative to the Interconnection \nFacilities, the System Protection Facilities and other protective equipment.  A \nParty may exercise these rights from time to time as it deems necessary upon \nreasonable notice to the other Party.  The exercise or non-exercise by a Party of \nany such rights shall not be construed as an endorsement or confirmation of any \nelement or condition of the Interconnection Facilities or the System Protection \nFacilities or other protective equipment or the operation thereof, or as a warranty \nas to the fitness, safety, desirability, or reliability of same.  Any information that a \nParty obtains through the exercise of any of its rights under this Article 6.4 shall \nbe deemed to be Confidential Information and treated pursuant to Article 22 of \nthis TSRA. \n \nArticle 7. \nMetering   \n \n7.1 \nGeneral.  Each Party shall comply with any Applicable Reliability Standards and \nthe Electric Reliability Organization requirements.  The Large Load \nInterconnection Customer shall comply with the provisions of the ISO Tariff \nregarding metering, including Section 10 of the ISO Tariff.  Unless otherwise \nagreed by the Parties, Participating TO may install additional Metering \nEquipment at the Point of Interconnection prior to any operation of the Large \nLoad and shall own, operate, test and maintain such Metering Equipment.  \nPower flows to the Large Load shall be measured at or, at Participating TO’s"},{"page":182,"startToken":54023,"endToken":54468,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \noption, compensated to, the Point of Interconnection.  Large Load \nInterconnection Customer’s access to meter data shall be provided in \naccordance with the ISO Tariff.  Large Load Interconnection Customer shall bear \nall reasonable documented costs associated with the purchase, installation, \noperation, testing and maintenance of the Metering Equipment. \n \n7.2 \nCheck Meters.  Large Load Interconnection Customer, at its option and \nexpense, may install and operate, on its premises and on its side of the Point of \nInterconnection, one or more check meters to check the ISO-polled meters or \nParticipating TO’s meters.  Such check meters shall be for check purposes only \nand shall not be used for the measurement of power flows for purposes of this \nTSRA, except in the case that no other means are available on a temporary \nbasis at the option of the Participating TO.  The check meters shall be subject at \nall reasonable times to inspection and examination by Participating TO or its \ndesignee.  The installation, operation and maintenance thereof shall be \nperformed entirely by Large Load Interconnection Customer in accordance with \nGood Utility Practice. \n \n7.3 \nParticipating TO Retail Metering.  If the Large Load is a retail transmission \ncustomer of the Participating TO, the Participating TO shall install retail revenue \nquality meters and associated equipment, pursuant to the Participating TO’s \napplicable retail tariffs. \n \nArticle 8. \nCommunications \n \n8.1 \nLarge Load Interconnection Customer Obligations.  Large Load \nInterconnection Customer shall maintain satisfactory operating communications \nwith Participating TO’s Transmission System dispatcher or representative \ndesignated by Participating TO.  Large Load Interconnection Customer shall \nprovide standard voice line and dedicated voice line at its control room or central \ndispatch facility through use of either the public telephone system, or a voice \ncommunications system that does not rely on the public telephone system.  \nLarge Load Interconnection Customer shall also provide the dedicated data \ncircuit(s) necessary to provide Large Load Interconnection Customer data to \nParticipating TO as set forth in Appendix F, Security Arrangements Details.  The \ndata circuit(s) shall extend from the Large Load to the location(s) specified by \nParticipating TO.  Any required maintenance of such communications equipment \nshall be performed by Large Load Interconnection Customer.  Operational \ncommunications shall be activated and maintained under, but not be limited to, \nthe following events: system paralleling or separation, scheduled and \nunscheduled shutdowns, equipment clearances, and hourly and daily load data. \n \n8.2 \nRemote Terminal Unit.  Prior to the Service Commencement Date of the Large \nLoad, a Remote Terminal Unit, or equivalent data collection and transfer \nequipment acceptable to the Parties, shall be installed by Large Load \nInterconnection Customer, or by Participating TO at Large Load Interconnection"},{"page":183,"startToken":54468,"endToken":54913,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nCustomer’s expense, to gather accumulated and instantaneous data to be \ntelemetered to the location(s) designated by Participating TO through use of a \ndedicated point-to-point data circuit(s) as indicated in Article 8.1.  The \ncommunication protocol for the data circuit(s) shall be specified by Participating \nTO.  Instantaneous bi-directional analog real power and reactive power flow \ninformation must be telemetered directly to the location(s) specified by \nParticipating TO. The telemetered data shall provide, but not be limited to, \noperational status and real-time consumption to the ISO and Participating TO in \naccordance with the ISO’s standards for direct telemetry and consistent with the \nrequirement for telemetry set forth in Section 7.6.1 of the ISO Tariff.   \n \nEach Party will promptly advise the other Party if it detects or otherwise learns of \nany metering, telemetry or communications equipment errors or malfunctions that \nrequire the attention and/or correction by the other Party.  The Party owning such \nequipment shall correct such error or malfunction as soon as reasonably feasible.  \n \n8.3 \nNo Annexation.  Any and all equipment placed on the premises of a Party shall \nbe and remain the property of the Party providing such equipment regardless of \nthe mode and manner of annexation or attachment to real property, unless \notherwise mutually agreed by the Parties. \n \nArticle 9. \nOperations \n \n9.1 \nGeneral.  Each Party shall comply with Applicable Reliability Standards and the \nElectric Reliability Organization requirements.  Each Party shall provide to the \nother Party all information that may reasonably be required by the other Party to \ncomply with Applicable Laws and Regulations and Applicable Reliability \nStandards. \n \n9.2 \nParticipating TO Obligations. The Participating TO and ISO shall cause the \nParticipating TO’s Transmission System to be operated and controlled in a safe \nand reliable manner and in accordance with this TSRA.  The Participating TO at \nthe Large Load Interconnection Customer’s expense shall cause the Participating \nTO’s Interconnection Facilities to be operated, maintained and controlled in a \nsafe and reliable manner and in accordance with this TSRA.  The Participating \nTO and ISO may provide operating instructions to the Large Load \nInterconnection Customer consistent with this TSRA and Participating TO and \nISO operating protocols and procedures as they may change from time to \ntime.  The Participating TO and ISO will consider changes to their operating \nprotocols and procedures proposed by the Large Load Interconnection \nCustomer. \n  \n9.3 \nLarge Load Interconnection Customer Obligations.  The Large Load \nInterconnection Customer shall at its own expense operate, maintain and control \nthe Large Load, co-located generation (if applicable), and the Large Load \nInterconnection Customer’s Interconnection Facilities, in a safe and reliable"},{"page":184,"startToken":54913,"endToken":55326,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nmanner and in accordance with this TSRA.  The Large Load Interconnection \nCustomer shall operate the Large Load, co-located generation (if applicable), \nand the Large Load Interconnection Customer’s Interconnection Facilities, in \naccordance with all applicable requirements of the Balancing Authority Area of \nwhich it is part, including such requirements as set forth in Appendix D of \nthis TSRA.  Appendix D will be modified to reflect changes to the requirements \nas they may change from time to time.  A Party may request that another Party \nprovide copies of the requirements set forth in Appendix D of this TSRA.  The \nLarge Load Interconnection Customer shall not commence operation of the \nLarge Load or co-located generation (if applicable) in parallel with the \nParticipating TO’s Transmission System until the Participating TO provides prior \nwritten approval, which approval shall not be unreasonably withheld, for \noperation of the Large Load or co-located generation (if applicable). \n \n9.4 \nStart-Up and Synchronization.  Consistent with the Parties’ mutually \nacceptable procedures, Large Load Interconnection Customer is responsible for \nthe proper synchronization of the Large Load and co-located generation (if \napplicable) to Participating TO’s Transmission System. \n \n9.5 \nReactive Power. \n \n. \nPower Factor Design Criteria.   \nLarge Load Interconnection Customer shall design the Large Load to \nmaintain a composite power flow at POI, at a power factor within the range \nof 0.99 leading to 0.97 lagging. This power factor range standard shall be \ndynamic and can be met using, for example, power electronics designed \nto supply this level of reactive capability (taking into account any \nlimitations due to voltage level, real power output, etc.) or fixed and \nswitched capacitors, or a combination of the two. \n \n  \n9.6 \nOutages and Performance Requirements. \n \n \n9.6.1 Outage Coordination.  Large Load Interconnection Customer shall \ncoordinate with Participating TO and provide reasonable notice of any \noutages or maintenance on Large Load Interconnection Customer’s \nInterconnection Facilities consistent with Good Utility Practice.   \n \n \n9.6.2 Ride Through Capability and Performance.  The Participating TO’s \nTransmission System is designed to automatically activate a load-shed \nprogram as required by the Electric Reliability Organization in the event of \nan under-frequency system disturbance.  Large Load Interconnection \nCustomer shall implement under-frequency and over-frequency relay set \npoints, or equivalent electronic controls, for the Large Load as required by \nthe Electric Reliability Organization to ensure frequency “ride through” \ncapability of the ISO Controlled Grid.  Large Load response to frequency \ndeviations of pre-determined magnitudes, both under-frequency and over-"},{"page":185,"startToken":55326,"endToken":55705,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nfrequency deviations, shall be studied and coordinated with Transmission \nProvider in accordance with Good Utility Practice, the latest applicable \nreliability standards, and the Participating TO’s Interconnection Handbook.  \nLarge Load Interconnection Customer shall also implement under-voltage \nand over-voltage relay set points, or equivalent electronic controls, as \nrequired by the Electric Reliability Organization to ensure voltage “ride \nthrough” capability of the Participating TO’s Transmission System in \naccordance with Good Utility Practice, the latest applicable reliability \nstandards, and the Participating TO’s Interconnection Handbook.  The \nterm “ride through” as used herein shall mean the ability of a Large Load \nto stay connected to and synchronized with the ISO Controlled Grid during \nsystem disturbances within a range of under-frequency, over-frequency, \nunder-voltage, and over-voltage conditions, in accordance with Good \nUtility Practice and consistent with any standards and guidelines that are \napplied to other Generating Facilities in the Balancing Authority Area on a \ncomparable basis.  The Large Load must ensure “ride through” capability \nfor abnormal frequency and voltage conditions within the “no trip zone” \ndefined by the Participating TO’s Interconnection Handbook, subject to its \nphysical limitations.   \n \n \n9.6.3 System Protection and Other Control Requirements. \n \n \n \n9.6.3.1 \nSystem Protection Facilities.  Large Load Interconnection \nCustomer shall, at its expense, install, operate and maintain \nSystem Protection Facilities as a part of the Large Load, and co-\nlocated generation, if applicable, or Large Load Interconnection \nCustomer’s Interconnection Facilities.  Participating TO shall install \nat Large Load Interconnection Customer’s expense any System \nProtection Facilities that may be required on Participating TO’s \nInterconnection Facilities or the Participating TO’s Transmission \nSystem as a result of the interconnection of the Large Load and \nLarge Load Interconnection Customer’s Interconnection Facilities. \n \n \n \n9.6.3.2 Each Party’s protection facilities shall be designed and coordinated \nwith other systems in accordance with Applicable Reliability \nStandards, Electric Reliability Organization criteria, and Good Utility \nPractice. \n \n \n \n9.6.3.3 Each Party shall be responsible for protection of its facilities \nconsistent with Good Utility Practice. \n \n \n \n9.6.3.4 Each Party’s protective relay design shall incorporate the \nnecessary test switches to perform the tests required in Article 6.  \nThe required test switches will be placed such that they allow \noperation of lockout relays while preventing breaker failure"},{"page":186,"startToken":55705,"endToken":56102,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nschemes from operating and causing unnecessary breaker \noperations and/or the tripping of the Large Load. \n \n \n \n9.6.3.5  \nEach Party will test, operate and maintain System Protection \nFacilities in accordance with Good Utility Practice and, if applicable, \nthe requirements of the Participating TO’s Interconnection \nHandbook. \n \n \n \n9.6.3.6 \nPrior to the Service Commencement Date, each Party or its \nagent shall perform a complete calibration test and functional trip \ntest of the System Protection Facilities.  At intervals suggested by \nGood Utility Practice, the standards and procedures of the \nParticipating TO, including, if applicable, the requirements of the \nParticipating TO’s Interconnection Handbook, and following any \napparent malfunction of the System Protection Facilities, each \nParty shall perform both calibration and functional trip tests of its \nSystem Protection Facilities.  These tests do not require the tripping \nof the Large Load.  These tests do, however, require that all \nprotective relays and lockout contacts be activated. \n \n \n9.6.4 Requirements for Protection.  In compliance with Good Utility Practice \nand, if applicable, the requirements of the Participating TO’s \nInterconnection Handbook, Large Load Interconnection Customer shall \nprovide, install, own, and maintain relays, circuit breakers and all other \ndevices necessary to remove any fault contribution of the Large Load, or \nco-located generation, if applicable, to any short circuit occurring on the \nParticipating TO’s Transmission System not otherwise isolated by \nParticipating TO’s equipment, such that the removal of the fault \ncontribution shall be coordinated with the protective requirements of the \nParticipating TO’s Transmission System.  Such protective equipment shall \ninclude, without limitation, a disconnecting device or switch with load-\ninterrupting capability located between the Large Load, and co-located \ngeneration, if applicable, and the Participating TO’s Transmission System \nat a site selected upon mutual agreement (not to be unreasonably \nwithheld, conditioned or delayed) of the Parties.  Large Load \nInterconnection Customer shall be responsible for protection of the Large \nLoad, and co-located generation, if applicable, and Large Load \nInterconnection Customer’s other equipment from such conditions as \nnegative sequence currents, over- or under-frequency, sudden load \nrejection, over- or under-voltage, and generator loss-of-field.  Large Load \nInterconnection Customer shall be solely responsible to disconnect the \nLarge Load, or co-located generation, if applicable, and Large Load \nInterconnection Customer’s other equipment if conditions on the \nParticipating TO’s Transmission System could adversely affect the Large \nLoad, or co-located generation, if applicable."},{"page":187,"startToken":56102,"endToken":56472,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n9.6.5 Power Quality.  Neither Party’s facilities shall cause excessive voltage \nflicker nor introduce excessive distortion to the sinusoidal voltage or \ncurrent waves as defined by the latest applicable standards identified in \nthe Participating TO’s Interconnection Handbook.  In the event of a conflict \namong these standards, the alternative Applicable Reliability Standard or \nElectrical Reliability Organization standard shall control. \n \n9.7 \nOperating Limitations Related to FILI. The conditions and limitations \napplicable to Flexible Interim Load Interconnection (FILI) service, including \ncurtailments, shall be specified in Appendix E to this TSRA. \n \n9.8 \nSwitching and Tagging Rules.  Each Party shall provide the other Party a copy \nof its switching and tagging rules that are applicable to the other Party’s activities.  \nSuch switching and tagging rules shall be developed on a non-discriminatory \nbasis.  The Parties shall comply with applicable switching and tagging rules, as \namended from time to time, in obtaining clearances for work or for switching \noperations on equipment. \n \n9.9 \nDisturbance Analysis Data Exchange.  The Parties will cooperate with one \nanother in the analysis of disturbances to either the Large Load or Participating \nTO’s Transmission System by gathering and providing access to any information \nrelating to any disturbance, including information from oscillography, protective \nrelay targets, breaker operations and sequence of events records, and any \ndisturbance information required by Good Utility Practice and Applicable \nReliability Standards. \n \n9.10 Compliance with ISO Tariff on Large Load Interconnections.  Each Large \nLoad must comply, as applicable, with the ISO Tariff provisions in ISO Tariff Section \n25.7, and any complementary technical specifications contained in SCE's \nInterconnection Handbook. \n \nArticle 10. \nMaintenance \n \n10.1 Participating TO Obligations.  Participating TO shall maintain the Participating \nTO’s Transmission System and Participating TO’s Interconnection Facilities in a \nsafe and reliable manner and in accordance with this TSRA. \n \n10.2 Large Load Interconnection Customer Obligations.  Large Load \nInterconnection Customer shall maintain the Large Load and co-located \ngeneration, if applicable, and Large Load Interconnection Customer’s \nInterconnection Facilities in a safe and reliable manner and in accordance with \nthis TSRA. \n \n10.3 Coordination.  The Parties shall confer regularly to coordinate the planning, \nscheduling and performance of preventive and corrective maintenance on the"},{"page":188,"startToken":56472,"endToken":56881,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nLarge Load, and co-located generation, if applicable, and the Interconnection \nFacilities. \n \n10.4 Secondary Systems.  Each Party shall cooperate with the other in the \ninspection, maintenance, and testing of control or power circuits that operate \nbelow 600 volts, AC or DC, including, but not limited to, any hardware, control or \nprotective devices, cables, conductors, electric raceways, secondary equipment \npanels, transducers, batteries, chargers, and voltage and current transformers \nthat directly affect the operation of a Party’s facilities and equipment which may \nreasonably be expected to impact the other Party.  Each Party shall provide \nadvance notice to the other Party before undertaking any work on such circuits, \nespecially on electrical circuits involving circuit breaker trip and close contacts, \ncurrent transformers, or potential transformers. \n \n10.5 Operating and Maintenance Expenses.  Subject to the provisions herein \naddressing the use of facilities by others, and except for operations and \nmaintenance expenses associated with modifications made for providing \ninterconnection or transmission service to a third party and such third party pays \nfor such expenses, Large Load Interconnection Customer shall be responsible \nfor all reasonable expenses including overheads, associated with: (1) owning, \noperating, maintaining, repairing, and replacing Large Load Interconnection \nCustomer’s Interconnection Facilities; and (2) operation, maintenance, repair and \nreplacement of Participating TO’s Interconnection Facilities and Distribution \nUpgrades. \n \nArticle 11. \nPerformance Obligation \n \n11.1 Large Load Interconnection Customer Interconnection Facilities.  Large \nLoad Interconnection Customer shall design, procure, construct, install, own \nand/or control Large Load Interconnection Customer Interconnection Facilities \ndescribed in Appendix A at its sole expense. \n \n11.2 Participating TO’s Interconnection Facilities and Distribution Upgrades.  \nParticipating TO shall design, procure, construct, install, own and/or control the \nParticipating TO’s Interconnection Facilities and Distribution Upgrades described \nin Appendix A at the sole expense of the Large Load Interconnection Customer.  \nThe Large Load Interconnection Customer shall be responsible for funding all \ncosts related to Participating TO’s Interconnection Facilities and Distribution \nUpgrades.  The costs set forth in Appendix A are estimates only and will not \nestablish any cap or maximum cost responsibility limit on the cost responsibility \nof the Large Load Interconnection Customer for the Participating TO’s \nInterconnection Facilities and Distribution Upgrades.  The Large Load \nInterconnection Customer shall be responsible for the actual costs related to \nParticipating TO’s Interconnection Facilities and Distribution Upgrades.  This \nSection 11.2 does not apply to Distribution Upgrades required by Large Load \nInterconnection Customers who are retail transmission customers of participating"},{"page":189,"startToken":56881,"endToken":57336,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nTO, as such facilities and their costs are governed by the Local Regulatory \nAuthority. \n \n11.3 Large Load Network Upgrades.  Participating TO shall design, procure, \nconstruct, install, and own the Large Load Network Upgrades described in \nAppendix A. The Participating TO shall be responsible for securing the costs of \nthe Large Load Network Upgrades attributable to the Large Load subject to the \nfinancial security and payment obligations specified in Appendix B. The costs set \nforth in Appendix A are estimates only. \n \n11.3.1    Non-Export Co-Located Generation Large Load Network Upgrades. \n \nParticipating TO shall design, procure, construct, install, own and/or \ncontrol the Large Load Network Upgrades attributable to non-export co-\nlocated generation, as described in Appendix A, at the sole expense of the \nLarge Load Interconnection Customer. The Large Load Interconnection \nCustomer shall be responsible for funding all costs related to such Large \nLoad Network Upgrades.  The costs set forth in Appendix A are estimates \nonly and will not establish any cap or maximum cost responsibility limit on \nthe cost responsibility of the Large Load Interconnection Customer for the \nLarge Load Network Upgrades. The Large Load Interconnection Customer \nshall be responsible for the actual costs related to Large Load Network \nUpgrades. When the Large Load Interconnection Customer is the \nParticipating TO’s retail transmission customer, the cost assignment and \nresponsibility for Large Load Network Upgrades associated with non-\nexport co-located generation will be made in accordance with the \nParticipating TO’s retail tariffs subject to the Local Regulatory Authority. \n \n11.4 Provision of Interconnection Financial Security.   \n \n \n11.4.1 Participating TO’s Interconnection Facilities and Distribution \nUpgrades. At least thirty (30) Calendar Days prior to the commencement of the \nengineering, design, procurement, installation, or construction of the Participating \nTO’s Interconnection Facilities or Distribution Upgrades, Large Load \nInterconnection Customer shall provide Participating TO, at Large Load \nInterconnection Customer’s option, a guarantee, a surety bond, letter of credit or \nother form of security that is reasonably acceptable to Participating TO, in \naccordance with LLIP Section 4.7.1.  Such security for payment, as specified in \nAppendix A of this TSRA, shall be in an amount sufficient to cover the costs for \nconstructing, procuring and installing the applicable portion of Participating TO’s \nInterconnection Facilities and Distribution Upgrades and shall be reduced on a \ndollar-for-dollar basis for payments made to Participating TO for these purposes.  \nParticipating TO must specify, in Appendix C of this TSRA, the dates for which \nInterconnection Customer must provide additional security for construction of \neach discrete portion of Participating TO’s Interconnection Facilities and \nDistribution Upgrades and Large Load Interconnection Customer must provide \nsuch additional security.    This Section 11.4.1 does not apply to Distribution"},{"page":190,"startToken":57336,"endToken":57716,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nUpgrades required by Large Load Interconnection Customers who are retail \ntransmission customers of participating TO, as such facilities and their costs are \ngoverned by the Local Regulatory Authority. \n \n11.4.2 Security Requirements.   \n \n11.4.2.1 Large Load Network Upgrades and Minimum Annual \nRevenue Contribution. At least thirty (30) Calendar Days prior to \nthe commencement of the engineering, design, procurement, \ninstallation, or construction of the Large Load Network Upgrades \nattributable to the Large Load, the Large Load Interconnection \nCustomer shall provide Interconnection Financial Security to \nmitigate potential cost shifting to other users of the ISO Controlled \nGrid. Such additional security requirements, associated payment \nobligations, and the methodology utilized for calculating such \nrequirements are specified in Appendix B to this TSRA.  \n \n11.4.2.2 Non-Export Co-Located Generation Large Load Network \nUpgrades. At least thirty (30) Calendar Days prior to the \ncommencement of the engineering, design, procurement, \ninstallation, or construction of the Large Load Network Upgrades \nattributable to non-export co-located generation, Large Load \nInterconnection Customer shall provide Participating TO, at Large \nLoad Interconnection Customer’s option, a guarantee, a surety \nbond, letter of credit or other form of security that is reasonably \nacceptable to Participating TO, in accordance with LLIP Section \n4.7.1.  Such financial security shall be in an amount as specified \nby the Participating TO in Appendix A of this TSRA and provided \nby the Large Load Interconnection Customer by the date(s) set \nforth in Appendix C. When the Large Load Interconnection \nCustomer is the Participating TO’s retail transmission customer, \nthe security for Large Load Network Upgrades associated with \nnon-export co-located generation will be made in accordance with \nthe Participating TO’s retail tariffs subject to the Local Regulatory \nAuthority. \n \n        11.4.2.3 ISO-Identified Network Upgrades. At least thirty (30) Calendar \nDays prior to the commencement of the engineering, design, \nprocurement, installation, or construction of the ISO-Identified \nNetwork Upgrades attributable to the Large Load, the Large Load \nInterconnection Customer shall provide financial security to \nmitigate shifting of the cost of the ISO-Identified Network \nUpgrades to other users of the ISO Controlled Grid. Such \nadditional security requirements, associated payment obligations, \nand the methodology utilized for calculating such requirements \nare specified in Appendix B to this TSRA."},{"page":191,"startToken":57716,"endToken":58160,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n11.4.2.4 Large Load Interconnection Customer may avoid duplicative \nInterconnection Financial Security requirements by demonstrating \nto Participating TO’s satisfaction that security or payments \nprovided pursuant to a retail agreement with the Large Load \nOwner satisfies some portion of Large Load Interconnection \nCustomer’s obligations under Articles 11.4.2.1, 11.4.2.2, and \n11.4.2.3.   \n \nArticle 12. \nInvoice \n \n12.1 General.  The Participating TO shall submit to the Large Load Interconnection \nCustomer, on a monthly basis, invoices of amounts due for the preceding month.  \nEach invoice shall state the month to which the invoice applies and fully describe \nthe services and equipment provided.   \n \n12.2 \nFinal Invoice.  Within twelve (12) months after completion of the construction of \nParticipating TO’s Interconnection Facilities and Distribution Upgrades, \nParticipating TO shall provide an invoice of the final cost of the construction of \nParticipating TO’s Interconnection Facilities and Distribution Upgrades, and shall \nset forth such costs in sufficient detail to enable Large Load Interconnection \nCustomer to compare the actual costs with the estimates and to ascertain \ndeviations, if any, from the cost estimates.  Participating TO shall refund to Large \nLoad Interconnection Customer any amount by which the actual payment by \nLarge Load Interconnection Customer for estimated costs exceeds the actual \ncosts of construction within thirty (30) Calendar Days of the issuance of such final \nconstruction invoice. \n \n12.3 Payment.  Invoices shall be rendered to the paying Party at the address \nspecified in Appendix G.  The Party receiving the invoice shall pay the invoice \nwithin thirty (30) Calendar Days of receipt.  All payments shall be made in \nimmediately available funds payable to the other Party, or by wire transfer to a \nbank named and account designated by the invoicing Party.  Payment of invoices \nby either Party will not constitute a waiver of any rights or claims either Party may \nhave under this TSRA. \n \n12.4 Disputes.  In the event of a billing dispute between Participating TO and Large \nLoad Interconnection Customer, Participating TO shall continue to provide \nTransmission Interconnection Service under this TSRA as long as Large Load \nInterconnection Customer: (i) continues to make all payments not in dispute; and \n(ii) pays to Participating TO or into an independent escrow account the portion of \nthe invoice in dispute, pending resolution of such dispute.  If Large Load \nInterconnection Customer fails to meet these two requirements for continuation \nof service, then Participating TO may provide notice to Large Load \nInterconnection Customer of a Default pursuant to Article 17.  Within thirty (30) \nCalendar Days after the resolution of the dispute, the Party that owes money to"},{"page":192,"startToken":58160,"endToken":58618,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nthe other Party shall pay the amount due with interest calculated in accord with \nthe methodology set forth in FERC’s regulations at 18 CFR § 35.19a(a)(2)(iii). \n \nArticle 13. \nEmergencies \n \n13.1 Definition.  \"Emergency Condition\" shall mean a condition or situation: (1) that in \nthe judgment of the Party making the claim is imminently likely to endanger life or \nproperty; or (2) that, in the case of the ISO, is imminently likely (as determined in \na non-discriminatory manner) to cause a material adverse effect on the security \nof, or damage to, the ISO Controlled Grid or the electric systems of others to \nwhich the ISO Controlled Grid is directly connected; (3) that, in the case of the \nParticipating TO, is imminently likely (as determined in a non-discriminatory \nmanner) to cause a material adverse effect on the security of, or damage to, the \nParticipating TO’s Transmission System, Participating TO’s Interconnection \nFacilities, Distribution System, or the electric systems of others to which the \nParticipating TO’s electric system is directly connected; or (4) that, in the case of \nthe Large Load Interconnection Customer, is imminently likely (as determined in \na non-discriminatory manner) to cause a material adverse effect on the security \nof, or damage to, the Large Load or Large Load Interconnection Customer’s \nInterconnection Facilities.   \n \n13.2 Obligations.  Each Party shall comply with the Emergency Condition procedures \nof the ISO, Electric Reliability Organization, Applicable Reliability Standards, \nApplicable Laws and Regulations, and any emergency procedures set forth in \nthis TSRA. \n \n13.3 \nNotice.  Participating TO shall notify Large Load Interconnection Customer \npromptly when it becomes aware of an Emergency Condition that affects \nParticipating TO’s Interconnection Facilities, Distribution System or the ISO \nControlled Grid that may reasonably be expected to affect Large Load \nInterconnection Customer’s operation of the Large Load or Large Load \nInterconnection Customer’s Interconnection Facilities.  Large Load \nInterconnection Customer shall notify Participating TO promptly when it becomes \naware of an Emergency Condition that affects the Large Load or Large Load \nInterconnection Customer’s Interconnection Facilities that may reasonably be \nexpected to affect the Distribution System, ISO Controlled Grid or Participating \nTO’s Interconnection Facilities.  To the extent information is known, the \nnotification shall describe the Emergency Condition, the extent of the damage or \ndeficiency, the expected effect on the operation of Large Load Interconnection \nCustomer’s or Participating TO’s facilities and operations, its anticipated duration \nand the corrective action taken and/or to be taken.  The initial notice shall be \nfollowed as soon as practicable with written notice. \n \n13.4 \nImmediate Action.  Unless, in Large Load Interconnection Customer’s \nreasonable judgment, immediate action is required, Large Load Interconnection \nCustomer shall obtain the consent of Participating TO, such consent to not be"},{"page":193,"startToken":58618,"endToken":59033,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nunreasonably withheld, prior to performing any manual switching operations at \nthe Large Load or Large Load Interconnection Customer’s Interconnection \nFacilities in response to an Emergency Condition either declared by Participating \nTO or ISO or in response to any other emergency condition. \n \n13.5 Participating TO Authority. \n \n \n13.5.1 General.  Participating TO may take whatever actions or inactions with \nregard to the Distribution System and Participating TO’s Transmission \nSystem or Participating TO’s Interconnection Facilities it deems necessary \nduring an Emergency Condition in order to (i) preserve public health and \nsafety, (ii) preserve the reliability of the Distribution System and \nParticipating TO’s Transmission System or Participating TO’s \nInterconnection Facilities, (iii) limit or prevent damage, and (iv) expedite \nrestoration of service. \n \nParticipating TO shall use Reasonable Efforts to minimize the effect of \nsuch actions or inactions on the Large Load or Large Load Interconnection \nCustomer’s Interconnection Facilities.  Participating TO may, on the basis \nof technical considerations, require the Large Load to mitigate an \nEmergency Condition by taking actions necessary and limited in scope to \nremedy the Emergency Condition, including, but not limited to, directing \nLarge Load Interconnection Customer to shut-down the Large Load; \nimplementing a reduction or disconnection pursuant to Article 13.5.2.  \nLarge Load Interconnection Customer shall comply with all of Participating \nTO’s operating instructions concerning Large Load within the \nmanufacturer’s design limitations of the Large Load’s equipment that is in \nservice and physically available for operation at the time, in compliance \nwith Applicable Laws and Regulations. \n \n \n13.5.2 Reduction and Disconnection.  Participating TO may reduce \nTransmission Interconnection Service or disconnect the Large Load or \nLarge Load Interconnection Customer’s Interconnection Facilities, when \nsuch, reduction or disconnection is necessary under Good Utility Practice \ndue to Emergency Conditions.  These rights are separate and distinct from \nany right of curtailment of the ISO pursuant to the ISO Tariff.  When \nParticipating TO can schedule the reduction or disconnection in advance, \nParticipating TO shall notify Large Load Interconnection Customer of the \nreasons, timing and expected duration of the reduction or disconnection.  \nParticipating TO shall coordinate with Large Load Interconnection \nCustomer using Good Utility Practice to schedule the reduction or \ndisconnection during periods of least impact to Large Load \nInterconnection Customer and Participating TO.  Any reduction or \ndisconnection shall continue only for so long as reasonably necessary \nunder Good Utility Practice.  The Parties shall cooperate with each other \nto restore the Large Load, the Interconnection Facilities, and the"},{"page":194,"startToken":59033,"endToken":59426,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nParticipating TO’s Transmission System to their normal operating state as \nsoon as practicable consistent with Good Utility Practice. \n \n13.6 \nLarge Load Interconnection Customer Authority.  Consistent with Good Utility \nPractice and the TSRA and the LLIP, Large Load Interconnection Customer may \ntake actions or inactions with regard to the Large Load or Large Load \nInterconnection Customer’s Interconnection Facilities during an Emergency \nCondition in order to (i) preserve public health and safety, (ii) preserve the \nreliability of the Large Load or Large Load Interconnection Customer’s \nInterconnection Facilities, (iii) limit or prevent damage, and (iv) expedite \nrestoration of service.  Large Load Interconnection Customer shall use \nReasonable Efforts to minimize the effect of such actions or inactions on the \nParticipating TO’s Transmission System and Participating TO’s Interconnection \nfacilities.  Participating TO shall use Reasonable Efforts to assist Large Load \nInterconnection Customer in such actions. \n \n13.7 Limited Liability.  Neither Party shall be liable to the other for any action it takes \nin responding to an Emergency Condition so long as such action is made in good \nfaith and is consistent with Good Utility Practice. \n \nArticle 14. \nRegulatory Requirements and Governing Law \n \n14.1 Regulatory Requirements.  Each Party’s obligations under this TSRA shall be \nsubject to its receipt of any required approval or certificate from one or more \nGovernmental Authorities in the form and substance satisfactory to the applying \nParty, or the Party making any required filings with, or providing notice to, such \nGovernmental Authorities, and the expiration of any time period associated \ntherewith.  Each Party shall in good faith seek and use its Reasonable Efforts to \nobtain such other approvals.   \n \n14.2 Governing Law. \n \n14.2.1 The validity, interpretation and performance of this TSRA and each of its \nprovisions shall be governed by the laws of the state where the Point of \nInterconnection is located, without regard to its conflicts of law principles. \n \n14.2.2 This TSRA is subject to all Applicable Laws and Regulations. \n \n14.2.3 Each Party expressly reserves the right to seek changes in, appeal, or \notherwise contest any laws, orders, rules, or regulations of a \nGovernmental Authority. \n \nArticle 15. \nNotices. \n \n15.1 General.  Unless otherwise provided in this TSRA, any notice, demand or \nrequest required or permitted to be given by either Party to the other and any"},{"page":195,"startToken":59426,"endToken":59858,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \ninstrument required or permitted to be tendered or delivered by either Party in \nwriting to the other shall be effective when delivered and may be so given, \ntendered or delivered, by recognized national courier, or by depositing the same \nwith the United States Postal Service with postage prepaid, for delivery by \ncertified or registered mail, addressed to the Party, or personally delivered to the \nParty, at the address set out in Appendix G. \n \nEither Party may change the notice information in this TSRA by giving five (5) \nBusiness Days written notice prior to the effective date of the change. \n \n15.2 Billings and Payments.  Billings and payments shall be sent to the addresses \nset out in Appendix G. \n \n15.3 Alternative Forms of Notice.  Any notice or request required or permitted to be \ngiven by a Party to the other and not required by this Agreement to be given in \nwriting may be so given by telephone or email to the telephone numbers and \nemail addresses set out in Appendix G. \n \n15.4 Operations and Maintenance Notice.  Each Party shall notify the other Party in \nwriting of the identity of the person(s) that it designates as the point(s) of contact \nwith respect to the implementation of Articles 9 and 10. \n \nArticle 16. \nUncontrollable Force \n \n16.1 Uncontrollable Force. \n \n \n16.1.1 Economic hardship is not considered an Uncontrollable Force event. \n \n16.1.2 Neither Party shall be considered to be in Default with respect to any \nobligation hereunder, including obligations under Article 4, other than the \nobligation to pay money when due, if prevented from fulfilling such \nobligation by Uncontrollable Force.  A Party unable to fulfill any obligation \nhereunder (other than an obligation to pay money when due) by reason of \nan Uncontrollable Force shall give notice and the full particulars of such \nUncontrollable Force to the other Party in writing or by telephone as soon \nas reasonably possible after the occurrence of the cause relied upon.  \nTelephone notices given pursuant to this Article shall be confirmed in \nwriting as soon as reasonably possible and shall specifically state full \nparticulars of the Uncontrollable Force, the time and date when the \nUncontrollable Force occurred and when the Uncontrollable Force is \nreasonably expected to cease.  The Party affected shall exercise due \ndiligence to remove such disability with reasonable dispatch, but shall not \nbe required to accede or agree to any provision not satisfactory to it in \norder to settle and terminate a strike or other labor disturbance. \n \nArticle 17. \nDefault"},{"page":196,"startToken":59858,"endToken":60322,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n17.1 Default  \n \n17.1.1 General.  No Default shall exist where such failure to discharge an \nobligation (other than the payment of money) is the result of an \nUncontrollable Force as defined in this TSRA or the result of an act or \nomission of the other Party.  Upon a Breach, the non-breaching Party shall \ngive written notice of such Breach to the breaching Party.  Except as \nprovided in Article 17.1.2, the breaching Party shall have thirty (30) \nCalendar Days from receipt of the Default notice within which to cure such \nBreach; provided however, if such Breach is not capable of cure within \nthirty (30) Calendar Days, the breaching Party shall commence such cure \nwithin thirty (30) Calendar Days after notice and continuously and \ndiligently complete such cure within ninety (90) Calendar Days from \nreceipt of the Default notice; and, if cured within such time, the Breach \nspecified in such notice shall cease to exist. \n \n17.1.2 Right to Terminate.  If a Breach is not cured as provided in this Article, or \nif a Breach is not capable of being cured within the period provided for \nherein, the non-breaching Party shall have the right to declare a Default \nand terminate this TSRA by written notice at any time until cure occurs, \nand be relieved of any further obligation hereunder and, whether or not \nthat Party terminates this TSRA, to recover from the breaching Party all \namounts due hereunder, plus all other damages and remedies to which it \nis entitled at law or in equity.  The provisions of this Article will survive \ntermination of this TSRA. \n \nArticle 18. \nIndemnity, Consequential Damages and Insurance \n \n18.1 Indemnity.  The Parties shall at all times indemnify, defend, and hold the other \nParty harmless from, any and all damages, losses, claims, including claims and \nactions relating to injury to or death of any person or damage to property, \ndemand, suits, recoveries, costs and expenses, court costs, attorney fees, and \nall other obligations by or to third parties, arising out of or resulting from the other \nParty’s action or inactions of its obligations under this TSRA on behalf of the \nIndemnifying Party, except in cases of gross negligence or intentional \nwrongdoing by the Indemnified Party. \n \n18.1.1 Indemnified Person.  If an Indemnified Person is entitled to \nindemnification under this Article 18 as a result of a claim by a third party, \nand the Indemnifying Party fails, after notice and reasonable opportunity to \nproceed under Article 18.1, to assume the defense of such claim, such \nIndemnified Person may at the expense of the Indemnifying Party contest, \nsettle or consent to the entry of any judgment with respect to, or pay in full, \nsuch claim."},{"page":197,"startToken":60322,"endToken":60809,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n18.1.2 Indemnifying Party.  If an Indemnifying Party is obligated to indemnify \nand hold any Indemnified Person harmless under this Article 18, the \namount owing to the Indemnified Person shall be the amount of such \nIndemnified Person’s actual Loss, net of any insurance or other recovery. \n \n18.1.3 Indemnity Procedures.  Promptly after receipt by an Indemnified Person \nof any claim or notice of the commencement of any action or \nadministrative or legal proceeding or investigation as to which the \nindemnity provided for in Article 18.1 may apply, the Indemnified Person \nshall notify the Indemnifying Party of such fact.  Any failure of or delay in \nsuch notification shall not affect a Party’s indemnification obligation unless \nsuch failure or delay is materially prejudicial to the Indemnifying Party. \n \nThe Indemnifying Party shall have the right to assume the defense thereof \nwith counsel designated by such Indemnifying Party and reasonably \nsatisfactory to the Indemnified Person.  If the defendants in any such \naction include one or more Indemnified Persons and the Indemnifying \nParty and if the Indemnified Person reasonably concludes that there may \nbe legal defenses available to it and/or other Indemnified Persons which \nare different from or additional to those available to the Indemnifying \nParty, the Indemnified Person shall have the right to select separate \ncounsel to assert such legal defenses and to otherwise participate in the \ndefense of such action on its own behalf.  In such instances, the \nIndemnifying Party shall only be required to pay the fees and expenses of \none additional attorney to represent an Indemnified Person or Indemnified \nPersons having such differing or additional legal defenses. \n \nThe Indemnified Person shall be entitled, at its expense, to participate in \nany such action, suit or proceeding, the defense of which has been \nassumed by the Indemnifying Party.  Notwithstanding the foregoing, the \nIndemnifying Party (i) shall not be entitled to assume and control the \ndefense of any such action, suit or proceedings if and to the extent that, in \nthe opinion of the Indemnified Person and its counsel, such action, suit or \nproceeding involves the potential imposition of criminal liability on the \nIndemnified Person, or there exists a conflict or adversity of interest \nbetween the Indemnified Person and the Indemnifying Party, in such event \nthe Indemnifying Party shall pay the reasonable expenses of the \nIndemnified Person, and (ii) shall not settle or consent to the entry of any \njudgment in any action, suit or proceeding without the consent of the \nIndemnified Person, which shall not be reasonably withheld, conditioned \nor delayed. \n \n18.2 Consequential Damages.  In no event shall either Party be liable under any \nprovision of this TSRA for any losses, damages, costs or expenses for any \nspecial, indirect, incidental, consequential, or punitive damages, including but not \nlimited to loss of profit or revenue, loss of the use of equipment, cost of capital,"},{"page":198,"startToken":60809,"endToken":61259,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \ncost of temporary equipment or services, whether based in whole or in part in \ncontract, in tort, including negligence, strict liability, or any other theory of liability; \nprovided, however, that damages for which a Party may be liable to the other \nParty under another agreement will not be considered to be special, indirect, \nincidental, or consequential damages hereunder. \n \n18.3 Insurance.  As indicated below, the designated Party shall, at its own expense, \nmaintain in force throughout the period of this TSRA, and until released by the \nother Party, the following insurance coverages, with insurers rated no less than \nA- under A. M Bests’ current Key Rating Guides and authorized to do business in \nthe state where the Point of Interconnection is located: \n \n18.3.1 Workers’ Compensation Insurance and Employers’ Liability.   The \nParticipating TO and the Large Load Interconnection Customer shall \nmaintain such coverage from the commencement of any construction \nactivities in statutory limits for workers’ compensation coverage, and \ncoverage amounts of one million dollars ($1,000,000) for employer’s \nliability for each employee for bodily injury by accident and one million \ndollars ($1,000,000) for each employee for bodily injury by disease in \naccordance with the laws and regulations of the state in which the \nPoint of Interconnection is located.   \n \n18.3.2 Commercial General Liability Insurance.  The Participating TO and the \nLarge Load Interconnection Customer shall maintain commercial general \nliability insurance coverage commencing within thirty (30) Calendar Days \nof the Effective Date of this TSRA, including coverage for premises and \noperations, bodily injury (including death), personal injury, property \ndamage, products and completed operations coverage, coverage for \nexplosion, collapse and underground hazards, independent contractors \ncoverage, and (i) liability of Participating TO and the Large Load \nInterconnection Customer that would be imposed without the TSRA, or (ii) \nliability assumed by the Participating TO and the Large Load \nInterconnection Customer in a contract or agreement that is an “insured \ncontract” under commercial general liability insurance policy.  Such \ninsurance shall include cross liability or separation of insured clause or \nendorsement. Such insurance shall be in limits of one million dollars \n($1,000,000) per occurrence and two million dollars ($2,000,000) in the \naggregate.   \n \n18.3.3 Business Automobile Liability Insurance.  Prior to the entry of any \nvehicles on any construction site in connection with work done by or on \nbehalf of either Party, each shall provide evidence of coverage of owned \nand non-owned and hired vehicles, trailers or semi-trailers designed for \ntravel on public roads, with a combined single limit of one million dollars \n($1,000,000) per occurrence for bodily injury, including death, and \nproperty damage."},{"page":199,"startToken":61259,"endToken":61701,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n18.3.4 Excess Liability Insurance.  Commencing at the time of entry of any \nperson on its behalf upon any construction site for the Large Load \nNetwork Upgrades, Distribution Upgrades, Interconnection Facilities, or \nLarge Load, the Participating TO and the Large Load Interconnection \nCustomer shall maintain excess liability insurance over and above the \nEmployers’ Liability, Commercial General Liability, and Business \nAutomobile Liability Insurance coverage, with a limit of five million dollars \nper MW, of Large Load capacity, rounded up to the nearest MW, per \noccurrence, up to a maximum of twenty-five million dollars ($25,000,000) \nper occurrence/twenty-five million dollars ($25,000,000) aggregate.  The \nrequirements of Articles 18.3.2 and 18.3.4 may be met by any combination \nof general and excess liability insurance. \n \n18.3.5 As required in this Article 18.3, the Commercial General Liability \nInsurance, Business Automobile Liability Insurance and Excess Liability \nInsurance policies shall include the other Party identified in the articles \nabove, its parent, their subsidiaries, respective directors, officers, agents, \nservants and employees (\"Other Party Group\") as additional insured.  All \npolicies shall contain provisions whereby the insurers waive all rights of \nsubrogation in accordance with the provisions of this TSRA against the \nOther Party Group.  If any Party can reasonably demonstrate that \ncoverage policies containing provisions for insurer waiver of subrogation \nrights, or advance notice are not commercially available, then the Parties \nshall meet and confer and mutually determine to (i) establish replacement \nor equivalent terms in lieu of subrogation or notice or (ii) waive the \nrequirements that coverage(s) include such subrogation provision or \nrequire advance written notice from such insurers. \n \n18.3.6 As required in this Article 18.3, the Commercial General Liability Insurance \nand Business Automobile Liability Insurance policies shall contain \nprovisions that specify that the policies are primary and non-contributory.  \nEach Party shall be responsible for its respective deductibles or self-\ninsured retentions. \n \n18.3.7 As required in this Article 18.3, the Commercial General Liability \nInsurance, Business Automobile Liability Insurance and Excess Liability \nInsurance policies, if written on a Claims First Made Basis, shall be \nmaintained in full force and effect for two (2) years after termination of this \nTSRA, which coverage may be in the form of extended reporting period \ncoverage if agreed by the Parties. \n \n18.3.8 If the activities of the Large Load Interconnection Customer are being \nconducted through the actions of an Affiliate, then the Large Load \nInterconnection Customer may satisfy the insurance requirements of this \nArticle 18.3 by providing evidence of insurance coverage carried by such"},{"page":200,"startToken":61701,"endToken":62215,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nAffiliate, together with the Large Load Interconnection Customer’s written \nrepresentation to the Participating TO that the insured Affiliate is \nconducting all of the necessary pre-construction work. Within thirty (30) \ncalendar days prior to the entry of any person on behalf of the Large Load \nInterconnection Customer onto any construction site to perform work \nrelated to the Interconnection Facilities or Large Load, the Large Load \nInterconnection Customer shall replace any evidence of Affiliate insurance \nwith evidence of such insurance carried by the Large Load Interconnection \nCustomer.  \n \n18.3.9 Thirty (30) Calendar Days prior to the start of any work at the construction \nsite related to Interconnection Facilities or Large Load under this TSRA, \nand as soon as practicable after the end of each fiscal year or at the \nrenewal of the insurance policy and in any event within ninety (90) \nCalendar Days thereafter, each Party shall provide a certificate of \ninsurance for all insurance required in this TSRA, executed by each \ninsurer or by an authorized representative of each insurer. \n \n18.3.10 Notwithstanding the foregoing, each Party may self-insure (a) to meet \nthe insurance requirements of Article 18.3.1, to the extent that it maintains \na self-insurance program and is a qualified self-insurer within the state in \nwhich the Point of Interconnection is located, under the laws and \nregulations of such state; and (b) to meet the insurance requirements of \nArticles 18.3.2 through 18.3.4 to the extent it maintains a self-insurance \nprogram; provided that, such Party is organized under the laws of the \nUnited States or a political subdivision thereof and such Party’s rating for \nits senior unsecured, long-term debt (not supported by third party credit \nenhancements) or if such Party does not have a rating for its senior \nunsecured long-term debt, then the rating then assigned to such Party by \nStandard & Poor’s Rating Group (a division of McGraw-Hill, Inc.) or its \nsuccessor (“S&P”) or Moody’s Investor Services, Inc. or its successor \n(“Moody’s”) is (i) if rated by S&P and Moody’s is rated at least ”BBB-” by \nS&P and “Baa3\" by Moody’s, or (ii) if rated by only one of S&P or Moody’s, \nrated at least ”BBB-” by S&P or “Baa3” by Moody’s, and (iii) that its self-\ninsurance program meets the insurance requirements of Articles 18.3.2 \nthrough 18.3.4.  For any period of time that a Party’s senior unsecured, \nlong-term debt is unrated by S&P or Moody’s, or its unsecured long-term \ndebt or the rating assigned to such Party does not meet the requirements \nin (ii), such Party shall comply with the insurance requirements applicable \nto it under Articles 18.3.2 through 18.3.4.  In the event that a Party is \npermitted to self-insure pursuant to this Article 18.3.10, it shall notify the \nother Party that it meets the requirements to self-insure and that its self-\ninsurance program meets the insurance requirements in a manner \nconsistent with that specified in Article 18."},{"page":201,"startToken":62215,"endToken":62624,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n18.3.11 The Parties agree to report to each other in writing as soon as practical \nwhenever an accident or incident occurs resulting in serious injuries to any \nperson, including death, and any third-party property damage greater than \n$500,000 arising out of this Agreement. \n \nArticle 19. \nAssignment \n \n19.1 Assignment.  This TSRA may be assigned by either Party only with the written \nconsent of the other; and provided further that Large Load Interconnection \nCustomer shall have the right to assign this TSRA, without the consent of \nParticipating TO, for collateral security purposes to aid in providing financing for \nthe Large Load, provided that Large Load Interconnection Customer will promptly \nnotify Participating TO of any such assignment.  Any financing arrangement \nentered into by Large Load Interconnection Customer pursuant to this Article will \nprovide that prior to or upon the exercise of the secured party’s, trustee’s or \nmortgagee’s assignment rights pursuant to said arrangement, the secured \ncreditor, the trustee or mortgagee will notify Participating TO of the date and \nparticulars of any such exercise of assignment right(s), including providing the \nParticipating TO with proof that it meets the requirements of Articles 11.5 and \n18.3.  Any attempted assignment that violates this Article is void and ineffective.  \nAny assignment under this TSRA shall not relieve a Party of its obligations, nor \nshall a Party’s obligations be enlarged, in whole or in part, by reason thereof.  \nWhere required, consent to assignment will not be unreasonably withheld, \nconditioned or delayed. \n \nArticle 20. \nSeverability \n \n20.1 Severability.  If any provision in this TSRA is finally determined to be invalid, \nvoid or unenforceable by any court or other Governmental Authority having \njurisdiction, such determination shall not invalidate, void or make unenforceable \nany other provision, agreement or covenant of this TSRA. \n \nArticle 21. \nComparability \n \n21.1 Comparability.  The Parties will comply with all applicable comparability and \ncode of conduct laws, rules and regulations, as amended from time to time. \n \nArticle 22. \nConfidentiality \n \n22.1 Confidentiality.  Confidential Information shall include, without limitation, all \ninformation relating to a Party’s technology, research and development, business \naffairs, and pricing, and any information supplied by either of the Parties to the \nother prior to the execution of this TSRA. \n \nInformation is Confidential Information only if it is clearly designated or marked in \nwriting as confidential on the face of the document, or, if the information is"},{"page":202,"startToken":62624,"endToken":63085,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nconveyed orally or by inspection, if the Party providing the information orally \ninforms the Party receiving the information that the information is confidential. \n \nIf requested by either Party, the other Party shall provide in writing, the basis for \nasserting that the information referred to in this Article 22 warrants confidential \ntreatment, and the requesting Party may disclose such writing to the appropriate \nGovernmental Authority.  Each Party shall be responsible for the costs \nassociated with affording confidential treatment to its information. \n \n22.1.1 Term.  During the term of this TSRA, and for a period of three (3) years \nafter the expiration or termination of this TSRA, except as otherwise \nprovided in this Article 22, each Party shall hold in confidence and shall \nnot disclose to any person Confidential Information. \n \n22.1.2 Scope.  Confidential Information shall not include information that the \nreceiving Party can demonstrate: (1) is generally available to the public \nother than as a result of a disclosure by the receiving Party; (2) was in the \nlawful possession of the receiving Party on a non-confidential basis before \nreceiving it from the disclosing Party; (3) was supplied to the receiving \nParty without restriction by a third party, who, to the knowledge of the \nreceiving Party after due inquiry, was under no obligation to the disclosing \nParty to keep such information confidential; (4) was independently \ndeveloped by the receiving Party without reference to Confidential \nInformation of the disclosing Party; (5) is, or becomes, publicly known, \nthrough no wrongful act or omission of the receiving Party or Breach of \nthis TSRA; or (6) is required, in accordance with Article 22.1.7 of the \nTSRA, Order of Disclosure, to be disclosed by any Governmental \nAuthority or is otherwise required to be disclosed by law or subpoena, or is \nnecessary in any legal proceeding establishing rights and obligations \nunder this TSRA.  Information designated as Confidential Information will \nno longer be deemed confidential if the Party that designated the \ninformation as confidential notifies the other Party that it no longer is \nconfidential. \n \n22.1.3 Release of Confidential Information.  Neither Party shall release or \ndisclose Confidential Information to any other person, except to its \nAffiliates (limited by the Standards of Conduct requirements), \nsubcontractors, employees, consultants, or to parties who may be or \nconsidering providing financing to or equity participation with Large Load \nInterconnection Customer, or to potential purchasers or assignees of \nLarge Load Interconnection Customer, on a need-to-know basis in \nconnection with this TSRA, unless such person has first been advised of \nthe confidentiality provisions of this Article 22 and has agreed to comply \nwith such provisions.  Notwithstanding the foregoing, a Party providing \nConfidential Information to any person shall remain primarily responsible"},{"page":203,"startToken":63085,"endToken":63503,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nfor any release of Confidential Information in contravention of this Article \n22. \n \n22.1.4 Rights.  Each Party retains all rights, title, and interest in the Confidential \nInformation that each Party discloses to the other Party.  The disclosure \nby each Party to the other Party of Confidential Information shall not be \ndeemed a waiver by either Party or any other person or entity of the right \nto protect the Confidential Information from public disclosure. \n \n22.1.5 No Warranties.  By providing Confidential Information, neither Party \nmakes any warranties or representations as to its accuracy or \ncompleteness.  In addition, by supplying Confidential Information, neither \nParty obligates itself to provide any particular information or Confidential \nInformation to the other Party nor to enter into any further agreements or \nproceed with any other relationship or joint venture. \n \n22.1.6 Standard of Care.  Each Party shall use at least the same standard of \ncare to protect Confidential Information it receives as it uses to protect its \nown Confidential Information from unauthorized disclosure, publication or \ndissemination.  Each Party may use Confidential Information solely to fulfill \nits obligations to the other Party under this TSRA or its regulatory \nrequirements. \n \n22.1.7 Order of Disclosure.  If a court or a Government Authority or entity with \nthe right, power, and apparent authority to do so requests or requires \neither Party, by subpoena, oral deposition, interrogatories, requests for \nproduction of documents, administrative order, or otherwise, to disclose \nConfidential Information, that Party shall provide the other Party with \nprompt notice of such request(s) or requirement(s) so that the other Party \nmay seek an appropriate protective order or waive compliance with the \nterms of this TSRA.  Notwithstanding the absence of a protective order or \nwaiver, the Party may disclose such Confidential Information which, in the \nopinion of its counsel, the Party is legally compelled to disclose.  Each \nParty will use Reasonable Efforts to obtain reliable assurance that \nconfidential treatment will be accorded any Confidential Information so \nfurnished. \n \n22.1.8 Termination of Agreement.  Upon termination of this TSRA for any \nreason, each Party shall, within ten (10) Calendar Days of receipt of a \nwritten request from the other Party, use Reasonable Efforts to destroy, \nerase, or delete (with such destruction, erasure, and deletion certified in \nwriting to the other Party) or return to the other Party, without retaining \ncopies thereof, any and all written or electronic Confidential Information \nreceived from the other Party."},{"page":204,"startToken":63503,"endToken":64050,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n22.1.9 Remedies.  The Parties agree that monetary damages would be \ninadequate to compensate a Party for the other Party’s Breach of its \nobligations under this Article 22.  Each Party accordingly agrees that the \nother Party shall be entitled to equitable relief, by way of injunction or \notherwise, if the first Party Breaches or threatens to Breach its obligations \nunder this Article 22, which equitable relief shall be granted without bond \nor proof of damages, and the receiving Party shall not plead in defense \nthat there would be an adequate remedy at law.  Such remedy shall not be \ndeemed an exclusive remedy for the Breach of this Article 22, but shall be \nin addition to all other remedies available at law or in equity.  The Parties \nfurther acknowledge and agree that the covenants contained herein are \nnecessary for the protection of legitimate business interests and are \nreasonable in scope.  No Party, however, shall be liable for indirect, \nincidental, or consequential or punitive damages of any nature or kind \nresulting from or arising in connection with this Article 22. \n \n22.1.10 Disclosure to FERC, its Staff, or a State.  Notwithstanding anything in \nthis Article 22 to the contrary, and pursuant to 18 CFR section 1b.20, if \nFERC or its staff, during the course of an investigation or otherwise, \nrequests information from one of the Parties that is otherwise required to \nbe maintained in confidence pursuant to this TSRA, the Party shall provide \nthe requested information to FERC or its staff, within the time provided for \nin the request for information.  In providing the information to FERC or its \nstaff, the Party must, consistent with 18 CFR section 388.112, request that \nthe information be treated as confidential and non-public by FERC and its \nstaff and that the information be withheld from public disclosure.  Parties \nare prohibited from notifying the other Party to this TSRA prior to the \nrelease of the Confidential Information to FERC or its staff.  The Party \nshall notify the other Party to the TSRA when it is notified by FERC or its \nstaff that a request to release Confidential Information has been received \nby FERC, at which time either of the Parties may respond before such \ninformation would be made public, pursuant to 18 CFR section 388.112.  \nRequests from a state regulatory body conducting a confidential \ninvestigation shall be treated in a similar manner if consistent with the \napplicable state rules and regulations. \n \n22.1.11 Subject to the exception in Article 22.1.10, any information that a Party \nclaims is competitively sensitive, commercial or financial information under \nthis TSRA (\"Confidential Information\") shall not be disclosed by the other \nParty to any person not employed or retained by the other Party, except to \nthe extent disclosure is (i) required by law; (ii) reasonably deemed by the \ndisclosing Party to be required to be disclosed in connection with a dispute \nbetween or among the Parties, or the defense of litigation or dispute; (iii) \notherwise permitted by consent of the other Party, such consent not to be \nunreasonably withheld; or (iv) necessary to fulfill its obligations under this \nTSRA or as a transmission service provider or a Balancing Authority Area"},{"page":205,"startToken":64050,"endToken":64468,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \noperator including disclosing the Confidential Information to an RTO or \nISO or to a regional or national reliability organization.  The Party \nasserting confidentiality shall notify the other Party in writing of the \ninformation it claims is confidential.  Prior to any disclosures of the other \nParty’s Confidential Information under this subparagraph, or if any third \nparty or Governmental Authority makes any request or demand for any of \nthe information described in this subparagraph, the disclosing Party \nagrees to promptly notify the other Party in writing and agrees to assert \nconfidentiality and cooperate with the other Party in seeking to protect the \nConfidential Information from public disclosure by confidentiality \nagreement, protective order or other reasonable measures. \n \nArticle 23. \nEnvironmental Releases \n \n23.1  Each Party shall notify the other Party, first orally and then in writing, of the \nrelease of any Hazardous Substances, any asbestos or lead abatement \nactivities, or any type of remediation activities related to the Large Load or the \nInterconnection Facilities, each of which may reasonably be expected to affect \nthe other Party.  The notifying Party shall: (i) provide the notice as soon as \npracticable, provided such Party makes a good faith effort to provide the notice \nno later than twenty-four hours after such Party becomes aware of the \noccurrence; and (ii) promptly furnish to the other Party copies of any publicly \navailable reports filed with any Governmental Authorities addressing such \nevents. \n \nArticle 24. \nInformation Requirements \n \n24.1 Information Acquisition.  Participating TO and Large Load Interconnection \nCustomer shall submit specific information regarding the electrical characteristics \nof their respective facilities to each other as described below and in accordance \nwith Applicable Reliability Standards. \n \n24.2 Information Submission by Participating TO.  The initial information \nsubmission by Participating TO shall occur no later than one hundred eighty \n(180) Calendar Days prior to Service Commencement Date and shall include \ntransmission system information necessary to allow Large Load Interconnection \nCustomer to select equipment and meet any system protection and stability \nrequirements, unless otherwise agreed to by the Parties.  On a monthly basis \nParticipating TO shall provide Large Load Interconnection Customer a status \nreport on the construction and installation of Participating TO’s Interconnection \nFacilities, Distribution Upgrades, and Large Load Network Upgrades, including, \nbut not limited to, the following information: (1) progress to date; (2) a description \nof the activities since the last report; (3) a description of the action items for the \nnext period; and (4) the delivery status of equipment ordered."},{"page":206,"startToken":64468,"endToken":64914,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n24.3 Updated Information Submission by Large Load Interconnection Customer.  \nThe updated information submission by Large Load Interconnection Customer, \nincluding manufacturer information, shall occur no later than one hundred eighty \n(180) Calendar Days prior to the Service Commencement Date.  Large Load \nInterconnection Customer shall submit a completed copy of the Large Load data \nrequirements contained in Appendix 1 to the LLIP.  It shall also include any \nadditional information provided to Participating TO for the Large Load \nInterconnection Study.  Information in this submission shall be the most current \nLarge Load design or expected performance data.  Information submitted for \nstability models shall be compatible with Participating TO standard models.  If \nthere is no compatible model, Large Load Interconnection Customer will work \nwith a consultant mutually agreed to by the Parties to develop and supply a \nstandard model and associated information. \n \nIf Large Load Interconnection Customer’s data is materially different from what \nwas originally provided to Participating TO pursuant to the Large Load Study \nProcess Agreement between Participating TO and Large Load Interconnection \nCustomer, then Participating TO will conduct appropriate studies to determine \nthe impact on Participating TO’s Transmission System and Distribution System \nbased on the actual data submitted pursuant to this Article 24.3.  The Large Load \nInterconnection Customer shall not energize or operate the Large Load or co-\nlocated generation, if applicable, in parallel with the Participating TO’s \nTransmission System until such studies are completed. Changes not previously \nstudied may require additional scope, may delay the Service Commencement \nDate, or, if determined by Participating TO to constitute a Material Modification, \nwill require Large Load Interconnection Customer to submit a new \nInterconnection Request pursuant to the LLIP.  \n \n24.4 Information Supplementation.  Prior to the Service Commencement Date, the \nParties shall supplement their information submissions described above in this \nArticle 24 with any and all “as-built” Large Load information or “as-tested” \nperformance information that differs from the initial submissions or, alternatively, \nwritten confirmation that no such differences exist.  The Large Load \nInterconnection Customer shall conduct tests on the Large Load as required by \nGood Utility Practice.  \n \nSubsequent to the Service Commencement Date, Large Load Interconnection \nCustomer shall provide Participating TO any information changes due to \nequipment replacement, repair, or adjustment.  Participating TO shall provide \nLarge Load Interconnection Customer any information changes due to equipment \nreplacement, repair or adjustment in the directly connected substation or any \nadjacent Participating TO-owned substation that may affect Large Load \nInterconnection Customer’s Interconnection Facilities equipment ratings, \nprotection or operating requirements.  The Parties shall provide such information \nno later than thirty (30) Calendar Days after the date of the equipment \nreplacement, repair or adjustment."},{"page":207,"startToken":64914,"endToken":65379,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nArticle 25. \nInformation Access and Audit Rights \n \n25.1 Information Access.  Each Party (the “disclosing Party”) shall make available to \nthe other Party information that is in the possession of the disclosing Party and is \nnecessary in order for the other Party to: (i) verify the costs incurred by the \ndisclosing Party for which the other Party is responsible under this TSRA; and (ii) \ncarry out its obligations and responsibilities under this TSRA.  The Parties shall \nnot use such information for purposes other than those set forth in this Article \n25.1 and to enforce their rights under this TSRA. \n \n25.2 Reporting of Non-Uncontrollable Force Events.  Each Party (the “notifying \nParty”) shall notify the other Party when the notifying Party becomes aware of its \ninability to comply with the provisions of this TSRA for a reason other than an \nUncontrollable Force event.  The Parties agree to cooperate with each other and \nprovide necessary information regarding such inability to comply, including the \ndate, duration, reason for the inability to comply, and corrective actions taken or \nplanned to be taken with respect to such inability to comply.  Notwithstanding the \nforegoing, notification, cooperation or information provided under this Article shall \nnot entitle the Party receiving such notification to allege a cause for anticipatory \nbreach of this TSRA. \n \n25.3 Audit Rights.  Subject to the requirements of confidentiality under Article 22 of \nthis TSRA, each Party shall have the right, during normal business hours, and \nupon prior reasonable notice to the other Party, to audit at its own expense the \nother Party’s accounts and records pertaining to either Party’s performance or \neither Party’s satisfaction of obligations under this TSRA.  Such audit rights shall \ninclude audits of the other Party’s costs, calculation of invoiced amounts, and \neach Party’s actions in an Emergency Condition.  Any audit authorized by this \nArticle shall be performed at the offices where such accounts and records are \nmaintained and shall be limited to those portions of such accounts and records \nthat relate to each Party’s performance and satisfaction of obligations under this \nTSRA.  Each Party shall keep such accounts and records for a period equivalent \nto the audit rights periods described in Article 25.4. \n \n25.4 Audit Rights Periods. \n \n25.4.1 Audit Rights Period for Construction-Related Accounts and Records.  \nAccounts and records related to the design, engineering, procurement, \nand construction of Participating TO’s Interconnection Facilities, \nDistribution Upgrades, and Large Load Network Upgrades shall be subject \nto audit for a period of twenty-four months following Participating TO’s \nissuance of a final invoice in accordance with Article 12.2. \n \n25.4.2 Audit Rights Period for All Other Accounts and Records.  Accounts \nand records related to either Party’s performance or satisfaction of all"},{"page":208,"startToken":65379,"endToken":65818,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nobligations under this TSRA other than those described in Article 25.4.1 \nshall be subject to audit as follows:  (i) for an audit relating to cost \nobligations, the applicable audit rights period shall be twenty-four months \nafter the auditing Party’s receipt of an invoice giving rise to such cost \nobligations; and (ii) for an audit relating to all other obligations, the \napplicable audit rights period shall be twenty-four months after the event \nfor which the audit is sought. \n \n25.5 Audit Results.  If an audit by a Party determines that an overpayment or an \nunderpayment has occurred, a notice of such overpayment or underpayment \nshall be given to the other Party together with those records from the audit which \nsupport such determination.   \n \nArticle 26. \nSubcontractors \n \n26.1 General.  Nothing in this TSRA shall prevent a Party from utilizing the services of \nany subcontractor as it deems appropriate to perform its obligations under this \nTSRA; provided, however, that each Party shall require its subcontractors to \ncomply with all applicable terms and conditions of this TSRA in providing such \nservices and each Party shall remain primarily liable to the other Party for the \nperformance of such subcontractor. \n \n26.2 Responsibility of Principal.  The creation of any subcontract relationship shall \nnot relieve the hiring Party of any of its obligations under this TSRA.  The hiring \nParty shall be fully responsible to the other Party for the acts or omissions of any \nsubcontractor the hiring Party hires as if no subcontract had been made; \nprovided, however, that in no event shall Participating TO be liable for the actions \nor inactions of Large Load Interconnection Customer or its subcontractors with \nrespect to obligations of Large Load Interconnection Customer under Article 5 of \nthis TSRA.  Any applicable obligation imposed by this TSRA upon the hiring \nParty shall be equally binding upon, and shall be construed as having application \nto, any subcontractor of such Party. \n \n26.3 No Limitation by Insurance.  The obligations under this Article 26 will not be \nlimited in any way by any limitation of subcontractor’s insurance. \n \nArticle 27. \nDisputes  \n \n27.1 Submission.  In the event either Party has a dispute, or asserts a claim, which \narises out of or in connection with the TSRA, the LLIP, or their performance, such \nParty (the \"disputing Party\") shall provide the other Party with written notice of \nthe dispute or claim (\"Notice of Dispute\").  Such dispute or claim shall be \nresolved in accordance with the Dispute Resolution Procedures set forth in \nSection 14 of the TO Tariff.  \n \nArticle 28. \nRepresentations, Warranties, and Covenants"},{"page":209,"startToken":65818,"endToken":66249,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n28.1 General.  Each Party makes the following representations, warranties and \ncovenants:  \n \n28.1.1 Good Standing.  Such Party is duly organized, validly existing and in \ngood standing under the laws of the state in which it is organized, formed, \nor incorporated, as applicable; that it is qualified to do business in the \nstate or states in which the Large Load, Interconnection Facilities and \nLarge Load Network Upgrades owned by such Party, as applicable, are \nlocated; and that it has the corporate power and authority to own its \nproperties, to carry on its business as now being conducted and to enter \ninto this TSRA and carry out the transactions contemplated hereby and \nperform and carry out all covenants and obligations on its part to be \nperformed under and pursuant to this TSRA. \n \n28.1.2 Authority.  Such Party has the right, power and authority to enter into this \nTSRA, to become a Party hereto and to perform its obligations hereunder.  \nThis TSRA is a legal, valid and binding obligation of such Party, \nenforceable against such Party in accordance with its terms, except as the \nenforceability thereof may be limited by applicable bankruptcy, insolvency, \nreorganization or other similar laws affecting creditors’ rights generally and \nby general equitable principles (regardless of whether enforceability is \nsought in a proceeding in equity or at law). \n \n \n28.1.3 No Conflict.  The execution, delivery and performance of this TSRA does \nnot violate or conflict with the organizational or formation documents, or \nbylaws or operating agreement, of such Party, or any judgment, license, \npermit, order, material agreement or instrument applicable to or binding \nupon such Party or any of its assets. \n \n28.1.4 Consent and Approval.  Such Party has sought or obtained, or, in \naccordance with this TSRA will seek or obtain, each consent, approval, \nauthorization, order, or acceptance by any Governmental Authority in \nconnection with the execution, delivery and performance of this TSRA, \nand it will provide to any Governmental Authority notice of any actions \nunder this TSRA that are required by Applicable Laws and Regulations. \n \nArticle 29. \nMiscellaneous \n \n29.1 Binding Effect.  This TSRA and the rights and obligations hereof, shall be \nbinding upon and shall inure to the benefit of the successors and assigns of the \nParties hereto. \n \n29.2 Conflicts.  In the event of a conflict between the body of this TSRA and any \nattachment, appendices or exhibits hereto, the terms and provisions of the body \nof this TSRA shall prevail and be deemed the final intent of the Parties."},{"page":210,"startToken":66249,"endToken":66758,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n29.3 Rules of Interpretation.  This TSRA, unless a clear contrary intention appears, \nshall be construed and interpreted as follows:  (1) the singular number includes \nthe plural number and vice versa;  (2) reference to any person includes such \nperson’s successors and assigns but, in the case of a Party, only if such \nsuccessors and assigns are permitted by this TSRA, and reference to a person in \na particular capacity excludes such person in any other capacity or individually; \n(3) reference to any agreement (including this TSRA), document, instrument or \ntariff means such agreement, document, instrument, or tariff as amended or \nmodified and in effect from time to time in accordance with the terms thereof and, \nif applicable, the terms hereof; (4) reference to any Applicable Laws and \nRegulations means such Applicable Laws and Regulations as amended, \nmodified, codified, or reenacted, in whole or in part, and in effect from time to \ntime, including, if applicable, rules and regulations promulgated thereunder; (5) \nunless expressly stated otherwise, reference to any Article, Section or Appendix \nmeans such Article of this TSRA or such Appendix to this TSRA, or such Section \nto the LLIP or such Appendix to the LLIP, as the case may be; (6) “hereunder”, \n“hereof”, “herein”, “hereto” and words of similar import shall be deemed \nreferences to this TSRA as a whole and not to any particular Article or other \nprovision hereof or thereof; (7) “including” (and with correlative meaning \n“include”) means including without limiting the generality of any description \npreceding such term; and (8) relative to the determination of any period of time, \n“from” means “from and including”, “to” means “to but excluding” and “through” \nmeans “through and including”. \n \n29.4 Entire Agreement.  This TSRA, including all Appendices and Schedules \nattached hereto, constitutes the entire agreement between the Parties with \nreference to the subject matter hereof, and supersedes all prior and \ncontemporaneous understandings or agreements, oral or written, between the \nParties with respect to the subject matter of this TSRA.  There are no other \nagreements, representations, warranties, or covenants which constitute any part \nof the consideration for, or any condition to, either Party’s compliance with its \nobligations under this TSRA. \n \n29.5 No Third Party Beneficiaries.  This TSRA is not intended to and does not \ncreate rights, remedies, or benefits of any character whatsoever in favor of any \npersons, corporations, associations, or entities other than the Parties, and the \nobligations herein assumed are solely for the use and benefit of the Parties, their \nsuccessors in interest and, where permitted, their assigns. \n \n29.6 Waiver.  The failure of a Party to this TSRA to insist, on any occasion, upon strict \nperformance of any provision of this TSRA will not be considered a waiver of any \nobligation, right, or duty of, or imposed upon, such Party. \n \nAny waiver at any time by either Party of its rights with respect to this TSRA shall \nnot be deemed a continuing waiver or a waiver with respect to any other failure to"},{"page":211,"startToken":66758,"endToken":67204,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \ncomply with any other obligation, right, duty of this TSRA.  Termination or Default \nof this TSRA for any reason by Large Load Interconnection Customer shall not \nconstitute a waiver of Large Load Interconnection Customer’s legal rights to \nobtain an interconnection from Participating TO.  Any waiver of this TSRA shall, if \nrequested, be provided in writing. \n \n29.7 Headings.  The descriptive headings of the various articles of this TSRA have \nbeen inserted for convenience of reference only and are of no significance in the \ninterpretation or construction of this TSRA. \n \n29.8 Multiple Counterparts.  This TSRA may be executed in two or more \ncounterparts, each of which is deemed an original but all constitute one and the \nsame instrument. \n \n29.9 Amendment.  The Parties may by mutual agreement amend this TSRA by a \nwritten instrument duly executed by the Parties. \n \n29.10 Modification by the Parties.  The Parties may by mutual agreement amend the \nAppendices to this TSRA by a written instrument duly executed by the Parties.  \nSuch amendment shall become effective and a part of this TSRA upon \nsatisfaction of all Applicable Laws and Regulations. \n \n29.11 Reservation of Rights.  Participating TO shall have the right to make a \nunilateral filing with FERC to modify this TSRA with respect to any rates, terms \nand conditions, charges, classifications of service, rule or regulation under \nsection 205 or any other applicable provision of the Federal Power Act and \nFERC’s rules and regulations thereunder, and Large Load Interconnection \nCustomer shall have the right to make a unilateral filing with FERC to modify this \nTSRA pursuant to section 206 or any other applicable provision of the Federal \nPower Act and FERC’s rules and regulations thereunder; provided that each \nParty shall have the right to protest any such filing by the other Party and to \nparticipate fully in any proceeding before FERC in which such modifications may \nbe considered.  Nothing in this TSRA shall limit the rights of the Parties or of \nFERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and \nregulations thereunder, except to the extent that the Parties otherwise mutually \nagree as provided herein. \n \n29.12 No Partnership.  This TSRA shall not be interpreted or construed to create an \nassociation, joint venture, agency relationship, or partnership between the \nParties or to impose any partnership obligation or partnership liability upon either \nParty.  Neither Party shall have any right, power or authority to enter into any \nagreement or undertaking for, or act on behalf of, or to act as or be an agent or \nrepresentative of, or to otherwise bind, the other Party."},{"page":212,"startToken":67204,"endToken":67262,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nIN WITNESS WHEREOF, the Parties have executed this TSRA in duplicate \noriginals, each of which shall constitute and be an original effective Agreement between \nthe Parties. \n \n[Insert name of Participating TO \n \nBy: \n                                                       \n \n \nName: ___________________________ \n \nTitle:                                                        \n \n  \nDate:                                                         \n \n \n \n \n[Insert name of Large Load Interconnection Customer] \n \n \nBy: \n                                                       \n \n \nName: ___________________________ \n \nTitle:                                                        \n \n \nDate:"},{"page":213,"startToken":67262,"endToken":67296,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nAppendix A to TSRA \n \nDescription of Participating TO’s Interconnection Facilities, Large Load Network \nUpgrades, Distribution Upgrades, Costs, Payments and Interconnection Financial \nSecurity"},{"page":214,"startToken":67296,"endToken":67645,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nAppendix B to TSRA \n \nRequirements for Mitigation of Potential Cost Shifting Related to New \nTransmission Facilities \n \n \n1. Security For Large Load Network Upgrades and ISO-Identified Network \nUpgrades \na. Initial Amount of Security.  For the Large Load Network Upgrades \nidentified in Appendix A and any ISO-Identified Network Upgrades, Large \nLoad Interconnection Customer must provide Interconnection Financial \nSecurity equal to the Participating TO’s estimated costs attributable to the \napplicable facilities, including engineering, design, procurement, \npermitting, construction, installation, testing, and commissioning costs, \ntogether with applicable labor, materials, contractor charges, and \noverhead.  If the final engineering and design indicates a change in the \nscope of Large Load Network Upgrades or ISO-Identified Network \nUpgrades, the costs of the incremental resulting Large Load Network \nUpgrades and ISO-Identified Network Upgrades shall be included as \nadditional Interconnection Financial Security. \ni. Large Load Network Upgrades and ISO-Identified Network \nUpgrades Interconnection Financial Security: ____________ \nb. Reduction in Amount of Security.  Large Load Interconnection \nCustomer is entitled to annually reduce the Interconnection Financial \nSecurity identified in Section 1.a, in accordance with this Section.  \nReductions shall commence once the Large Load commences retail \nservice.  The amount reduced against the total security for the Large Load \nNetwork Upgrades and any ISO-Identified Network Upgrades will equal \n75% multiplied by the amount of MWh counted as Gross Load of the \nLarge Load Interconnection Customer associated with withdrawals by the \nLarge Load multiplied by the Regional Access Charge.  The Regional \nAccess Charge will be set for purposes of this calculation in the same \nmanner as set in Section 2.c of this Appendix B and will be fixed once set.  \nIn order to receive this reduction, the Large Load Interconnection \nCustomer will inform the Participating TO of its Gross Load withdrawn as \nmeasured by the ISO revenue meter.  Any remaining unreduced balance \nof Interconnection Financial Security for the Large Load Network \nUpgrades and any ISO-Identified Network Upgrades after fifteen (15) \nyears will be drawn down by Participating TO and credited under \nParticipating TO’s Transmission Revenue Balancing Account Adjustment. \n2. Minimum Annual Revenue Obligation"},{"page":215,"startToken":67645,"endToken":68001,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \na. Calculation of Minimum Annual Revenue Obligation \ni. The Minimum Annual Revenue Obligation (“MARO”) is an amount \nof revenue that will be collected in each yearly period to ensure that \nthe Large Load Interconnection Customer contributes sufficiently to \nthe Gross Load in the ISO Balancing Authority Area, or else pays a \nshortfall amount that will flow through the relevant revenue \nrequirement (used to set the Regional Access Charge and Regional \nWheeling Access Charge and, if relevant, used to set the Local \nAccess Charge and Local Wheeling Access Charge) in accordance \nwith the ISO Tariff.  “Regional Access” Charge and “Regional \nWheeling Access Charge” are all defined in the ISO Tariff.   \nii. For each yearly period, Large Load Interconnection Customer’s \nMinimum Annual Revenue Obligation shall be calculated as follows: \nMinimum Annual Revenue Obligation = Minimum Obligation Capacity (MW) × [hours in \nthe year] × 80% × 75% × Regional Access Charge (if connected to High Voltage \nfacilities) \niii. The Regional Access Charge or the Regional Access Charge plus \nthe Local Access Charge amount will be fixed at the most recent \nrates posted by the ISO as of the date of execution for the fifteen \nyears that the Minimum Annual Revenue Obligation remains in \neffect.  The ISO posts the relevant rates (using the term “TAC” \nrather than the term “RAC” on the “Settlements” page of its website \n(currently https://www.ISO.com/market-operations/settlements).   \niv. “Requested Maximum Load” means the ultimate peak demand, \nexpressed in MW, specified by the Large Load Interconnection \nCustomer on behalf of the Large Load in the application process in \nthe LLIP.  For purposes of calculating the Minimum Annual \nRevenue Obligation during the load ramp, “Large Load Capacity” \nmeans the MW amount assigned to the applicable Year in the \nschedule below.  The Large Load Capacity shall reflect the \nexpected maximum capacity during the relevant annual period.  \nThe Large Load Capacity should be set at the Requested Maximum \nLoad no later than Year 5.   \nTable 1. Minimum Capacity Schedule \n \nYear \nDate \nMinimum Obligation Capacity \n1 \n[Date] \n MW \n2 \n[Date] \n MW \n3 \n[Date] \nMW \n4 \n[Date] \nMW \n5 \n[Date]  \nMW"},{"page":216,"startToken":68001,"endToken":68343,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nYear \nDate \nMinimum Obligation Capacity \n6 \n[Date] \n MW \n7 \n[Date] \n MW \n8 \n[Date] \nMW \n9 \n[Date] \nMW \n10 \n[Date]  \n MW \n11 \n[Date] \n MW \n12 \n[Date] \nMW \n13 \n[Date] \nMW \n14 \n[Date] \n MW \n15 \n[Date]  \n MW \n \nb. Minimum Annual Revenue Obligation Reconciliation Process \ni. After each year, Participating TO shall compare the Minimum \nAnnual Revenue Obligation with the annual wholesale revenues \nassociated with the Gross Load of the Large Load, as measured by \nthe ISO revenue meter (“Annual LL Gross Load Revenue”).  The \nAnnual LL Gross Load Revenue would be calculated by the Large \nLoad Interconnection Customer providing Participating TO the \nGross Load of the Large Load End User and multiplying that \namount by the Regional Access Charge only, or the Regional \nAccess Charge plus Local Access Charge, as appropriate.  The \nsame Regional Access Charge and/or Local Access Charge rates \nused to calculate the Minimum Annual Revenue Obligation will be \nused to calculate the Annual LL Gross Load Revenue.  If a Large \nLoad is a retail transmission customer of the Participating TO, then \nits Annual LL Gross Load Revenue shall be equal to its retail \ntransmission revenues.  If the Annual LL Gross Load Revenue for \nthe annual period is greater than Minimum Annual Revenue \nObligation, the Annual LL Gross Load Revenue calculation need \nnot be performed and no reconciliation will occur because the \nMinimum Annual Revenue Obligation has been met. \nii. If the Annual LL Gross Load Revenue is less than the Minimum \nAnnual Revenue Obligation, Participating TO shall invoice the \nLarge Load Interconnection Customer for the difference, payable \nwithin thirty (30) calendar days of receipt (“MARO Shortfall”).  \nPayment of the MARO Shortfall shall satisfy the Minimum Annual \nRevenue Obligation under this Section for that year.  Any MARO \nShortfalls paid by the Large Load Interconnection Customer would \nbe treated as revenue in Participating TO’s Transmission Revenue \nBalancing Account Adjustment.  \niii. A delay in achieving the Requested Maximum Load shall not, by \nitself, postpone a scheduled increase in Minimum Annual Revenue"},{"page":217,"startToken":68343,"endToken":68700,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nObligation.  The Parties may change the Minimum Capacity \nSchedule only by written amendment to this TSRA, subject to any \nrequired regulatory approval.  The number of amendments to the \nLarge Load Capacity Schedule are limited to one annually for the \nfirst four years after execution of the TSRA, with no amendments \nthereafter.   \nc. MARO Interconnection Financial Security \ni. Provision of Interconnection Financial Security to Secure \nMARO.  The Large Load Interconnection Customer shall provide \nadditional Interconnection Financial Security separate and apart \nfrom the Interconnection Financial Security described in Section 1 \nof this Appendix B to secure its MARO.  \nii. Amount of MARO Interconnection Financial Security.  The \nInterconnection Financial Security to secure the MARO shall be \nmaintained for as long as the Minimum Annual Revenue Obligation \nremains in effect, including any period necessary to resolve and \npay a final annual reconciliation.  The required amount of \nInterconnection Financial Security shall equal five years times the \nMinimum Annual Revenue Obligation calculated using the full \nLarge Load Capacity, rather than the Minimum Obligation Capacity \napplicable during the load ramp.   \n1. MARO Interconnection Financial Security: __________ \niii. Reduction and Release of MARO Interconnection Financial \nSecurity.  In each of the Years 10-15 of this TSRA, Large Load \nInterconnection Customer may reduce its Interconnection Financial \nSecurity under this Appendix B, Section 2.c by one year’s Minimum \nAnnual Revenue Obligation.  Thirty days after the expiration of this \nTSRA, if all amounts due have been paid, the Participating TO will \nrelease the remaining MARO Interconnection Financial Security. \nd. Failure to Pay MARO Shortfall \ni. Participating TO shall draw on the MARO Interconnection Financial \nSecurity for any MARO Shortfall that remains unpaid more than \nsixty (60) Calendar Days after its due date.  Participating TO shall \ngive Large Load Interconnection Customer written notice of the \namount drawn and apply the proceeds to the unpaid obligation.  A \ndraw does not discharge Large Load Interconnection Customer’s \nobligation to pay amounts exceeding the proceeds or relieve Large \nLoad Interconnection Customer of future payment obligations.  \nWithin thirty (30) Calendar Days after a draw, Large Load \nInterconnection Customer shall restore the available MARO"},{"page":218,"startToken":68700,"endToken":68994,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nInterconnection Financial Security to the required amount in \nSection 2(c)ii. \n3. Withdrawal Penalty; Exit Fee \na. Requirements Prior to Commencement of Service.  Prior to the Service \nCommencement Date, the provisions of this Section apply. \ni. Withdrawal Penalty.  In accordance with LLIP Section 3.10.1(c), if \nLarge Load Interconnection Customer fails to take service on or \nbefore its Service Commencement Date, the Large Load \nInterconnection Customer’s Withdrawal Penalty will be the greater \nof twenty percent (20%) of its estimated Large Load Network \nUpgrade costs as reflected in the most recently completed \nInterconnection Study, or the actual cost of any Large Load \nNetwork Upgrade abandoned facilities. \nb. Requirements Following Commencement of Service.  Following the \nService Commencement Date, the provisions of this Section apply. \ni. Exit Fee.  If the TSRA is terminated prior to the expiration of the \nTerm, Large Load Interconnection Customer shall pay an Exit Fee \nequal to the value of the required remaining Interconnection \nFinancial Security under this Appendix B on the date of termination, \nincluding all remaining Interconnection Financial Security for Large \nLoad Network Upgrades, ISO-Identified Network Upgrades, and \nLarge Load Interconnection Customer’s MARO.  Such Exit Fee will \nbe due thirty (30) Business Days after an invoice for the Exit Fee \nhas been sent.  If the Large Load Interconnection Customer does \nnot pay the Exit Fee in full within thirty (30) Business Days, the \nParticipating TO may draw on all Interconnection Financial Security \nto pay the Exit Fee.  If this agreement is terminated, the Large Load \nInterconnection Customer’s right to Transmission Interconnection \nService is terminated and the Large Load Interconnection \nCustomer may be rendered incapable of delivering electric energy \nfor consumption by the Large Load End User."},{"page":219,"startToken":68994,"endToken":69015,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \nAppendix C to TSRA \n \nMilestones \n \nCheck box if applicable \n[   ]"},{"page":220,"startToken":69015,"endToken":69033,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nAppendix D to TSRA \n \nInterconnection Details"},{"page":221,"startToken":69033,"endToken":69059,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nAppendix E to TSRA \n \nFlexible Interim Load Interconnection (FILI) Conditions \n \nCheck box if applicable  ☐"},{"page":222,"startToken":69059,"endToken":69172,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nAppendix F to TSRA \n \nSecurity Arrangements Details \n \n \nInfrastructure security of Participating TO’s Transmission System and Distribution \nSystem equipment and operations and control hardware and software is essential to \nensure day-to-day reliability and operational security.  FERC will expect the ISO, all \ntransmission providers, market participants, and Large Load Interconnection Customers \ninterconnected to the Participating TO’s Transmission System to comply with the \nrecommendations offered by the President’s Critical Infrastructure Protection Board \nand, eventually, best practice recommendations from the electric reliability authority.  All \npublic utilities will be expected to meet basic standards for system infrastructure and \noperational security, including physical, operational, and cyber-security practices."},{"page":223,"startToken":69172,"endToken":69244,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \nAppendix G to TSRA \n \nAddresses for Delivery of Notices and Billings \n \n \nNotices: \n \n \nParticipating TO: \n \n \n \n[To be supplied.] \n \n \n \nLarge Load Interconnection Customer: \n \n \n[To be supplied.] \n \n \nBillings and Payments: \n \n \n \nParticipating TO: \n \n \n[To be supplied.] \n \n \n \nLarge Load Interconnection Customer: \n \n \n[To be supplied.] \n \n \nAlternative Forms of Delivery of Notices (telephone or email): \n \n \n \nParticipating TO: \n \n \n[To be supplied.] \n \n \n \nLarge Load Interconnection Customer: \n \n \n[To be supplied.]"},{"page":224,"startToken":69244,"endToken":69285,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \n \n \nATTACHMENT 4 to LLIP \n \n \n \nOPERATING CONDITIONS AGREEMENT \nfor  \nFLEXIBLE INTERIM LOAD INTERCONNECTION (FILI)  \nAMONG \n \n \n[LARGE LOAD INTERCONNECTION CUSTOMER] \nAND \n \n \n \n \nSOUTHERN CALIFORNIA EDISON COMPANY \nAND \n \n \n \n \nCALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION"},{"page":225,"startToken":69285,"endToken":69628,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \nOPERATING CONDITIONS AGREEMENT  \nfor \nFLEXIBLE INTERIM LOAD INTERCONNECTION (FILI) \n  \n  \n THIS OPERATING CONDITIONS AGREEMENT for FLEXIBLE INTERIM LOAD \nINTERCONNECTION (FILI) is made and entered into this ____ day of \n______________ 20__, by and among _______________, a ______________ \norganized and existing under the laws of the State/Commonwealth of _____________ \n(\"Large Load Interconnection Customer\" with a Large Load), Southern California Edison \nCompany, a corporation organized and existing under the laws of the State of California \n(\"Participating TO\"), and California Independent System Operator Corporation, a \nCalifornia nonprofit public benefit corporation organized and existing under the laws of \nthe State of California (\"CAISO\"). Large Load Interconnection Customer, Participating \nTO, and CAISO each may be referred to as a \"Party\" or collectively as the \"Parties.\"  \n  \nRECITALS  \n  \nWHEREAS, Large Load Interconnection Customer has entered into a \nTransmission Security and Reliability Agreement (“TSRA”) with the Participating TO \ndated _________ and designated as Service Agreement No. ______ for the purpose of \ninterconnecting its Large Load to the Participating TO’s Transmission System, which is \npart of the ISO Controlled Grid; and \n \nWHEREAS, the Large Load Interconnection Customer elected FILI pursuant to the \nterms of the TSRA to allow interconnection and operation of the Large Load prior to the \ncompletion of the upgrades, subject to the conditions and limitations identified in Appendix \nE to the TSRA; and \n \nWHEREAS, ISO exercises Operational Control over the ISO Controlled Grid; and  \n  \nWHEREAS, the Participating TO owns, operates, and maintains the Participating \nTO’s Transmission System; and  \n  \nWHEREAS, Section 25.7.2 of the ISO Tariff requires the Large Load \nInterconnection Customer, the Participating TO, and the ISO to enter into this \nagreement for the purpose of describing the circumstances under which the ISO or \nParticipating TO may temporarily curtail the Large Load receiving FILI, the mechanism \nthe ISO or Participating TO will use to perform the curtailment, and other conditions or \nlimitations of FILI; and  \nWHEREAS, Large Load Interconnection Customer, Participating TO, and ISO \nhave agreed to enter into this agreement in accordance with Section 25.7.2 of the ISO \nTariff;"},{"page":226,"startToken":69628,"endToken":70043,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n NOW, THEREFORE, in consideration of and subject to the mutual covenants \ncontained herein, it is agreed: \nNOW, THEREFORE, in consideration of and subject to the mutual covenants contained \nherein the Parties agree as follows: \n \n1.0 \nWhen used in this Agreement, with initial capitalization, the terms \nspecified shall have the meanings indicated in the LLIP, or if not defined in \nthe LLIP, as defined in the TO Tariff. \n \n2.0 \nThis Agreement shall become effective upon execution by all Parties \nsubject to acceptance by FERC (if required), or if filed unexecuted, upon \nthe date specified by FERC. The ISO shall promptly file this Agreement \nwith FERC upon execution, if required.  \n \n \n3.0 \nThis Agreement shall remain in effect during the period in which the \nParticipating TO is providing FILI service pursuant to the TSRA and shall \nterminate on the earlier of: (i) termination of the TSRA; (ii) upon \ncompletion of the upgrades required for the full service requested under \nthe TSRA, identified in Appendix 4 to this Agreement, and such full service \ncommences; or, (iii) upon Default under Section 9.0 of this Agreement. \nUpon termination of this Agreement, the Large Load Interconnection \nCustomer shall not be entitled to FILI service. \n \n \n4.0 \nISO and Participating TO shall have the right to curtail FILI service in \naccordance with Appendix 1, in addition to any other rights provided \npursuant to the TSRA, the TO Tariff or the ISO Tariff. The Participating TO \nand ISO shall not be subject to any damages with respect to their exercise \nof such curtailment rights.  \n5.0 \nThe Large Load Interconnection Customer shall operate the Large Load in \naccordance with the conditions and limitations set forth in Appendix 2. \n6.0 \nThe failure of the Large Load Interconnection Customer to comply with an \ninstruction to curtail FILI service issued by the Participating TO or ISO \npursuant to Section 4.0, or to operate the Large Load pursuant to Section \n5.0, may result in disconnection of the Large Load from the ISO Controlled \nGrid and shall be considered a Breach of this Agreement. For the \npurposes of this Agreement, Breach shall mean the failure of a Party to \nperform or observe any material term or condition of this Agreement. \n \n7.0 \nThe Parties have designated the individuals identified in Appendix 3 as the \npoint(s) of contact with respect to the implementation of this Agreement \nand provision of notices."},{"page":227,"startToken":70043,"endToken":70507,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n8.0 \nConflicts. With regard to rights and obligations between the Participating \nTO and the Large Load Interconnection Customer, if and to the extent a \nmatter is specifically addressed by a provision of this Agreement \n(including any appendices), the provisions of this Agreement shall govern. \nIf and to the extent a provision of this Agreement is inconsistent with the \nISO Tariff and dictates rights and obligations between the ISO and the \nParticipating TO or the ISO and the Large Load Interconnection Customer, \nthe ISO Tariff shall govern. In the event of a conflict between this \nAgreement and the TSRA, the terms and provisions of this Agreement \nshall govern.  \n9.0 \nDefault. If a Breach is not cured as provided in this Section, or if a Breach \nis not capable of being cured within the period provided for herein, the \nnon-breaching Party shall have the right to declare a default (“Default”) \nand terminate this Agreement by written notice at any time until cure \noccurs, and be relieved of any further obligation hereunder and, whether \nor not that Party terminates this Agreement, to recover from the breaching \nParty all amounts due hereunder, plus all other damages and remedies to \nwhich it is entitled at law or in equity. The provisions of this Section will \nsurvive termination of this Agreement. \nNo Default shall exist where such failure to discharge an obligation (other \nthan the payment of money) is the result of an Uncontrollable Force or the \nresult of an act or omission of the other Party. Upon a Breach, the non-\nbreaching Party shall give written notice of such Breach to the breaching \nParty. The breaching Party shall have thirty (30) Calendar Days from \nreceipt of the Default notice within which to cure such Breach; provided \nhowever, if such Breach is not capable of cure within thirty (30) Calendar \nDays, the breaching Party shall commence such cure within thirty (30) \nCalendar Days after notice and continuously and diligently complete such \ncure within ninety (90) Calendar Days from receipt of the Default notice; \nand, if cured within such time, the Breach specified in such notice shall \ncease to exist. \n10.0 Consequential Damages. No Party shall be liable under any provision of \nthis Agreement for any losses, damages, costs or expenses for any \nspecial, indirect, incidental, consequential, or punitive damages, including \nbut not limited to loss of profit or revenue, loss of the use of equipment, \ncost of capital, cost of temporary equipment or services, whether based in \nwhole or in part in contract, in tort, including negligence, strict liability, or \nany other theory of liability; provided, however, that damages for which a \nParty may be liable to another Party under another agreement will not be"},{"page":228,"startToken":70507,"endToken":70921,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \nconsidered to be special, indirect, incidental, or consequential damages \nhereunder. \n \n11.0 Indemnity. Each Party shall at all times indemnify, defend, and hold the \nother Parties harmless from, any and all losses arising out of or resulting \nfrom another Party's action or inactions of its obligations under this \nAgreement on behalf of the indemnifying Party, except in cases of gross \nnegligence or intentional wrongdoing by the Indemnified Party. \n \n 12.0 Miscellaneous.  \n \n \n \n12.1 Dispute Resolution. In the event any Party has a dispute, or asserts a \nclaim, that arises out of or in connection with this Agreement, or their \nperformance, such Party (the \"disputing Party\") shall provide the other \nParty with written notice of the dispute or claim (\"Notice of Dispute\"). Such \ndispute or claim shall be resolved in accordance with the Dispute \nResolution Procedures set forth in Section 14 of the TO Tariff.  \n \n12.2 Confidentiality. Confidential Information shall be treated in accordance \nwith the TSRA. \n \n12.3 Binding Effect. This Agreement and the rights and obligations hereof, shall \nbe binding upon and shall inure to the benefit of the successors and \nassigns of the Parties hereto. \n \n12.4 Rules of Interpretation. This Agreement, unless a clear contrary intention \nappears, shall be construed and interpreted as follows: (1) the singular \nnumber includes the plural number and vice versa; (2) reference to any \nperson includes such person’s successors and assigns but, in the case of \na Party, only if such successors and assigns are permitted by this \nAgreement, and reference to a person in a particular capacity excludes \nsuch person in any other capacity or individually; (3) reference to any \nagreement (including this Agreement), document, instrument or tariff \nmeans such agreement, document, instrument, or tariff as amended or \nmodified and in effect from time to time in accordance with the terms \nthereof and, if applicable, the terms hereof; (4) reference to any applicable \nlaws and regulations means such applicable laws and regulations as \namended, modified, codified, or reenacted, in whole or in part, and in \neffect from time to time, including, if applicable, rules and regulations \npromulgated thereunder; (5) unless expressly stated otherwise, reference \nto any Section or Appendix means such Section of this Agreement or such \nAppendix to this Agreement; (6) “hereunder”, “hereof”, “herein”, “hereto” \nand words of similar import shall be deemed references to this Agreement \nas a whole and not to any particular Section, or other provision hereof or"},{"page":229,"startToken":70921,"endToken":71327,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \nthereof; (7) “including” (and with correlative meaning “include”) means \nincluding without limiting the generality of any description preceding such \nterm; and (8) relative to the determination of any period of time, “from” \nmeans “from and including”, “to” means “to but excluding” and “through” \nmeans “through and including”.  \n12.5 Entire Agreement. This Agreement, including all Appendices attached \nhereto, constitutes the entire agreement between the Parties with \nreference to the subject matter hereof, and supersedes all prior and \ncontemporaneous understandings or agreements, oral or written, between \nthe Parties with respect to the subject matter of this Agreement. There are \nno other agreements, representations, warranties, or covenants which \nconstitute any part of the consideration for, or any condition to, any Party’s \ncompliance with its obligations under this Agreement.  \n \n12.6 No Third Party Beneficiaries. This Agreement is not intended to and does \nnot create rights, remedies, or benefits of any character whatsoever in \nfavor of any persons, corporations, associations, or entities other than the \nParties, and the obligations herein assumed are solely for the use and \nbenefit of the Parties, their successors in interest and, where permitted, \ntheir assigns. \n \n12.7 Waiver. The failure of a Party to this Agreement to insist, on any occasion, \nupon strict performance of any provision of this Agreement will not be \nconsidered a waiver of any obligation, right, or duty of, or imposed upon, \nsuch Party.  \n \nAny waiver at any time by either Party of its rights with respect to this \nAgreement shall not be deemed a continuing waiver or a waiver with \nrespect to any other failure to comply with any other obligation, right, or \nduty of this Agreement. Any waiver of this Agreement shall, if requested, \nbe provided in writing. \n \n12.8 Headings. The descriptive headings of the various Sections of this \nAgreement have been inserted for convenience of reference only and are \nof no significance in the interpretation or construction of this Agreement  \n \n12.9 Multiple Counterparts. This Agreement may be executed in two or more \ncounterparts, each of which is deemed an original but all constitute one \nand the same instrument.  \n \n12.10 Amendment. The Parties may by mutual agreement amend this \nAgreement by a written instrument duly executed by the Parties. \n \n12.11 Modification by the Parties. The Parties may by mutual agreement amend \nthe Appendices to this Agreement by a written instrument duly executed"},{"page":230,"startToken":71327,"endToken":71809,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \nby the Parties. Such amendment shall become effective and a part of this \nAgreement upon satisfaction of all applicable laws and regulations. \n \n12.12 Reservation of Rights. The Participating TO shall have the right to make a \nunilateral filing with FERC to modify this Agreement with respect to any \nrates, terms and conditions, charges, classifications of service, rule or \nregulation under section 205 or any other applicable provision of the \nFederal Power Act and FERC’s rules and regulations thereunder, and \nLarge Load Interconnection Customer shall have the right to make a \nunilateral filing with FERC to modify this Agreement pursuant to section \n206 or any other applicable provision of the Federal Power Act and \nFERC’s rules and regulations thereunder; provided that each Party shall \nhave the right to protest any such filing by another Party and to participate \nfully in any proceeding before FERC in which such modifications may be \nconsidered. Nothing in this Agreement shall limit the rights of the Parties \nor of FERC under sections 205 or 206 of the Federal Power Act and \nFERC’s rules and regulations thereunder, except to the extent that the \nParties otherwise mutually agree as provided herein.  \n \n12.13 No Partnership. This Agreement shall not be interpreted or construed to \ncreate an association, joint venture, agency relationship, or partnership \nbetween the Parties or to impose any partnership obligation or partnership \nliability upon any Party. No Party shall have any right, power or authority \nto enter into any agreement or undertaking for, or act on behalf of, or to \nact as or be an agent or representative of, or to otherwise bind, another \nParty.  \n \n12.14 Assignment.  This Agreement may be assigned by either Party only with \nthe written consent of the other; and provided further that Large Load \nInterconnection Customer shall have the right to assign this Agreement, \nwithout the consent of Participating TO, for collateral security purposes to \naid in providing financing for the Large Load, provided that Large Load \nInterconnection Customer will promptly notify Participating TO of any such \nassignment.  Any financing arrangement entered into by Large Load \nInterconnection Customer pursuant to this article will provide that prior to \nor upon the exercise of the secured party’s, trustee’s or mortgagee’s \nassignment rights pursuant to said arrangement, the secured creditor, the \ntrustee or mortgagee will notify Participating TO of the date and particulars \nof any such exercise of assignment right(s), including providing the \nParticipating TO with proof that it meets the requirements of Articles 11.5 \nand 18.3.  Any attempted assignment that violates this article is void and \nineffective.  Any assignment under this Agreement shall not relieve a Party \nof its obligations, nor shall a Party’s obligations be enlarged, in whole or in \npart, by reason thereof.  Where required, consent to assignment will not \nbe unreasonably withheld, conditioned or delayed."},{"page":231,"startToken":71809,"endToken":71877,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \n \n \nIN WITNESS THEREOF, the Parties have caused this Agreement to be duly \nexecuted by their duly authorized officers or agents on the day and year first above \nwritten. \n \n \n[Insert Name of Large Load Interconnection Customer] \n \nBy: \n____________________________________________ \n \n \nName: ____________________________________________ \n \n \nTitle: ____________________________________________ \n \n \nDate: ____________________________________________                          \n \n \nSouthern California Edison Company \n \nBy: \n____________________________________________ \n \n \nName: ____________________________________________ \n \n \nTitle: ____________________________________________ \n \n \nDate: ____________________________________________                          \n \n \nCalifornia Independent System Operator Corporation \n \nBy: \n____________________________________________ \n \n \nName: ____________________________________________ \n \n \nTitle: ____________________________________________ \nDate: ____________________________________________"},{"page":232,"startToken":71877,"endToken":71938,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \n \n \n \nAppendix 1 \nConditions of Curtailment and Implementation Mechanisms \n[Appendix 1 shall specify the circumstances, Contingencies, and operating conditions \nunder which the Large Load may be curtailed; the curtailment mechanism; the entity \nresponsible for implementing the curtailment; and the applicable notification method, \nresponse time, duration, restoration, testing, and verification requirements.]"},{"page":233,"startToken":71938,"endToken":71973,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \n \n \n \n \nAppendix 2 \nConditions and Limitations of FILI \n[Appendix 2 shall specify the interim operating limits applicable both during and outside \nof curtailable events.]"},{"page":234,"startToken":71973,"endToken":71988,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \n \n \n \nAppendix 3 \nNotices"},{"page":235,"startToken":71988,"endToken":72011,"text":"Southern California Edison Company \nFERC Electric Tariff, Third Revised Volume No. 6 \n \n \n \n \n \n \n \n \nAppendix 4 \nUpgrades Required For Full Service Requested Under The TSRA"},{"page":236,"startToken":72011,"endToken":72024,"text":"ATTACHMENT B \n \nRedlined TO Tariff Sheets \nSections 1, 3, 4, 7-10, and 13"},{"page":237,"startToken":72024,"endToken":72289,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n \nTABLE OF CONTENTS \n \n \n1.  PREAMBLE ...............................................................................................................................  \n1.1  Transmission Access for Participating TOs ................................................................  \n1.2  Transmission Access for Wheeling Customers ..........................................................  \n1.3  Transmission Access for End-Users ...........................................................................  \n2.  EFFECTIVE DATE ....................................................................................................................  \n3.  TO DEFINITIONS ......................................................................................................................  \n4.  ELIGIBILITY ..............................................................................................................................  \n5.  ACCESS CHARGES AND TRANSMISSION RATES...............................................................  \n5.1  Low Voltage Access Charge .........................................................................................  \n5.2  Wheeling Access Charge ..............................................................................................  \n5.3  End-User Transmission Rates ......................................................................................  \n5.4  Transmission Revenue Requirement ...........................................................................  \n5.5  Transmission Revenue Balancing Account Adjustment (TRBAA). ...........................  \n5.6  Transmission Access Charge Balancing Account Adjustment (TRBAA). ................  \n6.  ANCILLARY SERVICES - APPLICABILITY AND CHARGES .................................................  \n7.  BILLING AND PAYMENT .........................................................................................................  \n7.1  End-Users .......................................................................................................................  \n7.2  Low Voltage Access Charge Revenues .......................................................................  \n    7.2.1  Billing Procedure ....................................................................................................  \n    7.2.2  Interest on Unpaid Balances ..................................................................................  \n    7.2.3  Default ......................................................................................................................  \n7.3  Wheeling and Usage Charge Revenues .......................................................................  \n8.  OBLIGATION TO INTERCONNECT OR CONSTRUCT TRANSMISSION EXPANSIONS & \nFACILITY UPGRADES ..................................................................................................................  \n8.1  Participating TO Obligation to Interconnect ................................................................  \n    8.1.1  Interconnection to Transmission System .............................................................  \n        8.1.1.1  Letter Agreement .............................................................................................  \n    8.1.2  Costs Associated with Interconnection ................................................................  \n    8.1.3  Interconnection Agreement ...................................................................................  \n    8.1.4  Due Diligence to Construct ....................................................................................  \n    8.1.5  Energization .............................................................................................................  \n    8.1.6  Coordination with ISO on Interconnection Requests ..........................................  \n8.2  Participating TO Obligation to Construct Transmission Expansions or Facility \nUpgrades ................................................................................................................................  \n    8.2.1  Obligation to Construct ..........................................................................................  \n    8.2.2  Local Furnishing Participating TO Obligation to Construct ...............................  \n8.3  Request for FERC Deference Regarding Need Determination ..................................  \n9.  EXPANSION PROCESS ...........................................................................................................  \n9.1  Determination of Facilities ............................................................................................  \n    9.1.1  Payment of Facilities Study’s Cost .......................................................................  \n \n \n         Tariff Record Proposed Effective Date: 06/15/202102/16/27 \n \n \n \n \n                       Version Number: 18.0.0 \n \n \n \n \n \n \n \n \n \n \n             Option Code:  A"},{"page":238,"startToken":72289,"endToken":72603,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n    9.1.1.1  Market Participant to Pay for Facilities Study ...............................................  \n    9.1.1.2  Project Sponsor or Project Proponent to Pay for Facilities Study ..............  \n    9.1.1.3  Principal Beneficiaries to Pay for Facilities Study ........................................  \n    9.1.2  Payment Procedure ................................................................................................  \n    9.1.3  Facilities Study Procedures ...................................................................................  \n9.2  Obligation to Build .........................................................................................................  \n    9.2.1  Due Diligence to Construct ....................................................................................  \n    9.2.2  Delay in Construction or Expansion .....................................................................  \n    9.2.2.1  Alternatives to the Original Facility Additions .............................................. \n    9.2.2.2  Refund Obligation for Unfinished Facility Additions ....................................  \n9.3  Provisions Relating To Transmission Construction On the Systems Of Other \nTOs .........................................................................................................................................  \n    9.3.1  Responsibility for Third Party Additions ..............................................................  \n    9.3.2  Coordination of Third-Party System Additions ....................................................  \n    9.3.3  Expansion by “Local Furnishing Participating TOs” ...........................................  \n10.  INTERCONNECTION PROCESS ...........................................................................................  \n10.1  Applicability ..................................................................................................................  \n10.2  Applications ..................................................................................................................  \n10.3  Interconnection Application ........................................................................................  \n10.4  Review of Completed Interconnection Application ..................................................  \n10.5  Notice of Need for System Impact Study ...................................................................  \n10.6  System Impact Study Cost Reimbursement ..............................................................  \n    10.6.1  Cost Reimbursement ............................................................................................  \n    10.6.2  Multiple Parties ......................................................................................................  \n10.7  System Impact Study Procedures ..............................................................................  \n    10.7.1  Procedures Upon Completion of System Impact Study ....................................  \n10.8   Notice of Need for Facilities Study ............................................................................  \n10.9  Facilities Study Procedures ........................................................................................  \n    10.9.1  Execution of Interconnection Agreement ...........................................................  \n10.10  Partial Interim Service ...............................................................................................  \n10.11  Expedited Interconnection Procedures ...................................................................  \n11.  UNCONTROLLABLE FORCES AND INDEMNIFICATION ....................................................  \n11.1  Procedures To Follow if Uncontrollable Force Occurs ............................................  \n11.2  Indemnification .............................................................................................................  \n12.  REGULATORY FILINGS .........................................................................................................  \n12.1  Open Access ................................................................................................................  \n        12.2  STRANDED COST RECOVERY ...................................................................................  \n13.  CREDITWORTHINESS ...........................................................................................................  \n13.1  UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low \nVoltage Transmission Facilities ..........................................................................................  \n13.2  End-Users .....................................................................................................................  \n14.  DISPUTES ...............................................................................................................................  \n15.  RECOVERY OF RELIABILITY SERVICES COSTS ...............................................................  \n16.  MISCELLANEOUS ..................................................................................................................  \n16.1  Notices ..........................................................................................................................  \n16.2  Waiver ...........................................................................................................................  \n16.3  Confidentiality ..............................................................................................................  \n    16.3.1  Maintaining Confidentiality If Not for Public Disclosure ...................................  \n    16.3.2  Disclosure of Confidential Information ..............................................................."},{"page":239,"startToken":72603,"endToken":72759,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n16.4  TO Tariff Supersedes Existing Tariffs ........................................................................  \n16.5  Titles ..............................................................................................................................  \n16.6  Severability ...................................................................................................................  \n16.7  Preservation of Obligations ........................................................................................  \n16.8  Governing Law .............................................................................................................  \n16.9  Appendices Incorporated ............................................................................................  \n16.10  Conflict With ISO Tariff ..............................................................................................  \n16.11  Conflicting Operating Instructions ...........................................................................  \n16.12  Self Provision of Ancillary Services .........................................................................  \n \n \nAPPENDIX I - TRANSMISSION REVENUE REQUIREMENT .......................................................  \nAPPENDIX II - CHARGES FOR WHOLESALE TRANSMISSION SERVICES .............................  \nAPPENDIX III – TRANSMISSION RATES FOR END-USE SERVICE ..........................................  \nAPPENDIX IV – RATES FOR CERTAIN ANCILLARY SERVICE BIDS .......................................  \nAPPENDIX V - NOTICES ...............................................................................................................  \nAPPENDIX VI - RELIABILITY SERVICES RATE SCHEDULE .....................................................  \nAPPENDIX VII - INTERCONNECTION PROCEDURES IN EFFECT PRIOR TO JULY 1, 2005 ...  \nAPPENDIX VIII – NOT USED .........................................................................................................  \nAPPENDIX IX – FORMULA RATE ................................................................................................  \nAPPENDIX X – RATE SCHEDULE FOR RECOVERY OF COSTS ASSOCIATED WITH \nFACILITIES INSTALLED PURSUANT TO INTERCONNECTION AGREEMENTS.…………….. \nAPPENDIX XI – TRANSMISSION MAINTENANCE AND COMPLIANCE REVIEW .....................  \nAPPENDIX XII – STAKEHOLDER REVIEW PROCESS ...............................................................  \nAPPENDIX XIII – LETTER AGREEMENT .....................................................................................  \nAPPENDIX XIV -  WEST OF DEVERS FORMULA RATE……………………………….................. \nAPPENDIX XV – LARGE LOAD INTERCONNECTION PROCEDURES………………………….."},{"page":240,"startToken":72759,"endToken":73001,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n1.  Preamble.  \nThe Participating TO's revenue requirements and applicable rates and charges for \ntransmission access over the ISO Controlled Grid and the terms and conditions for \ntransmission expansion and interconnection are set forth in this TO Tariff and the ISO \nTariff. \n1.1  Transmission Access for Participating TOs. \nParticipating TOs are able to participate in the ISO and utilize the entire ISO Controlled \nGrid to serve their End-Use Customers.  The applicable High Voltage Access Charges \nand Transition Charges shall be paid by Participating TOs to the ISO pursuant to the \nISO Tariff.  If a Participating TO utilizes the Low Voltage Transmission Facilities of \nanother Participating TO, such Participating TO shall also pay the Low Voltage Access \nCharge of the other Participating TO.  \n1.2  Transmission Access for Wheeling Customers. \nWheeling allows Scheduling Coordinators to deliver Energy through or out of the ISO \nControlled Grid to serve a load located outside the transmission or Distribution System \nof a Participating TO.  Wheeling Access Charges shall be paid by Scheduling \nCoordinators to the ISO pursuant to the ISO Tariff. \n1.3  Transmission Access for End-Users.   \nEnd-Users receive transmission service over the ISO Controlled Grid through the Utility \nDistribution Company, Small Utility Distribution Company, or MSS OperatorParticipating \nTO to whose transmission or distribution facilities the End-User is directly connected.  \nCharges to End-Users for access to the ISO Controlled Grid  shall be paid to the"},{"page":241,"startToken":73001,"endToken":73036,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \napplicable Utility Distribution Company, Small Utility Distribution Company, or MSS \nOperatorParticipating TO to whose transmission or distribution facilities the End-User is \ndirectly connected."},{"page":242,"startToken":73036,"endToken":73291,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n3.  TO Definitions. \nCapitalized terms used in this TO Tariff shall have the meanings set out below or in \nAppendix XV unless otherwise stated.  Capitalized terms used in this tariff and not \ndefined below or in Appendix XV shall have the meanings set out in the ISO Tariff. \n3.1 \nAccess Charge.  A charge paid by all UDCs, MSSs and, in certain cases, \nScheduling Coordinators, delivering Energy to Gross Load, as set forth in Section 26.1 \nof the ISO Tariff.  The Access Charge includes the High Voltage Access Charge, the \nTransition Charge, and the Low Voltage Access Charge. \n3.2 \nAutomatic Generation Control (AGC).  Generation equipment that \nautomatically responds to signals from the ISO’s EMS control in real time to control the \npower output of electric generators within a prescribed area in response to a change in \nsystem frequency, tieline loading, or the relation of these to each other, so as to \nmaintain the target system frequency and/or the established interchange with other \nareas within the predetermined limits. \n3.3 \nAncillary Services.  Regulation, Spinning Reserve, Non-Spinning Reserve, \nVoltage Support and Black Start together with such other interconnected operation \nservices as the ISO may develop in cooperation with Market Participants to support the \ntransmission of Energy from Generation resources to Loads while maintaining reliable \noperation of the ISO Controlled Grid in accordance with Good Utility Practice. \n \n \n                        Tariff Record Proposed Effective Date: 05/01/2026 \n \n  \n \n                           Version Number: 16.0.0 \n \n \n \n \n \n \n \n \n \n \n \nOption Code:  A"},{"page":243,"startToken":73291,"endToken":73497,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n \n3.4 \nApplicable Reliability Criteria.  The reliability standards established by NERC, \nWECC, and Local Reliability Criteria as amended from time to time, including any \nrequirements of the Nuclear Regulatory Commission. \n3.5 \nAvailable Transfer Capacity.  For a given transmission path, the capacity rating \nin MW of the path established consistent with ISO and WECC transmission capacity \nrating guidelines, less any reserved uses applicable to the path. \n3.6 \nBase Transmission Revenue Requirement.  The Transmission Revenue \nRequirement before deducting the Transmission Revenue Balancing Account \nAdjustment (TRBAA) and, for wholesale purposes, before deducting Standby \nTransmission Revenues. \n3.7 \nBlack Start.  The procedure by which a Generating Unit self-starts without an \nexternal source of electricity thereby restoring power to the ISO Controlled Grid \nfollowing system or local area blackouts. \n3.8 \nBusiness Day.  Monday through Friday, excluding federal holidays and the day \nafter Thanksgiving Day. \n3.9 \n(Omitted) \n3.10 Completed Application Date.  The date on which a party submits an \nInterconnection Application that satisfies the requirements of a Completed \nInterconnection Application.  \n3.11 Completed Interconnection Application.  An Interconnection Application that \nsatisfies all of the information and other requirements of Section 10.3 of this TO Tariff."},{"page":244,"startToken":73497,"endToken":73766,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.12 Congestion.  A condition that occurs when there is insufficient Available \nTransfer Capacity to implement all Preferred Schedules simultaneously or, in real time, \nto serve all Generation and Demand.  “Congested” shall be construed accordingly. \n3.13 Congestion Management.  The alleviation of Congestion in accordance with \napplicable ISO Protocols and Good Utility Practice. \n3.14 Converted Rights.  Those transmission service rights as defined in Section \n4.3.1.6 of the ISO Tariff. \n3.15 CPUC.  The California Public Utilities Commission, or its successor. \n3.16 (Omitted) \n3.17 Demand.  The rate at which Energy is delivered to Loads and Scheduling Points \nby Generation, transmission or distribution facilities.  It is the product of voltage and the \nin-phase component of alternating current measured in units of watts or standard \nmultiples thereof, e.g., 1,000W = 1kW, 1,000kW = 1MW, etc. \n3.18 Direct Assignment Facilities.  Facilities or portions of facilities that are owned \nby the Participating TO necessary to physically and electrically interconnect a particular \nparty requesting Interconnection under this TO Tariff to the ISO Controlled Grid at the \npoint of interconnection.  Direct Assignment Facilities shall be specified in the \nInterconnection Agreement that governs Interconnection service to such party and shall \nbe subject to FERC approval.  \n3.19 Dispatch.  The operating control of an integrated electric system to: i) assign \nspecific Generating Units and other sources of supply to effect the supply to meet the \nrelevant area Demand taken as Load rises or falls; ii) control operations and \nmaintenance of high voltage lines, substations, and equipment, including administration"},{"page":245,"startToken":73766,"endToken":74063,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nof safety procedures; iii) operate interconnections; iv) manage Energy transactions with \nother interconnected Control Areas; and v) curtail Demand.   \n3.20 Distribution System.  The distribution assets of a TO, UDC, or MSS.   \n3.21 Eligible Customer.  (i) Any utility (including Participating TOs, Market \nParticipants and any power marketer), Federal power marketing agency, or any person \ngenerating Energy for sale or resale; Energy sold or produced by such entity may be \nEnergy produced in the United States, Canada or Mexico; however, such entity is not \neligible for transmission service that would be prohibited by Section 212(h)(2) of the \nFederal Power Act; and (ii) any retail customer taking unbundled transmission service \npursuant to a state retail access program or pursuant to a voluntary offer of unbundled \nretail transmission service by the Participating TO. \n3.22 Encumbrance.  A legal restriction or covenant binding on the Participating TO \nthat affects the operation of any transmission lines or associated facilities and which the \nISO needs to take into account in exercising Operational Control over such transmission \nlines or associated facilities if the Participating TO is not to risk incurring significant \nliability.  Encumbrances shall include Existing Contracts and may include:  (1) other \nlegal restrictions or covenants meeting the definition of Encumbrance and arising under \nother arrangements entered into before the ISO Operations Date, if any; and (2) legal \nrestrictions or covenants meeting the definition of Encumbrance and arising under a \ncontract or other arrangement entered into after the ISO Operations Date.  \n3.23 End-Use Customer or End-User.  A purchaser of electric power who purchases \nsuch power to satisfy a Load directly connected to the ISO Controlled Grid or to a \nDistribution System and who does not resell the power."},{"page":246,"startToken":74063,"endToken":74327,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.24 Energy.  The electrical energy produced, flowing or supplied by generation, \ntransmission or distribution facilities, being the integral with respect to time of the \ninstantaneous power, measured in units of watt-hours or standard multiples thereof, \ne.g., 1,000 Wh = 1kWh, 1,000 kWh = 1MWh, etc. \n3.25 Entitlements.  The right of the Participating TO obtained through contract or \nother means to use another entity's transmission facilities for the transmission of \nEnergy.  \n3.26 Existing Contracts.  The contracts which grant transmission service rights in \nexistence on the ISO Operations Date (including any contracts entered into pursuant to \nsuch contracts) as may be amended in accordance with their terms or by agreement \nbetween the parties thereto from time to time. \n3.27 Existing Rights.  The transmission service rights and obligations of non-\nParticipating TOs under Existing Contracts, including all terms, conditions, and rates of \nthe Existing Contracts, as they may change from time to time under the terms of the \nExisting Contracts. \n3.28 Expedited Interconnection Agreement.  A contract between a party which has \nsubmitted a Request for Expedited Interconnection Procedures and the Participating TO \nunder which the Participating TO agrees to process, on an expedited basis, the \nCompleted Interconnection Application of such party and which sets forth the terms, \nconditions, and cost responsibilities for such interconnection.   \n3.29 Facilities Study Agreement.  An agreement between a Participating TO and \neither a party requesting Interconnection to the ISO Controlled Grid, Market Participant, \nProject Sponsor, or identified principal beneficiaries pursuant to which the party"},{"page":247,"startToken":74327,"endToken":74604,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nrequesting such Interconnection, Market Participants, Project Sponsor, or identified \nprincipal beneficiaries agrees to reimburse the Participating TO for the cost of \nperforming or reviewing a Facilities Study. \n3.30 Facility or Facilities Study.  An engineering study conducted to determine \nrequired modifications to the Participating TO’s transmission system, including the \nestimated cost and scheduled completion date for such modifications that will be \nrequired to provide needed services. \n3.31 FERC.  The Federal Energy Regulatory Commission or its successor.  \n3.32 FPA.  Parts II and III of the Federal Power Act, 16 U.S.C. § 824 et seq., as they \nmay be amended from time to time. \n3.33 FTR (Firm Transmission Right).  A contractual right, subject to the terms and \nconditions of the ISO Tariff, that entitles the FTR Holder to receive, for each hour of the \nterm of the FTR, a portion of the Usage Charges received by the ISO for transportation \nof energy from a specific originating Zone to a specific receiving Zone and, in the event \nof an uneconomic curtailment to manage Day-Ahead congestion, to a Day-Ahead \nscheduling priority higher than that of a schedule using Converted Rights capacity that \ndoes not have an FTR.  \n3.34 FTR Holder.  The owner of an FTR, as registered with the ISO.  \n3.35 Generating Unit.  An individual electric generator and its associated plant and \napparatus whose electrical output is capable of being separately identified and metered \nor a Physical Scheduling Plant that, in either case, is: (a) located within the ISO Control \nArea; (b) connected to the ISO Controlled Grid, either directly or via interconnected"},{"page":248,"startToken":74604,"endToken":74917,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ntransmission, or distribution facilities; and (c) that is capable of producing and delivering \nnet Energy (Energy in excess of a generating station’s internal power requirements). \n3.36 Generation.  Energy delivered from a Generating Unit. \n3.37 Good Utility Practice.  Any of the practices, methods, and acts engaged in or \napproved by a significant portion of the electric utility industry during the relevant time \nperiod, or any of the practices, methods, and acts which, in the exercise of reasonable \njudgment in light of the facts known at the time the decision was made, could have been \nexpected to accomplish the desired result at a reasonable cost consistent with good \nbusiness practices, reliability, safety, and expedition.  Good Utility Practice is not \nintended to be any one of a number of the optimum practices, methods, or acts to the \nexclusion of all others, but rather to be acceptable practices, methods, or acts generally \naccepted in the region. \n3.38 Gross Load.  Gross Load is all Energy (adjusted for distribution losses) \ndelivered for the supply of End-User Loads directly connected to the transmission \nfacilities or Distribution System of the Participating TO.  Gross Load shall exclude the \nportion of the Load of an individual End-Use Customer of the Participating TO that is \nserved by a Generating Unit that: (a) is located on the customer's site or provides \nservice to the customer's site through over-the-fence arrangements as authorized by \nSection 218 of the California Public Utilities Code; (b) is a qualifying small power \nproduction facility or qualifying cogeneration facility, as those terms are defined in the \nFERC's regulations implementing Section 201 of the Public Utility Regulatory Policies \nAct of 1978; (c) was serving the customer's Load on or before March 31, 2000; and (d) \nsecured Standby Service from the Participating TO under terms approved by a Local"},{"page":249,"startToken":74917,"endToken":75194,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nRegulatory Authority or FERC, as applicable, as of March 31, 2000 and continues to \nsecure Standby Service from the Participating TO or can be curtailed concurrently with \nan outage of the Generating Unit serving the Load. \n3.39 High Voltage Access Charge.  A component of the Access Charge determined \nby the ISO and assessed to the Participating TO under Section 26.1 of the ISO Tariff. \n3.40 High Voltage Existing Contracts Access Charge.  A charge for access to the \nISO Controlled Grid under certain specified Existing Contracts to be paid by the Existing \nContract holder to the Participating TO.  Such rate shall be calculated by dividing the \nHigh Voltage Transmission Revenue Requirement applicable to wholesale customers \nby the sum of Edison’s twelve monthly retail system peak demands measured at the \nISO Controlled Grid level, consistent with such revenue requirement.    \n3.41 High Voltage Transmission Facility.  A transmission facility under the \noperational control of the ISO that is owned by the Participating TO or to which the \nParticipating TO has an Entitlement that is represented by a Converted Right and that \noperates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs \nof which are not directly assigned to one or more specific customers. \n3.42 High Voltage Transmission Revenue Requirement.  The portion of the \nParticipating TO's TRR associated with and allocable to the Participating TO's High \nVoltage Transmission Facilities and Converted Rights associated with High Voltage \nTransmission Facilities.  \n3.43 High Voltage Utility-Specific Rate.  The Participating TO's High Voltage \nTransmission Revenue Requirement divided by the Participating TO's forecasted Gross \nLoad."},{"page":250,"startToken":75194,"endToken":75452,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.44 High Voltage Wheeling Access Charge.  The Wheeling Access Charge \nassessed by the ISO associated with the recovery of the Participating TOs' High \nVoltage Transmission Revenue Requirements in accordance with Section 26.1 of the \nISO Tariff. \n3.45 (Omitted) \n3.46 Interconnection.  Transmission facilities, other than additions or replacements \nto existing facilities that: i) connect one system to another system where the facilities \nemerge from one and only one substation of the two systems and are functionally \nseparate from the ISO Controlled Grid facilities such that the facilities are, or can be, \noperated and planned as a single facility; or ii) are identified as radial transmission lines \npursuant to contract; or iii) produce Generation at a single point on the ISO Controlled \nGrid; provided that such interconnection does not include facilities that, if not owned by \nthe Participating TO, would result in a reduction in the ISO’s Operational Control of the \nParticipating TO’s portion of the ISO Controlled Grid. \n3.47 Interconnection Agreement.  A contract between a party requesting \nInterconnection and the Participating TO that owns the transmission facility with which \nthe requesting party wishes to interconnect. \n3.48 Interconnection Application.   An application that requests Interconnection to \nthe ISO Controlled Grid. \n3.49 Interest.  Interest shall be calculated in accordance with the methodology \nspecified for interest on refunds in the regulations of FERC at 18 C.F.R. \n§35.19(a)(2)(iii)(1996).  Interest on delinquent amounts shall be calculated from the due"},{"page":251,"startToken":75452,"endToken":75702,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ndate of the bill to the date of payment.  When payments are made by mail, bills shall be \nconsidered as having been paid on the date of receipt. \n3.50 Independent System Operator (“ISO”).  The California Independent System \nOperator Corporation, a state chartered, nonprofit corporation that controls the \ntransmission facilities of all Participating TOs and dispatches certain Generating Units \nand Loads. \n3.51 ISO ADR Procedures.  The procedures for resolution of disputes or differences \nset out in Section 13 of the ISO Tariff, as amended from time to time. \n3.52 ISO Controlled Grid.  The system of transmission lines and associated facilities \nof the Participating TOs that have been placed under the ISO’s Operational Control.  \n3.53 ISO Protocols.  The rules, protocols, procedures and standards promulgated by \nthe ISO (as amended from time to time) to be complied with by the ISO Scheduling \nCoordinators, Participating TOs and all other Market Participants in relation to the \noperation of the ISO Controlled Grid and the participation in the markets for Energy and \nAncillary Services in accordance with the ISO Tariff. \n3.54 ISO Tariff.  The California Independent System Operator Agreement and Tariff, \ndated March 31, 1997, as it may be modified from time to time. \n3.55 Load.  An end-use device of an End-Use Customer that consumes power.  Load \nshould not be confused with Demand, which is the measure of power that a Load \nreceives or requires. \n3.56 (Omitted)"},{"page":252,"startToken":75702,"endToken":75966,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.57 Local Furnishing Bond.  Tax-exempt bonds utilized to finance facilities for the \nlocal furnishing of electric energy, as described in section 142(f) of the Internal Revenue \nCode, 26 U.S.C. § 142(f). \n3.58 Local Furnishing Participating TO.  Any Tax-Exempt Participating TO that \nowns facilities financed by Local Furnishing Bonds. \n3.59 Local Publicly Owned Electric Utilities.  A municipality or municipal \ncorporation operating as a public utility furnishing electric service, a municipal utility \ndistrict furnishing electric service, a public utility district furnishing electric services, an \nirrigation district furnishing electric services, or a joint powers authority that includes one \nor more of these agencies and that owns Generation or transmission facilities, or \nfurnishes electric services over its own or its members’ electric Distribution System. \n3.60 Local Regulatory Authority.  The state or local governmental authority \nresponsible for the regulation or oversight of a utility.  \n3.61 Local Reliability Criteria.  Reliability criteria established at the ISO Operations \nDate, unique to the transmission systems of each of the Participating TOs. \n3.62 Low Voltage Access Charge.  The Access Charge applicable under Section \n26.1 of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement \nof the Participating TO. \n3.63 Low Voltage Existing Contracts Access Charge.  A charge for access to the \nISO Controlled Grid under certain specified Existing Contracts to be paid by the Existing \nContract holder to the Participating TO.  Such rate shall be calculated by dividing the \nLow Voltage Transmission Revenue Requirement applicable to wholesale customers by"},{"page":253,"startToken":75966,"endToken":76236,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nthe sum of Edison’s twelve monthly retail system peak demands measured at the ISO \nControlled Grid level, consistent with such revenue requirement.    \n3.64 Low Voltage Transmission Facility.  A transmission facility under the \noperational control of the ISO owned by the Participating TO or to which the \nParticipating TO has an Entitlement that is represented by a Converted Right, which is \nnot a High Voltage Transmission Facility, and supporting facilities, and the costs of \nwhich are not directly assigned to one or more specific customers. \n3.65 Low Voltage Transmission Revenue Requirement.  The portion of the \nParticipating TO's TRR associated with and allocable to the Participating TO's Low \nVoltage Transmission Facilities and Converted Rights associated with Low Voltage \nTransmission Facilities. \n3.66 Low Voltage Wheeling Access Charge.  The Wheeling Access Charge \nassociated with the recovery of the Participating TO's Low Voltage Transmission \nRevenue Requirement in accordance with Section 26.1 of the ISO Tariff. \n3.67 Market Participant.  An entity, including a Scheduling Coordinator, who \nparticipates in the Energy marketplace through the buying, selling, transmission, or \ndistribution of Energy or Ancillary Services into, out of, or through the ISO Controlled \nGrid.  \n3.68 MSS (Metered Subsystem).  A geographically contiguous system located within \na single zone which has been operating as an electric utility for a number of years prior \nto the ISO Operations Date as a municipal utility, water district, irrigation district, State \nagency or Federal power administration subsumed within the ISO Control Area and \nencompassed by ISO certified revenue quality meters at each interface point with the"},{"page":254,"startToken":76236,"endToken":76492,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nISO Controlled Grid and ISO certified revenue quality meters on all Generating Units or, \nif aggregated, each individual resource and Participating Load internal to the system, \nwhich is operated in accordance with a MSS agreement described in Section 4.9.1 of \nthe ISO Tariff. \n3.69 NERC.  The North American Electric Reliability Council or its successor. \n3.70 (Omitted) \n3.71 (Omitted) \n3.72 New High Voltage Transmission Facility.  A High Voltage Transmission \nFacility of the Participating TO that enters service after the beginning of the transition \nperiod described in Section 4 of Schedule 3 of Appendix F of the ISO Tariff, or a capital \naddition made after the beginning of the transition period described in Section 4.2 of \nSchedule 3 of Appendix F of the ISO Tariff to an Existing High Voltage Transmission \nFacility. \n3.73 New Participating TO.  A Participating TO that is not an Original Participating \nTO. \n3.74 Non-Participating TO.  A TO that is not a party to the TCA or for the purposes of \nSection 16.1 of the ISO Tariff the holder of transmission service rights under an Existing \nContract that is not a Participating TO. \n3.75 Non-Spinning Reserve.   The portion of off-line generating capacity that is \ncapable of being synchronized and ramping to a specified load in ten minutes (or load \nthat is capable of being interrupted in ten minutes) and that is capable of running (or \nbeing interrupted) for at least two hours."},{"page":255,"startToken":76492,"endToken":76799,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.76 Operational Control.  The rights of the ISO under the Transmission Control \nAgreement and the ISO Tariff to direct Participating TOs how to operate their \ntransmission lines and facilities and other electric plant affecting the reliability of those \nlines and facilities for the purpose of affording comparable non-discriminatory \ntransmission access and meeting Applicable Reliability Criteria. \n3.77 Original Participating TO.  A Participating TO that was a Participating TO as of \nJanuary 1, 2000.  The Original Participating TOs are Pacific Gas and Electric Company, \nSouthern California Edison Company, and San Diego Gas & Electric Company. \n3.78 Participating TO.  A party to the TCA whose application under Section 2.2 of the \nTCA has been accepted and who has placed its transmission assets and Entitlements \nunder the ISO’s Operational Control in accordance with the TCA.  A Participating TO \nmay be an Original Participating TO or a New Participating TO.  For purposes of this TO \nTariff, the Participating TO is Southern California Edison Company.  \n3.79 Participation Agreement.  An agreement between a Participating TO and a \nProject Sponsor that specifies the terms and conditions under which the Participating \nTO will construct a transmission addition or upgrade on behalf of the Project Sponsor. \n3.80 Physical Scheduling Plant.  A group of two or more related Generating Units, \neach of which is individually capable of producing Energy, but which either by physical \nnecessity or operational design must be operated as if they were a single Generating \nUnit and any Generating Unit or Units containing related multiple generating \ncomponents which meet one or more of the following criteria: i) multiple generating \ncomponents are related by a common flow of fuel which cannot be interrupted without a \nsubstantial loss of efficiency of the combined output of all components; ii) the Energy"},{"page":256,"startToken":76799,"endToken":77069,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nproduction from one component necessarily causes Energy production from other \ncomponents; iii) the operational arrangement of related multiple generating components \ndetermines the overall physical efficiency of the combined output of all components; iv) \nthe level of coordination required to schedule individual generating components would \ncause the ISO to incur scheduling costs far in excess of the benefits of having \nscheduled such individual components separately; or v) metered output is available only \nfor the combined output of related multiple generating components and separate \ngenerating component metering is either impractical or economically inefficient. \n3.81 (Omitted)  \n3.82 Project Proponent.  A Market Participant or group of Market Participants that: (i) \nadvocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the \nproposed transmission addition and upgrade, and thus is not a Project Sponsor; and (iii) \ninitiates proceedings under the ISO ADR Procedures to determine the need for the \nproposed transmission addition or upgrade. \n3.83 Project Sponsor.  A Market Participant or group of Market Participants or a \nParticipating TO that proposes the construction of a transmission addition or upgrade in \naccordance with Section 24 of the ISO Tariff. \n3.84 Regional Transmission Group (“RTG”).  A voluntary organization approved by \nFERC and composed of transmission owners, transmission users, and other entities, \norganized to efficiently coordinate the planning, expansion and use of transmission on a \nregional and inter-regional basis. \n3.85 Regulation.  The service provided either by Generating Units certified by the ISO \nas equipped and capable of responding to the ISO’s direct digital control (AGC) signals,"},{"page":257,"startToken":77069,"endToken":77362,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nor by System Resources that have been certified by the ISO as capable of delivering \nsuch service to the ISO Balancing Authority Area, in an upward and downward direction \nto match, on a Real-Time basis, Demand and resources, consistent with established \nApplicable Reliability Criteria.  Regulation is used to control the power output of electric \ngenerators within a prescribed area in response to a change in system frequency, tieline \nloading, or the relation of these to each other so as to maintain the target system \nfrequency and/or the established Interchange with other Balancing Authority Areas \nwithin the predetermined Regulation Limits.  Regulation includes both the increase of \noutput by a Generating Unit or System Resource (Regulation Up) and the decrease in \noutput by a Generating Unit or System Resource (Regulation Down).  Regulation Up \nand Regulation Down are distinct capacity products, with separately stated \nrequirements and ASMPs in each Settlement Period.  \n3.86 Reliability Criteria.  Pre-established criteria that are to be followed in order to \nmaintain desired performance of the ISO Controlled Grid under contingency or steady \nstate conditions. \n3.87 Reliability Services.  Those services provided by the ISO:  1) that are deemed \nby the ISO as necessary to maintain reliable electric service in the ISO Control Area; \nand 2) whose costs are billed by the ISO to the Participating TO pursuant to the ISO \nTariff.  Reliability Services include services obtained from:  Reliability Must-Run units; \nand generators committed pursuant to the ISO’s Exceptional Dispatch authority, which \nincludes any costs of Exceptional Dispatches as well as any default costs allocated to \nthe Participating TO resulting from its incurrence of Exceptional Dispatch costs pursuant \nto Section 11.29.17.2.1 of the CAISO Tariff."},{"page":258,"startToken":77362,"endToken":77594,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.88 Reliability Upgrade.  The transmission facilities, other than Direct Assignment \nFacilities, beyond the first point of Interconnection necessary to interconnect a \nwholesale load safely and reliably to the ISO Controlled Grid, which would not have \nbeen necessary but for the Interconnection of a wholesale load, including network \nupgrades necessary to remedy short circuit or stability problems resulting from the \ninterconnection of a wholesale load to the ISO Controlled Grid.  Reliability Upgrades \nalso include, consistent with WECC practice, the facilities necessary to mitigate any \nadverse impact a wholesale load’s interconnection may have on a path’s WECC path \nrating.  Reliability Upgrades shall be specified in the Interconnection Agreement that \ngoverns Interconnection service to the wholesale load and shall be subject to FERC \napproval.   \n3.89 (Omitted).   \n3.90 Request for Expedited Interconnection Procedures.  A written request by \nwhich an applicant for Interconnection can request expedited processing of its \nInterconnection Application. \n3.91 Scheduling Coordinator.  An entity certified by the ISO for the purposes of \nundertaking the functions specified in Section 4.5.3 of the ISO Tariff. \n3.92 Scheduling Point.  A location at which the ISO Controlled Grid is connected, by \na group of transmission paths for which a physical, non-simultaneous transmission \ncapacity rating has been established for Congestion Management, to transmission \nfacilities that are outside the ISO’s Operational Control."},{"page":259,"startToken":77594,"endToken":77863,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.93 Spinning Reserve.  The portion of unloaded synchronized generating capacity \nthat is immediately responsive to system frequency and that is capable of being loaded \nin ten minutes, and that is capable of running for at least two hours. \n3.94 Standby Rate.  A rate assessed a Standby Service Customer by the \nParticipating TO, as approved by the Local Regulatory Authority, or FERC, as \napplicable, for Standby Service which compensates the Participating TO, among other \nthings, for costs of High Voltage Transmission Facilities. \n3.95 Standby Service.  Service provided by the Participating TO which allows a \nStandby Service Customer, among other things, access to High Voltage Transmission \nFacilities for the delivery of backup power on an instantaneous basis to ensure that \nEnergy may be reliably delivered to the Standby Service Customer in the event of an \noutage of a Generating Unit serving the customer's Load. \n3.96 Standby Service Customer.  A retail End-Use Customer of the Participating TO \nthat receives Standby Service and pays a Standby Rate. \n3.97 Standby Transmission Revenue.  The transmission rate revenues associated \nwith Standby Service collected by the Participating TO from those Standby Service \nCustomers who are not billed for Standby Service on a Gross Load basis.   \n3.98 System Impact Study.  An engineering study conducted to determine whether a \nrequest for Interconnection to the ISO Controlled Grid would require new transmission \nadditions, upgrades, or other mitigation measures.  \n3.99 System Impact Study Agreement.  An agreement between a Participating TO \nand an entity that has requested Interconnection to the Participating TO’s transmission"},{"page":260,"startToken":77863,"endToken":78134,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nsystem pursuant to which the entity requesting Interconnection agrees to reimburse the \nParticipating TO for the cost of performing or reviewing a System Impact Study. \n3.100 TO Tariff.  This Transmission Owner Tariff, as it may be amended or \nsuperseded. \n3.101 Transition Charge.  A component of the Access Charge determined by the ISO \nand assessed the Participating TO along with the High Voltage Access Charge in \naccordance with Section 5.7 of Appendix F, Schedule 3 of the ISO Tariff. \n3.102 Transmission Access Charge Balancing Account Adjustment (\"TACBAA\").  \nA mechanism established by the Participating TO which will ensure that the difference \nbetween (i) the actual charges by the ISO pursuant to Section 26.1.2 of the ISO Tariff \nfor the High Voltage Access Charge and Transition Charge and (ii) the revenues \ndisbursed by the ISO pursuant to Section 26.1.3 of the ISO Tariff are recovered from \nthe Participating TO's End-Use Customers. \n3.103 Transmission Control Agreement (“TCA”).  The agreement between the ISO \nand Participating TOs establishing the terms and conditions under which TOs will \nbecome Participating TOs and how the ISO and each Participating TO will discharge \ntheir respective duties and responsibilities, as may be modified from time to time. \n3.104 Transmission Owner (“TO”).  An entity owning transmission facilities or having \nfirm contractual rights to use transmission facilities.  \n3.105 Transmission Revenue Balancing Account Adjustment (“TRBAA”).  A \nmechanism established by the Participating TO which will ensure that all Transmission \nRevenue Credits and other credits specified in Sections 6 and 8 of Appendix F,"},{"page":261,"startToken":78134,"endToken":78403,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nSchedule 3 of the ISO Tariff, flow through to ISO Tariff and TO Tariff transmission \ncustomers. \n3.106 Transmission Revenue Credit.  The sum of:  1) the revenues received by the \nParticipating TO from the ISO for Wheeling service, including EDAM Recoverable \nRevenue; (2) the difference between the costs incurred by the Participating TO \nassociated with Existing Rights and the amount of such costs recovered by the \nParticipating TO from the Existing Rights customers (“ETC Cost Differentials”); and (3) \nany additional appropriate amounts included in the ISO Tariff definition of Transmission \nRevenue Credit set forth in Appendix A of the CAISO Tariff ; and (4) any remaining \nInterconnection Financial Security under the TSRA that has been drawn down by \nParticipating TO. \n3.107 Transmission Revenue Requirement (“TRR”).  The TRR is the total annual \nauthorized revenue requirements associated with transmission facilities and \nEntitlements turned over to the Operational Control of the ISO by the Participating TO, \nincluding the Projects under construction identified in Appendix VIII that are to be turned \nover to the Operational Control of the ISO upon completion.  The costs of any \ntransmission facility turned over to the Operational Control of the ISO, including the \ncosts of the Projects under construction identified in Appendix VIII that are to be turned \nover to the Operational Control of the ISO upon completion, shall be fully included in the \nParticipating TO's TRR.  The TRR includes the costs of transmission facilities and \nEntitlements and deducts Transmission Revenue Credits; for wholesale purposes, \ncredits for Standby Transmission Revenue; and the transmission revenue expected to"},{"page":262,"startToken":78403,"endToken":78651,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nbe actually received by the Participating TO for Existing Rights and Converted Rights.  \nThe TRR is shown in Appendix I. \n3.108 Uncontrollable Force.  Any act of God, labor disturbance, act of the public \nenemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, \norder, regulation or restriction imposed by governmental, military or lawfully established \ncivilian authorities or any other cause beyond the reasonable control of the ISO or \nMarket Participant which could not be avoided through the exercise of Good Utility \nPractice. \n3.109 Usage Charge.  The amount of money, per 1 kW of scheduled flow, that the ISO \ncharges a Scheduling Coordinator for use of a specific congested Inter-Zonal Interface \nduring a given hour. \n3.110 Utility Distribution Company (“UDC”).  An entity that owns a Distribution \nSystem for the delivery of Energy to and from the ISO Controlled Grid, and that provides \nregulated retail electric service to Eligible Customers, as well as regulated procurement \nservice to those End-Use Customers who are not yet eligible for direct access, or who \nchoose not to arrange services through another retailer. \n3.111 Voltage Support.  Services provided by Generating Units or other equipment \nsuch as shunt capacitors, static var compensators, or synchronous condensers that are \nrequired to maintain established grid voltage criteria.  This service is required under \nnormal or system emergency conditions. \n3.112 Western Electricity Coordinating Council (“WECC”).  The Western Systems \nCoordinating Council or its successor."},{"page":263,"startToken":78651,"endToken":78892,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n3.113 Wheeling Access Charge.  The charge assessed by the ISO that is paid by a \nScheduling Coordinator for Wheeling in accordance with Section 26.1 of the ISO Tariff.  \nWheeling Access Charges shall not apply for Wheeling under a bundled non-economy \nEnergy coordination agreement of a Participating TO executed prior to July 9, 1996.  \nThe Wheeling Access Charge may consist of a High Voltage Wheeling Access Charge \nand a Low Voltage Wheeling Access Charge. \n3.114 Wheeling Out.  Except for Existing Rights exercised under an Existing Contract \nin accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for \nthe transmission of Energy from a Generating Unit located within the ISO Controlled \nGrid to serve a Load located outside the transmission and Distribution System of a \nParticipating TO. \n3.115 Wheeling Through.  Except for Existing Rights exercised under an Existing \nContract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled \nGrid for the transmission of Energy from a resource located outside the ISO Controlled \nGrid to serve a Load located outside the transmission and Distribution System of a \nParticipating TO. \n3.116 Wheeling.  Wheeling Out or Wheeling Through. \n3.117 Wholesale Customer.  A person wishing to purchase Energy and Ancillary \nServices at a Bulk Supply Point or a Scheduling Point for resale. \n3.118 Omitted."},{"page":264,"startToken":78892,"endToken":78979,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n4.  Eligibility.   \nWholesale tTransmission service over a Participating TO’s system shall be provided \nonly to Eligible Customers who qualify for transmission service under the ISO Tariff.  \nAny dispute as to whether a customer is eligible for wholesale transmission service shall \nbe resolved by FERC and any dispute as to whether an End-Use Customer is eligible \nfor retail transmission service or retail interconnection service under this TO Tariff shall \nbe resolved by the Local Regulatory Authority."},{"page":265,"startToken":78979,"endToken":79226,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n7.  Billing and Payment. \n7.1  End-Users.   \nBilling and payment rules applicable to End-Users shall be pursuant to the then-current \nrules of the applicable Local Regulatory Authority and, as applicable, Appendix XV. \n7.2  Wholesale Customers.   \n7.2.1 Billing Procedure.  \n7.2.1.1  Low Voltage Access Charge Revenues.  Within a reasonable time after the \nParticipating TO receives from the ISO the monthly kilowatt-hours to which the Low \nVoltage Access Charge applies, the Participating TO shall submit an invoice to the \napplicable UDC, MSS or Scheduling Coordinator for the Low Voltage Access Charge \nbilling.  The invoice shall be paid by the UDC, MSS, or Scheduling Coordinator within \ntwenty days of receipt.  All payments shall be made in immediately available funds \npayable to the Participating TO, or by wire transfer to a bank named by the Participating \nTO.   \n7.2.1.2  Reliability Services Revenues.  The Participating TO shall submit an invoice \nto applicable Wheeling customers for billings under the Reliability Services Rate \nSchedule.  The invoice shall be paid by the Wheeling Customer within twenty days of \nreceipt.  All payments shall be made in immediately available funds payable to the \nParticipating TO, or by wire transfer to a bank named by the Participating TO. \n7.2.2  Interest on Unpaid Balances.   \nInterest on any unpaid amounts (including amounts placed in escrow) shall be \ncalculated in accordance with the methodology specified for interest on refunds in"},{"page":266,"startToken":79226,"endToken":79527,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nFERC’s regulations at 18 C.F.R. Section 35.19a(a)(2)(iii).  Interest on delinquent \namounts shall be calculated from the due date of the bill to the date of payment.  When \npayments are made by mail, bills shall be considered as having been paid on the date \nof receipt by the Participating TO. \n7.2.3  Default.  \nIn the event the UDC, MSS, Scheduling Coordinator, or Wheeling Customer fails, for \nany reason other than a billing dispute as described below, to make payment to the \nParticipating TO on or before the due date as described above, and such failure of \npayment is not corrected within 30 calendar days after the Participating TO notifies the \napplicable UDC, MSS, Scheduling Coordinator, or Wheeling Customer to cure such \nfailure, a default by the UDC, MSS, Scheduling Coordinator, or Wheeling Customer \nshall be deemed to exist.  Upon the occurrence of a default, the Participating TO may \ninitiate a proceeding with FERC (or the Local Regulatory Authority for a Local Publicly \nOwned Electric Utility) to terminate service but shall not terminate service until FERC, or \nthe Local Regulatory Authority, as applicable, so approves any such request.  In the \nevent of a billing dispute between the Participating TO and the UDC, MSS, Scheduling \nCoordinator, or Wheeling Customer, the Participating TO will continue to provide service \nunder this TO Tariff as long as the applicable UDC, MSS, Scheduling Coordinator, or \nWheeling Customer:  (i) continues to make all payments not in dispute, and (ii) pays into \nan independent escrow account the portion of the invoice in dispute, pending resolution \nof such dispute.  If the UDC, MSS, Scheduling Coordinator, or Wheeling Customer fails \nto meet these two requirements for continuation of service, then the Participating TO"},{"page":267,"startToken":79527,"endToken":79598,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nmay provide notice to the UDC, MSS, Scheduling Coordinator, or Wheeling Customer of \nits intention to suspend service in sixty days, in accordance with FERC policy. \n7.3  Wheeling and Usage Charge Revenues.   \nThe ISO, pursuant to the ISO Tariff, shall pay to Participating TOs all Wheeling and \nUsage Charge revenues, excluding Usage Charge revenues payable to FTR Holders."},{"page":268,"startToken":79598,"endToken":79855,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n8.  Obligation to Interconnect or Construct Transmission Expansions & Facility \nUpgrades.  \n8.1  Participating TO Obligation to Interconnect.   \nThe Participating TO shall, at the request of a third party pursuant to Section 10, \ninterconnect its system to the wholesale generation or wholesale load of such third \nparty, or modify an existing wholesale Interconnection.  Interconnections under this TO \nTariff shall be available to entities eligible to request Interconnection consistent with the \nprovisions of Section 210(a) of the FPA.  Interconnections requested by entities or \nindividuals that are not so eligible shall be governed by the Local Regulatory Authority.  \nThe procedures for Interconnections of wholesale generation to the ISO Controlled Grid \nshall be governed by the ISO Tariff, and if applicable, Appendix VII to the TO Tariff. \nInterconnections of Large Loads are governed by Appendix XV to the TO Tariff. \n8.1.1  Interconnection to Transmission System.   \nInterconnection must be consistent with Good Utility Practice, in conformance with all \nApplicable Reliability Criteria, all applicable statutes, regulations, and ISO reliability \ncriteria for the ISO Controlled Grid.  The Participating TO will not accommodate the \nInterconnection if doing so would impair system reliability, or would otherwise adversely \naffect the ability of the Participating TO to honor its Encumbrances existing as of the \ntime a party submits its Interconnection Application.  The Participating TO shall identify \nany such adverse effect on its Encumbrances in the System Impact Study performed \npursuant to Section 10.7.  To the extent the Participating TO determines that the"},{"page":269,"startToken":79855,"endToken":80147,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nInterconnection will have an adverse effect on Encumbrances, the party requesting \nInterconnection shall mitigate such adverse effect.   \n8.1.1.1  Letter Agreement. \nPursuant to Section 12 of Appendix DD of the ISO Tariff, prior to executing an \nInterconnection Agreement, a party seeking Interconnection may, in order to advance \nthe implementation of its Interconnection, request, and the Participating TO shall offer \nthe party, a Letter Agreement, a pro forma version of which is set forth in Appendix XIII \nto the TO Tariff, that authorizes the Participating TO to begin engineering, design, and \nprocurement of long lead-time items, or construction necessary for the establishment of \nthe Interconnection.  However, Participating TO shall not be obligated to offer a Letter \nAgreement if the party seeking Interconnection is in Dispute Resolution as a result of an \nallegation that the party seeking Interconnection has failed to meet any milestones or \ncomply with any prerequisites specified in the ISO Tariff.  The Letter Agreement is an \noptional procedure.  The Letter Agreement shall provide for the party seeking \nInterconnection to pay the cost of all activities authorized by the party and to make \nadvance payments or provide other satisfactory security for such costs. \nFollowing a party seeking Interconnection’s request for a Letter Agreement, the \nParticipating TO shall prepare and tender to the party seeking Interconnection a draft \nLetter Agreement in the form of the Participating TO’s FERC-approved Letter \nAgreement as set forth in Appendix XIII to the TO Tariff, including draft exhibits that \ninclude the proposed scope of work, estimated costs, payments, financial security and \nmilestones, as applicable.  The party seeking Interconnection shall provide written \ncomments, or notification of no comments, to the draft exhibits within thirty (30)"},{"page":270,"startToken":80147,"endToken":80450,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nCalendar Days.  The Participating TO and the party seeking Interconnection shall \nnegotiate concerning any disputed provisions of the exhibits to the draft Letter \nAgreement for not more than ninety (90) Calendar Days after the Participating TO \ntenders the draft Letter Agreement to the party seeking Interconnection.  If the party \nseeking Interconnection determines that negotiations are at an impasse, it may request \ntermination of the negotiations at any time after tender of the draft Letter Agreement and \nrequest submission of the unexecuted Letter Agreement with FERC or initiate dispute \nresolution procedures pursuant to Section 14 of this TO Tariff.  If the party seeking \nInterconnection requests termination of the negotiations, but within ninety (90) Calendar \nDays after the Participating TO tenders the draft Letter Agreement to the party seeking \nInterconnection, fails to request either the filing of the unexecuted Letter Agreement or \ninitiate dispute resolution procedures, it shall be deemed to have withdrawn its request \nfor a Letter Agreement and the Participating TO shall have no further obligation to enter \ninto a Letter Agreement, unless an extension is mutually agreed to by the parties.  The \nParticipating TO shall provide to the party seeking Interconnection a final Letter \nAgreement within fifteen (15) Business Days after the completion of the negotiation \nprocess. \nFollowing submission of the final Letter Agreement to the party seeking Interconnection, \nthe party shall either: (i) execute two originals of the tendered Letter Agreement and \nreturn them to the Participating TO; or (ii) request in writing that the Participating TO file \nwith FERC a Letter Agreement in unexecuted form.  As soon as practicable, but not \nlater than ten (10) Business Days after receiving either the two executed originals of the \ntendered Letter Agreement (if it does not conform with a FERC-approved Letter"},{"page":271,"startToken":80450,"endToken":80706,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nAgreement) or the request to file an unexecuted Letter Agreement, the Participating TO \nshall file the Letter Agreement with FERC, together with its explanation of any matters \nas to which the party seeking Interconnection and the Participating TO disagree and \nsupport for the costs that the Participating TO proposes to charge to the party seeking \nInterconnection under the Letter Agreement.  An unexecuted Letter Agreement should \ncontain terms and conditions deemed appropriate by the Participating TO for the \nInterconnection request.  \nIf the party seeking Interconnection executes the final Letter Agreement, the \nParticipating TO and the party seeking Interconnection shall perform their respective \nobligations in accordance with the terms of the Letter Agreement, subject to \nmodification by FERC.  Upon submission of an unexecuted Letter Agreement, the party \nseeking Interconnection and the Participating TO shall promptly comply with the \nunexecuted Letter Agreement, subject to modification by FERC.8.1.2  Costs Associated \nwith Interconnection. \nEach party requesting Interconnection shall pay the costs of planning, installing, owning, \noperating, and maintaining any Direct Assignment Facilities and, if applicable, any \nReliability Upgrades required to provide the requested Interconnection.  In addition, \nsuch party shall implement all existing operating procedures necessary to safely and \nreliably interconnect such party’s wholesale load to the facilities of the Participating TO \nand to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning \nCriteria, and shall bear all costs of implementing such operating procedures.  Any \nadditional costs associated with accommodating the Interconnection shall be allocated"},{"page":272,"startToken":80706,"endToken":80985,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nin accordance with the cost responsibility methodology set forth in the ISO Tariff for \ntransmission expansions or upgrades.   \n8.1.3  Interconnection Agreement. \nPursuant to Section 10.4, 10.7.1, or 10.9.1, a party requesting Interconnection shall \nrequest in writing that the Participating TO tender to such party an Interconnection \nAgreement that will be filed with FERC, or the Local Regulatory Authority, in the case of \na Local Publicly Owned Electric Utility.  The Interconnection Agreement will include, \nwithout limitation, cost responsibilities and payment provisions for any engineering, \nequipment, construction, ownership, operation and maintenance costs for any Direct \nAssignment Facilities, any Reliability Upgrades, and for any other mitigation measures.  \nFor an Interconnection request to remain a Completed Interconnection Application, the \nparty requesting the Interconnection shall execute the Interconnection Agreement and \nreturn it to the Participating TO within thirty (30) Business Days of receipt.  Alternatively, \nif an Eligible Customer requesting the Interconnection requests the Participating TO to \nfile an unexecuted Interconnection Agreement and commits to abide by the terms, \nconditions, and cost assignments determined to be just and reasonable under the ISO \nADR Procedures, including any determination by FERC or on appeal of a FERC \ndetermination in accordance with that process, the Participating TO shall promptly file \nan unexecuted Interconnection Agreement.  Provided, however, that if the ISO ADR \nProcedures concerns whether the requesting entity is an Eligible Customer, the \nParticipating TO shall not be obligated to file an unexecuted Interconnection Agreement \nor commence construction of the Interconnection facilities or incur other costs under the \nInterconnection Agreement until a final order determining the just and reasonable rates,"},{"page":273,"startToken":80985,"endToken":81260,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nterms, and conditions for such Interconnection Agreement has been issued by the \napplicable court or regulatory authority.  The Interconnection Agreement will set forth a \npayment schedule that enables the Participating TO to recover its costs.  If the applicant \nelects not to execute the Interconnection Agreement and does not request the \nParticipating TO to file an unexecuted Interconnection Agreement, its Completed \nInterconnection Application shall be deemed withdrawn, and the applicant shall \nreimburse to the Participating TO all costs reasonably incurred in processing the \napplication not covered by any System Impact Study Agreement or Facilities Study \nAgreement.   \n8.1.4 Due Diligence to Construct.  \nThe Participating TO shall use due diligence to construct, within a reasonable time, any \nDirect Assignment Facilities and any Reliability Upgrades that it is obligated to construct \npursuant to this TO Tariff.  The Participating TO’s obligation to build will be subject to:  \n1) its ability, after making a good faith effort, to obtain any necessary approvals and \nproperty rights under applicable federal, state, and local laws; 2) the presence of a cost \nrecovery mechanism with cost responsibility assigned in accordance with the ISO Tariff \nor applicable FERC precedent; and 3) a signed Interconnection Agreement or a signed \nExpedited Interconnection Agreement or, by mutual agreement of the parties, FERC \nacceptance for filing of an unexecuted Interconnection Agreement. \n8.1.5  Energization.   \nThe Participating TO shall not be obligated to energize, nor shall the wholesale load be \nentitled to have its interconnection to the ISO Controlled Grid energized, unless and \nuntil an Interconnection Agreement has been executed, or filed at FERC pursuant to"},{"page":274,"startToken":81260,"endToken":81513,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nSection 8.1.3, and becomes effective and such wholesale load has demonstrated to the \nISO's reasonable satisfaction that it has complied with all of the requirements of the ISO \nTariff and the requirements of this TO Tariff. \n8.1.6  Coordination with ISO on Interconnection Requests.   \nThe Participating TO shall coordinate with the ISO, pursuant to the provisions of the \nTCA, in developing Interconnection standards and guidelines for processing \nInterconnection requests under this TO Tariff. \n8.2  Participating TO Obligation to Construct Transmission Expansions or Facility \nUpgrades. \nThe Participating TO shall be obligated to:  (1) perform System Impact or Facility \nStudies where the Project Sponsor or the ISO agrees to pay the study cost and \nspecifies the project objectives to be achieved, and (2) build transmission additions and \nfacility upgrades where the Participating TO is obligated to construct or expand facilities \nin accordance with and subject to the limitations of Section 24 of the ISO Tariff and this \nTO Tariff. \n8.2.1  Obligation to Construct. \nA Participating TO shall not be obligated to construct or expand transmission facilities or \nsystem upgrades unless and until the conditions stated in Section 9.2.1 hereof have \nbeen satisfied.  \n8.2.2  Local Furnishing Participating TO Obligation to Construct.   \nA Local Furnishing Participating TO shall not be obligated to construct or expand \ntransmission facilities or system upgrades unless and until the conditions stated in \nSection 9.3.3 hereof have been satisfied."},{"page":275,"startToken":81513,"endToken":81583,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n8.3  Request for FERC Deference Regarding Need Determination.  \nIt is intended that FERC grant substantial deference to the factual determinations of the \nISO, (including the ISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated \nplanning processes as to the need for or construction of a facility, the need for full cost \nrecovery, and the allocation of costs."},{"page":276,"startToken":81583,"endToken":81864,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n9.  Expansion Process. \n9.1  Determination of Facilities.  \nA Participating TO shall perform a Facilities Study in accordance with this Section \nwhere (1) the Participating TO is obligated to construct or expand facilities in \naccordance with Section 24 of the ISO Tariff and this TO Tariff; (2) a Market Participant \nagrees to pay the costs of the Facilities Study and specifies the project objectives to be \nachieved in terms of increased capacity or reduced congestion; or (3) the Participating \nTO is required to perform a Facilities Study pursuant to the ISO Tariff. Eligible \nexpansions on behalf of Large Loads are not governed by this Section 9 but are instead \ngoverned by Appendix XV to the TO Tariff. \n9.1.1  Payment of Facilities Study’s Cost. \n9.1.1.1  Market Participant to Pay for Facilities Study.  \nWhere a Market Participant requests a Facilities Study and the need for the \ntransmission addition or upgrade has not yet been established in accordance with the \nprocedures established herein and the ISO Tariff, the Market Participant shall pay the \ncost of the Facilities Study. \n9.1.1.2  Project Sponsor or Project Proponent to Pay for Facilities Study.  \nWhere the facilities to be added or upgraded have been determined to be needed in \naccordance with the procedures established herein and the ISO Tariff, the Project \nSponsor, Project Proponent, or the ISO requesting the study shall pay the reasonable \ncost of the Facilities Study.  When the Participating TO is the Project Sponsor in \naccordance with the ISO Tariff, the costs of the Facilities Study shall be recovered \nthrough the Access Charges and transmission rates."},{"page":277,"startToken":81864,"endToken":82158,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n9.1.1.3  Principal Beneficiaries to Pay for Facilities Study. \nWhere the facilities to be added or upgraded have been determined to be needed and \nthe principal beneficiaries have been identified by the ISO or ISO ADR Procedures in \naccordance with the ISO Tariff, the Project Sponsor and the identified principal \nbeneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as \nmay be agreed, or, failing agreement, as determined in accordance with the ISO ADR \nProcedures. \n9.1.2  Payment Procedure.   \nWhere a Facilities Study is being conducted pursuant to this TO Tariff, the Participating \nTO shall, within thirty days of the receipt of all reasonably required information, tender to \nthe Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal \nbeneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, \ncontent, assumptions, and terms of reference for such study, the estimated time \nrequired to complete it, and such other provisions as the parties may reasonably require \nand pursuant to which such Market Participant, Project Sponsor, Project Proponent, the \nISO, or identified principal beneficiaries agree to reimburse the Participating TO the \nreasonable cost of performing the required Facilities Study.  If the Market Participant, \nProject Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the \ncase may be, agree to the terms of the Facilities Study Agreement, they shall execute \nthe Facilities Study Agreement and return it to the Participating TO within ten Business \nDays.  Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the \nISO, or identified principal beneficiaries, as the case may be, request the Participating \nTO to proceed with the Facilities Study and commit to abide by the terms, conditions,"},{"page":278,"startToken":82158,"endToken":82459,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nand cost assignments ultimately determined under the ISO ADR Procedures, including \nany determination by FERC or appeal of a FERC determination in accordance with that \nprocess, the Participating TO shall promptly proceed with the Facilities Study, and the \nparties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. \n9.1.3  Facilities Study Procedures.   \nUpon receipt of an executed Facilities Study Agreement or alternative request to \nproceed as provided for in Section 9.1.2, a copy of which has been provided to the ISO \nby the party requesting the Facilities Study, the Participating TO will use due diligence \nto complete the required Facilities Study within a sixty (60) day period.  If the \nParticipating TO is unable to complete the Facilities Study in the allotted time period, the \nParticipating TO shall notify the Market Participant and provide an estimate of the time \nneeded to reach a final determination along with an explanation of the reasons that \nadditional time is required to complete the study.  If additional time is required, the \nParticipating TO will use best efforts to complete the study within 10 months, provided \nadequate information is provided by all the parties. \n9.2  Obligation to Build. \n9.2.1  Due Diligence to Construct.   \nSubject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to \nconstruct, within a reasonable time, additions or upgrades to its transmission system \nthat it is obligated to construct pursuant to the ISO Tariff and this TO Tariff.  \nAlternatively, if a Market Participant requests the Participating TO to file an unexecuted \nParticipation Agreement and commits to abide by the terms, conditions, and cost \nassignments determined to be just and reasonable under the ISO ADR Procedures,"},{"page":279,"startToken":82459,"endToken":82765,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nincluding any determination by FERC or on appeal of a FERC determination in \naccordance with that process, the Participating TO shall promptly file an unexecuted \nParticipation Agreement.  Provided, however, that if the ISO ADR Procedures concerns \nwhether the requesting entity is an Eligible Customer, the Participating TO shall not be \nobligated to file an unexecuted Participation Agreement or commence construction of \nthe additions or upgrades or incur other costs under the Participation Agreement until a \nfinal order determining the just and reasonable rates, terms, and conditions for such \nParticipation Agreement has been issued by the applicable court or regulatory authority.  \nThe Participating TO’s obligation to build will be subject to:  1) its ability, after making a \ngood faith effort, to obtain the necessary approvals and property rights under applicable \nfederal, state, and local laws; 2) the presence of a cost recovery mechanism with cost \nresponsibility assigned in accordance with the ISO Tariff; and 3) a signed Participation \nAgreement.  The Participating TO will not construct or expand its existing or planned \ntransmission system, if doing so would impair system reliability as determined through \nsystems analysis based on the Applicable Reliability Criteria. \n9.2.2  Delay in Construction or Expansion.   \nIf any event occurs that will materially affect the time for completion of new facilities, or \nthe ability to complete them, the Participating TO shall promptly notify:  (1) the Project \nSponsor with regard to facilities determined to be needed; (2) the Parties to the \nParticipation Agreement with regard to facilities determined to be needed pursuant to \nthe ISO Tariff where principal beneficiaries were identified; and (3) the ISO.  In such \ncircumstances, the Participating TO shall, within thirty days of notifying such Project \nSponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a"},{"page":280,"startToken":82765,"endToken":83080,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ntechnical meeting with such Project Sponsor, Parties to the Participation Agreement, \nand the ISO to discuss the circumstances which have arisen and evaluate any options \navailable.  The Participating TO also shall make available to such Project Sponsor, \nParties to the Participation Agreement, and the ISO, as the case may be, studies and \nwork papers related to the cause and extent of the delay and the Participating TO’s \nability to complete the new facilities, including all information that is in the possession of \nthe Participating TO that is reasonably needed to evaluate the alternatives. \n9.2.2.1  Alternatives to the Original Facility Additions.   \nIf the review process of Section 9.2.2 determines that one or more alternatives exist to \nthe originally planned construction project, the Participating TO shall present such \nalternatives for consideration to the Project Sponsor, Parties to the Participation \nAgreement, and the ISO, as the case may be.  If upon review of any alternatives, such \nProject Sponsor, the ISO, or Parties to the Participation Agreement wish to evaluate or \nto proceed with one of the alternative additions or upgrades, such Project Sponsor, the \nISO, or Parties to the Participation Agreement may request that the Participating TO \nprepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO \nTariff.  In the event the Participating TO concludes that no reasonable alternative exists \nto the originally planned addition or upgrade and the Project Sponsor or Parties to the \nParticipation Agreement or the ISO disagree, the dispute shall be resolved pursuant to \nthe ISO ADR Procedure. \n9.2.2.2  Refund Obligation for Unfinished Facility Additions. \nIf the Participating TO and the Project Sponsor, the ISO, or Parties to the Participation \nAgreement, as the case may be, mutually agree that no other reasonable alternatives"},{"page":281,"startToken":83080,"endToken":83348,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nexist, the obligation to construct the requested additions or upgrades shall terminate \nand any deposit not yet applied toward the expended project costs shall be returned \nwith interest pursuant to FERC Regulation 35.19(a)(2)(iii).  However, the Project \nSponsor and any identified principal beneficiaries, as the case may be, shall be \nresponsible for all costs prudently incurred by the Participating TO through the time the \nconstruction was suspended.   \n9.3  Provisions Relating To Transmission Construction On the Systems Of Other \nTOs. \n9.3.1  Responsibility for Third Party Additions.  \nA Participating TO shall not be responsible for making arrangements for any \nengineering, permitting, and construction of transmission or distribution facilities on the \nsystem(s) of any other entity or for obtaining any regulatory approval for such facilities.  \nThe Participating TO will undertake reasonable efforts through the coordinated planning \nprocess to assist in making such arrangements, including, without limitation, providing \nany information or data required by such other electric system pursuant to Good Utility \nPractice. \n9.3.2  Coordination of Third-Party System Additions.  \nWhere transmission additions or upgrades being built pursuant to the ISO Tariff require \nadditions or upgrades on other systems, to the extent consistent with Section 9.3.3 of \nthis TO Tariff, the Participating TO shall coordinate construction on its own system with \nthe construction required by others.  The Participating TO, after consultation with the \nISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may \nbe, may defer construction if the new transmission facilities on another system cannot"},{"page":282,"startToken":83348,"endToken":83648,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nbe completed in a timely manner.  The Participating TO shall notify such Project \nSponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for \nany decision to defer construction and the specific problems which must be resolved \nbefore it will initiate or resume construction of the new facilities.  Within forty Business \nDays of receiving written notification by the Participating TO of its intent to defer \nconstruction pursuant to this section, such Project Sponsor, Parties to the Participation \nAgreement, or the ISO may challenge the decision in accordance with the ISO ADR \nProcedure. \n9.3.3  Expansion by “Local Furnishing Participating TOs”.   \nNotwithstanding any other provision of this TO Tariff, prior to requesting that a Local \nFurnishing Participating TO construct or expand facilities, the ISO or Project Sponsor \nshall tender (or cause to be tendered) an application under Section 211 of the FPA \nrequesting FERC to issue an order directing the Local Furnishing Participating TO to \nconstruct or expand facilities as necessary to provide transmission service as \ndetermined pursuant to the ISO Tariff.  Such Local Furnishing Participating TO shall \nthereafter, within ten Business Days of receiving a copy of the Section 211 application, \nwaive its right to a request for service under Section 213(a) of the FPA and to the \nissuance of a proposed order under Section 212(c) of the FPA.  Upon receipt of a final \norder from FERC under Section 211 of the FPA that is no longer subject to rehearing or \nappeal, such Local Furnishing Participating TO shall construct or expand facilities to \ncomply with that FERC order and shall transfer to the ISO Operational Control over the \nLocal Furnishing Participating TO’s expanded transmission facilities in accordance with \nthe ISO Tariff."},{"page":283,"startToken":83648,"endToken":83890,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.  Interconnection Process. \n10.1  Applicability.  \nAll requests for Interconnection of wholesale load directly to the ISO Controlled Grid from \nparties eligible to request such Interconnection consistent with Section 210(a) of the FPA \nshall be processed pursuant to the provisions of this Section 10., except requests for \ninterconnection on behalf of Large Loads to be located in the ISO BAA shall be subject \nto the procedures in Appendix XV of the TO Tariff.  All requests for Interconnection of \nwholesale generation directly to the ISO Controlled Grid shall be processed pursuant to \nthe provisions of the ISO Tariff, and if applicable, Appendix VII of the TO Tariff. Requests \nfor interconnection on behalf of Large Loads by retail transmission customers of \nParticipating TO shall be subject to the procedures in Appendix XV of the TO Tariff and \nthe Local Regulatory Authority, as applicable. \n10.2  Applications.   \nA party requesting Interconnection shall submit a written Interconnection Application \nwhich provides the information required in Section 10.3 to the Participating TO and shall \nsend a copy of the application to the ISO.  The Participating TO shall time-stamp the \napplication to establish study priority. \n10.3  Interconnection Application.   \nAn Interconnection Application shall provide all of the information listed in 18 CFR § \n2.20, including, but not limited to, the following: \n(i)  The identity, address, telephone number, and facsimile number of the party \nrequesting Interconnection;"},{"page":284,"startToken":83890,"endToken":84132,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n(ii)  The Interconnection point(s) to the ISO Controlled Grid contemplated by the \napplicant; \n(iii)  The resultant (or new) maximum amount of Interconnection capacity; \n(iv)  The proposed date for energizing the Interconnection and the term of the \nInterconnection service; \n(v)  Such other information as the Participating TO reasonably requires to process the \napplication. \nIn addition to the information specified above, the following information may also be \nprovided in order to properly evaluate system conditions: \n(vi)  The electrical location of the source of the power (if known) to be transmitted \npursuant to the applicant’s request for Interconnection.  If the source of the power is not \nknown, a system purchase will be assumed. \nWithin ten (10) Business Days after receipt of an Interconnection Application, the \nParticipating TO shall determine whether the application is complete (“Completed \nInterconnection Application”).  Wherever possible, the Participating TO will attempt to \nremedy deficiencies in the Interconnection Application through informal communications \nwith the applicant.  If such efforts are unsuccessful, the Participating TO shall return the \nInterconnection Application to the applicant.  The Participating TO will treat the \ninformation provided in the Interconnection Application, including the applicant’s identity, \nas confidential at the request of the applicant except to the extent that disclosure of this \ninformation is required by this TO Tariff, by regulatory or judicial order, for reliability \npurposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission"},{"page":285,"startToken":84132,"endToken":84413,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \ninformation sharing agreements.  The Participating TO shall treat this information \nconsistent with the standards of conduct contained in Part 37 of FERC’s regulations. \n10.4  Review of Completed Interconnection Application.   \nAfter receiving a Completed Interconnection Application, the Participating TO will \ndetermine on a non-discriminatory basis whether a System Impact Study is required.  \nWhenever the Participating TO determines that a System Impact Study is not required \nand that neither Reliability Upgrades nor changes in existing operating procedures are \nrequired, the Participating TO shall notify the applicant within fifteen (15) Business Days \nof the Completed Application Date.  If the Interconnection can be accommodated \nwithout any Direct Assignment Facilities, then within thirty (30) Business Days of such \nnotice from the Participating TO, the applicant shall request the Participating TO to \ntender to the applicant an Interconnection Agreement within thirty (30) Business Days of \nsuch request.  The Participating TO shall tender to the applicant an Interconnection \nAgreement as provided in Section 8.1.3.  If the Participating TO determines, upon the \nreview of the Completed Interconnection Application, that Direct Assignment Facilities \nare required, the Participating TO shall tender to the applicant a Facilities Study \nAgreement within twenty (20) Business Days of the Completed Application Date and \ncontinue the interconnection process pursuant to Section 10.8.   \n10.5  Notice of Need for System Impact Study.   \nIf the Participating TO determines that a System Impact Study is necessary to \naccommodate the requested Interconnection, the Participating TO shall so inform the \napplicant, as soon as practicable.  In such cases, the Participating TO shall within \ntwenty (20) Business Days of receipt of a Completed Interconnection Application, tender"},{"page":286,"startToken":84413,"endToken":84703,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \na System Impact Study Agreement that defines the scope, content, assumptions and \nterms of reference for such study to be completed by the Participating TO; the \nestimated time required to complete it; and such other provisions as the parties may \nreasonably require, and pursuant to which the applicant shall agree to reimburse the \nParticipating TO for the reasonable actual costs of performing the required System \nImpact Study.  A description of the Participating TO’s transmission assessment \npractices for completing a System Impact Study is provided in the Participating TO’s \nFERC Form 715.  For an Interconnection request to remain a Completed \nInterconnection Application, the applicant shall execute the System Impact Study \nAgreement and return it to the Participating TO within ten (10) Business Days together \nwith payment for the reasonable estimated cost of performing the System Impact Study.  \nAlternatively, if the applicant requests the Participating TO to proceed with the System \nImpact Study and commits to abide by the terms, conditions, and cost assignments \nultimately determined under the ISO ADR Procedures, including any determination by \nFERC or appeal of a FERC determination in accordance with that process, the \nParticipating TO shall promptly proceed with the System Impact Study provided that \nsuch request is accompanied by payment for the reasonable estimated cost of the \nSystem Impact Study, and the parties shall submit the disputed terms for resolution \nunder the ISO’s ADR Procedures.  If the applicant elects not to execute a System \nImpact Study Agreement, and does not request that the Participating TO proceed with \nthe System Impact Study, its application shall be deemed withdrawn, and the applicant \nshall reimburse to the Participating TO all costs reasonably incurred in processing the \napplication."},{"page":287,"startToken":84703,"endToken":84966,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.6  System Impact Study Cost Reimbursement and Agreement \n10.6.1  Cost Reimbursement. \nThe System Impact Study Agreement shall clearly specify the charge, based on the \nParticipating TO’s estimate of the cost and time for completion of the System Impact \nStudy.  The charge shall not exceed the reasonable actual cost of the study.  In \nperforming the System Impact Study, the Participating TO shall rely, to the extent \nreasonably practicable, on existing transmission planning studies.  The applicant will not \nbe assessed a charge for such existing studies; however, the applicant will be \nresponsible for the reasonable charges associated with any modifications to existing \nplanning studies that are reasonably necessary to evaluate the impact of the applicant’s \nrequest. \n10.6.2  Multiple Parties.   \nIf multiple parties request Interconnection at the same location, the Participating TO \nmay conduct a single System Impact Study.  The costs of that study shall be pro-rated \namong the parties requesting Interconnection. \n10.7  System Impact Study Procedures.  \nUpon receipt of an executed System Impact Study Agreement or initiation of the ISO \nADR Procedures and receipt of payment for estimated study costs, the Participating TO \nwill use due diligence to complete the required System Impact Study within a sixty (60) \ncalendar day period.  The System Impact Study will identify whether any Direct \nAssignment Facilities or Reliability Upgrades are necessary, as well as whether any \ntransmission additions or upgrades are necessary to serve a wholesale load.  The \nSystem Impact Study will also identify any adverse impact on Encumbrances existing as"},{"page":288,"startToken":84966,"endToken":85247,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nof the applicant’s Completed Application Date.  In the event that the Participating TO is \nunable to complete the required System Impact Study within such time period, it shall so \nnotify the applicant, in writing, and provide an estimated completion date along with an \nexplanation of the reasons why additional time is required to complete the required \nstudies.  A copy of the completed System Impact Study and related work papers shall \nbe made available to the applicant and the ISO.  The Participating TO will use the same \ndue diligence in completing the System Impact Study for others as it uses when \ncompleting studies for its affiliated UDC load.  The Participating TO shall notify the \napplicant immediately upon completion of the System Impact Study. \n10.7.1  Procedures Upon Completion of System Impact Study.   \nWithin fifteen (15) Business Days of completion of the System Impact Study, the \nParticipating TO shall notify the applicant whether the transmission system will be \nadequate to accommodate all of a request for Interconnection.  If no costs are likely to \nbe incurred for any Direct Assignment Facilities, any Reliability Upgrades, or \nimplementing any operating procedures, then within thirty (30) Business Days of receipt \nof the completed System Impact Study, the applicant shall request the Participating TO \nto tender an Interconnection Agreement within thirty (30) Business Days of such \nrequest.  The Participating TO shall tender to the applicant an Interconnection \nAgreement as provided in Section 8.1.3.  If costs are likely to be incurred to \naccommodate a request for Interconnection, the Participating TO shall tender to the \napplicant a Facilities Study Agreement pursuant to Section 10.8."},{"page":289,"startToken":85247,"endToken":85547,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n10.8  Notice of Need for Facilities Study.   \nIf a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid \nare needed to satisfy an applicant’s request for Interconnection, the Participating TO \nshall, within fifteen (15) Business Days of the completion date of the System Impact \nStudy tender to the applicant a Facilities Study Agreement that defines the scope, \ncontent, assumptions and terms of reference for such study; the estimated time required \nto complete the required study; and such other provisions as the parties may \nreasonably require, and pursuant to which the applicant agrees to reimburse the \nParticipating TO for the reasonable actual costs of performing the required Facilities \nStudy.   For an Interconnection request to remain a Completed Interconnection \nApplication, the applicant shall execute the Facilities Study Agreement and return it to \nthe Participating TO within ten (10) Business Days together with payment for the \nreasonable estimated cost of performing the Facilities Study.  Alternatively, if the \napplicant requests the Participating TO to proceed with the Facilities Study and commits \nto abide by the terms, conditions, and cost assignments ultimately determined under the \nISO ADR Procedures, including any determination by FERC or appeal of a FERC \ndetermination in accordance with that process, the Participating TO shall promptly \nproceed with the Facilities Study provided that such request is accompanied by \npayment for the reasonable estimated cost of the Facilities Study, and the parties shall \nsubmit the disputed terms for resolution under the ISO ADR Procedures.  If the \napplicant elects not to execute a Facilities Study Agreement and does not request that \nthe Participating TO proceed with the Facilities Study, its application shall be deemed \nwithdrawn and the applicant shall reimburse to the Participating TO all costs reasonably"},{"page":290,"startToken":85547,"endToken":85818,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nincurred in processing the application not covered by the System Impact Study \nAgreement. \n10.9  Facilities Study Procedures.  \nUpon receipt of an executed Facilities Study Agreement or initiation of the ISO ADR \nProcedures and receipt of payment for the estimated study costs, the Participating TO \nwill use due diligence to complete the required Facilities Study within a sixty (60) \ncalendar day period.  In the event that the Participating TO is unable to complete the \nrequired Facilities Study within such time period, it shall so notify the applicant, in \nwriting, and provide an estimated completion date along with an explanation of the \nreasons why additional time is required to complete the required studies.  A copy of the \ncompleted Facilities Study shall be made available to the applicant.   \n10.9.1  Execution of Interconnection Agreement.  \nWithin thirty (30) Business Days of receipt of the completed Facilities Study, the \napplicant shall request the Participating TO to tender an Interconnection Agreement \nwithin thirty (30) Business Days of such request.  The Participating TO shall tender to \nthe applicant an Interconnection Agreement as provided in Section 8.1.3.  \n10.10  Partial Interim Service.   \nIf the Participating TO determines that there will not be adequate transmission capability \nto satisfy the full amount requested in a Completed Interconnection Application, the \nParticipating TO nonetheless shall be obligated to offer and provide the portion of the \nrequested Interconnection that can be accommodated without any additional Direct \nAssignment Facilities or Reliability Upgrades.  However, the Participating TO shall not \nbe obligated to provide the incremental amount of requested Interconnection that"},{"page":291,"startToken":85818,"endToken":86093,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nrequires such additional facilities or upgrades until such facilities or upgrades have been \nplaced in service. \n10.11  Expedited Interconnection Procedures.   \nIn lieu of the procedures set forth above, the applicant shall have the option to expedite \nthe processing of its Completed Interconnection Application.  In order to exercise this \noption, the applicant shall submit in writing a Request for Expedited Interconnection \nProcedures to the Participating TO within ten (10) Business Days after receiving a copy \nof the System Impact Study for the proposed Interconnection.  Within ten (10) Business \nDays after receiving a Request for Expedited Procedures, the Participating TO shall \ntender an Expedited Interconnection Agreement that requires the applicant to \ncompensate the Participating TO for all costs reasonably incurred pursuant to the terms \nof this TO Tariff for processing the Completed Interconnection Application and providing \nthe requested Interconnection.  While the Participating TO agrees to provide the \napplicant with its best estimate of the costs of any needed Direct Assignment Facilities \nand, if applicable, Reliability Upgrades and other charges that may be incurred, unless \notherwise agreed by the parties, such estimate shall not be binding and the applicant \nmust agree in writing to compensate the Participating TO for all actual Interconnection \ncosts reasonably incurred pursuant to the provisions of this TO Tariff.  The applicant \nshall execute and return such Expedited Interconnection Agreement within ten (10) \nBusiness Days of its receipt or the applicant's request for Interconnection will cease to \nbe a Completed Interconnection Application and will be deemed terminated and \nwithdrawn.  In that event, the applicant shall reimburse the Participating TO for all costs"},{"page":292,"startToken":86093,"endToken":86122,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \nreasonably incurred in processing the application not covered by the terms of the \nSystem Impact Study Agreement."},{"page":293,"startToken":86122,"endToken":86320,"text":"Southern California Edison Company   \n \n  \nFERC Electric Tariff, Third Revised Volume No. 6  \n \n \n \n \n \n13.  Creditworthiness. \n13.1  UDCs, MSSs, and Scheduling Coordinators Using the Participating TO's Low \nVoltage Transmission Facilities.  \nFor the purpose of determining the ability of a UDC, MSS, and Scheduling Coordinator \nto meet its obligations related to service using the Participating TO's Low Voltage \nTransmission Facilities hereunder, the Participating TO may require reasonable credit \nreview procedures for the UDC, MSS, or Scheduling Coordinator.  This review shall be \nmade in accordance with standard commercial practices.  In addition, the Participating \nTO may require the UDC, MSS, or Scheduling Coordinator to provide and maintain in \neffect during the term of the service, an unconditional and irrevocable letter of credit as \nsecurity to meet its responsibilities and obligations under this TO Tariff, or an alternative \nform of security proposed by the UDC, MSS, or Scheduling Coordinator and acceptable \nto the Participating TO, and consistent with commercial practices established by the \nUniform Commercial Code, that protect the Participating TO against the risk of non-\npayment. \n13.2  End-Users.   \nCreditworthiness rules applicable to End-Users shall be pursuant to the then-current \nrules of the applicable Local Regulatory Authority. and, as applicable, Appendix XV."},{"page":294,"startToken":86320,"endToken":86427,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have, this day, served a true copy of the foregoing document on all parties \nidentified on the official service list(s) for FERC dockets EL26-71, the California Public Utilities \nCommission (“CPUC”) and SCE TO Tariff customers. Service was effected by transmitting copies via \nemail to all parties who have provided an e-mail address. First class mail will be used if electric service \ncannot be effectuated. \n \nDated at Rosemead, California, this 16th day of November 2026. \n \n/s/Sandra Sedano \n \n \n \nSandra Sedano \nSr Specialist, Legal Support \nSouthern California Edison Company \n2244 Walnut Grove Avenue \nRosemead, CA 91770 \nsandra.sedano@sce.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":392,"startToken":0,"endToken":310},{"p":2,"at":392,"title":"I. BACKGROUND","method":"printed heading","endPage":4,"endAt":108,"startToken":310,"endToken":983},{"p":4,"at":108,"title":"II. RESPONSE TO SHOW CAUSE ORDER","method":"printed heading","endPage":6,"endAt":108,"startToken":983,"endToken":1530},{"p":6,"at":108,"title":"A. APPLICATION PROCESS, STUDY PROCEDURES, AND ONGOING","method":"printed heading","endPage":19,"endAt":1693,"startToken":1530,"endToken":6287},{"p":19,"at":1693,"title":"B. COST SHIFTING MITIGATION","method":"printed heading","endPage":26,"endAt":110,"startToken":6287,"endToken":8377},{"p":26,"at":110,"title":"C. FLEXIBLE SERVICE","method":"printed heading","endPage":28,"endAt":1783,"startToken":8377,"endToken":9287},{"p":28,"at":1783,"title":"D. PROXIMATE LARGE LOAD AND CO-LOCATED LOAD","method":"printed heading","endPage":33,"endAt":1025,"startToken":9287,"endToken":10679},{"p":33,"at":1025,"title":"E. SUMMARY OF OTHER PROPOSED TARIFF CHANGES","method":"printed heading","endPage":34,"endAt":837,"startToken":10679,"endToken":10968},{"p":34,"at":837,"title":"III. EFFECTIVE DATE","method":"printed heading","endPage":34,"endAt":1033,"startToken":10968,"endToken":10999},{"p":34,"at":1033,"title":"IV. CONTENTS OF FILING","method":"printed heading","endPage":34,"endAt":1459,"startToken":10999,"endToken":11066},{"p":34,"at":1459,"title":"V. OTHER FILING REQUIREMENTS","method":"printed heading","endPage":35,"endAt":509,"startToken":11066,"endToken":11240},{"p":35,"at":509,"title":"VI. CORRESPONDENCE","method":"printed heading","endPage":35,"endAt":1230,"startToken":11240,"endToken":11327},{"p":35,"at":1230,"title":"VII. NOTICE","method":"printed heading","endPage":36,"endAt":110,"startToken":11327,"endToken":11372},{"p":36,"at":110,"title":"VIII. CONCLUSION","method":"printed heading","endPage":37,"endAt":0,"startToken":11372,"endToken":11422},{"p":37,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":38,"endAt":88,"startToken":11422,"endToken":11440},{"p":38,"at":88,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":96,"endAt":90,"startToken":11440,"endToken":25766},{"p":96,"at":90,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":134,"endAt":1141,"startToken":25766,"endToken":39466},{"p":134,"at":1141,"title":"A. Site drawing showing Large Load location and Point of Interconnection","method":"printed heading","endPage":134,"endAt":1266,"startToken":39466,"endToken":39483},{"p":134,"at":1266,"title":"B. Single-line diagram showing applicable equipment such as large load","method":"printed heading","endPage":134,"endAt":1727,"startToken":39483,"endToken":39541},{"p":134,"at":1727,"title":"A. Rated total MW consumption and power factor of the Large Load, including","method":"printed heading","endPage":134,"endAt":1913,"startToken":39541,"endToken":39564},{"p":134,"at":1913,"title":"B. Percentage of the total MW consumption of the Large Load for each of the","method":"printed heading","endPage":135,"endAt":172,"startToken":39564,"endToken":39639},{"p":135,"at":172,"title":"C. If the Large Loadhas some form of forced cooling system, indicate what it is","method":"printed heading","endPage":135,"endAt":624,"startToken":39639,"endToken":39694},{"p":135,"at":624,"title":"D. Motor-driven components of the cooling systems are driven by (check all","method":"printed heading","endPage":135,"endAt":1029,"startToken":39694,"endToken":39742},{"p":135,"at":1029,"title":"E. Voltage sag levels and durations below which the components within the","method":"printed heading","endPage":135,"endAt":1563,"startToken":39742,"endToken":39814},{"p":135,"at":1563,"title":"F. Voltage swell levels and durations above which the components within the","method":"printed heading","endPage":135,"endAt":2105,"startToken":39814,"endToken":39886},{"p":135,"at":2105,"title":"G. Frequency thresholds above and below which any computing/server load","method":"printed heading","endPage":135,"endAt":2259,"startToken":39886,"endToken":39904},{"p":135,"at":2259,"title":"H. Reconnection of load after voltage and frequency recover (check all that","method":"printed heading","endPage":136,"endAt":261,"startToken":39904,"endToken":39956},{"p":136,"at":261,"title":"I. Emergency generation and battery energy storage:","method":"printed heading","endPage":136,"endAt":1844,"startToken":39956,"endToken":40156},{"p":136,"at":1844,"title":"A. Arrangement and operating mode:","method":"printed heading","endPage":137,"endAt":457,"startToken":40156,"endToken":40247},{"p":137,"at":457,"title":"B. Technology and ratings (aggregate nameplate MVA and MW for each","method":"printed heading","endPage":137,"endAt":1139,"startToken":40247,"endToken":40317},{"p":137,"at":1139,"title":"C. Gross and net withdrawal and requested service:","method":"printed heading","endPage":137,"endAt":1615,"startToken":40317,"endToken":40374},{"p":137,"at":1615,"title":"D. Non-export controls (for non-exporting co-located generation):","method":"printed heading","endPage":137,"endAt":1877,"startToken":40374,"endToken":40396},{"p":137,"at":1877,"title":"E. Ride-through, protection, and disturbance behavior:","method":"printed heading","endPage":138,"endAt":792,"startToken":40396,"endToken":40515},{"p":138,"at":792,"title":"F. Models and data:","method":"printed heading","endPage":138,"endAt":1139,"startToken":40515,"endToken":40561},{"p":138,"at":1139,"title":"G. NERC registration:","method":"printed heading","endPage":138,"endAt":1892,"startToken":40561,"endToken":40648},{"p":138,"at":1892,"title":"A. Total Generating Facility rated output (MW):","method":"printed heading","endPage":138,"endAt":2129,"startToken":40648,"endToken":40676},{"p":138,"at":2129,"title":"B. Generating Facility auxiliary load (MW): _______________","method":"printed heading","endPage":138,"endAt":2191,"startToken":40676,"endToken":40682},{"p":138,"at":2191,"title":"C. Net Generating Facility capacity at generator/inverter terminals (MW):","method":"printed heading","endPage":138,"endAt":2300,"startToken":40682,"endToken":40695},{"p":138,"at":2300,"title":"D. Collector system losses (MW): _______________ (insert “n/a” if not","method":"printed heading","endPage":139,"endAt":89,"startToken":40695,"endToken":40720},{"p":139,"at":89,"title":"E. Main step-up transformer losses (MW): _______________ (insert “n/a” if","method":"printed heading","endPage":139,"endAt":196,"startToken":40720,"endToken":40734},{"p":139,"at":196,"title":"F. Net Generating Facility capacity at high-side of main step-up transformer","method":"printed heading","endPage":139,"endAt":306,"startToken":40734,"endToken":40747},{"p":139,"at":306,"title":"G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert","method":"printed heading","endPage":139,"endAt":422,"startToken":40747,"endToken":40763},{"p":139,"at":422,"title":"H. Net Generating Facility capacity at Point of Interconnection (MW):","method":"printed heading","endPage":139,"endAt":853,"startToken":40763,"endToken":40819},{"p":139,"at":853,"title":"I. Standby Load when Generating Facility is off-line (MW):","method":"printed heading","endPage":139,"endAt":2028,"startToken":40819,"endToken":40944},{"p":139,"at":2028,"title":"A. Rated Generator speed (rpm): ____________","method":"printed heading","endPage":139,"endAt":2075,"startToken":40944,"endToken":40949},{"p":139,"at":2075,"title":"B. Rated MVA: _______________","method":"printed heading","endPage":139,"endAt":2107,"startToken":40949,"endToken":40952},{"p":139,"at":2107,"title":"C. Rated Generator Power Factor: ____________","method":"printed heading","endPage":139,"endAt":2155,"startToken":40952,"endToken":40957},{"p":139,"at":2155,"title":"D. Generator Efficiency at Rated Load (%): ____________","method":"printed heading","endPage":139,"endAt":2213,"startToken":40957,"endToken":40963},{"p":139,"at":2213,"title":"E. Moment of Inertia (including prime mover): ____________","method":"printed heading","endPage":139,"endAt":2274,"startToken":40963,"endToken":40970},{"p":139,"at":2274,"title":"F. Inertia Time Constant (on machine base) H: ____________ sec or","method":"printed heading","endPage":139,"endAt":2350,"startToken":40970,"endToken":40982},{"p":139,"at":2350,"title":"G. SCR (Short-Circuit Ratio - the ratio of the field current required for","method":"printed heading","endPage":140,"endAt":227,"startToken":40982,"endToken":41018},{"p":140,"at":227,"title":"H. Please attach generator reactive capability curves.","method":"printed heading","endPage":140,"endAt":284,"startToken":41018,"endToken":41025},{"p":140,"at":284,"title":"I. Rated Hydrogen Cooling Pressure in psig (Steam Units only):","method":"printed heading","endPage":140,"endAt":694,"startToken":41025,"endToken":41079},{"p":140,"at":694,"title":"A. Indicate the Manufacturer ____________________ and Type","method":"printed heading","endPage":140,"endAt":2191,"startToken":41079,"endToken":41269},{"p":140,"at":2191,"title":"B. Attach a copy of the block diagram of the excitation system from its","method":"printed heading","endPage":141,"endAt":89,"startToken":41269,"endToken":41312},{"p":141,"at":89,"title":"C. Excitation system response ratio (ASA): ______________","method":"printed heading","endPage":141,"endAt":150,"startToken":41312,"endToken":41318},{"p":141,"at":150,"title":"D. Full load rated exciter output voltage: ___________","method":"printed heading","endPage":141,"endAt":208,"startToken":41318,"endToken":41325},{"p":141,"at":208,"title":"E. Maximum exciter output voltage (ceiling voltage): ___________","method":"printed heading","endPage":141,"endAt":276,"startToken":41325,"endToken":41332},{"p":141,"at":276,"title":"F. Other comments regarding the excitation system?","method":"printed heading","endPage":141,"endAt":738,"startToken":41332,"endToken":41384},{"p":141,"at":738,"title":"A. Manufacturer:","method":"printed heading","endPage":141,"endAt":804,"startToken":41384,"endToken":41386},{"p":141,"at":804,"title":"B. Is the PSS digital or analog?","method":"printed heading","endPage":141,"endAt":875,"startToken":41386,"endToken":41393},{"p":141,"at":875,"title":"C. Note the input signal source for the PSS?","method":"printed heading","endPage":141,"endAt":1032,"startToken":41393,"endToken":41411},{"p":141,"at":1032,"title":"D. Please attach a copy of a block diagram of the PSS from the PSS","method":"printed heading","endPage":141,"endAt":1203,"startToken":41411,"endToken":41441},{"p":141,"at":1203,"title":"E. Other comments regarding the PSS?","method":"printed heading","endPage":141,"endAt":1623,"startToken":41441,"endToken":41478},{"p":141,"at":1623,"title":"A. Steam, gas or combined-cycle turbines:","method":"printed heading","endPage":142,"endAt":288,"startToken":41478,"endToken":41590},{"p":142,"at":288,"title":"B. Hydro turbines:","method":"printed heading","endPage":142,"endAt":830,"startToken":41590,"endToken":41663},{"p":142,"at":830,"title":"C. Complete this section for each machine, independent of the turbine","method":"printed heading","endPage":143,"endAt":570,"startToken":41663,"endToken":41834},{"p":143,"at":570,"title":"A. Motoring Power (kW): ______________","method":"printed heading","endPage":143,"endAt":611,"startToken":41834,"endToken":41838},{"p":143,"at":611,"title":"B. I22t or K (Heating Time Constant): ______________","method":"printed heading","endPage":143,"endAt":667,"startToken":41838,"endToken":41845},{"p":143,"at":667,"title":"C. Rotor Resistance, Rr: ______________","method":"printed heading","endPage":143,"endAt":710,"startToken":41845,"endToken":41849},{"p":143,"at":710,"title":"D. Stator Resistance, Rs: ______________","method":"printed heading","endPage":143,"endAt":756,"startToken":41849,"endToken":41853},{"p":143,"at":756,"title":"E. Stator Reactance, Xs: ______________","method":"printed heading","endPage":143,"endAt":799,"startToken":41853,"endToken":41857},{"p":143,"at":799,"title":"F. Rotor Reactance, Xr: ______________","method":"printed heading","endPage":143,"endAt":844,"startToken":41857,"endToken":41861},{"p":143,"at":844,"title":"G. Magnetizing Reactance, Xm: ______________","method":"printed heading","endPage":143,"endAt":892,"startToken":41861,"endToken":41865},{"p":143,"at":892,"title":"H. Short Circuit Reactance, Xd'': ______________","method":"printed heading","endPage":143,"endAt":944,"startToken":41865,"endToken":41870},{"p":143,"at":944,"title":"I. Exciting Current: ______________","method":"printed heading","endPage":143,"endAt":1454,"startToken":41870,"endToken":41932},{"p":143,"at":1454,"title":"A. Number of generators to be interconnected pursuant to this","method":"printed heading","endPage":143,"endAt":1550,"startToken":41932,"endToken":41944},{"p":143,"at":1550,"title":"B. Average Site Elevation: ______ Single Phase _____ Three Phase_____","method":"printed heading","endPage":143,"endAt":1622,"startToken":41944,"endToken":41952},{"p":143,"at":1622,"title":"C. Field Volts: _________________","method":"printed heading","endPage":143,"endAt":1658,"startToken":41952,"endToken":41955},{"p":143,"at":1658,"title":"D. Field Amperes: ______________","method":"printed heading","endPage":143,"endAt":1693,"startToken":41955,"endToken":41958},{"p":143,"at":1693,"title":"E. Motoring Power (MW): _______","method":"printed heading","endPage":143,"endAt":1727,"startToken":41958,"endToken":41962},{"p":143,"at":1727,"title":"F. Neutral Grounding Resistor (If Applicable): ____________","method":"printed heading","endPage":143,"endAt":1789,"startToken":41962,"endToken":41968},{"p":143,"at":1789,"title":"G. I22t or K (Heating Time Constant): ____________","method":"printed heading","endPage":144,"endAt":89,"startToken":41968,"endToken":41987},{"p":144,"at":89,"title":"H. Rotor Resistance: ____________","method":"printed heading","endPage":144,"endAt":125,"startToken":41987,"endToken":41990},{"p":144,"at":125,"title":"I. Stator Resistance: ____________","method":"printed heading","endPage":144,"endAt":1274,"startToken":41990,"endToken":42133},{"p":144,"at":1274,"title":"A. Inverter Manufacturer and Model: _________________________","method":"printed heading","endPage":144,"endAt":1339,"startToken":42133,"endToken":42138},{"p":144,"at":1339,"title":"B. Number of Inverters: ___________________","method":"printed heading","endPage":144,"endAt":1386,"startToken":42138,"endToken":42142},{"p":144,"at":1386,"title":"C. Nameplate Rating (AC, each inverter): _______/_______ kW","method":"printed heading","endPage":144,"endAt":1451,"startToken":42142,"endToken":42149},{"p":144,"at":1451,"title":"D. Nameplate Voltage Rating (AC): _______ kV","method":"printed heading","endPage":144,"endAt":1501,"startToken":42149,"endToken":42155},{"p":144,"at":1501,"title":"E. Maximum AC line current: _______ Amps","method":"printed heading","endPage":144,"endAt":1547,"startToken":42155,"endToken":42161},{"p":144,"at":1547,"title":"F. Nameplate Power Factor Rating (AC): _______","method":"printed heading","endPage":144,"endAt":1600,"startToken":42161,"endToken":42167},{"p":144,"at":1600,"title":"G. Please attach capability curve describing reactive power or power factor","method":"printed heading","endPage":144,"endAt":1724,"startToken":42167,"endToken":42186},{"p":144,"at":1724,"title":"H. Inverter control mode (e.g. voltage, power factor, reactive power): _____","method":"printed heading","endPage":144,"endAt":1807,"startToken":42186,"endToken":42197},{"p":144,"at":1807,"title":"I. Short Circuit Characteristics: Applicant to provide technical data related to","method":"printed heading","endPage":148,"endAt":298,"startToken":42197,"endToken":42784},{"p":148,"at":298,"title":"A. Number of individual shunt capacitor banks: _____________","method":"printed heading","endPage":148,"endAt":362,"startToken":42784,"endToken":42791},{"p":148,"at":362,"title":"B. Individual shunt capacitor bank rated voltage (kV): _____________","method":"printed heading","endPage":148,"endAt":434,"startToken":42791,"endToken":42799},{"p":148,"at":434,"title":"C. Individual shunt capacitor bank size (kVAR at rated voltage):","method":"printed heading","endPage":148,"endAt":517,"startToken":42799,"endToken":42809},{"p":148,"at":517,"title":"D. Planned dynamic reactive control devices (SVC, STATCOM):","method":"printed heading","endPage":148,"endAt":594,"startToken":42809,"endToken":42817},{"p":148,"at":594,"title":"E. Control range: _____________ kVAR (lead) _____________ kVAR (lag)","method":"printed heading","endPage":148,"endAt":668,"startToken":42817,"endToken":42824},{"p":148,"at":668,"title":"F. Control mode (e.g. voltage, power factor, reactive power):","method":"printed heading","endPage":148,"endAt":748,"startToken":42824,"endToken":42834},{"p":148,"at":748,"title":"G. Please provide the overall plant reactive power control strategy","method":"printed heading","endPage":148,"endAt":1093,"startToken":42834,"endToken":42878},{"p":148,"at":1093,"title":"A. Manufacturer and model: ____________________________________","method":"printed heading","endPage":148,"endAt":1160,"startToken":42878,"endToken":42882},{"p":148,"at":1160,"title":"B. Source Functions","method":"printed heading","endPage":148,"endAt":1689,"startToken":42882,"endToken":42945},{"p":148,"at":1689,"title":"C. Charging Functions","method":"printed heading","endPage":149,"endAt":335,"startToken":42945,"endToken":43049},{"p":149,"at":335,"title":"D. Primary frequency response operating range for electric storage resources","method":"printed heading","endPage":149,"endAt":1591,"startToken":43049,"endToken":43242},{"p":149,"at":1591,"title":"A. Provide load flow model for the generating plant and its interconnection","method":"printed heading","endPage":149,"endAt":1945,"startToken":43242,"endToken":43291},{"p":149,"at":1945,"title":"B. For each generator, governor, exciter, power system stabilizer, WTG, or","method":"printed heading","endPage":149,"endAt":2415,"startToken":43291,"endToken":43358},{"p":149,"at":2415,"title":"C. For Large Loads, the Large Load Interconnection Customer shall provide a","method":"printed heading","endPage":160,"endAt":88,"startToken":43358,"endToken":46315},{"p":160,"at":88,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":236,"endAt":0,"startToken":46315,"endToken":72011},{"p":236,"at":0,"title":"ATTACHMENT B","method":"printed heading","endPage":237,"endAt":108,"startToken":72011,"endToken":72036},{"p":237,"at":108,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":294,"endAt":0,"startToken":72036,"endToken":86320},{"p":294,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":294,"endAt":700,"startToken":86320,"endToken":86427}]}