{"document":{"slug":"rec-20261116-5286","title":"LSPGNY 205: Proposed Revisions re: RS10 Large Load-Driven Upgrade Cost Recovery","issued":"2026-11-16","accession":"20261116-5286","docket":"ER27-518-000","group":"NYISO and New York transmission owners’ large-load tariff revisions","filer":"LS Power Grid New York Corporation INew York Independent System Operator, Inc.","kind":"tariff filing","file":"sources/filings/text/20261116-5286_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5286","tier":"record","sha256":"5066b78c9fce11ad7bc4a27d95dbf2a73febc0eee583b1743b7a796dabac0e16","pages":13,"tokens":4338,"emptyPages":[],"textThemes":["cost","credit","study"]},"pages":[{"page":1,"startToken":0,"endToken":323,"text":"13 Corporate Drive, Halfmoon, NY 12065 \nlspowergrid.com  \nNovember 16, 2026 \nVIA ETARIFF \nThe Honorable Debbie-Anne A. Reese \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, N.E. \n \nWashington, D.C. 20426 \n \nRe:  \nLS Power Grid New York Corporation I, Docket No. ER27-___-000 \nNew York Independent System Operator, Inc., Docket No. EL26-69-000 \nProposed Revisions to Rate Schedule 10 of the NYISO OATT to Provide \nfor Large Load-Driven Upgrade Cost Recovery \n \nDear Secretary Reese: \nPursuant to section 205 of the Federal Power Act (“FPA”)1 and Part 35 of the \nFederal Energy Regulatory Commission’s (“FERC” or “Commission”) regulations, 2 and \nin response to the Commission’s order instituting the show-cause proceeding in \nNew York Independent System Operator, Inc.,3 LS Power Grid New York Corporation \nI (“LS Power Grid”)4 submits revisions to Section 6.10 (Rate Schedule 10) of the \nNYISO OATT, specifically the generally applicable provisions of Rate Schedule 10 \nand LS Power Grid’s company-specific provisions in Attachment 1 to Rate Schedule \n10, Section 6.10.7. LS Power Grid respectfully requests that the Commission accept \nthe proposed tariff revisions to become effective January 16, 2027, sixty-one (61) \ndays after filing, consistent with the Commission’s prior notice requirement, 5 and \ngrant any necessary waivers. \n \n1 16 U.S.C. § 824d (2022). \n2 18 C.F.R. Pt. 35 (2026). \n3 195 FERC ¶ 61,216 (2026) (“Show Cause Order”). \n4 The New York Independent System Operator, Inc. (\"NYISO\") is submitting this ﬁling via eTariff on \nbehalf of LS Power Grid solely in its role as the tariff administrator of the NYISO Open Access \nTransmission Tariff (\"OATT\"). The burden of demonstrating that the proposed tariff amendments are \njust and reasonable rests with LS Power Grid, the sponsoring party. The NYISO takes no position on \nany substantive aspect of the ﬁling at this time and reserves the right to ﬁle comments and/or \nprotest the ﬁling. \n5 18 C.F.R. § 35.3(a)(1)."},{"page":2,"startToken":323,"endToken":709,"text":"Page 2 \nI. \nIntroduction and Summary of Filing \nThe proposed revisions establish a transparent, company-specific mechanism for \nLS Power Grid to recover the costs of transmission upgrades that are identified as \nnecessary, in whole or in part, to provide transmission service to an Eligible \nCustomer6 on behalf of a Large Load (“Large Load-Driven Upgrades”). The revisions \ninclude a pro forma Large Load Cost Recovery Agreement (“CRA”), revisions to the \nFormula Rate Template (“Template”) and Formula Rate Implementation Protocols \n(“Protocols”), cost-allocation provisions, and new Rate Schedule 10 provisions \ngoverning NYISO billing, collection, security, remittance, data exchange, and formula \nrate treatment of CRA amounts. \nThe filing responds to the Commission’s preliminary concerns regarding potential \ncost shifting by assigning the wholesale payment obligation to the Eligible \nCustomer that takes or requests transmission service on behalf of the Large Load \nFacility and by requiring Construction Security, Operational Security, NYISO billing \nand collection, Security-draw procedures, and direct collection rights. The \nframework is designed to mitigate the risk that other customers bear costs \nassociated with a Large Load Facility that is delayed, reduced, or does not \nmaterialize, while preserving NYISO’s existing roles and LS Power Grid’s Formula \nRate recovery. \nNo Large Load-Driven Upgrade is listed in proposed Table 1 as of the requested \neffective date. Accordingly, the filing does not change currently effective Regulated \nTransmission Facilities Charge (“RTFC”) rates under the NYISO OATT or impose a \nLarge Load Charge on any customer upon effectiveness. The proposed revisions \nalso make conforming corrections to existing Formula Rate Template and Protocol \nprovisions, including provisions governing the cost-of-capital and true-up \ncalculations. Those corrections do not revise the currently effective RTFC; they will \nbe reflected, as applicable, in future Annual Projections, Annual Updates, and True-\nUp Adjustments under the Formula Rate. An individual Large Load-Driven Upgrade \nmay be included in the RTFC only after a separate FPA section 205 filing adds that \nupgrade to Table 1 and the Commission accepts the designation. \n \n6 Capitalized terms used but not otherwise deﬁned in this transmittal letter have the meanings \nassigned to them in the NYISO OATT, including the proposed revisions to Rate Schedule 10 and \nAttachment 1 thereto, the proposed pro forma Large Load Cost Recovery Agreement (“CRA”) set forth \nin Appendix 1 to Attachment 1, and, as applicable, the proposed Formula Rate Template and Formula \nRate Implementation Protocols."},{"page":3,"startToken":709,"endToken":1059,"text":"Page 3 \nII. \nBackground \nA. LS Power Grid and its Rate Schedule 10 Recovery \nLS Power Grid is a non-incumbent Transmission Owner in the NYISO region. LS \nPower Grid and the New York Power Authority (“NYPA”) developed Segment A of \nthe AC Transmission Public Policy Transmission Need, a 345 kV project between the \nMarcy/Edic and New Scotland substations (“AC Transmission Project”), which is \nnow in service as part of Central East Energy Connect. LS Power Grid has no \nfranchised retail service territory and no Transmission Service Charge under \nAttachment H of the NYISO OATT. LS Power Grid currently recovers its \nCommission-accepted revenue requirement exclusively under Rate Schedule 10 \nthrough its formula rate and the associated RTFC. \nB. Show Cause Order and Stakeholder Process \nOn June 18, 2026, the Commission issued the Show Cause Order, instituting a \nsection 206 proceeding in Docket No. EL26-69-000 and identifying concerns \nabout cost shifting, transparency, minimum-revenue commitments, credit support, \nand the rate treatment of large load payments.7 The Commission later granted \nabeyance through November 16, 2026, for respondents that make timely section \n205 filings addressing its preliminary findings.8 \nLS Power Grid participated in NYISO and stakeholder discussions concerning large \nload integration and cost recovery. Those discussions confirmed that a \ntransmission owner without retail customers needs a wholesale mechanism to \nprotect its other transmission customers when a Large Load Facility requires a \nLarge Load-Driven Upgrade to that transmission owner’s facilities. LS Power Grid’s \nproposal is designed to operate alongside NYISO’s study and interconnection \nprocedures. It does not displace the separate arrangements that an Eligible \nCustomer must enter into with the owner of an Affected System for an Affected \nSystem Upgrade.9 \nIII. \nDescription of the Proposed Revisions \nA. Rate Schedule 10 Eligibility and Cost Allocation \nNew Section 6.10.1.1(xii) identifies a Large Load-Driven Upgrade of a Transmission \nOwner or Other Developer that does not recover a transmission revenue \n \n7 Show Cause Order at PP 72-91. \n8 N.Y. Indep. Sys. Operator, Inc., 196 FERC ¶ 61,130 (2026) (granting abeyance). \n9 See CRA §§ 4.2 and 6.2 and Schedule 1."},{"page":4,"startToken":1059,"endToken":1486,"text":"Page 4 \nrequirement through an Attachment H Transmission Service Charge or NYPA \nTransmission Adjustment Charge as an eligible project category, subject to \nCommission acceptance of the applicable Transmission Owner’s or Other \nDeveloper’s designation. Section 6.10.1.2 confirms that the otherwise-applicable \nexclusion for projects outside Attachment Y does not exclude such an eligible Large \nLoad-Driven Upgrade. The definition cross-references NYISO’s proposed definition \nof “Large Load” in Section 1.12 of the OATT, which is separately being filed. The \nprovisions preserve the exclusion for directly assigned facilities that are paid by the \nEligible Customer and not included in the Transmission Owner’s rate base. \nUnder Sections 6.10.3.7.2 and 6.10.7.3.2, a Large Load-Driven Upgrade becomes an \nEligible Project only after Commission acceptance of a section 205 filing adding it \nto Table 1. That section 205 designation filing will provide the appropriate \nopportunity to evaluate the particular upgrade, the supporting study record, and \nthe application of the CRA protections before the upgrade is included in the RTFC. \nEach designated Large Load-Driven Upgrade is recovered together with the AC \nTransmission Project through a single RTFC and allocated to Responsible LSEs in \nthe same manner as the AC Transmission Project. The assignment, reassignment, \nreduction, or cessation of service by the Large Load does not itself modify that \nCommission-accepted RTFC allocation. \nB. Pro Forma CRA \nThe pro forma CRA and Limited Acknowledgment are included as Appendix 1 to \nAttachment 1 to Rate Schedule 10, Section 6.10.7.5.1. The CRA is entered into by LS \nPower Grid and the Eligible Customer. The Large Load Customer executes a Limited \nAcknowledgment but does not become a party to the Eligible Customer’s wholesale \npayment obligations. NYISO is not a party to the CRA; its billing, collection, security, \nremittance, and data functions arise under the Rate Schedule 10 Large Load \nProvisions.10  \nFor each Covered Upgrade, the CRA establishes a fixed Annual Minimum \nTransmission Revenue Contribution (“Annual MTRC”) under the Schedule 5 MTRC \nCalculation Template. The Annual MTRC is initially estimated and is redetermined to \nthe Final Annual MTRC on the Final MTRC Determination Date, which occurs no later \nthan one year after the applicable Upgrade In-Service Date after actual capital \ncosts are known and accounted for. Schedule 5 uses the applicable capital \nstructure, return on equity, cost of debt, tax, depreciation, and expense-allocation \ninputs to establish the levelized Fixed Charge Rate and Final Annual MTRC. The \n \n10 See id. Article 1 and Limited Acknowledgment; Rate Schedule 10 §§ 6.10.3.7 and 6.10.7.4."},{"page":5,"startToken":1486,"endToken":1906,"text":"Page 5 \nMTRC Term begins on the actual Upgrade In-Service Date and ends on the day \nimmediately preceding its twentieth anniversary, with the first and final Rate Years \nprorated. The CRA does not reset the final contractual Annual MTRC through \nordinary annual formula rate updates, except for the limited prospective \nadjustments expressly identified in the CRA.11 \nThe twenty-year MTRC Term is a defined contractual revenue-support period, not \nthe depreciable life of a Covered Upgrade. Schedule 5 establishes a levelized \nAnnual MTRC for that period, while the Covered Upgrade remains subject to \nordinary Formula Rate depreciation and other cost-of-service treatment. The term \nprovides a substantial, predictable period of revenue responsibility for the Large \nLoad-Driven Upgrade and is reinforced by Operational Security based on the \nremaining Cumulative Revenue Responsibility and a Termination Fee equal to that \nremaining responsibility less any Supplemental MTRC already billed and remaining \nunpaid upon an early termination or permanent cessation of service. The excluded \nunpaid bills remain separately payable.12 \nThe Eligible Customer owes a Supplemental MTRC to the extent Qualifying \nTransmission Revenues attributable to the Large Load Facility are less than the \napplicable Annual MTRC. The CRA provides for annual reconciliation. Construction \nSecurity protects pre-service commitments and cancellation exposure. After an \nupgrade enters service, Operational Security equals the nominal remaining \nCumulative Revenue Responsibility, subject to Qualifying Retail Security Support \nthat is legally available for the corresponding wholesale obligation. A termination or \npermanent cessation after in-service triggers a Termination Fee equal to the \nRemaining Cumulative Revenue Responsibility less any Supplemental MTRC already \nbilled and remaining unpaid as of the effective termination or cessation date, as \nprovided in CRA Section 3.3.4. Those unpaid bills remain separately payable as \nLarge Load Charges. NYISO’s receipt of the Termination Fee in full discharges only \nthe remaining responsibility included in the fee and does not discharge the \nexcluded unpaid bills. The Termination Fee is an accelerated contractual \ntermination charge, not a penalty. Rather than producing a one-time Formula Rate \nCredit, the Termination Fee Balance is held by NYISO and remitted as Annual \nTermination Fee Remittances over the remaining MTRC Term, so the resulting \nFormula Rate Credits follow the annual schedule that would have applied absent \ntermination.13 \n \n11 See CRA §§ 3.2 and 6.3.1 and Schedule 5. \n12 See id. §§ 3.3.4–3.3.6, 6.3, 6.7, and Article 7; Schedule 5. \n13 See id. §§ 3.3.4–3.3.6, 6.4–6.8, and Article 7; Rate Schedule 10 § 6.10.7.4."},{"page":6,"startToken":1906,"endToken":2295,"text":"Page 6 \nThe CRA requires Operational Security equal to one hundred percent (100%) of the \nnominal Remaining Cumulative Revenue Responsibility. The Commission \npreliminarily found that “an Eligible Customer may include a credit support or other \nfinancial security posted by a large load as part of a retail agreement to avoid \ncreating duplicative credit support requirements.”14 To avoid duplicative collateral, \nthe direct Operational Security requirement may be reduced dollar-for-dollar by \nqualifying retail security support only where the Eligible Customer delivers a current \nRetail Security Certification. The certification must confirm that the retail Large \nLoad Customer has posted security available to the Eligible Customer for the \ncorresponding wholesale obligations and that the Eligible Customer has \nenforceable draw or application rights, or the benefit of a binding undertaking, \npermitting it to use the proceeds for that purpose. Qualifying retail security support \ndoes not reduce the Eligible Customer’s underlying payment obligations, does not \napply to Construction Security or Pre-In-Service Termination Costs, and is subject \nto notice and verification requirements if the support is reduced, drawn, expires, is \nnot renewed, or otherwise may be impaired.15 \nLS Power Grid recognizes that, after further stakeholder experience and discussion, \na lower Operational Security requirement may be appropriate in defined \ncircumstances where an alternative credit support arrangement provides \nequivalent protection against a cost shift. The Show Cause Order also invited \nfurther consideration of alternative mechanisms that could provide comparable or \ngreater protection against cost shifting.16 This filing nonetheless adopts a \nconservative requirement of Operational Security equal to one hundred percent \n(100%) of the nominal Remaining Cumulative Revenue Responsibility, subject only \nto the limited treatment of qualifying retail security support described above. LS \nPower Grid intends to work with NYISO and interested stakeholders to evaluate \nwhether, and under what objectively defined circumstances, a different security \nlevel or alternative credit support structure could provide comparable protection. \nAny future change to the security requirement would be submitted to the \nCommission for review and acceptance under section 205 of the Federal Power \nAct. \nC. Revenue Attribution, Allocation, and Rate Treatment \nQualifying Transmission Revenues are not a separate retail or load-based charge \nimposed by LS Power Grid. They are the portion of RTFC revenues assessed on the \n \n14 Show Cause Order at P 89. \n15 See CRA Article 7 and Schedule 3. \n16 Show Cause Order at PP 88–89."},{"page":7,"startToken":2295,"endToken":2660,"text":"Page 7 \nActual Energy Withdrawals of the Large Load Facility, collected from the \nResponsible LSE or LSEs serving that facility, and remitted to LS Power Grid that is \nattributable to the applicable Covered Upgrade and reduces the RTFC otherwise \ncollected from other Responsible LSEs. Schedule 2 to the CRA provides a \nreproducible methodology using the applicable metering data, RTFC rate, Load \nZone or Subzone allocation, and Covered Upgrade Revenue Share.17 \nWhere an upgrade is driven by more than one Large Load Facility, Schedule 1 \nidentifies an Initial Allocation Percentage for each Large Load Customer based on \nthe applicable final study and allocation methodology. That allocation accounts for \nthe large loads studied individually, jointly, or in a cluster; their differing requested \nservice levels, development phases, and facility configurations; and any portion of \nthe facility that serves other system needs or customers. The aggregate allocation \nto all Large Load Customers may not exceed one hundred percent (100%), and any \nunallocated portion remains subject to the otherwise applicable Rate Schedule 10 \ncost-allocation and recovery rules.18 \nThe CRA does not itself determine whether a facility is directly assigned or included \nin rate base. That determination is made under the applicable NYISO tariff, study \nprocess, and interconnection arrangements. Direct Assignment Facilities and other \nfacilities whose costs are directly assigned to, and paid by, the Eligible Customer \nand are not included in LS Power Grid’s rate base are excluded from the definition \nof Large Load-Driven Upgrades and from the MTRC framework.19 \nCovered Upgrades are separately identified in LS Power Grid’s Formula Rate and \nuse the capital structure and generally applicable return components applicable to \nLS Power Grid under Rate Schedule 10, including any Commission-approved \ngenerally applicable return on equity incentive, as applicable. Covered Upgrades do \nnot receive return on equity incentives that are specific to the AC Transmission \nProject or become subject to the AC Transmission Project’s Competitive Bid \nConcession, cost cap, or other project-specific cost-containment commitments.20 \n \n17 See CRA § 6.2 and Schedule 2. \n18 See id. § 6.3.2–6.3.4 and Schedule 1. \n19 See id. §§ 2.37 (deﬁnition of “Large Load-Driven Upgrades”), 6.2. \n20 See id. § 6.2 and Arzola Testimony."},{"page":8,"startToken":2660,"endToken":3078,"text":"Page 8 \nD. NYISO Billing Security and Remittance Functions \nNew Section 6.10.3.7 confirms that the Attachment-level Large Load Provisions are \npart of Rate Schedule 10, directs NYISO to perform the functions assigned to it \nunder those provisions, distinguishes Large Load Charges from RTFC charges and \nrevenues, and confirms that NYISO does not become a party to a Large Load CRA. \nNew Section 6.10.7.4 requires execution of an applicable CRA and delivery of \nConstruction Security before LS Power Grid undertakes specified construction \ncommitments. It directs NYISO to bill customer-specific Large Load Charges based \non LS Power Grid Charge Statements; hold and administer CRA Security; draw and \napply Security under defined conditions; hold and remit Termination Fees; provide \nload and settlement data; and remit collected amounts to LS Power Grid. The \nprovision separately identifies these charges from RTFC charges and preserves \napplicable NYISO billing and dispute procedures.21  \nThe proposed Template and Protocols provide the rate treatment and supporting \nworkpapers. In the Annual Projection, Large Load CRA Revenue consists of \nprojected Supplemental MTRC, including any prior-period Supplemental MTRC \ntrue-up adjustment, and projected Annual Termination Fee Remittances. In the \nAnnual Update, the Formula Rate Credit reflects Actual Large Load CRA Revenue \nactually received by LS Power Grid during the Rate Year, including Supplemental \nMTRC payments collected and remitted by NYISO, Applied Security Proceeds \napplied and remitted to LS Power Grid, direct recoveries from an Eligible Customer \napplied to Supplemental MTRC obligations, and Annual Termination Fee \nRemittances. The Annual Update replaces the projected credit with actual cash \nreceipts, and any difference is addressed through the Formula Rate true-up \nmechanism in the next Rate Year, with the applicable Formula Rate interest \ntreatment. An Eligible Customer remains liable for all unpaid Large Load Charges, \nand the CRA’s Security and collection provisions are designed to mitigate the risk of \nnonpayment.22 \nE. Supporting Testimony and Illustrative Exhibits \nMr. Patrick Hayes’ testimony (Exhibit No. GNY-100) explains the need for the CRA \nframework and describes the operation of the Annual MTRC, Supplemental MTRC, \nrevenue responsibility, security, and termination provisions. His supporting exhibits \nprovide an illustrative MTRC Calculation (Exhibit No. GNY-101), an example \nReconciliation Statement (Exhibit No. GNY-102), and an example Charge Statement \n \n21 See Rate Schedule 10 §§ 6.10.3.7 and 6.10.7.4; CRA Articles 5 and 7. \n22 See CRA §§ 6.10.7.4.5, 6.10.7.4.7, and 6.10.7.4.11; CRA §§ 6.6, 6.8, 6.13.5, and Article 7."},{"page":9,"startToken":3078,"endToken":3451,"text":"Page 9 \n(Exhibit No. GNY-103), each of which tracks the corresponding provisions of the \nCRA, including Schedule 5 and Sections 6.4 through 6.8. \nMr. D. Eric Arzola’s testimony (Exhibit No. GNY-200) sponsors the Template and \nProtocol revisions and explains the Formula Rate Credit for Large Load CRA \nRevenue. His supporting exhibits include the clean and marked Formula Rate \nTemplates (Exhibit Nos. GNY-201 and GNY-202), the clean Formula Rate Template \nin native Excel format with all formula intact (Exhibit No. GNY-203), an illustrative \nFormula Rate Template – Annual Projection (Exhibit No. GNY-204), an illustrative \nFormula Rate Template – Annual Update (Exhibit No. GNY-205), and the clean and \nmarked Formula Rate Implementation Protocols (Exhibit Nos. GNY-206 and GNY-\n207). Exhibit No. GNY-205 illustrates the Annual Update, including the customer-\nlevel Supplemental MTRC true-up and the ordinary Formula Rate true-up of \nprojected CRA revenue credits to actual receipts. Together, those materials \ndemonstrate the projected, annual-update, and true-up treatment of Supplemental \nMTRC and Annual Termination Fee Remittances. \nIV. \nThe Proposed Revisions Are Just and Reasonable \nThe proposal materially mitigates the cost-shifting concern identified in the Show \nCause Order. Before in-service, Construction Security and termination-cost \nprovisions protect against cancellation and related exposure. After an upgrade \nenters service, the Annual MTRC, Supplemental MTRC, Required Operational \nSecurity, and termination provisions establish a defined revenue responsibility \nassociated with the service request that caused the upgrade. Required Operational \nSecurity equals one hundred percent (100%) of the nominal Remaining Cumulative \nRevenue Responsibility, subject to any qualifying retail-security support recognized \nunder the CRA. NYISO billing, mandatory Security draws, and LS Power Grid’s direct \ncollection rights further protect against nonpayment. \nThe proposal also supplies the transparency and crediting mechanisms the \nCommission identified. The pro forma CRA in Appendix 1, Table 1, Schedules 1 and 5, \nthe Template and Protocol workpapers, and the Annual Projection and Annual \nUpdate provide a traceable record of the relevant upgrades, customer obligations, \ncredits, billings, and reconciliations. The illustrative MTRC Calculation (Exhibit No. \nGNY-101), example Reconciliation Statement (Exhibit No. GNY-102), and example \nCharge Statement (Exhibit No. GNY-103) further demonstrate the calculation and \nadministration of these requirements. Customer-specific information is protected \nunder CRA § 6.12 and Protocols § 8, while the required public information remains \navailable in aggregated or redacted form as appropriate."},{"page":10,"startToken":3451,"endToken":3803,"text":"Page 10 \nThe proposed use of the existing Rate Schedule 10 RTFC allocation does not assign \nresponsibility for a Large Load-Driven Upgrade to Responsible LSEs on the theory \nthat those LSEs caused the underlying Large Load Facility or its service request. \nRather, once the Commission accepts a designation of a Covered Upgrade in Table \n1, the existing RTFC provides the established mechanism for collecting LS Power \nGrid’s Commission-authorized revenue requirement for that transmission facility. \nThe CRA separately requires the Eligible Customer serving the Large Load Facility to \nprovide the Annual MTRC through Qualifying Transmission Revenues and \nSupplemental MTRC payments, and the Formula Rate credits Actual Large Load \nCRA Revenue dollar-for-dollar against LS Power Grid’s revenue requirement. Thus, \nthe RTFC allocation supplies the collection path, while the CRA framework assigns \nthe relevant payment obligation to the Eligible Customer and materially mitigates \nthe associated risk through Security, NYISO billing and collection, and direct \nenforcement rights. \nFinally, the proposal is appropriately tailored to LS Power Grid. It provides a cost-\nrecovery and security path for a non-incumbent Transmission Owner with no retail \ncustomers or Attachment H Transmission Service Charge. It does not disturb the \ncurrent AC Transmission Project allocation, existing RTFC recovery, NYISO study \nauthority, or the retail arrangements between an Eligible Customer and a Large \nLoad Customer. \nV. \nRequested Effective Date and Waivers \nLS Power Grid requests an effective date of January 16, 2027, sixty-one (61) days \nafter the date of this filing, satisfying the Commission’s sixty-day notice \nrequirement.23 LS Power Grid requests waiver of the cost-of-service-statement \nrequirements of 18 C.F.R. § 35.13, and any other Part 35 requirements that otherwise \nmay apply, to the extent necessary. The requested waivers are appropriate \nbecause the filing establishes a prospective formula rate and contractual \nframework, identifies no Large Load-Driven Upgrade in Table 1, does not change \ncurrently effective RTFC rates, and makes only conforming Formula Rate Template \nand Protocol corrections that will be implemented through the ordinary formula-\nrate processes. \nVI. \nContents of Filing \nLS Power Grid submits the following materials: \n• This transmittal letter; \n \n23 18 C.F.R. § 35.3(a)(1)."},{"page":11,"startToken":3803,"endToken":4132,"text":"Page 11 \n• Clean and marked tariff records revising Rate Schedule 10 and Attachment 1 \nto Rate Schedule 10, including the proposed changes in Sections 6.10.7.3 \nthrough 6.10.7.5 and the pro forma CRA and Limited Acknowledgment in \nAppendix 1, Section 6.10.7.5.1; \n• Direct testimony of Patrick Hayes (Exhibit No. GNY-100) and supporting \nexhibits: illustrative MTRC Calculation (Exhibit No. GNY-101), example \nReconciliation Statement (Exhibit No. GNY-102), and example Charge \nStatement (Exhibit No. GNY-103); and \n• Direct testimony of D. Eric Arzola (Exhibit No. GNY-200) and supporting \nexhibits: clean and marked Formula Rate Templates (Exhibit Nos. GNY-201 \nand GNY-202), clean Formula Rate Template in native Excel format with all \nformulas intact (Exhibit No. GNY-203), illustrative Formula Rate Template – \nAnnual Projection (Exhibit No. GNY-204), illustrative Formula Rate Template – \nAnnual Update (Exhibit No. GNY-205), and clean and marked Formula Rate \nImplementation Protocols (Exhibit Nos. GNY-206 and GNY-207), \ndemonstrating the customer-level Supplemental MTRC true-up and the \nordinary Formula Rate true-up of projected CRA revenue credits to actual \nreceipts. \nVII. \nCommunications and Service \nLS Power Grid requests that all pleadings, correspondence, and other \ncommunications concerning this matter be directed to the following persons, and \ntheir names and addresses be placed on the official service list for this docket: \nPatrick Hayes \nLS Power Development, LLC \nAssociate Vice President, Transmission \nRegulatory \n(636) 532-2200 | phayes@lspower.com \nBlake R. Urban \nLS Power Development, LLC \nSenior Regulatory Counsel \n(636) 231-0475 | burban@lspower.com \nLS Power Grid has confirmed with the NYISO that a complete copy of this filing will \nbe posted on the NYISO’s website at www.nyiso.com. The NYISO has also informed \nLS Power Grid that it will send an electronic link to this filing to the official \nrepresentative of each its customers and each participant on its stakeholder \ncommittees. Additionally, LS Power Grid has served a copy of this filing on the \nservice list in Docket No. EL26-69-000 and on parties otherwise entitled to service \nunder the Commission’s regulations."},{"page":12,"startToken":4132,"endToken":4219,"text":"Page 12 \nVIII. \nConclusion \nFor the reasons stated above and in the supporting testimony, LS Power Grid \nrespectfully requests that the Commission accept the proposed tariff revisions \neffective January 16, 2027, subject to the requested waivers. \n \nRespectfully submitted, \n/s/ Blake R. Urban  \nBlake R. Urban \nSenior Regulatory Counsel \nSeth Yeazel \nAssociate Regulatory Counsel \nLS Power Development, LLC  \n16150 Main Circle Drive  \nSuite 310  \nChesterfield, MO 63017  \nTel: (636) 231-0475 \nTel: (240) 904-5109 \nburban@lspower.com \nsyeazel@lspower.com \n \nAttorneys for LS Power Grid New York \nCorporation I"},{"page":13,"startToken":4219,"endToken":4338,"text":"Page 13 \nCERTIFICATE OF SERVICE \n \nPursuant to Rule 2010 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission, 18 C.F.R. § 385.2010, I hereby certify that I have this \nday caused a copy of the foregoing ﬁling of LS Power Grid New York Corporation I to \nbe served electronically upon each person designated on the ofﬁcial service list in \nDocket No. EL26-69-000 and upon each other person entitled to service under the \nCommission’s regulations. \nDated at Rockville, Maryland this 16th day of November 2026. \n/s/ Blake R. Urban  \n \nBlake R. Urban \nSenior Regulatory Counsel \nLS Power Development, LLC  \n16150 Main Circle Drive  \nSuite 310  \nChesterﬁeld, MO 63017  \nTel: (636) 231-0475 \nburban@lspower.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":8,"startToken":0,"endToken":325},{"p":2,"at":8,"title":"I. Introduction and Summary of Filing","method":"printed heading","endPage":3,"endAt":8,"startToken":325,"endToken":711},{"p":3,"at":8,"title":"II. Background","method":"printed heading","endPage":3,"endAt":25,"startToken":711,"endToken":713},{"p":3,"at":25,"title":"A. LS Power Grid and its Rate Schedule 10 Recovery","method":"printed heading","endPage":3,"endAt":745,"startToken":713,"endToken":826},{"p":3,"at":745,"title":"B. Show Cause Order and Stakeholder Process","method":"printed heading","endPage":3,"endAt":1875,"startToken":826,"endToken":987},{"p":3,"at":1875,"title":"III. Description of the Proposed Revisions","method":"printed heading","endPage":3,"endAt":1920,"startToken":987,"endToken":993},{"p":3,"at":1920,"title":"A. Rate Schedule 10 Eligibility and Cost Allocation","method":"printed heading","endPage":4,"endAt":1492,"startToken":993,"endToken":1282},{"p":4,"at":1492,"title":"B. Pro Forma CRA","method":"printed heading","endPage":6,"endAt":2399,"startToken":1282,"endToken":2239},{"p":6,"at":2399,"title":"C. Revenue Attribution, Allocation, and Rate Treatment","method":"printed heading","endPage":8,"endAt":8,"startToken":2239,"endToken":2662},{"p":8,"at":8,"title":"D. NYISO Billing Security and Remittance Functions","method":"printed heading","endPage":8,"endAt":2104,"startToken":2662,"endToken":2970},{"p":8,"at":2104,"title":"E. Supporting Testimony and Illustrative Exhibits","method":"printed heading","endPage":9,"endAt":1141,"startToken":2970,"endToken":3241},{"p":9,"at":1141,"title":"IV. The Proposed Revisions Are Just and Reasonable","method":"printed heading","endPage":10,"endAt":1507,"startToken":3241,"endToken":3666},{"p":10,"at":1507,"title":"V. Requested Effective Date and Waivers","method":"printed heading","endPage":10,"endAt":2282,"startToken":3666,"endToken":3780},{"p":10,"at":2282,"title":"VI. Contents of Filing","method":"printed heading","endPage":11,"endAt":1182,"startToken":3780,"endToken":3973},{"p":11,"at":1182,"title":"VII. Communications and Service","method":"printed heading","endPage":12,"endAt":9,"startToken":3973,"endToken":4134},{"p":12,"at":9,"title":"VIII. Conclusion","method":"printed heading","endPage":13,"endAt":9,"startToken":4134,"endToken":4221},{"p":13,"at":9,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":734,"startToken":4221,"endToken":4338}]}