{"document":{"slug":"rec-20261116-5286-7","title":"Exhibit No. GNY-202 to Arzola Testimony","issued":"2026-11-16","accession":"20261116-5286","docket":"ER27-518-000","group":"NYISO and New York transmission owners’ large-load tariff revisions","filer":"LS Power Grid New York Corporation INew York Independent System Operator, Inc.","kind":"attachment","file":"sources/filings/text/20261116-5286_010.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5286","tier":"record","parent":"rec-20261116-5286","sha256":"ad868f4c4c0add75f66003542f58f96679ac2e13d51519c99012782e29d65bcc","pages":36,"tokens":14330,"emptyPages":[],"textThemes":["cost"]},"pages":[{"page":1,"startToken":0,"endToken":149,"text":"6.10.7.2.1 LSPG-NY Formula Rate Template\nIndex\nRate Formula Template \n Utilizing FERC Form 1 Data\nAnnual Transmission Revenue Requirement\nFor the 12 months ended 12/31/____\nLS Power Grid New York Corporation I\nType of revenue requirement:  enter \"P\" if projected or \"A\" if actual:\n-\nEnter the year to which the revenue requirement relates:\n-\nAppendix A\nMain body of the Formula Rate\nAttachment 1\nDetail of the Revenue Credits\nAttachment 1a\nLarge Load CRA Revenue (Supplemental MTRC and Annual Termination Fee Remittances) by \nEligible Customer and Covered Upgrade\nAttachment 2\nMonthly Plant and Accumulated Depreciation balances\nAttachment 2a\nProject Plant Detail\nAttachment 3\nCost Support Detail\nAttachment 4\nCalculations showing the revenue requirement by Investment, including any Incentives, \nAttachment 5\nTrue-Up calculations\nAttachment 6a-6d\nDetail of the Accumulated Deferred Income Tax Balances\nAttachment 7\nDepreciation Rates\nAttachment 8\nAnnual Excess or Deficient Accumulated Deferred IncomeTaxes Worksheet"},{"page":2,"startToken":149,"endToken":342,"text":"LSPG-NY-501\nAppendix A\nPage 1 of 5\nFormula Rate - Non-Levelized \nRate Formula Template \n Utilizing FERC Form 1 Data\nAnnual Transmission Revenue Requirement\nFor the 12 months ended 12/31/____\nLS Power Grid New York Corporation I\n(1)\n(2)\n(3)\nLine\nAllocated\nNo.\nAmount\n1\nGROSS REVENUE REQUIREMENT    \n(page 3, line 79)\n12 months\n $                                 - \n \nREVENUE CREDITS \nTotal\nAllocator\n2\nTotal Revenue Credits\nAttachment 1, line 6\n                                        -   \nTP\n                        1.0000 \n                                  -   \n3\nNet Revenue Requirement\n(line 1 minus line 2)\n                                  -   \n4\nTrue-up Adjustment\n(Attachment 5, line 3, col. G)\n                                        -   \nDA\n1.00000\n                                  -   \n5\nNET ADJUSTED REVENUE REQUIREMENT\n(line 3 plus line 4)\n $                                 - \nLARGE LOAD CRA REVENUE (for NYISO billing and remittance) (Note R)\na1\nProjected Supplemental MTRC for the Rate Year - active Eligible Customers (Attachment 1a, Column 6)\n                                  -   \na2\nPrior-period true-up adjustments (Attachment 1a, Column 7)\n                                  -   \na\nSupplemental MTRC to be billed by NYISO to Eligible Customers and remitted to LSPGNY (line a1 plus line a2; Attachment 1a, line 12)\n                                  -   \nb\nAnnual Termination Fee Remittances to be made by NYISO from funds held (Attachment 1a, line 13)\n                                  -   \nc\nTotal Large Load CRA Revenue (line a plus line b; Attachment 1, line 5a; included in line 2)\n                                  -"},{"page":3,"startToken":342,"endToken":766,"text":"LSPG-NY-501\nAppendix A\nPage 2 of 5\nFormula Rate - Non-Levelized \nRate Formula Template \n \n Utilizing FERC Form 1 Data\nFor the 12 months ended 12/31/____\nLS Power Grid New York Corporation I\n(1)\n(2)\n(3)\n \n(4)\n(5)\nTransmission\nLine\nSource\nCompany Total\n                  Allocator\n(Col 3 times Col 4)\nNo.\nRATE BASE:\nGROSS PLANT IN SERVICE (Note A)\n6\n  Production\n(Attach 2, line 75)\n                                        -   \nNA\n                                 -   \n                                  -   \n7\n  Transmission \n(Attach 2, line 15)\n                                        -   \nTP\n                        1.0000 \n                                  -   \n8\n  Distribution\n(Attach 2, line 30)\n                                        -   \nNA\n                                 -   \n                                  -   \n9\n  General & Intangible\n(Attach 2, lines 45 + 60)\n                                        -   \nW/S\n                        1.0000 \n                                  -   \n10\nTOTAL GROSS PLANT (sum lines 6-9)\n                                        -   \nGP=\n                                 -   \n                                  -   \n11\nACCUMULATED DEPRECIATION & AMORTIZATION (Note A)\n12\n  Production\n(Attach 2, line 151)\n                                        -   \nNA\n                                 -   \n                                  -   \n13\n  Transmission \n(Attach 2, line 91)\n                                        -   \nTP\n                        1.0000 \n                                  -   \n14\n  Distribution\n(Attach 2, line 106)\n                                        -   \nNA\n                                 -   \n                                  -   \n15\n  General & Intangible\n(Attach 2, lines 121 + 136)\n                                        -   \nW/S\n                        1.0000 \n                                  -   \n16\nTOTAL ACCUM. DEPRECIATION (sum lines 12-15)\n                                        -   \n                                  -   \n17\nNET ACQUISITION ADJUSTMENT\n(Note B)\n18\n  Transmission\n(Attach 2, line 166)\n                                        -   \nDA\n                        1.0000 \n                                  -   \n19\nTOTAL NET ACQUISITION ADJUSTMENT\n                                        -   \n                                  -   \n20\nNET PLANT IN SERVICE\n21\n  Production\n (line 6- line 12)\n                                        -   \n                                  -   \n22\n  Transmission\n (line 7- line 13)\n                                        -   \n                                  -   \n23\n  Distribution\n (line 8- line 14)\n                                        -   \n                                  -   \n24\n  General & Intangible \n (line 9- line 15)\n                                        -   \n                                  -   \n25\nTOTAL NET PLANT (sum lines 21-24)\n                                        -   \nNP=\n                                 -   \n                                  -   \n26\nADJUSTMENTS TO RATE BASE\n27\n  ADIT                    (Attach 6a proj., line 5, Column D or Attach 6c True-up - line 5, column D)  (Note C)\n                                        -   \nTP\n                        1.0000 \n                                  -   \n28\n  Account No. 255 (enter negative) (Note D)\n(Attach 3, line 169) (Note D)\n                                        -   \nNP\n                                 -   \n                                  -   \n28a\n  Excess / Deficient Accumulated Deferred Income Taxes\n(Attach 8, line 29) (Note F)\n                                        -   \nTP\n                        1.0000 \n                                  -   \n29\n  Unamortized Lumpsum Lease Payment\nNote G\n                                        -   \nDA\n                        1.0000 \n                                  -   \n30\n  Unfunded Reserves (enter negative)\nNote H\n                                        -   \nDA\n                        1.0000 \n                                  -   \n31\n  Unamortized Regulatory Assets\n(Attach 3, line 204, col. b)  (Note I)\n                                        -   \nDA\n                        1.0000 \n                                  -   \n32\n  Unamortized Abandoned Plant\n(Attach 3, line 204, col. c)  (Note J)\n                                        -   \nDA\n                        1.0000 \n                                  -   \n33\nTOTAL ADJUSTMENTS  (sum lines 27-32)\n                                        -   \n                                  -   \n34\nLAND HELD FOR FUTURE USE\nCompany records\n                                        -   \nTP\n                        1.0000 \n                                  -   \n35\nWORKING CAPITAL  (Note K)\n \n36\n  CWC  \n(1/8 * (Line 48 less Line 47a)\n                                        -   \n                                  -   \n37\n  Materials & Supplies\n(Attach 3, line 221, column c)\n                                        -   \nTP\n                        1.0000 \n                                  -   \n38\n  Prepayments (Account 165 - Note K)\n(Attach 3, line 189, column b)\n                                        -   \nGP\n                                 -   \n                                  -   \n39\nTOTAL WORKING CAPITAL (sum lines 36-38)\n                                        -   \n                                  -   \n40\nRATE BASE  (sum lines 25, 33, 34, & 39)\n                                        -   \n                                  -   \n(If line 7>0, GP= line 10 column 5 / line 10 column 3.  If \nline 7=0, GP=0)\n(If line 19>0, NP= line 22, column 5 / line 22, column 3.  \nIf line 19=0, NP=0)"},{"page":4,"startToken":766,"endToken":1217,"text":"LSPG-NY-501\nAppendix A\nPage 3 of 5\nFormula Rate - Non-Levelized \nRate Formula Template \n \n Utilizing FERC Form 1 Data\nFor the 12 months ended 12/31/____\nLS Power Grid New York Corporation I\n(1)\n(2)\n(3)\n \n(4)\n (5) \n Transmission \nSource\nCompany Total\n                  Allocator\n (Col 3 times Col 4) \n41\nO&M\n42\n  Transmission \n321.112.b\n                                        -   \nTP=\n                        1.0000 \n                                  -   \n43\n     Less Account 565\n321.96.b\n                                        -   \nTP=\n                        1.0000 \n                                  -   \n44\n  A&G\n323.197.b\n                                        -   \nW/S\n                        1.0000 \n                                  -   \n45\n     Less EPRI & Reg. Comm. Exp. & Other  Ad.  \nNote L, company records\n                                        -   \nDA\n                        1.0000 \n                                  -   \n46\n     Plus Transmission Related Reg. Comm.  Exp.  \nNote L, company records\n                                        -   \nTP=\n                        1.0000 \n                                  -   \n47\n    Less Account 566\n321.97.b\n                                        -   \nDA\n                        1.0000 \n                                  -   \n47a\n    Amortization of Regulatory Assets\ncompany records\n                                        -   \nDA\n                        1.0000 \n                                  -   \n47b\n    Account 566 excluding amort. of Reg Assets\n(line 47 less line 47a)\n                                        -   \nDA\n                        1.0000 \n                                  -   \n48\nTOTAL O&M   (sum lines 42, 44, 46, 47a, 47b less lines 43 & 45, 47) (Note L)\n                                        -   \n                                  -   \n49\nDEPRECIATION EXPENSE \n50\n  Transmission \n336.7.f (Note A)\n                                        -   \nTP\n                        1.0000 \n                                  -   \n51\n  General and Intangible\n336.1.f + 336.10.f (Note A)\n                                        -   \nW/S\n                        1.0000 \n                                  -   \n52\n  Amortization of Abandoned Plant\n(Attach 3, line 205, column c) (Note J)\n                                        -   \nDA\n                        1.0000 \n                                  -   \n53\n  Amortization of Acquisition Adjustment\n(Attach 2, line 166)\n                                        -   \nDA\n                        1.0000 \n                                  -   \n54\nTOTAL DEPRECIATION (Sum lines 50-52)\n                                        -   \n                                  -   \n55\nTAXES OTHER THAN INCOME TAXES  (Note M)\n56\n  LABOR RELATED\n57\n          Payroll\n263.l\n                                        -   \nW/S\n                        1.0000 \n                                  -   \n58\n          Highway and vehicle\n263.l\n                                        -   \nW/S\n                        1.0000 \n                                  -   \n59\n  PLANT RELATED\n \n60\n         Property\n263.l\n                                        -   \nGP\n                                 -   \n                                  -   \n61\n         Gross Receipts\n263.l\n                                        -   \nGP\n                                 -   \n                                  -   \n62\n         Other\n263.l\n                                        -   \nGP\n                                 -   \n                                  -   \n63\nTOTAL OTHER TAXES  (sum lines 57-62)\n                                        -   \n                                  -   \n64\nINCOME TAXES          \n65\n     T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p))} =\n (Note E)\n0.00%\n66\n     CIT=(T/1-T) * (1-(WCLTD/R)) =\n0.00%\n67\n       where WCLTD=(line 96) and R= (line 99)\n68\n       and FIT, SIT, p, & n are as given in footnote E.\n69\n      1 / (1 - T)  = (T from line 65)\n                                        -   \n70\nIncome Tax Calculation = line 66 * line 76 \n                                        -   \n                                  -   \n71\nInvestment Tax Credit Amortization Adjustment\n(Attachment 3, line 174)  (Note D)\n                                        -   \nNP\n                                 -   \n                                  -   \n72\nPermanent Differences Tax Adjustment\n(Attach 3, line 207 * line 65)\n                                        -   \nNP\n                                 -   \n                                  -   \n73\nExcess/Deficient Deferred Taxes Adjustment\nAttach 8, line 58 (proj.), line 90 (actual)  Note F\n                                        -   \nNP\n                                 -   \n                                  -   \n74\nTotal Income Taxes\n(Sum lines 72 to 73)\n                                        -   \n \n \n                                  -   \n75\nRETURN \n76\n [ Rate Base (line 40) * Rate of Return (line 99)]\n                                        -   \n                                  -   \n77\nRev Requirement before Incentive Projects  (sum lines 48, 54, 63, 74, 76)\n                                        -   \n                                  -   \n78\nIncentive Return and Income Tax and Competitive Bid Concessions for Projects \n                                        -   \nDA\n                        1.0000 \n                                  -   \n(Attach 4, line 67, cols. h, j & less p)\n79\nTotal Revenue Requirement  (sum lines 77 & 78)\n                                        -   \n                                  -"},{"page":5,"startToken":1217,"endToken":1552,"text":"LSPG-NY-501\nAppendix A\nPage 4 of 5\nFormula Rate - Non-Levelized \nRate Formula Template\n Utilizing FERC Form 1 Data\nFor the 12 months ended 12/31/____\nLS Power Grid New York Corporation I\nSUPPORTING CALCULATIONS AND NOTES\n80\nTRANSMISSION PLANT INCLUDED IN ISO RATES\n81\nTotal transmission plant    (line 7, column 3)\n                                  -   \n82\nLess transmission plant excluded from ISO rates       (Note N)\n                                  -   \n83\nLess transmission plant included in OATT Ancillary Services    (Note N)\n                                  -   \n84\nTransmission plant included in ISO rates  (line 81 less lines 82 & 83)\n                                  -   \n85\nPercentage of transmission plant included in ISO Rates (line 84 divided by line 81) [If line 81 equal zero, enter 1)\nTP=\n                         1.0000 \n86\nWAGES & SALARY ALLOCATOR   (W&S)\n87\nForm 1 Reference\n$\nTP\nAllocation\n88\n  Production\n354.20.b\n                                        -                                   -   \n                                 -   \n89\n  Transmission\n354.21.b\n                                        -                                1.00 \n                                 -   \n90\n  Distribution\n354.23.b\n                                        -                                   -   \n                                 -   \nW&S Allocator\n91\n  Other\n354.24,25,26.b\n                                        -                                   -   \n                                 -   \n($ / Allocation)\n92\n  Total  (sum lines 88-91) [TP equals 1 if there are no wages & salaries]\n                                        -   \n                                 -   \n=\n                         1.0000 \n=\nWS\n93\nRETURN (R)      (Notes O and P)\n94\n95\n$\n%\nCost\nWeighted\n96\n  Long Term Debt \n(Attach 3, line 229) (Note O)\n                                 -   \n100.00%\n0.00%\n0.00% =WCLTD\n97\n  Preferred Stock  \n(Attach 3, line 230) (Note O)\n                                 -   \n0.00%\n0.00%\n0.00%\n98\n  Common Stock \n(Attach 3, line 231) (Note O, Note P)\n                                 -   \n0.00%\n0.00%\n0.00%\n99\nTotal  (sum lines 96-98)\n                                 -    \n0.00% =R\nDevelopment of Base Carrying charge and Summary of Incentive and Non-Incentive Investments\n(a)\n(b)\n(c)\nSource of Total Column\nTotal\n100\nNet Transmission Plant in Service\n(Line 22 and Transmission CIACs)\n                                 -   \n                                  -   \n                               -   \n101\nUnamortized Abandoned Plant\n(Line 32)\n                                 -   \n                                  -   \n                               -   \n102\nProject Specific Regulatory Assets\n(Line 31)\n                                 -   \n                                  -   \n                               -   \n103\nDevelopment of Base Carrying charge and Summary of Incentive and Non-Incentive Investments\n                               -   \n104\nReturn and Taxes\n(Lines 74 & 76)\n                               -   \n105\nTotal Revenue Credits\n                               -   \n106\nBase Carrying Charge (used in Attach 4, Line 65)\n(Line 104 - Line 105)/ Line 103\n0.00%\n Non-incentive \nInvestments from \nAttachment 4 (Note \nQ) \nIncentive Investments \nfrom Attachment 4 \n(Note Q)"},{"page":6,"startToken":1552,"endToken":2845,"text":"LSPG-NY-501\nAppendix A\nPage 5 of 5\n                SUPPORTING CALCULATIONS AND NOTES\nFormula Rate - Non-Levelized \nRate Formula Template \n \n Utilizing FERC Form 1 Data\nFor the 12 months ended 12/31/____\nLS Power Grid New York Corporation I\nGeneral Note:  References to pages in this formulary rate are indicated as:  (page#, line#, col.#)\n                      References to data from FERC Form 1 are indicated as:   #.y.x  (page, line, column)\nNote\nLetter\nA\nBalances exclude Asset Retirement Costs.\nB\nNo Acquisition Adjustment will be recovered until a filing requesting recovery is submitted to and approved by FERC under FPA Section 205.\nC\n  associated with asset or liability accounts excluded from rate base do not affect rate base, such as ADIT related to asset retirement obligations and certain tax-related regulatory assets or \n  liabilities.  To the extent that the normalization requirements apply to ADIT activity in the projected net revenue requirement calculation or the true-up adjustment calculation, the ADIT \n  amounts are computed in accordance with the proration formula of Treasury regulation Section 1.167(l)-1(h)(6) with averaging in accordance with IRC Section 168(i)(9)(B).  The remaining\n  ADIT activity are averaged.  Work papers supporting the ADIT calculations will be posted with each projected net revenue requirement and/or Annual True-Up and included in the annual \n  Informational Filing submitted to the Commission.\nD\nInvestment tax credit (ITC) is recorded in accordance with the deferral method of accounting and any normalization requirements that relate to the eligibility to claim the credit or the \n  Credit (266.8.f) multiplied by the applicable tax gross-up factor.\nE\nThe composite income tax rate (T) applicable to each Rate Year (including both Annual Projections and True-Up Adjustments) is based on the Federal income tax rate (FIT),\n  the State income tax rate (SIT) and the percentage of federal income tax deductible for state income tax purposes (P).  If the utility is taxed in more than one state, \n  it must attach a work paper showing the name of each state and how the blended or composite SIT was computed.  \n \n         Inputs Required:\nFederal income tax rate (FIT) =\n0.00%\nComposite state income tax rate (SIT) =\n0.00%   (Attachment 3)\nPercent of federal income tax deductible for state purposes (P) =\n0.00%\n  For each Rate Year (including both Annual Projections and True-Up Adjustments) the statutory income tax rates utilized in the Formula Rate shall reflect the weighted average rates \n  181/365 and 184/365, respectively, for a non-leap year.\nF\nUpon enactment of changes in tax law, ADIT balances are re-measured and adjusted in the Company’s books of account, resulting in excess or deficient accumulated deferred income tax \n  assets and liabilities.  Such excess or deficient ADIT attributable to assets or liabilities reflected in ISO rates and subsequent recoverable or refundable amortization will be based upon tax \n  records and be calculated and recorded in accordance with ASC 740 and any applicable normalization requirements of the taxing jurisdiction.  For each re-measurement of deferred taxes,\n  the amounts entered as Adjustments to Rate Base or a component of Income Taxes will be supported by work papers providing the balance for each taxing jurisdiction at the beginning \n  and end of the year, amortization for the year and any other information required to support compliance with any applicable normalization requirements. \nG\nIn the event that transmission assets or right of ways involve a lumpsum upfront payment under a lease that qualifies as a capital lease, it will be amortized over the life of the lease to Account 567 \n  and the unamortized balance will be included here. In the event such a lease involves monthly or annual payments, the payments will be booked to Account 567.\nH\nUnfunded Reserves are customer contributed capital authorized by a regulatory agency.  Balances, if any, will be supported by a workpaper.  \n  No amounts shall be credited to accounts 228.1 through 228.4 unless authorized by a regulatory authority or authorities to be collected in a utility’s rates.\nI\nRecovery of Regulatory Assets must be authorized by the Commission.\nJ\nUnamortized Abandoned Plant and Amortization of Abandoned Plant will be zero until the Commission accepts or approves recovery of the cost of Abandoned Plant.\nK\nCash Working Capital assigned to transmission is transmission-allocated O&M minus the amortization of any Regulatory Asset, divided by eight.\n  Prepayments are the electric related prepayments booked to Account No. 165 and reported on Pages 110-111 line 57 in the Form 1.\nL\nLine 45 removes all EEI and EPRI research, development and demonstration expenses.\nLine 46 reflects all Regulatory Commission Expenses directly related to transmission service, ISO filings, or transmission siting itemized at 351.h\nLine 42 or Line 44 and thus Line 48 shall include any NYISO charges other than penalties, including but not limited to administrative costs.  \nM\nIncludes only FICA, unemployment, highway, property, gross receipts, and other assessments charged in the current year.\nN\nRemoves dollar amount of transmission plant included in the development of OATT ancillary services rates and generation\n  step-up facilities, which are deemed to included in OATT ancillary services.  For these purposes, generation step-up\n  facilities are those facilities at a generator substation on which there is no through-flow when the generator is shut down.\nO\nIn accordance with the Settlement Agreement in Docket No. ER 20-716 approved June 17, 2021, the Base Return on Equity shall be 9.65% and no change in ROE may be made absent a filing with FERC under FPA Section 205 or 206.\nP\nA hypothetical capital structure of 47% debt and 53% equity will be used until the entire Marcy to New Scotland 345 kV Upgrade Project is placed in-service.  After all facilities of the Marcy to New Scotland 345 kV\n  Upgrade Project are placed in- service, the lesser of a 52% equity ratio or the actual equity ratio will be used.   \nQ\nNon-incentive investments are investments without ROE incentives and incentive investments are investments with ROE incentives\nR\nThe balances in Accounts 190, 281, 282 and 283 are allocated to transmission plant included in ISO rates based on company accounting records.  Accumulated deferred income tax amounts \n  recapture of the credit.  The revenue requirement impact of any ITC amortization permitted to reduce income tax expense is determined as the amount of the Amortized Investment Tax \n  actually in effect during the Rate Year.  For example, if the statutory tax rate is 10% from January 1 through June 30, and 5% from July 1 through December 31, such rates would be weighted \nLine 45 removes EPRI Annual Membership Dues listed in Form 1 at 353.f, any EPRI Lobbying expenses included in line 42 of the template and all Regulatory Commission Expenses itemized at 351.h.\nLine 45 removes all advertising included in Account 930.1, except safety, education or out-reach related advertising.\nLines a1 through c are completed in the Annual Projection only. Line a is the projected Supplemental MTRC for the Rate Year (line a1) plus prior-period true-up adjustments (line a2); \nNYISO bills line a to active Eligible Customers in equal monthly installments during the Rate Year and remits the amounts it collects to LSPGNY. Line b is the Annual Termination Fee \nRemittances NYISO makes to LSPGNY during the Rate Year from funds it holds. Differences between the Supplemental MTRC billed and the Supplemental MTRC based on actual \nQualifying Transmission Revenues are trued up, without interest, by Eligible Customer and Covered Upgrade on Attachment 5 and included in line a2 of a subsequent Annual Projection. In \nthe Annual Update, lines a1 through c show zero, and Large Load CRA Revenue is the Actual Large Load CRA Revenue received during the Rate Year, recorded on Attachment 1, line 5a; \nany difference from the projected amount, including a billed amount that is not received, is reflected in the True-Up Adjustment."},{"page":7,"startToken":2845,"endToken":3444,"text":"Attachment 1 - Revenue Credit Workpaper* \nLS Power Grid New York Corporation I\nAccount 454 - Rent from Electric Property  (300.19.b)\nNotes 1 & 3\n1 Rent from FERC Form No. 1\n                           -   \nAccount 456 (including 456.1) (300.21.b and 300.22.b)\nNotes 1 & 3\n2 Other Electric Revenues (Note 2)\n                           -   \n3 Professional Services \n                           -   \n4 Revenues from Directly Assigned Transmission Facility Charges (Note 2)\n                           -   \n5 Rent or Attachment Fees associated with Transmission Facilities \n                           -   \n5a Large Load CRA Revenue - Supplemental MTRC and Annual Termination Fee Remittances (Note 4)\n                           -   \n6 Total Revenue Credits\nSum lines 2-5a + line 1\n                           -   \nNote 1\nNote 2\nIf the facilities associated with the revenues are not included in the formula, the revenue is shown below, but not included in the total above. \nNote 3\nAll Account 454, 456, and 456.1 Revenues must be itemized below and tie to FERC Form No. 1 cites set forth below.\nNote 4\nLine No.\n1\nAccounts 456 and 456.1 (300.21.b plus 300.22.b)\nTOTAL\nNY-ISO\nOther 1\nOther 2\n1a\n-\n                                                                               -                              -                         -                        -   \n…\n                                                                               -                              -                         -                        -   \n1x\n                                                                               -                              -                         -                        -   \n2\nLarge Load CRA Revenue recorded in Account 456 (Note 4)\n                                                                               -                              -                         -                        -   \n3\nTotal\n                                                                               -                              -                         -                        -   \n4\nLess:\n5\n     Revenue for Demands in Divisor \n                                                                               -                              -                         -                        -   \n6\nSub Total Revenue Credit\n                                                                               -                              -                         -                        -   \n7\nPrior Period Adjustments\n                                                                               -                              -                         -                        -   \n8\nTotal  (must tie to 300.21.b plus 300.22.b)\n                                                                               -                              -                         -                        -   \n9\nAccount 454 (300.19.b)\n $ \n9a\n-\n                                                                               -   \n9b\n                                                                               -   \n9c\n                                                                               -   \n9d\n                                                                               -   \n9e\n                                                                               -   \n9f\n                                                                               -   \n9g\n                                                                               -   \n…\n9x\n                                                                               -   \n10\nTotal  (must tie to 300.19.b)\n                                                                               -   \nAll revenues booked to Account 454 that are derived from cost items classified as transmission-related will be included as a revenue credit.  All revenues booked to Account 456 (includes 456.1) that are \nderived from cost items classified as transmission-related, and are not derived from rates under this transmission formula rate will be included as a revenue credit.   Work papers will be included to properly \nclassify revenues booked to these accounts to the transmission function.  A breakdown of all Account 454 revenues by subaccount will be provided below, and will be used to derive the proper calculation \nof revenue credits.  A breakdown of all Account 456 revenues by subaccount and customer will be provided and tabulated below, and will be used to develop the proper calculation of revenue credits.  \nLine 5a is Large Load CRA Revenue from Attachment 1a. In an Annual Projection, it is the Projected Large Load CRA Revenue: the Supplemental MTRC NYISO bills to active Eligible Customers, including \nprior-period true-up adjustments, plus the Annual Termination Fee Remittances NYISO makes for terminated Eligible Customers (Attachment 1a, Column 8 total). In an Annual Update, it is the Actual Large \nLoad CRA Revenue received by LSPGNY during the Rate Year (Attachment 1a, line 34): Supplemental MTRC payments collected and remitted by NYISO, Applied Security Proceeds remitted by NYISO, \namounts recovered directly from an Eligible Customer, and Annual Termination Fee Remittances. A billed amount that is not received is not credited, and the resulting difference from the projected credit is \nreflected in the True-Up Adjustment; a later receipt is credited in the Rate Year in which it is received, and no amount is credited more than once. Line 2 below is the Large Load CRA Revenue recorded in \nAccount 456; any difference from Line 5a is reconciled in the work papers required by Section 3.C.11 of the Protocols. Differences between the projected Supplemental MTRC and the amount based on \nactual Qualifying Transmission Revenues are trued up, without interest, for each Eligible Customer and Covered Upgrade on Attachment 5, Lines 14-23 (Supplemental MTRC True-Up by Eligible Customer \nand Covered Upgrade). Qualifying Transmission Revenues are not credited on Line 5a."},{"page":8,"startToken":3444,"endToken":4425,"text":"Attachment 1a - Supplemental MTRC\nLS Power Grid New York Corporation I\nRate Year\n-\nProjected Large Load CRA Revenue for the Rate Year (Col. 8 total)\n                                                  -   \nLine\nEligible Customer\nAnnual MTRC (Note A)\n1\n2\n3\n4\n5\n6\n7\n8\n1\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n2\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n3\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n4\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n5\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n6\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n7\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n8\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n9\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n10\n                                                  -                                            -                                                  -                                                  -                                                  -                                                  -   \n11\nTotal\n                                                  -                                            -                                                  -                                                  -                                                  -   \n12\nSupplemental MTRC billed and remitted by NYISO - active Eligible Customers\n                                               -   \n13\nAnnual Termination Fee Remittances by NYISO - terminated Eligible Customers\n                                               -   \nProjected Qualifying Transmission Revenue Workpaper\nLine\nEligible Customer\nCovered Upgrade\nForecast Load (MW)\nBilling Hours\n14\n                                                      -   \n15\n                                                      -   \n16\n                                                      -   \n17\n                                                      -   \n18\n                                                      -   \n19\n                                                      -   \n20\n                                                      -   \n21\n                                                      -   \n22\n                                                      -   \n23\n                                                      -   \nActual Large Load CRA Revenue Received - Annual Update (Note E)\nLine\nEligible Customer\nCovered Upgrade\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n24\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n25\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n26\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n27\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n28\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n29\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n30\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n31\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n32\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n33\n                                        -   \n                                                          -                                                  -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n                                                      -   \n34\nTotal\n                                  -                                                     -                                            -                                                  -                                                  -                                                  -                                                  -                                                  -   \nNotes\nA\nColumn 5 shows the Annual MTRC for each Eligible Customer and Covered Upgrade under its CRA. Use the applicable partial-year amount.\nB\nC\nD\nE\nThis worksheet calculates, by Eligible Customer and Covered Upgrade, Large Load CRA Revenue for the Rate Year. The Annual Minimum Transmission Revenue Contribution (\"Annual MTRC\") is the annual minimum transmission revenue an Eligible Customer commits to for a Covered Upgrade \nunder its CRA; it is determined under the CRA and entered in this worksheet. The Supplemental MTRC is the amount by which the Annual MTRC exceeds Qualifying Transmission Revenues. Projected Large Load CRA Revenue is the Supplemental MTRC NYISO bills to active Eligible Customers, \nincluding prior-period true-up adjustments, plus the Annual Termination Fee Remittances NYISO makes for terminated Eligible Customers (Lines 1-13). Actual Large Load CRA Revenue is the amount LSPGNY receives during the Rate Year (Lines 24-34). In the Annual Projection, this worksheet uses \nprojected Qualifying Transmission Revenues; in the Annual Update, it uses actual Qualifying Transmission Revenues to determine the actual Supplemental MTRC trued up on Attachment 5 (Notes B-D) and records the Actual Large Load CRA Revenue (Note E). Eligible Customer, CRA, Covered \nUpgrade, Annual MTRC, Supplemental MTRC, Qualifying Transmission Revenues, Annual Termination Fee Remittance, Applied Security Proceeds, Large Load CRA Revenue, Projected Large Load CRA Revenue, and Actual Large Load CRA Revenue have the meanings set forth in, or incorporated \nby reference in the Formula Rate Implementation Protocols\nCovered Upgrade (Att \n4, Col. (a))\nStatus (Active / \nTerminated)\nProjected Qualifying \nTransmission Revenues (Lines \n14-23)\nProjected Supplemental \nMTRC or Annual Termination \nFee Remittance (Note C)\nPrior-Period True-Up \nAdjustment (Note D)\nProjected Supplemental \nMTRC and Annual \nTermination Fee Remittances \n(Col. 6 + Col. 7)\nScheduled Annual \nTermination Fee Remittance \n— CRA Schedule 5\nTransmission Rate \n($/MWh)\nProjected Qualifying \nTransmission Revenues ($)\nOpening Unpaid \nSupplemental MTRC\nNet Supplemental MTRC Billed \n(including prior-period \nadjustments; Note E)\nCustomer Payments \nCollected and Remitted \nby NYISO\nSecurity Proceeds Received \nfrom NYISO and Applied to \nSupplemental MTRC\nDirect Recoveries Received \nand Applied to Supplemental \nMTRC\nAnnual Termination Fee \nRemittances Received\nActual Large Load CRA \nRevenue (c)+(d)+(e)+(f)\nClosing Unpaid Supplemental \nMTRC (a)+(b)-(c)-(d)-(e)\nNYISO bills each active Eligible Customer its projected Supplemental MTRC (Column 8) in equal monthly installments during the Rate Year. In the Annual Update, Column 6 and line 12 show the actual Supplemental MTRC based on actual Qualifying Transmission Revenues, and the \nSupplemental MTRC billed is trued up to that amount, without interest, on Attachment 5, Lines 14-23 (Supplemental MTRC True-Up by Eligible Customer and Covered Upgrade). That customer-level true-up is separate from the credit on Attachment 1, Line 5a, which in the Annual Update is \nthe Actual Large Load CRA Revenue on line 34 (Note E). When an Eligible Customer terminates its CRA, NYISO holds the Termination Fee and makes an Annual Termination Fee Remittance to LSPGNY each year under the CRA.\nFor an active row, Column 6 equals Column 5 less Column 4, not less than zero; each Covered Upgrade is measured separately. For a terminated row, Column 6 equals the scheduled Annual Termination Fee Remittance entered in Column K from the Termination Fee Remittance \nWorksheet in Schedule 5 of the applicable CRA. That scheduled amount reflects applicable partial-year proration, is limited to the available Termination Fee Balance, and includes any residual balance and actual earnings required to be remitted with the final installment. Actual Annual \nTermination Fee Remittances received are recorded separately on Lines 24–34.\nColumn 7 is the true-up adjustment for the Eligible Customer and Covered Upgrade from Attachment 5, Lines 14-23 (Supplemental MTRC True-Up by Eligible Customer and Covered Upgrade). True-up adjustments for terminated Eligible Customers are addressed under the CRA. In the \nAnnual Update, Column 7 is zero.\nLines 24-34 are completed in the Annual Update only. Record Supplemental MTRC billed, including prior-period adjustments, and amounts LSPGNY actually receives during the Rate Year for current- or prior-year bills: customer payments collected and remitted by NYISO (c); Security \nproceeds received from NYISO and applied to Supplemental MTRC obligations (d); direct recoveries received and applied to Supplemental MTRC obligations (e); and Annual Termination Fee Remittances received (f). Exclude construction-cost recoveries, unapplied Security, and the full \nTermination Fee held by NYISO; only annual termination remittances enter (f). Enter refunds of previously credited receipts as negative amounts in the original receipt category, supported by a receipt/refund workpaper. A Supplemental MTRC refund restores an unpaid balance only to the \nextent the underlying obligation remains due. If a refund corrects an overbilling, also enter the corresponding signed billing correction in (b); reconcile gross bills, corrections, and net billed amounts in the workpaper. Refunds in (f) reverse the termination-remittance credit without changing \nunpaid Supplemental MTRC. Column (g) credits net receipts on Attachment 1, Line 5a. Unreceived bills are not credited; differences from projected credits flow through the ordinary true-up with applicable interest. Later receipts are credited in the year received, once. Carry closing unpaid \nSupplemental MTRC (h) to opening balance (a) in the next Annual Update. Expected collections of prior-year unpaid amounts are excluded from Projected Large Load CRA Revenue."},{"page":9,"startToken":4425,"endToken":4596,"text":"Attachment 2 - Cost Support\nLS Power Grid New York Corporation I\nPlant in Service Worksheet (Note 2)\n1\nCalculation of Transmission  Plant In Service\nSource (Less ARO, see Note 1)\n Year \nBalance\n2\nDecember\np206.58.b\n-\n                                               -   \n3\nJanuary\ncompany records\n-\n                                               -   \n4\nFebruary\ncompany records\n-\n                                               -   \n5\nMarch\ncompany records\n-\n                                               -   \n6\nApril\ncompany records\n-\n                                               -   \n7\nMay\ncompany records\n-\n                                               -   \n8\nJune \ncompany records\n-\n                                               -   \n9\nJuly\ncompany records\n-\n                                               -   \n10\nAugust\ncompany records\n-\n                                               -   \n11\nSeptember\ncompany records\n-\n                                               -   \n12\nOctober \ncompany records\n-\n                                               -   \n13\nNovember\ncompany records\n-\n                                               -   \n14\nDecember\np207.58.g\n-\n                                               -   \n15\nTransmission Plant In Service\n(sum lines 2-14) /13\n                                               -   \n16\nCalculation of Distribution Plant In Service\nSource (Less ARO, see Note 1)\n17\nDecember\np206.75.b\n-\n                                               -   \n18\nJanuary\ncompany records\n-\n                                               -   \n19\nFebruary\ncompany records\n-\n                                               -   \n20\nMarch\ncompany records\n-\n                                               -   \n21\nApril\ncompany records\n-\n                                               -   \n22\nMay\ncompany records\n-\n                                               -   \n23\nJune \ncompany records\n-\n                                               -   \n24\nJuly\ncompany records\n-\n                                               -   \n25\nAugust\ncompany records\n-\n                                               -   \n26\nSeptember\ncompany records\n-\n                                               -   \n27\nOctober\ncompany records\n-\n                                               -   \n28\nNovember\ncompany records\n-\n                                               -   \n29\nDecember\np207.75.g\n-\n                                               -   \n30\nDistribution Plant In Service\n(sum lines 17-29) /13\n                                               -"},{"page":10,"startToken":4596,"endToken":4835,"text":"31\nCalculation of Intangible Plant In Service\nSource (Less ARO, see Note 1)\n32\nDecember\np204.5.b\n-\n                                               -   \n33\nJanuary\ncompany records\n-\n                                               -   \n34\nFebruary\ncompany records\n-\n                                               -   \n35\nMarch\ncompany records\n-\n                                               -   \n36\nApril\ncompany records\n-\n                                               -   \n37\nMay\ncompany records\n-\n                                               -   \n38\nJune \ncompany records\n-\n                                               -   \n39\nJuly\ncompany records\n-\n                                               -   \n40\nAugust\ncompany records\n-\n                                               -   \n41\nSeptember\ncompany records\n-\n                                               -   \n42\nOctober\ncompany records\n-\n                                               -   \n43\nNovember\ncompany records\n-\n                                               -   \n44\nDecember\np205.5.g\n-\n                                               -   \n45\nIntangible Plant In Service\n(sum lines 32-44) /13\n                                               -   \n46\nCalculation of General Plant In Service\nSource (Less ARO, see Note 1)\n47\nDecember\np206.99.b\n-\n                                               -   \n48\nJanuary\ncompany records\n-\n                                               -   \n49\nFebruary\ncompany records\n-\n                                               -   \n50\nMarch\ncompany records\n-\n                                               -   \n51\nApril\ncompany records\n-\n                                               -   \n52\nMay\ncompany records\n-\n                                               -   \n53\nJune \ncompany records\n-\n                                               -   \n54\nJuly\ncompany records\n-\n                                               -   \n55\nAugust\ncompany records\n-\n                                               -   \n56\nSeptember\ncompany records\n-\n                                               -   \n57\nOctober\ncompany records\n-\n                                               -   \n58\nNovember\ncompany records\n-\n                                               -   \n59\nDecember\np207.99.g\n-\n                                               -   \n60\nGeneral Plant In Service\n(sum lines 47-59) /13\n                                               -   \n61\nCalculation of Production Plant In Service\nSource (Less ARO, see Note 1)\n62\nDecember\np204.46b\n-\n                                               -   \n63\nJanuary\ncompany records\n-\n                                               -   \n64\nFebruary\ncompany records\n-\n                                               -   \n65\nMarch\ncompany records\n-\n                                               -   \n66\nApril\ncompany records\n-\n                                               -   \n67\nMay\ncompany records\n-\n                                               -   \n68\nJune \ncompany records\n-\n                                               -   \n69\nJuly\ncompany records\n-\n                                               -   \n70\nAugust\ncompany records\n-\n                                               -   \n71\nSeptember\ncompany records\n-\n                                               -   \n72\nOctober\ncompany records\n-\n                                               -   \n73\nNovember\ncompany records\n-\n                                               -   \n74\nDecember\np205.46.g\n-\n                                               -   \n75\nProduction Plant In Service\n(sum lines 62-74) /13\n                                               -   \n76\nTotal Plant In Service\n(sum lines 15, 30, 45, 60, & 75)\n                                               -"},{"page":11,"startToken":4835,"endToken":5004,"text":"Accumulated Depreciation Worksheet\nAppendix A Line #s, Descriptions, Notes, Form 1 Page #s and Instructions\n77\nCalculation of Transmission Accumulated Depreciation\nSource (Less ARO, see Note 1)\n Year \nBalance\n78\nDecember\nPrior year p219.25.c\n-\n                                               -   \n79\nJanuary\ncompany records\n-\n                                               -   \n80\nFebruary\ncompany records\n-\n                                               -   \n81\nMarch\ncompany records\n-\n                                               -   \n82\nApril\ncompany records\n-\n                                               -   \n83\nMay\ncompany records\n-\n                                               -   \n84\nJune \ncompany records\n-\n                                               -   \n85\nJuly\ncompany records\n-\n                                               -   \n86\nAugust\ncompany records\n-\n                                               -   \n87\nSeptember\ncompany records\n-\n                                               -   \n88\nOctober\ncompany records\n-\n                                               -   \n89\nNovember\ncompany records\n-\n                                               -   \n90\nDecember\np219.25.c\n-\n                                               -   \n91\nTransmission Accumulated Depreciation\n(sum lines 78-90) /13\n                                               -   \n92\nCalculation of Distribution Accumulated Depreciation\nSource (Less ARO, see Note 1)\n93\nDecember\nPrior year p219.26.c\n-\n                                               -   \n94\nJanuary\ncompany records\n-\n                                               -   \n95\nFebruary\ncompany records\n-\n                                               -   \n96\nMarch\ncompany records\n-\n                                               -   \n97\nApril\ncompany records\n-\n                                               -   \n98\nMay\ncompany records\n-\n                                               -   \n99\nJune \ncompany records\n-\n                                               -   \n100\nJuly\ncompany records\n-\n                                               -   \n101\nAugust\ncompany records\n-\n                                               -   \n102\nSeptember\ncompany records\n-\n                                               -   \n103\nOctober \ncompany records\n-\n                                               -   \n104\nNovember\ncompany records\n-\n                                               -   \n105\nDecember\np219.26.c\n-\n                                               -   \n106\nDistribution Accumulated Depreciation\n(sum lines 93-105) /13\n                                               -"},{"page":12,"startToken":5004,"endToken":5251,"text":"107\nCalculation of Intangible Accumulated Amortization\nSource (Less ARO, see Note 1)\n108\nDecember\nPrior year p200.21.c\n-\n                                               -   \n109\nJanuary\ncompany records\n-\n                                               -   \n110\nFebruary\ncompany records\n-\n                                               -   \n111\nMarch\ncompany records\n-\n                                               -   \n112\nApril\ncompany records\n-\n                                               -   \n113\nMay\ncompany records\n-\n                                               -   \n114\nJune \ncompany records\n-\n                                               -   \n115\nJuly\ncompany records\n-\n                                               -   \n116\nAugust\ncompany records\n-\n                                               -   \n117\nSeptember\ncompany records\n-\n                                               -   \n118\nOctober \ncompany records\n-\n                                               -   \n119\nNovember\ncompany records\n-\n                                               -   \n120\nDecember\np200.21.c\n-\n                                               -   \n121\nAccumulated Intangible Amortization\n(sum lines 108-120) /13\n                                               -   \n122\nCalculation of General Accumulated Depreciation\nSource (Less ARO, see Note 1)\n123\nDecember\nPrior year p219.28.c\n-\n                                               -   \n124\nJanuary\ncompany records\n-\n                                               -   \n125\nFebruary\ncompany records\n-\n                                               -   \n126\nMarch\ncompany records\n-\n                                               -   \n127\nApril\ncompany records\n-\n                                               -   \n128\nMay\ncompany records\n-\n                                               -   \n129\nJune \ncompany records\n-\n                                               -   \n130\nJuly\ncompany records\n-\n                                               -   \n131\nAugust\ncompany records\n-\n                                               -   \n132\nSeptember\ncompany records\n-\n                                               -   \n133\nOctober \ncompany records\n-\n                                               -   \n134\nNovember\ncompany records\n-\n                                               -   \n135\nDecember\np219.28.c\n-\n                                               -   \n136\nAccumulated General Depreciation\n(sum lines 123-135) /13\n                                               -   \n137\nCalculation of Production Accumulated Depreciation\nSource (Less ARO, see Note 1)\n138\nDecember\np219.20.c to 24.c (prior year)\n-\n                                               -   \n139\nJanuary\ncompany records\n-\n                                               -   \n140\nFebruary\ncompany records\n-\n                                               -   \n141\nMarch\ncompany records\n-\n                                               -   \n142\nApril\ncompany records\n-\n                                               -   \n143\nMay\ncompany records\n-\n                                               -   \n144\nJune \ncompany records\n-\n                                               -   \n145\nJuly\ncompany records\n-\n                                               -   \n146\nAugust\ncompany records\n-\n                                               -   \n147\nSeptember\ncompany records\n-\n                                               -   \n148\nOctober \ncompany records\n-\n                                               -   \n149\nNovember\ncompany records\n-\n                                               -   \n150\nDecember\np219.20.c to 24.c\n-\n                                               -   \n151\nProduction Accumulated Depreciation\n(sum lines 138-150) /13\n                                               -   \n152\nTotal Accumulated Depreciation and Amortization\n(sum lines 91, 106, 121, 136, & 151)\n                                               -"},{"page":13,"startToken":5251,"endToken":5370,"text":"Acquisition Adjustment Worksheet\nFERC 115 -\nFERC 406 -\nCalculation of Transmission Acquisition Adj.\nSource\n Year \nFERC 114 - Balance\nAccumulated Amortization\nNet Balance\nAmortization Exp\n153\nDecember\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n154\nJanuary\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n155\nFebruary\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n156\nMarch\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n157\nApril\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n158\nMay\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n159\nJune \ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n160\nJuly\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n161\nAugust\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n162\nSeptember\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n163\nOctober \ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n164\nNovember\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n165\nDecember\ncompany records\n-\n                                               -                                                  -                                                  -                                    -   \n166\nTransmission Acquisition Adj.\n(sum lines 153-165) /13\n                                               -                                                  -                                                  -                                    -   \nNote\n1\nBalances exclude Asset Retirement Costs.\n2\nFor the initial rate year, capital balances that are typically based on a 13-month average will be divided by the number of months the rate is in effect."},{"page":14,"startToken":5370,"endToken":5701,"text":"Attachment 2a - Project Plant Detail Worksheet\nLS Power Grid New York Corporation I\n(1)\n(2)\n(3)\n(4)\n(5)\n(6)\n(7)\n(8)\n(9)\n(10)\n(11)\n(12)\n(13)\n(14)\n(15)\nProject Name (Note A)\nDecember\nJanuary\nFebruary\nMarch\nApril\nMay\nJune\nJuly\nAugust\nSeptember\nOctober\nNovember\nDecember\n13-month average\n1a\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n1b\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n1c\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n1d\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n1e\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n…\n…\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n1\nTotal Project Transmission Gross Plant\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n(1)\n(2)\n(3)\n(4)\n(5)\n(6)\n(7)\n(8)\n(9)\n(10)\n(11)\n(12)\n(13)\n(14)\n(15)\nProject Name\nDecember\nJanuary\nFebruary\nMarch\nApril\nMay\nJune\nJuly\nAugust\nSeptember\nOctober\nNovember\nDecember\n13-month average\n2a\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n2b\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n2c\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n2d\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n2e\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n…\n…\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n2\nTotal Project Transmission Accumulated Depreciation\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n(1)\n(2)\n(3)\n(4)\n(5)\n(6)\n(7)\n(8)\n(9)\n(10)\n(11)\n(12)\n(13)\n(14)\n(15)\nProject Name\nDecember\nJanuary\nFebruary\nMarch\nApril\nMay\nJune\nJuly\nAugust\nSeptember\nOctober\nNovember\nDecember\n13-month average\n3a\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n3b\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n3c\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n3d\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n3e\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n…\n…\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n3\nTotal Project Unamortized Regulatory Asset\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n(1)\n(2)\n(3)\n(4)\n(5)\n(6)\n(7)\n(8)\n(9)\n(10)\n(11)\n(12)\n(13)\n(14)\n(15)\nProject Name\nDecember\nJanuary\nFebruary\nMarch\nApril\nMay\nJune\nJuly\nAugust\nSeptember\nOctober\nNovember\nDecember\n13-month average\n4a\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n4b\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n4c\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n4d\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n4e\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n…\n…\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n4\nTotal Project Unamortized Abandoned Plant\n                                                               -                                -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -                          -   \n(1)\n(2)\nProject Name\n5a\n                                                               -   \n5b\n                                                               -   \n5c\n                                                               -   \n5d\n                                                               -   \n5e\n                                                               -   \n…\n…\n                                                               -   \n5\nTotal Project Transmission Net Plant\n                                                               -    Ties to Appendix A, Line 103 \nNote\nA\nMonthly balances are from company records. Project names entered in column (1) carry to Attachment 4, Column (a), and Attachment 5, Lines 2-2d. Project names entered on Attachment 1a, Column 2 and Lines 14-23, and on Attachment 5, Lines 14-23, Column B, must match the names entered here.\nB\nLine 5 is used as each project's Net Investment on Attachment 4, Column (b); Line 1 is used as Gross Plant In Service on Attachment 4, Column (l).\nLine \nNo.\nProject\nTransmission\nGross Plant (Note B)\nLine \nNo.\nProject\nTransmission Accumulated \nDepreciation\nLine \nNo.\nProject\nUnamortized Regulatory Asset\nLine \nNo.\nProject\nUnamortized Abandoned Plant\nLine \nNo.\nProject\nTransmission\nNet Plant (Note B)\n13-month average\n(Line 1 - Line 2 + Line 3 + Line 4)"},{"page":15,"startToken":5701,"endToken":6140,"text":"Attachment 3 - Cost Support\nLS Power Grid New York Corporation I\nNumbering continues from Attachment 2\nBeginning of Year\nEnd of Year\n Average Balance \n167\n  Account No. 255 (enter negative)  \n267.8.h\n                                   -                                                   -   \n168\n  Portion of Unamortized ITC Not Reflected in Rate Base (enter negative)\n                                   -                                                   -   \n169\n  Portion of Unamortized ITC Reducing in Rate Base\n                                   -                                                   -                                          -   \n Jurisdiction 1 \n Jurisdiction 2 \n Total \n170\n  Investment Tax Credit Amortization (enter negative) \n114.19.c\n                                   -                                                   -   \n171\n  ITC Amortization Not Permitted to Reduce Recoverable Tax Expense (enter negative) \n                                   -                                                   -   \n172\n  ITC Amortization Permitted to Reduce Recoverable Tax Expense \n                                   -                                                   -   \n173\n  Applicable Tax Gross-up Factor\n                                   -                                                   -   \n174\n  Investment Tax Credit Amortization Adjustment\n                                   -                                                   -                                          -   \n175\n  Prepayments (Account 165)\n A \n B  \n     (Prepayments exclude Prepaid Pension Assets)\nYear\nBalance\n176\nDecember\n111.57.d\n-\n                                                -   \n177\nJanuary\ncompany records\n-\n                                                -   \n178\nFebruary\ncompany records\n-\n                                                -   \n179\nMarch\ncompany records\n-\n                                                -   \n180\nApril\ncompany records\n-\n                                                -   \n181\nMay\ncompany records\n-\n                                                -   \n182\nJune \ncompany records\n-\n                                                -   \n183\nJuly\ncompany records\n-\n                                                -   \n184\nAugust\ncompany records\n-\n                                                -   \n185\nSeptember\ncompany records\n-\n                                                -   \n186\nOctober \ncompany records\n-\n                                                -   \n187\nNovember\ncompany records\n-\n                                                -   \n188\nDecember\n111.57.c\n-\n                                                -   \n189\nPrepayments\n(sum lines 176-188) /13\n                                                -   \nReserves\n189a\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\nList of all Reserves\nAmount\n190\nReserve 1\n                                                       -                                      -                                                  -                                           -                                          -                                   -   \n190a\nReserve 2\n                                                       -                                     -                                                   -                                          -                                          -                                    -   \n190b\nReserve 3\n                                                       -                                     -                                                   -                                          -                                          -                                    -   \n190c\nReserve 4\n                                                       -                                     -                                                   -                                          -                                          -                                    -   \n190d\n…\n                                                       -                                     -                                                   -                                          -                                          -                                    -   \n190e\n…\n                                                       -                                     -                                                   -                                          -                                          -                                    -   \nTotal\n                                 -   \nEnter 1 if NOT in a \ntrust or reserved \naccount, enter zero (0) \nif included in a trust or \nreserved account \nEnter 1 if the accrual account \nis included in the formula rate, \nenter (0) if  O if the accrual \naccount is NOT included in the \nformula rate\nEnter the percentage paid \nfor by customers, less the \npercent associated with \nan offsetting liability on \nthe balance sheet \nAllocation (Plant or Labor \nAllocator) \nAmount Allocated, \ncol. c x col. d x col. e \nx col. f x col. g\nAll unfunded reserves will be listed above, specifically including (but not limited to) all subaccounts for FERC Account Nos. 228.1 through 228.4.  \"Unfunded reserve\" is defined as an accrued balance (1) created and increased by debiting an expense which is included in \nthis formula rate (column (e), using the same allocator in column (g) as used in the formula to allocate the amounts in the corresponding expense account)  (2) in advance of an anticipated expenditure related to that expense (3) that is not deposited in a restricted account \n(e.g., set aside in an escrow account, see column (d)) with the earnings thereon retained within that account.  Where a given reserve is only partially funded through accruals collected from customers, only the balance funded by customer collections shall serve as a rate \nbase credit, see column (f).  The source of monthly balance data is company records."},{"page":16,"startToken":6140,"endToken":6427,"text":"Month\nYear\n(a)\n(b)\n(c) \n(d) \nNote A\nNote B\n191\nDecember\n-\n                                   -                                                  -   \n192\nJanuary\n-\n                                   -                                                  -   \n193\nFebruary\n-\n                                   -                                                  -   \n194\nMarch\n-\n                                   -                                                  -   \n195\nApril\n-\n                                   -                                                  -   \n196\nMay\n-\n                                   -                                                  -   \n197\nJune\n-\n                                   -                                                  -   \n198\nJuly\n-\n                                   -                                                  -   \n199\nAugust\n-\n                                   -                                                  -   \n200\nSeptember\n-\n                                   -                                                  -   \n201\nOctober\n-\n                                   -                                                  -   \n202\nNovember\n-\n                                   -                                                  -   \n203\nDecember\n-\n                                   -                                                  -   \n204\nAverage of the 13 Monthly Balances\n                                   -                                                  -   \n205\nAmortization Expense of Abandoned Plant\n                                                -   \nMulti-jurisdictional Workpaper\nNew York\nState 2\nState 3\nState 4\nState 5\nWeighed Average\n \nIncome Tax Rates\nWeighting\n206\nSIT=Composite State Income Tax Rate \n0\nSIT will include multiple state or local income tax rates, if applicable, weighted based on the apportionment methodologies of each jurisdiction and the number of days in the year that the rates are effective.\n207\nThe Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix A that are not the result of a timing difference. If any, a workpaper showing the calculation will be attached.\n                 -   \nMaterials & Supplies\nTotal\n Note:  for the projection, the prior year's actual balances will be used \np227.16\np227.8\n Form No.1 page\n(a)\n(b)\nc (col a+col b)\n208\nDecember\nColumn b\n                                   -                                        -                                          -   \n209\nJanuary\nCompany Records\n                                   -                                        -                                          -   \n210\nFebruary\nCompany Records\n                                   -                                        -                                          -   \n211\nMarch\nCompany Records\n                                   -                                        -                                          -   \n212\nApril\nCompany Records\n                                   -                                        -                                          -   \n213\nMay\nCompany Records\n                                   -                                        -                                          -   \n214\nJune \nCompany Records\n                                   -                                        -                                          -   \n215\nJuly\nCompany Records\n                                   -                                        -                                          -   \n216\nAugust\nCompany Records\n                                   -                                        -                                          -   \n217\nSeptember\nCompany Records\n                                   -                                        -                                          -   \n218\nOctober \nCompany Records\n                                   -                                        -                                          -   \n219\nNovember\nCompany Records\n                                   -                                        -                                          -   \n220\nDecember\nColumn c\n                                   -                                        -                                          -   \n221\nAverage\nsum line 208 to 220 divided by 13\n                                        -   \nNotes\nA\nRecovery of regulatory assets requires authorization from the Commission.\nB\nRecovery of abandoned plant is limited to any abandoned plant recovery authorized by FERC.\nUnamortized \nRegulatory Asset\nUnamortized Abandoned \nPlant\nStores Expense \nUndistributed\nTransmission Materials & \nSupplies"},{"page":17,"startToken":6427,"endToken":6802,"text":"Attachment 3 - Cost Support\nCOST OF CAPITAL\nLS Power Grid New York Corporation I\nRETURN ON RATE BASE ( R )\n$\n222\nLong Term Interest (117, sum of 62.c through 67.c) (Note D)\n                               -   \n223\nPreferred Dividends (118.29c) (positive number)\n                               -   \n224\nProprietary Capital (Line 25 (c))\n                               -   \n225\nLess Preferred Stock (Line 9) \n                               -   \n226\nLess Account 216.1 Undistributed Subsidiary Earnings (Line 25 (d))     \n                               -   \n227\nLess Account 219 Accum. Other Comprehensive Income (Line 25 (e))        \n                               -   \n228\nCommon Stock\n(Sum of Lines 224 through 227)\n                               -   \n$\n%\nCost\nWeighted\n229\nLong Term Debt\nLine 246 col (a), Note A and Appendix A Note P\n                               -   \n100.00%\n0.00%\n0.00%\n=WCLTD\n230\nPreferred Stock\nLine 246 col (b), Note B and Appendix A Note P\n                               -   \n0.00%\n0.00%\n0.00%\n231\nCommon Stock\nLine 228 col (b), Note C and Appendix A Notes O and P\n                               -   \n0.00%\n0.00%\n0.00%\n232\nTotal\n(Sum of Lines 229 through 231)\n                               -   \n0.00%\n=R\n(a)\n(b)\n( c ) \n(d) \n( e ) \nMonthly Balances for Capital Structure\n233\nDecember (Prior Year)\n                                         -                                 -                                 -                                 -                          -   \n234\nJanuary\n                                         -                                 -                                 -                                 -                          -   \n235\nFebruary\n                                         -                                 -                                 -                                 -                          -   \n236\nMarch\n                                         -                                 -                                 -                                 -                          -   \n237\nApril\n                                         -                                 -                                 -                                 -                          -   \n238\nMay\n                                         -                                 -                                 -                                 -                          -   \n239\nJune\n                                         -                                 -                                 -                                 -                          -   \n240\nJuly\n                                         -                                 -                                 -                                 -                          -   \n241\nAugust\n                                         -                                 -                                 -                                 -                          -   \n242\nSeptember\n                                         -                                 -                                 -                                 -                          -   \n243\nOctober\n                                         -                                 -                                 -                                 -                          -   \n244\nNovember\n                                         -                                 -                                 -                                 -                          -   \n245\nDecember\n                                         -                                 -                                 -                                 -                          -   \n246\n13-Month Average\n                                         -                                 -                                 -                                 -                          -   \nNotes\nA\nLong Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112,  lines 18.c to 21.c, in the Form No. 1; the cost is calculated by dividing line 222 by the Long Term Debt balance on line 229.\nB\nPreferred Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112 line 3.c in the Form No. 1\nC\nCommon Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on Form 1 page 112 line 16.c less lines 3.c , 12.c, and 15.c\nD\nLong-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies\nLong Term Debt \n(Note A)\nPreferred Stock \n(112.3.c)\nProprietary Capital \n(112.16.c)\nUndistributed Sub \nEarnings 216.1 \n(112.12.c)\nAccum Other \nComp. Income \n219 (112.15.c)"},{"page":18,"startToken":6802,"endToken":7096,"text":"LS Power Grid New York Corporation I\n Project Worksheet \nAttachment 4\nFor the 12 months ended 12/31/____\n Utilizing Appendix A Data\n \nThe calculations below calculate that additional revenue requirement for 100 basis points of ROE and 1 percent change in the equity component of the capital structure. \nThese amounts are then used to valuate the actual increase in revenue in the table below (starting on line 66) associated with the actual incentive authorized by the Commission\nThe use of the 100 basis point calculations do not presume any particular incentive (i.e., 100 basis points) being granted by the Commission. \n Base ROE and Income Taxes Carrying Charge \nAllocator\nResult\n                   1 Rate Base\n                                       -   \n                   2 BASE RETURN CALCULATION:\n$\n%\nCost\nWeighted\n                   3   Long Term Debt  \n(Appendix A, Line 96)\n                       -   \n100.00%\n0.00%\n0.00%\n                   4   Preferred Stock \n(Appendix A, Line 97)\n                       -   \n0.00%\n                      -   \n0.00%\n                   5   Common Stock \n(Appendix A, Line 98)\n                       -   \n0.00%\n0.00%\n0.00%\n                   6 Total  (sum lines 3-5)\n                       -    \n0.00%\n                   7 Return multiplied by Rate Base (line 1 * line 6)\n                                       -   \n                   8 INCOME TAXES          \n                   9      T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =  (Appendix A, line 65)\n                       -   \n                 10      CIT=(T/1-T) * (1-(WCLTD/R)) =\n                       -   \n                 11        where WCLTD=(line 3) and R= (line 6)\n                 12        and FIT, SIT & p are as given in footnote E on Appendix A.\n                 13       1 / (1 - T)  = (T from line 9)\n                       -   \n                 14 Amortized Investment Tax Credit (266.8f) (enter negative)\n                       -   \n                 15 Income Tax Calculation = line 10 * line 7 * (1-n)\n                       -   \n                                       -   \n                 16 ITC adjustment (line 13 * line 14)  * (1-n)\n                       -   \nNP\n                      -   \n                                       -   \n                 17 Total Income Taxes\n(line 15 plus line 16)\n                       -   \n                                       -   \n                 18 Base Return and Income Taxes\nSum lines 7 and 17\n                                       -   \n                 19 Rate Base\nLine 1\n                                       -   \n                 20 Return and Income Taxes at Base ROE\nLine 18 / line 19\n                                       -"},{"page":19,"startToken":7096,"endToken":7549,"text":"100 Basis Point Incentive ROE and Income Taxes Carrying Charge\nAttachment 4\nResult\n                 21 Rate Base\n                                       -   \n                 22 100 Basis Point Incentive Return impact on \n$\n%\nCost\nWeighted\n                 23   Long Term Debt  \n(line 3)\n                       -   \n100.00%\n0.00%\n0.00%\n                 24   Preferred Stock \n(line 4)\n                       -   \n0.00%\n0.00%\n0.00%\n                 25   Common Stock\n(line 5 plus 100 basis points)\n                       -   \n0.00%\n0.00%\n0.00%\n                 26 Total  (sum lines 24-26)\n                       -   \n \n0.00%\n                 27 100 Basis Point Incentive Return multiplied by Rate Base (line 21 * line 26)\n                                       -   \n                 28 INCOME TAXES          \n                 29      T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =  (Appendix A, line 61)\n                       -   \n                 30      CIT=(T/1-T) * (1-(WCLTD/R)) =\n                       -   \n                 31        where WCLTD=(line 23) and R= (line 26)\n                 32        and FIT, SIT & p are as given in footnote E on Appendix A.\n                 33       1 / (1 - T)  = (T from line 29)\n                       -   \n                 34 Amortized Investment Tax Credit (line 14)\n                       -   \n                 35 Income Tax Calculation = line 30 * line 27 * (1-n)\n                       -   \n                                       -   \n                 36 ITC adjustment (line 33 * line 34)  * (1-n)\n                       -   \nNP\n                      -   \n                                       -   \n                 37 Total Income Taxes\n(line 35 plus line 36)\n                       -   \n                                       -   \n                 38 Return and Income Taxes with 100 basis point increase in ROE\nSum lines 27 and 37\n                                       -   \n                 39 Rate Base\nLine 21\n                                       -   \n                 40 Return and Income Taxes with 100 basis point increase in  ROE\nLine 38 / line 39\n                                       -   \n                 41 Difference in Return and Income Taxes between Base ROE and 100 Basis Point Incentive\nLine 41- Line 20\n                                       -   \nEffect of 1% Increase in the Equity Ratio\n Results \n                 42 Rate Base\n                                       -   \n                 43 100 Basis Point Incentive Return\n$\n%\nCost\nWeighted\n                 44   Long Term Debt  \n(line 3 minus 1% in equity ratio)\n                       -   \n0.00%\n0.00%\n0.00%\n                 45   Preferred Stock \n(line 4)\n                       -   \n0.00%\n0.00%\n0.00%\n                 46   Common Stock  \n(line 5 plus 1% in equity ratio))\n                       -   \n0.00%\n0.00%\n0.00%\n                 47 Total  (sum lines 44-46)\n                       -    \n0.00%\n                 48 Line 47 x line 42\n                                       -   \n                 49 INCOME TAXES          \n                 50      T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =  (Appendix A, line 61)\n                       -   \n                 51      CIT=(T/1-T) * (1-(WCLTD/R)) =\n                       -   \n                 52        where WCLTD=(line 44) and R= (line 47)\n                 53        and FIT, SIT & p are as given in footnote E on Appendix A.\n                 54       1 / (1 - T)  = (T from line 50)\n                       -   \n                 55 Amortized Investment Tax Credit (line 14)\n                       -   \n                 56 Income Tax Calculation = line 51 * line 48 * (1-n)\n                       -   \n                                       -   \n                 57 ITC adjustment (line 54 * line 55)  * (1-n)\n                       -   \nNP\n                      -   \n                                       -   \n                 58 Total Income Taxes\n(line 56 plus line 57)\n                       -   \n                                       -   \n                 59 Return and Income Taxes with 1% Increase in the Equity Ratio\nSum lines 48 and 58\n                                       -   \n                 60 Rate Base\nLine 42\n                                       -   \n                 61 Return and Income Taxes with 1% Increase in the Equity Ratio\nLine 59 / line 60\n                                       -   \n                 62 Difference between Base ROE and 1% Increase in the Equity Ratio\nLine 61 - Line 20\n                                       -"},{"page":20,"startToken":7549,"endToken":7942,"text":"63  Revenue Requirement per project including incentives \n                 64  Expense Allocator \n[Appendix A, lines 48 and 63, less Appendix A, line 47a (project specific) / Gross Transmission Plant In Service Column (l).  If Gross Transmission Plant is zero, then the Expense Allocator should be zero] (Note B)\n                            -   \n                 65  Base Carrying Charge \nAppendix A, Line 106\n                            -   \nThe table below breaks out the total revenue requirement on Appendix A separately for each investment.  The total of Column (q) must equal the amount shown on Appendix A, Line 3.\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n(k)\n(l)\n(m)\n(n)\n(o)\n(p)\n(q)\n Line Description\nNet Investment                                                                      (Note A)\nLine 41\n                 66                                                        -                                                                                                              -   \n0.00%\n                      -                            -                                -   \n                                      -                                                         -                               -                             -                                       -   \n                                -   \n 66a                                                        -                                                                                                              -   \n0.00%\n                      -                            -                                -   \n                                      -                                                         -                               -                             -                                       -   \n                                -   \n 66b                                                        -                                                                                                              -   \n0.00%\n                      -                            -                                -   \n                                      -                                                         -                               -                             -                                       -   \n                                -   \n 66c                                                        -                                                                                                              -   \n0.00%\n                      -                            -                                -   \n                                      -                                                         -                               -                             -                                       -   \n                                -   \n 66d                                                        -                                                                                                              -   \n0.00%\n                      -                            -                                -   \n                                      -                                                         -                               -                             -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n … \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                                -   \n0.00%\n                      -                            -                                -   \n                                      -                                                         -   \n                          -                                       -   \n                 67 Total\n$0\n                             -   \n                                      -                                                         -   \n$0\n                                    -                                   -                                   -                                   -   \n                 68 Check Sum Appendix A Line 3\n                                -   \n                 69 Difference (must be equal to zero)\n                                -   \n Note: \nA\nColumn (b), Net Investment includes the Net Plant In Service, unamortized regulatory assets, and unamortized abandoned plant.\nB\nColumn (l), Gross Plant in Service excludes Regulatory Assets, CWIP, and Abandoned Plant.\nC\nCompetitive Bid Concession, if any, will reflect outcome of competitive developer selection process and will be computed on a workpaper that will be provided as supporting documentation \nfor each Annual Update and will be zero or a reduction to the revenue requirement.  The amount in Column (p) above equals the amount by which the annual revenue requirement is reduced from the ceiling rate.   \nD\nColumn (e), for each project with an incentive in column (e), note the docket No. in which FERC granted the incentive>\nProject\nDocket No.\nNote\nROE Authorized \nby FERC (Note \nD)\nROE Base \n(From Appendix \nA, line 9498)\nIncentive % \nAuthorized by \nFERC\nCol (e) / .01 x Col \n(f)\nIncentive $ (Col (b) \nx Col (g)\nEquity % in Capital \nStructure (% above base \n%, -% below base %)(1 \nequals 1%)\nImpact of Equity \nComponent of Capital \nStructure(Col (b) x (i) x \nLine 62\nBase Return and Tax (Line 65 x Col \n(b)\nGross Plant In \nService (Note B)\nExpense Allocator  \n  (line 64)\nO&M, Taxes Other than \nIncome                  (Col. \n(l) x Col. (n)(m))\nDepreciation/\nAmortization Expense\nCompetitive Bid \nConcession      (Note \nC)\nTotal Revenues (Col. \n(h) + (j) + (k) +(n) +\n(o) -(p))"},{"page":21,"startToken":7942,"endToken":8404,"text":"Attachment 5 - Example of True-Up Calculation\nLS Power Grid New York Corporation I\nYear\nAnnual True-Up Calculation\n1\nA\nB\nC\nD\nE\nF\nG\nActual\nNet \nAdjusted\nUnder/(Over)  \nInterest\nTotal True-Up\nProject\nNet Revenue\nCollection\nIncome\nAdjustment\nIdentification\nProject Name\nRequirement1\nRevenue Received2\n(C-D)\n(Expense)\n(E + F)\n2\n                                                                                         -   \n                            -                                              -                             -                                              -                               -   \n2a\n                                                                                         -                               -                                              -                             -                                              -                               -   \n2b\n                                                                                         -                               -                                              -                             -                                              -                               -   \n2c\n                                                                                         -                               -                                              -                             -                                              -                               -   \n2d\n                                                                                         -                               -                                              -                             -                                              -                               -   \n                            -                                              -                             -                                              -                               -   \n3\n Total \n                            -                                              -                             -                                              -                               -   \nNotes\n1. From Attachment 4, Column (q) for the period being trued-up \n2. The \"revenue received\" is the total amount of revenue distributed in the True-Up Year. The amounts do not include any true-ups or prior period\n     adjustments and reflects any Competitive Bid Concessions\n3. Then Monthly Interest Rate shall be equal to the interest rate set forth below on line 13 and be applied to the amount in Column E for a period of 24 months\n4. The True-Up Adjustment is applied to each project prorata based its contribution to the Revenue Requirement shown in Attachment 4\nFERC Refund Interest Rate\n(a)\n(b)\n(c)\n(d)\n4\nInterest Rate:\nQuarter\nYear\n5\n1st Qtr.\n-\n0.00%\n6\n2nd Qtr \n-\n0.00%\n7\n3rd Qtr \n-\n0.00%\n8\n4th Qtr\n-\n0.00%\n9\n1st Qtr \n-\n0.00%\n                                           \n10\n2nd Qtr \n-\n0.00%\n11\n3rd Qtr \n-\n0.00%\n12\nSum lines 5-11\n0.00%\n13\nAvg. Monthly FERC Rate\nLine 12 divided by 7\n0.00%\nSupplemental MTRC True-Up by Eligible Customer and Covered Upgrade (Note 5)\nA\nB\nC\nD\nE\nEligible Customer\nCovered Upgrade\nActual Supplemental MTRC\n14\n                            -                                              -                             -   \n15\n                            -                                              -                             -   \n16\n                            -                                              -                             -   \n17\n                            -                                              -                             -   \n18\n                            -                                              -                             -   \n19\n                            -                                              -                             -   \n20\n                            -                                              -                             -   \n21\n                            -                                              -                             -   \n22\n                            -                                              -                             -   \n23\n                            -                                              -                             -   \n24\n Total \n                            -                                              -                             -   \n Notes \n1. From Attachment 4, Column (q) for the period being trued-up \n2. The \"revenue received\" is the total amount of revenue distributed in the True-Up Year, excluding Large Load CRA Revenue on Attachment 1, Line 5a. The amounts do not include any true-ups \n     or prior period adjustments and reflects any Competitive Bid Concessions\n3. The Monthly Interest Rate shall be equal to the interest rate set forth on line 13 and be applied to the amount in Column E for a period of 24 months\n4. The True-Up Adjustment is applied to each project pro rata based on its contribution to the Revenue Requirement shown in Attachment 4\nQuarterly Interest Rate under \nSection 35.19(a)\nSupplemental \nMTRC Billed \nExcluding Prior-\nPeriod True-Up \nAdjustments\nTrue-Up \nAdjustment (D - \nC)\n5. Lines 14-23 (Supplemental MTRC True-Up by Eligible Customer and Covered Upgrade) compare Supplemental MTRC billed to each active Eligible Customer for each Covered Upgrade during the True-Up Year, EXCLUDING any \nprior-period true-up adjustment included in that billing, with Supplemental MTRC based on actual Qualifying Transmission Revenues from Attachment 1a, Column 6, in the Annual Update for that year. The difference, without interest, is \nincluded in Attachment 1a, Column 7. Nonpayment alone does not create another customer-level charge."},{"page":22,"startToken":8404,"endToken":8582,"text":"LS Power Grid New York Corporation I\nAttachment 6a - Accumulated Deferred Income Taxes (ADIT) Proration and Averaging Worksheet\nProjected Annual Transmission Revenue Requirement\nFor the 12 months ended 12/31/____\nLine\nNo. \nADIT Account\nAmount\n1 \n190\n                                -   From line 25\n2\n281 (enter negative)\n                                -   From line 58\n3\n282 (enter negative)\n                                -   From line 91\n4\n283 (enter negative)\n                                -   From line 124\n5\nTotal Projected ADIT\n                                -   Enter as negative Appendix A, page 2, line 27\n6\nRate year =\n-\n7\nTest period days after rates become effective\n                    -   \n8\n9\nNote 2 - The components of the accumulated deferred income tax balances are detailed on Attachment 6b. \nNote 1 - The computations on this workpaper average the projected annual activity of accumulated deferred income taxes.  To the extent that the ADIT is subject to the normalization \nrequirements,  the proration rules of Treasury Regulation Sec. 1.167(l)-1(h)(6) and the consistency rules of IRC Section 168(i)(9)(B) are applied.  Activity related to the portions of the \naccount balances not subject to the proration requirement are averaged instead of prorated."},{"page":23,"startToken":8582,"endToken":8892,"text":"10\nAccount 190 - Accumulated Deferred Income Taxes\n11\nBeginning Balance\n                                -   \n12\nLess:  Portion not related to transmission\n                                -   \n13\nLess:  Portion not reflected in rate base\n                                -   \n14\nSubtotal:  Portion reflected in rate base\nLine 11 - line 12 - line 13\n                                -   \n15\nLess:  Portion subject to proration\nLine 29, Col. D\n                                -   \n16\nPortion subject to averaging\nLine 14 - line 15\n                                -   \n17\nEnding Balance\n                                -   \n18\nLess:  Portion not related to transmission\n                                -   \n19\nLess:  Portion not reflected in rate base\n                                -   \n20\nSubtotal:  Portion reflected in rate base\nLine 17 - line 18 - line 19\n                                -   \n21\nLess:  Portion subject to proration (before proration)\nLine 41 Col. D\n                                -   \n22\nPortion subject to averaging (before averaging)\nLine 20 - line 21\n                                -   \n23\nEnding balance of portion subject to proration (prorated)\nLine 41 Col. H\n                                -   \n24\nAverage balance of portion subject to averaging\n(Line 16 + line 22) / 2\n                                -   \n25\nAmount reflected in rate base\nLine 23 + line 24\n                                -   Enter on line 1\n26\n27\nAccount 190 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n28\nMonth\nYear\n29\nDecember 31,\n-\n NA                                 -   \nNA\n                    -   \n NA                                 -   \n30\nJanuary \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n31\nFebruary\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n32\nMarch \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n33\nApril\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n34\nMay\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n35\nJune\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n36\nJuly\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n37\nAugust \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n38\nSeptember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n39\nOctober\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n40\nNovember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n41\nDecember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n42\nTotal \n                                -   \nAmount\ndebit / <credit>\nNote 3 - Accumulated deferred income tax activity in account 190 subject to the proration rules relates to taxable contributions in aid of construction, net operating loss carryforwards, \nregulatory liabilities for excess deferred income taxes and any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)"},{"page":24,"startToken":8892,"endToken":9194,"text":"43\nAccount 281 - Accumulated Deferred Income Taxes\n44\nBeginning Balance\n                                -   \n45\nLess:  Portion not related to transmission\n                                -   \n46\nLess:  Portion not reflected in rate base\n                                -   \n47\nSubtotal:  Portion reflected in rate base\nLine 44 - line 45 - line 46\n                                -   \n48\nLess:  Portion subject to proration\nLine 62 Col. D\n                                -   \n49\nPortion subject to averaging\nLine 47 - line 48\n                                -   \n50\nEnding Balance\n                                -   \n51\nLess:  Portion not related to transmission\n                                -   \n52\nLess:  Portion not reflected in rate base\n                                -   \n53\nSubtotal:  Portion reflected in rate base\nLine 50 - line 51 - line 52\n                                -   \n54\nLess:  Portion subject to proration (before proration)\nLine 74 Col. D\n                                -   \n55\nPortion subject to averaging (before averaging)\nLine 53 - line 54\n                                -   \n56\nEnding balance of portion subject to proration (prorated)\nLine 74 Col. H\n                                -   \n57\nAverage balance of portion subject to averaging\n(Line 49 + line 55) / 2\n                                -   \n58\nAmount reflected in rate base\nLine 56 + line 57\n                                -   Enter on line 2\n59\n60\nAccount 281 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n61\nMonth\nYear\n62\nDecember 31,\n-\n NA                                 -   \nNA\n                    -   \n NA                                 -   \n63\nJanuary \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n64\nFebruary\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n65\nMarch \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n66\nApril\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n67\nMay\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n68\nJune\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n69\nJuly\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n70\nAugust \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n71\nSeptember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n72\nOctober\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n73\nNovember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n74\nDecember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n75\nTotal \n                                -   \nAmount\ndebit / <credit>\nNote 4 - Accumulated deferred income tax activity in account 281 subject to the proration rules relates differences between depreciation methods and lives for public utility property \nand any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)"},{"page":25,"startToken":9194,"endToken":9496,"text":"76\nAccount 282 - Accumulated Deferred Income Taxes\n77\nBeginning Balance\n                                -   \n78\nLess:  Portion not related to transmission\n                                -   \n79\nLess:  Portion not reflected in rate base\n                                -   \n80\nSubtotal:  Portion reflected in rate base\nLine 77 - line 78 - line 79\n                                -   \n81\nLess:  Portion subject to proration\nLine 95 Col. D\n                                -   \n82\nPortion subject to averaging\nLine 80 - line 81\n                                -   \n83\nEnding Balance\n                                -   \n84\nLess:  Portion not related to transmission\n                                -   \n85\nLess:  Portion not reflected in rate base\n                                -   \n86\nSubtotal:  Portion reflected in rate base\nLine 78 - line 79 - line 80\n                                -   \n87\nLess:  Portion subject to proration (before proration)\nLine 107 Col. D\n                                -   \n88\nPortion subject to averaging (before averaging)\nLine 81 - line 82\n                                -   \n89\nEnding balance of portion subject to proration (prorated)\nLine 107 Col. H\n                                -   \n90\nAverage balance of portion subject to averaging\n(Line 82 + line 88) / 2\n                                -   \n91\nAmount reflected in rate base\nLine 89 + line 90\n                                -   Enter on line 3\n92\n93\nAccount 282 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n94\nMonth\nYear\n95\nDecember 31,\n-\n NA                                 -   \nNA\n                    -   \n NA                                 -   \n96\nJanuary \n-\n                                -   \n0\n                    -                                   -                                   -   \n97\nFebruary\n-\n                                -   \n0\n                    -                                   -                                   -   \n98\nMarch \n-\n                                -   \n0\n                    -                                   -                                   -   \n99\nApril\n-\n                                -   \n0\n                    -                                   -                                   -   \n100\nMay\n-\n                                -   \n0\n                    -                                   -                                   -   \n101\nJune\n-\n                                -   \n0\n                    -                                   -                                   -   \n102\nJuly\n-\n                                -   \n0\n                    -                                   -                                   -   \n103\nAugust \n-\n                                -   \n0\n                    -                                   -                                   -   \n104\nSeptember\n-\n                                -   \n0\n                    -                                   -                                   -   \n105\nOctober\n-\n                                -   \n0\n                    -                                   -                                   -   \n106\nNovember\n-\n                                -   \n0\n                    -                                   -                                   -   \n107\nDecember\n-\n                                -   \n0\n                    -                                   -                                   -   \n108\nTotal \n                                -   \nAmount\ndebit / <credit>\nNote 5 - Accumulated deferred income tax activity in account 282 subject to the proration rules relates differences between depreciation methods and lives for public utility property \nand any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)"},{"page":26,"startToken":9496,"endToken":9798,"text":"109\nAccount 283 - Accumulated Deferred Income Taxes\n110\nBeginning Balance\n                                -   \n111\nLess:  Portion not related to transmission\n                                -   \n112\nLess:  Portion not reflected in rate base\n                                -   \n113\nSubtotal:  Portion reflected in rate base\nLine 110 - line 111 - line 112\n                                -   \n114\nLess:  Portion subject to proration\nLine 128 Col. D\n                                -   \n115\nPortion subject to averaging\nLine 113 - line 114\n                                -   \n116\nEnding Balance\n                                -   \n117\nLess:  Portion not related to transmission\n                                -   \n118\nLess:  Portion not reflected in rate base\n                                -   \n119\nSubtotal:  Portion reflected in rate base\nLine 111 - line 112 - line 113\n                                -   \n120\nLess:  Portion subject to proration (before proration)\nLine 135 Col. D\n                                -   \n121\nPortion subject to averaging (before averaging)\nLine 114 - line 115\n                                -   \n122\nEnding balance of portion subject to proration (prorated)\nLine 135 Col. H\n                                -   \n123\nAverage balance of portion subject to averaging\n(Line 110 + line 116) / 2\n                                -   \n124\nAmount reflected in rate base\nLine 117 + line 118\n                                -   Enter on line 4\n125\n126\nAccount 283 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n127\nMonth\nYear\n128\nDecember 31,\n-\n NA                                 -   \nNA\n                    -   \n NA                                 -   \n129\nJanuary \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n130\nFebruary\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n131\nMarch \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n132\nApril\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n133\nMay\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n134\nJune\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n135\nJuly\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n136\nAugust \n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n137\nSeptember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n138\nOctober\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n139\nNovember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n140\nDecember\n-\n                                -                                   -   \n0\n                    -                                   -                                   -   \n141\nTotal \n                                -   \nAmount\ndebit / <credit>\nNote 6 - Accumulated deferred income tax activity in account 283 subject to the proration rules relates differences between depreciation methods and lives for public utility property \nand any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)"},{"page":27,"startToken":9798,"endToken":10012,"text":"LS Power Grid New York Corporation I\nAttachment 6b - Accumulated Deferred Income Taxes (ADIT) Detail Worksheet\nProjected Annual Transmission Revenue Requirement\nFor the 12 months ended 12/31/____\n-\n-\n-\nComposite income tax rate\n0.00%\n0.00%\n0.00%\nExplanation\nAccount 190 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nExcluded from rate base\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nTotal Temporary Differences - account 190\n                         -                            -                                -   \nTotal DTA / <DTL> - account 190\n                         -                            -                                -   \nAccount 281 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nExcluded from rate base\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nTotal Temporary Differences - account 281\n                         -                            -                                -   \nTotal DTA / <DTL> - account 281\n                         -                            -                                -   \nProjected \namount - \nbeginning of \nyear\nProjected \namount during \nthe year\nProjected amount \n- end of year"},{"page":28,"startToken":10012,"endToken":10190,"text":"Account 282 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nTax depreciation\n                         -   \nBook depreciation of tax basis\n                         -                            -                                -   \nItem 3\n                         -                            -                                -   \nItem 4\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nIncluded in rate base but not subject to proration\nItem 1\nItem 2\n                         -   \nItem 3\n                         -                            -                                -   \nItem 4\n                         -                            -                                -   \nItem 5\n                         -                            -                                -   \nItem 6\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nExcluded from rate base\nAFUDC-equity accrual\nAFUDC-equity - book depreciation\nItem 3\n                         -                            -                                -   \nItem 4\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nTotal Temporary Differences - account 282\n                         -                            -                                -   \nDTA / <DTL> - account 282\n                         -                            -                                -   \nAccount 283 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -                            -                                -   \nItem 2\n                         -                            -                                -   \nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nExcluded from rate base\nItem 1\nItem 2\nSubtotal of temporary differences\n                         -                            -                                -   \nDTA / <DTL> for such temporary differences\n                         -                            -                                -   \nTotal Temporary Differences - account 283\n                         -                            -                                -   \nDTA / <DTL> - account 283\n                         -                            -                                -"},{"page":29,"startToken":10190,"endToken":11218,"text":"LS Power Grid New York Corporation I\nAttachment 6c - Accumulated Deferred Income Taxes (ADIT) Proration and Averaging Worksheet\nActual Annual Transmission Revenue Requirement (True-up Adjustment)\nFor the 12 months ended 12/31/____\nLine\nNo. \nADIT Account\nAmount\n1 \n190\n                                 -   From line 25\n2\n281 (enter negative)\n                                 -   From line 58\n3\n282 (enter negative)\n                                 -   From line 91\n4\n283 (enter negative)\n                                 -   From line 124\n5\nTotal Projected ADIT\n                                 -   Enter as negative Appendix A, page 2, line 27\n6\nRate year =\n                       - \n7\nTest period days after rates become effective\n                       - \n8\n9\nNote 2 - The components of the accumulated deferred income tax balances are detailed on Attachment 6d. \n10\nAccount 190 - Accumulated Deferred Income Taxes\n11\nBeginning Balance\nFF1 234.8.b\n                                 -   \n12\nLess:  Portion not related to transmission\n                                 -   \n13\nLess:  Portion not reflected in rate base\n                                 -   \n14\nSubtotal:  Portion reflected in rate base\nLine 11 - line 12 - line 13\n                                 -   \n15\nLess:  Portion subject to proration\nLine 29, Col. D\n                                 -   \n16\nPortion subject to averaging\nLine 14 - line 15\n                                 -   \n17\nEnding Balance\nFF1 234.8.c\n                                 -   \n18\nLess:  Portion not related to transmission\n                                 -   \n19\nLess:  Portion not reflected in rate base\n                                 -   \n20\nSubtotal:  Portion reflected in rate base\nLine 17 - line 18 - line 19\n                                 -   \n21\nLess:  Portion subject to proration (before proration)\nLine 41 Col. D\n                                 -   \n22\nPortion subject to averaging (before averaging)\nLine 20 - line 21\n                                 -   \n23\nEnding balance of portion subject to proration (prorated)\nLine 41 Col. H\n                                 -   \n24\nAverage balance of portion subject to averaging\n(Line 16 + line 22) / 2\n                                 -   \n25\nAmount reflected in rate base\nLine 23 + line 24\n                                 -   Enter on line 1\n26\n27\nAccount 190 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n(k)\n(l)\n(m)\n(n)\n28\nMonth\nYear\nActual Monthly Activity\n29\nDecember 31,\n-\n NA                                  -   \nNA\n                       - \n NA                                 -   \n NA \n NA \n NA \n NA \n NA                                   -   \n30\nJanuary \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n31\nFebruary\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n32\nMarch \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n33\nApril\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n34\nMay\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n35\nJune\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n36\nJuly\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n37\nAugust \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n38\nSeptember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n39\nOctober\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n40\nNovember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n41\nDecember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n42\nTotal \n                                 -   \n                                   -                                     -   \n43\nAccount 281 - Accumulated Deferred Income Taxes\n44\nBeginning Balance\nFF1 272.8.b\n                                 -   \n45\nLess:  Portion not related to transmission\n                                 -   \n46\nLess:  Portion not reflected in rate base\n                                 -   \n47\nSubtotal:  Portion reflected in rate base\nLine 44 - line 45 - line 46\n                                 -   \n48\nLess:  Portion subject to proration\nLine 62 Col. D\n                                 -   \n49\nPortion subject to averaging\nLine 47 - line 48\n                                 -   \n50\nEnding Balance\nFF1 273.8.k\n                                 -   \n51\nLess:  Portion not related to transmission\n                                 -   \n52\nLess:  Portion not reflected in rate base\n                                 -   \n53\nSubtotal:  Portion reflected in rate base\nLine 50 - line 51 - line 52\n                                 -   \n54\nLess:  Portion subject to proration (before proration)\nLine 74 Col. D\n                                 -   \n55\nPortion subject to averaging (before averaging)\nLine 53 - line 54\n                                 -   \n56\nEnding balance of portion subject to proration (prorated)\nLine 74 Col. H\n                                 -   \n57\nAverage balance of portion subject to averaging\n(Line 49 + line 55) / 2\n                                 -   \n58\nAmount reflected in rate base\nLine 56 + line 57\n                                 -   Enter on line 2\n59\n60\nAccount 281 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n(k)\n(l)\n(m)\n(n)\n61\nMonth\nYear\nActual Monthly Activity\n62\nDecember 31,\n-\n NA                                  -   \nNA\n                       - \n NA                                 -   \n NA \n NA \n NA \n NA \n NA                                   -   \n63\nJanuary \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n64\nFebruary\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n65\nMarch \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n66\nApril\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n67\nMay\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n68\nJune\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n69\nJuly\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n70\nAugust \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n71\nSeptember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n72\nOctober\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n73\nNovember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n74\nDecember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n75\nTotal \n                                 -   \n                                   -                                     -   \nNote 1 - The computations on this workpaper average the actual annual activity of accumulated deferred income taxes.  To the extent that the ADIT is subject to the normalization \nrequirements,  the proration rules of Treasury Regulation Sec. 1.167(l)-1(h)(6) and the consistency rules of IRC Section 168(i)(9)(B) are applied.  Activity related to the portions of \nthe account balances not subject to the proration requirement are averaged instead of prorated.  \nAmount\ndebit / <credit>\nNote 3 - Accumulated deferred income tax activity in account 190 subject to the proration rules relates to taxable contributions in aid of construction, net operating loss \ncarryforwards, regulatory liabilities for excess deferred income taxes and any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)\nDifference between \nprojected monthly and \nactual monthly activity\n(See Note 7.)\nPreserve projected \nproration when actual \nmonthly and projected \nmonthly activity are \neither both increases or \ndecreases.  \n(See Note 8.)\nFifty percent of the \ndifference between \nprojected and actual activity \nwhen actual and projected \nactivity are either both \nincreases or decreases.  \n(See Note 9.)\nFifty percent of actual \nactivity (Col I) when \nprojected activity is an \nincrease while actual \nactivity is a decrease OR \nprojected activity is a \ndecrease while actual \nactivity is an increase.\n(See Note 10.)\nBalance reflecting \nproration or averaging \n(See Note 11.)\nAmount\ndebit / <credit>\nNote 4 - Accumulated deferred income tax activity in account 281 subject to the proration rules relates differences between depreciation methods and lives for public utility property \nand any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)\nDifference between \nprojected monthly and \nactual monthly activity\n(See Note 7.)\nPreserve projected \nproration when actual \nmonthly and projected \nmonthly activity are \neither both increases or \ndecreases.  \n(See Note 8.)\nFifty percent of the \ndifference between \nprojected and actual activity \nwhen actual and projected \nactivity are either both \nincreases or decreases.  \n(See Note 9.)\nFifty percent of actual \nactivity (Col I) when \nprojected activity is an \nincrease while actual \nactivity is a decrease OR \nprojected activity is a \ndecrease while actual \nactivity is an increase.\n(See Note 10.)\nBalance reflecting \nproration or averaging \n(See Note 11.)"},{"page":30,"startToken":11218,"endToken":12452,"text":"76\nAccount 282 - Accumulated Deferred Income Taxes\n77\nBeginning Balance\nFF1 274.2.b\n                                 -   \n78\nLess:  Portion not related to transmission\n                                 -   \n79\nLess:  Portion not reflected in rate base\n                                 -   \n80\nSubtotal:  Portion reflected in rate base\nLine 77 - line 78 - line 79\n                                 -   \n81\nLess:  Portion subject to proration\nLine 95 Col. D\n                                 -   \n82\nPortion subject to averaging\nLine 80 - line 81\n                                 -   \n83\nEnding Balance\nFF1 275.2.k\n                                 -   \n84\nLess:  Portion not related to transmission\n                                 -   \n85\nLess:  Portion not reflected in rate base\n                                 -   \n86\nSubtotal:  Portion reflected in rate base\nLine 78 - line 79 - line 80\n                                 -   \n87\nLess:  Portion subject to proration (before proration)\nLine 107 Col. D\n                                 -   \n88\nPortion subject to averaging (before averaging)\nLine 81 - line 82\n                                 -   \n89\nEnding balance of portion subject to proration (prorated)\nLine 107 Col. H\n                                 -   \n90\nAverage balance of portion subject to averaging\n(Line 82 + line 88) / 2\n                                 -   \n91\nAmount reflected in rate base\nLine 89 + line 90\n                                 -   Enter on line 3\n92\n93\nAccount 282 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n(k)\n(l)\n(m)\n(n)\n94\nMonth\nYear\nActual Monthly Activity\n95\nDecember 31,\n-\n NA                                  -   \nNA\n                       - \n NA                                 -   \n NA \n NA \n NA \n NA \n NA                                   -   \n96\nJanuary \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n97\nFebruary\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n98\nMarch \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n99\nApril\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n100\nMay\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n101\nJune\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n102\nJuly\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n103\nAugust \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n104\nSeptember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n105\nOctober\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n106\nNovember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n107\nDecember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n108\nTotal \n                                 -   \n                                   -                                     -   \n109\nAccount 283 - Accumulated Deferred Income Taxes\n110\nBeginning Balance\nFF1 276.9.b\n                                 -   \n111\nLess:  Portion not related to transmission\n                                 -   \n112\nLess:  Portion not reflected in rate base\n                                 -   \n113\nSubtotal:  Portion reflected in rate base\nLine 110 - line 111 - line 112\n                                 -   \n114\nLess:  Portion subject to proration\nLine 128 Col. D\n                                 -   \n115\nPortion subject to averaging\nLine 113 - line 114\n                                 -   \n116\nEnding Balance\nFF1 277.9.k\n                                 -   \n117\nLess:  Portion not related to transmission\n                                 -   \n118\nLess:  Portion not reflected in rate base\n                                 -   \n119\nSubtotal:  Portion reflected in rate base\nLine 111 - line 112 - line 113\n                                 -   \n120\nLess:  Portion subject to proration (before proration)\nLine 135 Col. D\n                                 -   \n121\nPortion subject to averaging (before averaging)\nLine 114 - line 115\n                                 -   \n122\nEnding balance of portion subject to proration (prorated)\nLine 135 Col. H\n                                 -   \n123\nAverage balance of portion subject to averaging\n(Line 110 + line 116) / 2\n                                 -   \n124\nAmount reflected in rate base\nLine 117 + line 118\n                                 -   Enter on line 4\n125\n126\nAccount 283 - Accumulated Deferred Income Taxes\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n(k)\n(l)\n(m)\n(n)\n127\nMonth\nYear\nActual Monthly Activity\n128\nDecember 31,\n-\n NA                                  -   \nNA\n                       - \n NA                                 -   \n NA \n NA \n NA \n NA \n NA                                   -   \n129\nJanuary \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n130\nFebruary\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n131\nMarch \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n132\nApril\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n133\nMay\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n134\nJune\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n135\nJuly\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n136\nAugust \n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n137\nSeptember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n138\nOctober\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n139\nNovember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n140\nDecember\n-\n                                 -                                    -   \n0\n                       -                                 -                                    -   \n                                   -                                     -                                        -                                        -                                        -                                     -   \n141\nTotal \n                                 -   \n                                   -                                     -   \n142\n143\n144\n145\n146\nAmount\ndebit / <credit>\nNote 5 - Accumulated deferred income tax activity in account 282 subject to the proration rules relates differences between depreciation methods and lives for public utility property \nand any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)\nDifference between \nprojected monthly and \nactual monthly activity\n(See Note 7.)\nPreserve projected \nproration when actual \nmonthly and projected \nmonthly activity are \neither both increases or \ndecreases.  \n(See Note 8.)\nFifty percent of the \ndifference between \nprojected and actual activity \nwhen actual and projected \nactivity are either both \nincreases or decreases.  \n(See Note 9.)\nFifty percent of actual \nactivity (Col I) when \nprojected activity is an \nincrease while actual \nactivity is a decrease OR \nprojected activity is a \ndecrease while actual \nactivity is an increase.\n(See Note 10.)\nBalance reflecting \nproration or averaging \n(See Note 11.)\nAmount\ndebit / <credit>\nNote 6 - Accumulated deferred income tax activity in account 283 subject to the proration rules relates differences between depreciation methods and lives for public utility property \nand any other amounts subject to the Section 168 or other normalization requirements.\nForecasted Monthly \nActivity\ndebit / <credit>\nForecasted Month-\nend Balance\ndebit / <credit>\nDays until End \nof Test Period\nDays in Test \nPeriod\nProrated Forecasted \nMonthly Activity\ndebit / <credit>\n(c) X (e) X (f)\nForecasted  Prorated \nMonth-end Balance\ndebit / <credit>\nPrior Month Col. (h) + \nCurrent Month Col. (g)\nDifference between \nprojected monthly and \nactual monthly activity\n(See Note 7.)\nPreserve projected \nproration when actual \nmonthly and projected \nmonthly activity are \neither both increases or \ndecreases.  \n(See Note 8.)\nFifty percent of the \ndifference between \nprojected and actual activity \nwhen actual and projected \nactivity are either both \nincreases or decreases.  \n(See Note 9.)\nFifty percent of actual \nactivity (Col I) when \nprojected activity is an \nincrease while actual \nactivity is a decrease OR \nprojected activity is a \ndecrease while actual \nactivity is an increase.\n(See Note 10.)\nBalance reflecting \nproration or averaging \n(See Note 11.)\nNote 7  -  Column J is the difference between actual monthly and projected monthly activity (Column I minus Column C).  Specifically, if projected and actual activity are both \npositive, a negative in Column J represents over-projection (i.e., the amount of projected activity that did not occur) and a positive in Column J represents under-projection (i.e., the \nexcess of actual activity over projected activity). If projected and actual activity are both negative, a negative in Column J represents under-projection (i.e., the excess of actual \nactivity over projected activity) and a positive in Column J represents over-projection (i.e., the amount of projected activity that did not occur). \nNote 8  -  Column K preserves the effects of ADIT proration from the projected revenue requirement when actual monthly and projected monthly activity are either both increases or \ndecreases.  Specifically, if Column J indicates that ADIT activity was over-projected, enter Column G x [Column I / Column C].  If Column J indicates that ADIT activity was under-\nprojected, enter the amount from Column G and complete Column L).  In other situations, enter zero.\nNote 9  -  Column L applies when (1) Column J indicates that ADIT activity was under-projected AND (2) actual monthly and projected monthly activity are either both increases or \nboth decreases.  Enter 50 percent of the amount from Column J.  In other situations, enter zero.  The ADIT activity in column L is multiplied by 50 percent to reflect averaging of rate \nbase to the extent that the proration requirement has not been applied to a portion of the monthly ADIT activity.\nNote 10  -  Column M applies when (1) projected monthly activity was an increase while actual monthly activity was a decrease OR (2) projected monthly activity was a decrease \nwhile actual monthly activity was an increase.  Enter 50 percent of the amount of actual monthly activity (Col I).  In other situations, enter zero.  The ADIT activity in column M is \nmultiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly ADIT activity.\nNote 11  -  Column N is computed by adding the prorated monthly ADIT activity, if any, from Column K to the portion of monthly ADIT activity, if any, from Column L or M to the \nbalance at the end of the prior month."},{"page":31,"startToken":12452,"endToken":12665,"text":"LS Power Grid New York Corporation I\nAttachment 6d - Accumulated Deferred Income Taxes (ADIT) Detail Worksheet\nActual Annual Transmission Revenue Requirement (True-up Adjustment)\nFor the 12 months ended 12/31/____\n-\n-\n-\nComposite income tax rate\n0.00%\n0.00%\n0.00%\nExplanation\nAccount 190 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nExcluded from rate base\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nTotal Temporary Differences - account 190\n                         -                            -                            -   \nTotal DTA / <DTL> - account 190\n                         -                            -                            -   \nAccount 281 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nExcluded from rate base\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nTotal Temporary Differences - account 281\n                         -                            -                            -   \nTotal DTA / <DTL> - account 281\n                         -                            -                            -   \nAmount - \nbeginning of \nyear\nAmount during \nthe year\nAmount - end of \nyear"},{"page":32,"startToken":12665,"endToken":12843,"text":"Account 282 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nTax depreciation\n                         -                            -                            -   \nBook depreciation of tax basis\n                         -                            -                            -   \nItem 3\n                         -                            -                            -   \nItem 4\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nItem 3\n                         -                            -                            -   \nItem 4\n                         -                            -                            -   \nItem 5\n                         -                            -                            -   \nItem 6\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nExcluded from rate base\nAFUDC-equity accrual\n                         -                            -                            -   \nAFUDC-equity - book depreciation\n                         -                            -                            -   \nItem 3\n                         -                            -                            -   \nItem 4\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nTotal Temporary Differences - account 282\n                         -                            -                            -   \nDTA / <DTL> - account 282\n                         -                            -                            -   \nAccount 283 (+ = debit for DTA/DTL amounts)\nIncluded in rate base and subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nIncluded in rate base but not subject to proration\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nExcluded from rate base\nItem 1\n                         -                            -                            -   \nItem 2\n                         -                            -                            -   \nSubtotal of temporary differences\n                         -                            -                            -   \nDTA / <DTL> for such temporary differences\n                         -                            -                            -   \nTotal Temporary Differences - account 283\n                         -                            -                            -   \nDTA / <DTL> - account 283\n                         -                            -                            -"},{"page":33,"startToken":12843,"endToken":13144,"text":"LS Power Grid New York Corporation I\nAttachment 7 - Depreciation and Amortization Rates\nFor the 12 months ended 12/31/____\n Line \n Account Number \n FERC Account \n Rate (Annual)Percent \n  TRANSMISSION PLANT  \n(Note A)\n              1 350.2\n Land Rights \n1.43%\n              2 352\n Structures and Improvements \n1.60%\n              3 353\n Station Equipment \n2.06%\n              4 354 \n Towers and Fixtures \n2.06%\n              5 355 \n Poles and Fixtures\n2.06%\n              6 356 \n Overhead Conductor and Devices \n2.06%\n              7 357 \n Underground Conduit \n1.40%\n              8 358 \n Underground Conductor and Devices \n1.75%\n              9 359 \n Roads and Trails \n1.00%\n GENERAL PLANT \n            10 390\nStructures and Improvements\n1.75%\n            11 391\nOffice Furniture & Equipment\n12.50%\n            12 391.1\nComputer Hardware\n12.50%\n            13 392\nTransportation Equipment\n10.00%\n            14 393\nStores Equipment\n12.50%\n            15 397\nCommunication Equipment\n25.00%\n INTANGIBLE PLANT \n            16 301\nOrganization\n1.85%\n            17 302\nFranchises and Consents\n1.85%\n            18 303\nMiscellaneous  Intangible Plant / Computer Software\n6.67%\n            19 303.1\nContributions in Aid of Construction\n Note B\n Notes \n A \nThese depreciation rates shall stay in effect until changed pursuant to a Commission order emanating from \n an FPA Section 205 or Section 206 filing.\n B \nIn the event a Contribution in Aid of Construction (CIAC) is made for a transmission facility, the transmission  \n depreciation rates above will be weighted based on the relative amount of underlying plant booked to the accounts \n shown in lines 1-9 above and the weighted average depreciation rate will be used to amortize the CIAC. The life of a\n facility subject to a CIAC will be equivalent to the depreciation rate calculated above, i.e., 100% ÷ deprecation rate = life\n in years. The estimated life of the facility or rights associated with the facility will not change over the life of a CIAC\n without prior FERC approval."},{"page":34,"startToken":13144,"endToken":13883,"text":"LS Power Grid New York Corporation I\nWorksheet - Annual Excess or Deficient Accumulated Deferred Income Taxes Worksheet\nAnnual Transmission Revenue Requirement\nFor the 12 months ended 12/31/____\nLine No. \n1\nPurpose of worksheet\n2\n3\nDescription of changes in tax law\n4\nNote 1a - The composite tax rates used for the remeasurement of ADIT balances are:\n5\n6\nHistorical\nNew\n7\nFederal income tax rate\n0%\n0%\n8\nState income tax rate\n0%\n0%\n9\nComposite federal/state income tax rate\n0%\n0%\n10\nTax gross-up factor\n0.00000\n0.00000\n11\nNote 1b - Describe change in tax law.\n12\nSummary of re-measurement of ADIT resulting from the 2017 decrease in federal income tax rate\n13\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n14\nAccount\n15\n190\n                -   \n16\n281 (enter negative)\n                -   \n17\n282 (enter negative)\n                -   \n18\n283 (enter negative)\n                -   \n19\nTotal\n                             -                               -                               -                               -                               -                               -                               -                               -                               -                               -                               -                               -                               -                               -                               -   \n                             -   \n20\nSummary of entry related to ADIT affecting rate base\n                             -                               -   \n                             -   \n                             -                               -                               -                               -                               -                               -                   -   \n21\nEffect on rate base prior to re-measurement\n                             -   \n                -   \n22\nEffect on rate base after re-measurement\n                             -   \n                             -   \n                             -   \n                             -   \n                -   \n23\nThe purposes of this portion of the worksheet are to: \n- describe legislation resulting in remeasurement of ADIT accounts, \n- explain how any ADIT accounts were re-measured, \n- explain the excess or deficient ADIT contained therein,  \n- explain the accounting for any excess or deficient amounts in Accounts 182.3 (Other Regulatory Assets) and 254 (Other Regulatory Liabilities),\n- reconcile the amounts of excess or deficient ADIT determined as a result of each specific change in tax law (i.e., unrecovered regulatory assets and unrefunded regulatory liabilities comprising the Rate Base Adjustment \nMechanism) as of the beginning and end of the current test period,\n- indicate whether each excess or deficient ADIT amount is protected (i.e., subject to the normalization rules) or unprotected (i.e., not subject to the normalization rules),\n- indicate the amount of amortization of the excess or deficient ADIT returned or recovered through rates (i.e., the Income Tax Allowance Adjustment Mechanism) during the current period,\n- indicate the accounts to which the excess or deficient ADIT are amortized,\n- indicate the amortization period of the excess or deficient ADIT being returned or recovered through rates, and\n- describe the method of amortization each excess or deficient ADIT amount.\nBalance Prior to \nChange in Law\nPortion Affecting \nRate Base\nBalance Re-\nmeasured after \nChange in Law\nPortion Affecting \nRate Base Re-\nmeasured after \nChange in Law\nDebit or <Credit> \nto ADIT Affecting \nRate Base\nDebit or <Credit> \nto Account 182.3\nPortion of Debit \nor <Credit> to \nAccount 182.3 \nAffecting Rate \nBase\nDebit or <Credit> \nto Account 254\nPortion of Debit \nor <Credit> to \nAccount 254 \nAffecting Rate \nBase\nADIT on \nRegulatory Asset \nor Liability\nAccount 190 or \n283\nADIT on \nRegulatory Asset \nor Liability \nAffecting Rate \nBase\nAccount 190 or \n283\nDebit or <Credit> \nto Account 410.1\nDebit or <Credit> \nto Account 411.1\nDebit or <Credit> \nto Account 410.2\nDebit or <Credit> \nto Account 411.2\nNote 2 - Explanation of how ADIT accounts are re-measured upon a change in income tax law\nDeferred tax assets and liabilities are adjusted (re-measured) for the effect of the changes in tax law (including tax rates) in the period that the change is enacted.  Adjustments are recorded in the appropriate deferred tax balance sheet \naccounts (Accounts 190, 281, 282 and 283) based on the nature of the temporary difference and the related classification requirements of the accounts.   If as a result of action or expected action by a regulator, it is probable that the \nfuture increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, a regulatory asset or liability is recognized in Account 182.3 (Other Regulatory \nAssets), or Account 254 (Other Regulatory Liabilities), as appropriate, for that probable future revenue or reduction in future revenue.  Re-measurements of deferred tax balance sheet accounts may also result in re-measurements of \ntax-related regulatory assets or liabilities that had been recorded prior to the change in tax law.  If is not probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or \nreturned to customers through future rates, tax expense is recognized in Account 410.2 (Provision for Deferred Income Taxes, Other Income or Deductions) or tax benefit is recognized in Account 411.2 (Provision for Deferred \nIncome Taxes-Credit, Other Income or Deductions), as appropriate."},{"page":35,"startToken":13883,"endToken":14127,"text":"24\nRate Base Adjustment Mechanism - Summary\n25\nProjected Revenue Requirement\nActual Revenue Requirement (True-up)\n26\nAccount\nAmount\nAmount\n27\n182.3 (debit or <credit>)\n28\n254 (debit or <credit>)\n29\nTotal Excess / Deficient ADIT\n                             -   \n                             -   \n30\nRate Base Adjustment Mechanism - Reconciliation of Beginning and End of Test Period Balances - Projected\n31\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n32\nDescription (+ = debit, <> = credit)\nAmortization period and method\n33\nItem 1\n                             -   \n34\n                             -   \n35\n                             -   \n36\nItem …\n37\nTotal for account 182.3\n                             -                               -                               -                               -                               -   \n38\nItem 1\n                             -   \n39\n                             -   \n40\n                             -   \n41\nItem …\n42\nTotal for account 254\n                             -                               -                               -                               -                               -   \n43\nTotal excess or deficient ADIT\n                             -                               -                               -                               -                               -   \n44\nIncome Tax Allowance Mechanism - Projected\n45\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n46\nDescription (+ = debit, <> = credit)\n47\nItem 1\n                             -                               -   \n                             -   \n48\n                             -                               -   \n                             -   \n49\n                             -                               -   \n                             -   \n50\nItem …\n51\nTotal for account 182.3\n                             -                               -                               -                               -                               -                               -                               -                               -   \n52\nItem 1\n                             -   \n                             -   \n                             -   \n53\n                             -   \n                             -   \n                             -   \n54\n                             -   \n                             -   \n                             -   \n55\nItem …\n56\nTotal for account 254\n                             -                               -                               -                               -                               -                               -                               -                               -   \n57\nTotal amortization and offsetting entries\n                             -                               -                               -                               -                               -                               -                               -                               -   \n58\n                             -   \n59\n60\nNote\n61\nNote \n62\nNote \nBalance at \nBeginning of Year \n- \nProjected\nRemeasurement \nof ADIT - \nProjected\n(Note 3)\nAnnual \nAmortization - \nProjected\n(Note 4)\nOther \nAdjustments - \nProjected\n(Note 5)\nBalance at End of \nYear - \nProjected\n(d)+(e)+(f)+(g)\nWhether subject \nto normalization \nrules\n(Note 6)\nAnnual \nAmortization \nfrom Table Above\nDebit or <Credit> \nto Account 410.1\nDebit or <Credit> \nto Account 411.1\nDebit or <Credit> \nto Account 410.2\nDebit or <Credit> \nto Account 411.2\nDebit or <Credit> \nto Account 190\nDebit or <Credit> \nto Account 283\nNote"},{"page":36,"startToken":14127,"endToken":14330,"text":"63\nRate Base Adjustment Mechanism - Reconciliation of Beginning and End of Test Period Balances - Actual\n64\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n(g)\n(h)\n(i)\n(j)\n65\nDescription (+ = debit, <> = credit)\nAmortization period and method\n66\nItem 1\n                             -   \n67\n                             -   \n68\n                             -   \n69\nItem …\n70\nTotal for account 182.3\n                             -                               -                               -                               -                               -   \n71\nItem 1\n                             -   \n72\n                             -   \n73\n                             -   \n74\nItem …\n75\nTotal for account 254\n                             -                               -                               -                               -                               -   \n76\nTotal excess or deficient ADIT\n                             -                               -                               -                               -                               -   \n76\nIncome Tax Allowance Mechanism - Actual\n77\n(a)\n(b)\n(c)\n(d)\n(e)\n(f)\n78\nDescription (+ = debit, <> = credit)\n79\nItem 1\n                             -   \n80\n                             -   \n81\n                             -   \n82\nItem …\n83\nTotal for account 182.3\n                             -                               -                               -                               -                               -                               -                               -                               -   \n84\nItem 1\n                             -   \n                             -   \n                             -   \n85\n                             -   \n                             -   \n                             -   \n86\n                             -   \n                             -   \n                             -   \n87\nItem …\n88\nTotal for account 254\n                             -                               -                               -                               -                               -                               -                               -                               -   \n89\nTotal amortization and offsetting entries\n                             -                               -                               -                               -                               -                               -                               -                               -   \n90\n                             -   \n91\nNote \n92\nNote \n93\nNote \n94\nNote \nBalance at \nBeginning of Year \n- \nProjected\nRemeasurement \nof ADIT - \nActual\n(Note 7)\nAnnual \nAmortization - \nActual\n(Note 8)\nOther \nAdjustments - \nActual\n(Note 9)\nBalance at End of \nYear - \nProjected\n(d)+(e)+(f)+(g)\nWhether subject \nto normalization \nrules\n(Note 10)\nAnnual \nAmortization\nDebit or <Credit> \nto Account 410.1\nDebit or <Credit> \nto Account 411.1\nDebit or <Credit> \nto Account 410.2\nDebit or <Credit> \nto Account 411.2\nDebit or <Credit> \nto Account 190\nDebit or <Credit> \nto Account 283"}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 4","method":"page range","endPage":5,"endAt":0,"startToken":0,"endToken":1217},{"p":5,"at":0,"title":"Pages 5 to 8","method":"page range","endPage":9,"endAt":0,"startToken":1217,"endToken":4425},{"p":9,"at":0,"title":"Pages 9 to 12","method":"page range","endPage":13,"endAt":0,"startToken":4425,"endToken":5251},{"p":13,"at":0,"title":"Pages 13 to 16","method":"page range","endPage":17,"endAt":0,"startToken":5251,"endToken":6427},{"p":17,"at":0,"title":"Pages 17 to 20","method":"page range","endPage":21,"endAt":0,"startToken":6427,"endToken":7942},{"p":21,"at":0,"title":"Pages 21 to 24","method":"page range","endPage":25,"endAt":0,"startToken":7942,"endToken":9194},{"p":25,"at":0,"title":"Pages 25 to 28","method":"page range","endPage":29,"endAt":0,"startToken":9194,"endToken":10190},{"p":29,"at":0,"title":"Pages 29 to 32","method":"page range","endPage":33,"endAt":0,"startToken":10190,"endToken":12843},{"p":33,"at":0,"title":"Pages 33 to 36","method":"page range","endPage":36,"endAt":3061,"startToken":12843,"endToken":14330}]}