{"document":{"slug":"rec-20261116-5312","title":"Viridon Path 15 - Trans. Owner Tariff Response to Show Cause Order EL26-71","issued":"2026-11-16","accession":"20261116-5312","docket":"ER27-523-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"Viridon Path 15 LLC","kind":"tariff filing","file":"sources/filings/text/20261116-5312_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5312","tier":"record","sha256":"14924880bdf547312eef93fe885c0333aa3ea1ccc96055257f2577823ae2e359","pages":23,"tokens":8307,"emptyPages":[],"textThemes":["study","cost","flex","colo"]},"pages":[{"page":1,"startToken":0,"endToken":398,"text":"W I L K I N S O N  B A R K E R  K N A U E R ,  L L P  \n2 1 3 8  W . 3 2\nN D  A V E  \n \nS U I T E  3 0 0  \nD E N V E R ,  C O  8 0 2 1 1  \nT E L  3 0 3 . 6 2 6 . 2 3 5 0  \nw w w . w b k l a w . c o m  \n \n \n \nNovember 16, 2026 \n \nVia eTariff \n \nMs. Debbie-Anne A. Reese \nSecretary  \nFederal Energy Regulatory Commission \n888 First Street N.E. \nWashington, D.C. 20426 \n \nRe:  Viridon Path 15 LLC \n        Docket No. ER26-___-000 \n        Docket No. EL26-71-000  \nRevisions to Path 15 Transmission Owner Tariff in Response to Show Cause \nOrder \n \nDear Secretary Reese: \nPursuant to Section 205 of the Federal Power Act (“FPA”),1 Section 35.13 of the \nRegulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”),2 and the \nCommission’s June 18, 2026 order directed to the California Independent System Operator \n(“CAISO”) and participating transmission owners (“PTOs”),3 Viridon Path 15 LLC (“Viridon Path \n15”)4 hereby respectfully files a revised Transmission Owner Tariff (“Path 15 TO Tariff”).  \nViridon Path 15 appreciates the Commission’s efforts to address large load \ninterconnections in organized electric markets. Viridon Path 15 is pleased to present its proposed \nrevisions to its Transmission Owner Tariff (“TO Tariff Revisions”) governing its interest in the \nPath 15 Upgrade Project. The TO Tariff Revisions, in concert with the tariff revisions proposed \n \n1 16 U.S.C. § 824d. \n2 18 C.F.R. § 35.13. \n3 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 62,214, at P 5 & n.9 (2026) (“Show Cause Order”). \n4 Viridon Path 15 submitted a notice of succession on April 21, 2025, to reflect the name change from DATC Path \n15, LLC (“DATC Path 15”) to Viridon Path 15, effective March 28, 2025, following consummation of a \nCommission-approved transaction through which Viridon California LLC (“VCA”) acquired 100% of the equity \ninterests in Viridon Path 15 (“Transaction”). See Viridon Path 15 LLC, Docket No. ER25-2007-000 (issued June 18, \n2025) (unpublished letter order) (accepting Viridon Path 15’s notice of succession and revisions to Transmission \nOwner Tariff under its former name, DATC Path 15, LLC) (“Notice of Succession”); DATC Path 15, LLC, 190 \nFERC ¶ 62,162 (2025) (“Section 203 Order”) (approving the Transaction)."},{"page":2,"startToken":398,"endToken":931,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 2 \n \n \n \nby the CAISO and other PTOs, address the concerns identified in the Show Cause Order. \nSpecifically, and as discussed in further detail later in this transmittal letter, the proposed TO Tariff \nRevisions address: (1) the application process, study procedures, and operational requirements that \napply to Eligible Customers seeking transmission service on behalf of large loads; (2) cost-\nrecovery mechanisms that prevent cost-shifts to third parties; (3) the terms and conditions that \napply for large loads co-located with generation resources; and (4) the extension of new \ntransmission service to Eligible Customers taking service on behalf of large loads with flexible \ndemand.5 Viridon Path 15 has generally designed the TO Tariff Revisions to be consistent with \nthe tariff revisions proposed by the CAISO and other PTOs. However, given the relatively \naccelerated timeframe for developing revisions, the differing operating structures for CAISO \nPTOs, and the complex issues at hand, the TO Tariff Revisions do not perfectly align with every \nother PTO’s proposed revisions. Viridon Path 15 respectfully requests that the Commission accept \nthe revised TO Tariff Revisions for filing, without a hearing or suspension, with an effective date \nof February 16, 2027.6  \nI. \nBACKGROUND AND SUMMARY OF FILING \nViridon Path 15 is a CAISO PTO and a named respondent to the Show Cause Order. \nViridon Path 15 and its parent company, VCA, are uniquely situated amongst CAISO PTOs.  VCA \nis a Delaware limited liability company formed to develop, construct, own, and operate \ntransmission facilities in CAISO. In addition to owning Viridon Path 15, VCA owns a 100% \ninterest in California Grid Holdings LLC (“CalGrid”), which actively pursues competitive \nsolicitations for CAISO-identified Order No. 1000 projects. To date, CalGrid has been selected as \nan Approved Project Sponsor7 to construct, own, and operate three separate Order No. 1000 \nprojects within the CAISO footprint.8 Because these projects remain under development, CalGrid \n \n5 See generally id. (identifying these features as provisions to be included in relevant tariffs). The Show Cause Order \nalso identified a study process to consider generating facilities that will serve electrically proximate large loads. See \nid. at P 106-119. CAISO proposes that a future stakeholder initiative can best address this issue. See CAISO, Large \nLoad Enhancements - Draft Final Proposal at 69 (Sept. 24, 2026) (“CAISO Draft Final Proposal”), \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load-Enhancements-Sep-24-\n26.pdf. Viridon Path 15 agrees and accordingly does not propose any tariff revisions addressing this issue at this \ntime, as discussed below.  \n6 Viridon Path 15 is cognizant of the Commission’s instruction that “proposed tariff revisions should include a \nreasonable effective date that accommodates . . . existing commercial arrangements.” Show Cause Order, 195 FERC \n¶ 61,214 at P 5. Viridon Path 15 has no pending large load interconnection requests, thus the proposed effective date \nof February 16, 2027 is reasonable, and aligns with the effective dates that the CAISO has proposed. \n7 Capitalized terms not otherwise defined herein are used consistent with the Appendix A of the CAISO tariff.  \n8 CalGrid is the Approved Project Sponsor to construct, own, and operate the following CAISO-approved \ntransmission solutions: (1) the New Humboldt 500 kV Substation, with a 500/115 kV transformer, together with the"},{"page":3,"startToken":931,"endToken":1375,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 3 \n \n \n \nis a CAISO Approved Project Sponsor and will be a PTO once the projects are completed.  \nHowever, CalGrid is not a current CAISO PTO and does not own in-service transmission facilities \non the CAISO system. \nViridon Path 15 is a PTO as owner of the existing Transmission Service Rights interest \n(“TSR Interest”) in the Path 15 upgrade. The Path 15 Upgrade includes critical 500 kV \ntransmission infrastructure that was built as a public-private partnership to relieve bottlenecks \nalong the Northern California Path 15 transmission corridor after the California Energy crisis \n(“Path 15 Upgrade”).  The Western Area Power Administration (“WAPA”) owns the physical \ntransmission infrastructure constituting the Path 15 Upgrade. The entire Path 15 Upgrade—both \nWAPA’s physical infrastructure and Viridon Path 15’s TSR Interest—are under CAISO \noperational control.9 The Path 15 TO Tariff is for transmission service along this particular line \nunder the TSR Interest.  \nThe existing Path 15 TO Tariff is limited in scope because it governs only Viridon Path \n15’s TSR Interest. Based on the unique ownership structure for the Path 15 Upgrade, Section 8 of \nthe existing Path 15 TO Tariff directs requests for interconnection, construction of transmission \nexpansions and facility upgrades to WAPA, Pacific Gas & Electric Company (“PG&E”), or the \nCAISO, as applicable.10  Similarly, Section 9 of the existing Path 15 TO Tariff directs expansion \nrequests to WAPA, PG&E, or the CAISO.11  Notwithstanding this direction, the Path 15 TO Tariff \nincludes transmission interconnection and expansion provisions in existing subsections 8a and 9a.  \nThese tariff subsections specifically denote that “Section 8a and Section 9a, and their subparts, are \nprovided for consistency with other PTOs’ TO Tariffs. Sections 8a and 9a, and their subparts, have \nno application to the Entitlements turned over to the ISO’s operational control.”12 Viridon Path 15 \nmaintains this framework in the TO Tariff Revisions by incorporating new Sections 10 and 10a to \n \nnew Humboldt to Collinsville 500 kV line, (2) the new Humboldt to Fern Road 500 kV transmission line, and (3) \nthe new Manning to Metcalf 500 kV transmission line. See the CAISO’s June 2, 2025 Project Sponsor Selection \nReports at https://stakeholdercenter.caiso.com/InitiativeDocuments/New-Humboldt-Fern-Road-500kV-\nTransmission-Line-Project-Reconciled-Final-Costs.pdf and \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/New-Humboldt-Fern-Road-500kV Transmission-Line-\nProject-Reconciled-Final-Costs.pdf. See also the CAISO’s May 19, 2026 Project Sponsor Selection Report at \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/Manning-to-Metcalf-500-kV-Transmission-Line-Project-\nProject-Sponsor-Selection-Report-May-20-2026.pdf.  \n9 See CAISO Transmission Control Agreement, Appendix A at pages 145-146, \nhttps://www.caiso.com/Documents/TransmissionControlAgreement.pdf.  \n10 See Path 15 TO Tariff Section 8.  \n11 See Path 15 TO Tariff Section 9.  \n12 See Path 15 TO Tariff Section 8a."},{"page":4,"startToken":1375,"endToken":1798,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 4 \n \n \n \naddress large load interconnections.  Similar to Sections 8 and 9, new Section 10 provides that new \ninterconnections to the Path 15 Upgrade must apply to WAPA, PG&E, or the CAISO, as \napplicable. New Section 10a describes a proposed interconnection process that is provided only to \nmaintain consistency with other PTO tariffs.  Because Viridon Path 15 owns only the TSR Interest \nin the Path 15 Upgrade, all interconnection requests to the Path 15 Upgrade infrastructure will be \nrouted to the physical asset owner. The TO Tariff Revisions are necessary because Viridon Path \n15 is a named respondent to the Show Cause Order.  \nSince the Commission issued the Show Cause Order, Viridon Path 15 has worked \ncollaboratively with the CAISO and other CAISO PTOs to address the issues identified in the \nShow Cause Order.13 Through that process, Viridon Path 15 developed the TO Tariff Revisions \nthat it hereby submits to the Commission. The TO Tariff Revisions, together with the concurrently \nfiled tariff revisions from the CAISO and other PTOs, address the issues in the Show Cause Order. \nThe TO Tariff Revisions are intended to be consistent with the provisions in CAISO’s most recent \nproposed tariff revisions as reflected in its October 30th Second Revised Draft Tariff Language.14  \nThe TO Tariff Revisions are also intended to be consistent with other PTO tariff revisions filed in \nresponse to the Show Cause Order, to the extent possible. Insofar as Viridon is aware of differences \nbetween its TO Tariff Revisions and those expected to be proposed by other PTOs, Viridon has \nmade efforts to explain the rationale for those differences.   \nII. \nDESCRIPTION AND BASIS FOR THE TO TARIFF REVISIONS \nViridon developed the TO Tariff Revisions to respond to the concerns identified in the \nShow Cause Order regarding transmission service to Eligible Customers on behalf of large loads. \nAs described below, the proposed revisions address application and study procedures, ongoing \noperational requirements and service agreements, cost recovery, co-located generation, and \nflexible interim interconnection service. Viridon Path 15 has sought to align these provisions with \nCAISO’s proposed tariff framework and the approaches developed with other PTOs, while \naccounting for its role as a non-load-serving PTO and the need for coordination among affected \ntransmission owners. \n \n13 See, e.g., Comments of Viridon California Submitted Regarding CAISO Large Loads Straw Proposal (Submitted \nAug. 28, 2026), https://stakeholdercenter.caiso.com/Comments/AllComments/43a11ec9-fe21-4255-bb1c-\n336ad3703845#org-6c9bf931-895d-4eae-81ad-98b9e78738e0.  \n14 See https://stakeholdercenter.caiso.com/InitiativeDocuments/Second-Revised-Draft-Tariff-Language-Large-\nLoads-Order-to-Show-Cause-Oct-30-2026.docx (opens link) (“Second Revised Draft Tariff Language”)."},{"page":5,"startToken":1798,"endToken":2177,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 5 \n \n \n \nAs discussed below, the TO Tariff Revisions are designed to facilitate timely large load \ninterconnections, protect other transmission customers from cost shifts, and maintain reliable \ntransmission system operations. Further, the TO Tariff Revisions specifically address co-located \ngeneration and the conditions under which flexible large loads may obtain interim interconnection \nservice subject to operating limits and curtailment obligations. The proposed tariff changes do not \ndisrupt existing commercial agreements as there are no existing requests to use the TSR Interest \nto large loads or any other End User.15 Finally, Section II.E discusses electrically proximate \ngeneration and explains why, consistent with CAISO’s recommendation, Viridon Path 15 does not \npropose revisions addressing this topic at this time. \nA. \nApplication and Study Procedures Applicable to Eligible Customers Seeking \nTransmission Service on Behalf of Large Loads \nThe Show Cause Order identifies that the Commission is concerned that CAISO and/or \nPTOs do not currently have tariff provisions expressly addressing how the provision of \ntransmission service to Eligible Customers on behalf of large loads will be studied in a timely \nfashion.16 The Commission therefore directed CAISO and the PTOs “to explain whether their \ntariffs remain just and reasonable without an application process, study procedures, and ongoing \noperational requirements that address the unique characteristics and challenges of providing \ntransmission service to Eligible Customers on behalf of large loads, or to propose appropriate tariff \nrevisions.”17 \nThe Commission specifically identified four particular areas in which tariff provisions \ncould be improved to address the process for providing transmission service to Eligible Customers \non behalf of large loads: (1) definition of large load; (2) the application process for requesting \ntransmission service to Eligible Customers on behalf of large loads and the relevant study \nprocedures; (3) ongoing operational requirements for transmission customers serving large loads; \nand (4) pro forma provisions in transmission service agreements, or other applicable agreements, \nto memorialize the terms of the operational requirements.18 \nCAISO addresses each of these four topics and states in its Draft Final Proposal that it \n“agrees with the Commission that additional clarity and information requirements are necessary \n \n15 Show Cause order at P 34. \n16 Show Cause Order at P 38. \n17 Id. at P 40. \n18 Id. at P 56."},{"page":6,"startToken":2177,"endToken":2532,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 6 \n \n \n \nwithin the CAISO tariff, especially if interim or non-firm service is being considered to facilitate \n‘speed-to-power,’ or accelerated large load interconnections.”19 CAISO further noted, however, \nthat “PTOs remain largely responsible for processing applications and studying new large loads, \nwhile the CAISO remains responsible for reviewing these studies and ensuring alignment with \ntransmission planning activities.”20 Thus, CAISO expects “the PTOs to collectively develop their \nown consistent set of Tariff reforms to clarify their load interconnection processes and \ncommunications, and to align their proposals with the CAISO’s processes.”21  \nViridon Path 15 addresses how the Commission framed each issue, how CAISO proposed \naddressing these issues, and how the TO Tariff Revisions implement the CAISO proposal, where \napplicable. \n1. \nDefinition of Large Load \nThe Show Cause Order states that a definition of large load would be useful to develop a \ndefinition of large load interconnection process.22 In its Second Revised Draft Tariff Language, \nCAISO proposed to define a large load as: “An End User located at a single site behind one or \nmore Points of Interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW \nor greater.”23 Viridon Path 15 agrees with this proposed definition and incorporates it directly into \nthe TO Tariff Revisions.24 To Viridon Path 15’s knowledge, other PTOs may propose differing \ndefinitions for large load. Viridon Path 15 supports the CAISO’s proposed definition as a \nstraightforward framework consistent with existing CAISO and PTO tariff provisions.   \n2. \nLarge Load Application  \nThe CAISO Draft Final Proposal “suggests that the PTOs develop consistent application \nprocesses, study requirements, and agreements to ensure sufficient transparency in the load \napplication and study process.”25 Viridon Path 15 has worked with other PTOs to develop a \nconsistent application process, and Viridon Path 15 has attempted to develop substantively \n \n19 CAISO Draft Final Proposal at 10. \n20 Id. at 10-11. \n21 Id. at 11. \n22 Show Cause Order at P 57. \n23 Second Revised Draft Tariff Language at Appendix A. \n24 See TO Tariff Revisions § 3.14.  \n25 CAISO Draft Final Proposal at 19."},{"page":7,"startToken":2532,"endToken":2994,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 7 \n \n \n \nconsistent application requirements. However, Viridon Path 15 underscores that, given the short \ntimeframe, the complexity of issues involved, and the large number of PTOs, it was not possible \nto coordinate in perfect lockstep with all other PTOs.  \nIn general, the TO Tariff Revisions incorporate new provisions for large load applications \nwithin the existing framework for interconnection applications in existing non-load serving entity \n(“non-LSE”) PTO tariffs. The TO Tariff Revisions do not establish an entirely separate process \nfor large load interconnection applications, but instead specify additional requirements for \napplications on behalf of large loads. The TO Tariff Revisions’ provisions on large load application \nprocess address the required contents of any such applications, the required application fee, and \nthe timeframe by which the PTO determines an application is complete.26 These provisions are \ndesigned to collect sufficient information to move forward with a request by an Eligible Customer \non behalf of a large load.  \nViridon highlights two specific provisions in the application process that may differ \nsubstantively from other CAISO PTO tariffs.  First, proposed Tariff Section 10a.4.2(vii)   requires \n“disclosure of any other interconnection requests to the ISO Controlled Grid the applicant has filed \non behalf of the same Large Load or any of its affiliate(s).”  This section ensures full transparency \nregarding potentially duplicative requests from a single End User.  Viridon Path 15 understands \nthat other PTOs will require a similar disclosure, with a more limited scope; for example, limiting \ndisclosure to interconnection requests from the same large load customer that are within the \nEligible Customer’s footprint.  Viridon Path 15 suggests that limiting the obligation to disclose a \nsingle large load customer’s applications within an Eligible Customer “footprint” is vague and \npotentially under-inclusive.  An applicant requesting interconnection on behalf of a large load \ncustomer should be obligated to disclose any interconnection requests it has filed on behalf of the \nsame large load customer.27   \nSecond, Viridon Path 15 notes its proposed Tariff Section 10a.5 requiring a PTO \ncoordination process for large load interconnections. Viridon Path 15 believes that a transparent \nand actionable PTO coordination process is vital to ensure that end use large load customers can \nexercise the most cost-effective and timely options to access the transmission system. Viridon Path \n15’s proposed Tariff Section 10a.5 requires the PTO receiving a completed large load \n \n26 See TO Tariff Revisions § 10a.3–10a.5. \n27 Additionally, and consistent with the approach that Viridon understands Horizon West Transmission, LLC is \nincluding it its tariff revisions, Section 10a.2 of the TO Tariff Revisions provides for the voluntary offer of \nunbundled retail transmission service to any End-Use Customer whose Point of Interconnection is on facilities \nowned by Company, in accordance with the CAISO Tariff."},{"page":8,"startToken":2994,"endToken":3368,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 8 \n \n \n \ninterconnection application to provide notice and a copy of the application to the CAISO and any \nother PTO with potentially affected transmission facilities.  In addition, this section requires the \nPTO receiving the interconnection application to coordinate with other PTOs to determine the \nmost cost-effective solution to provide the requested transmission service.  \nAn effective PTO coordination process is essential to ensure the existing transmission \nsystem is utilized at maximum efficiency.  Without PTO coordination at the application stage, \nlarge load customers will have limited, or non-existent, insight regarding where to interconnect to \nthe CAISO Controlled Grid.  Non-LSE PTOs do not have direct relationships with large load retail \ncustomers and, without a PTO coordination process, may not be aware of large load \ninterconnection requests that are geographically or electrically proximate to their transmission \nfacilities.  As a result, non-LSE PTO facilities could be underutilized by large load customers.  A \nlarge load interconnection process that favored connecting to load serving entity PTO facilities \nwould not be just and reasonable.  The CAISO’s Order No. 1000 process has been incredibly \nsuccessful and the majority of regional transmission projects have been awarded to non-LSE \ncompetitive transmission developers.  This means that non-LSE PTOs will likely own and operate \nan increasingly large portion of the CAISO transmission system in the foreseeable future.  The \nCommission should ensure the large load interconnection process allows end users to effectively \nuse those new facilities.  \nViridon Path 15 recommends that all CAISO PTO tariffs include similar coordination \nlanguage to ensure alignment. \n3. \nLarge Load Study Process \nRegarding large load interconnection study processes, “CAISO [did] not propose changing \nthe allocation of rights and responsibilities for studying large load interconnection requests from \nthe framework in place today: the PTOs will continue to manage the bulk of the study \nresponsibilities.”28  Rather, the CAISO Draft Final Proposal “encourages the PTOs to align their \nload interconnection study procedures among themselves and with the CAISO resource \ninterconnection standards and [transmission planning process (“TPP”)] for enhanced clarity and \nconsistency for customers.”29 CAISO also stated that it “expects the PTOs to develop consistent \nstudy procedures to be completed within 60 to 90 days, as required by the Commission,” and that \n \n28 Id. at 25. \n29 Id."},{"page":9,"startToken":3368,"endToken":3736,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 9 \n \n \n \nthe study procedures should account for large loads with load flexibility.30 CAISO also “expects \nPTOs to propose enhanced alignment of their load interconnection request windows and study \ntimelines with the CAISO processes.”31  \nViridon Path 15 has largely aligned its proposed study procedures with those of other \nPTOs, though it has not had prior opportunity to review other PTOs’ final proposed language.  The \nTO Tariff Revisions may differ from other PTO study processes by proposing a serial study \nprocess for large load interconnections rather than a cluster study process.  At this time, Viridon \nPath 15 does not believe there is a need to implement a cluster study process.   \nConsistent with other PTOs, under the TO Tariff Revisions, the Transmission Owner and \nCAISO (if applicable) will determine whether a system impact study is required.32 If no such study \nis required, the TO Tariff Revisions set forth a process for expeditiously entering an \ninterconnection agreement if no direct assignment facilities are required, or if direct assignment \nfacilities are required, then the parties will enter a facilities study agreement and continue the \ninterconnection process.33 If a system impact study is required, the TO Tariff Revisions then set \nforth the process by which such study will be completed, including the relevant timelines and \npayment for the costs of the study.34  \nViridon Path 15 highlights that its proposed Tariff Section 10a.6.4 includes a requirement \nfor a PTO to share its System Impact Studies with other potentially affected PTOs, in addition to \nthe applicant and the CAISO.  Viridon Path 15 recommends requiring PTOs to share System \nImpact Studies to enable affected PTOs to study and identify upgrades to downstream facilities, \nas well as the right to construct, own, and operate those upgrades. \n \n30 Id.  \n31 Id. at 26. CAISO explains that this approach “is needed for all the information to be communicated back to the \nCAISO in a timely and consistent manner to inform the CAISO’s broader transmission planning, resource \ninterconnection, and deliverability allocation procedures.” Id.  \n32 See TO Tariff Revisions § 10a.6.1. \n33 See id. § 10a.6.6. \n34 See id. §§ 10a.6.2 – 10a.6.5."},{"page":10,"startToken":3736,"endToken":4107,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 10 \n \n \n \nThe TO Tariff Revisions provide for the study process being completed within 60 to 90 \ndays of a completed application and system impact study agreement, consistent with the Show \nCause Order and the CAISO Draft Final Proposal.35 \n4. \nLarge Load Operational Requirements \nThe Commission also identified the potential need to provide for tariff provisions \naddressing “ongoing operational requirements for transmission customers serving large loads \nnecessary to ensure reliable operation of the transmission system.”36  \nCAISO’s Draft Final Proposal notes in response that CAISO’s Large Load Technical \nRequirements Working Group (“LLTRWG”) has been developing requirements to address this \nissue.37 Based on the LLTRWG’s work and in coordination between CAISO and PTOs, CAISO \nproposes that its tariff will address: requirements on ramp-rates; frequency and voltage ride-\nthrough requirements, forecasts, telemetry, and other necessary operational data; communication \nprotocols for remote disconnection; and maintaining communication channels between CAISO \nand transmission customers serving large loads.38  \nCAISO then proposes that the following requirements be addressed through PTO tariffs: \nrequired installation of phasor measurement units or other high-speed monitoring equipment, with \ncost assigned to the transmission customer; and requirements for systems that can limit large load \nwithdrawals from the transmission system.39 CAISO identifies, however, that the LLTRWG \ncontinues to refine technical requirements, with potential changes to flow through to the CAISO \ntariff, PTO tariffs, or other mechanisms.40 \n \n35 See id. § 10a.6. \n36 Show Cause Order at P 56 (footnote omitted). See also id. at P 63 (“The unique nature of these large loads creates \nchallenges for operation of the transmission system and necessitates greater visibility and operational control when \nproviding transmission service to transmission customers on behalf of large loads, without which the reliability of \nthe transmission system could be at risk. For example, we are concerned that CAISO’s Tariff and/or the TO Tariffs \ndo not require transmission customers to provide CAISO hourly forecasts, telemetry data, and other data to ensure \nsufficient visibility or specify requirements for maintaining communication channels between CAISO and the \ntransmission customer on behalf of the large load.” (footnote omitted)).  \n37 See CAISO Draft Final Proposal at 36.  \n38 Id. \n39 Id. at 36-37. \n40 Id. at 37."},{"page":11,"startToken":4107,"endToken":4453,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 11 \n \n \n \nThe TO Tariff Revisions would require that certain of the necessary information for \ncollection would be required as part of any interconnection application, to be provided to CAISO \nduring the interconnection process. However, Viridon Path 15 proposes that such information be \nincluded in the interconnection agreements.41 \n5. \nLarge Load Service Agreements \nThe Show Cause Order also identifies the potential need for “pro forma provisions in \ntransmission service agreements, or other applicable agreements, to memorialize” the terms set \nforth regarding operational requirements.42 The Commission explained its concern that “without \nsuch pro forma provisions in a transmission service agreement, or other applicable agreement, \nbetween CAISO and/or the Participating Transmission Owner and the transmission customer, \nCAISO may be unable to enforce ongoing operational requirements for transmission customers \ntaking transmission service on behalf of large loads.”43  \nTo address this issue, CAISO proposes that the PTOs develop “consistent pro forma \nagreements to memorialize the technical and operational terms the Order describes.”44 CAISO \nexplains that, in its view, “it is not clear whether the CAISO should always be a signatory to a \nthree-party agreement for large load interconnections.”45 CAISO identifies that it would likely \nneed to be a signatory in an agreement addressing non-firm interconnection service based on the \noperational procedures necessary to provide such service.46 And for co-located large loads with \nexporting generation, CAISO states that it would need to be a party to “a pro forma agreement that \nbridges the pro forma Large Generator Interconnection Agreement (LGIA) with the pro forma \nlarge load interconnection agreement or negotiate a non-conforming LGIA to account for certain \ndetails of the co-located large load interconnection on an individual basis.”47 \nThe TO Tariff Revisions contemplate a Large Load Interconnection Agreement that will \nrequire the applicant to provide the technical and operational requirements provided by the Show \n \n41 See id. § 10a.6.8.1. \n42 Show Cause Order at P 56. \n43 Id. at P 64. \n44 CAISO Draft Final Proposal at 40. \n45 Id.  \n46 Id.  \n47 Id."},{"page":12,"startToken":4453,"endToken":4830,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 12 \n \n \n \nCause Order and the CAISO’s proposed tariffs.48 Viridon Path 15 understands that CAISO PTOs \nhave developed a pro forma Large Load Interconnection Agreement that incorporates these \ntechnical and operational requirements, but Viridon Path 15 was not able to substantively review \nthe proposal prior to making this filing.  In an effort to coordinate with other PTOs and maintain \nconsistency to the extent possible, the TO Tariff Revisions do not include a separate pro forma \nLarge Load Interconnection Agreement.  Instead, Viridon Path 15 will review the pro forma Large \nLoad Interconnection Agreement proposed by other CAISO PTOs and provide recommended edits \nor comments as necessary.   \nB. \nCost-Recovery Mechanisms that Prevent Cost-Shifts to Third Parties \nIn the Show Cause Order, the Commission preliminarily found “that cost transparency \nmeasures are needed to provide stakeholders with sufficient information and visibility regarding \nthe network upgrades, and their associated costs, needed to accommodate transmission service to \nEligible Customers on behalf of large loads.”49 The Commission therefore called for measures to \nincrease transparency.50  \nIn addition to improved transparency, the Commission cited the need for development of \na pro forma cost recovery agreement between CAISO, the applicable PTO, and the Eligible \nCustomer taking transmission service on behalf of large loads.51 The Show Cause Order identifies \na concern that speculative transmission service requests could result in cost shifting among \ntransmission customers, which could result, for example, if an “Eligible Customer takes less \ntransmission service than anticipated because the large load operates at a lower demand than \nanticipated or fails to materialize at all” after network upgrades are already constructed to serve \nthat load.52 The Commission urged that cost recovery agreements “would help ensure that the \nEligible Customer makes a minimum contribution to the transmission owner’s transmission \nrevenue requirement commensurate with the costs incurred to provide the requested transmission \nservice, including the costs of any needed network upgrades.”53 The Show Cause Order therefore \n“preliminarily find[s] that … cost recovery agreements are necessary to help ensure that the \n \n48 See TO Tariff Revisions § 10a.6.8.1.  \n49 Show Cause Order at P 70. \n50 Id. at P 75. \n51 Id. at P 76. \n52 Id. at P 78. \n53 Id. at P 79."},{"page":13,"startToken":4830,"endToken":5263,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 13 \n \n \n \nEligible Customer is responsible for timely paying the costs of large load-driven transmission (i.e., \nthe costs incurred to provide them with the requested transmission service, including the costs of \nany needed network upgrades) ….”54 \nTo address the potential for cost shifts, the CAISO Draft Proposal proposes that the PTO \ntariffs address the cost allocation issues identified by the Commission.55 “CAISO believes that the \nPTOs may develop their own proposals to address any cost shifting, and that the current \ntransmission revenue requirement and credit mechanisms in the TAC can accommodate those \nproposals.”56 CAISO also suggests that PTOs should account for the impact of construction \ncontributions, revenues, or other cost offsets associated with network upgrade costs directly \nattributed to large loads and paid for by the large load customer through the utility distribution \ncompany or metered subsystem in determining its transmission revenue requirement.57  \nAs to cost data transparency, CAISO identifies the data already shared on its website and \n“proposes to clarify in the TPP where network upgrades were needed to accommodate both general \nload growth and large load interconnection specifically,” and to publicly post certain information \non its website.58 Viridon Path 15 supports this approach and notes that this obligation falls on \nCAISO and not PTOs.  \nAs noted above, the TO Tariff Revisions contemplate adopting a pro forma Large Load \nInterconnection Agreement.  Cost recovery mechanisms that ensure that the Eligible Customer is \nresponsible for timely paying the costs of large load-driven transmission (i.e., the costs incurred \nto provide the requested transmission service, including the costs of any needed network \nupgrades) will be reflected in the pro forma Large Load Interconnection Agreement. As also \nnoted above, Viridon Path 15 understands that other CAISO PTOs have developed a pro forma \nLarge Load Interconnection Agreement that incorporates these cost recovery mechanisms that \n \n54 Id. at P 80. The Show Cause Order further identified that a potentially appropriate approach for determining the \nlevel of minimum contribution would be the “based on the level of jurisdictional transmission service (in MW) \nrequested by the Eligible Customer on behalf of large load.” Id. at 82. The Commission further explained that in \naddition to the minimum contribution, “the cost recovery agreement should include a credit support (or other \nfinancial security) requirement sufficient to secure the obligations of the Eligible Customer taking transmission \nservice on behalf of a large load to pay the amounts owed pursuant to the cost recovery agreement.” Id. \n55 CAISO Final Draft Proposal at 44. \n56 Id. \n57 Id. at 45. \n58 Id. at 48."},{"page":14,"startToken":5263,"endToken":5663,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 14 \n \n \n \nmeet the Show Cause Order requirements, but Viridon Path 15 was not able to substantively \nreview the proposal prior to making this filing.  \nIn an effort to coordinate with other PTOs and maintain consistency to the extent \npossible, the TO Tariff Revisions do not include a separate pro forma Large Load \nInterconnection Agreement or cost recovery mechanisms.  Viridon Path 15 believes that \ndeveloping an entirely separate and distinct cost recovery mechanism for this filing would not \nhave been productive, especially given that Viridon Path 15’s current ownership in the Path 15 \nUpgrade is limited to the TSR Interest.  Rather than proposing its own separate cost recovery \nmechanisms, Viridon Path 15 will review the pro forma Large Load Interconnection Agreement \nand the cost recovery mechanisms proposed by other CAISO PTOs and provide recommended \nedits or comments as necessary.   \nC. \nRates, Terms, and Conditions for Large Loads Co-Located with Generation \nResources  \nThe Show Cause Order directed CAISO and PTOs, to the extent applicable to PTO tariffs, \nto explain whether their tariffs are “just and reasonable without provisions addressing the rates, \nterms, and conditions that apply to interconnection customers serving co-located load and for \nEligible Customers taking transmission service on behalf of Eligible Load, or [to] propose Tariff \nrevisions establishing the rates, terms, and conditions that apply to co-location arrangements.”59  \nThe CAISO Draft Final Proposal states in response to this concern that CAISO proposes \nto clarify co-location arrangements that would not require a CAISO resource interconnection \nrequest and could be accommodated through applicable PTO or CPUC-jurisdictional retail \ninterconnection tariffs.60 Additionally, for large loads seeking to co-locate with new generation \nthat may export to the grid, CAISO proposes requiring a CAISO interconnection study, with \nscoring and study results based on the requested capacity figures the developer may provide, \nallowing the generator to “significantly limit the generation potentially to be exported based on \nhow much generation will serve the large load.”61  \nAccordingly, because of the changes CAISO intends to make to address co-located loads \nset forth in its Second Revised Draft Tariff Language, PTOs do not need to make extensive \nrevisions to specifically address co-located loads in their tariffs. The TO Tariff Revisions \nspecifically address co-located large loads by providing that large loads with co-located generation \n \n59 Show Cause Order at P 86. \n60 CAISO Draft Final Proposal at 55. \n61 See id."},{"page":15,"startToken":5663,"endToken":6021,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 15 \n \n \n \nfacilities will be studied based on their expected load on the transmission system, net of the co-\nlocated generation’s output that offsets the large load’s energy usage.62 For co-located generation \nresources that may export to the transmission system, the TO Tariff Revisions specify that such \ngeneration must comply with the applicable CAISO generator interconnection procedures and \nrequirements.63 \nD. \nExtending New Transmission Service to Eligible Customers Taking Service on \nBehalf of Flexible Large Loads  \nIn the Show Cause Order, the Commission identified that flexible large loads can \npotentially defer the need for transmission network upgrades, which in turn would allow for faster \ninterconnection and potentially avoid the need for transmission system build-out.64 The \nCommission further noted that the CAISO tariff does not currently “include transmission services \nthat reflect the use of the transmission system by Eligible Customers on behalf of flexible large \nload, on both an interim and permanent basis,” and the Commission directed CAISO to explain \nwhether the Tariff remains just and reasonable without an interim or permanent non-firm network \ntransmission service, or in the alternative, “explain what specific changes to its existing \ntransmission service framework would effectively provide comparable transmission service \noptions for flexible large loads.”65 \nIn the CAISO Draft Final Proposal, CAISO explains that its straw proposal created two \nnew flexible interconnection service offerings, “one offered on an interim basis and one offered \nfor permanent use, to shorten interconnection timelines and reduce interconnection costs, \nrespectively.”66 CAISO proposed to advance the interim option at present, given time constraints \nand because the interim option is meant to shorten interconnection timeframes.67 For the interim \napproach, CAISO proposed creating a new flexible interconnection service that would allow large \nloads and co-located loads to limit their energy withdrawals or injections until their network \nupgrades are placed into service.68 The CAISO Draft Final Proposal states that “CAISO believes \n \n62 See TO Tariff Revisions § 10a.8.  \n63 See id. \n64 Show Cause Order at PP 103-104. \n65 Id. at P 105. \n66 CAISO Draft Final Proposal at 63. \n67 See id. at 64. \n68 Id. at 66."},{"page":16,"startToken":6021,"endToken":6427,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 16 \n \n \n \nthis will provide large load developers with the option to interconnect quickly through enforceable \nphysical and operational controls to prevent transmission congestion.”69 To implement this \napproach, CAISO proposed creating a new Flexible Interim Load Interconnection (“FILI”) service \nto be implemented in close coordination with the CAISO PTOs to enable faster interconnections \nwhile mitigating transmission constraints.70 \nAccordingly, within the TO Tariff Revisions presented here, Viridon Path 15 has \nimplemented a new service for that concept, identified as Flexible Interim Large Load \nInterconnection (“FILLI”).71 The TO Tariff Revisions are intended to be closely consistent with \nthe framework set forth in CAISO’s Second Revised Draft Tariff Language, along with other PTOs \nthat Viridon Path 15 has coordinated with, to maintain uniformity within the CAISO footprint. The \nTO Tariff Revisions also address the need to ensure that there is an enforceable chain of authority \nand obligations to curtail when required so that any flexibility credited in interconnection studies \nis realized in operation. These provisions are just and reasonable because they reasonably balance \nthe benefits of facilitating flexible load additions earlier and at lower cost, while at the same time \nproviding the terms necessary to ensure the stability and reliability of the transmission system. \nIt is important to emphasize that for the FILLI offering to function as intended, curtailment \nobligations must be enforceable and the chain of authority must be clear. Experience with existing \nreliability-based demand response arrangements suggests that voluntary curtailment commitments \nare difficult to enforce in practice. Flexible interconnection service agreements should therefore \ninclude clear performance obligations, verification through the telemetry and monitoring \nrequirements described above, and meaningful consequences for non-performance to ensure that \nthe benefits of flexibility are achieved in practice. The Path 15 Tariff Revision sections addressing \nFILLI are designed with these considerations in mind, requiring a FILLI service agreement that \nwould fill in the operational details.  \nThe TO Tariff Revisions would define FILLI as “A transmission interconnection service \noffered by the Participating TO and accepted by an Eligible Customer on behalf of a Large Load \nretail customer to manage operational constraints on withdrawals from the transmission system \nwhile the interconnection and system upgrades necessary to provide Firm Interconnection Service \nare being developed.”72 The TO Tariff Revisions then define the interconnection service for FILLI \n \n69 Id. \n70 Id. at 67. \n71 See TO Tariff Revisions §§ 3.12, 10a.7.  \n72 See id. § 3.12."},{"page":17,"startToken":6427,"endToken":6806,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 17 \n \n \n \ncustomers, including the study process used to identify the maximum amount of FILLI service, if \nany, that may be provided based on the anticipated availability of transmission capacity, and \nconditions for FILLI service.73  \nFor interconnection service to FILLI customers, the TO Tariff Revisions specify that FILLI \nservice will be available for load that cannot receive interim firm interconnection service, if the \nlarge load customer is able to reduce load according to requirements specified in a FILLI service \nagreement.74 \nThe TO Tariff Revisions also include a study process for FILLI service, where the \nParticipating TO performs an initial study to determine the maximum amount of interim firm \nservice, if any, and FILLI service, if any, that may be provided based on the projected availability \nof transmission capacity available to serve the large load customer.75 The PTO shall determine the \nlevel of FILLI service available on an annual basis to accommodate changing conditions on the \ntransmission system over time.76 \nThe TO Tariff Revisions also specify certain prerequisite conditions related to FILLI \nservice by providing that a FILLI Service Agreement will identify what Eligible Customer \ninterconnection facilities must be installed, protection and control equipment to be installed, and \noperating limits to allow the FILLI customer to withdraw energy.77  The TO Tariff Revisions \ncontemplate including the FILLI Service Agreement as an Appendix to the TO Tariff.  Viridon \nPath 15 understands that other CAISO PTOs have developed a pro forma FILLI Service \nAgreement that incorporates terms for offering FILLI service, FILLI service reliability \nrequirements, rules for curtailment and protocols for reducing load, and consequences for \nexceeding authorities FILLI Service.78  To date, Viridon Path 15 has not had the opportunity to \nsubstantively review the pro forma FILLI Service Agreement.    \nIn an effort to coordinate with other PTOs and maintain consistency to the extent possible, \nthe TO Tariff Revisions do not include a separate pro forma FILLI Service Agreement.  Viridon \nPath 15 believes that developing an entirely separate and distinct FILLI Service Agreement for \n \n73 See id. §§ 10a.7.1 – 10a.7.2. \n74 See id. § 10a.7.1. \n75 See id. § 10a.7.2. \n76 See id. § 10a.7. \n77 See id. § 10a.7.3. \n78 See id. § 10a.7."},{"page":18,"startToken":6806,"endToken":7167,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 18 \n \n \n \nthis filing would not have been productive, especially given that Viridon Path 15’s current \nownership in the Path 15 Upgrade is limited to the TSR Interest.  Rather than proposing its own \nseparate FILLI Service Agreement, Viridon Path 15 will review the pro forma agreement proposed \nby other CAISO PTOs and provide recommended edits or comments as necessary.   \n Additionally, the TO Tariff Revisions set forth when service to FILLI customers may be \ncurtailed and the priority of FILLI service relative to firm service.79 As provided in the TO Tariff \nRevisions, the PTO and CAISO may curtail FILLI service as necessary to maintain the reliable \noperation of the CAISO-controlled transmission system.80 The TO Tariff Revisions further provide \nthat the Eligible Customer shall ensure that the PTO’s operating instructions are not exceeded at \nthe point of withdrawal and that the PTO has the right to disconnect service to the FILLI customer \nif energy withdrawals by the FILLI customer violate the terms of the relevant service agreement, \nwith the PTO following good utility practice in carrying out any such disconnection and \nsubsequent reconnection.81  \nE. \nLarge Load Electrically Proximate to Generation Resources \nThe Show Cause Order identifies the potential need for a specific process that would \nprioritize interconnecting generation resources that are electrically proximate to large loads.82 The \nCommission explained that  \n[w]here a generating facility’s output is matched to the demand of the electrically \nproximate large load or large co-located load or if the generating facility’s output \nis limited to ensure no new injection, the impacts to the transmission system of \ninterconnecting the generating facility to serve that electrically proximate large load \nor large co-located load may be limited.83  \nThe Commission further stated that these limited impacts may reduce the need for network \nupgrades, which would accelerate the generator interconnection process.84 The Commission stated \nthat it was concerned by the CAISO tariff’s lack of study procedures and generator interconnection \n \n79 See id. § 10a.7.3.2. \n80 See id. \n81 See id. § 10a.7.3.3. \n82 Show Cause Order at PP 106-119. \n83 Id. at P 113. \n84 Id."},{"page":19,"startToken":7167,"endToken":7532,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 19 \n \n \n \nservices addressing electrically proximate generation resources.85 The Commission stated that it \npreliminarily found the absence may be unjust and unreasonable.86 However, the Commission \nnotably did not state that any PTOs’ tariffs may be unjust and unreasonable,87 because the CAISO \ntariff provisions are where these types of procedures would typically reside.88 \nIn CAISO’s Draft Final Proposal, CAISO proposed that it would consider provisions for \ninterconnection customers to serve electrically proximate large loads in a future stakeholder \ninitiative.89 In support of its approach, CAISO explained that “it currently has a process for \nconnecting generator interconnection request applications to non-load-serving entities (e.g. \ncommercial and industrial consumers) in its generator interconnection process, which awards \n‘points’ in the interconnection scoring process to projects that have a commercial arrangement \nwith a non-load-serving entity off-taker.”90 This process “seeks to tie generation projects to loads \nto the extent that they have a commercial arrangement with the goal of enabling large loads to \nprocure generation.”91 While CAISO agreed “with many stakeholders that it is worth continuing \nto explore the potential benefits of proximate loads,” it did not “propose development of this \noption” in immediate response to the Show Cause Order.92 PTOs commenting on this approach \nagreed.93  \nBecause CAISO plans to address the issue of generation interconnection electrically \nproximate to large loads in a future stakeholder process, and because the terms of such \ninterconnection service best reside within the CAISO tariff, Viridon Path 15 does not propose \nmaking any changes to its Path 15 Tariff on this issue. Viridon Path 15 looks forward to \nparticipating in the CAISO stakeholder process on this issue and understands the potential benefits \nfrom pairing electrically proximate generation and large loads to achieve faster interconnection.  \n \n85 Id. at P 117. \n86 Id. \n87 See id. \n88 See Joint Participating Transmission Owners, Request for Abeyance at 5-6 (Aug. 3, 2026). \n89 CAISO Draft Final Proposal at 69. \n90 Id. \n91 Id. \n92 Id. \n93 See id. (noting that PG&E and SDG&E agreed with not creating new tariff provisions at this time for \ninterconnection customers to serve electrically proximate large loads)."},{"page":20,"startToken":7532,"endToken":7772,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 20 \n \n \n \nIII. \nINFORMATION REQUIRED UNDER 18 C.F.R. § 35.13(b) \nIn accordance with Section 35.13(a)(2)(iii) and 35.13(b) of the Commission’s regulations, \nViridon Path 15 provides the following information: \nA. \nDocuments Submitted with this Filing94 \nIn addition to this transmittal letter, Viridon Path 15 is also submitting clean and redlined \nversions of the TO Tariff Revisions.  \nB. \nProposed Effective Date95  \nViridon Path 15 proposes a February 16, 2027 effective date for the TO Tariff Revisions.  \nC. \nPersons Receiving Service96 \nViridon Path 15 has served a copy of this filing electronically, including attachments, upon \nall Path 15 Tariff customers and all parties to Docket No. EL26-71-000. This filing will also be \nposted in conformance with the Commission’s regulations.97 \nD. \nDescription of Rate Change98 \nViridon Path 15 describes the rate change in detail in Section II of this transmittal letter.  \nE. \nStatement of the Reasons for the Rate Change99 \nAs discussed in more detail in Section II of this transmittal letter, Viridon Path 15 is \nrevising its Path 15 Tariff because of the Commission’s Show Cause Order and based on the \nstakeholder process that has occurred through CAISO. \n \n94 18 C.F.R. § 35.13(b)(1). \n95 Id. § 35.13(b)(2). \n96 Id. § 35.13(b)(3). \n97 Id. § 35.2(e). \n98 Id. § 35.13(b)(4). \n99 Id. § 35.13(b)(5)."},{"page":21,"startToken":7772,"endToken":8132,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 21 \n \n \n \nF. \nRequisite Agreement to the Rate Change100 \nNo third-party agreement is required for Viridon Path 15 to file or implement the proposed \nchanges presented here. However, Viridon Path 15 notes that its proposed changes are largely \nconsistent with Viridon Path 15’s understanding of the changes that will be proposed by other \nTransmission Owners within the CAISO footprint.  \nIV. \nREQUEST FOR WAIVERS \nPursuant to 18 C.F.R. § 385.101(e), Viridon Path 15 respectfully requests, to the extent \nnecessary, that the Commission waive the requirement to provide the information identified in 18 \nC.F.R. § 35.13(c) relating to the effect of rate changes because the TO Tariff Revisions would not \nchange the cost of service or Viridon Path 15’s revenue requirement. Waiver is appropriate where \nsuch information is not “necessary for the Commission to determine whether a rate is just and \nreasonable.”101  \nThe TO Tariff Revisions are targeted to the specific issues that FERC identified in the \nShow Cause Order, including study processes, cost-shifts, and co-located large loads. These \nrevisions are not focused on the cost of service or revenue requirement and do not yield any readily \ncalculable differences in projected revenues from sales and services. Thus, to the extent the \nCommission concludes that 18 C.F.R. § 35.13(c) is applicable, Viridon Path 15 respectfully \nrequests that the Commission waive the requirements contained therein. \nV. \nCOMMUNICATIONS \nViridon Path 15 respectfully requests that all correspondence related to this filing be sent \nto the following individuals, and that they be placed on the official service list in this docket:102 \n \n100 Id. § 35.13(b)(6). \n101 ISO New England Inc. New England Power Co. d/b/a Nat’l Grid, 178 FERC ¶ 61,115, at P 57 (Feb. 18, 2022); \nsee also id. at P 57 n.91 (collecting previous FERC orders on this point). \n102 Pursuant to 18 C.F.R. § 385.101(e), Viridon Path 15 respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) to \npermit more than two persons to be added to the Commission’s official service list in this proceeding."},{"page":22,"startToken":8132,"endToken":8245,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 22 \n \n \n \nVerónica Gómez  \nGeneral Counsel and  \nChief Administrative Officer  \nChad Newhouse \nVice President Regulatory \nViridon Services LLC \n515 North State Street \nSuite 1150 \nChicago, IL 60654  \n(773) 551-1920 \nveronica@viridon.com \nchad@viridon.com \nJordan Pinjuv \nMichael Miller \nWilkinson Barker Knauer, LLP \n2138 W. 32nd Ave. \nSuite 300 \nDenver, CO 80211 \n303-626-2350 \njpinjuv@wbklaw.com \nmmiller@wbklaw.com  \n \nVI. \nCONCLUSION \nViridon Path 15 respectfully requests that the Commission permit the revised Path 15 Tariff \nto become effective as of February 16, 2027.  \nRespectfully Submitted, \n \nWILKINSON BARKER KNAUER, LLP \n \n \n/s/ Jordan Pinjuv  \nJordan Pinjuv \nMichael Miller \n \nCounsel for Viridon Path 15 LLC \n \n \nDated: November 16, 2026"},{"page":23,"startToken":8245,"endToken":8307,"text":"Ms. Debbie-Anne A. Reese \nNovember 16, 2026 \nPage 23 \n \n \n \nCERTIFICATE OF SERVICE \n I hereby certify that a copy of this filing, including attachments, has been served \nelectronically upon all Path 15 Tariff customers and each registered person on the official service \nlist compiled by the Secretary in Docket No. EL26-71-000. \n \nDated, this 16th day of November, 2026 \n \n/s/ Jordan Pinjuv \n \n \n \n \n \n \n \n \nJordan Pinjuv"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1333,"startToken":0,"endToken":598},{"p":2,"at":1333,"title":"I. BACKGROUND AND SUMMARY OF FILING","method":"printed heading","endPage":4,"endAt":1711,"startToken":598,"endToken":1651},{"p":4,"at":1711,"title":"II. DESCRIPTION AND BASIS FOR THE TO TARIFF REVISIONS","method":"printed heading","endPage":5,"endAt":887,"startToken":1651,"endToken":1922},{"p":5,"at":887,"title":"A. Application and Study Procedures Applicable to Eligible Customers Seeking","method":"printed heading","endPage":12,"endAt":754,"startToken":1922,"endToken":4566},{"p":12,"at":754,"title":"B. Cost-Recovery Mechanisms that Prevent Cost-Shifts to Third Parties","method":"printed heading","endPage":14,"endAt":955,"startToken":4566,"endToken":5409},{"p":14,"at":955,"title":"C. Rates, Terms, and Conditions for Large Loads Co-Located with Generation","method":"printed heading","endPage":15,"endAt":465,"startToken":5409,"endToken":5731},{"p":15,"at":465,"title":"D. Extending New Transmission Service to Eligible Customers Taking Service on","method":"printed heading","endPage":18,"endAt":1223,"startToken":5731,"endToken":6997},{"p":18,"at":1223,"title":"E. Large Load Electrically Proximate to Generation Resources","method":"printed heading","endPage":20,"endAt":60,"startToken":6997,"endToken":7541},{"p":20,"at":60,"title":"III. INFORMATION REQUIRED UNDER 18 C.F.R. § 35.13(b)","method":"printed heading","endPage":20,"endAt":259,"startToken":7541,"endToken":7576},{"p":20,"at":259,"title":"A. Documents Submitted with this Filing94","method":"printed heading","endPage":20,"endAt":437,"startToken":7576,"endToken":7603},{"p":20,"at":437,"title":"B. Proposed Effective Date95","method":"printed heading","endPage":20,"endAt":560,"startToken":7603,"endToken":7622},{"p":20,"at":560,"title":"C. Persons Receiving Service96","method":"printed heading","endPage":20,"endAt":845,"startToken":7622,"endToken":7665},{"p":20,"at":845,"title":"D. Description of Rate Change98","method":"printed heading","endPage":20,"endAt":975,"startToken":7665,"endToken":7686},{"p":20,"at":975,"title":"E. Statement of the Reasons for the Rate Change99","method":"printed heading","endPage":21,"endAt":60,"startToken":7686,"endToken":7781},{"p":21,"at":60,"title":"F. Requisite Agreement to the Rate Change100","method":"printed heading","endPage":21,"endAt":438,"startToken":7781,"endToken":7838},{"p":21,"at":438,"title":"IV. REQUEST FOR WAIVERS","method":"printed heading","endPage":21,"endAt":1506,"startToken":7838,"endToken":8010},{"p":21,"at":1506,"title":"V. COMMUNICATIONS","method":"printed heading","endPage":22,"endAt":472,"startToken":8010,"endToken":8198},{"p":22,"at":472,"title":"VI. CONCLUSION","method":"printed heading","endPage":23,"endAt":60,"startToken":8198,"endToken":8254},{"p":23,"at":60,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":23,"endAt":422,"startToken":8254,"endToken":8307}]}