{"document":{"slug":"rec-20261116-5335-5","title":"Att H Pro Forma LL Interconnection Agreement","issued":"2026-11-16","accession":"20261116-5335","docket":"ER27-529-000","group":"NYISO and New York transmission owners’ large-load tariff revisions","filer":"New York Independent System Operator, Inc.Central Hudson Gas & Electric CorporationNew York State Electric & Gas Corporation ,Rochester Gas and Electric Corporation ,Niagara Mohawk Power Corporation ,Consolidated Edison Company of New York, Inc. ,Orange and Rockland Utilities, Inc. ,","kind":"attachment","file":"sources/filings/text/20261116-5335_009.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5335","tier":"record","parent":"rec-20261116-5335","sha256":"88f1688e44b0d75c5fba2ac7d3e4b550e2fa38ecc607c9a6f09baefda2024988","pages":44,"tokens":14362,"emptyPages":[],"textThemes":["cost","study","registry","credit"]},"pages":[{"page":1,"startToken":0,"endToken":8,"text":"Attachment H \nPro Forma Large Load Interconnection Agreement"},{"page":2,"startToken":8,"endToken":48,"text":"44.16.11 Appendix 11 to Attachment LL – Pro Forma Interconnection Agreement  \n \n[TRANSMISSION OWNER] SERVICE AGREEMENT NO. [●] \nPRO FORMA LARGE LOAD INTERCONNECTION \nAGREEMENT \nBETWEEN \n[LEGAL NAME OF TRANSMISSION OWNER] \n(Transmission Owner) \nAND \n[LEGAL NAME OF CUSTOMER] \n(Customer) \nDated as of [●]"},{"page":3,"startToken":48,"endToken":192,"text":"TABLE OF CONTENTS \nRecitals \nArticle 1: Definitions \nArticle 2: Effective Date, Term, and Termination \nArticle 3: Scope of Interconnection Service \nArticle 4: Conditions to Energization and Permission to Operate \nArticle 5: Engineering, Procurement, and Construction \nArticle 6: Cost Responsibility, Security, and Payment \nArticle 7: Operations \nArticle 8: Emergencies \nArticle 9: Metering and Telemetry \nArticle 10: Testing and Inspection \nArticle 11: Maintenance \nArticle 12: Modifications \nArticle 13: Information Requirements \nArticle 14: Regulatory Requirements and Governing Law \nArticle 15: Notices \nArticle 16: Force Majeure, Breach, and Default \nArticle 17: Indemnity, Limitation of Liability, and Consequential Damages \nArticle 18: Insurance \nArticle 19: Confidentiality \nArticle 20: Dispute Resolution \nArticle 21: Representations and Warranties \nArticle 22: Assignment \nArticle 23: Miscellaneous \n• Exhibit A: Large Load Project and Customer Attachment Facilities \n• Exhibit B: Point(s) of Interconnection and Point(s) of Change of Ownership, TO \nAttachment Facilities, and Network Upgrade Facilities"},{"page":4,"startToken":192,"endToken":236,"text":"• Exhibit C: Simplified One-Line Diagram \n• Exhibit D: Milestones \n• Exhibit E: Operating Requirements \n• Exhibit F: Conditions to Initial Energization and Parallel Operation \n• Exhibit G: Cost Recovery, Security, and Related Agreements \n• Exhibit H: Form of Commercial Operation Date Notice \n• Exhibit I: Addresses for Notices and Billings"},{"page":5,"startToken":236,"endToken":678,"text":"PRO FORMA \nLARGE LOAD INTERCONNECTION AGREEMENT \nThis LARGE LOAD INTERCONNECTION AGREEMENT (this “Agreement”) is made and \nentered into as of [Date] (the “Execution Date”) by and between [LEGAL NAME OF \nTRANSMISSION OWNER], a [New York corporation / municipal instrumentality / public \nbenefit corporation] organized and existing under the laws of the State of New York, with offices \nat [Address] (“Transmission Owner” or “TO”), and [LEGAL NAME OF CUSTOMER], a [entity \ntype and jurisdiction], with offices at [Address] (“Customer”). Transmission Owner and \nCustomer are each referred to herein as a “Party” and collectively as the “Parties.” \nRECITALS \nWHEREAS, Transmission Owner owns and operates, among other things, electric transmission \nfacilities that form part of the New York State Transmission System, provides transmission \nservice over such facilities through the New York Independent System Operator, Inc. (“NYISO”) \npursuant to the Tariff on file with FERC, and [provides electric delivery service pursuant to its \nretail tariff on file with the NYPSC]; \nWHEREAS, Customer intends to design, construct, own, operate, and maintain a large load \nfacility, together with the associated Customer Attachment Facilities, located at [Site Address] \n(the “Load Facility”), as more particularly described in Exhibit A; \nWHEREAS, Customer has requested that the Load Facility be interconnected to Transmission \nOwner’s transmission system at the Point of Interconnection identified in Exhibit B, with a \nMaximum Load Facility Peak Demand of [●] MW; \nWHEREAS, Transmission Owner, alone or in coordination with NYISO, has conducted or will \nconduct a System Impact Study, a Facilities Study, and such other engineering, detailed design, \nand special studies as are required by Applicable Laws and Regulations, Applicable Reliability \nStandards, and Good Utility Practice to determine the effect of the Load Facility on the TO \nSystem and the New York State Transmission System and the need, if any, for TO Attachment \nFacilities and the Customer Attachment Facilities and Network Upgrades[, and the Parties have \nentered into or will enter into a Cost Recovery Agreement dated [●] with respect to the Network \nUpgrades and TO Attachment Facilities determined to be necessary as a result of such studies]; \nWHEREAS, Transmission Owner will design, construct, own, operate, and maintain the TO \nAttachment Facilities and, if applicable, the Network Upgrades, and Customer will design, \nconstruct, own, operate, and maintain the Customer Attachment Facilities, in each case at \nCustomer’s cost to the extent provided in this Agreement or the Cost Recovery Agreement; and \nWHEREAS, the Parties wish to set forth the terms and conditions under which the Load Facility \nwill be interconnected with, and operated in parallel with, the transmission system. \nNOW, THEREFORE, in consideration of the mutual covenants and agreements set forth \nherein, and intending to be legally bound, the Parties agree as follows:"},{"page":6,"startToken":678,"endToken":1137,"text":"ARTICLE 1 \nDEFINITIONS \nWhenever used in this Agreement with initial capitalization, the following terms have the \nmeanings specified in this Article 1. Capitalized terms used but not defined in this Agreement \nhave the meanings given in the Tariff or the NYISO Services Tariff, as applicable. \n1.1 \n“Affiliate” means, with respect to a person or entity, any other person or entity \ndirectly or indirectly controlling, controlled by, or under common control with such \nperson or entity. “Control” means the possession, directly or indirectly, of the \npower to direct the management or policies of a person or entity; a voting interest \nof ten percent (10%) or more creates a rebuttable presumption of control. \n1.2 \n“Applicable Laws and Regulations” means all duly promulgated or issued \napplicable federal, state, and local laws, treaties, statutes, regulations, rules, \nordinances, codes, decrees, judgments, permits, licenses, approvals, directives, and \njudicial, executive, or administrative orders of any Governmental Authority, \nincluding Environmental Law and the NYISO tariffs, manuals, and technical \nbulletins, in each case as amended from time to time. \n1.3 \n“Applicable Reliability Standards” means the requirements and guidelines of \nNERC, NPCC, and NYSRC, and of the transmission district to which the Load \nFacility is directly interconnected, as amended from time to time; provided that no \nParty waives its right to challenge the applicability or validity of any such \nrequirement or guideline as applied to it. \n1.4 \n“Attachment Facilities” means all facilities and equipment between the Load \nFacility and the Point of Interconnection, including any modifications, additions, \nor upgrades that are necessary to physically and electrically interconnect the Load \nFacility to the New York State Transmission System. Attachment Facilities are sole \nuse facilities and shall not include Network Upgrades. Attachment Facilities may \ninclude equipment (e.g., metering) necessary for the entity authorized to serve load \nwithin a Transmission District, if Transmission Owner is not the entity authorized \nto serve that load. \n1.5 \n“Breach” means the failure of a Party to perform any material term, condition, or \nobligation of this Agreement, and “Breaching Party” means the Party that has \ncommitted a Breach. \n1.6 \n“Business Day” means Monday through Friday, excluding federal holidays and \n[TO holidays].  \n1.7 \n“Calendar Day” means any day, including Saturday, Sunday, or a federal holiday. \n1.8 \n“Commercial Operation” means the status of the Load Facility once (a) the Load \nFacility has successfully completed testing and commissioning in accordance with \nthis Agreement and the Operating Documents; (b) the In-Service Date has occurred \nfor the TO Attachment Facilities and Network Upgrades, and the Customer \nAttachment Facilities have been completed, energized, and placed into service, in \neach case to the extent necessary for the Load Facility to take firm electric service \nat or above its designated minimum capacity commitment; (c) all conditions"},{"page":7,"startToken":1137,"endToken":1605,"text":"precedent to Delivery Service have been satisfied; (d) Transmission Owner has \nissued Permission to Operate; and (e) the Load Facility is in operation. \n1.9 \n“Commercial Operation Date” means the date on which the Load Facility has \nachieved energization and begins taking firm electric service at or above its \ndesignated minimum capacity commitment, as confirmed by notice substantially in \nthe form of Exhibit H. \n1.10 \n“Cost Recovery Agreement” means the [Large Load Cost Recovery Agreement] \nbetween Transmission Owner and Customer dated [●], attached as or referenced in \nExhibit G, which governs Customer’s responsibility for and payment of the costs \nof the Network Upgrades and the TO Attachment Facilities, including through the \nLarge Load Upgrade Charge (as defined therein), as amended from time to time. \n1.11 \n“Customer Attachment Facilities” means all facilities and equipment on \nCustomer’s side of the Point of Change of Ownership that are owned or controlled \nby Customer, including but not limited to breakers, switches, transformers, bus \nwork, cables, relays, System Protection Facilities, communication and telemetry \nequipment, and associated civil and structural works, as described and shown in \nExhibits A and C. \n1.12 \n“Default” means the failure of a Breaching Party to cure a Breach in accordance \nwith Article 16. \n1.13 \n“Delivery Service” means the electric delivery service provided to Customer \npursuant to the applicable Tariff, for delivery of energy from the New York State \nTransmission System to the Load Facility. \n1.14 \n“Emergency State” means a condition or situation that, in the reasonable judgment \nof a Party or NYISO, (a) presents an imminent threat to the safety of persons or \nproperty, or (b) requires automatic or immediate manual action to prevent or limit \nloss of, or threatens the integrity, reliability, or security of, the TO System or the \nNew York State Transmission System. \n1.15 \n“Environmental Law” means Applicable Laws and Regulations relating to \npollution or protection of the environment or natural resources. \n1.16 \n“Exceedance Event” means the Load Facility exceeding the energy or demand \nstated for the applicable period as further defined in Article 3.7 and Exhibits A and \nC.  \n1.17 \n“FERC” means the Federal Energy Regulatory Commission or any successor \nagency. \n1.18 \n“Force Majeure” has the meaning set forth in Article 16.1. \n1.19 \n“Good Utility Practice” means any of the practices, methods, and acts engaged in \nor approved by a significant portion of the electric utility industry during the \nrelevant time period, or any of the practices, methods, and acts which, in the \nexercise of reasonable judgment in light of the facts known at the time the decision \nwas made, could have been expected to accomplish the desired result at a \nreasonable cost consistent with good business practices, reliability, safety, and \nexpedition. Good Utility Practice is not intended to be limited to the optimum"},{"page":8,"startToken":1605,"endToken":2069,"text":"practice, method, or act to the exclusion of all others, but rather to delineate \nacceptable practices, methods, or acts generally accepted in the region. \n1.20 \n“Governmental Authority” means any federal, state, local, or other \ngovernmental, regulatory, or administrative agency, court, commission, \ndepartment, board, legislature, tribunal, or other governmental authority having \njurisdiction over a Party, its facilities, or the services it provides. \n1.21 \n“Hazardous Substances” means any chemical, material, or substance defined as \nor included in the definition of “hazardous substances,” “hazardous wastes,” \n“hazardous materials,” “toxic substances,” “pollutants,” “contaminants,” or words \nof similar meaning and regulatory effect under any Environmental Law. \n1.22 \n“In-Service Date” means the date on which the TO Attachment Facilities and \nNetwork Upgrades are energized, as set forth in Exhibit D. \n1.23 \n“Load Ramp Projection” has the meaning set forth in Article 3.5. \n1.24 \n“Material Modification” means any modification to the Load Facility or \nCustomer Attachment Facilities that, in Transmission Owner’s reasonable \njudgment, may require changes to the TO Attachment Facilities and the Customer \nAttachment Facilities or Network Upgrades or may otherwise materially affect \nsystem reliability, including (a) an increase or decrease in maximum demand \nbeyond levels specified in the Operating Documents; (b) a material change in power \nfactor, ramp rate, or other operating characteristics, including those reported in the \nNYISO Load Interconnection Data Request; (c) relocation of the Point of \nInterconnection; or (d) any modification having a material impact on the cost or \ntiming of any interconnection request with a later queue position. \n1.25 \n“Maximum Annual Energy” means the maximum annual energy (in MWh) to be \nconsumed by the Load Facility, as measured at the Point of Interconnection during \nany calendar year, as set forth in Exhibit A, prorated for any partial calendar year. \n1.26 \n“Maximum Load Facility Peak Demand” means the maximum peak demand for \nFirm Withdrawal Service of the Load Facility at any time, as set forth in Exhibit A, \nnot to exceed the amount studied in the System Impact Study and Facilities Study.  \n1.27 \n“Metering Equipment” means all revenue-quality metering equipment installed \nor to be installed at or near the Point of Interconnection, including instrument \ntransformers, meters, data acquisition equipment, transducers, remote terminal \nunits, and communications equipment, as specified in Exhibit B. \n1.28 \n“Minimum Committed Load” means [eighty percent (80%)] of the Maximum \nLoad Facility Peak Demand.  \n1.29 \n“NERC” means the North American Electric Reliability Corporation, or its \nsuccessor. \n1.30 \n“Network Upgrades” means additions, modifications, enhancements, or \nreplacements to the TO System or the New York State Transmission System at or \nbeyond the Point of Interconnection, other than TO Attachment Facilities, that are \nrequired to accommodate the interconnection of the Load Facility and maintain \nsystem reliability, as identified in the System Impact Study, the Facilities Study,"},{"page":9,"startToken":2069,"endToken":2488,"text":"and such other engineering, detailed design, and special studies, and set forth in \nExhibit B. \n1.31 \n“New York State Transmission System” means the entire New York State \nelectric transmission system, including the transmission facilities under NYISO \noperational control, the transmission facilities requiring NYISO notification, and \nall remaining transmission facilities within the New York Control Area. \n1.32 \n“NPCC” means the Northeast Power Coordinating Council, Inc., or its successor. \n1.33 \n“NYISO” has the meaning set forth in the Recitals and includes any successor \nthereto. \n1.34 \n“NYPSC” means the New York State Public Service Commission, or its successor. \n1.35 \n“NYSRC” means the New York State Reliability Council, L.L.C., or its successor. \n1.36 \n“Operating Documents” means the operating requirements developed by \nTransmission Owner and provided to Customer before initial energization, \nincluding those described in Exhibit E, and the Operations Manual described in \nArticle 7.11, in each case as amended from time to time in accordance with this \nAgreement. \n1.37 \n“Permission to Operate” or “PTO” means the written authorization issued by \nTransmission Owner permitting Customer to place the Load Facility into \nCommercial Operation and to take Delivery Service at the Point of Interconnection \nupon satisfaction of the conditions set forth in Article 4 and Exhibit F. \n1.38 \n“Point of Change of Ownership” or “PCO” means the point described in Exhibit \nB and shown in Exhibit C. \n1.39 \n“Point of Interconnection” or “POI” means the physical point, described in \nExhibit B and shown in Exhibit C, at which the Attachment Facilities connect to \nthe New York State Transmission System. \n1.40 \n“Reasonable Efforts” means, with respect to an action required to be attempted or \ntaken by a Party, efforts that are timely and consistent with Good Utility Practice \nand are substantially equivalent to those a Party would use to protect its own \ninterests. \n1.41 \n“Related Agreements” means, collectively, the Cost Recovery Agreement, the \nSecurity Agreement, and any other agreements listed in Exhibit G. \n1.42 \n“Security Agreement” means the [Large Load Security Agreement] between the \nParties dated [●], attached as or referenced in Exhibit G, which governs the posting, \nmaintenance, adjustment, application, and release of the security Customer \nprovides to Transmission Owner for the TO Attachment Facilities and Network \nUpgrades, as amended from time to time. \n1.43 \n“Single Contingency Design” means a design of the interconnection under which \nservice to the Load Facility may be interrupted upon the loss of a single element of \nthe TO System, as described in Exhibit E."},{"page":10,"startToken":2488,"endToken":2906,"text":"1.44 \n“System Impact Study” or “SIS” means the study performed by NYISO, in \ncoordination with Transmission Owner, under Attachment LL of the Tariff \n(including the Assessment of Load Integration) to evaluate the impact of the Load \nFacility on the New York State Transmission System. \n1.45 \n“Facilities Study” means the study performed by or on behalf of Transmission \nOwner under the facilities study agreement between the Parties to specify and \nestimate the cost of the TO Attachment Facilities and Network Upgrades, including \nany updates thereto. \n1.46 \n“System Protection Facilities” means the equipment, including protection signal \ncommunications and direct transfer trip equipment, required to protect (a) the New \nYork State Transmission System from faults or other disturbances occurring at the \nLoad Facility and (b) the Load Facility from faults or other disturbances occurring \non the New York State Transmission System. \n1.47 \n“Tariff” means the NYISO Open Access Transmission Tariff, including \nTransmission Owner-specific rate schedules and attachments on file with and \naccepted by FERC, and, where applicable, Transmission Owner’s retail electric \ntariff on file with the NYPSC, each as amended from time to time. “NYISO \nServices Tariff” means the NYISO Market Administration and Control Area \nServices Tariff. \n1.48 \n“TO Attachment Facilities” means all facilities and equipment owned or \ncontrolled by Transmission Owner between the Point of Interconnection and the \nPoint of Change of Ownership that are constructed or modified for the purpose of \ninterconnecting the Load Facility, including line taps, breakers, disconnect \nswitches, bus work, metering instrument transformers (if owned by Transmission \nOwner), System Protection Facilities at a Transmission Owner substation, and \nassociated civil and structural works, as described and shown in Exhibits B and C. \n1.49 \n“TO Standards” means Transmission Owner’s design criteria, specifications, \nprocedures, policies, guidelines, and requirements for customer interconnections, \nas provided to Customer and/or referenced in Exhibit B. \n1.50 \n“TO System” means the electric facilities owned or controlled by Transmission \nOwner, including its transmission system and distribution system.  \nARTICLE 2 \nEFFECTIVE DATE, TERM, AND \nTERMINATION \n2.1 \nEffective Date. This Agreement shall become effective upon the later of (a) the \nExecution Date; (b) Customer’s execution and delivery of the Security Agreement \nand any other agreements listed in Exhibit G; and (c) if Transmission Owner \ndetermines that this Agreement must be filed with FERC or the NYPSC, the \neffective date established upon acceptance of such filing (the “Effective Date”). \n2.2 \nConditions to Interconnection Activities. The Parties’ obligations to undertake \nconstruction, testing, and other interconnection activities are conditioned upon (a)"},{"page":11,"startToken":2906,"endToken":3352,"text":"completion of the System Impact Study, Facilities Study, and such other \nengineering, detailed design, and special studies as are required; (b) execution of \nany related construction or cost reimbursement agreements, the Cost Recovery \nAgreement, the Security Agreement, and any transmission service agreement \nrequired under the applicable Tariff (“TSA”), and receipt of required deposits and \nadvance payments; (c) receipt of all Required Approvals; and (d) completion of the \ninitial Operating Documents. If this Agreement is required to be filed with FERC \nor the NYPSC, Transmission Owner shall have no obligation to commence \nengineering, procurement, or construction before acceptance of such filing. \n2.3 \nTerm. This Agreement shall remain in effect for [fifteen (15)] years from the \nEffective Date [or, if longer, the term of the Cost Recovery Agreement] (the “Initial \nTerm”) and shall thereafter automatically renew for successive [five (5)]-year \nperiods unless either Party provides written notice of non-renewal at least one \nhundred eighty (180) Calendar Days before the end of the then-current term, unless \nearlier terminated in accordance with this Agreement (the “Term”). Neither Party \nmay deliver a notice of non-renewal while the Cost Recovery Agreement remains \nin effect. \n2.4 \nTermination. This Agreement may be terminated as follows: \n(1) \nby mutual written agreement of the Parties; \n(2) \nby Customer for any reason upon at least one hundred eighty (180) Calendar \nDays’ prior written notice, subject to payment of the Net Present Value \nResidual Charge (as defined in the Cost Recovery Agreement), all amounts \nowed under this Agreement, the Security Agreement, the Cost Recovery \nAgreement, and any other related agreements, and confirmation that all \namounts owed to NYISO for the Load Facility have been paid; such \ntermination shall constitute an early termination under the Cost Recovery \nAgreement; \n(3) \nby Transmission Owner upon thirty (30) Calendar Days’ prior written \nnotice if Customer fails to achieve Commercial Operation within twelve \n(12) months after Transmission Owner has completed the TO Attachment \nFacilities and any required Network Upgrades, or such later date as the \nParties agree in writing, or if Customer fails to achieve any Customer \nmilestone in Exhibit D by more than one hundred eighty (180) Calendar \nDays for reasons other than Force Majeure or Transmission Owner’s \nBreach; provided that such termination shall not relieve Customer of its \nobligations under Article 2.6, the Cost Recovery Agreement, or the Security \nAgreement; \n(4) \nby the non-defaulting Party upon a Default in accordance with Article 16; \nor \n(5) \nby either Party upon thirty (30) Calendar Days’ prior written notice if a \nParty is prevented by Force Majeure from materially performing its \nobligations for twelve (12) consecutive months; provided Customer’s \ntermination under this clause shall not relieve Customer of its obligations"},{"page":12,"startToken":3352,"endToken":3820,"text":"under Article 2.6, the Cost Recovery Agreement, or the Security \nAgreement. \n2.5 \nTransmission Owner Rights Upon Customer Breach. Without limiting Article \n2.4, upon a Breach by Customer that remains uncured for ten (10) Business Days \nafter notice, Transmission Owner may suspend work on the TO Attachment \nFacilities and Network Upgrades, suspend or reduce service to the Load Facility to \nthe extent consistent with Applicable Laws and Regulations, and draw upon \nsecurity under the Security Agreement, in each case until the Breach is cured. \nCustomer shall bear all costs of suspension and remobilization, and milestone dates \nshall be extended as reasonably necessary. \n2.6 \nTermination Costs. Upon any termination other than for Transmission Owner’s \nDefault, Customer shall pay all costs incurred or irrevocably committed by \nTransmission Owner as of the date of termination that are Customer’s responsibility \nunder this Agreement, including cancellation costs for orders and contracts for TO \nAttachment Facilities and the Customer Attachment Facilities, Network Upgrades, \nand equipment, and all costs of the removal, relocation, retirement, or other \ndisposition of such facilities to the extent required by Good Utility Practice and \nnecessary to restore the New York State Transmission System to a reliable \ncondition in accordance with Applicable Reliability Standards, in each case except \nto the extent such costs are recovered under the Cost Recovery Agreement. Each \nParty shall use Reasonable Efforts to mitigate such costs. Early termination and \nstranded cost payments, including the Net Present Value Residual Charge (as \ndefined in the Cost Recovery Agreement) for the TO Attachment Facilities and \nNetwork Upgrades, are further governed by the Cost Recovery Agreement and the \nSecurity Agreement.  \n2.7 \nDisconnection Upon Termination. Upon termination, Transmission Owner shall \ntake all appropriate steps to disconnect the Load Facility from the New York State \nTransmission System consistent with Good Utility Practice, and Customer shall \ncooperate with any disconnection and bear all costs of disconnection. \n2.8 \nSurvival. This Agreement shall continue in effect after termination to the extent \nnecessary to provide for final billings and payments; to permit the determination \nand enforcement of liability and indemnification obligations arising from acts or \nevents that occurred while this Agreement was in effect; to give effect to the \nconfidentiality and dispute resolution provisions; and to permit each Party to access \nthe lands of the other to disconnect, remove, or salvage its facilities. \nARTICLE 3 \nSCOPE OF INTERCONNECTION SERVICE \n3.1 \nProvision of Service. For purposes of this Agreement, Transmission Owner shall \nprovide load interconnection service to Customer at the Point of Interconnection \nfor the Term, up to the Maximum Load Facility Peak Demand, subject to this \nAgreement, the Tariff, and Applicable Laws and Regulations. \n3.2 \nLoad Limits. Customer shall ensure that the actual demand of the Load Facility \ndoes not exceed the Maximum Load Facility Peak Demand, the Maximum Annual"},{"page":13,"startToken":3820,"endToken":4328,"text":"Energy, or the amount fully studied in the System Impact Study and Facilities \nStudy, as measured at the Point of Interconnection.  \n3.3 \nIdentification of Reliability Violation. If NYISO or Transmission Owner \nidentifies a reliability violation associated with the Load Facility, at any time, \nTransmission Owner shall notify Customer of the amount of load that may be \nreliably served, and the Parties shall coordinate operational limitations or \nmitigation measures to minimize interruptions or reductions; Customer shall \nconform its load to such amount. \n3.4 \nNo Transmission Service or Other Services. This Agreement does not constitute \na request for, or agreement to provide, transmission service under the Tariff, or the \nsale or purchase of energy, capacity, or ancillary services under the NYISO \nServices Tariff. Transmission Owner does not sell electric energy under this \nAgreement. Customer shall be solely responsible for arranging its energy supply \nand shall maintain a service agreement with a load serving entity for the Load \nFacility. All Delivery Service shall be provided pursuant to, and billed in \naccordance with, the applicable Tariff, and Customer shall select and qualify for \nthe applicable service classification. Nothing in this Agreement obligates \nTransmission Owner to provide Delivery Service beyond the Tariff or to expand \nthe transmission system beyond the facilities identified in the studies for the Load \nFacility. \n3.5 \nLoad Ramp Projection. Within ten (10) Business Days after the Effective Date, \nCustomer shall provide monthly projections of energy and demand for the Term in \nthe form of Exhibit A. On the fifth anniversary of the Effective Date and every fifth \nanniversary thereafter, Customer shall provide updated projections for the \nremainder of the Term (the most recent version, the “Load Ramp Projection”); \nprovided that no update may change the monthly projections by more than [five \npercent (5%)] from the prior version (absent prior written authorization by \nTransmission Owner and NYISO), and in no event may the demand projection \nexceed the Maximum Load Facility Peak Demand or the annual energy projection \nexceed the Maximum Annual Energy.  \n3.6 \nReduction of Interconnection Rights. If the Load Facility fails to meet the \nMinimum Committed Load for [three (3)] consecutive months or [three (3)] non-\nconsecutive months in any [six (6)]-month period after the Commercial Operation \nDate (a “Shortfall Event”), Transmission Owner may notify Customer that it \nintends to reduce the Maximum Load Facility Peak Demand if Customer does not \nconsistently meet the Minimum Committed Load during the following sixty (60) \nCalendar Days. Any reduction shall be proportionate to the average load shortfall \nover the applicable period, and Exhibit A shall be amended accordingly, subject to \nany filing with or acceptance by FERC or the NYPSC required under Applicable \nLaws and Regulations. Any reduction of the Maximum Load Facility Peak Demand \nunder this Article 3.6 shall not reduce Customer’s obligations under the Cost \nRecovery Agreement or the Security Amount under the Security Agreement. \n3.7 \nExceedance Events. Customer shall not permit the actual demand or energy \nconsumption of the Load Facility to exceed the limits set forth in Article 3.2, and"},{"page":14,"startToken":4328,"endToken":4709,"text":"Exceedance Events are not permitted under this Agreement. The parameters, \nthresholds, number and duration of occurrences, and other criteria that constitute \nan Exceedance Event shall be as set forth in Exhibits A and C. Upon the occurrence \nof an Exceedance Event, Transmission Owner may require Customer to reduce \nload, may interrupt Delivery Service in accordance with Article 7.4, and may \nrequire additional study at Customer’s cost to identify any further upgrades \nnecessary to serve the Load Facility and additional security under the Security \nAgreement.  \nARTICLE 4 \nCONDITIONS TO ENERGIZATION AND \nPERMISSION TO OPERATE \n4.1 \nConditions Precedent. Transmission Owner shall not energize the Load Facility \nor permit its parallel operation with the TO System until the conditions set forth in \nExhibit F have been satisfied to Transmission Owner’s reasonable satisfaction. \n4.2 \nPermission to Operate. Upon satisfaction of the conditions in Exhibit F, \nTransmission Owner shall issue PTO or identify in writing the deficiencies \npreventing issuance of PTO within a reasonable time after completion of required \ntesting and receipt of all required documentation. \n4.3 \nParallel Operation. Upon issuance of PTO, Transmission Owner shall permit \nparallel operation of the Load Facility with the TO System subject to this \nAgreement, the Tariff, and Applicable Laws and Regulations. \nARTICLE 5 \nENGINEERING, PROCUREMENT, AND \nCONSTRUCTION \n5.1 \nTransmission Owner Construction. Transmission Owner shall use Reasonable \nEfforts to design, procure, construct, and install the TO Attachment Facilities and \nNetwork Upgrades described in Exhibit B by the milestone dates in Exhibit D. \nTransmission Owner will act in accordance with its safety practices, TO Standards, \nlabor agreements, applicable agreements, and Applicable Laws and Regulations. If \nTransmission Owner reasonably expects not to meet a milestone, it shall promptly \nnotify Customer (and NYISO, if required) and use Reasonable Efforts to meet the \nearliest practicable date thereafter. Milestones may otherwise be modified by \nmutual written agreement. \n5.2 \nCustomer Attachment Facilities. Customer shall, at its sole expense, design, \nprocure, construct, own, install, operate, and maintain the Customer Attachment \nFacilities and the Load Facility described in Exhibit A in accordance with Good \nUtility Practice, TO Standards (including the specifications, technical manuals, and \nstandards furnished by Transmission Owner), and Applicable Laws and \nRegulations. Customer shall submit design drawings and initial specifications for \nthe Customer Attachment Facilities, including System Protection Facilities, for"},{"page":15,"startToken":4709,"endToken":5170,"text":"Transmission Owner’s engineering review at least one hundred eighty (180) \nCalendar Days, and final specifications at least ninety (90) Calendar Days, before \nthe In-Service Date. Transmission Owner shall comment within thirty (30) \nCalendar Days, and Customer shall make such changes as Transmission Owner \nreasonably requires for compatibility with its technical, operational, and safety \nrequirements. At least ninety (90) Calendar Days before initial energization, \nCustomer shall deliver as-built or redlined drawings and relay settings for the \nCustomer Attachment Facilities, and within one hundred twenty (120) Calendar \nDays after the In-Service Date, Customer shall deliver final “as-built” drawings and \nrelay settings. Customer shall use Reasonable Efforts to complete the Customer \nAttachment Facilities and its other activities by the Customer milestone dates in \nExhibit D and acknowledges that Transmission Owner’s ability to meet its \nmilestones may depend on Customer’s timely completion of such activities. \n5.3 \nAffected Transmission Owner Construction. Facilities or Network Upgrades to \nbe constructed by an Affected Transmission Owner shall be governed by a separate \nagreement between Customer and the applicable Affected Transmission Owner. \nCustomer shall timely execute that agreement, provide all required payments, \ndeposits, information, property rights, and financial security, and promptly notify \nTransmission Owner of any delay in, or change to, the scope or milestones under \nsuch agreement. Transmission Owner shall use Reasonable Efforts to coordinate its \nwork with the Affected Transmission Owner but shall not be responsible for the \nAffected Transmission Owner’s acts, omissions, performance, or delays. Any \nTransmission Owner milestone dependent upon Affected Transmission Owner \nperformance shall be equitably extended to reflect the resulting delay. Customer’s \nability to receive service may be dependent on the completion of milestones under \nits agreements with the Affected Transmission Owner, and Transmission Owner \nshall not be required to energize the Load Facility, issue Permission to Operate, or \nauthorize the applicable level of service until all required Affected Transmission \nOwner facilities have been completed and placed in service. \n5.4 \nNo Warranty. Transmission Owner’s review, approval, inspection, or acceptance \nof any design, specification, or facility shall not constitute an endorsement or \nwarranty of its design, fitness, safety, durability, or reliability. TRANSMISSION \nOWNER DISCLAIMS ANY RESPONSIBILITY OR LIABILITY FOR THE \nDESIGN OR ENGINEERING OF THE LOAD FACILITY, OR THE \nCUSTOMER ATTACHMENT FACILITIES, EXCEPT FOR BREACH OF \nTRANSMISSION OWNER’S OBLIGATIONS HEREUNDER. \n5.5 \nWork Progress and Information Exchange. The Parties shall keep each other \nadvised of the progress of their respective design, procurement, and construction \nefforts, including through engineering and project meetings beginning thirty (30) \nCalendar Days before the start of construction at a cadence established by \nTransmission Owner, provide progress reports upon request, and exchange \ninformation (and provide NYISO information as required) regarding the design, \nmodification, and compatibility of their facilities, including submission of \nCustomer facility design details for Transmission Owner engineering review."},{"page":16,"startToken":5170,"endToken":5634,"text":"5.6 \nLand Rights. Each Party shall furnish to the other such rights of use, licenses, \nrights of way, or easements over lands it owns or controls as are reasonably \nnecessary to construct, operate, maintain, test, inspect, replace, or remove facilities \nunder this Agreement. For the avoidance of doubt, this Agreement (i) does not \nestablish on behalf of Customer or the Load Facility any rights or title to \nTransmission Owner’s real property, other than the limited rights reasonably \nnecessary for the Customer Attachment Facilities to connect to the TO Attachment \nFacilities, and (ii) does not create an obligation on Transmission Owner to transfer, \nconvey, or use its real property rights on behalf of Customer or the Load Facility, \nor to acquire property on behalf of Customer or the Load Facility. \n5.7 \nRight of Entry. Upon reasonable notice (or without notice in an Emergency State) \nand subject to the granting Party’s reasonable safety rules and site access \nprocedures, as amended from time to time, each Party shall permit the other to enter \nits property as reasonably necessary to perform its obligations under this \nAgreement. Customer shall provide Transmission Owner unescorted 24-hour \naccess to the TO Attachment Facilities, Metering Equipment, and System \nProtection Facilities located on Customer’s premises, subject only to compliance \nwith Customer’s site security protocols provided in advance. The accessing Party \nshall maintain the insurance required under Article 18, shall not unreasonably \ninterfere with the granting Party’s operations, and shall indemnify the granting \nParty against third-party claims resulting from its acts or omissions in connection \nwith its exercise of such access rights. \n5.8 \nPermits. Customer shall cooperate in good faith to obtain all permits, licenses, and \nauthorizations necessary for the performance of this Agreement. \n5.9 \nTransfers Regarding Real Property. To the extent that the TO Attachment \nFacilities or Network Upgrades require the acquisition of real estate, Customer \nrepresents and warrants that it holds, or will hold prior to transfer, and shall transfer, \nat Customer’s sole cost, all real estate rights necessary to own, operate, and \nmaintain the TO Attachment Facilities or Network Upgrades, free and clear of liens \nand encumbrances, and the ability to convey such rights to Transmission Owner in \naccordance with Transmission Owner requirements, by the date set forth in Exhibit \nD. \nARTICLE 6 \nCOST RESPONSIBILITY, SECURITY, AND \nPAYMENT \n6.1 \nCustomer Cost Responsibility. Customer’s responsibility for, and the recovery of, \nthe costs of the TO Attachment Facilities and the Network Upgrades shall be \ngoverned exclusively by the Cost Recovery Agreement or any other rate or \nagreement directed by FERC or the NYPSC, and no such costs shall be invoiced or \npayable under this Agreement. \n6.2 \nSecurity. As a condition to Transmission Owner’s performance with respect to the \nTO Attachment Facilities and Network Upgrades, Customer shall provide and"},{"page":17,"startToken":5634,"endToken":6182,"text":"maintain, at its sole cost, security in favor of Transmission Owner in the amounts, \nforms, and at the times specified in the Security Agreement. The amount, form, \nreplenishment, adjustment, draw, and release of such security shall be governed by \nthe Security Agreement. Transmission Owner may require additional security upon \na Material Modification. Failure to timely provide, maintain, or replenish such \nsecurity as required by the Security Agreement or this Article 6.2 shall constitute a \nBreach of this Agreement, in addition to any rights or remedies of Transmission \nOwner under the Security Agreement, and Article 6.6 shall not be construed to limit \nthe foregoing. Customer acknowledges that a Default under this Agreement, among \nother events, shall constitute a draw event under the Security Agreement. \n6.3 \nInvoicing and Payment. Transmission Owner reserves the right to invoice \nCustomer for any amount that may be due under this Agreement, including in \nadvance of performing the applicable work. Any such invoices shall be paid within \nthirty (30) Calendar Days of receipt in immediately available funds to the account \ndesignated in Exhibit I. Late payments shall bear interest calculated in accordance \nwith 18 C.F.R. § 35.19a(a)(2)(iii). \n6.4 \nBilling Disputes. Transmission Owner shall continue to perform during a billing \ndispute so long as Customer pays all amounts to Transmission Owner on or before \ntheir due date, regardless of whether Customer disputes the same in good faith. Any \nbalances that remain unpaid when due shall accrue interest at the interest rate \nspecified at 18 C.F.R. § 35.19a or successor regulation. Transmission Owner may \ninclude unpaid balances, with any accrued interest, on the next monthly bill. Any \ndisputes shall be addressed in accordance with Article 20. If Customer fails to pay \nany amount when due, Transmission Owner may issue a notice of Breach under \nArticle 16 and may exercise its rights under Article 6.2. Upon resolution of the \ndispute, the disputed amount shall be retained by or released to the Party in whose \nfavor the dispute is resolved, without interest, within thirty (30) Calendar Days after \nresolution. Billing disputes not raised within twelve (12) months after the invoice \ndate are waived. \n6.5 \nTaxes. The Parties intend that payments and property transfers by Customer to \nTransmission Owner for the TO Attachment Facilities and Network Upgrades be \nnon-taxable to the extent permitted by law. Customer shall indemnify Transmission \nOwner for the cost consequences of any tax liability imposed on Transmission \nOwner as a result of such payments or transfers, including interest and penalties \nother than those attributable to Transmission Owner’s delay.  \n6.6 \nRelationship to Cost Recovery Agreement and Security Agreement. This \nAgreement is entered into in connection with, and shall be read together with, the \nCost Recovery Agreement between Transmission Owner and Customer dated [●] \nand/or other applicable agreement and the Security Agreement between \nTransmission Owner and Customer dated [●]. Customer shall be the same legal \nentity as the customer under the Cost Recovery Agreement (or other applicable \nagreement) and the Security Agreement. No cost recovered under the Cost \nRecovery Agreement shall be recovered again under this Agreement. In the event \nof any conflict between this Agreement and the Cost Recovery Agreement \nregarding the costs of, or charges for, the Network Upgrades or the TO Attachment"},{"page":18,"startToken":6182,"endToken":6618,"text":"Facilities, the Cost Recovery Agreement shall control, and in the event of any \nconflict regarding security, the Security Agreement shall control. \nARTICLE 7 \nOPERATIONS \n7.1 \nCompliance; Change in Law. Each Party shall comply with Applicable Laws and \nRegulations and Applicable Reliability Standards and provide the other Party \ninformation reasonably required for such compliance. If a change in Applicable \nLaws and Regulations or Applicable Reliability Standards materially affects a \nParty’s rights, obligations, or performance, the affected Party shall notify the other, \nand the Parties shall negotiate in good faith an amendment to address such change. \n7.2 \nTransmission Owner Obligations. Transmission Owner shall operate and \nmaintain the TO Attachment Facilities and Network Upgrades in a safe and reliable \nmanner in accordance with TO Standards, the Tariff, and Applicable Laws and \nRegulations, and shall use Reasonable Efforts to maintain service to the Load \nFacility in accordance with the Operating Documents [and the Single Contingency \nDesign]. Transmission Owner may issue operating instructions consistent with this \nAgreement and its operating protocols. \n7.3 \nCustomer Obligations. Customer shall, at its own expense: \n(1) \noperate, maintain, and control the Load Facility and Customer Attachment \nFacilities in a safe and reliable manner in accordance with Good Utility \nPractice, TO Standards, the Operating Documents (including Exhibit E), \nand Applicable Laws and Regulations; \n(2) \nmaintain the Load Facility within the Maximum Load Facility Peak \nDemand, power factor, voltage, ramp rate, and other operating \ncharacteristics specified in Exhibits A and E, it being understood that \nCustomer shall not be compensated for reactive power; \n(3) \nimplement under-frequency and over-frequency relay set points and permit \nNYISO or Transmission Owner to shed load as required by NPCC, NYISO, \nor Transmission Owner load-shed programs; and \n(4) \nnotify Transmission Owner immediately by telephone, and in writing within \ntwenty-four (24) hours, of any condition that materially affects or may \naffect the safe and reliable operation of the Load Facility, the Customer \nAttachment Facilities, or the TO System. \n7.4 \nInterruption and Disconnection. Transmission Owner may interrupt, reduce, or \ndisconnect service to the Load Facility, in whole or in part: (a) consistent with Firm \nWithdrawal Service, Non-Firm Withdrawal Service, or any other type of \ntransmission service for which Customer has taken service as specified in an \nexecuted TSA, as the case may be; (b) as necessary to construct, maintain, repair, \nreplace, or test the TO System or TO Attachment Facilities and the Customer \nAttachment Facilities; (c) if continued operation may endanger persons or property \nor adversely affect the safety or reliability of the TO System or the New York State \nTransmission System; (d) upon operation of any protective device or direct transfer"},{"page":19,"startToken":6618,"endToken":7126,"text":"trip equipment; (e) as required or directed by NYISO or any Governmental \nAuthority; (f) upon Exceedance Events as provided in Article 3.7; (g) if Customer \nlacks the agreements required for the purchase of energy; (h) upon a Default by \nCustomer or as provided in Article 2.5; (i) if Customer operates the Load Facility \nwithout PTO or implements a Material Modification without approval; or (j) as \notherwise permitted by the Tariff or Applicable Laws and Regulations. Any \ninterruption shall continue only as long as reasonably necessary under Good Utility \nPractice, be made on a non-discriminatory basis, and, except in an Emergency \nState, be scheduled after advance notice and, to the extent practicable, during \nperiods of least impact. Where advance notice is not possible, Transmission Owner \nshall notify Customer by telephone as soon as practicable, followed by written \nnotice. Interruptions resulting from the Single Contingency Design shall not \nconstitute a Breach by Transmission Owner, and Transmission Owner shall have \nno liability therefor except to the extent caused by its gross negligence or willful \nmisconduct. \n7.5 \nOutages. Each Party may, in accordance with Good Utility Practice and in \ncoordination with the other, remove from service its facilities that may affect the \nother Party to perform maintenance, testing, or replacement, using Reasonable \nEfforts to schedule such outages at mutually acceptable times and to minimize their \neffect. Customer shall submit planned maintenance schedules for a rolling eighteen \n(18)-month period, and Transmission Owner may request rescheduling to maintain \nreliability. The owner of a facility that is out of service shall use Reasonable Efforts \nto restore it promptly and keep the other Party informed. Nothing in this Agreement \nrestricts Transmission Owner’s use of the TO System to serve other customers. \n7.6 \nCustomer Disconnection. Customer may temporarily disconnect the Load Facility \nin accordance with TO Standards and the Operating Documents on at least thirty \n(30) Calendar Days’ prior notice of a planned disconnection and [prompt advance] \nnotice of an emergency disconnection. \n7.7 \nSystem Protection and Power Quality. Customer shall, at its expense, install, \noperate, and maintain System Protection Facilities, including a load-interrupting \ndisconnecting device accepted by Transmission Owner at a mutually agreed \nlocation, and any System Protection Facilities as required by Transmission Owner \ndue to the interconnection. Each Party’s protection shall be coordinated in \naccordance with Good Utility Practice and Applicable Reliability Standards, \ninclude necessary test switches, and be calibration- and functional-trip-tested \nbefore the In-Service Date and at intervals required by Good Utility Practice. \nNeither Party’s facilities shall cause excessive voltage flicker or harmonic \ndistortion as defined by ANSI C84.1 and IEEE 519, or any successor standards. \n7.8 \nSwitching and Tagging. All switching and tagging affecting the TO System or the \nTO Attachment Facilities and the Customer Attachment Facilities shall be \nperformed by Transmission Owner, or pursuant to switching orders issued by \nTransmission Owner, and in accordance with the Operating Documents and \nTransmission Owner’s switching and tagging rules. Transmission Owner’s system \noperator shall have operational jurisdiction over switching operations affecting the \nTO System, as identified in Exhibit E."},{"page":20,"startToken":7126,"endToken":7566,"text":"7.9 \nUse of TO Attachment Facilities and the Customer Attachment Facilities. \nExcept as required by Applicable Laws and Regulations or agreed in writing, the \nTO Attachment Facilities and Customer Attachment Facilities shall be used solely \nto interconnect the Load Facility. \n7.10 \nDisturbance Analysis. The Parties shall cooperate in the analysis of disturbances \naffecting the Load Facility or the New York State Transmission System by \nproviding disturbance recorder data, relay targets, breaker operations, sequence-of-\nevents records, and logs. \n7.11 \nOperations Manual. At least ninety (90) Calendar Days before initial energization, \nCustomer shall prepare and submit for Transmission Owner’s review and approval \nan operations manual for the Load Facility and Customer Attachment Facilities \ncontaining, at a minimum, 24/7 emergency and operating contacts, maintenance \ncontacts, customer-specific operating characteristics, switching and clearance \nprocedures, outage and maintenance coordination procedures, SCADA and \ntelemetry points, and communication protocols (the “Operations Manual”). \nCustomer shall address Transmission Owner’s comments in good faith and \nresubmit the Operations Manual for approval. Customer shall update the \nOperations Manual as necessary and at least annually and shall submit any changes \nfor Transmission Owner’s review and approval before implementation. The \nOperations Manual shall be consistent with, and shall not conflict with, the \nOperating Documents and TO Standards, and in the event of any conflict, the \nOperating Documents and TO Standards shall control. The Parties shall perform \ntheir obligations under Articles 7, 8, 11, and 15 in accordance with the Operations \nManual. \nARTICLE 8 \nEMERGENCIES \n8.1 \nObligations. Each Party shall comply with the Emergency State procedures of \nNYISO, Applicable Reliability Standards, and Applicable Laws and Regulations. \n8.2 \nNotice. Each Party shall promptly notify the other upon becoming aware of an \nEmergency State that may reasonably be expected to affect the other Party’s \nfacilities, describing (to the extent known) the Emergency State, the extent of \ndamage, the expected effect, its anticipated duration, and corrective action taken or \nplanned, followed as soon as practicable by written notice. \n8.3 \nTransmission Owner Authority. Transmission Owner may take whatever actions \nit deems necessary during an Emergency State to preserve public health and safety, \npreserve reliability, limit or prevent damage, and expedite restoration, including \ncurtailing, reducing, or disconnecting the Load Facility, in coordination with \nNYISO as applicable, and shall use Reasonable Efforts to minimize the effect on \nCustomer and to restore service as soon as practicable. \n8.4 \nCustomer Authority. Customer shall take actions with respect to the Load Facility \nduring an Emergency State consistent with Good Utility Practice, using Reasonable \nEfforts to minimize the effect on the New York State Transmission System. Unless \nimmediate action is required in Customer’s reasonable judgment, Customer shall"},{"page":21,"startToken":7566,"endToken":8040,"text":"obtain Transmission Owner’s consent, not to be unreasonably withheld, before \nperforming manual switching in response to an Emergency State. \n8.5 \nLimited Liability. No Party shall be liable to the other for any action taken in good \nfaith and consistent with Good Utility Practice in responding to an Emergency \nState, except to the extent caused by its gross negligence or willful misconduct. \nARTICLE 9 \nMETERING AND TELEMETRY \n9.1 \nMetering Equipment. Customer shall pay for the purchase and installation of \nTransmission Owner-approved revenue-quality Metering Equipment at or near the \nPoint of Interconnection before any operation of the Load Facility, including a \nlockable cabinet for instrument transformers as specified in Exhibit B. \nTransmission Owner shall [provide the meters and] own, operate, test, and maintain \nthe Metering Equipment used for billing and settlement, and Customer shall bear \nall reasonable costs thereof. While the Cost Recovery Agreement is in effect, such \ncosts shall be recovered pursuant to the Cost Recovery Agreement; thereafter, such \ncosts shall be invoiced and paid in accordance with Article 6.3. The Metering \nEquipment shall record interval demand and energy (including MW, MVAR, and \nMWh) in sufficient detail to support billing and NYISO settlement.  \n9.2 \nStandards. Metering Equipment shall be installed, calibrated, and tested in \naccordance with applicable ANSI and NYPSC standards, the NYISO Revenue \nMetering Requirements Manual, and TO Standards. \n9.3 \nCheck Meters. Customer may, at its expense, install and operate check meters on \nits side of the Point of Interconnection, subject to inspection by Transmission \nOwner. Check meters shall not be used for billing except as provided in Article 9.4. \n9.4 \nTesting and Adjustment. Transmission Owner shall test the Metering Equipment \nupon installation and at least once every [four (4)] years thereafter, and more \nfrequently at Customer’s request and expense, upon reasonable notice and with \nCustomer’s right to be present. If Metering Equipment fails to register or is found \ninaccurate by more than [two percent (2%)], it shall be repaired or replaced at \nCustomer’s expense (unless due to Transmission Owner’s failure to maintain), and \nmeasurements shall be corrected for the period of inaccuracy using check meter \ndata, if available, or otherwise for one-half of the period since the last test, or as \nprovided in the Tariff. \n9.5 \nMetering Data. Metered data shall be telemetered at Customer’s expense to \nlocations designated by Transmission Owner and shall be the official measurement \nunder normal operating conditions. Transmission Owner shall make interval \nmetering data available to Customer upon request. \n9.6 \nTelemetry and Communications. Before the In-Service Date, Customer shall \ninstall, own, and maintain remote terminal units and dedicated data circuits, as \nspecified in Exhibit B, to provide Transmission Owner (and NYISO, as applicable) \nreal-time telemetry of, at a minimum, real power demand, reactive power or power \nfactor, voltage at the Point of Interconnection, and breaker and switch status, and"},{"page":22,"startToken":8040,"endToken":8453,"text":"shall coordinate SCADA requirements, points lists, and protocols with \nTransmission Owner and NYISO. Customer shall maintain voice communications \nwith Transmission Owner’s control center and shall promptly correct telemetry \nfailures. Each Party shall promptly advise the other of any metering, telemetry, or \ncommunications errors requiring correction. \n9.7 \nNo Annexation. Equipment placed on a Party’s premises shall remain the property \nof the Party providing it, regardless of the mode of annexation, unless otherwise \nagreed. \nARTICLE 10 TESTING AND INSPECTION \n10.1 \nPre-Energization Testing. Before energization, Transmission Owner shall test the \nTO Attachment Facilities and Network Upgrades, and Customer shall test the Load \nFacility and Customer Attachment Facilities (including System Protection \nFacilities), as required by the Operating Documents or as Transmission Owner \nreasonably requests. Each Party shall make modifications found necessary as a \nresult, and Customer shall bear the cost of such testing and modifications. Customer \nshall deliver test results within five (5) Business Days after testing. \n10.2 \nPost-Energization Testing. Each Party shall, at its own expense, perform routine \ninspection and testing of its facilities in accordance with Good Utility Practice and \nApplicable Reliability Standards. Each Party may require reasonable additional \ntesting of the other’s facilities at the requesting Party’s expense. \n10.3 \nRight to Observe and Inspect. Each Party shall notify the other (and NYISO, as \napplicable) in advance of post-energization tests of its TO Attachment Facilities \nand the Customer Attachment Facilities, and the other Party may observe such tests \nat its own expense. Transmission Owner may, upon reasonable notice (or without \nnotice in an Emergency State) and subject to Customer’s reasonable safety and \nsecurity requirements, inspect the Load Facility and Customer Attachment \nFacilities, review and require changes to protective settings, review maintenance \nrecords, and witness or require re-testing whenever it reasonably believes the \nfacilities do not comply with this Agreement, in which case Customer shall bear \nthe cost of such re-testing and any required corrective action. The exercise or non-\nexercise of such rights shall not constitute an endorsement or warranty or impose \nany liability on Transmission Owner. Information Transmission Owner obtains in \nsuch exercise shall be treated as Confidential Information. \nARTICLE 11 MAINTENANCE \n11.1 \nMaintenance Obligations. Transmission Owner shall maintain the TO Attachment \nFacilities and Network Upgrades, and Customer shall maintain the Load Facility, \nCustomer Attachment Facilities, and any System Protection Facilities on \nCustomer’s property, in each case in a safe and reliable condition in accordance \nwith Good Utility Practice, TO Standards, the Operating Documents, and \nApplicable Laws and Regulations."},{"page":23,"startToken":8453,"endToken":8856,"text":"11.2 \nCoordination. The Parties shall confer regularly to coordinate preventive and \ncorrective maintenance, keep NYISO informed as required, and schedule \nmaintenance in accordance with NYISO procedures. \n11.3 \nSecondary Systems. Each Party shall cooperate in the inspection, maintenance, \nand testing of control and power circuits operating below 600 volts that may \nreasonably be expected to affect the other Party, and shall give advance notice \nbefore working on such circuits, especially those involving breaker trip and close \ncontacts and instrument transformers. \nARTICLE 12 MODIFICATIONS \n12.1 \nNotice of Modification. Either Party may modify its facilities. A Party planning a \nmodification that may reasonably be expected to affect the other Party’s facilities \nshall provide drawings, plans, specifications, and timing information at least [one \nhundred eighty (180)] Calendar Days in advance (or such longer period as \nreasonably required for evaluation). Notice of any change to the load characteristics \nreported in the NYISO Load Interconnection Data Request (NYISO Technical \nBulletin 266 or its successor) shall be provided in substantially that form. \nModifications required in response to an Emergency State do not require the \nadvance notification specified in this Article 12.1 but shall be noticed as soon as \npracticable.  \n12.2 \nMaterial Modifications. Transmission Owner shall determine, in its reasonable \ndiscretion, whether a proposed modification is a Material Modification. Customer \nshall not implement a Material Modification or change the configuration of the \nCustomer Attachment Facilities or the Load Facility without Transmission Owner’s \nprior written approval. Transmission Owner has no obligation to approve a Material \nModification until (a) required studies are complete; (b) all required approvals are \nobtained; and (c) Customer has provided any additional security required under the \nSecurity Agreement. A Material Modification may require amendment of this \nAgreement. \n12.3 \nStudies and Costs. Transmission Owner or NYISO may perform studies \nreasonably necessary to evaluate a proposed modification. Customer shall pay the \ncost of such studies and all costs incurred by Transmission Owner as a result of any \nmodification requested or implemented by Customer, and shall be responsible for \nthe costs of modifications to the Customer Attachment Facilities required by \nApplicable Laws and Regulations, Applicable Reliability Standards, or Good \nUtility Practice. All modifications shall comply with this Agreement, NYISO \nrequirements, and TO Standards. \n(1) \nCustomer shall pay the costs of all required engineering or design studies \nprior to the provision of service (e.g., transient studies) that result in the \nneed for further scope of work."},{"page":24,"startToken":8856,"endToken":9256,"text":"ARTICLE 13 INFORMATION REQUIREMENTS \n13.1 \nPre-Energization Information. At least ninety (90) Calendar Days before initial \nenergization, Customer shall provide complete and accurate information regarding \nthe electrical characteristics and configuration of the Load Facility and Customer \nAttachment Facilities, including as-built or redlined single-line diagrams and \nprotective device settings, for review by Transmission Owner’s testing and \ncommissioning, engineering, construction management, and control center \npersonnel. \n13.2 \nLoad Information. Upon request, Customer shall promptly provide load data and \nforecast information (in MW and MWh) required for Transmission Owner to \nperform its load forecasting obligations under the NYISO tariffs and manuals. \n13.3 \nSupplementation and Updates. Before the In-Service Date, each Party shall \nsupplement its submissions with “as-built” and “as-tested” information or confirm \nthat no differences exist. After the In-Service Date, each Party shall provide the \nother with information on changes due to equipment replacement, repair, or \nadjustment that may affect the other’s ratings, protection, or operating requirements \nwithin thirty (30) Calendar Days. \n13.4 \nEnvironmental Releases. Customer shall notify Transmission Owner, first orally \nand then in writing, of any release of Hazardous Substances, asbestos or lead \nabatement, or remediation related to the Load Facility, TO Attachment Facilities, \nCustomer Attachment Facilities, or Network Upgrades that may reasonably be \nexpected to affect Transmission Owner, in good faith within twenty-four (24) hours \nafter becoming aware, and shall furnish copies of publicly available reports filed \nwith Governmental Authorities. \nARTICLE 14 REGULATORY REQUIREMENTS AND \nGOVERNING LAW \n14.1 \nRegulatory Approvals. Each Party’s obligations are subject to its receipt of any \nrequired approval of a Governmental Authority (“Required Approvals”). Each \nParty shall timely seek, using Reasonable Efforts and at its own expense, all \napprovals, permits, and authorizations required of it, including those of FERC, the \nNYPSC, and NYISO. [Nothing in this Agreement shall require Transmission \nOwner to take any action that could result in the loss of its status or exemption \nunder the Federal Power Act, the Public Utility Holding Company Act of 2005, or \nthe Public Utility Regulatory Policies Act of 1978.]  \n14.2 \nGoverning Law. The validity, interpretation, and performance of this Agreement \nshall be governed by and construed in accordance with the laws of the State of New \nYork, without regard to conflict-of-laws principles (other than Section 5-1401 of \nthe New York General Obligations Law), except to the extent preempted by federal \nlaw. This Agreement is subject to all Applicable Laws and Regulations, and each"},{"page":25,"startToken":9256,"endToken":9711,"text":"Party reserves the right to seek changes in, appeal, or contest any law, order, rule, \nor regulation of a Governmental Authority. \n14.3 \nForum; Waiver of Jury Trial. Subject to the jurisdiction of FERC or the NYPSC, \nany action arising out of or relating to this Agreement shall be brought exclusively \nin the Supreme Court of the State of New York, [County] County, or the United \nStates District Court for the applicable (i.e., Northern, Southern, Western, or \nEastern) District of New York, and the Parties irrevocably submit to the jurisdiction \nof such courts. EACH PARTY EXPRESSLY WAIVES ANY RIGHT TO TRIAL \nBY JURY IN ANY ACTION ARISING OUT OF OR IN CONNECTION WITH \nTHIS AGREEMENT. \nARTICLE 15 NOTICES \n15.1 \nGeneral. Unless otherwise provided, any notice required or permitted under this \nAgreement shall be in writing and shall be effective when delivered by hand, \nnationally recognized overnight courier, certified or registered mail (return receipt \nrequested), or electronic mail, to the addresses in Exhibit I. A Party may change its \nnotice information on five (5) Business Days’ written notice. \n15.2 \nBillings and Payments. Billings and payments shall be effectuated through the \nwire instructions or sent to the addresses included in Exhibit I or as otherwise \nmutually agreed to by the Parties. \n15.3 \nAlternative and Operational Communications. Notices not required to be in \nwriting may be given by telephone or email to the contacts in Exhibit I. Operational \ncommunications, \nincluding \noutage \ncoordination \nand \nEmergency \nState \ncommunications, shall be made to the 24/7 contacts in Exhibit E using three-part \ncommunication consistent with NERC Reliability Standards. Each Party shall \ndesignate in writing its points of contact for operations and maintenance. \nARTICLE 16 FORCE MAJEURE, BREACH, AND DEFAULT \n16.1 \nForce Majeure. “Force Majeure” means any event or circumstance beyond a \nParty’s reasonable control that prevents the Party from performing an obligation, is \nnot the result of the negligence or intentional wrongdoing of such Party, and could \nnot have been prevented or mitigated by the exercise of Good Utility Practice (in \nthe case of Transmission Owner) or due diligence (in the case of Customer), \nincluding acts of God, fire, flood, storm, lightning, explosion, breakage of or \naccident to machinery, epidemic or pandemic, cyber-attack (except to the extent \ncaused by or resulting from Customer’s failure to comply with its obligations under \nthis Agreement), sabotage, terrorism, war, civil disturbance, strikes and labor \ndisturbances, acts or orders of any Governmental Authority, and curtailment or \ninterruption directed by NYISO for reliability reasons. Force Majeure shall not \ninclude, with respect to Customer: (a) economic hardship, changes in market \nconditions, or the cost or unavailability of financing; (b) delays in Customer’s \nprocurement of equipment or failure of Customer’s suppliers or contractors, unless"},{"page":26,"startToken":9711,"endToken":10280,"text":"caused by an independent Force Majeure event; (c) labor disputes involving only \nCustomer’s or its contractors’ workforce; (d) Customer’s failure to obtain required \npermits or approvals, unless it has diligently and timely pursued them; or (e) \nchanges in the demand for, or the business case of, the Load Facility’s end use. \nInterruptions resulting from the Single Contingency Design shall not be treated as \nForce Majeure. Force Majeure shall not excuse the failure to make payments when \ndue or to timely post or maintain the Financial Security. \n16.2 \nEffect of Force Majeure. A Party shall be excused from performance (other than \nthe obligation to pay money when due) to the extent prevented by Force Majeure, \nprovided it gives prompt notice with full particulars (confirming any telephone \nnotice in writing), keeps the other Party informed, and exercises due diligence to \nremedy the effects with reasonable dispatch. A Party shall not be required to settle \na labor dispute on terms unsatisfactory to it. \n16.3 \nBreach and Cure. No Breach shall exist where the failure (other than to pay money \nor to provide or maintain security) results from Force Majeure or the other Party’s \nact or omission. Upon a Breach, the non-breaching Party shall give written notice \ndescribing the Breach in reasonable detail. The Breaching Party shall have thirty \n(30) Calendar Days from receipt to cure; provided that (a) a Breach consisting of a \nfailure to pay any amount when due or to provide, maintain, or replenish security \nshall be cured within five (5) Business Days after notice; (b) if a non-monetary \nBreach cannot reasonably be cured within thirty (30) Calendar Days, the Breaching \nParty shall commence the cure within such period, provide a written cure plan, and \ndiligently complete it within [sixty (60)] Calendar Days after receipt of notice; and \n(c) no cure period shall apply to a Breach that creates an Emergency State, operation \nwithout PTO, or an unauthorized Material Modification, or to an Event of \nInsolvency. Where a Breach is also a default under the Cost Recovery Agreement \nor the Security Agreement, the applicable cure periods shall run concurrently. \n16.4 \nInsolvency. An “Event of Insolvency” occurs if Customer (a) files a voluntary \npetition in bankruptcy or for reorganization or similar relief, (b) has an involuntary \npetition filed against it that is not dismissed within sixty (60) Calendar Days, (c) \nmakes a general assignment for the benefit of creditors, (d) has a receiver, trustee, \nor custodian appointed for all or substantially all of its assets, (e) is generally unable \nto pay its debts as they become due, or (f) undergoes dissolution. An Event of \nInsolvency shall constitute a Default without notice or cure, to the extent permitted \nby applicable bankruptcy law. \n16.5 \nDefault; Remedies. If a Breach is not cured as provided in Article 16.3, a Default \nshall exist, and the non-defaulting Party may terminate this Agreement by written \nnotice, recover all amounts due, and pursue all other remedies available at law or \nin equity, including specific performance and injunctive relief. \n16.6 \nCross-Default. Each of the following shall constitute a Breach by Customer under \nthis Agreement: (a) a default, event of default, or material breach by Customer \nunder the Cost Recovery Agreement, the Security Agreement, or any other \nagreement listed in Exhibit G, in each case after the expiration of any cure period \nprovided therein, which shall constitute a Default under this Agreement and shall"},{"page":27,"startToken":10280,"endToken":10735,"text":"not be subject to any further cure period under this Agreement; (b) Customer’s \nfailure to pay amounts owed to NYISO for the Load Facility, or the suspension or \ntermination of Customer’s or its load serving entity’s NYISO market participation \nfor the Load Facility for credit reasons; (c) Customer’s failure to pay undisputed \namounts owed to Transmission Owner under its retail electric tariff or any other \nagreement between Customer (or its Affiliate) and Transmission Owner relating to \nthe Load Facility; and (d) a default by Customer or its Affiliate under any other \ninterconnection or service agreement with Transmission Owner relating to a facility \non the same site or that shares the TO Attachment Facilities or Network Upgrades. \nThe Breaches described in clauses (b) through (d) shall be subject to the cure period \napplicable under Article 16.3(a). \n16.7 \nReporting of Non-Force Majeure Events. Each Party shall notify the other when \nit becomes aware of its inability to comply with this Agreement for a reason other \nthan Force Majeure, including the date, duration, reason, and corrective actions it \nis taking or will take; such notification shall not by itself give rise to a claim of \nanticipatory breach. \nARTICLE 17 INDEMNITY, LIMITATION OF LIABILITY, \nAND CONSEQUENTIAL DAMAGES \n17.1 \nSingle Contingency Design. Customer acknowledges that Transmission Owner \nmay design and operate the interconnection using a Single Contingency Design, \nand Customer has elected to accept the reliability level associated therewith. \nTransmission Owner shall have no liability for loss or damage, including loss of \ndata, computing operations, or business interruption, resulting from service \ninterruptions, reductions, or power quality events due to contingencies reasonably \ncontemplated by the Single Contingency Design, and Customer shall be solely \nresponsible for installing any backup generation, uninterruptible power supply, or \nredundancy it requires. \n17.2 \nCustomer Indemnity. To the fullest extent permitted by law, Customer shall \nindemnify, defend, and hold harmless Transmission Owner, its Affiliates, and their \nrespective trustees, directors, officers, employees, and agents (the “TO \nIndemnitees”) from and against all claims, demands, suits, losses, liabilities, \ndamages, fines, penalties (including penalties assessed under Applicable Reliability \nStandards to the extent attributable to the Load Facility or Customer’s acts or \nomissions), costs, and expenses, including reasonable attorneys’ fees and claims \nfor injury to or death of any person or damage to property (“Losses”), arising out \nof or resulting from (a) the design, construction, ownership, operation, or \nmaintenance of the Load Facility or Customer Attachment Facilities; (b) \nCustomer’s performance or non-performance under this Agreement; (c) \nCustomer’s violation of Environmental Law or release of Hazardous Substances by \nCustomer or arising from the Load Facility or the Customer Attachment Facilities; \n(d) pre-existing environmental contamination encountered or exacerbated by \nCustomer on property conveyed by Customer to Transmission Owner or pre-"},{"page":28,"startToken":10735,"endToken":11170,"text":"existing environmental contamination that Customer encounters or exacerbates on \nTransmission Owner’s property; (e) claims by Customer’s contractors, tenants, end \nusers, or customers relating to interruptions or quality of service; (f) any claim by \na third party that the Load Facility’s operation caused harm to other customers or \naffected systems; and (g) any cybersecurity incident, breach, or attack affecting, \noriginating from, or arising out of the Load Facility, the Customer Attachment \nFacilities, or Customer’s systems, or Customer’s failure to comply with its physical \nor cybersecurity obligations under this Agreement, except, in each case, to the \nextent caused by the gross negligence or willful misconduct of a TO Indemnitee. \n17.3 \nIndemnity Procedures. Transmission Owner shall promptly notify Customer of \nany claim; failure or delay shall not relieve Customer except to the extent materially \nprejudiced. Customer may assume the defense with counsel reasonably satisfactory \nto Transmission Owner, subject to Transmission Owner’s right to participate at its \nown expense and to retain separate counsel at Customer’s expense (limited to one \nadditional firm) where it has different or additional defenses or a conflict of interest \nexists, or the claim involves potential criminal liability. Customer shall not settle \nany claim without Transmission Owner’s consent, not to be unreasonably withheld, \nconditioned, or delayed. If Customer fails to assume the defense, Transmission \nOwner may contest, settle, or pay the claim at Customer’s expense. The amount \nowed shall be the actual Loss, net of insurance or other recovery. \n17.4 \nNo Consequential Damages; Limitation of Liability. EXCEPT FOR (A) \nINDEMNIFICATION OBLIGATIONS FOR THIRD-PARTY CLAIMS UNDER \nTHIS ARTICLE 17; (B) DAMAGES ARISING FROM A PARTY’S GROSS \nNEGLIGENCE OR WILLFUL MISCONDUCT; (C) DAMAGES RESULTING \nFROM A BREACH OF ARTICLE 19; AND (D) AMOUNTS PAYABLE BY \nCUSTOMER UNDER THIS AGREEMENT, THE COST RECOVERY \nAGREEMENT, THE SECURITY AGREEMENT, OR OTHER SEPARATE \nAGREEMENTS LISTED IN EXHIBIT G (INCLUDING TERMINATION \nCOSTS UNDER SECTION 2.6), NEITHER PARTY SHALL BE LIABLE TO \nTHE \nOTHER \nFOR \nANY \nSPECIAL, \nINDIRECT, \nINCIDENTAL, \nCONSEQUENTIAL, EXEMPLARY, PENAL, OR PUNITIVE DAMAGES, \nINCLUDING DELAYS, LOSS OF PROFIT OR REVENUE, LOSS OF USE OF \nEQUIPMENT, LOSS OF DATA, BUSINESS INTERRUPTION, COST OF \nCAPITAL, COST OF TEMPORARY EQUIPMENT OR SERVICES, OR \nCLAIMS OF SUPPLIERS AND CUSTOMERS, WHETHER IN CONTRACT, \nTORT (INCLUDING NEGLIGENCE), STRICT LIABILITY, OR OTHERWISE, \nAND WHETHER OR NOT SUCH DAMAGES WERE REASONABLY \nFORESEEABLE. IN ADDITION, EXCEPT FOR ITS GROSS NEGLIGENCE \nOR WILLFUL MISCONDUCT, TRANSMISSION OWNER’S AGGREGATE \nLIABILITY TO CUSTOMER ARISING OUT OF OR RELATING TO THIS \nAGREEMENT SHALL NOT EXCEED THE LESSER OF [$1,000,000] OR TWO \nPERCENT (2%) OF THE AMOUNTS PAID BY CUSTOMER TO \nTRANSMISSION OWNER UNDER THIS AGREEMENT [AND THE COST \nRECOVERY AGREEMENT]."},{"page":29,"startToken":11170,"endToken":11578,"text":"ARTICLE 18 INSURANCE \n18.1 \nRequired Coverage. As applicable, Customer shall, as determined by \nTransmission Owner in its sole discretion, at Customer’s own expense, procure and \nmaintain throughout the Term, with insurers licensed in, or eligible surplus lines \ncarriers in, the State of New York rated A- (VIII) or better by A.M. Best, the \nfollowing minimum coverages:  \n(1) \nWorkers’ Compensation (statutory) and Employers’ Liability with limits of \nnot less than $1,000,000 per accident, including coverage under the U.S. \nLongshore and Harbor Workers’ Compensation Act and Federal \nEmployers’ Liability Act where applicable; \n(2) \nCommercial General Liability on ISO Form CG 00 01 or equivalent, \nincluding premises and operations, products and completed operations, \ncontractual liability, independent contractors, explosion, collapse, and \nunderground hazards, with limits of not less than $2,000,000 per occurrence \nand $2,000,000 in the aggregate; \n(3) \nAutomobile Liability covering owned, non-owned, and hired vehicles with \na combined single limit of not less than $1,000,000 per accident; \n(4) \nUmbrella/Excess Liability in excess of the foregoing with limits of not less \nthan $20,000,000 per occurrence and in the aggregate; \n(5) \nContractor’s Pollution Liability with limits of not less than $[7,500,000] per \noccurrence and in the aggregate; \n(6) \nCyber/Network Security and Data Privacy Liability with limits of not less \nthan $[10,000,000] per occurrence and in the aggregate; \n(7) \nProfessional Liability of not less than $[3,000,000] (or $[5,000,000] for \nstructural design services) where professional services are performed, and \nBuilder’s Risk coverage during construction; \n(8) \nProperty insurance on an “all risk” basis covering the Load Facility and \nCustomer Attachment Facilities; and \n(9) \nPremises Pollution Liability with limits of not less than $[____] for property \nconveyed by Customer to Transmission Owner.  \n18.2 \nAdditional Insureds; Primary Coverage; Subrogation. The liability policies \nrequired of Customer shall name Transmission Owner, its Affiliates, and their \nrespective directors, officers, and employees as additional insureds, shall be \nprimary and non-contributory, and shall contain waivers of subrogation. All \npolicies required of Customer shall be issued in the name of, or expressly cover, \nthe Customer entity executing this Agreement, and not solely a parent or Affiliate. \nCustomer shall be responsible for its deductibles and retentions. Claims-made \npolicies shall be maintained for at least three (3) years after termination. \n18.3 \nCertificates and Notice. Upon execution of this Agreement and upon each \nrenewal, Customer shall provide Transmission Owner certificates of insurance and"},{"page":30,"startToken":11578,"endToken":12021,"text":"shall give at least thirty (30) Calendar Days’ prior written notice of cancellation, \nnon-renewal, or material change. \n18.4 \nSelf-Insurance. Customer, if its senior debt is rated investment grade by Standard \n& Poor’s, Moody’s, or Fitch, may self-insure to meet these requirements upon \nnotice and evidence that its program meets the minimum requirements. \n18.5 \nContractors; No Limitation. Customer shall cause its contractors and \nsubcontractors to maintain, as applicable, the insurance described in Article 18.1 \nwith additional insured status and waivers of subrogation in favor of Transmission \nOwner. The insurance requirements shall not limit Customer’s liability. All \namounts are in U.S. Dollars. Transmission Owner may reasonably adjust required \nlimits upon annual review. Each Party shall report to the other in writing all \naccidents or occurrences resulting in injury or property damage arising out of this \nAgreement. \nARTICLE 19 CONFIDENTIALITY \n19.1 \nConfidential Information. “Confidential Information” means non-public \ninformation furnished by a Party in connection with this Agreement that is \nidentified in writing as confidential at or promptly after disclosure, or that \nreasonably should be understood to be confidential, including system plans, studies, \nspecifications, operating procedures, and customer-specific usage data, and \ninformation designated confidential under the NYISO Code of Conduct. \n19.2 \nExclusions. Confidential Information does not include information that the \nreceiving Party can demonstrate (a) is or becomes publicly available other than \nthrough its breach; (b) was lawfully in its possession on a non-confidential basis; \n(c) was supplied by a third party without restriction; (d) was independently \ndeveloped; or (e) is required to be disclosed by law, subpoena, or Governmental \nAuthority [, including pursuant to Article 6 of the New York Public Officers Law \n(FOIL)], or is necessary in a proceeding to enforce this Agreement. \n19.3 \nObligation and Standard of Care. During the Term and for three (3) years \nthereafter (or, with respect to Critical Energy/Electric Infrastructure Information \nand information concerning the physical or cyber security of the TO System, for so \nlong as such information remains non-public), each Party shall hold the other’s \nConfidential Information in confidence, use it solely to perform this Agreement and \nits regulatory obligations, and protect it with at least the same care it uses for its \nown confidential information, but no less than reasonable care. \n19.4 \nPermitted Disclosures. A Party may disclose Confidential Information to its \nAffiliates, employees, contractors, consultants, professional advisors, prospective \nfinanciers, and permitted assignees on a need-to-know basis, provided they are \nbound by confidentiality obligations, and the disclosing Party shall remain \nresponsible for their compliance. \n19.5 \nCompelled Disclosure. If disclosure is requested or required by a court or \nGovernmental Authority, the receiving Party shall give the other prompt notice so"},{"page":31,"startToken":12021,"endToken":12501,"text":"it may seek a protective order, shall cooperate in seeking confidential treatment, \nand may disclose only what its counsel advises is legally required. Disclosures to \nFERC, the NYPSC, or a state regulatory body in a confidential investigation shall \nbe handled consistent with applicable rules. \n19.6 \nRights; No Warranties; Return. Each Party retains all rights in its Confidential \nInformation. No Party warrants the accuracy or completeness of Confidential \nInformation. Upon termination or written request, the receiving Party shall return \nor destroy Confidential Information, except one archival copy. \n19.7 \nEquitable Relief. Monetary damages may be inadequate for a breach of this Article \n19, and the non-breaching Party shall be entitled to seek injunctive relief and \nspecific performance in addition to other remedies. \n19.8 \nNon-Disclosure Agreement; CEII. Critical Energy/Electric Infrastructure \nInformation (“CEII”) shall be protected and disclosed only as permitted by 18 \nC.F.R. § 388.113, the Tariff, applicable NYISO procedures, and any FERC order. \nTransmission Owner may require Customer and its contractors, subcontractors, \nvendors, or agents to execute a separate non-disclosure agreement as a condition \nof receiving Confidential Information or CEII, and nothing in this Agreement \nshall limit, modify, or supersede any such non-disclosure agreement. \nARTICLE 20 DISPUTE RESOLUTION \n20.1 \nNotice and Informal Resolution. A Party asserting a dispute arising out of or \nrelating to this Agreement (a “Dispute”) shall give written notice (a “Notice of \nDispute”). The Dispute shall be referred to designated senior representatives of the \nParties for good-faith negotiation. \n20.2 \nArbitration by Agreement. If the Dispute is not resolved within [thirty (30) / sixty \n(60)] Calendar Days after receipt of the Notice of Dispute, the Parties may, by \nmutual agreement, submit it to arbitration under Article 20.3. Absent such \nagreement, either Party may pursue any remedy available at law or in equity, \nincluding proceedings before FERC, the NYPSC, or a court identified in Article \n14.3. Notwithstanding this Article 20, (a) either Party may at any time seek \ntemporary, preliminary, or injunctive relief, or specific performance, from a court \nidentified in Article 14.3 or from FERC or the NYPSC to prevent irreparable harm, \nprotect system reliability or safety, or preserve the status quo, without first \ncomplying with Article 20.1; and (b) the informal resolution and arbitration \nprocedures shall not delay or limit Transmission Owner’s exercise of its rights \nunder Articles 2.4, 6.2, 7.4, and 8, or Customer’s payment obligations under \nArticles 6.3 and 6.4. \n20.3 \nArbitration Procedures. Any arbitration shall be conducted before a single neutral \narbitrator, or, if the Parties cannot agree on one within ten (10) Calendar Days, a \nthree-member panel (one appointed by each Party and a third selected by the two \nparty-appointed arbitrators), each knowledgeable in electric utility matters and \nwithout substantial business relationships with either Party, under the Commercial \nArbitration Rules of the American Arbitration Association, except as modified"},{"page":32,"startToken":12501,"endToken":12926,"text":"herein. The arbitrator(s) shall render a written, reasoned decision within ninety (90) \nCalendar Days of appointment, shall have no authority to modify this Agreement, \nand the decision shall be final, with judgment enterable in any court of competent \njurisdiction, subject to appeal only on grounds permitted by the Federal Arbitration \nAct. Each Party shall bear its own costs, the cost of its appointed arbitrator, and \none-half of the cost of the single or third arbitrator. \n20.4 \nContinued Performance; Termination. Pending resolution, each Party shall \ncontinue to perform its obligations, subject to Article 6.4; provided that the \npendency of a Dispute shall not suspend or toll any cure period under Article 16 or \nlimit Transmission Owner’s rights described in Article 20.2(b). Whether a \ntermination is proper shall not be subject to arbitration unless the Parties agree \notherwise. \nARTICLE 21 REPRESENTATIONS AND WARRANTIES \nEach Party represents and warrants to, and covenants and agrees with, the other, as of the \nExecution Date and throughout the Term, that: \n21.1 \nit is duly organized, validly existing, and in good standing under the laws of its \njurisdiction of organization and is qualified to do business in each jurisdiction \nwhere required to perform this Agreement; \n21.2 \nit has all requisite power and authority to execute, deliver, and perform this \nAgreement, and this Agreement is its legal, valid, and binding obligation, \nenforceable in accordance with its terms, subject to bankruptcy, insolvency, and \nsimilar laws and general equitable principles; \n21.3 \nthe execution, delivery, and performance of this Agreement do not violate its \norganizational documents or any law, judgment, order, or material agreement \nbinding on it; and \n21.4 \nit has sought or obtained, or will seek or obtain, all Required Approvals necessary \nfor its performance of this Agreement. \n21.5 \nAdditional Customer Representations. Customer further represents and \nwarrants to, and covenants and agrees with, Transmission Owner, as of the \nExecution Date and throughout the Term, that (a) it has executed and delivered \nthe Security Agreement and has provided the security required thereunder in the \namounts and forms specified therein, and such security remains in full force and \neffect; and (b) the representations in Articles 21.1 through 21.4 are true and \ncorrect with respect to each Related Agreement to which Customer is a party. \nARTICLE 22 ASSIGNMENT \n22.1 \nAssignment. This Agreement may be assigned by a Party only with the other \nParty’s written consent, not to be unreasonably withheld, conditioned, or delayed; \nprovided that (a) Transmission Owner may assign without consent to an Affiliate"},{"page":33,"startToken":12926,"endToken":13389,"text":"or successor with the legal authority and operational ability to perform; (b) \nTransmission Owner may assign without consent in connection with a sale, merger, \nrestructuring, or transfer of all or substantially all of its assets, including the TO \nAttachment Facilities and the Customer Attachment Facilities, if the assignee \nassumes in writing all obligations hereunder; and (c) Customer may assign without \nconsent for collateral security purposes to aid in financing the Load Facility, upon \nprompt notice to Transmission Owner. Any assignment by Customer (other than a \ncollateral assignment) and any change of control of Customer shall require \nTransmission Owner’s prior written consent, not to be unreasonably withheld, \nconditioned, or delayed, and shall be conditioned on (i) the assignee assuming in \nwriting all obligations under this Agreement, the Cost Recovery Agreement, the \nSecurity Agreement, and the other agreements listed in Exhibit G; (ii) the assignee \nposting replacement security under the Security Agreement before the assignment \nbecomes effective and having a credit rating equal to or greater than that of \nCustomer as of the date of assignment or providing such additional security under \nthe Security Agreement as Transmission Owner reasonably requires; and (iii) \nCustomer reimbursing Transmission Owner’s reasonable costs of administering the \nassignment or performing due diligence with respect to a change of control, \nincluding reissuing invoices and amending related contracts. Any financing \nobtained by Customer shall require the secured party to notify Transmission Owner \nbefore exercising assignment rights and to demonstrate compliance with Article 6.2 \nand Article 18. Any assignment in violation of this Article is void. No assignment \nby Customer shall release Customer or any existing security until the assignee’s \nreplacement security has been posted and accepted. No assignment shall relieve a \nParty of, or enlarge, its obligations. \nARTICLE 23 MISCELLANEOUS \n23.1 \nBinding Effect. This Agreement shall be binding upon and inure to the benefit of \nthe Parties and their successors and permitted assigns. \n23.2 \nRules of Interpretation. Unless a contrary intention clearly appears: the singular \nincludes the plural; references to any agreement, tariff, or law mean it as amended \nfrom time to time; references to Articles (including numbered subdivisions thereof) \nand Exhibits are to this Agreement; “including” means including without \nlimitation; “hereunder,” “herein,” and similar words refer to this Agreement as a \nwhole; and “from” means “from and including,” “to” means “to but excluding,” \nand “through” means “through and including.” \n23.3 \nCompliance. Each Party shall perform in accordance with Applicable Laws and \nRegulations, Applicable Reliability Standards, and Good Utility Practice, and shall \nnot be in Breach for compliance therewith; a Party becoming aware of such a \nsituation shall promptly notify the other so the Parties may discuss an appropriate \namendment. \n23.4 \nComparability. The Parties shall comply with all applicable comparability and \ncode of conduct laws, rules, and regulations."},{"page":34,"startToken":13389,"endToken":13836,"text":"23.5 \nSeveral Obligations. The obligations of the Parties are several, and not joint or \njoint and several. \n23.6 \nEntire Agreement. This Agreement and the Related Agreements are intended to \noperate together and shall be interpreted consistently with one another. This \nAgreement, including its Exhibits and the Related Agreements, constitutes the \nentire agreement of the Parties with respect to its subject matter and supersedes all \nprior understandings, oral or written. \n23.7 \nNo Third-Party Beneficiaries. Except for the TO Indemnitees under Article 17.2, \nthis Agreement is solely for the benefit of the Parties and their successors and \npermitted assigns. \n23.8 \nWaiver. No waiver shall be effective unless in writing and signed by the waiving \nParty, and no waiver of any Breach shall be a waiver of any other or subsequent \nBreach. Failure to insist on strict performance shall not constitute a waiver. \n23.9 \nAmendment. This Agreement, including its Exhibits, may be amended by a written \ninstrument executed by both Parties, effective upon satisfaction of any \nrequirements of Applicable Laws and Regulations. \n23.10 Reservation of Rights. Transmission Owner reserves the right to make unilateral \nfilings with any appropriate regulatory agency or Governmental Authority to \nmodify this Agreement as permitted by law, and Customer reserves its right to \nprotest any such filing.   \n23.11 Severability. If any provision is finally determined to be invalid or unenforceable \nby a court or Governmental Authority, the remaining provisions shall continue in \nfull force and effect. \n23.12 Headings. Headings are for convenience only and do not affect interpretation. \n23.13 Counterparts; Electronic Signatures. This Agreement may be executed in \ncounterparts, each of which shall be an original and all of which together constitute \none instrument. Electronic signatures shall be deemed originals. \n23.14 No Partnership. Nothing in this Agreement creates a partnership, joint venture, \nagency, or fiduciary relationship, and neither Party may bind the other. \n23.15 Contractors and Subcontractors. Either Party may use contractors and \nsubcontractors, provided that each Party requires its contractors and \nsubcontractors to comply with applicable terms of this Agreement and remains \nprimarily liable for their performance. Notwithstanding the foregoing, all \nmaterials, equipment, vendors, contractors, and subcontractors used by or for \nCustomer for work on existing or future Transmission Owner facilities shall be \napproved in advance in writing by Transmission Owner. Transmission Owner \nshall not be liable for the acts or omissions of Customer or its contractors or \nsubcontractors with respect to Customer’s obligations under Article 5. \nSubcontractor obligations shall not be limited by any limitation of the \nsubcontractor’s insurance. \n23.16 Physical and Cyber Security Arrangements. Customer shall comply with the \nphysical, operational, and cyber-security requirements set forth in Exhibit B, TO"},{"page":35,"startToken":13836,"endToken":13907,"text":"Standards, and applicable NERC Critical Infrastructure Protection standards, and \nshall implement and maintain cybersecurity controls consistent with recognized \nindustry best practices appropriate to the systems used in the performance of this \nAgreement. \nIN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their duly \nauthorized representatives as of the Execution Date. \n[LEGAL NAME OF TRANSMISSION \nOWNER] \nBy: _______________________________ \nName:  \nTitle:  \nDate: _____________________________ \n[LEGAL NAME OF CUSTOMER] \nBy: _______________________________ \nName:  \nTitle:  \nDate: _____________________________"},{"page":36,"startToken":13907,"endToken":13938,"text":"EXHIBIT A – LARGE LOAD PROJECT AND CUSTOMER \nATTACHMENT FACILITIES \n1. Description of Large Load Project \n[Insert description of Large Load Project] \n2. Customer Attachment Facilities \n[Insert description of Customer Attachment Facilities]"},{"page":37,"startToken":13938,"endToken":14107,"text":"EXHIBIT B – POINT(S) OF INTERCONNECTION AND \nPOINT(S) OF CHANGE OF OWNERSHIP, TO ATTACHMENT \nFACILITIES, AND NETWORK UPGRADE FACILITIES \n1. Point(s) of Interconnection (“POI”) \n[Insert description of Point(s) of Interconnection] \n2. Point(s) of Change of Ownership (“PCO”) \n[Insert description of Point(s) of Change of Ownership] \n3. TO Attachment Facilities \n[Insert description of TO Attachment Facilities] \n4. Network Upgrades \na. Local Network Upgrades \n[Insert description of Local Network Upgrades] \nb. Non-local Network Upgrades \n[Insert description of Non-local Network Upgrades] \n5. Affected Systems \n[Insert description of any Network Upgrades for Affected Systems and reference related \nagreement (e.g., Engineering, Procurement, and Construction Agreement)] \n6. External Affected Systems \n[Insert description of upgrades required on External Affected Systems] \n7. Phasor Measurement Unit Responsibilities \n[Describe PMU responsibilities, if applicable, or specify “none.”] \n8. Metering, Telemetry, and Security Requirements \n[Insert Metering Equipment configuration, CT/PT ratios, approved meter model [NYTO-\nSPECIFIC PROVISION], interval data requirements, telemetry points, RTU and communication \nprotocols, data retention requirements, and physical, operational, and cyber-security \nrequirements.]"},{"page":38,"startToken":14107,"endToken":14132,"text":"EXHIBIT C – SIMPLIFIED ONE-LINE DIAGRAM \n[Parties to insert simplified one-line diagram that clearly shows Customer Attachment Facilities, \nTO Attachment Facilities, Network Upgrades, POI, and PCO]"},{"page":39,"startToken":14132,"endToken":14188,"text":"EXHIBIT D – MILESTONES \n[If applicable: Where the interconnection of the Load Facility requires facilities or upgrades to be \nconstructed by an Affected Transmission Owner, the provision of service to the Load Facility is \nalso dependent upon completion of the milestones set forth in Customer’s agreement(s) with \nsuch Affected Transmission Owner(s).] \n[Insert table of Milestones]"},{"page":40,"startToken":14188,"endToken":14230,"text":"EXHIBIT E – OPERATING REQUIREMENTS \n[Transmission Owner to insert a high-level description of the operating requirements applicable \nto the Load Facility, which may incorporate by reference Transmission Owner’s interconnection \nand operating requirements, as amended from time to time, including, as applicable, the \nfollowing:]"},{"page":41,"startToken":14230,"endToken":14247,"text":"EXHIBIT F – CONDITIONS TO INITIAL ENERGIZATION AND \nPARALLEL OPERATION \n[Transmission Owner will provide the pre-conditions to service.]"},{"page":42,"startToken":14247,"endToken":14271,"text":"EXHIBIT G – COST RECOVERY, SECURITY, AND RELATED \nAGREEMENTS \n[List and/or copies of the Cost Recovery Agreement, the Security Agreement, and any related \nagreements.]"},{"page":43,"startToken":14271,"endToken":14329,"text":"EXHIBIT H – FORM OF COMMERCIAL OPERATION DATE \nNOTICE \n[Date] \n[Transmission Owner Name and Address], with a copy to: \nNew York Independent System Operator, Inc. \nAttn: Vice President, Operations \n10 Krey Boulevard \nRensselaer, NY 12144 \nRe: [Load Facility] \nThis letter confirms that [Customer] commenced Commercial Operation of the Load Facility \neffective as of [Date]. \nThank you, \n[Signature] [Customer Representative]"},{"page":44,"startToken":14329,"endToken":14362,"text":"EXHIBIT I – ADDRESSES FOR NOTICES AND BILLINGS \nNotices – Transmission Owner: [●] Customer: [●] \nBillings and Payments – Transmission Owner: [●]   Customer: [●] \nAlternative Forms of Notice (telephone/email) – Transmission Owner: [●] Customer: [●] \nNYISO: interconnectionsupport@nyiso.com [confirm current address]"}],"sections":[{"p":1,"at":0,"title":"Attachment H","method":"printed heading","endPage":3,"endAt":0,"startToken":0,"endToken":48},{"p":3,"at":0,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":44,"endAt":314,"startToken":48,"endToken":14362}]}