{"document":{"slug":"rec-20261116-5257","title":"TO: Response to Large Load Order to Show Cause in EL26-71-000","issued":"2026-11-16","accession":"20261116-5257","docket":"ER27-513-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"Pacific Gas and Electric Company","kind":"tariff filing","file":"sources/filings/text/20261116-5257_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5257","tier":"record","sha256":"26f1e93cfbb843d25e6de86490f52d40c8dfc153e0dd242fdb9c1650c80da184","pages":53,"tokens":24354,"emptyPages":[],"textThemes":["study","cost","flex","credit"]},"pages":[{"page":1,"startToken":0,"endToken":405,"text":"Mailing Address \nP.O. Box 1018 \nOakland, CA 94612-3534 \n501-551-4036 \nJohn.Perkins@pge.com \n \nJohn Perkins III \nChief Counsel \n \nNovember 16, 2026 \nThe Honorable Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC 20426 \nRE: Tariff Amendments in Response to FERC Order to Show Cause in Docket No. \nEL26-71-000 \nFiling Code: 10 \nDear Secretary Reese:   \nPursuant to section 205 of the Federal Power Act (“FPA”), Pacific Gas and Electric \nCompany (“PG&E”) submits amendments to its Transmission Owners Tariff, FERC Electric \nTariff Volume No. 5 (“TO Tariff”), to address the issues identified by the Federal Energy \nRegulatory Commission (“Commission” or “FERC”) as potentially unjust and unreasonable in \nits Order to Show Cause (“OSC”) issued in Docket No. EL26-71-000.1  Specifically, PG&E \nproposes changes to its TO Tariff to implement a process that will enable Transmission \nCustomers for Large Load (“TCLLs”) to interconnect “Large Load End Users” to the PG&E \ntransmission system.  The process will ensure that the necessary transmission facilities are in \nplace to provide the interconnection and transmission service required for the TCLLs to serve \nthose customers.2  PG&E’s proposed TO Tariff amendments and this filing are submitted in \nresponse to and answer the OSC pursuant to section 206 of the FPA, 16 U.S.C. § 824e, Rule 213 \nof the Commission’s Rules of Practice and Procedure, and Ordering Paragraph B of the OSC.   \nPG&E requests that the Commission find the proposed changes to the TO Tariff just and \nreasonable and that the changes address the issues raised in the OSC.  PG&E notes that the \nCAISO is proposing amendments to the CAISO Open Access Transmission Tariff (“CAISO \nTariff”) to address the issues raised in the OSC regarding the CAISO Tariff.  PG&E requests that \nthe Commission accept the proposed changes effective February 16, 2027, the same day that the \n \n1 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (“OSC”). \n2 The TO Tariff defines a TCLL as a “[Utility Distribution Company (“UDC”) or [Metered Subsystem \n(“MSS”] that provides service to Large Load End User(s); a UDC or MSS procures transmission service \nfrom the ISO based on its Gross Load in order to deliver power to End Users.”  TCLLs are referred to in \nother regions and the OSC as “Eligible Customers” (i.e., customers that take transmission service on \nbehalf of Loads, including Large Loads, in the CAISO’s Balancing Authority Area (“BAA”))."},{"page":2,"startToken":405,"endToken":945,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 2 \n \n \nCAISO requests that its proposed changes become effective.  PG&E also requests that the \nCommission, through its acceptance of PG&E’s proposed TO Tariff changes, terminate the show \ncause proceeding as to PG&E.   \nI. \nINTRODUCTION \nThe California Energy Commission (“CEC”) forecasts that data center load in the CAISO \nBAA will increase by 1.8 gigawatts (“GW”) by 2030 and 4.9 GW by 2040.3  In recent years, \nPG&E has received substantially more applications from large load customers seeking \ntransmission-level interconnections.4  The OSC arises from this increase in large load.   \nOn June 18, 2026, the Commission issued the OSC in Docket No. EL26-71 as one of six-\nregion specific orders to show cause addressing the unprecedented growth of large loads.5  The \nCommission instituted this proceeding to address the “urgent challenges associated with \nproviding the transmission service needed to serve the ongoing influx of large loads while \nmaintaining reliability and affordability,” including concerns that large loads are not efficiently \nintegrated onto the transmission system, that they pose unique reliability challenges, and that the \nrates, terms, and conditions of transmission service may not remain just and reasonable as large \nloads are added.6  The OSC preliminarily finds that the CAISO Tariff and the TO Tariffs may \nlack the provisions needed to provide transmission service to TCLLs reliably, affordably, and \nwithout shifting costs to other transmission customers.7  The OSC’s preliminary findings reflect \nfour related policy objectives.   \nThe first is reliability.  The OSC finds that large loads can be more energy-intensive and \ngeographically concentrated than other load growth and can affect the transmission system in \n \n3 CAISO, Large Load Considerations Issue Paper at 3, 8-9 (Jan. 30, 2026) (“CAISO Issue Paper”), \nhttps://www.caiso.com/documents/issue-paper-large-load-consideration-jan-20-2026.pdf (citing CEC data \ncenter forecast assumptions: https://www.energy.ca.gov/sites/default/files/2025-11-\n2025_IEPR_Preliminary_Data_Center_Forecast_ada.pfg). \n4 OSC at P 8 (citing PG&E November ANOPR Comments at 3). See generally Application of Pac. Gas & \nElec. Co. for Approval of Elec. Rule No. 30, A.24-11-007, Decision Partly Granting and Partly Denying \nPG&E’s Motion for Interim Implementation of Electric Rule No. 30, at 15 & Finding of Fact 7 (Cal. \nP.U.C. [July 24, 2025]) (“Rule 30 Interim Decision”). \n5 PJM Interconnection, LLC, 195 FERC ¶ 61,211 (2026); Southwest Power Pool, Inc., 195 FERC \n¶ 61,213 (2026); N.Y. Indep. System Operator, Inc., 195 FERC ¶ 61,216 (2026); Midcontinent Indep. Sys. \nOperator, Inc., 195 FERC ¶ 61,212 (2026); ISO New England Inc., 195 FERC ¶ 61,215 (2026).  See also \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (PJM Show Cause Order); PJM \nInterconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (PJM Co-Location Order); Sw. Power Pool, Inc., 194 \nFERC ¶ 61,031 (2026) (SPP HILL Order); Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026) (SPP \nCHILLS Order); see also, e.g., Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025); Commonwealth \nEdison Co., 194 FERC ¶ 61,181 (2026). \n6 OSC PP 1-2. \n7 OSC at PP 1-5; See also Interconnection of Large Loads to the Interstate Transmission System, Advance \nNotice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 23, 2025) (ANOPR)."},{"page":3,"startToken":945,"endToken":1455,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 3 \n \n \nways comparable to large generators, and therefore, require study processes and ongoing \noperational requirements tailored to their characteristics.8  The second is timely and efficient \nintegration.  The OSC seeks application study processes with defined timelines and readiness \nrequirements that deter speculative or duplicative requests, which can delay studies, distort load \nforecasts, and lead to unnecessary network upgrades, and it directs the evaluation of alternative \ntransmission technologies that can add capacity more quickly and at lower cost.9  The third is \nprotection of transmission customers.  The Commission seeks transparency regarding the \nnetwork upgrades and costs needed to serve large loads, and a cost recovery agreement to ensure \nthat transmission customers serving large loads bear their fair share of the costs to provide \ntransmission service to those loads.10  The fourth is flexibility.  The OSC notes that “load \nflexibility can avoid inefficient and costly transmission system build-out.”11 Accordingly, the \nCommission seeks tariff provisions that offer transmission services, with regional variation as \nappropriate, that reflect “the use of the transmission system by Eligible Customers on behalf of \nflexible large load, on both an interim and permanent basis.”12 In ordering these directives to be \nmet, however, the OSC acknowledges that the CAISO framework “is unique among the \nRTOs/ISOs” and that certain responsibilities fall to the Participating Transmission Owners \n(“PTOs” or “Participating TOs”), and the Commission does not seek to alter the allocation of \nresponsibilities between the CAISO and the PTOs.13 \nPG&E’s proposal responds to each of these concerns within the CAISO’s existing \nstructure and provides a clear, standardized framework that the growth of large loads in PG&E’s \nservice territory and the CAISO more broadly requires.  Because the CAISO does not offer \ntraditional stand-alone transmission service, PG&E proposes to implement the OSC’s directives \nprimarily through a new Section 10A of its TO Tariff that governs the interconnection of TCLLs \nto the transmission system on behalf of their Large Load End Users.  PG&E also proposes to \nimplement four new pro forma agreements, which can be found in Appendix XI of PG&E’s TO \nTariff.14  Specifically, PG&E proposes:  (1) an application process with readiness requirements, \nand separate Serial and Cluster Study processes for Electrically Independent and Electrically \nDependent Large Loads; (2) an Agreement to Interconnect Transmission Customer for Large \nLoad (“TCLL Agreement”) memorializing the TCLL Interconnection; (3) a Facilities Agreement \ngoverning construction and the cost responsibility framework for Direct Assignment and TCLL \nInterconnection Network Upgrades and expansions; (4) a Cost Assurance Agreement that \nprotects other transmission customers from cost shifting associated with TCLL Reliability \nNetwork Upgrades; and (5) a voluntary Interim Service Agreement that allows a TCLL to permit \nLarge Load End Users to begin taking Flexible Interim Large Load Interconnection Service \n \n8 Id. at PP 51-52, 57, 62. \n9 Id. at PP 54-55, 60. \n10 Id. at PP 65-66, 80. \n11 Id. at P 104. \n12 Id. at 104-105. \n13 Id. at P 37. \n14 These changes triggered other TO Tariff changes that are addressed herein."},{"page":4,"startToken":1455,"endToken":1916,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 4 \n \n \n(“FILLI Interconnection Service”), subject to curtailment, while the facilities needed for \ntraditional Standard Interconnection Service are completed.   \nIn developing these proposals, PG&E coordinated with the other Participating TOs in the \nCAISO footprint.  PG&E and Southern California Edison Company (“SCE”) reached broad \nconsensus on the cost responsibility and flexible service frameworks adopted in their respective \nproposals.  PG&E is also aligned with San Diego Gas & Electric Company (“SDG&E”) and LS \nPower Grid California, LLC (“LS Power”) on requiring a financial mechanism to protect against \nthe risk of cost shifting due to speculative or departing loads.  PG&E’s proposed changes provide \nthe clarity, consistency, and protection the OSC seeks.  They also preserve the CAISO’s \nTransmission Planning Process (“TPP”) as the primary means by which the CAISO plans the \nsystem to serve aggregate Load growth, including Large Loads, and preserve the coordinated \nroles of the CAISO and the Participating TOs.   \nFor these reasons and the reasons set forth below, PG&E requests that the Commission \nfind the proposed changes to the TO Tariff just and reasonable and that the changes address the \nissues raised in the OSC. \nII. \nBACKGROUND \nA. \nCAISO Is a Unique Transmission Market That Does Not Operate in \nthe Same Manner as Other RTOs.  \nThe OSC recognizes that “the framework under which CAISO provides transmission \nservice is unique among the RTOs/ISOs and that certain responsibilities fall to the Participating \nTransmission Owners.”15  Most other regions operate under the traditional framework \nestablished in Order No. 888.  There, the Commission required all public utilities that own, \noperate, or control interstate transmission facilities to offer network and point-to-point \ntransmission services to all Eligible Customers under a pro forma open access transmission \ntariff, and established “rules for discounting practices, provisions governing priority of service \nand curtailment, and a right of first refusal for all firm transmission customers.”16  That \nframework is based on advance reservations of transmission capacity by transmission customers.  \nA transmission customer, including the transmission provider, may reserve existing capacity for \nnative and network load growth, and the customer may secure firm transmission service ahead of \n \n15 OSC at P 37. \n16 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services \nby Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. \n888, FERC Stats. & Regs. ¶ 31,036 (1996), order on reh'g, Order No. 888-A, FERC Stats. & Regs. ¶ \n31,048, order on reh'g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh'g, Order No. 888-C, 82 \nFERC ¶ 61,046 (1998), aff'd in relevant part sub nom. Transmission Access Policy Study Group v. FERC, \n225 F.3d 667 (D.C. Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002)."},{"page":5,"startToken":1916,"endToken":2378,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 5 \n \n \nits need.17  Those transmission reservation requests are made through a formal application \nprocess set forth in the transmission provider’s Tariff.18  \nAs the OSC recognizes, the CAISO’s framework differs from this traditional framework \nin several key ways.  The CAISO’s transmission service model has no formal application process \nfor transmission service, and wholesale transmission customers do not reserve transmission \ncapacity in advance.19  Instead, Scheduling Coordinators—entities certified by the CAISO to \nsubmit balanced schedules on behalf of customers20—submit bids or self-schedules for supply \nand demand into the CAISO day-ahead and real-time markets, with equal access to all available \ntransmission capacity each day.   If available transmission capacity is insufficient, losing bidders \ncannot schedule service.  If in real-time all accepted schedules cannot be met, due to unexpected \nor unplanned events, the CAISO curtails schedules based on tariff-defined scheduling \npriorities.21   \nUnlike a traditional network customer, the Scheduling Coordinator does not reserve, or \npay for, transmission service on behalf of a specific Load.  Nor does the Scheduling Coordinator \npay an access charge for scheduling and settling Load on behalf of Eligible Customers.  Rather, \nthe CAISO Tariff assesses Regional and Local Access Charges on each UDC or MSS, as \nEligible Customers, represented by a Scheduling Coordinator to serve Load.  As a result, the \nfunctions of a single network customer requesting service in other RTOs are divided among, and \ncoordinated between, the PTOs, Scheduling Coordinators, and UDCs and MSSs.   \nUnder this unique framework, the CAISO does not refer to wholesale transmission \ncustomers as “Eligible Customers” in the same way as the OSC.22  Rather, in the CAISO, an \n“Eligible Customer” is the UDC or MSS that procures transmission service and provides service \nto Large Load End Users.23  PG&E is therefore proposing terminology tailored to how \ntransmission service is provided to the same wholesale transmission customers referenced in the \n \n17 Order No. 888-B, 81 FERC ¶ 61,248 (1997) (addressing the provider’s ability to reserve existing \ncapacity for native and network load growth, and a firm point-to-point customer’s options to elect \nnetwork service, extend its contract term, or reassign capacity). \n18 See pro forma Tariff §§ 17, 29. See also, Open Access Same-Time Information System (formerly Real-\nTime Information Networks) and Standards of Conduct, Order No. 889 (establishing the OASIS through \nwhich requests for service under the pro forma tariff are made). \n19 Virani Testimony at 2-3; Nedrud Testimony at 2-5; OSC at P 39.   \n20 Cal. Indep. Sys. Operator Corp., 87 FERC ¶ 61,143 (1999) (describing Scheduling Coordinators as \nentities certified by the ISO to submit balanced schedules under the ISO Tariff). \n21 See generally CAISO Tariff § 7. \n22 Virani Testimony at 2-3.  \n23 See generally CAISO Tariff § 4.4 (Relationship Between CAISO and UDCs)."},{"page":6,"startToken":2378,"endToken":2824,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 6 \n \n \nOSC.24  For these reasons, PG&E refers to the entities that receive transmission service on behalf \nof Large Loads as TCLLs, not Eligible Customers.25   \nB. \nCAISO and the PTOs Each Perform Unique and Coordinated \nFunctions with Respect to Requests to Interconnect to the \nTransmission System  \nParticipating TOs are responsible for studying requests from customers with Wholesale \nLoad to interconnect to the CAISO-controlled transmission system (“CAISO Controlled Grid”) \nor increase or modify the nature or number of delivery points to serve such Load as it grows \nunder the TO Tariff.26  PG&E’s Wholesale Load Interconnection service is coordinated with the \nCAISO, which provides Market Access and Generation (i.e., resource) interconnection service to \nsuch Wholesale Load.27  This coordinated framework supports the respective tariff \nresponsibilities of the Participating TOs and the CAISO under the Transmission Control \nAgreement and ensures that Wholesale Load Interconnections are studied, planned, and \nimplemented consistent with transmission reliability requirements and long-term transmission \nplans.28  Applicants seeking wholesale generation interconnection to the CAISO Controlled Grid \nsubmit their requests to the CAISO, while applicants seeking Wholesale Load Interconnection \nsubmit their requests to the relevant Participating TO.29   \nThe CAISO reviews the impacts of all new Load interconnections and increases in Load \ngrowth using two related processes.  The first is the annual TPP conducted under Section 24 of \nthe CAISO Tariff.  The TPP is the process the CAISO uses to plan the transmission system and \napprove transmission solutions, including constructing new transmission facilities and network \nupgrades, to serve load growth within the CAISO footprint.30  The TPP integrates the CEC \nstatewide long-term energy demand forecast and the CPUC’s integrated resource planning \ninformation, both of which consider and account for large loads.31  The second is the CAISO’s \n“concurrence” process, which allows the Participating TOs to propose transmission solutions and \n \n24 See CAISO, Proposed Appendix A (definition of \"Large Load\"), Second Revised Draft Tariff Language \n– Large Loads Order to Show Cause at 17 (Oct. 30, 2026), \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/Second-Revised-Draft-Tariff-Language-Large-\nLoads-Order-to-Show-Cause-Oct-30-2026.docx. (“CAISO Tariff, Proposed”). \n25 Virani Testimony at 2-3, 5-6. \n26 Wholesale loads connecting to the Distribution System of PG&E interconnect under its Wholesale \nDistribution Tariff (“WDT”). \n27 Generator interconnections to the Distribution System of PG&E also are subject to the WDT. \n28 Virani Testimony at 3-6; Nedrud Testimony at 3-5. \n29 See TO Tariff, § 10. \n30 CAISO Tariff § 24.1; OSC at PP 21-22 & n.79; Memorandum of Understanding Between the CPUC, \nthe CEC, and the CAISO Regarding Transmission and Resource Planning and Implementation (Dec. \n2022). \n31 CAISO, Large Load Considerations Issue Paper at 8-10 (Jan. 30, 2026)."},{"page":7,"startToken":2824,"endToken":3242,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 7 \n \n \nnetwork upgrades in the TPP when Load seeks to interconnect after the demand forecast and \nresource portfolios have been developed.32  Under this process, the Participating TO studies the \nproposed Load interconnection and identifies any Reliability and network upgrades.33  The \nParticipating TO may then submit the Load interconnection study results to the CAISO for \nreview and concurrence that the Load meets applicable transmission reliability and long-term \ntransmission planning requirements.34  The CAISO reviews the interconnection studies, together \nwith other Load growth, in the TPP to determine whether additional upgrades are necessary.35  \nThe CAISO, however, does not conduct studies to determine the necessary network upgrades for \nthe provision of transmission service outside the TPP.36   \nC. \nPG&E and the Other Founding Transmission Owning Members of \nCAISO Have Unique and Specific Roles. \nPG&E is one of the three Original Participating Transmission Owners (“Original \nParticipating TOs”) that transferred Operational Control of their transmission facilities to the \nCAISO while retaining ownership, physical operation, and maintenance responsibilities of those \nfacilities.  The Original Participating TOs have a distinct position within the CAISO market \nstructure.   \nLike the other Original Participating TOs, PG&E must purchase transmission service for \nall retail customers within its service territory.  Most retail customers located in the CAISO BAA \ninterconnect to distribution facilities owned by a UDC or MSS under retail tariffs approved by \nthe Local Regulatory Authority, or the California Public Utilities Commission (“CPUC”), if the \nutility is investor-owned.  These retail tariffs govern the study costs, retail rates, and potential \ncost recovery for retail Load interconnections.37  However, when the MSS or UDC is not a PTO, \nthe MSS or UDC must seek Wholesale Load Interconnection service through the Participating \nTO Tariff to provide transmission service to those retail customers.  As an Original Participating \nTO, PG&E is not a wholesale transmission customer on its transmission system and is not \n \n32 Nedrud Testimony at 10-11. \n33 Id. \n34 Id.; Virani at 4-5. \n35 Nedrud  at 10-11. \n36 OSC at P 39. \n37 The few retail customers that seek to interconnect directly to a Participating TO’s Transmission System \nalso obtain service through a UDC or MSS (i.e., the Eligible Customer) rather than seeking service \ndirectly from the CAISO.  Such retail customers can only obtain transmission service from their UDC or \nMSS but may be permitted by their Local Regulatory Authority to choose another load-serving entity \n(“LSE”) to provide them “generation service” (i.e., energy and capacity)."},{"page":8,"startToken":3242,"endToken":3773,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 8 \n \n \nrequired to seek Wholesale Load Interconnection service to serve retail customers connecting to \nits Distribution System.38   \nParticipating TOs recover their just and reasonable regional transmission costs through \nRegional Transmission Revenue Requirements (“RTRRs”) approved by the Commission.  Non-\nLoad Serving Entity (“LSE”) Participating TOs bear different obligations within the CAISO \nframework; they generally joined the CAISO after its formation by constructing transmission \nfacilities selected through the competitive solicitation process the Commission established in \nOrder No. 1000.  Order No. 1000 directed transmission providers to remove federal rights of first \nrefusal for facilities selected in a regional transmission plan for purposes of cost allocation and to \nadopt qualification criteria and protocols for evaluating competing, non-incumbent proposals.39  \nSuch entities do not have Participating TO Service Territories and do not have an obligation to \nserve retail Load.40  Because Non-LSE Participating TOs do not sell retail services, Participating \nTOs with Participating TO Service Territories41 will bear primary responsibility for processing \nLarge Load applications from TCLLs, conducting Wholesale Load Interconnection studies, \ncoordinating with Affected Systems with regard to changes in Load, and managing the cost \nresponsibility and cost recovery. \nD. \nThe OSC Preliminarily Found the CAISO and TO Tariffs to Be Unjust \nand Unreasonable as They Pertain to Eligible Customers Serving \nLarge Loads.  \nIn the OSC, the Commission preliminarily found that the CAISO’s Tariff and/or the TO \nTariffs appear to be unjust, unreasonable, or unduly discriminatory or preferential on the five \nbases summarized above.  The Commission directed its findings to “CAISO’s Tariff and/or the \nTO Tariffs” and expected the CAISO and the Participating TOs to “coordinate with each other, \nas appropriate, to develop responses to this order.”42  Consistent with that direction, the CAISO \n \n38 See Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (clarifying that \"retail customers taking unbundled \nservice pursuant to a state requirement (i.e., direct retail service) are eligible for such service only from \nthose transmission providers that the state orders to provide service.\"). \n39 Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. \n1000, 136 FERC ¶ 61,051, at PP 6, 9, 13, 558, 690 (2011), order on reh'g, Order No. 1000-A, 139 FERC \n¶ 61,132, order on reh'g & clarification, Order No. 1000-B, 141 FERC ¶ 61,044 (2012), aff'd sub nom. \nS.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014). \n40 In collecting their RTRRs from the CAISO, there is no netting of the TRR entitlement and payment for \ntransmission service.   \n41 A Participating TO Service Territory is “[t]he area in which an IOU, a Local Public Owned Electric \nUtility, or federal power marketing authority that has turned over its transmission facilities and/or \nEntitlements to CAISO Operational Control is obligated to provide electric service to Load.  A \nParticipating TO Service Territory may be comprised of the Service Areas of more than one Local \nPublicly Owned Electric Utility, if they are operating under an agreement with the CAISO for aggregation \nof their MSS and their MSS Operator is designated as the Participating TO.” Appendix A to CAISO \nTariff (defining Participating TO Service Territory). \n42 OSC at P 37."},{"page":9,"startToken":3773,"endToken":4214,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 9 \n \n \nand the Participating TOs have divided their responses along the lines that govern their \nrespective roles.  The CAISO is addressing the matters that implicate the CAISO Tariff and the \nfunctions for which it is responsible—market access, the generator interconnection process, and \nthe CAISO’s responsibility “for access to and the provision of transmission service, including \ntransmission and ancillary services, to all Eligible Customers, and the reliability of that \ntransmission service.”43  PG&E and the other Participating TOs are addressing the matters that \nimplicate their TO Tariffs—the application process, study procedures, related requirements for \nevaluating and effectuating the TCLL’s request to interconnect Large Loads, and the provision of \ncost responsibility for a TCLL providing transmission service on behalf of a Large Load End \nUser.  PG&E submits the proposed TO Tariff revisions described below pursuant to its rights \nunder section 205 of the FPA, as the Commission encouraged.44  As explained below, those \nchanges are just and reasonable and address the issues in the OSC. \nIII. \nPG&E SUPPORTS THE CAISO’S PROPOSED DEFINITION OF LARGE LOAD \nAS BEING JUST AND REASONABLE. \nA. \nThe OSC Requires a Definition of Large Load Sufficient to Capture \nthe Loads That Present the Unique Challenges to the Transmission \nSystem Identified in the OSC. \nThe OSC preliminarily found that the CAISO Tariff and/or the TO Tariffs appear to be \nunjust and unreasonable because they lack “a definition of large load, as a new category of \nload.”45  As the Commission explained, integrating large loads poses specific challenges \nbecause, although large loads are retail customers, they can impact reliability on the transmission \nsystem in ways comparable to large wholesale generators.46  The OSC therefore directs that an \nappropriate definition, including load size, be adopted.  The OSC also notes that the definition \nshould be based on the characteristics of CAISO’s transmission system.47 \nImportantly, the OSC did not mandate a particular definition.  Rather, the Commission \nidentified, based on the record in the Large Load Advanced Notice of Proposed Rulemaking \nproceeding, a definition that it preliminarily found would be reasonable:  \na new commercial or industrial customer, located at a single site \nbehind one or more points of interconnection, that has a peak load \nof 50 MW or greater, interconnects to the transmission system at a \n \n43 Id. at P 39. \n44 16 U.S.C. § 824d; OSC at P 34. \n45 OSC at P 57; see also id. at P 56 (identifying the absence of \"a definition of large load sufficient to \ncapture loads that present the unique challenges described herein\"). \n46 Id. at P 57. \n47 Id."},{"page":10,"startToken":4214,"endToken":4646,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 10 \n \n \nvoltage level of greater than 69 kV, and is not part of a co-location \narrangement.48  \nThe Commission directed the CAISO and the Participating TOs either to explain whether \ntheir tariffs remain just and reasonable without such a definition or to propose tariff revisions \nestablishing their own definition of large load.49  \nB. \nPG&E Supports and Adopts CAISO’s Proposed Definition of Large \nLoad Because it Meets the Requirements of the OSC While \nMaintaining the Unique Aspects of the CAISO Transmission System.  \nIn response to the OSC, PG&E proposes to amend its TO Tariff to adopt the CAISO’s \nproposed definition of Large Load.  CAISO proposes to define Large Load as “an End User \nlocated at a single site or behind one or more point(s) of interconnection to the CAISO \nControlled Grid, and that has a peak load of 50 MW or greater.”50  This definition satisfies the \nOSC’s requirements.  It adopts the 50 MW peak-load threshold and includes Large Loads that \nare interconnecting behind the CAISO Controlled Grid and that have a Point of Withdrawal on \nthe CAISO Controlled Grid for taking transmission service.51  \nThe CAISO’s proposed definition appropriately captures the transmission-service \nrelationship at issue in the OSC, while avoiding an artificial requirement that the end user \nconnect directly to the grid.52  The vast majority of Large Loads in the CAISO do not connect \ndirectly to the CAISO-Controlled Grid.  Rather, Large Loads typically connect to the \nDistribution Systems of their TCLL.  However, those Large Loads have an impact on the \ntransmission system when the TCLL seeks interconnection and transmission service to serve the \nLarge Load End User.  The proposed definition encompasses the Large Load that the OSC \nintended to reach and therefore appropriately addresses the Commission’s concerns.  The \n \n48 OSC at P 57. \n49 Id. \n50 CAISO, Proposed Appendix A (definition of \"Large Load\"). \n51 OSC at P 57.  PG&E proposes accommodating changes in its TO Tariff to add a definition of “Large \nLoad End User” to define a specific Large Load as a retail transmission customer that purchases energy \nbehind one or more points of interconnection to the ISO Controlled Grid or to the Distribution System.  \nFor Large Load End Users with multiple “Point(s) of Withdrawal,” the definition is clear that for a Large \nLoad End User the Point of Withdrawal is “where a non-transmission facility that is used to withdraw \nEnergy from the ISO Controlled Grid to serve a Large Load End User connects to the ISO Controlled \nGrid.”   \n52 OSC at P 57."},{"page":11,"startToken":4646,"endToken":5136,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 11 \n \n \nCAISO’s proposed definition is also consistent with the definition of large load proposed in the \nOSC53 and definitions adopted by other regions that have been approved by the Commission.54   \nFor these reasons, PG&E concludes that the CAISO’s proposed definition is just and \nreasonable and should be used consistently in the CAISO Tariff and the TO Tariffs.  Thus, \nPG&E proposes to include the CAISO proposed definition for Large Load in its TO Tariff.    \nIV. \nPG&E PROPOSES JUST AND REASONABLE CHANGES TO ITS TARIFF TO \nIMPLEMENT A NEW APPLICATION AND STUDY PROCESS FOR TCLLS \nINTERCONNECTING LARGE LOAD END USERS TO THE PG&E \nTRANSMISSION SYSTEM. \nAs discussed in Section II, the CAISO does not offer Order No. 888 network or point-to-\npoint transmission service, does not accept advance reservations of transmission capacity, and \nhas no formal application process for transmission service.55 Identifying the necessary \ntransmission facilities needed to accommodate new Loads interconnecting to the transmission \nsystem through UDCs and MSSs is conducted through either the TO Tariff or the CAISO TPP \nProcess.  The CAISO conducts the TPP pursuant to Section 24 of the CAISO Tariff to identify \ntransmission solutions needed for the CAISO system, including maintaining system reliability \nand reducing congestion.56  Participating TOs study interconnection requests under the TO Tariff \nand, where reliability network upgrades and network upgrades are implicated, either seek the \nCAISO’s concurrence that the project is a transmission facility that should be included in the \nCAISO Controlled Grid, that transmission cost recovery is appropriate, and that the project is \nconsistent with the CAISO’s operational and planning requirements, or the need is addressed \nthrough the TPP.57  \nConsistent with this existing framework for addressing interconnection service requests, \nPG&E proposes to address the OSC’s directives concerning the provision of transmission service \nto Eligible Customers on behalf of Large Loads (referred to by PG&E as TCLL’s) through its \n \n53 OSC at P 57. \n54 See e.g., PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at PP 16, 27-32 (2026) (approving PJM’s \ndefinition of large load as an end-use customer “…behind one or more points of interconnection….”).  \nSee also, NERC, Characteristics and Risks of Emerging Large Loads (July 2025), \nhttps://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics-and-\nrisks-of-emerging-large-loads.pdf (NERC Characteristics and Risks of Large Loads). \n55 OSC at P 19; see Cal. Indep. Sys. Operator Corp., 87 FERC ¶ 61,143 (1999) (the ISO Tariff “differs \nfrom the pro forma tariff in that it does not delineate transmission services into firm and nonfirm \ncategories,” and the Access Charge provides “general access to the ISO grid, but without any \ncommitment as to what specific transactions … will be accommodated”). \n56 CAISO Tariff § 24.1. \n57 Nedrud Testimony at 10-11, 32; OSC at PP 23, 25, 39; see Pac. Gas & Elec. Co., 81 FERC ¶ 61,122 \n(1997) (addressing the ISO’s “transmission expansion and planning process”)."},{"page":12,"startToken":5136,"endToken":5631,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 12 \n \n \nTO Tariff interconnection process, coordinated with the CAISO’s TPP and concurrence \nprocesses, as described below. \nA. \nPG&E Proposes a Just and Reasonable Process for a TCLL to Apply \nfor Large Load Interconnection Service That Meets the Requirements \nof the OSC. \nThe OSC found that PG&E’s TO Tariff may be unjust and unreasonable because it lacks \n“sufficiently clear and consistent provisions establishing the application process . . . that will be \nused when CAISO and/or the [PTO] evaluate the provision of transmission service to Eligible \nCustomers on behalf of Large Loads.”58  Specifically, the OSC identifies three elements the TO \nTariff appears to lack: (1) an application process that accepts Eligible Customers’ applications \nfor transmission service on behalf of large loads on a rolling basis; (2) a non-refundable \napplication fee and sufficient readiness requirements that escalate at distinct phases of the study \nprocess to deter duplicative or speculative requests for transmission service, such as meaningful \nmilestones and/or financial commitments; and (3) information and data requirements that \nEligible Customers must submit to the CAISO and/or the Participating TOs regarding the \ncharacteristics of the large load, including disclosure to the CAISO of any substantially similar \npending transmission service requests on behalf of the same Large Load End User.59  \nPG&E proposes to address this directive through a structured application process in a \nnew Section 10A.2 of its TO Tariff under which a TCLL applies for interconnection service to \nserve a Large Load End User.60  PG&E’s proposed Section 10A.2 is modeled on the existing \nSection 10 wholesale-load process but with specific attributes targeted at addressing the \ndeficiencies in the OSC, including readiness, data, and coordination requirements needed for \nTCLL Interconnection Applications.61  Under this process, PG&E intends to review TCLL \nInterconnection Applications for completion on a rolling basis, with the request then being \nstudied under a Serial Study Process (§ 10A.4) or a Cluster Study Process (§ 10A.5) after an \nelectrical-independence determination.62   \nProposed Section 10A.2.1 requires a TCLL requesting interconnection service to submit \na TCLL Interconnection Application electronically to PG&E in the manner and format \nprescribed through PG&E’s Open Access Same-Time Information System (“OASIS”) and \nprovide a copy of the application to the CAISO.  Proposed Section 10A.2.1 also requires that a \nTCLL Interconnection Application include information that describes the characteristics of the \n \n58 OSC at P 58. \n59 Id. . \n60 To avoid any appearance of discrimination, PG&E will treat itself as a TCLL when the “Large Load \nEnd User” is in its service area.  PG&E provides retail transmission service in its service area regardless \nof the identity of the LSE or Scheduling Coordinator for the Large Load End User.   \n61 Virani Testimony at 10-11. \n62 An exception being that TCLL Interconnections associated with a Co-Located Large Load End User \nwill always be studied under the Cluster Study Process.  Id. at 18, 19."},{"page":13,"startToken":5631,"endToken":6131,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 13 \n \n \nLarge Load End User, including:  (i) the Point of Withdrawal; (ii) a proposed Large Load End \nUser fifteen-year load ramp schedule identifying anticipated Load additions over time and its \nmaximum Load; (iii) a single-line electrical diagram; (iv) the electrical location of the source of \nthe power (if known) to be transmitted pursuant to the TCLL’s request for TCLL \nInterconnection; and (v) a completed PG&E Large Load Technical Data Request Workbook in \nthe form provided on PG&E’s public website.63  The TCLL Interconnection Application also \nrequires information demonstrating that the request is not speculative and is capable of moving \nforward, such as:  (i) a site plan; and (ii) an attestation from the TCLL that the Large Load End \nUser has Site Control.  The TCLL Interconnection Application also requires the TCLL to \ndisclose TCLL Interconnection requests in the TCLL’s footprint that are for the same Large \nLoad End User or any of its affiliate(s).  In addition, if the TCLL Interconnection Application \nrequests Interim Standard Interconnection Service and/or FILLI Interconnection Service, the \nTCLL must so indicate and, if FILLI Interconnection Service is requested, the FILLI \nInterconnection Service addendum to the TCLL Interconnection Application must be completed.  \nFinally, the TCLL Interconnection Application requires that the TCLL provide information \nconcerning all relevant co-located generating facilities if the Large Load End User will be a Co-\nLocated Large Load End User. Thus, consistent with the OSC directives, PG&E proposes an \napplication process that requires the TCLL to submit information necessary for PG&E and the \nCAISO to understand the characteristics of the Large Load End User and to demonstrate that the \napplication is not speculative through a site plan and attestations of clear Site Control.64 \nProposed Section 10A.2.2 establishes a nonrefundable application fee of $25,000 to be \nsubmitted by the TCLL with its TCLL Interconnection Application.  The fee is designed to cover \nPG&E’s costs to review the application for completeness.65  It also will assist in ensuring that \napplications are not speculative.  As outlined in the OSC, the nonrefundable application fee when \ncombined with the study deposit requirements proposed below will help deter speculative \nrequests.66 \nProposed Section 10A.2.3 sets forth the study deposit requirements for a TCLL \nsubmitting a TCLL Interconnection Application.  The study deposit requirement includes a \n$500,000 cash deposit and financial security in the amount of $1,000 per MW of requested \nmaximum load.67  The deposit and security will cover the Participating TOs’ actual costs \nincurred to perform the Electrical Independence Test and specific required studies,68 including \nany analysis for FILLI Interconnection Service and/or Interim Standard Interconnection Service.   \n \n63 See Virani Testimony at 20. \n64 OSC at P 58. \n65 Virani Testimony at 17-18. \n66 OSC at P 58. \n67 Virani Testimony at 17-18. \n68 Id. As detailed below, a second deposit is required for Electrically Dependent Large Load to proceed \nthrough the Phase 2 Cluster Study."},{"page":14,"startToken":6131,"endToken":6542,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 14 \n \n \nProposed Section 10A.2.4 establishes a process for reviewing and processing TCLL \nInterconnection Applications.  Within ten (10) Business Days of receipt of a TCLL \nInterconnection Application, PG&E shall determine whether the application is complete.  Thus, \nconsistent with the OSC requirements, PG&E will process the TCLL Interconnection \nApplications for completeness on a rolling 10-day basis.69  The proposed provisions also require \nPG&E to treat all information provided in the TCLL Interconnection Application as confidential \nexcept to the extent that disclosure of this information is required by the TO Tariff, the CAISO \nTariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, \nfor Affected Systems purposes pursuant to other Interconnection Agreements, or pursuant to \nRTO or ISO transmission information sharing agreements.   \nWithin fifteen (15) Business Days after the TCLL Interconnection Application is deemed \ncomplete, PG&E shall perform the Electrical Independence Test pursuant to proposed Section \n10A.3.1.70  The Electrical Independence Test determines whether the Large Load End User \nbeing interconnected by the TCLL qualifies as an Electrically Independent Large Load or an \nElectrically Dependent Large Load.71  The Electrical Independence Test will include an \nincremental power flow test and aggregate power flow tests.72  These tests will analyze whether \na TCLL Interconnection Application materially affects, or does not affect, other projects, and the \nresults of that analysis will determine how the TCLL Interconnection Application is studied.73  \nWithin five (5) Business Days of completion of the Electrical Independence Test, PG&E will \nhold a scoping meeting for Electrically Independent Large Load to address the preliminary \ninterconnection scope, discuss the Point of Withdrawal, present preliminary planning \nassumptions and known system limitations, and available system capacity.74   \nWithin fifteen (15) Business Days after the meeting, the TCLL must elect to proceed \nunder the applicable Serial Study Process or withdraw its TCLL Interconnection Application.  If \nwithdrawn, the Participating TO shall calculate its costs spent on the application and return the \nunspent portion of the $500,000 study deposit and financial security and release any remaining \nportion of the financial security.  Electrically Dependent Large Load proceeds under the Cluster \nStudy Process in proposed section 10A.5 detailed below.  \n \n69 OSC at P 58. \n70 Nedrud Testimony at 12. \n71 Id. at 13-14.  \n72 Id. See also CAISO Tariff, Proposed § 25.7.  \n73 Nedrud Testimony at 13-14; TO Tariff, Proposed § 10A.3. \n74 Nedrud Testimony at 14-15."},{"page":15,"startToken":6542,"endToken":7011,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 15 \n \n \nB. \nPG&E Proposes a Just and Reasonable Study Process for Evaluating \nthe Provision of Transmission Service to TCLLs on Behalf of Large \nLoads That Meets the Requirements of the OSC. \nThe OSC found that PG&E’s TO Tariff may be unjust and unreasonable because it lacks \n“sufficiently clear and consistent provisions establishing a study process for evaluating the \nprovision of transmission service to Eligible Customers on behalf of large loads that considers \nthe unique characteristics and impacts of large loads on the transmission system.”75  Specifically, \nthe OSC requires PG&E to establish a study process that evaluates the transmission system’s \nability to withstand the risks observed from analyzed large load behavior, together with any other \nsupplemental studies necessary to evaluate the impact of providing such transmission service.76  \nThe study-process provisions must also recognize the unique operational characteristics of large \nloads that are willing and able to limit their energy withdrawals under certain conditions that \nmay lessen or avoid the need for certain network upgrades.77  The OSC indicates that it appears \nreasonable for such study processes — culminating in a report to the Eligible Customer with the \nstudy results, including any Direct Assignment Facilities and network upgrades necessary to \naccommodate the request and a non-binding good-faith estimate of the cost and time to construct \nsuch facilities — to take no more than 60-90 calendar days to complete.78  Finally, the OSC \nrequires PG&E to evaluate alternative transmission technologies as potential solutions to \naccommodate an Eligible Customer’s request for transmission service on behalf of a large load.79   \nTo address the issues identified in the OSC, PG&E proposes to amend its TO Tariff to \nincorporate a process to study TCLL requests in Section 10A, which accommodates two distinct \nstudy processes: a Serial Study Process in Section 10A.4 to govern Electrically Independent \nLarge Loads and a Cluster Study Process in Section 10A.5 to govern Electrically Dependent \nLarge Loads.  \nPG&E proposes two separate study processes for TCLLs based on the type of Load being \nstudied to ensure that each Large Load End User is properly studied based on its technical \ncharacteristics and potential impact on the transmission system.  Based on its experience \nstudying Large Load requests to interconnect to date, Electrically Dependent Large Loads and \nElectrically Independent Large Loads have different impacts on the transmission system and thus \nmust be studied differently.80 An Electrically Independent Large Load’s interconnection impacts \nare not materially affected by other projects.81  As a result, an Electrically Independent Large \nLoads can be studied on a rolling, serial basis without assuming the status, timing, or \n \n75 OSC at P 59. \n76 Id. \n77 Id.  at P 59. \n78 Id. at P 62. \n79 Id.  \n80 Nedrud Testimony at 13-14.  \n81 Id."},{"page":16,"startToken":7011,"endToken":7438,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 16 \n \n \nconfiguration of other queued projects and can be studied within the timeframe contemplated by \nthe OSC.82   \nIn contrast, an Electrically Dependent Large Load’s interconnection impacts are \nmaterially affected by other projects or arise when multiple projects collectively affect the same \ngrid facilities.83  Studying such requests sequentially would require repeated restudies as \napplicants withdraw or change their configurations and would delay later applicants.84  Instead, \nin PG&E’s experience, studying Electrically Dependent Large Loads together produces more \naccurate results, identifies interactions among projects, and avoids serial restudies.85  Within the \nlast few years, PG&E has performed three (3) cluster studies, involving ninety-three (93) \nseparate applications, for Large Load End Users greater than 20 MW seeking CPUC-\njurisdictional interconnections and has found that the collective approach effectively and \nefficiently identifies needs and plans solutions.86  In light of the differences in the types of Large \nLoad and PG&E’s experiences, PG&E proposes a Serial Study Process for Electrically \nIndependent Large Loads and a Cluster Study Process for Electrically Dependent Large Loads.   \n1. \nPG&E Proposes a Serial Study Process for Electrically Independent \nLarge Loads that Mirrors the Serial Process for Other Wholesale \nInterconnections in Section 10 Of the TO Tariff \nProposed Section 10A.4 establishes a serial study process for Electrically Independent \nLarge Loads consistent with the existing process used for Wholesale Load Interconnections in \nSection 10.  The proposed serial process starts with a System Impact Study.  Under Section \n10A.4.2, within sixty (60) Business Days of receipt of an executed System Impact Study \nAgreement, PG&E will use due diligence to complete the required System Impact Study.  The \nSystem Impact Study will identify: (i) whether any Direct Assignment Facilities and TCLL \nInterconnection Network Upgrades are required; and (ii) any adverse impact on existing \nEncumbrances.  In addition, PG&E will consider alternative transmission technologies, and if \ntraditional network upgrades are selected instead of alternative transmission technologies, PG&E \nwill provide a demonstration of why alternative transmission technologies are not feasible or \nwould not result in lower costs or a faster timeline for accommodating the TCLL \nInterconnection.  The System Impact Study will also provide an estimated cost for the Direct \nAssignment Facilities and TCLL Interconnection Network Upgrades.87  To the extent reasonably \npracticable, PG&E shall rely on existing transmission planning studies.   \n \n82 Nedrud Testimony at 14. \n83 Nedrud Testimony at 19-20. \n84 Id. at 19, 26-27.   \n85 Id. \n86 Id. at 26. \n87 Each of these facility types is discussed in more detail below."},{"page":17,"startToken":7438,"endToken":7978,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 17 \n \n \nProposed Sections 10A.4.4 and 10A.4.5 then set the conditions for moving from the \ncompleted System Impact Study to a Facilities Study, if a Facilities Study is elected or required.  \nThe TCLL can also choose to move forward with the requisite agreements rather than have a \nFacilities Study that will provide more detail as to required upgrades and their costs, with the \nexception that a TCLL seeking Interim Interconnection Service88 is required to undergo a \nFacilities Study.  When the customer elects Interim Interconnection Service, the more detailed \nFacilities Study is required to assess those more dynamic and flexible interconnections.   \nIf no Facilities Study is requested or required, the TCLL proceeds to proposed Section \n10A.4.8, and the Participating TO will tender the Facilities Study Agreement within fifteen (15) \nBusiness Days.  The Facilities Study Agreement will, among other things, define the scope, \nterms, and estimated completion time of the Facilities Study.  The TCLL shall execute the \nFacilities Study Agreement within fifteen (15) Business Days, or ask that it be filed unexecuted \nat FERC, or the application shall be deemed withdrawn.  If an unexecuted filing is requested, the \nSerial Study Process will be paused until the Facilities Study Agreement is made effective by \nFERC. \nProposed Section 10A.4.6 describes the Facilities Study procedures and provides that \nwithin sixty (60) Business Days of receipt of an executed Facilities Study Agreement, PG&E \nwill use due diligence to complete the Facilities Study.  The Facilities Study will provide a \nrevised cost estimate of Direct Assignment Facilities and TCLL Interconnection Network \nUpgrades, as well as identify and provide a cost estimate of any TCLL FILLI Facilities, if \napplicable.   Proposed Section 10A.4.7 sets forth the timeline for tendering the TCLL Agreement \nand related agreements.  If the TCLL seeks to move forward, Section 10A.4.8 would be the next \nstep, which provides sixty (60) Business Days to negotiate and execute the various required \ninterconnection agreements: the TCLL Agreement, the Facilities Agreement, the Cost Assurance \nAgreement, and if applicable, the Interim Service Agreement.   \nThe deadlines collectively reflect a Serial Study Process of approximately 80 to 95 \nBusiness Days, depending on how long the applicant takes to execute the System Impact Study \nAgreement, from the application being complete to having System Impact Study results, \nconsistent with the OSC’s 90-day target for Electrically Independent Large Loads.89  It also \nreflects that a decision to go through the Facilities Study process is optional (with the exception \nof a TCLL seeking Interim Standard Interconnection Service) and that negotiating and drafting \nthe TCLL Agreement and associated agreements may take additional time.   \nPG&E’s proposed study procedure will also account for the dynamic behavior of Large \nLoad End Users at the Point of Withdrawal on the CAISO system, consistent with the OSC \ndirectives.90  In addition, in accordance with the OSC, PG&E will assess alternative transmission \ntechnologies and where traditional network upgrades are selected, PG&E will demonstrate why \n \n88 The use of the term Interim Interconnection Service in this document refers to both Interim Standard \nInterconnection Service and FILLI Interconnection Service. \n89 Nedrud Testimony at 27; OSC at P 38. \n90 OSC at P 38."},{"page":18,"startToken":7978,"endToken":8448,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 18 \n \n \nalternative transmission technologies were not selected.91  Finally, if Interim Standard \nInterconnection Service or FILLI Interconnection Service is requested, the Facilities Study will \naddress such request.       \n2. \nPG&E Proposes a Cluster Study Process for Electrically Dependent \nLarge Loads \nSection 10A.5 proposes a Cluster Study Process for Electrically Dependent Large Loads, \nunder which PG&E will batch the Electrically Dependent Large Load requests submitted by \nTCLLs into a single Cluster Study conducted annually.92  PG&E will accept applications on a \nrolling basis throughout the year, but Electrically Dependent Large Loads will be studied \ntogether as a cluster annually.93  All applications of Electrically Dependent Large Loads and Co-\nLocated Large Load End Users required to participate in the Cluster Study Process with \ncompleted applications by the last day of February each year will be included in that year’s \nCluster Study Process, which will begin April 1st of each year.  To the extent these proposed \ntariff modifications are approved by the requested effective date and completed applications are \nreceived by the end of February 2027, there will be a Cluster Study Process for Large Load End \nUsers in 2027.  Otherwise, the first Cluster Study Process for Large Load End Users under this \nproposed tariff will be in 2028.     \nThe Cluster Study will have two phases.  In Phase 1 (utilizing the initial study deposit), \nPG&E will evaluate all projects in the cluster using a steady state power flow and short circuit \nanalysis.94  Phase 1 will produce a list of the Direct Assignment Facilities, TCLL Interconnection \nNetwork Upgrades, and TCLL FILLI Facilities, if applicable, preliminarily identified as \nrequired, along with their estimated costs and each applicant’s share of cost responsibility.95  \nPG&E will use reasonable efforts to complete this study within one hundred twenty (120) \nBusiness Days after the annual commencement of the Phase 1 Study.  Within twenty (20) \nBusiness Days after providing the final Phase 1 study report, PG&E will hold a results meeting \nwith each TCLL, the CAISO, and any Affected System Operators, if applicable, to review the \nresults, after which the TCLL may withdraw its application or proceed to Phase 2.96   \nIf the TCLL decides to proceed to Phase 2, it must enter a second Cluster Study Process \nAgreement, wherein it commits to provide an additional refundable security equal to 15 percent \nof the Phase 1 Study’s estimated costs of the Direct Assignment Facilities and TCLL \nInterconnection Network Upgrades.97  The security will be used to pay for actual costs incurred \n \n91 Id. at PP 60-61; Nedrud Testimony at 16, 23-24. \n92 Nedrud Testimony at 20. \n93 Id. \n94 Id. at 21. \n95 Id.  \n96 TO Tariff, Proposed § 10A.5.5.2. \n97 Nedrud Testimony at 22-23; TO Tariff, Proposed § 10A.5.3."},{"page":19,"startToken":8448,"endToken":9036,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 19 \n \n \nby PG&E to perform and administer the Phase 2 Study.  In addition, the security may be used by \nPG&E for engineering, design, and procurement, together with applicable labor, materials, \ncontractor charges, and overhead, including applicable ITCC, for the Direct Assignment \nFacilities and TCLL Interconnection Network Upgrades identified in the Phase 1 Study.  This \nserves two purposes: (1) it further prevents speculative large load interconnection requests and \nprovides ever-increasing financial commitments from large load in accordance with the OSC, \nand (2) it allows PG&E to begin capital procurement for long lead time materials and \npreliminary engineering work on required upgrades.  The deposit will be refundable,98 less the \nactual costs incurred, including for capital procurement and engineering, and can be made in the \nform of cash or security as set forth in proposed Section 10A.5.5.3 of the Tariff.   \nThe Phase 2 Study will (i) update, as necessary, analyses performed in the Phase 1 Study \nto account for the withdrawal of requests after the Phase 1 Study process, (ii) identify Direct \nAssignment Facilities, TCLL Interconnection Network Upgrades, and TCLL FILLI Facilities, \n(iii) assign cost responsibility for Direct Assignment Facilities, TCLL Interconnection Network \nUpgrades, and TCLL FILLI Facilities needed for the TCLL’s interconnection request, (iv) \nallocate estimated cost responsibility for financing the identified TCLL Interconnection Network \nUpgrades, (v) identify for each TCLL Interconnection request a final Point of Withdrawal, and \n(vi) preliminarily identify any TCLL Reliability Network Upgrades.  Phase 2 also includes a \ntransient stability study and as needed, a voltage stability analysis, which are more detailed \nanalyses that are most useful once the cluster has been narrowed to the requests moving forward \nunder Phase 2.99  Within twenty (20) Business Days of receipt of the final Cluster Study report, \nthe TCLL, Participating TO, the CAISO, and any Affected System Operators, if applicable, and \nthe Interconnection Customer, shall hold a results meeting to discuss the results.  Within twenty-\nfive (25) Business Days of receipt of the completed Phase 2 Study, the TCLL must request the \nTCLL Agreement, the Facilities Agreement, the Cost Assurance Agreement, and if applicable, \nthe Interim Service Agreement or withdraw its application.  The parties have thirty (30) Business \nDays to negotiate and execute the various required interconnection agreements.     \nGiven the interrelated nature of these projects and how they can affect each other’s \nnecessary facilities and upgrades, they need to be studied together.  As indicated above, studying \nseveral interrelated projects together takes additional time.  The Participating TO will use \nreasonable efforts to complete each phase of the Cluster Study within one hundred twenty (120) \nBusiness Days, and the entire process, including the meetings to review results, is expected to \ntake a little over a year.100  Although the Cluster Study process will take longer than a single \nserial study, it is more efficient and accurate than studying the same interdependent requests one \nat a time (within 90 days each) because they would have to be continually restudied for \nwithdrawals and rescoping from other dependent interconnections.  The proposed cluster \n \n98 PG&E proposes to provide refunds with interest at the rate on commercial paper (A2/P2 nonfinancial) \nas found in “The Fed-Commercial Paper Rates and Outstanding Summary,” or its successor publication.  \nAs detailed below, PG&E is not likely able to earn interest at the current FERC interest rate, and instead, \nproposes to provide interest on refunds at the more attainable commercial paper rate.   \n99 Nedrud Testimony at 23-24. \n100 Nedrud Testimony at 26-28."},{"page":20,"startToken":9036,"endToken":9406,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 20 \n \n \napproach thus aligns with the OSC’s 60-90 day timeline where that timeline is achievable, for the \nElectrically Independent Large Loads, while adopting the most expeditious and practical process \nfor Electrically Dependent Large Loads.101  \n3. \nPG&E’s Load Interconnection Studies are Coordinated with the \nCAISO’s Concurrence and TPP Processes. \nGenerally, the Participating TOs are responsible for studying load interconnections, and \nthe CAISO is responsible for studying generation interconnections.  The results of PG&E’s load \ninterconnection studies, however, feed directly into the CAISO’s planning processes.  PG&E \nsubmits its load interconnection study results to the CAISO, which reviews the identified \nnetwork upgrades in its concurrence process.  In addition, the Load identified in PG&E’s \ninterconnection studies, together with other load growth, is considered in the TPP and can trigger \nTCLL Reliability Network Upgrades.102   \nV. \nPG&E PROPOSES A SET OF PRO FORMA AGREEMENTS TO MEET THE \nVARIOUS REQUIREMENTS OF THE OSC \nA. \nPG&E Proposes a Just and Reasonable Set of Agreements to Address \nthe Various Requirements of the OSC. \nTo address the general operational requirements in the OSC, PG&E proposes to include \nin its TO Tariff, as Appendix XI, a pro forma Agreement to Interconnect Transmission Customer \nfor Large Load (the “TCLL Agreement”).  The pro forma TCLL Agreement also includes \nseparate attachments that address other aspects of the OSC requirements.  Those include the \nFacilities Agreement (Attachment A to Appendix XI), the Cost Assurance Agreement \n(Attachment B to Appendix XI), and the optional Interim Service Agreement (Attachment C to \nAppendix XI) (collectively, the “Associated Agreements”).103  Each of those agreements will be \ndiscussed in more detail below. \nThe TCLL and Associated Agreements will be executed after the study process is \ncomplete and after the facilities needed for Standard Interconnection Service have been \nidentified and, optionally, the facilities needed for FILLI Service and Interim Standard \nInterconnection Service.104 \n \n101 Id. at 27. \n102 Virani Testimony at 4-5; Nedrud Testimony at 10-11. \n103 TO Tariff, Proposed § 10A and Appendix XI, including the TCLL Agreement, TCLL Facilities \nAgreement, Cost Assurance Agreement, and Interim Service Agreement. \n104 The optional Interim Interconnection Service is discussed in more detail below in Section.V.C.5."},{"page":21,"startToken":9406,"endToken":9865,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 21 \n \n \nB. \nPG&E Proposes to Address the Operational and General Pro Forma \nRequirements of the OSC Through use of the TCLL Agreement. \nThe OSC preliminarily found that the CAISO Tariff and/or the TO Tariffs appear to be \nunjust and unreasonable because they lack pro forma provisions in a transmission service \nagreement, or other applicable agreement, between the CAISO and/or the Participating \nTransmission Owner and the transmission customer taking transmission service on behalf of a \nlarge load.  Those provisions would memorialize the ongoing operational requirements that \napply to such service, such as equipment requirements, data requirements, and remote disconnect \ncapability.105  The Commission explained that, without such provisions, the CAISO may be \nunable to enforce those requirements against transmission customers taking transmission service \non behalf of large loads.106  The Commission therefore directed the CAISO and/or the \nParticipating TO to propose a pro forma agreement that memorializes the ongoing operational \nrequirements in a transmission service agreement between the CAISO and/or the Participating \nTO and the transmission customer taking transmission service on behalf of large loads.107  \nNotably, the OSC did not require a single form of agreement.  Instead, it expressly permitted \nthose requirements to be memorialized in a transmission service agreement “or other applicable \nagreement.”108 \nTo address these general requirements for interconnection service, PG&E proposes a new \npro forma TCLL Agreement.  The TCLL Agreement is a pro forma service agreement that sets \nout the terms and conditions PG&E will use to ensure that a TCLL meets the requirements that \napply to the requested interconnection service.   \nParties.  The parties to the TCLL Agreement will be (i) PG&E, acting as a Participating \nTO; and (ii) the TCLL.  While the OSC suggests that the pro forma agreement can be between \nthe CAISO or the Participating TO and the Eligible Customer, PG&E is the appropriate \ncounterparty because it provides wholesale interconnection service to the TCLL.   \nTerm and Termination.  PG&E proposes that the TCLL Agreement become effective \non the later of the Commission’s acceptance of the agreement and the related Facilities \nAgreement, Cost Assurance Agreement, and Interim Service Agreement, if any, and remain in \neffect until terminated by mutual agreement, for default, or on sixty (60) days’ notice from the \nTCLL, subject to any required FERC acceptance of a notice of cancellation.  Termination may \nresult in the payment of an exit fee under the Cost Assurance Agreement.  \nInterconnection and Facilities.  The TCLL Agreement reflects the commitment of the \nTCLL and Participating TO to interconnect and the terms and conditions relating to actual \nphysical interconnection will reside in the Facilities Agreement.  Likewise, if Interim Standard \n \n105 OSC at P 64. \n106 Id. \n107 Id. \n108 Id."},{"page":22,"startToken":9865,"endToken":10378,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 22 \n \n \nInterconnection Service and/or FILLI Interconnection Service is to be provided, the TCLL \nAgreement indicates that the Interim Service Agreement will include the relevant terms and \nconditions. \nRisk Allocation and General Terms.  The agreement also includes several terms and \nconditions found in most pro forma agreements.  Those terms include:  (1) Indemnity: a mutual \nindemnity, with exceptions for the indemnified party’s gross negligence or intentional \nwrongdoing; (2) Damages waiver: a broad waiver of consequential, indirect, and similar \ndamages; (3) Default: a material breach is a default, and the other party may terminate after \nwritten notice and a cure period of at least 60 days; (4) Confidentiality: confidentiality \nobligations last for the term plus three years, with carve-outs for disclosures to FERC and state \nregulators; (5) Assignment: assignment requires consent, which cannot be unreasonably \nwithheld, with certain exceptions; (6) Disputes and governing law: disputes are resolved under \nSection 13 of the TO Tariff, and California law governs; (7) Order of priority: the TO Tariff \nprevails over the TCLL agreement, and the TCLL Agreement prevails over the CAISO Tariff; \nand (8) Unilateral FERC filings: PG&E may make unilateral filings with FERC under section \n205 of the Federal Power Act, and the TCLL may do so under section 206. \nC. \nPG&E Proposes to Address the Cost Assurance Requirements of the \nOSC With Pro Forma Cost Recovery Agreements – the Facilities \nAgreement and the TCLL Cost Assurance Agreement. \nThe OSC preliminarily finds that the TO Tariffs appear to be unjust and unreasonable \nbecause they lack adequate mechanisms to mitigate the risk of cost shifting among transmission \ncustomers.109  The OSC identifies three elements that a just and reasonable cost recovery \nframework for large load service should include: (1) a cost recovery agreement requiring a \nminimum contribution toward the transmission owner’s transmission revenue requirement, based \non the level of transmission service requested on behalf of the large load; (2) credit support or \nother financial security sufficient to secure the Eligible Customer’s payment obligations; and \n(3) appropriate crediting of any such payments toward the transmission owner’s transmission \nrevenue requirement.  PG&E’s proposal satisfies each of these requirements and, in several \nrespects, provides additional protection against cost shifting by matching the cost recovery \nmechanism to the type of facility needed to serve the Large Load End User. \nAs explained below, PG&E proposes to address cost responsibility based on the type of \nfacilities required to provide Standard Interconnection Service to a TCLL and to ensure recovery \nof those costs and to prevent cost shifting through the Facilities Agreement and the TCLL Cost \nAssurance Agreement.  Section V.C.1 describes this facility-based approach, under which the \ncost recovery mechanism and cost assurance requirements of Direct Assignment Facilities, \nTCLL FILLI Facilities, TCLL Interconnection Network Upgrades, and TCLL Reliability \nNetwork Upgrades are set forth for each type of facility.  Section V.C.2 describes how the \nFacilities Agreement memorializes the determination, funding, and recovery of the costs for \nDirect Assignment, TCLL FILLI Facilities and TCLL Interconnection Network Upgrades.  \n \n109 OSC at P 76."},{"page":23,"startToken":10378,"endToken":10885,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 23 \n \n \nFinally, Section V.C.3 describes the Cost Assurance Agreement, which addresses cost recovery \nfor TCLL Reliability Network Upgrades by establishing a Minimum Annual Revenue Obligation \ntied to the requested interconnection capacity, an annual reconciliation process, and a financial \nsecurity requirement securing that obligation, consistent with the cost recovery agreement \ncontemplated by the OSC.110 \n1. \nPG&E Proposes to Allocate and Secure Costs Based on the Relevant \nFacilities to Ensure that TCLLs and Large Load End Users Pay Their \nFair Share of the Costs of Facilities Necessary to Interconnect Large \nLoad End Users to the Transmission System. \nThe TO Tariff and related TCLL Agreement identify four different types of facilities: (1) \nDirect Assignment Facilities; (2) TCLL FILLI Facilities; (3) TCLL Interconnection Network \nUpgrades; and (4) TCLL Reliability Network Upgrades.111  Costs will be recovered and cost \nassurance requirements established based on the unique nature of each facility type as discussed \nin more detail below.     \nImportantly, PG&E’s cost recovery proposal must be considered on a holistic basis.  The \nproposal is not a collection of independent cost allocation rules.  Rather, it is intended to be an \nintegrated framework designed to ensure that TCLLs and Large Load End Users bear the costs of \nthe facilities needed to serve them, which often involve this array of facilities, while protecting \nPG&E’s other transmission customers from cost shifts.  A summary of the cost responsibility for \neach type of facility is provided below with a detailed explanation in the following sections that \nexplains the mechanics of how each cost recovery mechanism will work in the relevant sections \nof each of the pro forma agreements. \nDirect Assignment Facilities and TCLL FILLI Facilities.  Direct Assignment \nFacilities are defined as facilities owned by the Participating TO necessary to physically and \nelectrically interconnect a particular party requesting interconnection.  TCLL FILLI Facilities are \ndefined as facilities identified through the Section 10A study process that are required to provide \nservice under the Interim Service Agreement that will be owned by the Participating TO or \nTCLL.  Both Direct Assignment and TCLL FILLI Facilities are developed for the sole use and \nbenefit of the TCLL requesting service under Section 10A of the TO Tariff.112  Accordingly, \nPG&E proposes to directly assign costs for Direct Assignment Facilities and TCLL FILLI \n \n110 OSC at P 125; TO Tariff, Proposed § 10A and Appendix XI, Attachment A (Facilities Agreement) and \nAttachment B (Cost Assurance Agreement). \n111 Under the proposed Electric Rule 30, tariff provisions will apply to our types of transmission facilities \nneeding infrastructure upgrades: Type 1 (Transmission Service Facilities), Type 2 (Transmission \nInterconnection Upgrades), Type 3 (Transmission Interconnection Network Upgrades), and Type 4 \n(Transmission Network Upgrades). \n112 Nedrud Testimony at 20-21.  See also Green Development, LLC v. FERC, 77 F.4th 997, 1006-07 (D.C. \nCir. 2023) (upholding FERC’s interpretation of direct assignment facilities as facilities constructed for the \nsole benefit of a particular customer and explaining that direct assignment protects network users from \nsubsidizing facilities that benefit a single user)."},{"page":24,"startToken":10885,"endToken":11440,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 24 \n \n \nFacilities to the TCLL.  Direct assignment is consistent with the principles of cost causation \nbecause it ensures that the costs are allocated to those who caused and fully benefit from the \nproposed facilities.113  The direct assignment of such facilities is also consistent with the \nCommission’s policy for direct assignment of interconnection facilities in other contexts.114   \nTCLL Interconnection Network Upgrades.  TCLL Interconnection Network Upgrades \nare additional facilities needed to expand the transmission system from the ISO Controlled Grid \nto the point of interconnection of the TCLL. These facilities will be identified in the Facilities \nAgreement and are network upgrades caused by the interconnection of the Large Load End Users \nfor which the TCLL seeks interconnection service.115  TCLL Interconnection Network Upgrades \nare subject to the CAISO’s concurrence review process for transmission planning purposes as \ndiscussed above.116  Under Attachment A, the TCLL pays the costs of the TCLL Interconnection \nNetwork Upgrades upfront before Interconnection Service begins, but the costs can be refunded \nas set forth in the Facilities Agreement described below.  \nThe OSC finds that the TO Tariff may be unjust and unreasonable because it fails to \nprevent unjust and unreasonable costs shifts among transmission customers.117  By requiring the \nTCLL to fund the costs of the TCLL Interconnection Network Upgrades upfront, PG&E ensures \nthat the TCLL and the Large Load End User for which the TCLL is taking service, pays the full \ncost of those upgrades before service commences and protects other transmission customers if \nthe Large Load End User does not materialize or does not materialize as intended.   \n \n113  Green Development, 77 F.4th at 1006-07 ; Exxon Mobil Corp v. FERC, 517 F.3d 1208, 1213 (D.C. \nCir. 2009) (holding that entities bear the full cost of interconnection facilities that solely benefit them); \nOld Dominion Elec. Co-op, Inc. v. FERC, 518 F.3d 43, 50-51 (D.C. Cir. 2008) (upholding FERC's \ndetermination that generation interconnection customers were responsible for 100% of the costs of  \nupgrades to accommodate interconnection requests that would not have been built but for their \ninterconnection request, and denying recovery of those costs through transmission revenue).  \n114 The cost causation principle requires costs to be allocated to those who cause the costs to be incurred \nand reap the resulting benefits.  See S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 87 (D.C. Cir. 2014) \n(explaining that rates must reflect to some degree the costs actually caused by the customer who must pay \nthem) (citing Nat’l Ass’n of Regul. Util. Com’nrs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007)); \nMidwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368-69 (D.C. Cir. 2004) (evaluating cost \ncausation by comparing the costs assessed against a party to the burdens imposed or benefits drawn by \nthat party); Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 476-477 (7th Cir. 2009) (explaining that costs \nmay not be allocated to parties receiving no benefits or benefits trivial in relation to the costs). \n115 TCLL Interconnection Network Upgrades generally will be consistent with Facility Type 2 and 3, as \nproposed in PG&E’s Electric Rule 30 Application (A.24-11-007), filed before the California Public \nUtilities Commission. \n116 Nedrud Testimony at 10-11, 32.  \n117 OSC at P 80."},{"page":25,"startToken":11440,"endToken":11932,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 25 \n \n \nHowever, because the facilities are network upgrades, they benefit all transmission \ncustomers118 and thus, it is consistent with Commission policy to ensure that the costs are \nultimately rolled into network rates, subject to the Large Load End User paying their appropriate \nshare through transmission rates.119  As such, PG&E proposes to make these upfront TCLL \nInterconnection Network Upgrade costs eligible for refunds based on realized transmission \nrevenues, and disbursed annually at a rate equal to 75% of realized wholesale Transmission \nrevenues until the cost is fully refunded.   \nThis approach of upfront funding with refunds will ensure that the TCLL or Large Load \nEnd User fully pays for the costs of the facilities as they are being constructed.  If the Large Load \nEnd User does not materialize, the TCLL or Large Load End User bears the costs.  If the Large \nLoad End User materializes, but is smaller in size than expected, the refund amount will be \nreduced, such that the TCLL or Large Load End User may never recoup its full costs or may take \nlonger to earn a full refund. \nMoreover, PG&E proposes to refund only seventy-five (75) percent of the realized \nwholesale transmission revenues on an annual basis in conformance with the recently passed \nlegislation in California, SB 886 (known as the California Technology Innovation and Ratepayer \nProtection Act), signed into law on September 21, 2026.120  SB 886 provides that any refund \nmade by a utility to a large load customer cannot exceed seventy-five percent of the annual net \ntransmission revenue requirement that the utility receives from the large load customer.121   This \nis also consistent with several recent CPUC orders approving similar arrangements between \nPG&E and large load customers at the retail level.  As the CPUC explains, the twenty-five \npercent of funds not refunded annually are intended to account for costs that are not part of the \nproject’s direct energization such as ongoing maintenance costs and broad grid upgrades.122 \nTCLL Reliability Network Upgrades.  TCLL Reliability Network Upgrades are \nNetwork Upgrades planned through the CAISO TPP or similar processes and identified as \nnecessary for the provision of Standard Interconnection Service to the TCLL and other load \n \n118 See e.g., Exxon Mobil, F.3d at 1213 (discussing Network Upgrades as those upgrades funded upfront \nby customer and later refunded); Entergy Servs., Inc. v. FERC, 319 F.3d 536, 539 (D.C. Cir. 2003) \n(upholding FERC’s policy to provide credits for network upgrades that benefit all users on the grid). \n119 See also, Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025).  \n120 S.B. 886, 2025–2026 Reg. Sess. (Cal. 2026) (California Technology Innovation and Ratepayer \nProtection Act)). \n121 Id. \n122 Resolution E-5439 at 17 (Jan. 15, 2026) (directing refund of 75 percent of PG&E’s net annual revenue \nplus ITCC adjustment); Resolution E-5420 at 18 (same) Resolution E-5420 at 18 (same); Resolution E-\n5433 (same)."},{"page":26,"startToken":11932,"endToken":12282,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 26 \n \n \ninterconnections.123  Importantly, unlike TCLL Interconnection Network Upgrades, the TCLL \nReliability Network Upgrades are facilities that are identified as necessary by the CAISO to \naddress Load growth or other reliability driven requirements on the CAISO system, while also \nbeing necessary to reliably provide transmission service to the TCLL.124   \nAccordingly, consistent with the OSC requirements, PG&E proposes to require a \nMinimum Annual Revenue Obligation backed by security requirements from the TCLL or Large \nLoad End User to ensure that the TCLL or the Large Load End User pays their fair share of the \ncosts of the TCLL Reliability Network Upgrades.  PG&E’s approach preserves the CAISO’s \nintegrated planning and cost-of-service framework while satisfying the OSC’s requirement for a \nminimum contribution and appropriate credit support.125  The OSC specifically finds that “in \norder to prevent unjust and unreasonable cost shifting among transmission customers it appears \nnecessary” for the relevant parties to “enter into a cost recovery agreement that requires the \n[TCLL] to make a minimum contribution toward the transmission owner’s revenue \nrequirement.”126  The Minimum Annual Revenue Obligation does exactly that by requiring the \nTCLL, or Large Load End User if the TCLL is PG&E, to pay its minimum revenue requirement \nbased on requested maximum load and backed by security to prevent unjust and unreasonable \ncost shifting.  As described in more detail below, PG&E also proposes to require an Exit Fee to \ncover the costs of TCLL Reliability Network Upgrades should the TCLL/Large Load End User \nprematurely leave.   \n \n123 TCLL Reliability Network Upgrades will generally be consistent with Facility Type 4, as used in \nPG&E’s Electric Rule 30 application. \n124 In the event a TCLL Reliability Network Upgrade is identified as being attributable to an individual \nLarge Load End User, the TCLL/Large Load End User may be responsible for costs associated with that \nTCLL Reliability Network Upgrade under the framework provided for TCLL Interconnection Network \nUpgrades. \n125 OSC at PP 79–82; PG&E Large Load Comments at 12–13. \n126 OSC at P 80."},{"page":27,"startToken":12282,"endToken":12734,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 27 \n \n \n2. \nThe Facilities Agreement Provides a Just and Reasonable Solution for \nProtecting Customers Against Cost Shifts for the Direct Assignment \nFacilities, TCLL FILLI Facilities, and TCLL Interconnection \nNetwork Upgrades. \na. \nThe terms and conditions of the Facilities Agreement are just \nand reasonable. \nAs summarized above, PG&E proposes to include as Attachment A to the TCLL \nAgreement, a Facilities Agreement to govern the costs of the Direct Assignment Facilities, \nTCLL FILLI Facilities, and the TCLL Interconnection Network Upgrades (collectively, the \n“Attachment A Facilities”).  The parties to the Facilities Agreement will include PG&E, as the \nParticipating TO, and the TCLL.  If PG&E is also the TCLL, the Large Load End User will also \nexecute the agreement.   \nSection 2 of the Facilities Agreement identifies required Direct Assignment Facilities, \nTCLL Interconnection Network Upgrades, TCLL FILLI Facilities, and TCLL Reliability \nNetwork Upgrades.  It also makes clear that the TCLL Reliability Network Upgrades have only \nbeen identified on a preliminary basis and the final TCLL Reliability Network Upgrades that \nmust be completed before Standard Interconnection Service may begin will be identified at a \nlater date, subject to the review and agreement of the CAISO.   \nSection 3 requires each Large Load End User to have the facilities to provide continuous \ndynamic disturbance recording data and storage on the high-side of the main power transformer \nor common point of connection, as required by the CAISO.  It also requires the facilities to allow \nPG&E to disconnect or isolate the Large Load End User during a contingency to maintain \nsystem reliability. \nSection 4 identifies, by reference to the single-line diagram, the PG&E-owned Point of \nWithdrawal and the Points of Change of Ownership between the parties.   \nSection 5 addresses the design, engineering, and construction of the TCLL Facilities \nexcluding the TCLL Reliability Network Upgrades and provides that certain Attachment A \nFacilities may be constructed by the TCLL, with the consent of the Participating TO.  This \nsection also includes the general obligations of the parties regarding the development of the \nAttachment A Facilities.   \nSection 6 provides the cost estimates to construct the Direct Assignment Facilities, TCLL \nInterconnection Network Upgrades, and TCLL FILLI Facilities.   \nSection 7 details how the Attachment A Facility costs will be allocated.  Costs for all of \nAttachment A Facilities will be paid for initially by the TCLL/Large Load End User prior to \nconstruction.  If the TCLL constructs the Direct Assignment or TCLL FILLI Facility, the \nagreement makes clear that the facility itself shall constitute the upfront, directly-assigned \npayment and requires the TCLL to transfer the facility to the Participating TO prior to \nenergization.  If the TCLL does not construct the facilities, the Facilities Agreement provides"},{"page":28,"startToken":12734,"endToken":13362,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 28 \n \n \nthat the upfront payment responsibility will be based on the estimated costs of the facilities, \nsubject to true up and reconciliation, and paid consistent with the payment schedule set forth in \nthe agreement.127  Section 7.3 states that the TCLL/Large Load End User must pay PG&E for the \nincome tax component of contributions (“ITCC”) in connection with the transactions made under \nthe agreement.  Section 7.6 sets forth how the cost of ownership charge for the Participating TO-\nowned Direct Assignment Facilities will be calculated.  The cost of ownership charge will \nreimburse PG&E for the ongoing costs of owning and operating the PG&E-owned Direct \nAssignment Facilities.   \nSection 8 details how billing will be performed under the agreement.  Section 9 describes \nthe refund methodology for the TCLL Interconnection Network Upgrades.  As discussed above, \nPG&E will refund to the TCLL/Large Load End User, a portion of the upfront payment on an \nannual basis, including ITCC, made by the TCLL/Large Load End User for the TCLL \nInterconnection Network Upgrades.  Refunds shall commence once the Large Load End User \ncommences retail service.  Refunds will be paid annually and will equal 75% multiplied by the \namount of MWh counted as Gross Load of the TCLL associated with withdrawals by the Large \nLoad End User multiplied by the Regional Access Charge or by the Regional Access Charge \nplus the Local Access Charge, as applicable.  In order to receive this refund, the TCLL/Large \nLoad End User must inform PG&E of its Gross Load withdrawn as measured by the CAISO \nrevenue meter.  The refunds will be paid over a period of fifteen years and may not necessarily \nequal the full costs of the upfront payments depending on the cost of the upgrades and the \namount of service taken by the TCLL/Large Load End User.  Termination of this agreement \nprior to fifteen years from the date refunds commence will result in the end of further refunds as \nof the date of termination and the unrefunded amount of the upfront payment will serve as an \nexit fee for prematurely ending service. \nAs set forth in Section 9, PG&E intends to pay interest on the refunds of the upfront \npayments made for the TCLL Interconnection Network Upgrades. However, rather than use the \ntraditional interest rate established by the Commission under Section 35.19a, PG&E proposes to \nuse the interest rate on commercial paper (A2/P2 nonfinancial) as found in “The Commercial \nPaper Rates and Outstanding Summary,” or its successor publication.128  Once PG&E collects \nthe upfront payment for the TCLL Interconnection Network Upgrades, the payments collected \nwill be used to pay for the cost of constructing those upgrades.  PG&E believes that because \nthose upgrades will be network upgrades it is appropriate to provide refunds to the TCLL or \nLarge Load End User for those facilities over time.  However, requiring PG&E to pay high \ninterest rates will unnecessarily shift costs on to other PG&E transmission customers.  PG&E \ncannot obtain a rate equivalent to the Commission’s interest rate set out in Section 35.19a from a \nbank or escrow account for such deposits.  Thus, even if PG&E were to place the funds collected \n \n127 The Phase 2 Security payment discussed above (equal to 15 percent of the estimated costs of the Direct \nAssignment Facilities and TCLL Interconnection Network Upgrades), less the actual incurred costs to \nconduct the Phase 2 Study, may be utilized to satisfy this upfront cost payment responsibility in whole or \nin part by written agreement of the parties. \n128 Board of Governors of the Federal Reserve System, Commercial Paper Rates and Outstanding \nSummary, https://www.federalreserve.gov/releases/cp/."},{"page":29,"startToken":13362,"endToken":13867,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 29 \n \n \nfrom the TCLL or Large Load End User in an interest-bearing account that aligns with the \nannual refund obligation, the interest earned is likely to be lower than the interest it would need \nto pay on refunds to the Large Load End User based on Section 35.19a.  The costs of paying a \nhigher interest rate on those funds would be shifted to other transmission customers.  This is \ndirectly contrary to the Commission’s goals in the OSC of preventing cost shifts.129  Moreover, \nthe Commission has accepted use of interest rates other than the rates used in Section 35.19a in \nsimilar situations.130  Accordingly, to the extent necessary, PG&E seeks a waiver of Section \n35.19a to allow it to charge a rate other than the prescribed interest rate in Section 35.19a. \nSection 10 makes the TCLL/Large Load End User responsible, if the agreement is \nterminated before energization, for PG&E’s unreimbursed design, engineering, and construction \ncosts and for its necessary and reasonable termination costs, including safety, system-integrity, \nand unavoidable contract cancellation costs.  Both Parties must use commercially reasonable \nefforts to mitigate those costs.  Again, this ensures that the TCLL and, in turn, the Large Load \nEnd User will pay their fair share of the costs, consistent with the requirements of the OSC. \nSection 11 sets forth how TCLL Reliability Network Upgrades will be funded.  As noted \nabove, the costs of these network upgrades are recovered in accordance with the CAISO Tariff \nprovisions governing the funding of integrated transmission projects, and cost recovery is \nassured through the Cost Assurance Agreement.  The TCLL/Large Load End User cost assurance \nresponsibilities for these types of facilities are covered in Attachment B to the pro forma \ndiscussed below.  Section 12 includes accounting and audit provisions providing the right for \nboth parties to conduct audits under conditions set forth in the agreement. \nSection 13 governs the commencement of Standard Interconnection Service.  The \nParticipating TO and TCLL shall exchange a notice in the form of Attachment B memorializing \ntheir mutual agreement that the Attachment A Facilities and the TCLL Reliability Network \nUpgrades have been completed and tested.  If another transmission owner or transmission \nprovider must first complete transmission facilities, the parties will also confirm that work is \ncompleted and tested.  Section 14 provides the Large Load End User obligations and rights, \nincluding the requirement to finance the TCLL Facilities as specified under the Facilities \nAgreement.   \nThe remaining provisions include the following standard contract terms and conditions \ntypically found in pro forma FERC interconnection and transmission service agreements:  \nSection 15 (Indemnification and Liability); Section 16 (Default); Section 17 (Confidential \nInformation); Section 18 (Assignment); and Section 19 (Miscellaneous Provisions).   \n \n129 OSC at P 65. \n130 See e.g., BJ Energy, LLC Franklin Power, LLC Gle Trading, LLC Ocean Power, LLC & Pillar Fund, \nLLC, 129 FERC ¶ 61, 265 (Dec. 22, 2009) (finding PJM not required to pay interest rate under section \n35.19a for funds used as financial security)."},{"page":30,"startToken":13867,"endToken":14412,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 30 \n \n \nb. \nPGE’s proposal to include the Large Load End User as a \nsignatory to the Facilities Agreement when PG&E is the TCLL \nis just and reasonable. \nPG&E proposes to include the Large Load End Users as a party to the pro forma \nFacilities Agreement when PG&E is the TCLL.  This will be an administratively efficient \nmechanism to ensure that Large Load End User pays for the costs of the facilities and does not \nresult in those costs being shifted to other PG&E customers if the Large Load End User does not \nmaterialize as anticipated.  In those instances when PG&E is a TCLL, if the Large Load End \nUser was not also a signatory to the agreement and given cost responsibility for the relevant \nfacilities, PG&E would be required to enter into an agreement with itself to secure payments for \nfacilities needed to provide transmission interconnection service to that Large Load End User.  If \nthat Large Load End User does not materialize, PG&E would have no means to ensure payment \nby that Large Load End User under the agreement.  This could result in costs being shifted to \nother PG&E transmission customers.  Accordingly, to prevent that cost shifting and to avoid \nneeding to enter into multiple complicated agreements, PG&E proposes to require the Large \nLoad End User to execute the Facilities Agreement when PG&E is the TCLL.    \nThe pro forma Facilities Agreement, including the Large Load End User’s obligations \nunder it, is within the Commission’s jurisdiction to approve.  The Commission has jurisdiction \nover the terms and conditions of transmission service.131  The Facilities Agreement is an \nagreement covering cost assurance for transmission facilities needed to ensure Large Load End \nUsers can safely and reliably connect to the transmission system.  Accordingly, because it is a \nservice agreement addressing the terms and conditions for transmission-related service, it is \nwithin the Commission’s jurisdiction to approve and the Commission has approved similar \ntransmission security agreements that include end use customers as signatories.132  While the \nCommission has rejected proposals that include payment and other requirements for retail \ncustomers, those obligations were retail energy service obligations, not transmission service \nobligations.133  Here, PG&E seeks to ensure that other PG&E transmission customers are \nprotected if the Large Load End User does not materialize as anticipated pursuant to the Large \nLoad End User’s transmission service obligations.     \n \n131 16 U.S.C. § 824(b); New York v. FERC, 535 U.S. 1, 16-24 (2002) (“That text unquestionably supports \nFERC’s jurisdiction to order unbundling of wholesale transactions (which none of the parties before us \nquestions), as well as to regulate the unbundled transmissions of electricity retailers.”).  \n132 See PECO Energy Co., 195 FERC ¶ 61,074 (2026) (order accepting transmission security agreement); \nCommonwealth Edison Co., 194 FERC ¶ 61,109 (2026) (order accepting transmission security \nagreement); Dayton Power & Light Co., 195 FERC ¶ 61,059 (2026) (order accepting construction service \nagreement); PECO Energy Co., 193 FERC ¶ 61,148 (2025) (order accepting transmission security \nagreement). \n133 PJM Interconnection, L.L.C., 197 FERC ¶ 61,109, P 81 (2026) (finding outside the Commission’s \njurisdiction provisions that require retail customers to curtail as part of a wholesale capacity market \nconstruct)."},{"page":31,"startToken":14412,"endToken":14971,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 31 \n \n \nMoreover, PG&E proposes to require the Large Load End User to sign when PG&E is \nthe TCLL for a combination of legal, efficiency, and transparency reasons.  A TCLL that is also \nthe Participating TO from whom the interconnection is sought is differently situated than a \n“third-party TCLL.”  PG&E has no legal right to seek payment for services from the retail \ncustomer of a third-party TCLL.  In contrast, where the PTO and TCLL are a single legal entity, \nthat one entity already has a legal relationship with, and transacts directly with, the Large Load \nEnd User.  In addition, requiring PG&E as a Participating TO to “collect” amounts from another \nbusiness unit (i.e., PG&E as the TCLL) before the bill can be sent to the Large Load End User \nwould be administratively inefficient, and as detailed above, could result in stranded costs if the \nLarge Load End User load does not materialize.   \n3. \nThe TCLL Cost Assurance Agreement Provides a Just and \nReasonable Solution for Protecting Customers Against Cost Shifts for \nTCLL Reliability Network Upgrades. \na. \nThe terms and conditions of the Cost Assurance Agreement \nare just and reasonable and protect against cost shifting. \nPG&E proposes to address the OSC’s concerns regarding cost shifting for TCLL \nReliability Network Upgrades through a Cost Assurance Agreement.  The Cost Assurance \nAgreement will be a pro forma agreement included as Attachment B to the TCLL Agreement \namong PG&E, in its capacity as Participating TO under its TO Tariff, the TCLL, and the Large \nLoad End User if PG&E is the TCLL.  If PG&E is not the TCLL, the agreement will be among \nPG&E and the TCLL and the TCLL will have the option of requiring the Large Load End User \nto execute the agreement.   \nConsistent with the requirements of the OSC, the Cost Assurance Agreement establishes \na Minimum Annual Revenue Obligation payable by the TCLL/Large Load End User and a \nFinancial Security requirement equal to five (5) times the Minimum Annual Revenue Obligation \nto secure that obligation.  The Cost Assurance Agreement also provides for an Exit Fee should \nthe Large Load End User prematurely leave and the agreement is terminated.   \nCalculation of Minimum Annual Revenue Obligation.  Section 3 of the Cost \nAssurance Agreement establishes and calculates a Minimum Annual Revenue Obligation that \nmust be collected from the TCLL or Large Load End User.  The Minimum Annual Revenue \nObligation is a minimum amount of revenue that must be collected from the TCLL or Large \nLoad End User each year to ensure that entity contributes sufficiently to the Gross Load in the \nCAISO BAA.  If the TCLL or Large Load End User does not meet the minimum obligation, a \nshort fall amount will be charged to the TCLL or Large Load End User as discussed below, that \nwill be flowed through PG&E’s revenue requirement.   \nThe Minimum Annual Revenue Obligation is based on the applicable RAC or LAC, as \napplicable, assessed on Gross Load.  RAC/LAC is the applicable CAISO charge to the TCLL for \ntransmission access that is assessed on the Gross Load of the Large Load End User, including \nany applicable components of that charge under the CAISO Tariff.  Each year the Minimum \nAnnual Revenue Obligation will be calculated using the following formula:"},{"page":32,"startToken":14971,"endToken":15491,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 32 \n \n \nMinimum Annual Revenue Obligation = Minimum Obligation \nCapacity (MW) × [hours in the year] × 80% × 75% × Regional \nAccess Charge (if connected to High Voltage facilities) or \nRegional Access Charge + PG&E’s Local Access Charge (if \nconnected to Low Voltage facilities) \nThe Minimum Obligation Capacity will be the expected maximum capacity during the \nrelevant annual period.  Section 3 includes a schedule that will reflect the Minimum Obligation \nCapacity during each year.  The Minimum Obligation Capacity will increase on specified dates \nset out in the Cost Assurance Agreement but should reach the Requested Interconnection \nCapacity no later than Year 5 under the schedule.  Section 3.1 defines “Requested \nInterconnection Capacity” as the ultimate peak demand, expressed in MW, specified by the \nTCLL on behalf of the Large Load End User in the application.  The agreement requires the \nParties to complete the minimum capacity schedule before executing the agreement.134 \nThe Minimum Annual Revenue Obligation is intended to ensure that a TCLL or Large \nLoad End User contributes toward revenues associated with the Gross Load in the CAISO BAA, \neven if load ramps more slowly than anticipated.  The use of realized transmission revenues for \nrefunds and annual reconciliation aligns the obligation with actual service and reduces the risk of \ncost shifting.  As noted above, the seventy-five (75) percent factor allows variation in Large \nLoad End User usage while preserving a substantial contribution toward the broader transmission \nsystem, consistent with PG&E’s CPUC-approved practice for end users.135 \nThe formula also appropriately uses an eighty (80) percent capacity factor.  Because the \nCAISO bills transmission service based on Energy withdrawals, a capacity factor is required to \nconvert the MWs of interconnection capacity to the anticipated annual Energy withdrawals of a \nLarge Load End User. While a typical End-Use Customer could have a capacity factor of 50% or \nlower, PG&E’s assumption here, reflects the fact that the utilization anticipated from Large \nLoads such as data centers is expected to be significantly higher.  A recent study of actual data \ncenter operation by E3 indicates that “[o]nly two data centers had load factors above 90% of \ntheir reported peak loads, and fewer than half had load factors above 80%.”136  As a result, \nPG&E proposes to convert the scheduled capacity into an annual Energy quantity for calculating \nthe Minimum Annual Revenue Obligation by assuming an 80% annual capacity factor.    \nAnnual Minimum Revenue Obligation Reconciliation Process.  After each calendar \nyear, PG&E will compare the Minimum Annual Revenue Obligation with the wholesale \n \n134 Section 1.1 defines “Requested Interconnection Capacity” as the ultimate peak demand, expressed in \nMW, specified on behalf of the Large Load End User in the application process in the TO Tariff. \n135 Resolution E-5439 at 17 (Jan. 15, 2026) (directing refund of 75 percent of PG&E’s net annual revenue \nplus ITCC adjustment); Resolution E-5420 at 18 Resolution E-5420 at 18 (same); Resolution E-5433 \n(same).  \n136 Energy and Environmental Economics, Forecasting Large Loads in the Age of AI and Data Centers \n(December 2025),  www.ethree.com/wp-\ncontent/uploads/2025/12/E3Whitepaper_DataCenterForecasting.pdf."},{"page":33,"startToken":15491,"endToken":16055,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 33 \n \n \ntransmission revenue associated with the Gross Load of the Large Load End User, as measured \nby the CAISO revenue meter (“Annual LL Gross Load Revenue”).  The Annual LL Gross Load \nRevenue will be calculated by the TCLL/Large Load End User providing PG&E the Gross Load \nof the Large Load End User and multiplying that amount by the Regional Access Charge only, or \nthe Regional Access Charge plus Local Access Charge, as appropriate.  If the Annual LL Gross \nLoad Revenue is less than the Minimum Annual Revenue Obligation, PG&E will invoice the \nTCLL or Large Load End User for the difference (“MARO Shortfall”).  And the difference must \nbe paid in thirty (30) calendar days.  This will ensure that the TCLL or Large Load End User \npays its fair share of its requested Load, including for relevant TCLL Reliability Network \nUpgrades that are necessary, in part, to bring the Large Load online and enable it to receive its \nrequired transmission service.   \nFailure to Pay the Shortfall.  If the Participating TO informs the TCLL of a MARO \nShortfall, the TCLL may recover such amount from its Large Load End User through retail rate \nmechanisms or may allow PG&E to draw on the Financial Security for any MARO Shortfall that \nremains unpaid more than sixty (60) days after its due date.  Within five (5) Business Days after \na draw, the Large Load End User/TCLL is required to restore the available Financial Security to \nthe required amount. \nFinancial Security Obligation.  Section 4 establishes the Financial Security obligations \nunder the Cost Assurance Agreement.  If PG&E is the TCLL, the Large Load End User will \nassume the Financial Security obligation.  If the TCLL is not PG&E, the TCLL will have the \noption to assume the Financial Security obligation or require the Large Load End User to assume \nthe Financial Security obligation, in which event the Large Load End User must be a Party to the \nCost Assurance Agreement.  Financial Security must be provided within thirty (30) Business \nDays of Construction Activities commencing on any TCLL Reliability Network Upgrade \nidentified as being required, in part, for Standard Interconnection Service under the Facilities \nAgreement.137   \nThe Cost Assurance Agreement requires that Financial Security be maintained for as long \nas the Minimum Annual Revenue Obligation remains in effect, including any period necessary to \nresolve and pay a final annual reconciliation.  The Financial Security requirement shall equal \nfive (5) years times the Minimum Annual Revenue Obligation calculated using the formula \ndiscussed above.  However, instead of the Minimum Obligation Capacity being used in \ndetermining the Financial Security amount, PG&E shall use the full Requested Interconnection \nCapacity.  \nAcceptable Financial Security for the TCLL/Large Load End User will be determined by \nthe Creditworthiness Procedures attached as Exhibit 1 to the Cost Assurance Agreement, which \nallows for a cash deposit,138 letter of credit, parent guaranty, or surety bond.  The TCLL/Large \n \n137 Construction Activities are defined as actions by any entity constructing the Reliability Network \nUpgrades that result in irrevocable financial commitments for the purchase of major electrical equipment \nor land. \n138 If the cash deposit is paid to PG&E, PG&E proposes to pay interest on refunds from when fully paid \nuntil refunded (the Financial Security is released) at the commercial paper rate for the reasons detailed"},{"page":34,"startToken":16055,"endToken":16540,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 34 \n \n \nEnder User shall maintain the form of Financial Security in the required amount without \ninterruption.  The Cost Assurance Agreement also allows that in each of the Years 12-15 of the \nCost Assurance Agreement, the TCLL/Large Load End User may reduce its Financial Security \nby one year’s Minimum Annual Revenue Obligation. \nEarly Termination and Exit Fee.   If the Cost Assurance Agreement is terminated prior \nto the expiration of the Term, the Cost Assurance Agreement provides for an Exit Fee equal to \nthe value of the required Financial Security on the date of termination.  If the TCLL/Large Load \nEnd User does not otherwise pay the Exit Fee in the required time under the agreement, PG&E is \nallowed to draw on all Financial Security to pay the Exit Fee.   \nThe Exit Fee and Financial Security obligations are consistent with the directives \ncontemplated by the OSC.  The Commission called for a secured minimum contribution, based \non the level of requested jurisdictional transmission service in MW and credited to the revenue \nrequirement, sufficient to “mitigate cost shifting if the Eligible Customer ultimately takes less \ntransmission service than anticipated because the large load does not materialize as planned or is \nnot developed at all.”139  Here, PG&E’s proposal will treat amounts recovered for MARO \nShortfalls as a credit in PG&E’s wholesale revenue requirements, consistent with the OSC.   \nThe proposed Exit Fee also protects other customers from cost shifts that result from a \nLarge Load End User failing to maintain service for the full term of the Cost Assurance \nAgreement.  If the Large Load End User departs before the full term is satisfied, the cost of the \nupgrades needed to provide, at least in part, interconnection service to the TCLL will remain in \nPG&E’s transmission revenue requirement, but the revenue expected from the departing load \nwill not materialize.  To mitigate this concern, PG&E’s proposed Exit Fee requires the Large \nLoad End User to pay five (5) years of their targeted expected Minimum Annual Revenue \nObligation to avoid shifting costs onto other customers.   \nLarge Load End User Rights and Obligations.  In Section 6 of the Cost Assurance \nAgreement, the Large Load End User agrees that its obligations under the agreement are: (i) the \nannual payment of any MARO Shortfall; (ii) posting of Financial Security; and (iii) payment of \nExit Fee, if any.  \nOther Provisions.  The remaining provisions of the Cost Assurance Agreement include \nstandard contract terms and conditions typically found in pro forma Commission-approved \ninterconnection and transmission service agreements.  They include Section 7 (Indemnification \nand Liability); Section 8 (Default); Section 9 (Confidential Information); Section 10 \n(Assignment); and Section 11 (Miscellaneous Provisions).     \n \nabove.  If the cash deposit is paid into escrow, the interest obtained in the escrow account will accrue to \nthe benefit of the TCLL/Large Load End User.   \n139 OSC at PP 80, 82, 84."},{"page":35,"startToken":16540,"endToken":16993,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 35 \n \n \nb. \nPGE’s proposal to include the Large Load End User as a \nsignatory to the Cost Assurance Agreement when PG&E is the \nTCLL is just and reasonable. \nLike the Facilities Agreement, PG&E proposes to include the Large Load End User as a \nparty to the pro forma Cost Assurance Agreement when PG&E is the TCLL for the reasons \ndetailed in Section V(C)(2)(b) above.   \n4. \nPG&E Proposes to Include the Payments Received from TCLLs and \nLarge Load End Users in the TO Formula Rate in Accordance with \nCost-Of-Service Requirements  \nThe OSC requires that payments made by an Eligible Customer to a transmission owner \npursuant to a cost recovery agreement will be appropriately credited toward the transmission \nowner’s transmission revenue requirement consistent with the Commission’s cost-of-service \nregulations.140  The Commission preliminarily finds in the OSC that it appears reasonable for \nfilers of formula rates to provide a separate workpaper in the annual informational filing \ndescribing how any payments made pursuant to a cost recovery agreement are reflected in the \ntransmission owner’s transmission formula rate.141 \nPG&E proposes to treat the cost recovery associated with the four different types of \nfacilities, i.e., (1) Direct Assignment Facilities; (2) TCLL FILLI Facilities; (3) TCLL \nInterconnection Network Upgrades; and (4) TCLL Reliability Network Upgrades in accordance \nwith the Uniform System of Accounts, its approved formula rate,142 and where appropriate, make \ncertain modifications to the formula rate to allow specific cost recording and transparency into \nhow TCLL and/or Large Load End User payments will be recorded in PG&E’s revenue \nrequirement.    \nDirect Assignment Facilities and TCLL FILLI Facilities.  Consistent with current \npractice, Direct Assignment Facilities and payments for those facilities are removed from the TO \nformula rate.  This is done through PG&E’s accounting system by recording the payment of \nDirect Assignment Facilities and associated plant and other costs in certain Maintenance Activity \nTypes (“MAT”) codes143 and Unbundled Cost Categories (“UCCs”)144 that are excluded from \nrecovery in the approved formula rate.  PG&E will utilize this same methodology for Direct \n \n140 OSC at P 84 (citing 18 C.F.R. pt. 101 (2025)).   \n141 Id. \n142 Pac. Gas & Elec. Co., Transmission Owner Tariff, FERC Electric Tariff, Vol. No. 5, App. VIII \n(Formula Rate). \n143 PG&E uses MAT codes to categorize costs for capital work, replacements, emergency work, new \nbusiness, etc. according to the type of work being done.  MAT codes 82A/82N are direct-connect, non-\nCAISO controlled facilities that are excluded from the TO formula rate. \n144 UCCs are regulatory categories used to separate and categorize Plant, Accumulated Depreciation, and \nDepreciation Expense for reporting and ratemaking purposes."},{"page":36,"startToken":16993,"endToken":17553,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 36 \n \n \nAssignment Facilities and TCLL FILLI Facilities to exclude those upfront payments from \nrecovery in the formula rate.        \nTCLL Interconnection Network Upgrades.  As explained above, the costs of TCLL \nInterconnection Network Upgrades are paid upfront by the TCLL before Interconnection Service \nbegins and may be refunded over fifteen (15) years based on the transmission revenues generated \nby the TCLL.  PG&E proposes to include the upfront payment as a rate base credit.  Currently, \nthe TO formula rate provides for the crediting of generator interconnection upfront payments as a \ncredit to rate base in Schedule 15-NUC (Network Upgrade and Credit Interest Expense).145 \nThese amounts are supported in Workpaper WP_15-NUC, which details the calculations.146  \nPG&E proposes the same treatment for Large Load End User upfront payments, i.e., those \namounts would be recorded to Schedule 15-NUC (Network Upgrade and Credit Interest \nExpense) and act as a rate base credit.  To increase transparency, if PG&E’s proposed cost \nresponsibility framework is accepted, PG&E proposes to submit on compliance the form of an \nadditional workpaper to support the Large Load End User payment amounts that will be reflected \nin Schedule 15-NUC (Network Upgrade and Credit Interest Expense) similar to the current \nWP_15-NUC for generator interconnection upfront payments.     \nWhen the asset is placed in service, it is recorded in the appropriate plant accounts.  If \nthose upfront costs are refunded to the TCLL or Large Load End User, PG&E would reduce the \nrate base credit.  In this manner, when the asset is placed in service it is recorded in plant and \nappropriately depreciated, offset by a rate base credit for the upfront payment made by the \ncustomer.  When the Large Load End User pays for the upfront cost of the facilities through its \ntargeted contribution to transmission revenue, the upfront cost is refunded and the rate base \ncredit is reduced.  PG&E proposes to treat the non-refundable portion of the upfront payment in \na manner similar to direct assignment facilities, i.e., the upfront payment and associated costs of \nthe asset are excluded from the TO formula rate. \nTCLL Reliability Network Upgrades.  As discussed above, for TCLL Reliability \nNetwork Upgrades, PG&E proposes to require a Minimum Annual Revenue Obligation backed \nby security from the TCLL or Large Load End User to ensure that the TCLL or Large Load End \nUser pays their expected targeted transmission revenue.  Any relevant TCLL Reliability Network \nUpgrades constructed, in part, for the Large Load End Users’ interconnection would be recorded \nto the appropriate plant account when placed in service and recovered through PG&E’s TO \nrevenue requirement and associated Regional Access Charge or Regional Access Charge plus \nLocal Access Charge, as applicable.  As stated in the pro forma, the Minimum Annual Revenue \nObligation Shortfall or Exit Fee recovered from the TCLL/Large Load End User will be treated \nas a credit in PG&E’s wholesale revenue requirements.  In this manner, PG&E would properly \naccount for customer revenue in its TO formula rate in accordance with cost-of-service \nprinciples, the Uniform System of Accounts, and the approved formula rate, with limited \nmodifications where required.  If PG&E’s proposed cost responsibility framework is accepted, \n \n145 Appendix VIII, TO Formula Rate, Schedule 1-Base TRR, line 112. \n146 Id. Att. 1, Protocols, Section 20 (List of Work Papers)."},{"page":37,"startToken":17553,"endToken":18013,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 37 \n \n \nPG&E proposes to submit on compliance the necessary edits to the Appendix VIII: Formula Rate \nto effectuate this treatment.     \n5. \nPG&E Proposes a Just and Reasonable Interim Standard \nInterconnection Service and Flexible Interim Large Load \nInterconnection Service to Accommodate Transmission Customers \nSeeking to Take Transmission Service on Behalf of Large Load End \nUsers   \nThe OSC found that CAISO’s Tariff may be unjust and unreasonable because it lacks \n“transmission services that reflect the use of the transmission system by Eligible Customers on \nbehalf of flexible large load, on both an interim and permanent basis.”147  The OSC directs the \nCAISO to explain whether the CAISO’s Tariff remains just and reasonable without (1) an \ninterim non-firm network transmission service while network upgrades are being constructed and \n(2) permanent firm and non-firm contract-demand transmission services (service up to a \nspecified MW contract level on a firm or non-firm basis), or to propose such revisions—or, \nalternatively, to explain how the CAISO’s existing framework provides comparable options. \nAs discussed above, unlike other regions, the CAISO does not process stand-alone \nrequests for transmission service; therefore, a flexible service for Large Loads cannot be offered \nas a separate transmission product.  Instead, any flexible transmission service must be offered as \npart of the interconnection services.148  Accordingly, PG&E proposes to address this directive of \nthe OSC through its interconnection process and proposes to amend its TO Tariff to incorporate \nan Interim Standard Interconnection Service and Flexible Interim Large Load Interconnection \n(“FILLI”) Service. \nPG&E proposes to allow TCLLs, on behalf of Large Load End Users, to request Interim \nStandard Interconnection Service and/or FILLI Interconnection Service in their TCLL \nInterconnection Application.  The terms and conditions of Interim Standard Interconnection \nService and FILLI Interconnection Service will be set forth in the pro forma Interim Service \nAgreement (Attachment C of Appendix XI).  Interim Standard Interconnection Service is defined \nas Standard Interconnection Service that can be provided, if any, prior to the completion of all \nTCLL Facilities identified as necessary for the Large Load to withdraw Energy.  However, \nproposed Section 10A.7.1 makes it clear that the Participating TO is not obligated to provide any \namount of Standard Interconnection Service until necessary facilities have been placed in \nservice.  \nWhen Interim Standard Interconnection Service is not available, or only partially \navailable, FILLI Interconnection Service is available for all remaining Load if the Large Load \nEnd User can reduce Load at a specified Point of Withdrawal.  FILLI Interconnection Service is \nintended to be a temporary, as-available transmission interconnection service that allows PG&E, \nworking with the CAISO and the Large Load End User, to manage operational constraints on \n \n147 OSC at P 105. \n148 Virani Testimony at 5-6."},{"page":38,"startToken":18013,"endToken":18490,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 38 \n \n \nwithdrawals from the transmission system while the interconnection and system upgrades \nnecessary to provide standard, firm service are being developed.149  As discussed in more detail \nbelow, if the TCLL requests FILLI Interconnection Service or Interim Standard Interconnection \nService, PG&E will identify the extent to which interim services can be provided, prior to when \nall TCLL Facilities are in service.  The rates charged for transmission service, subject to the \nFILLI Interconnection Service restrictions, will also not be discounted because it is a voluntary \nservice. \nFILLI Interconnection Service automatically terminates once Standard Interconnection \nService is available to serve the entire requested capacity.  PG&E is not proposing permanent \nnon-firm or conditional-firm interconnection service at this time.  PG&E will work with the \nCAISO to develop any permanent option through a future stakeholder initiative informed by \nexperience with FILLI Interconnection Service and customer interest.150   \nHowever, PG&E believes that its proposed FILLI Interconnection Service is functionally \nequivalent to the interim non-firm network transmission service contemplated by the OSC and \ntherefore satisfies this requirement of the OSC.  PG&E also believes that FILLI Interconnection \nService, together with CAISO’s Tariff, addresses the OSC directive by providing a functionally \ncomparable service.  PG&E proposes to include a new Section 10A.7 in its TO Tariff, along with \na pro forma Interim Service Agreement, that together will govern Interim Standard \nInterconnection Service and FILLI Interconnection Service for those Large Load End Users \nvoluntarily electing to take it. \na. \nPG&E proposes to include new sections in the TO Tariff to \naddress the requirements for applying for, studying, and \nimplementing Interim Standard Interconnection Service and \nFILLI Interconnection Service. \nProposed Section 10A.7 allows TCLLs to request Interim Standard Interconnection \nService and/or FILLI Interconnection Service as part of their TCLL Interconnection Application \nand establishes a process for reviewing and processing Interim Standard Interconnection Service \nand/or FILLI Interconnection Service requests.  If the TCLL on behalf of the Large Load End \nUser has requested one or both of these interim interconnection services, PG&E will perform an \nanalysis to identify the extent to which the Large Load End User can be served by Interim \nStandard Interconnection Service and the amount of remaining requested capacity that can be \nserved by FILLI Interconnection Service.151  Proposed Section 10A.7.1 makes clear that PG&E \nwill not be obligated to provide any amount of Standard Interconnection Service requested until \n \n149 Nedrud Testimony at 29-30. \n150 CAISO, Large Loads Enhancements Draft Final Proposal, at 68 (Sept. 24, 2026), \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load-\nEnhancements-Sep-24-26.pdf (“Although the CAISO is not proposing to advance the permanent flexible \ninterconnection offering, FLIP, in this draft final proposal, the CAISO does commit to further exploration \nof this permanent offering in a future stakeholder initiative.”).  \n151 Nedrud Testimony at 29-30."},{"page":39,"startToken":18490,"endToken":18943,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 39 \n \n \nnecessary facilities have been placed in service.  It also specifies that the actual amount of \nEnergy that a Large Load End User may withdraw is based on expected operations and real-time \noperations.   As discussed in more detail below, FILLI Interconnection Service will also be \ngoverned by an Interim Service Agreement. \nProposed Section 10A.7.2 establishes a study process for interim service to determine the \nmaximum amount of Interim Standard Interconnection Service and/or FILLI Interconnection \nService available to the Large Load End User.  The study is performed as part of the applicable \nSerial or Cluster Study Process and evaluates service under NERC Transmission System \nPlanning Performance Requirement conditions, including normal and contingency conditions, to \ndetermine firm and curtailable amounts and required operating protections.152  The analysis does \nnot guarantee that the maximum amount will be available under actual system conditions.  \nPG&E will require studying load under both N-1-1 and N-1 conditions to determine how \nmuch, if any, FILLI Interconnection Service can be offered while upgrades are being constructed \nto enable Standard Interconnection Service for the entire load request.153  The study will identify \ncapacity (in MW) of Interim Standard Interconnection Service and FILLI Interconnection \nService (which can vary seasonally and over time) as well as any operational requirements, \nprotections, and control systems to maintain safe and reliable service, consistent with the data \nrequirements for flexible interim load interconnection service set forth in the proposed CAISO \nTariff.154  FILLI Interconnection Service is subject to curtailment at all times, and is available \nonly where the Participating TO determines service may be provided within limitations in certain \nperiods under normal operating conditions.155 \nProposed Section 10A.7.3.1 and the Interim Service Agreement, discussed below, set \nforth the FILLI Interconnection Service reliability requirements, including what TCLL \nInterconnection facilities must be installed, the necessary protection and control systems, and \noperating procedures to allow the Large Load End User to withdraw Energy.  Proposed Section \n10A.7.3.1 also specifies that FILLI Interconnection Service will not commence until PG&E and \nthe TCLL have completed installation of all equipment specified under the Interim Service \nAgreement. \nProposed Section 10A.7.3.2 provides that Exhibit 1 to the Interim Service Agreement \nshall set forth the circumstances, contingencies, and operating conditions under which FILLI \nInterconnection Service will be curtailed.  Specifically, a TCLL receiving FILLI Interconnection \nService will be subject to curtailment prior to any curtailment of a TCLL receiving Standard \nInterconnection Service, and PG&E may curtail FILLI Interconnection Service as necessary to \n \n152 Nedrud Testimony at 29-30. \n153 Id. \n154 CAISO Tariff, Proposed § 25.7.2 (Flexible Interim Load Interconnection).  \n155 See Nedrud Testimony at 29-30."},{"page":40,"startToken":18943,"endToken":19368,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 40 \n \n \nmaintain the reliable operation of the CAISO Controlled Grid, including during normal operating \nconditions.  \nProposed Section 10A.7.3.3 provides that a Large Load End User receiving FILLI \nInterconnection Service shall not exceed the authorized quantity of FILLI Interconnection \nService and that PG&E may disconnect service to the Large Load End User if the Large Load \nEnd User’s Energy withdrawals violate the terms of the Interim Service Agreement. \nb. \nPG&E Proposes to Include a Pro Forma Interim Service \nAgreement as Attachment C to the TCLL Agreement That will \nProvide the Terms and Conditions of Interim Standard \nInterconnection Service and/or FILLI Interconnection Service. \nPG&E proposes to include as Attachment C to the TCLL Agreement a pro forma Interim \nService Agreement among PG&E (as Participating TO under its TO Tariff), the CAISO, the \nTCLL (if not PG&E), and the Large Load End User.  An executed and effective Interim Service \nAgreement will supply the operative terms for Interim Standard Interconnection Service and/or \nFILLI Interconnection Service for each Large Load End User opting to take such service. \nSection 1 (Definitions) references the TCLL Agreement and the CAISO and TO Tariffs \nfor Definitions. \nSection 2 (Interconnection Service Quantities) provides the amounts and types of \ninterconnection service that PG&E expects to initially provide to the TCLL based on the results \nof the requisite studies.  \nSection 3 (Curtailment of FILLI Interconnection Service) provides the Interim Service \nAgreement shall set forth the circumstances, contingencies, and operating conditions under \nwhich FILLI Interconnection Service will be curtailed.  It also makes clear that FILLI \nInterconnection Service shall be subject to curtailment prior to any curtailment of customers \nreceiving Standard Interconnection Service and that the Participating TO may curtail FILLI \nService as necessary to maintain the reliable operation of the CAISO Controlled Grid, including \nduring normal operating conditions.  \nSection 4 (TCLL and Large Load End User Obligations) provides that the TCLL and \nLarge Load End User will abide by the requirements set forth in the Interim Service Agreement, \nand that the Large Load End User shall ensure that it and its Scheduling Coordinator comply \nwith all applicable requirements in the CAISO Tariff. \nSection 5 (FILLI Interconnection Service Reliability Requirements) provides that Exhibit \n1 to the Interim Service Agreement addresses the CAISO and Participating TO requirements for \nFILLI Interconnection Service.  Section 5 also specifies that the Facilities Agreement identifies \nthe TCLL Facilities to be owned by the Participating TO or the TCLL and addresses cost \nresponsibility for such facilities."},{"page":41,"startToken":19368,"endToken":19794,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 41 \n \n \nSection 6 (Exceedances) requires the Large Load End User to avoid exceedances, which \ncan result in disconnection. \nSection 7 (Termination of FILLI Interconnection Service and/or Interim Standard \nInterconnection Service) provides that FILLI Interconnection Service automatically terminates \nupon PG&E’s notice to the TCLL of the completion of the transmission facilities needed to \nprovide Standard Interconnection Service, at which time the service automatically transitions to \nservice pursuant to the standard, non-FILLI Interconnection Service provisions of the TO Tariff \nand the Interim Service Agreement.  \nSection 8 (Conditions Precedent) addresses the requirements that need to be in place \nbefore FILLI Interconnection Service or Interim Standard Interconnection Service can be \nprovided.   \nThe remaining provisions are similar in nature to the standard provisions included in the \nTCLL Agreement and other attachments. \nc. \nInclusion of the Large Load End User on the pro forma Interim \nService Agreement is necessary and within the Commission’s \njurisdiction to approve. \nPG&E proposes to include the Large Load End User as a party to the pro forma Interim \nService Agreement because PG&E must have a binding commitment from the Large Load End \nUser that it will adhere to curtailment requirements.  FILLI Interconnection Service is voluntary.  \nTo take the service, both the TCLL and the Large Load End User must elect it, and that election \nplaces a reliability burden on the transmission system.  It is critical for reliability that the Large \nLoad End User comply with curtailments, particularly where PG&E serves as both the \nParticipating TO and the TCLL.  FILLI Interconnection Service will also impose equipment and \nother operational requirements with which PG&E must have assurance that the Large Load End \nUser will comply.156  Without binding obligations running directly to the Large Load End User, \nPG&E would have no guarantee of that compliance. \nThe pro forma Interim Service Agreement, including the Large Load End User’s \nobligations under it, is within the Commission’s jurisdiction to approve.  The Commission has \njurisdiction over the terms and conditions of transmission service.157  The Interim Service \nAgreement allows TCLLs, on behalf of Large Load End Users, to take transmission-level, \nflexible interconnection service before the transmission facilities necessary to provide Standard \nInterconnection Service are in place.158  In other regions, FILLI Interconnection Service would \nbe offered as a transmission service, but given the structure of the CAISO market it is offered by \n \n156 See Nedrud Testimony at 29-30. \n157 16 U.S.C. § 824(b); New York, 535 U.S. at 16-24.  \n158 Nedrud Testimony at 29-30."},{"page":42,"startToken":19794,"endToken":20258,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 42 \n \n \nPG&E, the Participating TO, as an interconnection service.159  Accordingly, because it is a \ntransmission service agreement, it is within the Commission’s jurisdiction to approve.160  While \nthe Commission has rejected proposals that place certain obligations on retail customers, those \nobligations were placed in the context of wholesale capacity market constructs where the \nCommission does not have jurisdiction over the provision of retail energy service.161  Here, \nhowever, PG&E seeks to ensure the retail customer, the Large Load End User, adheres to the \nrequirements for TCLL taking flexible transmission interconnection service on its behalf.  The \nprovision of this flexible transmission service is also completely voluntary.   \nD. \nPG&E Proposes Changes to the TO Tariff That Provide a Just and \nReasonable Process for Affected Systems \nThe OSC does not separately address affected systems. It does, however, find that the TO \nTariffs lack clear provisions for studying the transmission system impacts of large loads. It also \nrequires that large load-driven costs not shift to customers who neither caused nor benefit from \nthem.162 \nProposed Sections 10A.4.3 and 10A.6 address Affected Systems directly. When PG&E’s \nstudies show that another system will be affected by a TCLL Interconnection request, PG&E \nmust notify the Affected System Operator, the TCLL, and the CAISO. PG&E will then \ncoordinate any studies to determine the impact of the TCLL Interconnection request on the \nAffected System and include the Affected System Operator in the applicable meetings with the \nTCLL. Section 10A.6 requires the TCLL to fund any required upgrades on the Affected System, \nwhich are identified in the Facilities Agreement. An Affected System Operator taking service \nunder PG&E's TO Tariff must inform the Participating TO and TCLL within forty (40) Business \nDays whether it intends to perform an affected system study, at the TCLL's expense. If the \nAffected System Operator fails to notify PG&E within forty (40) Business Days, it waives its \nrights to bring any related claims against PG&E. \nThese provisions meet the OSC’s directives. They establish a clear, timely process for \nidentifying and studying impacts beyond PG&E's system. They also assign the resulting costs to \nthe TCLL, whose request causes them, rather than to other transmission customers. \n \n159 Virani Testimony at 3-6.  \n160 Supra, note 131. \n161 PJM Interconnection, L.L.C., 197 FERC ¶ 61,109, P 81 (2026) (finding outside the Commission’s \njurisdiction provisions that require retail customers to curtail as part of a wholesale capacity market \nconstruct); FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278-80 (2016) (explaining that FERC may \nregulate practices directly affecting wholesale rates but may not regulate retail electricity sales, which are \nreserved to the states). \n162 OSC at P 80."},{"page":43,"startToken":20258,"endToken":20697,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 43 \n \n \nVI. \nPG&E PROPOSES CHANGES TO THE TO TARIFF THAT PROVIDE A JUST \nAND REASONABLE PROCESS FOR LARGE LOADS THAT SEEK TO CO-\nLOCATE WITH GENERATION PROJECTS \nIn the OSC, the Commission preliminarily found that the CAISO Tariff appears to be \nunjust and unreasonable because it does not contain provisions addressing with sufficient clarity \nand consistency the rates, terms, and conditions of service that apply to interconnection \ncustomers serving co-located load, and because it does not reflect that an Eligible Customer \ntaking transmission service on behalf of such load is willing and able to limit its energy \nwithdrawals from the transmission system under certain conditions.163  The Commission \ndescribed co-located load as end-use customer load physically connected to the facilities of an \nexisting or planned generating facility on the generator interconnection customer’s side of the \npoint of interconnection to the transmission system, and it referred to the co-located load and its \nassociated generating facility together as a co-location arrangement.164  The Commission \ndirected the CAISO and the Participating TOs to address these issues.165 \nA. \nThe CAISO and the Participating TOs Propose to Maintain the \nExisting Division of Requirements Between the CAISO Tariff and the \nParticipating TO Tariffs, with the CAISO Remaining Responsible for \nGenerator Interconnections and PG&E Remaining Responsible for \nLoad Interconnections. \nAs noted above, the OSC’s co-location directives fall principally on the CAISO rather \nthan on the Participating TOs.  The Commission recognized that co-location concerns “mostly \nimplicate the CAISO Tariff,” because only the CAISO Tariff governs the generator \ninterconnection process.166  Accordingly, the OSC directs the CAISO to clarify how \ninterconnection customers may use the generator interconnection process to serve co-located \nload—including whether a generating facility may request interconnection service below its \nmaximum facility output and may use provisional and surplus interconnection service—and to \naccount in its study process for the dynamic impacts of co-located load and any request to \nmodify an existing generating facility’s interconnection service level to serve that load.167  The \nOSC also directs the CAISO to address cost-causation concerns, including whether an Eligible \nCustomer taking service on behalf of co-located load should pay for regulation and black start \nservices on a gross demand basis, so that these costs are not shifted to other transmission \ncustomers.168  \n \n163 OSC at P 93. \n164 Id. at P 88. The Commission uses the term “Eligible Load” to refer to co-located load and/or load with \nbehind-the-meter generation. Id. at P 90. \n165 Id. at P 86. \n166 Id. at P 86 n.77. \n167 Id. at P 96. \n168 Id. at PP 98-100."},{"page":44,"startToken":20697,"endToken":21233,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 44 \n \n \nThe OSC’s directives to the Participating TOs are correspondingly narrower, reaching the \nprovision of transmission service to an Eligible Customer on behalf of co-located load and the \nprevention of cost shifting.  As a Participating TO, PG&E must ensure that its TO Tariff \nprovides a clear and consistent process for a TCLL to interconnect a Co-Located Large Load \nEnd User, coordinated with the CAISO-administered generator interconnection process that \ngoverns the associated generating facility. \nBased on stakeholder discussions with the CAISO, PG&E expects the CAISO to address \nthe directives of the OSC in its filing by clarifying how co-located large loads and generation \nmay interconnect to, and operate within, the CAISO-controlled grid.  Consistent with the existing \ndivision of responsibilities, PG&E expects that the changes in the CAISO Tariff will apply to the \ngeneration component of a co-location arrangement and PG&E’s proposed changes will apply to \nthe Large Load End User, with the CAISO continuing to govern and study wholesale generation \ninterconnection requests and PG&E continuing to govern and study Load interconnection \nrequests.169  Where a new or existing Large Load proposes to co-locate with a new Generating \nFacility that may export Energy to the transmission grid, PG&E understands the CAISO will \npropose that the Generating Facility will require a CAISO interconnection study under its \nResource Interconnection Standards (Appendix KK to the CAISO Tariff), so that the request is \nscreened and competes for capacity in the next cluster study based on the CAISO’s scoring \ncriteria.  Because scoring, financial requirements, and study results would be based on the \ncapacity the developer requests, a developer may limit the quantity of Generation to be exported \nin light of how much Generation will instead serve the Co-Located Large Load End User, and \nthe CAISO would work with the affected Participating TO to produce study results reflecting the \ncombined impact of the Co-Located Large Load End User and Generating Facility.170  \nB. \nPG&E Proposes to Include a New Process for Addressing the TCLL \nPortion of the Co-Located Large Load End User Interconnection \nProcess that will Ensure Coordination with the CAISO’s Generator \nInterconnection Process.   \nPG&E proposes to include a new Section 10A.8 that will govern Co-Located Large Load \nEnd Users.  Proposed Section 10A.8 describes the interconnection process applicable to Co-\nLocated Large Load End Users connecting to facilities of a Generating Facility.  For such Co-\nLocated Large Load End Users, the TCLL will be subject to the TCLL Interconnection process \nin Section 10A.  The CAISO will be a party to a pro forma agreement that bridges the pro forma \nLarge Generator Interconnection Agreement (“LGIA”) with the TCLL Agreement or will \nnegotiate a non-conforming LGIA to account for certain details of the Co-Located Large Load \nEnd User interconnection on an individual basis.  The Generating Facility developer will also \nexecute a CAISO pro forma Participating Generator Agreement for the generating facility, but \nnot a Participating Load Agreement for the Co-Located Large Load End User. \n \n169 See e.g., California Independent System Operator Corp., Large Loads Enhancements Draft Final \nProposal, Serving Co-Located Loads (Sept. 17, 2026) (“CAISO Draft Final Proposal”). \n170 CAISO Draft Final Proposal, Serving Co-Located Loads."},{"page":45,"startToken":21233,"endToken":21700,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 45 \n \n \nThe Section 10A.8 process will coordinate the Large Load study with the CAISO \ngenerator-interconnection study for any Co-Located Large Load End User and produce study \nresults reflecting the combined operation of the Generating Facility and the Large Loads.  The \nstudies will account for the combined operating configuration, requested export capacity, and \nany controls or protections needed to ensure that the assumed withdrawal arrangement is \neffective.  \nC. \nElectrically Proximate Load \nIn the OSC, the Commission preliminarily finds that the CAISO Tariff appears to be \nunjust and unreasonable because it lacks a generator interconnection study process and/or \ngenerator interconnection service to reflect an interconnection customer’s commitment to limit \nthe generating facility’s output to minimize the impact on the transmission system while serving \nan electrically proximate large load.171  The CAISO has deferred addressing electrically \nproximate generators and large loads until a future stakeholder initiative.  PG&E supports this \napproach and believes that the CAISO should first discuss with stakeholders whether any such \ninitiative is necessary.  PG&E is unclear how a Generator’s sale of Energy to a Large Load (even \nusing a wholesale sleeve), using wires it does not own would be in accord with state, municipal, \nand other public power service area rights.  Indeed, co-location itself may be rare in the CAISO, \ngiven state laws on when a retail seller is deemed to be a CPUC-jurisdictional electrical \ncorporation, subject to CPUC rate regulation and myriad other California laws and CPUC \nregulation.172  In CPUC-regulated utility service areas, renewable and cogeneration generators \nare permitted in limited circumstances to serve up to two retail loads without being regulated by \nthe CPUC, such that even co-location relies on a fairly narrow legal exception, which does not \ncover electrically proximate generators and loads.  Public power utilities can prohibit co-location \naltogether.173   \nVII. \nPG&E PROPOSES A TRANSITION PERIOD CONSISTENT WITH THE \nREQUIREMENTS OF THE OSC. \nThe OSC states that it is “not intended to disrupt existing commercial arrangements” and \nspecifically recognizes that any proposed changes to the Participating TO Tariffs should “(a) \npropose a reasonable implementation period to ensure minimal disruption to such existing \ncommercial arrangements, and (b) allow a reasonable amount of time to finalize ongoing \nagreements that are nearing completion as of the date such tariff provisions are filed with the \n \n171 OSC at P 113. \n172 S.B. 886, 2025–2026 Reg. Sess. (Cal. 2026) (California Technology Innovation and Ratepayer \nProtection Act)). \n173 Presumably there are transmission owners similarly located in states throughout the United States with \nservice area laws that render transactions between electrically proximate generators and retail loads \nunlawful, such that RTOs in such regions would need to restrict study procedures based on whether the \nLocal Regulatory Authority permits the service in the first place."},{"page":46,"startToken":21700,"endToken":22246,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 46 \n \n \nCommission.”174  Consistent with that directive, PG&E proposes a new Section 10A.9 of the TO \nTariff to govern the transition to the new Section 10A process.  Proposed Section 10A.9 provides \nthat, as to a retail customer with a load of 50 MW or greater that has provided its UDC or MSS \nwith a completed application for retail service before the original effective date of Section 10A, \nthe UDC or MSS is not required to obtain a TCLL Interconnection under Section 10A.  In \naddition, because PG&E must begin its annual Cluster Study Process no later than April of each \nyear, Section 10A.5.1 provides that, if there are no Completed TCLL Interconnection \nApplications that have been found to be electrically dependent by the end of February 2027, \nthere will be no Cluster Study Process commencing on April 1, 2027, under the proposed tariff. \nAs a result, any TCLL Interconnection Applications completed before the effective date \nof the new Section 10A process will be processed under PG&E’s existing Large Load process, \nand PG&E will make any filings necessary to obtain Commission approval of agreements \nassociated with those requests. \nVIII. OTHER CHANGES TO THE TO TARIFF \nIn addition to adding a new Section 10A, as well as replacing the currently unused \nAppendix XI, the new Large Load processes had a ripple effect on other TO Tariff sections, \nincluding, most importantly, the Definitions, where many new terms were added.  The changes \nthat required PG&E to add new processes for Large Load also evidenced the fact certain portions \nof the TO Tariff had not always been revised through the past nearly three decades in a manner \nthat kept it congruent with the CAISO Tariff.  Thus, PG&E has revised the body of its TO Tariff \nin a variety of ways.175   \nFirst, PG&E observed that Section 1 no longer reflected Appendix F of the CAISO Tariff \nregarding how in-BAA transmission service was paid for.  Section 1 also was the first section \nthat indicated that PG&E had not adopted the CAISO’s “Regional” and “Local” vernacular \nrather than “High Voltage” and “Low Voltage.”  The sets of terms are identical, and the \nDefinitions now indicate that they are interchangeable.  But, PG&E chose only to update the \nterms in the body of the TO Tariff (as they were relevant) and left the terms High- and Low-\nVoltage in its Appendices I-X.176  As noted, many new terms had to be defined, not only to \nreflect Section 10A, but to differentiate the TCLL Interconnection process from the existing \nWholesale Load Interconnection process.  The term “Wholesale Load Interconnection” is now \nused for this more traditional service, primarily in Sections 8 and 10.  The definition of “Gross \nLoad” was updated to the CAISO definition because Gross Load is used in Appendix XI.   \nSections 4, 5.1, and 8.1 were redrafted to better reflect the entities subject to the TO Tariff \nfor interconnection purposes.  When the TO Tariff was drafted, the wholesale interconnections \n \n174 OSC at P 5. \n175 To avoid excessive redlining, “ISO,” “ISO Controlled Grid,” and “ISO Tariff” were retained rather \nthan updated. \n176 Section 5, which addresses rates, retains usage of “High-Voltage” and “Low-Voltage.”"},{"page":47,"startToken":22246,"endToken":22716,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 47 \n \n \nenvisioned were not the same as today given Order No. 1000 and other changes.  Thus, Section \n10 was modified to reflect a new term “Wholesale Load Interconnection.” \nFinally, the new Large Load procedures required a second look at the creditworthiness \nsection of the TO Tariff (Section 13).  The existing provisions addressed those paying the Low \nVoltage (a/k/a Local) Access Charge and End Users, whose rates are identified in the TO Tariff \nbut whose creditworthiness was a matter for the CPUC.  With the proposed changes in Section \n10A and Appendix XI, TCLLs will be seeking to add load on behalf of Large Load End Users \n(thus triggering capital projects).  Additionally, for efficiency, Large Load End Users may \ntransact directly with PG&E, which requires a new approach to credit as to both these entities, \nwhich is found in Exhibit 1 to the Cost Assurance Agreement (Attachment B to Appendix XI).   \nFinally, given the congruent nature of PG&E and the CAISO’s large load tariff filings, \nthere may be additional conforming changes that need to be made on compliance.   \nIX. \nRESPONSES TO THE OSC BRIEFING QUESTIONS \nSection IV of the OSC directs further briefing on five sets of questions. PG&E responds \nto each below, in the order presented in the OSC, to the extent the questions implicate PG&E’s \nTO Tariff. \nA. \nProtection of Existing Commercial Arrangements \nThe OSC asks how the CAISO and the Participating TOs should protect existing \ncommercial arrangements, including (1) what would be a reasonable implementation period to \nensure minimal disruption to such arrangements, and (2) how to allow a reasonable amount of \ntime to finalize ongoing agreements that are nearing completion as of the date the tariff \nprovisions are filed.177  As discussed in Section VII, PG&E proposes a new Section 10A.9 under \nwhich a UDC or MSS serving a retail customer with a Load of 50 MW or greater that has \nsubmitted a completed application for retail service before the original effective date of Section \n10A is not required to obtain a TCLL Interconnection under Section 10A.  Requests completed \nbefore the effective date will continue to be processed under PG&E’s existing Section 10 process \nfor Wholesale Load Interconnection Applications.  In addition, PG&E requests an effective date \nof February 16, 2027, which, together with the annual Cluster Study timing in Section 10A.5.1, \nprovides a reasonable implementation period and avoids disrupting arrangements that are nearing \ncompletion. \nB. \nImpacts of New FILLI Interconnection Service on Transmission \nPlanning \nThe OSC also asks what potential impacts on regional and local transmission planning \nwould arise from the introduction of new transmission services for flexible Large Loads, \nincluding how providers and planners would account for flexible large loads’ potential \n \n177 OSC at P 123."},{"page":48,"startToken":22716,"endToken":23232,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 48 \n \n \npreference to take such services and the associated uncertainties around the type, location, and \nquantity of expected Loads.178  As discussed above, PG&E is not proposing a new permanent \nnon-firm or conditional-firm service at this time, and proposed Section 10A.7 makes clear that \nPG&E is not obligated to provide any amount of Standard Interconnection Service requested \nuntil necessary facilities have been placed in service.  Instead, Interim Standard Interconnection \nService and FILLI Interconnection Service are temporary as-available services that are studied \nwithin the applicable Serial Study Process or Cluster Study Process, subject to identified \noperating limits and curtailment, and automatically terminated once Standard Interconnection \nService is available for the full requested capacity.  Any TCLL FILLI Facilities necessary to \ninitiate interim service, will be identified in the Facilities Agreement.  Because the full requested \ncapacity of each Large Load End User will continue to be studied and planned for under the \nCAISO’s TPP and concurrence process, PG&E’s proposal does not alter the inputs to regional or \nlocal transmission planning.   \nTo facilitate this flexible service, the CAISO is also proposing Section 25.7.2, which \nspecifies that the CAISO, Participating TO, and Large Load End User or its authorized agent will \nexecute an agreement, for PG&E this is the Interim Service Agreement, to enable Large Load \nEnd Users to interconnect prior to the completion of the Large Load’s transmission upgrades.  \nHowever, the Interim Service Agreement does not alter the current transmission planning \nprocesses in the CAISO; rather, it specifies the circumstances in which the Large Load End User \nreceiving interim service may be temporarily curtailed and the mechanisms used to perform the \ncurtailment.  PG&E will continue to work with the CAISO to consider any permanent flexible \noption, and its planning implications, in a future stakeholder initiative. \nC. \nStructure of Cost Recovery Agreements and Minimum Cost Recovery \nand Financial Security  \nThe OSC directs respondents to provide information on potential structures for \nagreements between the transmission owner or provider and an Eligible Customer to prevent \nunjust and unreasonable cost shifts related to network upgrades required for Large Loads, and on \nthe appropriate minimum level of cost recovery and Financial Security under such \nagreements.179  As discussed in Section V.C, PG&E proposes a facility-specific structure to \nensure there are adequate cost recovery protections when Large Loads require transmission \nupgrades or additions.  Direct Assignment Facilities and TCLL FILLI Facilities are directly \nassigned to the TCLL or Large Load End User and fully funded before service begins.  TCLL \nInterconnection Network Upgrades are funded upfront by the TCLL or Large Load End User and \nrefunded over fifteen years at 75 percent of realized wholesale transmission revenues.  TCLL \nReliability Network Upgrades are only preliminarily identified in the Facilities Agreement found \nin Attachment A to Appendix XI and remain subject to funding in accordance with the CAISO \nTariff.   The Cost Assurance Agreement found in Attachment B to Appendix XI, however, \nprovides Financial Security requirements and establishes a Minimum Annual Revenue \n \n178 OSC at P 124. \n179 Id. at P 125."},{"page":49,"startToken":23232,"endToken":23673,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 49 \n \n \nObligation to ensure that Large Load End Users that do not materialize or fail to meet an \nexpected minimum capacity are financially responsible for any shortfall to prevent shifting costs \nto other customers. \nD. \nEvaluation of Alternative Transmission Technologies \n \nThe OSC seeks further briefing on whether specific characteristics of providing \ntransmission service to Eligible Customers on behalf of Large Loads warrant requirements \nbeyond (1) the evaluation of alternative transmission technologies in all studies, without the need \nfor a request, and (2) a demonstration in the study report of why alternative transmission \ntechnologies are not feasible or would not result in lower costs or a faster timeline when \ntraditional network upgrades are selected.180  As discussed in Section IV.B, PG&E’s proposed \nSerial Study Process and Cluster Study Process require PG&E to consider alternative \ntransmission technologies in every TCLL Interconnection study and, where traditional network \nupgrades are selected, to demonstrate why alternative transmission technologies are not feasible \nor would not result in lower costs or a faster timeline.   \nE. \nGenerating Facilities Serving Electrically Proximate Large Load or \nLarge Co-Located Load \nThe OSC asks (a) to what extent the CAISO would allow an interconnection customer’s \ngenerating facility serving electrically proximate large load or large co-located load to participate \nin the CAISO’s energy and ancillary services markets, and what restrictions or mitigation would \napply; and (b) whether, and how, the CAISO would account for such generating facilities in its \nresource adequacy construct, including participation and accreditation in any capacity market.181  \nThese questions are directed to the CAISO and implicate the CAISO Tariff rather than PG&E’s \nTO Tariff, and PG&E defers to the CAISO’s response.  For its part, PG&E’s proposed Section \n10A.8 addresses the Load side of a co-location arrangement by requiring the TCLL for a Co-\nLocated Large Load End User to proceed under Section 10A and by coordinating PG&E’s study \nwith the CAISO’s Generator interconnection study so that the results reflect the combined \noperation of the Generating Facility and the Large Load.   \nX. \nETARIFF CHANGES \nWhen PG&E initially sectionalized its TO Tariff, it sectionalized the tariff to a greater \ndegree than required (i.e., three levels).  Due to the number of changes required, the third level \ntariff records of Section 3, i.e., 3.1, 3.2, etc. will all be cancelled and the new version of the \nTariff Record “3., TO Definitions (1.0.0)” will contain all Definitions.   \n \n180 OSC at P 126. \n181 Id. at P 127; TO Tariff, Proposed § 10A.8; CAISO Tariff, Proposed §§ 25.5.1, 25.7.6."},{"page":50,"startToken":23673,"endToken":23871,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 50 \n \n \nXI. \nEFFECTIVE DATE \nPG&E requests that the Commission accept the proposed amendment to the TO Tariff \nwithout hearing, modification, or condition effective Tuesday, February 16, 2027.   \nXII. \nCORRESPONDENCE AND COMMUNICATIONS \nPG&E requests that all correspondence, pleadings, and other communications concerning \nthis filing be served upon the following:   \nTara Kaushik \nJohn P. Perkins, III \nWilliam Brenc \nChristopher Randall \nPacific Gas and Electric Company \nLaw Department, 19th Floor  \n300 Lakeside Drive, Suite 210  \nOakland, CA 94612  \nTelephone: 925-359-5235 \nE-Mail:  John.Perkins@pge.com \n \nAmy Barr \nPacific Gas and Electric Company \nRegulatory Relations \n300 Lakeside Drive, Suite 210  \nOakland, CA 94612  \nTelephone: 510-203-0187 \nE-Mail:  Amy.Barr@pge.com \n \nWilliam M. Keyser \nJennifer Key \nKelsey Robinson \nSteptoe LLP \n1330 Connecticut Avenue, NW \nWashington, DC 20036 \n(202) 429-8186 \nwkeyser@steptoe.com \njkey@steptoe.com \nkrobinson@steptoe.com \n \nXIII. ADDITIONAL INFORMATION REQUIRED BY REGULATION 35.13(b) \nA. \nContents of Filing \nThis filing consists of the following documents in addition to the Tariff Records:   \n• The instant Transmittal Letter; \n• Clean Tariff Attachment; \n• Marked Tariff Attachment;182 \n \n182 The Marked Tariff Attachment does not include Section 10A and Appendix XI, which are entirely \nnew."},{"page":51,"startToken":23871,"endToken":24129,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 51 \n \n \n• Exhibit PGE-0001:  Testimony of Nadim Virani; and  \n• Exhibit PGE-0002:  Testimony of Jens Nedrud.  \nB. \nService \nCopies of this filing have been served upon the CPUC and the CAISO.  Notice of this \nfiling will be made and served via email to the official service list in the OSC Docket No. EL26-\n71-000.  In addition, this filing will be available on PG&E’s website at Wholesale Transmission \nService | PG&E.183  \nC. \nDescription of and Reason for Changes \nA detailed description of the changes are included above. \nD. \nRequest for Waivers \nThe information submitted with this filing substantially complies with the requirements \nof Part 35 of the Commission’s rules and regulations applicable to filings of this type.  To the \nextent necessary, PG&E requests waiver of the requirement to submit cost-of-service data \nrequired by 18 C.F.R. § 35.13.  Further, PG&E requests waiver of any applicable requirement of \nPart 35 for which a waiver is not specifically requested, if necessary, to permit this filing to \nbecome effective as proposed. \nXIV. CONCLUSION \nPG&E requests that the Commission find the proposed changes to the TO Tariff detailed \nherein just and reasonable and that the changes address the issues raised in the OSC.  PG&E \nrequests that the Commission accept the proposed changes effective February 16, 2027, and \nrequests that the Commission, through its acceptance of PG&E’s proposed tariff changes, \nterminate the show cause proceeding as to PG&E.    \n \n183 See https://www.pge.com/en/regulation/wholesale-transmission-service.html."},{"page":52,"startToken":24129,"endToken":24209,"text":"Ms. Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 52 \n \n \n \n \n \n \n \n \nSincerely,  \n \n \n \n \n \n \n \n/s/ John P. Perkins, III \n \n \n \n \n \n \n \n \nTara Kaushik \nJohn P. Perkins, III \nWilliam Brenc \nChristopher Randall \nPacific Gas and Electric Company \nLaw Department, 19th Floor  \n300 Lakeside Drive, Suite 210  \nOakland, CA 94612  \nTelephone: 925-359-5235 \nE-Mail:  John.Perkins@pge.com \n \nWilliam M. Keyser \nJennifer Key \nKelsey Robinson \nSteptoe LLP \n1330 Connecticut Avenue, NW  \nWashington, DC 20036 \n(202) 429-8186 \nwkeyser@steptoe.com \njkey@steptoe.com \nkrobinson@steptoe.com  \n \n \n \nNovember 16, 2026"},{"page":53,"startToken":24209,"endToken":24354,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day caused a copy of the foregoing document to be \nserved upon all affected parties in accordance with the requirements of Rule 2010 of the \nCommission’s Rules of Practice and Procedure and the additional parties listed below: \nNAME \nORGANIZATION/ADDRESS \nE-MAIL ADDRESS \nChristine J. Hammond \nAssistant General \nCounsel \nCalifornia Public Utilities \nCommission \n505 Van Ness Avenue \nSan Francisco, CA  94102 \nChristine.hammond@cpuc.ca.gov  \nAnthony Ivancovich \nDeputy General Counsel \nCalifornia Independent System \nOperator Corporation \n250 Outcropping Way  \nFolsom, CA  95630 \naivancovich@caiso.com \nEnergy Division \nCalifornia Public Utilities \nCommission \n505 Van Ness Avenue \nSan Francisco, CA  94102 \n \nenergydivisioncentralfiles@cpuc\n.ca.gov \n \n \nDated at Oakland, California, this 16th day of November, 2026. \n \n  /s/ Debbie Lee \n \n \nPacific Gas and Electric Company \nFERC Electric Proceedings Dept. \n300 Lakeside Drive \nOakland, California 94612-3534 \nE-mail: Debbie.Lee@pge.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":282,"startToken":0,"endToken":449},{"p":2,"at":282,"title":"I. INTRODUCTION","method":"printed heading","endPage":4,"endAt":1307,"startToken":449,"endToken":1652},{"p":4,"at":1307,"title":"II. BACKGROUND","method":"printed heading","endPage":4,"endAt":1324,"startToken":1652,"endToken":1654},{"p":4,"at":1324,"title":"A. CAISO Is a Unique Transmission Market That Does Not Operate in","method":"printed heading","endPage":6,"endAt":222,"startToken":1654,"endToken":2414},{"p":6,"at":222,"title":"B. CAISO and the PTOs Each Perform Unique and Coordinated","method":"printed heading","endPage":7,"endAt":877,"startToken":2414,"endToken":2950},{"p":7,"at":877,"title":"C. PG&E and the Other Founding Transmission Owning Members of","method":"printed heading","endPage":8,"endAt":1459,"startToken":2950,"endToken":3437},{"p":8,"at":1459,"title":"D. The OSC Preliminarily Found the CAISO and TO Tariffs to Be Unjust","method":"printed heading","endPage":9,"endAt":1174,"startToken":3437,"endToken":3949},{"p":9,"at":1174,"title":"III. PG&E SUPPORTS THE CAISO’S PROPOSED DEFINITION OF LARGE LOAD","method":"printed heading","endPage":9,"endAt":1272,"startToken":3949,"endToken":3965},{"p":9,"at":1272,"title":"A. The OSC Requires a Definition of Large Load Sufficient to Capture","method":"printed heading","endPage":10,"endAt":396,"startToken":3965,"endToken":4276},{"p":10,"at":396,"title":"B. PG&E Supports and Adopts CAISO’s Proposed Definition of Large","method":"printed heading","endPage":11,"endAt":529,"startToken":4276,"endToken":4731},{"p":11,"at":529,"title":"IV. PG&E PROPOSES JUST AND REASONABLE CHANGES TO ITS TARIFF TO","method":"printed heading","endPage":12,"endAt":186,"startToken":4731,"endToken":5161},{"p":12,"at":186,"title":"A. PG&E Proposes a Just and Reasonable Process for a TCLL to Apply","method":"printed heading","endPage":15,"endAt":69,"startToken":5161,"endToken":6552},{"p":15,"at":69,"title":"B. PG&E Proposes a Just and Reasonable Study Process for Evaluating","method":"printed heading","endPage":20,"endAt":1016,"startToken":6552,"endToken":9179},{"p":20,"at":1016,"title":"V. PG&E PROPOSES A SET OF PRO FORMA AGREEMENTS TO MEET THE","method":"printed heading","endPage":20,"endAt":1110,"startToken":9179,"endToken":9197},{"p":20,"at":1110,"title":"A. PG&E Proposes a Just and Reasonable Set of Agreements to Address","method":"printed heading","endPage":21,"endAt":69,"startToken":9197,"endToken":9416},{"p":21,"at":69,"title":"B. PG&E Proposes to Address the Operational and General Pro Forma","method":"printed heading","endPage":22,"endAt":1436,"startToken":9416,"endToken":10081},{"p":22,"at":1436,"title":"C. PG&E Proposes to Address the Cost Assurance Requirements of the","method":"printed heading","endPage":42,"endAt":810,"startToken":10081,"endToken":19911},{"p":42,"at":810,"title":"D. PG&E Proposes Changes to the TO Tariff That Provide a Just and","method":"printed heading","endPage":43,"endAt":69,"startToken":19911,"endToken":20268},{"p":43,"at":69,"title":"VI. PG&E PROPOSES CHANGES TO THE TO TARIFF THAT PROVIDE A JUST","method":"printed heading","endPage":43,"endAt":1229,"startToken":20268,"endToken":20442},{"p":43,"at":1229,"title":"A. The CAISO and the Participating TOs Propose to Maintain the","method":"printed heading","endPage":44,"endAt":2149,"startToken":20442,"endToken":21026},{"p":44,"at":2149,"title":"B. PG&E Proposes to Include a New Process for Addressing the TCLL","method":"printed heading","endPage":45,"endAt":531,"startToken":21026,"endToken":21309},{"p":45,"at":531,"title":"C. Electrically Proximate Load","method":"printed heading","endPage":45,"endAt":2098,"startToken":21309,"endToken":21541},{"p":45,"at":2098,"title":"VII. PG&E PROPOSES A TRANSITION PERIOD CONSISTENT WITH THE","method":"printed heading","endPage":46,"endAt":1214,"startToken":21541,"endToken":21903},{"p":46,"at":1214,"title":"VIII. OTHER CHANGES TO THE TO TARIFF","method":"printed heading","endPage":47,"endAt":1152,"startToken":21903,"endToken":22435},{"p":47,"at":1152,"title":"IX. RESPONSES TO THE OSC BRIEFING QUESTIONS","method":"printed heading","endPage":47,"endAt":1395,"startToken":22435,"endToken":22478},{"p":47,"at":1395,"title":"A. Protection of Existing Commercial Arrangements","method":"printed heading","endPage":47,"endAt":2577,"startToken":22478,"endToken":22663},{"p":47,"at":2577,"title":"B. Impacts of New FILLI Interconnection Service on Transmission","method":"printed heading","endPage":48,"endAt":2066,"startToken":22663,"endToken":23024},{"p":48,"at":2066,"title":"C. Structure of Cost Recovery Agreements and Minimum Cost Recovery","method":"printed heading","endPage":49,"endAt":280,"startToken":23024,"endToken":23275},{"p":49,"at":280,"title":"D. Evaluation of Alternative Transmission Technologies","method":"printed heading","endPage":49,"endAt":1226,"startToken":23275,"endToken":23411},{"p":49,"at":1226,"title":"E. Generating Facilities Serving Electrically Proximate Large Load or","method":"printed heading","endPage":49,"endAt":2320,"startToken":23411,"endToken":23580},{"p":49,"at":2320,"title":"X. ETARIFF CHANGES","method":"printed heading","endPage":50,"endAt":69,"startToken":23580,"endToken":23683},{"p":50,"at":69,"title":"XI. EFFECTIVE DATE","method":"printed heading","endPage":50,"endAt":257,"startToken":23683,"endToken":23710},{"p":50,"at":257,"title":"XII. CORRESPONDENCE AND COMMUNICATIONS","method":"printed heading","endPage":50,"endAt":1041,"startToken":23710,"endToken":23817},{"p":50,"at":1041,"title":"XIII. ADDITIONAL INFORMATION REQUIRED BY REGULATION 35.13(b)","method":"printed heading","endPage":50,"endAt":1103,"startToken":23817,"endToken":23826},{"p":50,"at":1103,"title":"A. Contents of Filing","method":"printed heading","endPage":51,"endAt":172,"startToken":23826,"endToken":23894},{"p":51,"at":172,"title":"B. Service","method":"printed heading","endPage":51,"endAt":486,"startToken":23894,"endToken":23950},{"p":51,"at":486,"title":"C. Description of and Reason for Changes","method":"printed heading","endPage":51,"endAt":588,"startToken":23950,"endToken":23966},{"p":51,"at":588,"title":"D. Request for Waivers","method":"printed heading","endPage":51,"endAt":1115,"startToken":23966,"endToken":24050},{"p":51,"at":1115,"title":"XIV. CONCLUSION","method":"printed heading","endPage":53,"endAt":0,"startToken":24050,"endToken":24209},{"p":53,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":53,"endAt":1046,"startToken":24209,"endToken":24354}]}