{"document":{"slug":"rec-20261116-5335","title":"NYTOs 205: Proposed Revisions re: Integration of Large Loads","issued":"2026-11-16","accession":"20261116-5335","docket":"ER27-529-000","group":"NYISO and New York transmission owners’ large-load tariff revisions","filer":"New York Independent System Operator, Inc.Central Hudson Gas & Electric CorporationNew York State Electric & Gas Corporation ,Rochester Gas and Electric Corporation ,Niagara Mohawk Power Corporation ,Consolidated Edison Company of New York, Inc. ,Orange and Rockland Utilities, Inc. ,","kind":"tariff filing","file":"sources/filings/text/20261116-5335_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5335","tier":"record","sha256":"3bc694244184205757ded4e406dafe09a6ee8f60239a1396279aece4c5906cc2","pages":37,"tokens":17268,"emptyPages":[],"textThemes":["study","cost","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":376,"text":"Troutman Pepper Locke LLP \n401 9th Street, N.W., Suite 1000 \nWashington, D.C. 20004 \ntroutman.com \nNovember 16, 2026 \n \nVIA ETARIFF \nThe Honorable Debbie-Anne A. Reese \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC 20426 \n \nRE:  New York Transmission Owners \nSection 205 Filing in Response to the Large Load Show Cause Order1   \n \nDocket No. ER27-___-000 \nDear Secretary Reese: \nPursuant to section 205 of the Federal Power Act (“FPA”)2 and Rule 205 of the Federal \nEnergy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure,3 \nCentral Hudson Gas & Electric Corporation (“Central Hudson”), Consolidated Edison Company \nof New York, Inc. (“Con Edison”), New York State Electric & Gas Corporation (“NYSEG”), \nNiagara Mohawk Power Corporation d/b/a National Grid (“National Grid”), Orange and Rockland \nUtilities, Inc. (“O&R”), and Rochester Gas and Electric Corporation (“RG&E”) (collectively \nreferred to herein as the “New York Transmission Owners” or “NYTOs”) submit for filing \nproposed revisions to the New York Independent System Operator, Inc. (“NYISO”) Open Access \nTransmission Tariff (“OATT” or “Tariff”)4 and certain pro forma agreements to address concerns \nthe Commission raised in its June 18, 2026 Large Load Show Cause Order in Docket No. EL26-\n69-000 that fall within the NYTOs’ responsibilities.5  In particular, the NYTOs submit with this \nfiling letter the following: \n1. Attachments A (clean) and B (marked): Tariff amendments to new Attachment LL of the \nOATT.  Attachment LL is being contemporaneously filed by the NYISO, and the NYTOs \n \n1  \nN.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216 (2026) (“Large Load Show Cause Order” or “Show \nCause Order”).   \n2  \n16 U.S.C. § 824d. \n3  \n18 C.F.R. § 385.205 (2025). \n4  \nThe NYISO is submitting this filing in FERC’s eTariff system on the NYTOs’ behalf solely in the NYISO’s \nrole as the Tariff Administrator.  The burden of demonstrating that the proposed Tariff amendments are just and \nreasonable rests on the NYTOs, the sponsoring parties.  If the NYISO has any comments on this filing, the NYISO \nwill submit a separate pleading in this proceeding.  Unless otherwise defined herein, capitalized terms used in this \ntransmittal letter shall have the meanings ascribed to them in the NYISO OATT.  \n5  \nSee Show Cause Order, 195 FERC ¶ 61,216."},{"page":2,"startToken":376,"endToken":836,"text":"November 16, 2026 \nPage 2 \n \n \nare sponsoring the following revisions to Attachment LL:  Section 44.1; Sections 44.2.2, \n44.6.8, 44.7.3.1, 44.8.2.4.5, 44.8.3.1.1, 44.8.3.3, 44.10.4.4, 44.12.1.2, 44.12.1.8, 44.14.1, \nand 44.14.3.2; new Section 44.14.3.5; and new Sections 44.16.8 through 44.16.11 \n(Appendices 8 through 11 to Attachment LL); \n2. Attachments C (clean) and D (marked): Tariff amendments revising Section 5 of the \nOATT, the definitions in Sections 1.18 and 1.20, and Attachment B of Section 8 of the \nOATT;6 \n3. Attachment E: Pro Forma Large Load Cost Recovery Agreement (“CRA”); \n4. Attachment F: Pro Forma Large Load Security Agreement; \n5. Attachment G: Pro Forma Facilities Study Agreement; \n6. Attachment H: Pro Forma Large Load Interconnection Agreement; and  \n7. Attachment I: Panel Testimony and exhibit of Brian McNierney, Carol Teixeira, Yan \nFlishenbaum, and Stacy Powers.  \nI. \nEXECUTIVE SUMMARY \nThe NYTOs submit this filing under section 205 of the FPA and their reserved filing rights \nunder section 3.10(a) of the NYISO-TO Agreement7 to address the concerns the Commission \nidentified in the Large Load Show Cause Order that fall within the NYTOs’ responsibilities.  This \nfiling complements, and is submitted in parallel with, the NYISO’s section 205 filing establishing \nnew Large Load Integration Procedures in Attachment LL of the OATT.  The substantial majority \nof the proposed tariff revisions submitted herewith are amendments to the currently effective \nNYISO OATT.  In addition, certain amendments submitted in exercise of the NYTOs’ unilateral \nfiling rights propose to amend revisions to the NYISO OATT sponsored by the NYISO in its \ncontemporaneous section 205 filing.8  While the NYISO’s filing establishes the study process, \nreadiness requirements, and new Firm and Non-Firm Withdrawal Services for Large Loads, the \nNYTOs’ filing addresses the complementary elements necessary to recover the costs of facilities \nbuilt to serve Large Loads, to protect other customers from cost shifts, and to integrate Large Loads \nreliably onto the NYTOs’ systems. \n \n6  \nThe NYTOs’ proposed revisions to Section 1.20 and Attachment B of Section 8 of the OATT are added to \npending tariff changes as proposed by the NYISO’s companion section 205 filing.   \n7  \nNYISO, Foundation Agreements, Agreement Between New York Independent System Operator and \nTransmission Owners (0.0.0) (“NYISO-TO Agreement”).  \n8  \nThese sections include the following: (1) Attachment LL; (2) Attachment B of Section 8; and (3) Section \n1.20 of the NYISO OATT.  Accordingly, when proposing changes to the NYISO companion filing, the \nNYTOs accepted the NYISO’s proposed changes and then marked the NYTOs’ proposed changes as though \nthe NYISO’s proposed changes were accepted."},{"page":3,"startToken":836,"endToken":1374,"text":"November 16, 2026 \nPage 3 \n \n \nSpecifically, the NYTOs propose four pro forma agreements.  First, a pro forma CRA \nallows each Transmission Owner to recover 100% of the costs of Network Upgrades and \nAttachment Facilities allocated to a Large Load Customer through a formula rate applicable \nexclusively to Large Load Customers (“Large Load Formula Rate”) that compresses cost recovery \ninto a 15-year term without accelerated depreciation.  Second, a pro forma Large Load Security \nAgreement requires the Large Load Customer to post security for those allocated costs, which the \nTransmission Owner may draw upon in the event of abandonment of a Large Load project, default, \nor other specified events.  Third, a pro forma Facilities Study Agreement provides a uniform \nframework, fixed study deposits, and a defined schedule for the Facilities Studies the Transmission \nOwners perform under Attachment LL.  Fourth, a pro forma Large Load Interconnection \nAgreement establishes the terms and conditions for interconnecting a Large Load, ties service \nlevels and operating requirements to studied load, and incorporates the CRA and Security \nAgreement. \nThe NYTOs also propose targeted revisions to Attachment LL that fall within NYTO \nresponsibilities and supplement Attachment LL as proposed by the NYISO.  These revisions:  (i) \nadd definitions, including Franchise Utility, Large Load Customer, and Retail Tariff; (ii) integrate \nthe Facilities Study Agreement into the NYISO’s study timeline through execution, deposit, and \nwithdrawal deadlines; (iii) include a covenant that each NYTO will not recover Large Load \nupgrade costs from other FERC-jurisdictional customers without explaining the associated rate \ntreatment and revenue credits; (iv) limit Non-Firm Withdrawal Service to thermal and resource \nadequacy constraints; (v) establish new operating requirements that preserve each Transmission \nOwner’s authority to maintain bulk and local system reliability, including through requests to the \nNYISO to reduce Non-Firm withdrawals; and (vi) establish disconnection requirements or \ncapabilities. \nFinally, the NYTOs propose revisions to Section 5 of the OATT, and conforming \ndefinitions in Sections 1.18 and 1.20, to extend the existing retail access framework to Large Loads \nand Eligible Customers9 serving Large Loads.  The NYTOs do not propose new delivery rates.  \nInstead, consistent with the cooperative federalism framework the Commission has accepted since \nthe NYISO’s existence, and recognizing that the NYTOs’ transmission and distribution rates are \nbundled, Section 5 will continue to reference the voltage-differentiated delivery rates and service \nclassifications approved by the New York Public Service Commission (“NYPSC”) or the Long \nIsland Power Authority (“LIPA”) Board of Trustees, including optional classifications that allow \nLarge Loads that are dispatched down or otherwise reduce load to reduce their delivery charges.  \nBecause the first Large Loads under the NYISO’s new procedures are not expected to complete \nFacilities Studies until Q3 2028, the NYTOs request that the Commission allow the NYPSC to \naddress any changes to delivery rates serving Large Loads in the NYPSC’s pending proceeding in \n \n9  \nNYISO OATT, Section 1.5 defines “Eligible Customer” as an entity that is engaged, or proposes to engage, \nin the wholesale or retail electric power business, including any electric utility, power marketer, Federal power \nmarketing agency, or any person generating Energy for sale for resale, is an Eligible Customer under the Tariff.  \nElectric energy sold or produced by such entity may be electric energy produced in the United States, Canada or \nMexico."},{"page":4,"startToken":1374,"endToken":1838,"text":"November 16, 2026 \nPage 4 \n \n \nthe first instance, and the NYTOs commit to make any necessary filing with the Commission \nbefore those rates take effect.10 \nTogether with the NYISO’s filing, these proposals provide a robust framework for the \nstudy, interconnection, cost recovery, and operation of Large Loads in New York that is just and \nreasonable, not unduly discriminatory or preferential, and protective of other transmission \ncustomers. \nThis filing is without prejudice to and does not take any position concerning the scope of \nthe NYPSC and FERC jurisdiction over the subject matter contained in this filing.  Rather, since \nthe start of the NYISO’s operations in 1999, the NYTOs have relied on cooperative federalism.  \nThe NYPSC has been the sole entity to conduct proceedings to establish retail delivery rates for \ntransmission and distribution services to retail customers unbundled from the supply function.  The \nNYTOs included references in Section 5 of the NYISO OATT to the delivery rates, terms and \nconditions contained in their rate schedules authorized by and on file with the NYPSC, as they \nmay be modified or superseded from time to time.   \nAs explained in more detail below, the NYTOs propose to continue a system that has \nworked since the NYISO’s existence (27 years) to produce retail delivery rates without a major \ndispute that required FERC intervention.  Accordingly, while the NYTOs believe that this \ncooperative federal-state framework can and should continue to provide solutions to Large Load \nprocedures and rates addressed in this proceeding, they reserve all jurisdictional positions in the \nhope that they can continue to satisfy both regulators without creating jurisdictional disputes.11  \nThe NYTOs respectfully request that the Commission accept the instant filing, effective on the \nvarious effective dates described below.  \nII. \nBACKGROUND \nA. \nThe Large Load Show Cause Order \nOn June 18, 2026, the Commission issued the Show Cause Order, instituting a proceeding \nunder FPA section 206 based on the Commission’s preliminary finding that the NYISO’s OATT12 \nappears to be unjust, unreasonable, or unduly discriminatory or preferential.13  The Commission \nissued the Large Load Show Cause Order as part of a suite of six coordinated orders directed to \neach of the Regional Transmission Organization/Independent System Operator regions subject to \nthe Commission’s jurisdiction. \n \n10  \nNYPSC Case No. 26-E-0045, Proceeding on Motion of the Commission to Address Interconnection Reforms \nfor Large Loads, Order Instituting Proceeding and Soliciting Comments (Feb. 12, 2026).  \n11  \nThe NYTOs appreciate that the Commission’s “objective in this proceeding is to respect the cooperative \nfederalism approach established under the FPA.”  Show Cause Order, 195 FERC ¶ 61,216 at P 76.  \n12  \nCapitalized terms not otherwise defined herein have the meanings set forth in the NYISO OATT or Market \nAdministration and Control Area Services Tariff, as applicable.   \n13  \nShow Cause Order, 195 FERC ¶ 61,216 at P 3."},{"page":5,"startToken":1838,"endToken":2314,"text":"November 16, 2026 \nPage 5 \n \n \nThe Large Load Show Cause Order included preliminary findings that the NYISO’s Tariff \nappears unjust and unreasonable in five principal respects: \n1.  Transmission Service Study Process for Large Loads.  The Commission \npreliminarily found that the NYISO’s Tariff lacks sufficiently clear and consistent provisions \naddressing: (a) a definition of Large Load as a distinct category of load; (b) a mandatory \napplication process, readiness requirements, and study procedures for Eligible Customers seeking \ntransmission service on behalf of Large Loads; (c) study timelines of no more than 60-90 calendar \ndays; (d) ongoing operational requirements – including telemetry, data reporting, remote \ndisconnect capability, ramp rate and ride-through requirements, and protection systems – for \ntransmission customers serving Large Loads; (e) evaluation of alternative transmission \ntechnologies as potential solutions in lieu of or in addition to traditional Network Upgrades; and \n(f) pro forma provisions in transmission service agreements to memorialize operational \nrequirements.14 \n2.  Cost Transparency and Cost Recovery.  The Commission preliminarily found that \nthe NYISO Tariff lacks: (a) robust, centralized, publicly accessible data on its website regarding \nthe Network Upgrades and associated costs needed to provide transmission service to Eligible \nCustomers on behalf of Large Loads; and (b) a pro forma CRA between the NYISO, the relevant \nTransmission Owner, and the Eligible Customer taking transmission service on behalf of a Large \nLoad, with a minimum financial contribution and credit support requirement sufficient to mitigate \nthe risk of cost shifting among transmission customers.15 \n3.  Co-Location Arrangements and Behind-the-Meter Generation.  The Commission \npreliminarily found that the NYISO’s Tariff lacks: (a) a definition of co-located load; (b) \nsufficiently clear and consistent provisions governing the rates, terms, and conditions of service \napplicable to interconnection customers serving co-located load, including required ancillary \nservice charges (regulation and black start service on a gross demand basis); and (c) provisions \naddressing netting of behind-the-meter generation from gross load for purposes of calculating \napplicable Transmission Service Charges in a manner consistent with the cost causation \nprinciple.16 \n4.  New Transmission Services for Eligible Load and Flexible Large Loads.  The \nCommission preliminarily found that the NYISO’s Tariff lacks transmission services that reflect \nthe operational capabilities of Eligible Customers taking transmission service on behalf of Eligible \nLoad (co-located load and load with behind-the-meter generation) and flexible Large Loads that \nare willing and able to limit their energy withdrawals from the transmission system under certain \nconditions, specifically:  (a) an interim Non-Firm network transmission service available while \n \n14  \nId. PP 56-71. \n15  \nId. PP 77-91. \n16  \nId. PP 101-110.  See, e.g., Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868-69 (D.C. Cir. 2024) \n(“[T]he cost causation principle requires that ‘all approved rates reflect to some degree the costs actually caused by \nthe customer who must pay them.’”) (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 88 (D.C. Cir. 2014))."},{"page":6,"startToken":2314,"endToken":2765,"text":"November 16, 2026 \nPage 6 \n \n \nNetwork Upgrades are being constructed; and (b) permanent firm and Non-Firm contract demand \ntransmission services.17 \n5.  Generator Interconnection for Electrically Proximate Large Load and Co-Located \nLoad.  The Commission preliminarily found that the NYISO’s Tariff lacks generator \ninterconnection study procedures and generator interconnection services tailored to reflect an \ninterconnection customer’s commitment to limit a generating facility’s output to match the hourly \nforecast of an electrically proximate Large Load or large co-located load, thereby potentially \nreducing the need for Network Upgrades and accelerating the interconnection process.18 \nThe Commission therefore directed the NYISO and the other named parties,19 within 60 \ndays of issuance (i.e., by August 17, 2026), to either:  (1) show cause as to why the Tariff remains \njust and reasonable and not unduly discriminatory or preferential without provisions addressing \nthe foregoing concerns; or (2) explain what Tariff changes would remedy those concerns were the \nCommission to determine that the Tariff is in fact unjust and unreasonable and to establish a \nreplacement Tariff.20  Alternatively, the Commission indicated it would consider requests to hold \nthe Show Cause Order proceeding in abeyance for up to 90 days to allow the NYISO and the other \nnamed parties time to “work through the stakeholder processes to develop FPA section 205 filings \nto revise the Tariff to address the issues raised in [the Show Cause Order].”21 \nOn August 3, 2026, the NYISO, certain NYTOs, LS Power Grid New York Corporation I, \nand New York Transco, LLC submitted separate requests to hold the Show Cause Order \nproceeding in abeyance for 90 days.22  The Commission granted those requests in an August 14, \n2026, order.23   \nB. \nThe NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement  \nAs the NYTOs explained in their motion to hold the Show Cause Order proceeding in \nabeyance, the NYTOs have explicitly reserved FPA section 205 filing rights in section 3.10(a) of \nthe NYISO-TO Agreement.24  Section 3.10(a) provides, in relevant part, that: \n \n17  \nShow Cause Order, 195 FERC ¶ 61,216 at PP 109, 112-113. \n18  \nId. PP 121-127. \n19  \nThe following entities were named as parties to the Show Cause Order: NYISO, Central Hudson, Con Edison, \nNYSEG, National Grid, O&R, RG&E, LS Power Grid New York Corporation I, New York Transco LLC, and NextEra \nEnergy Transmission New York, Inc.   \n20  \nSee, e.g., Show Cause Order, 195 FERC ¶ 61,216 at P 3. \n21  \nId. P 42. \n22  \nNew York Power Authority (“NYPA”) and LIPA did not join the abeyance request because they were not \nnamed as parties to the Show Cause Order.  \n23  \nN.Y. Indep. Sys. Operator, Inc., 196 FERC ¶ 61,130 (2026). \n24  \nNYISO-TO Agreement."},{"page":7,"startToken":2765,"endToken":3268,"text":"November 16, 2026 \nPage 7 \n \n \nEach Transmission Owner shall have the right at any time \nunilaterally to file pursuant to Section 205 of the Federal Power Act \nto change the ISO OATT, a Service Agreement under the ISO \nOATT, or the ISO Agreement to the extent necessary: (i) to recover \nall of its reasonably incurred costs, plus a reasonable return on \ninvestment related to services under the ISO OATT and (ii) to \naccommodate implementation of, and changes to, a Transmission \nOwner’s retail access program.25 \nSection 3.10(a) confers upon each Transmission Owner the unilateral right to file with the \nCommission under FPA section 205 – independent of the NYISO’s concurrence – to the extent \nnecessary to recover reasonably incurred costs associated with services provided under the NYISO \nOATT and to accommodate changes to the NYTOs’ retail access programs.26 \nThe Show Cause Order directly implicates the NYTOs’ ability to recover their reasonably \nincurred costs through rates filed with the Commission, including rates for recovery of costs of \nNetwork Upgrades and Attachment Facilities needed to provide transmission service to Eligible \nCustomers on behalf of Large Loads,27 new study procedures and requirements applicable to Large \nLoad Customers, and new services for Large Load Customers.  Accordingly, the NYTOs’ \nindependent filing rights under section 3.10(a) of the NYISO-TO Agreement are directly \nexercisable with respect to key issues identified below. \nSection 3.10(a) also provides an independent, second basis for the NYTOs’ exercise of \ntheir unilateral FPA section 205 filing rights that is equally applicable to certain key issues \nidentified below:  the right to file “to accommodate implementation of, and changes to, a \nTransmission Owner’s retail access program.”  The Show Cause Order’s directives directly affect \nthe NYTOs’ retail access obligations.  Specifically, the Show Cause Order requires that the NYISO \nOATT address eligibility for Large Load interconnection study procedures, the procedures \nthemselves, terms of transmission service for Large Load Customers, cost transparency \nrequirements, security and related cost recovery agreements, among other things.  Addressing each \nof these subjects, including through the associated new pro forma agreements submitted with this \nfiling (the pro forma Facilities Study Agreement, Interconnection Agreement, Large Load Security \nAgreement, and CRA), all of which requires changes to the portion of Section 5 of the NYISO \nOATT that deals with each Transmission Owner’s retail access program and retail transmission \nand distribution services. Because the Tariff reforms at issue necessarily affect each NYTO’s retail \n \n25  \nId. § 3.10(a). \n26  \nWhile the NYISO-TO Agreement recognized that OATT revisions are subject to NYISO stakeholder and \ngovernance requirements, it also excepted Section 3.10’s reservation of each Transmission Owner’s right to make \nunilateral section 205 filings.  See id. § 3.03 (providing that “[n]otwithstanding any other provision in this Agreement \nexcept for the provisions of Section 3.10,” proposed OATT revisions are subject to certain stakeholder and NYISO \ngovernance procedures (including review by the NYISO Board of Directors) before being filed at FERC) (emphasis \nadded). \n27  \nShow Cause Order, 195 FERC ¶ 61,216 at PP 20, 85."},{"page":8,"startToken":3268,"endToken":3631,"text":"November 16, 2026 \nPage 8 \n \n \naccess obligations, section 3.10(a) provides an additional, independent basis for the NYTOs’ filing \nauthority over the OATT revisions and pro forma agreements proposed in this proceeding. \nC. \nStakeholder Processes \nThe NYTOs participated in the NYISO stakeholder process relating to this proceeding, \nculminating in the NYISO’s Management Committee’s unanimous approval with abstentions of \nthe extensive FPA section 205 filing the NYISO makes in parallel with this filing.  Once the \nparameters of the NYISO filing were identified with reasonable particularity, and after extensive \nnegotiations and meetings over the shared and divided responsibilities for Large Load \ninterconnection processes, studies and reports, the NYTOs addressed the elements for which they \nwere responsible and that the NYISO did not include in its filing.  The NYISO first presented its \nproposed filing at a special joint meeting of its Operating Committee and the Business Issues \nCommittee on October 21, 2026.28  \nThe NYTOs have unilateral section 205 filing rights that do not require any particular \nstakeholder process or votes.  Nevertheless, on October 22, 2026, the NYTOs presented their \nconceptual proposal to a joint meeting of the NYISO Transmission Planning Advisory \nSubcommittee, the Electric System Planning Working Group, and the Installed Capacity Working \nGroup, the three bodies responsible for vetting the NYISO’s Large Load procedures.29    \nIII. \nPROPOSED TARIFF REVISIONS AND PRO FORMA AGREEMENTS \nThe NYTOs have worked extensively in a concentrated time frame to develop with the \nNYISO new interconnection study procedures for Large Loads.  The NYTOs have assumed \nresponsibility for significant aspects of the Large Load interconnection process, including: \n• physical infeasibility screening; \n• a preapplication process to lead to better-informed interconnection decisions by \nLarge Loads;  \n• review and updating of NYISO base cases; \n• identification of non-bulk transmission and distribution reliability violations; \n• identification of upgrades to solve those violations in addition to the bulk system \nviolations identified by the NYISO; \n \n28  \nWith certain revisions, the NYISO’s proposed filing was approved by the Management Committee on \nOctober 28, 2026. \n29  \nSee NYTO FPA Section 205 Filing on Certain Large Load Interconnection and Service Matters, NYISO \nTPAS/ESPWG/ICAP \nMeeting \n(Oct. \n22, \n2026), \navailable \nat \nNYTO_Section_205_Large_Load_Deck_Final_TPAS_10.22.26.pdf."},{"page":9,"startToken":3631,"endToken":4076,"text":"November 16, 2026 \nPage 9 \n \n \n• identification of Attachment Facilities; and  \n• estimates of the cost and time to construct all of the upgrades.  \nThese elements are included in the NYISO FPA section 205 filing but are NYTO \ncommitments to facilitate an improved Large Load interconnection process.  In contrast, this filing \naddresses complementary and necessary elements within the scope of the NYTOs’ reserved \nsection 205 filing rights.   \nThe NYTOs propose Tariff revisions and certain pro forma agreements regarding the \nfollowing topics addressed in the Show Cause Order:  (1) Network Upgrade cost allocation and \nrecovery and Attachment Facility cost recovery; (2) mechanisms to ensure that payments made \npursuant to cost recovery agreements or Tariff provisions are appropriately credited toward each \nNYTO’s transmission revenue requirement to the extent such costs are included in such revenue \nrequirements consistent with the Commission’s cost-of-service regulations and rates or formula \nrates accepted or approved by the Commission for each NYTO; (3) rates applicable to transmission \nservices arranged by Eligible Customers on behalf of Large Loads; (4) certain operational \nrequirements for Eligible Customers taking service on behalf of Large Loads and Large Loads \nthemselves; and (5) a pro forma Large Load Interconnection Agreement, along with necessary \nagreements and Tariff changes to implement the foregoing.30   \nThe NYISO Tariff already contains Commission-approved provisions pertaining to cost \nrecovery that explicitly reference the New York Public Service Law, the enabling statute for the \nNYPSC.  For example, section 31.5.1.6 of the NYISO OATT, Attachment Y, with respect to cost \nrecovery for Regulated Non-Transmission Projects, states in part, “[c]osts related to regulated non-\ntransmission projects will be recovered by Responsible Transmission Owners, Transmission \nOwners, and Other Developers in accordance with the provisions of New York Public Service \nLaw, New York Public Authorities Law, or other applicable state law.”31  Thus, tariff provisions \nproposed herein that explicitly reference mechanisms that are creatures of the New York Public \nService Law are not invoking an unprecedented practice.   \nOverall, the NYTOs’ FPA section 205 filing contains the following tariff additions and pro \nforma agreements as complements to the NYISO section 205 Large Load filing:  \n• Complementary and necessary amendments to the NYISO’s proposed Attachment \nLL to its OATT.  \n• Amendments to NYISO OATT Section 5 pertaining to various aspects of \nTransmission Owners’ service to retail access customers as detailed below, as well \n \n30  \nThis is not intended to be an exclusive list of the items within the NYTOs’ unilateral FPA section 205 filing \nright and does not constitute a waiver of any NYTO filing right.   \n31  \nNew York Independent System Operator, Inc. – NYISO Tariffs, Attachment Y, Section 31.5, Cost Allocation \nand Cost Recovery (32.0.0), § 31.5.1.6."},{"page":10,"startToken":4076,"endToken":4407,"text":"November 16, 2026 \nPage 10 \n \n \nas revised rates to accommodate the Commission’s rate directives within the \ncontext of the NYISO construct. \n• Amendments to Attachment B of Section 8 of the NYISO OATT, the pro forma \nTransmission Service Agreement (“TSA”), to add cross-references to Section 5 of \nthe NYISO OATT. \nIn addition, the following three proposed pro forma agreements are intended to work \ntogether to ensure appropriate cost recovery and integration of Large Loads in a manner that avoids \nundue cost shifts to other transmission customers: \n• A pro forma CRA recovering the allocated costs of Transmission Owner \nAttachment Facilities and Network Upgrades to Large Load Customers as \nexplained in greater detail below.  \n• A pro forma Large Load Security Agreement, which sets forth the security posting \nrequirements for the Large Load.  \n• A pro forma Large Load Interconnection Agreement which sets forth the terms and \nconditions for Large Load interconnection between the customer and the \nTransmission Owner.   \nFinally, to meet its study responsibilities under the proposed Attachment LL construct, the \nNYTOs propose one additional pro forma agreement:    \n• A pro forma Facilities Study Agreement which establishes the scope of \nTransmission Owner study work under Attachment LL and at the request of a Large \nLoad Customer. \nEach of these filing components is discussed in turn below following discussion on the \njurisdictional status of this filing:  \nA. \nJurisdictional Status of this Filing  \nIn the Show Cause Order, in the context of transmission security agreements and \nconstruction service agreements, the Commission “declines to preliminarily find that cost \nrecovery agreements between the transmission owner and the large load customer (rather than \nfrom the Eligible Customer taking transmission service on behalf of the large load customer) are \nnecessary to ensure just and reasonable transmission rates, … [and] continue[s] to find that such \nagreements directly affect Commission-jurisdictional transmission rates.  Therefore, to the extent \na Transmission Owner and a Large Load Customer enter into a cost recovery agreement \n(whether voluntary or pursuant to state law) through which the Large Load Customer guarantees"},{"page":11,"startToken":4407,"endToken":4890,"text":"November 16, 2026 \nPage 11 \n \n \ncontributions to the transmission owner’s Commission-jurisdictional transmission revenue \nrequirement, we find that such an agreement should be filed with the Commission.”32  \n  \nThe NYTOs present in this filing pro forma Large Load Facilities Study, Security, Cost \nRecovery, and Interconnection Agreements.  While they relate to the NYISO Large Load \nIntegration Process as proposed in new Attachment LL of the NYISO OATT, they are not \nappropriate agreements for intermediaries between the Large Loads themselves and the NYTOs \nresponsible for interconnection studies, cost recovery, associated security and interconnection, \nincluding certain operational reliability requirements.  In each of these contexts, the NYTOs \nhave dealt directly with the Large Load Customers themselves, who are the financially \nresponsible parties, and propose to continue this practice.  \n \nHistorically, in New York, energy service companies (“ESCOs”) have provided \ncommodity supply unbundled from retail delivery services and have been Eligible Customers for \npurposes of the NYISO’s energy and capacity market settlements.  ESCOs have been Eligible \nCustomers under the NYISO Tariffs for limited purposes, enabling retail access programs \nintended to introduce competition for supply, but not for purposes of retail customer \ninterconnection studies and associated agreements to effect retail interconnections with grid \nowners.  \n \nESCOs or other intermediaries have not functioned as the primary interfaces or \ncontracting parties in the interconnection process for new Large Loads.  This is not by accident; \nunlike serving as a supply source to enable retail access, ESCOs would serve no legitimate \nbusiness function as an intermediary in the Large Load Interconnection Process.  In fact, their \ninsertion would only serve to frustrate that process, making it riskier and, not insignificantly, \ncostlier.  \nUntil recently, the interconnection process for loads was subject to NYPSC regulation \nand not FERC regulation.  The interconnection of retail loads has been to facilitate local \ndistribution of electric energy which the Commission found to be involved in every retail \ntransmission transaction33 and to facilitate retail sales of electric energy.  These functions are \nsubject to State jurisdiction, and the NYPSC regulates such functions.   \n \n32  \nShow Cause Order, 195 FERC ¶ 61,216 at P 88. \n33  \nIn Order No. 888, FERC stated: “while we believe in most cases there will be identifiable local distribution \nfacilities subject to state jurisdiction, we also believe that even where there are no identifiable local distribution \nfacilities, states nevertheless have jurisdiction in all circumstances over the service of delivering energy to end \nusers.”  In re Promoting Wholesale Competition by Pub. Utilities, Order No. 888, 75 FERC ¶ 61,080 at 21,626 (1996) \n(subsequent history omitted).   FERC similarly noted in Order No. 888-B:  “We reiterate that we believe there is \nalways a local distribution service element of a retail transaction, through which the state may impose charges on the \nretail customer.”  Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. \nby Pub. Utilities Recovery of Stranded Costs by Pub. Utilities & Transmitting Utilities, Order No. 888-B, 81 FERC ¶ \n61,248 at 62,098 (1997)."},{"page":12,"startToken":4890,"endToken":5342,"text":"November 16, 2026 \nPage 12 \n \n \nThe NYISO relatively recently has been more involved in considering bulk power system \nimpacts associated with certain large retail load interconnection requests.  The Show Cause \nOrder asks for clear and transparent rules governing the interconnection of Large Loads.  The \nNYISO will continue to analyze bulk system impacts and violations caused by the \ninterconnection of Large Loads.  The Transmission Owners, however, are responsible for \nsignificant aspects of the Large Load interconnection process, including: \n \n• physical infeasibility screening; \n• a preapplication process to lead to better-informed interconnection decisions by \nLarge Loads;  \n• review and updating of NYISO base cases; \n• identification of non-bulk transmission and distribution reliability violations; \n• identification of upgrades to solve those violations in addition to the bulk system \nviolations identified by the NYISO; \n• identification of Attachment Facilities; and  \n• estimates of the cost and time to construct all of the upgrades.  \n \nThe Transmission Owners have extensive experience in handling all forms of retail load \ninterconnection studies and entering into appropriate agreements which have not been subject to \nFERC jurisdiction or filing requirements.  Each of the six NYTOs has its own forms of \nagreement.  In response to the Show Cause Order, however, the NYTOs have worked to adopt \nstandardized procedures and forms of agreement to make the process more transparent and easier \nto navigate.  \n \nThe Transmission Owners, however, do not agree that the interconnection study process, \nupgrade and attachment facility cost recovery, associated security and interconnection and \noperational reliability requirements should be subject to the insertion of an intermediary between \nthe Large Load Customer and the Transmission Owners responsible for a substantial majority of \nthe interconnection study process, building upgrades and Attachment Facilities and maintaining \nsystem reliability, including through operating and interconnection requirements.  \n \nIn the compressed time that the NYTOs have to handle the tasks listed above, direct \ncommunications with the Large Load Customer will be necessary in order to have an efficient \nand effective interconnection study process which inevitably involves discussions with many \ncustomers simultaneously.  ESCOs or other intermediaries have not played a significant role in \nthese processes, are not the ultimate parties-in-interest (i.e., the transactions and services \naddressed by the pro forma agreements bear no relationship to the supply services ESCOs are \nengaged by customers to perform) and FERC should not enter the process now. \n \nOnce the Facilities Study is issued, each Large Load Customer will have a short period of \ntime to enter into a Security Agreement on a Transmission Owner-specific basis for each \nUpgrade that the Transmission Owner has identified and to secure the Attachment Facility and \nNetwork Upgrade costs.  Some upgrades will cost tens or even hundreds of millions of dollars.  \nIt is not realistic to have ESCOs or intermediaries cover such large security amounts without"},{"page":13,"startToken":5342,"endToken":5850,"text":"November 16, 2026 \nPage 13 \n \n \nrelying on the Large Load Customer directly, and expanding such agreements to cover a \nsuperfluous party adds risk, delay, and complexity that should be avoided.  \n \nOnce security is posted, the relevant Transmission Owner(s) will enter into the CRA, \nSecurity Agreement, and Large Load Interconnection Agreement with the Large Load Customer \n(as required by the NYISO’s revisions in proposed Attachment LL section 44.12.1.8) rather than \nthe Eligible Customer.  The CRA as proposed is a long-term agreement and may involve the \nrecovery of tens or even hundreds of millions of dollars in upgrade and attachment facility costs.  \nAs noted, ESCOs will be dependent on the Large Load Customers themselves, and if there is a \ndefault, the Transmission Owners will be seeking redress directly through the security provided \nby the Large Load Customer.  Interjecting a third-party intermediary between the Large Load \nCustomer and the Transmission Owners only complicates remedies when needed on short notice \nand increases risk and costs with high stakes involved.  The goal of avoiding stranded costs \nbeing shifted to other customers would not be served by adding intermediaries to the contracting \nprocess.  \n \nThe Interconnection Agreement with Large Load Customers will identify facilities \nneeded to reliably interconnect the customer to the retail franchise utility’s system.  Any special \noperating conditions that are required will need to be followed by the Large Load Customer, not \nan ESCO.  The ability to operate a Large Load associated with dispatch instructions, ramping, \ncurtailment, disconnect and restoration will be handled by the Large Load Customer and not by \nan ESCO or other intermediary, and system reliability will depend on this relationship, direct \ncommunication and prompt responsiveness. \n \nThe NYTOs do not in this filing or in the companion NYISO filing offer to provide \nvoluntary retail transmission, distribution or delivery services.  They provide such services only \nas directed by the NYPSC or in accordance with NYPSC policy.  They do not volunteer to enter \ninto Facilities Study, Security, Cost Recovery, and Interconnection Agreements with ESCOs or \nother intermediaries of Large Load Customers.  It would not be just and reasonable to require \nsuch arrangements, and if they were required, it would raise troubling issues associated with 16 \nU.S.C. § 824k(h). \n \nAs discussed in the context of the delivery rates identified in Section 5 of the NYISO \nOATT and as proposed to be modified in this filing, the NYTOs plan to continue the practice in \neffect since NYISO started applying NYPSC-determined delivery rates for Large Load \nCustomers as well as for other retail customers.  Cooperative federalism, expressly recognized as \na goal of the Commission in the large load context,34 has worked for 27 years whereby the \nCommission accepted NYPSC-determined rates, terms, and conditions for retail delivery \nservices.  If the Commission were to accept this filing, subject to any amendments the NYTOs \nmake in response to further orders of the NYPSC, the NYTOs would once again seek to satisfy \nboth regulators without endangering jurisdictional or preemption disputes.  \n \n \n34  \nSee Show Cause Order, 195 FERC ¶ 61,216 at P 76."},{"page":14,"startToken":5850,"endToken":6381,"text":"November 16, 2026 \nPage 14 \n \n \nThe Commission expressed concerns that the rates the Transmission Owners charge \nLarge Load Customers for Network Upgrades and the associated security agreements may affect \nother Commission-jurisdictional rates.  The NYTOs have adopted a covenant in the NYISO \nproposed Section 44.12.1.8 of Attachment LL whereby each NYTO covenants not to include \ncosts recovered through such CRA or Security Agreement in rates for other FERC-jurisdictional \ntransmission customers without an accompanying revenue credit and an explanation of the rate \ntreatment.  This covenant is to directly address the impacts that Large Load Customer \ninterconnections can have on other FERC-jurisdictional rates.  \n \nThe NYTOs recognize that the Commission may determine that it does not have \njurisdiction over some aspects of the Large Load Integration Process, particularly those elements \nfiled herewith.  The NYTOs reserve the right to submit any agreements, rates, terms and \nconditions associated with Large Loads to the NYPSC.  As noted below in this filing, the \nNYPSC commenced a proceeding in February 2026 concerning Large Load matters.  The \nNYTOs reserve the right to amend this filing based on further guidance and direction from the \nNYPSC.  \n \nThe NYTOs, however, submit this filing to be responsive to the Show Cause Order and \nto provide interested stakeholders an integrated process and forms applicable to Large Load \nIntegration Procedures.  \n \nB. \nNetwork Upgrade Cost Recovery \nThe NYTOs submit with this filing a pro forma CRA to recover the costs of Network \nUpgrades and Attachment Facilities identified by each Transmission Owner in its Large Load \nFacilities Studies in accordance with NYISO OATT Attachment LL.  The proposed pro forma \nCRA may be used by as many as three different types of Transmission Owners with a single Large \nLoad Customer.  First, upgrades required to accommodate a Large Load Customer may be limited \nto a single Transmission Owner, which is often the Connecting Transmission Owner (“CTO”) that \nowns the transmission facility at the proposed point of interconnection and which is also the retail \ndistribution utility.  Second, a Transmission Owner that owns the line at the proposed point of \ninterconnection (the CTO) may not have a Certificate of Public Convenience and Necessity under \nSection 68 of the New York Public Service Law to serve retail load at the requested location.  In \nsuch a case, the franchise distribution utility with the right to serve retail load, which is not the \nCTO, will need to install and/or own the retail meter and appurtenant facilities and the \nTransmission Owner that owns the facility at the proposed point of interconnection will have to \nmodify its facilities and construct any necessary upgrades on its facilities/system.  Third, in either \nof these cases, the Large Load Customer may cause reliability violations on another ATO’s system.  \nAccordingly, the CTO that is also the retail distribution utility for the Large Load, a CTO that is \nnot the retail utility, and one or more Affected Transmission Owners (“ATOs”), each would need \na CRA to recover its costs of the Network Upgrades and Attachment Facilities to interconnect a \nLarge Load Customer.  \nUnder the CRA, each Transmission Owner will recover 100% of its costs of Network \nUpgrades and Attachment Facilities from Large Load Customers.  For each Network Upgrade or"},{"page":15,"startToken":6381,"endToken":6925,"text":"November 16, 2026 \nPage 15 \n \n \nAttachment Facility that is to mitigate or remedy violations caused by more than one project of a \nLarge Load Cluster, the costs of the associated upgrade shall be allocated in accordance with the \nAllocation Factors identified in the Facilities Study (see discussion of the Facilities Study below).   \nWhen the CTOs and ATOs complete the Facilities Studies for a Cluster under the NYISO \nLarge Load Integration Procedure (“LLIP”), each Large Load project will be required to post cash \nor a letter of credit as security for the Network Upgrades and Attachment Facilities assigned to it \nin the Facilities Study.  A Large Load’s failure to timely post security will result in removal of the \nLarge Load from the LLIP.  If a Large Load that had responsibility for a Network Upgrade shared \nwith one or more other customers in the Cluster is removed from the Cluster, then either:  (a) the \nother Large Load(s) with shared responsibility for a Network Upgrade will have new allocations \nof the cost of the upgrade and new security posting requirements, or (b) the CTO or ATO that \nidentified the Network Upgrade may determine that the Network Upgrade is no longer required, \nand the remaining Large Load(s) will no longer be responsible for that upgrade.  Prior to the \nissuance of the first Cluster under the NYISO’s November 16, 2026 FPA section 205 Large Load \nfiling, the NYTOs plan for the NYISO or the NYTOs to make a filing under the FPA to adopt \nprocedures governing a failure of one or more projects in the then-current Cluster to timely post \nrequired security and the reallocation of costs of such upgrades, unless the upgrade is no longer \nneeded. \nUnder the CRA, each Transmission Owner would recover the allocable share of the costs \nof the Network Upgrade(s) and Attachment Facilities over a 15-year period, as described further \nbelow.  In each LLIP Cluster, the upgrade costs will be recovered from the Large Load Customer \nthat causes the violation giving rise to the Network Upgrade(s) and Attachment Facilities.  Where \nmore than one Large Load contributes to a violation resulting in an upgrade, costs shall be allocated \nin accordance with the procedures discussed below. \nUnder the proposed NYISO LLIP, the NYISO is responsible for identifying violations and \noverloads on the Bulk Power System caused by the interconnection of a Large Load following the \nLLIP.  When more than one Large Load contributes to a violation, the NYISO provides \ncontribution factors.  Each CTO and ATO is responsible for identifying:  (a) violations on the non-\nBulk Electric System, including local transmission and distribution systems, (b) the Network \nUpgrades to address both bulk system and non-bulk violations (subject to consultation with the \nNYISO), (c) cost estimates and time to construct the Network Upgrades, (d) the allocation of costs \namong the Large Loads following the LLIP Cluster based on the NYISO- and NYTO-determined \ncontribution factors, (e) Attachment Facilities, and (f) estimates of Attachment Facility costs and \ntime to construct.  \nConsistent with the Show Cause Order, the NYTOs provide with this filing a pro forma \nCRA pursuant to which each Large Load Customer would compensate the applicable CTO or ATO \nfor its allocable share of the Network Upgrade costs and all of the Transmission Owner Attachment"},{"page":16,"startToken":6925,"endToken":7544,"text":"November 16, 2026 \nPage 16 \n \n \nFacility costs.35  The CRA would appear in the NYISO OATT as Appendix 9 to Attachment LL \n(Section 44.16.9), and the pro forma Security Agreement as Appendix 10 (Section 44.16.10).  \nIn its orders related to Large Load Network Upgrade cost allocation, the Commission has \nbeen clear that it seeks to avoid shifting upgrade costs from Large Loads to other customers and \nto avoid upgrade costs being stranded if a Large Load does not cover its share of such costs before \nceasing compensation for the upgrades.  In the Show Cause Order, the Commission stated that it \n“must act to address the risk of cost shifting among transmission customers” to address, inter alia, \ncosts associated with facilities needed to serve Large Loads as well as the risk of speculative \nrequests associated with Large Load Customers.36  \nIn the Show Cause Order, FERC expressly noted the risk for transmission customers to \n“pay for potentially unnecessary Network Upgrades that they neither caused the need for nor \nbenefit commensurately from” if a Large Load fails to materialize as anticipated.37  The \nCommission has otherwise noted that transmission customers should be protected from paying for \ntransmission facilities to serve Large Load Customers or otherwise bear the costs of a Large Load \nfailing to achieve planned commercial operations.38  \nThe NYTOs have addressed the Commission’s concerns in the CRA and a pro forma Large \nLoad Security Agreement.  The pro forma CRA includes a Large Load Formula Rate to recover \neach Large Load Customer’s Allocable Network Upgrade Costs and Attachment Facilities costs \nfrom the customer.39  The useful life of many Network Upgrades will be 40 years or longer.  \nEntering into a CRA of such a long duration increases performance and financial security/collateral \nrisks that can result in stranded costs and cost shifts to other customers.  Accordingly, the CRA \n \n35  \nFor ease of reference, we refer to “upgrades” and “Network Upgrades” in discussing the Large Load CRA, \nbut the terms are intended also to apply to Attachment Facilities as noted above.  \n36  \nShow Cause Order, 195 FERC ¶ 61,216 at P 74; see also Midcontinent Indep. Sys. Operator, Inc., 195 FERC \n¶ 61,212 at PP 78-82 (2026) (discussing the need for a cost recovery agreement among other requirements to ensure \ncost shifting risks to other transmission customers are mitigated).  \n37  \nShow Cause Order, 195 FERC ¶ 61,216 at P 85.  \n38 \nSee Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 at P 20 (2025) (FERC rejecting a proposed Amended \nNetwork Integration Transmission Service Agreement and noting no explanation for how the proposed transmission \nrate would not shift costs of necessary transmission facilities to other customers); PECO Energy Co., 193 FERC ¶ \n61,148 at P 32 (2025) (FERC noting an applicant’s representation that a filed Transmission Security Agreement \nincludes “safeguards to protect customers” by requiring that the Large Load make a minimum contribution to the \ntransmission revenue requirement regardless of whether the Large Load ever achieved operation); The Dayton Power \n& Light Co., 192 FERC ¶ 61,103 at P 13 (2025) (FERC noting the filed Construction Service Agreement “includes \ncustomer protection provisions designed to prevent AES Ohio’s other customers from bearing ultimately cost \nresponsibility if the Data Center fails to achieve commercial operations”).  \n39  \nIn some circumstances, the NYPSC, a CTO, or ATO may determine that an alternate cost allocation and/or \nrecovery mechanism is justified.  Nothing in the default mechanism of the CRA is intended to limit the NYPSC’s \nauthority to determine an alternative cost allocation methodology pursuant to its own procedures or a CTO or ATO’s \nright to file an alternative agreement, pro forma agreement or non-conforming agreement governing cost allocation \nand recovery under FPA section 205."},{"page":17,"startToken":7544,"endToken":8049,"text":"November 16, 2026 \nPage 17 \n \n \nprovides for a term of 15 years over which the Transmission Owner that constructs the upgrade \nwould be fully compensated for the cost of the upgrade.  \nAccelerating depreciation of the assets to correspond to their repayment term, however, \nwould raise accounting and rate-making issues that should be avoided.  For example, accelerated \ndepreciation may conflict with how depreciation rates are established pursuant to the FERC chart \nof accounts.  Further, certain utility software that marks asset classes for a variety of purposes may \nnot be able to implement separate project-specific depreciation rates.  Accordingly, rather than \ndepreciating the upgrade over 15 years, the risk of cost shifts to other customers and avoids the \npitfalls of accelerated depreciation.  The Large Load Upgrade Charge under the CRA compresses \ncost recovery into the CRA term but does not accelerate depreciation on the Transmission Owner’s \nbooks.  Rather, for accounting purposes, the Transmission Owner would depreciate each upgrade \nover its full economic life on a composite straight-line basis, as usual.  The Large Load, however, \npays the full cost within the 15-year term rather than over the decades the equipment will be in \nservice.  This substantially mitigates the risk of cost shifts to other customers and avoids the pitfalls \nof accelerated depreciation. \n \nAs a result, the Large Load’s yearly payments during the term are higher than the \nequipment’s normal yearly straight-line depreciation cost.  The Transmission Owner will defer in \nits accounts that excess (the “Annual Deferred Revenue”).  Starting in Year 16 and continuing for \nthe rest of the upgrade’s economic life, the Transmission Owner will credit the deferred amounts \nback to its cost of service in its bundled T&D rates, or, if unbundled, in its transmission rates, \nthereby protecting other customers from upgrade costs. \n \nThe annual revenue requirement for each upgrade is calculated as if the upgrade were \nrecovered over its Average Service Life, using the Transmission Owner’s approved depreciation \nrates, and the Transmission Owner earns its return on the depreciated, not the original, cost of the \nupgrade.  That is, the investment balance used in the annual calculation is the original cost reduced \nby accumulated depreciation and amortization.  As the equipment depreciates each year, the \nremaining balance on which the Transmission Owner earns a return reduces in amount, so the \nreturn portion of the charge declines over the term, while the depreciation portion stays level under \nstraight-line depreciation.  That annual revenue requirement is then multiplied by the Average \nService Life and divided by the 15-year contract term to produce the compressed charge. \n \n1. How the Charge Is Calculated \nThe Transmission Owner calculates the charge in four steps: \n \n1. Start with upgrade cost.  The Transmission Owner uses estimated costs at first.  \nAfter construction, it substitutes actual, prudently incurred costs and corrects all prior \nbills, with interest, back to the start of payments. \n \n2. Apply the carrying charge.  The annual costs associated with the Large Load \nUpgrade shall consist of two components:  (1) the Large Load Upgrade-specific \nreturn of and return on investment, including associated income taxes; and (2) an"},{"page":18,"startToken":8049,"endToken":8452,"text":"November 16, 2026 \nPage 18 \n \n \nestimate of O&M, A&G, property tax, payroll tax, and other applicable expenses \nassociated with the Large Load Upgrade, excluding depreciation, amortization, \nreturn, and associated income taxes.  This second component shall be calculated using \nan Annual Ongoing Charge Factor equal to the applicable system-wide expenses, \nexcluding depreciation, amortization, return, and associated income taxes, divided by \ntotal gross plant in service.  The Annual Ongoing Charge Factor shall be applied to \nthe Large Load Upgrade-specific gross plant in service. \n \n3. Compress into the contract term.  The Transmission Owner multiplies that yearly \ncost by the equipment’s average service life and divides by the number of years in the \ncontract term. \n \n4. Bill monthly.  The Large Load pays one-twelfth of the resulting yearly amount each \nmonth. \n \n2. How the Carrying Charge Is Adjusted Each Year \n \nThe carrying charge percentage (the “Annual On-going Charge Factor”) changes from \nyear to year.  It equals the Transmission Owner’s total yearly transmission and distribution costs, \nexcluding depreciation, amortization, return, and associated income taxes, divided by total gross \nplant in service.  Those costs are municipal and payroll taxes, operations and maintenance, and \nadministrative and general expenses, minus rents received.  Because these system-wide figures \nchange, the percentage changes too. \n \nAnnual update.  No later than August 1 of each year, the Transmission Owner \nrecalculates the carrying charge percentage using the most recent rate data from NYPSC sources:  \nthe Transmission Owner’s NYPSC rate order, its annual and compliance reports to the NYPSC, \nand its books and records, with FERC Form No. 1 data used only if an input cannot be derived \nfrom those NYPSC sources.  All inputs must cover the same reporting period and be measured \nthe same way.  The update calculation reflects changes in the Transmission Owner’s approved \nreturn on equity, capital structure, and depreciation rates.  The Transmission Owner then resets \nthe yearly charge, the Annual Deferred Revenue, and the monthly billing schedule for the \ncoming year.  The NYTOs propose using NYPSC data because the NYPSC establishes rates for \nall retail customer classes in utility-specific, comprehensive rate cases which review \ntransmission, distribution, common costs and overheads, cost allocation and rate design on a \nregular basis.  \n \nTrue-up.  Each year’s carrying charge percentage relies on prior-year data, so each year’s \nbills are estimates of actual charges.  The next year, the Transmission Owner compares what it \nbilled with what it would have billed using actual data for that period.  The Transmission Owner"},{"page":19,"startToken":8452,"endToken":8923,"text":"November 16, 2026 \nPage 19 \n \n \nrefunds any overcharge, or collects any undercharge, with interest at the FERC rate,40 in equal \nmonthly installments over the next rate year. \n \nTransparency and disputes.  With each update, the Transmission Owner provides to the \nLarge Load a written statement showing every input and its source, the true-up calculation, and \nsupporting workpapers.  The Large Load may challenge the calculation under the Agreement’s \ndispute resolution provisions. \n \nImplementation of formula.  Once the Large Load Formula Rate is accepted or approved \nby FERC, a change to an NYPSC-approved input will flow through the annual update of the \nLarge Load Formula Rate and will not require a new FERC filing.  A change to the Large Load \nFormula Rate itself will require a filing with the Commission for acceptance or approval. \n \n3. Relationship to Large Load Security Agreement and Proposed \nEffective Date \n \nEven with the shorter term of 15 years, it is possible that some Large Loads will default.  \nTo avoid cost shifts and consistent with Commission guidance,41 the NYTOs are submitting a \npro forma Large Load Security Agreement for Commission acceptance or approval to secure the \nNYTOs’ cost recovery in the event of a default or early termination by the Large Load Customer \n(discussed in the next section of this transmittal). \n \nC. \nLarge Load Security Agreement \nIn the Show Cause Order, the Commission stated, “[w]e further preliminarily find that \nthe cost recovery agreement should include a credit support (or other financial security) \nrequirement …”42  The proposed pro forma Large Load Security Agreement would require the \nLarge Load Customer to post security to cover the allocated costs of Network Upgrades and \nTransmission Owner Attachment Facilities.  The initial security amount is based on the Facilities \nStudy cost estimates, is subject to adjustment through the cost allocation process when other \nprojects in the Cluster fail to post security, and, once the CRA is executed, is adjusted annually \nto cover the Large Load Customer’s remaining obligations under the CRA.  The CRA and Large \nLoad Security Agreement are related agreements (along with the Large Load Interconnection \nAgreement) and these related agreements work to address the Commission’s concerns regarding \nrisks to other customers associated with loads that do “not materialize as planned or is not \ndeveloped at all.”43  The Large Load Security Agreement allows the Transmission Owner to \ndraw on security, which would be provided by the Large Load Customer in the form of cash or \n \n40  \nSee 18 C.F.R. § 35.19a (2026). \n41  \nSee Show Cause Order, 195 FERC ¶ 61,216 at P 85 (noting FERC’s concern that “speculative transmission \nservice requests by Eligible Customers on behalf of large loads that could result in cost shifting among transmission \ncustomers, which may lead to unjust and unreasonable increases in jurisdictional transmission rates”).  \n42  \nId. P 89. \n43  \nId. PP 87, 89."},{"page":20,"startToken":8923,"endToken":9365,"text":"November 16, 2026 \nPage 20 \n \n \nan irrevocable standby letter of credit from a qualifying bank, for such events as abandonment of \nthe project, events of default under the related agreements after any applicable cure period, \nnotification by the customer that it is ceasing to negotiate the CRA or Large Load \nInterconnection Agreement where the facilities must still be completed, failure to renew or \nreplace a letter of credit, and other events as listed in the Large Load Security Agreement that \ncreate undue risks of cost shifts for the Transmission Owner or other customers.  The CRA links \nto the Large Load Security Agreement by specifying that the Transmission Owner can draw \nupon the security in the amount and manner specified under the Large Load Security Agreement \nin order to protect other customers against stranded asset risks in the case of such events as \nabandonment or customer default, including to satisfy the Net Present Value Residual Charge \nowed upon early termination.    \n \n \nOverall, the NYTOs respectfully submit that the CRA and the Large Load Security \nAgreement mitigate undue risks to other customers and Transmission Owners consistent with \nCommission guidance as set forth in the Show Cause Order.  \n \nD. \nRevenue Crediting \nThe Commission expressed concern that to the extent Large Load Customers paid for \nNetwork Upgrades, the Transmission Owner building and owning the upgrades should provide \nrevenue credits in rates applicable to other customers to avoid double recovery.44  The NYTOs \nhave proposed an addition to Section 44.12.1.8 of Attachment LL of the NYISO OATT that \nprovides a restrictive covenant whereby each NYTO agrees not to recover any costs of Large Load \nNetwork Upgrades from any other FERC-jurisdictional transmission customer without a separate \nsection 205 filing explaining the rate treatment and any revenue credit(s) associated with the \nupgrade costs, or, if the costs of such a Large Load Upgrade are already includable in a formula \nrate on file with the Commission, the Transmission Owner will explain the costs and revenue \ncredits associated with the Large Load Upgrade in any update to the formula that includes Large \nLoad Upgrade costs.  \nE. \nTransmission Service Charges  \n1. \nDevelopment and Evolution of Current Delivery Rates Applicable to \nRetail Access and Large Load Customers \n \nThe NYISO FPA section 205 filing proposes rules governing the market settlements \napplicable to each Large Load Customer.  In particular, Eligible Customers obtaining Non-Firm \nTransmission Service for Large Loads will be required to bid into the NYISO Day-Ahead Market \nand to settle deviations in the Real-Time Market.  The NYISO will apply Transmission Usage \nCharges for Transmission Congestion and Marginal Losses.  The NYISO will also apply certain \nAncillary Service Charges.  \n \n44  \nId. P 38."},{"page":21,"startToken":9365,"endToken":9818,"text":"November 16, 2026 \nPage 21 \n \n \nThe NYISO charges do not address the embedded cost delivery charges (bundled \ntransmission and distribution rates discussed below) that the utility with the retail franchise to serve \nretail customers in each service area applies under its NYPSC-authorized retail tariff service \nclassification.  As explained in the attached Panel Testimony, the NYPSC adopted retail access \nprograms in 1996, before the NYISO was operational in late 1999, whereby electric commodity \nsupply was unbundled from transmission and distribution delivery rates applicable to this form of \n“retail wheeling” or “retail transmission service” – i.e., deliveries of third-party supplied energy \nto retail customers in New York.45  Since before the NYISO’s inception, the NYPSC has \nestablished through many proceedings the retail delivery charges that retail customers in New York \npay to NYPSC-jurisdictional distribution companies.  In the spirit of cooperative federalism, the \nNYTOs identified, in Section 5 of the NYISO OATT, the NYPSC-jurisdictional retail service \nclassifications, and incorporated the rates, terms and conditions applicable to retail delivery service \nby reference as those NYPSC service classifications may be amended or superseded from time to \ntime.  The Commission accepted these tariff provisions.46  \nAs explained in the attached Panel Testimony, this system has been in place for 27 years, \nthrough which the NYPSC has determined voltage-differentiated delivery rates that unbundle \nsupply and apply to delivery service by the jurisdictional Transmission Owners (excluding the \nNYPA and LIPA).47  While the NYTOs recover almost all of their transmission and distribution \ncosts through “bundled” delivery rates set by the NYPSC,48 some delivery rates are not fully \nbundled because they are voltage-differentiated based on cost allocations that intentionally remove \ncertain distribution costs from the rates developed for transmission-level customers.49   \nThese voltage-differentiated rates generally provide demand charges that are considerably \nlower for higher voltage customers, as compared to the rates applicable to lower voltage, \ndistribution-level interconnecting customers.  For example, for NYSEG’s NYPSC service \nclassification SC 7, Large General Service with Time-of-Use Metering, there are three applicable \nvoltages:   \n• 7-1 – Secondary, 120–480 volts;  \n \n45  \nPrepared Testimony of Brian McNierney, Carol Teixeira, Yan Flishenbaum, and Stacy Powers, Attachment \nI at 7 (“Panel Testimony”).  See also In the Matter of Competitive Opportunities Regarding Electric Service, Case 94-\nE-0952, et al., Opinion No. 96-12 (1996). \n46  \nCent. Hudson Gas & Elec. Corp., 86 FERC ¶ 61,062, order on reh’g and compliance, 88 FERC ¶ 61,138 \n(1999). \n47  \nPanel Testimony at 9. \n48  \nCertain transmission rates recovered under NYISO OATT Schedules 10 and 19 are facility-specific formula \nrates for such projects as Public Policy Transmission Projects identified by the NYPSC with cost recovery permitted \nunder the NYISO’s Order No. 1000 Public Policy Transmission Planning Process (Attachment Y of the NYISO \nOATT).  \n49  \nPanel Testimony at 10."},{"page":22,"startToken":9818,"endToken":10224,"text":"November 16, 2026 \nPage 22 \n \n \n• 7-2 – Primary, 2.4–34.5 kV or regulated 46 kV; and  \n• 7-4 – Transmission, 115 kV and above.   \nThe applicable demand charge (per kW) for each one of those voltage classifications is:  \n• 7-1 – $14.55;  \n• 7-2 – $13.76; and  \n• 7-4 – $2.07.   \nThese rates make clear that the demand charge applicable to the highest transmission level \ncustomer is one-seventh of the demand charge applicable to the lowest distribution level customer \nbased in part on the exclusion of certain distribution and lower voltage system costs from the \ndemand charge applicable to transmission level customers.  \nThe Panel Testimony also provides a hypothetical savings example that illustrates how \nsubstantially lower the rate and charges would be under the transmission level rate compared to \nthe distribution rate.50 \nThe NYPSC-approved retail tariffs for the franchise distribution utilities provide Large \nLoad Customers an alternative optional rate under which they may take delivery service.  In \nparticular, each utility has “time-of-day” demand delivery rates in which the monthly demand \ncharges will reflect the customer’s metered load for each daily peak or super peak period thereby \ncalculating “as used” demand charges for that day based on actual withdrawals.    \nA Large Load having selected the time-of-use delivery rate would pay less as-used demand \nwhen curtailed during the relevant period by the NYISO.  Each Large Load Customer will have \nthe option of determining whether a standard delivery rate or time-of-use rate makes the most \nsense to that customer, thereby providing the opportunity to reduce costs.  The Panel Testimony \nprovides another example in which a Large Load is curtailed by the NYISO or a utility to zero on \nfive days in which on-peak daily as-used demand is measured, which shows how a flexible Large \nLoad can lower its monthly delivery bill under NYPSC optional demand service if it is subject to \npersistent curtailments and dispatch during peak or off-peak hours on any given day.51 \nIn the supporting Panel Testimony, NYTO witnesses describe in further detail both the \nmanner in which the retail delivery rates were formed through NYPSC proceedings and the rate \noptions that Large Load Customers have for delivery service.  These NYPSC-approved rates and \nservice classifications are referenced in the proposed revised NYISO OATT Section 5.  These \nNYPSC-approved delivery rates have evolved significantly through many NYPSC proceedings \nthat have addressed many cost allocation and rate design issues.  The delivery rates applicable to \n \n50  \nId. at 17-18. \n51  \nId. at 21-22."},{"page":23,"startToken":10224,"endToken":10795,"text":"November 16, 2026 \nPage 23 \n \n \ndelivery service allocate costs across many classes of customers.  Among other things, the \nNYPSC-established delivery rates provide for revenue neutrality and are specifically designed to \navoid cost shifting among customer classes that would deviate from the NYPSC’s determination \nof just and reasonable rates.  As the Panel Testimony explains, any changes in rates applicable to \none or a few classes in isolation from the others could potentially result in cost shifting and/or \nviolate revenue neutrality, potentially causing unjust and unreasonable rates.52  \n \nThe NYISO has explained in its FPA section 205 filing how the NYISO system uniquely \ndoes not provide for Non-Firm Point-to-Point or Non-Firm Services.  The NYISO is adopting Non-\nFirm Service that will be available to Large Load Customers under certain circumstances.  For \nsuch customers taking Non-Firm Service, the NYISO will dispatch the amount of withdrawal that \ncan be accommodated under economic security constrained dispatch.  There also may be instances \nof bulk system reliability concerns in which the NYISO, including at the request of the CTO or \nATO, may reduce the dispatched withdrawals of a Large Load in whole or in part.  For instance, a \nLarge Load that takes Interim Non-Firm Service prior to completion of bulk upgrades may be \ndispatched by the NYISO to withdraw only a portion of its requested withdrawal due to conditions \non the bulk system despite having requested firm retail service under the utility’s retail service \ntariff.  For example, if a Large Load requests firm service, and the CTO can provide firm service, \nbut the NYISO requires Non-Firm Service pending new capacity additions because the Large Load \nfails a Resource Adequacy Screen, then the CTO may still be providing Firm Service on its system \nand treating the Large Load as a firm load so far as its system is concerned.  The NYISO would \nhave the ability to interrupt the load if the NYISO system was approaching resource deficiency, \nbut this has nothing to do with the CTO’s ability to provide Firm Service and the treatment of the \nLarge Load for purposes of providing service. \nAs another example, if a CTO can provide Firm Service to a Large Load, but an ATO \nrequires an upgrade before Firm Service is available, then the CTO is still going to provide Firm \nService on its system.  The pendency of the Firm Service awaiting another Transmission Owner’s \nnon-local upgrade may be completely unrelated to the manner in which the retail utility provides \nservice and plans its bulk or local system to be able to provide reliable service prospectively.  \nConsequently, the reason that Non-Firm Service is required is relevant to which Transmission \nOwners are providing Non-Firm Service.  It is not a one-size-fits-all dynamic.  \nThe NYISO worked diligently to define the terms of new Non-Firm Withdrawal Services.  \nUntil these terms were developed, it was not reasonable to establish new retail delivery rates for \nthese services.  The terms of this new service were evolving until very recently.  Moreover, as \ndiscussed in the Panel Testimony, changes in rates applicable to some retail service classifications \nin isolation from the establishment and updating of rates for other service classifications, a function \nthat has always been overseen by the NYPSC and still is, would create risks of undue cost shifts \nbetween Large Load and non-Large Load Customers.  The NYPSC commenced a proceeding in \nFebruary 2026 to consider changes in Large Load services and associated rates, terms and \n \n52  \nId. at 23-24."},{"page":24,"startToken":10795,"endToken":11415,"text":"November 16, 2026 \nPage 24 \n \n \nconditions.53  Any proposed changes to the rates paid by Large Loads should be considered in this \nbroader context before the Commission accepts or approves such changes.  \nUnder the NYISO’s proposal, the earliest that new Non-Firm Withdrawal Services would \nbe available for projects is after the first Cluster has proceeded under the proposed LLIP.  As filed, \nthe NYISO process would result in Facilities Study completion and security posting in or after \nJuly 2028.  This time frame should precede service to the new Large Loads.  In the meantime, the \nNYTOs have updated Section 5 of the NYISO OATT to better address Large Load delivery rates \nand to include the flexibility of the Large Load Customers to choose among the NYPSC service \nclassifications for which they are eligible that best meet their needs.  \nThe Commission’s acceptance of the NYTOs’ reliance on NYPSC rate proceedings and \ncross-references in the NYISO OATT represents cooperative federalism as envisioned by the \nCommission and the U.S. Supreme Court.  FERC has repeatedly deferred to the states’ respective \nrole pertaining to retail facilities used in “local distribution.”54  Thus, deferring to the NYPSC rate \nproceedings is consistent with the Commission’s recognition of enabling cooperative federalism \nas an objective of its regulation.55  Further, the U.S. Supreme Court has expressly recognized \ncooperative federalism as a guiding principle for FERC’s regulation.56 \nThe NYTOs respectfully urge the Commission to permit the NYTOs to work with the \nNYPSC in the first instance on any new rates that may be appropriate and then, if necessary, to \nmake appropriate filings with the Commission.  Subject to their jurisdictional reservations, the \nNYTOs request that the Commission accept the proposed changes to Section 5 to the extent they \nare subject to the Commission’s jurisdiction.   \n \n53   \nNYPSC Case No. 26-E-0045, Proceeding on Motion of the Commission to Address Interconnection Reforms \nfor Large Loads, Order Instituting Proceeding and Soliciting Comments (Feb. 12, 2026). \n54  \nSee Am. Elec. Power Serv. Corp., 153 FERC ¶ 61,167 at P 16 (2015) (FERC recognizing that section 201 of \nthe FPA demonstrates “the authority of the states over retail sales and facilities used in ‘local distribution’”); Bldg. for \nthe Future Through Elec. Reg’l Transmission Plan. & Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 at P 254 \n(2024) (FERC’s Order No. 1920 recognizing that it does not “regulate, aim at, or otherwise attempt to influence … \ndecisions related to the siting and construction transmission facilities … or any other matters reserved to states under \nFPA section 201”). \n55  \n Bldg. for the Future Through Elec. Reg’l Transmission Plan. & Cost Allocation, Order No. 1920-B, 191 \nFERC ¶ 61,026 at P 91 (2025) (FERC noting that the U.S. Supreme Court’s holding that a state’s “veto power” in the \nCommission’s regulation of demand response ensured “the Commission’s compliance with principles of cooperative \nfederalism”); Show Cause Order, 195 FERC ¶ 61,216 at P 76 (noting the Commission’s objective in this FPA section \n206 proceeding is “to respect the cooperative federalism approach established under the FPA”). \n56  \nNew York v. F.E.R.C., 535 U.S. 1, 28 (2002) (holding that “a federal order claiming jurisdiction over all retail \ntransmission would have even greater implications for the States’ regulation of retail sales—a state regulatory power \nrecognized by the same statutory provision that authorizes FERC’s transmission jurisdiction”); F.E.R.C. v. Elec. \nPower Supply Ass’n, 577 U.S. 260, 288 (2016) (holding that wholesale demand response “is a program of cooperative \nfederalism, in which the States retain the last word”); Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 151 (2016) \n(recognizing that “[s]tates may regulate within their assigned domain even when their laws incidentally affect areas \nwithin FERC’s domain”)."},{"page":25,"startToken":11415,"endToken":11932,"text":"November 16, 2026 \nPage 25 \n \n \n2. \nChanges to Section 5 of the NYISO OATT (Retail Access) \n     \nThe NYTOs do not propose new rates in Section 5 of the NYISO OATT.  Instead, the \nNYTOs’ rates continue the existing practice of referencing the applicable NYPSC-approved \ndelivery service classifications, as they may be amended or superseded from time to time.  The \nproposed revisions to Section 5 clarify that its terms apply to Large Loads and to Eligible \nCustomers serving Large Loads and reference currently applicable NYPSC-approved, or LIPA \nBoard of Trustees-approved, service classifications and delivery rates.57  Revisions to the \nPreamble clarify that Section 5 applies to all retail access service, delivery service unbundled \nfrom commodity supply, irrespective of whether the retail Large Load Customer takes \ncommodity supply from an ESCO or the Transmission Owner that is the franchise utility to serve \nthe Large Load Customer.58 \n \nMore specifically, revised Section 5.1.1 requires each retail access customer, including \nEligible Customers serving Large Loads, to pay the Retail Transmission Service Charge to the \nTransmission Owner that is the retail franchise utility authorized under state law to serve at retail \nin the service area in which the Large Load is located, consistent with the rates, terms, and \nconditions of that Transmission Owner’s retail tariff, as approved by the NYPSC and referenced \nin Sections 5.2 and 5.3.59  Revised Section 5.1.3 allows each Transmission Owner to collect the \nRetail Transmission Service Charge from customers that take service under its retail tariffs, \nincluding Eligible Customers serving Large Loads, and these retail tariffs are approved by the \nNYPSC or the LIPA Board of Trustees.60  \n \nRevised Section 5.2 now contains references to the current NYPSC tariffs and notes the \napplicability to Eligible Customers serving Large Loads under Attachment LL.61  Newly created \nSection 5.2.8 sets out the rates, terms, and conditions of service for Eligible Customers taking \nservice on behalf of Large Loads and lists the applicable service classifications for each \nTransmission Owner.62  Newly created Section 5.2.9 reserves each Transmission Owner’s right \nto modify its rates, terms, and conditions, subject to required filings under the New York Public \n \n57  \nPanel Testimony at 25.  Historically, Section 5 of the NYISO OATT has included language addressing \nLIPA’s service in support of retail choice programs, on an informational basis.  Consistent with that process, the \nNYTOs requested, and LIPA has provided, information on the service classifications within the LIPA Tariff for \nElectric Service which are applicable to large loads.  As a non-jurisdictional utility, the LIPA service classifications \nreferenced in the proposed changes to NYISO OATT, Section 5 are subject to review and approval by the LIPA’s \nBoard of Trustees under applicable state law.  Inclusion of the LIPA service classification references in NYISO OATT \nSection 5 is for informational purposes and shall in no way be considered to be a waiver of LIPA's non-jurisdictional \nstatus pursuant to Section 201(f) of the FPA, including with respect to the Commission's exercise of its FPA general \nratemaking authority. \n58  \nId. \n59  \nId. at 26.  \n60  \nId.   \n61  \nId.   \n62  \nId."},{"page":26,"startToken":11932,"endToken":12362,"text":"November 16, 2026 \nPage 26 \n \n \nService Law, the New York Public Authorities Law, or the FPA.63  Section 5.2.9 also requires \nEligible Customers both to satisfy certain interconnection requirements established in \nAttachments HH and LL and to execute the Transmission Service Agreement attached to the \nOATT.64   \n \nNewly created Section 5.3 references cost responsibilities for Large Loads as described in \nthe CRA in the NYISO OATT.65  Newly created Section 5.4.1 requires Transmission Owners to \napply revenue credits or adjustments to prevent double recovery of costs recovered under CRAs \nthrough FERC-jurisdictional wholesale transmission rates.66  Finally, newly created Section 5.4.2 \nrequires Transmission Owners to file an annual informational report with FERC and the NYPSC \nto identify CRA revenues received by upgrade(s) during the following year and demonstrate that \nappropriate revenue credits have been or will be applied.67 \n \nThe NYTOs also propose conforming changes to the definitions in Sections 1.18 and \n1.20 of the NYISO OATT to support the revised Section 5.  First, the NYTOs propose to add to \nSection 1.18 a new defined term, “Retail Transmission Service Charge,” meaning a charge \nincurred by a retail access customer, including a Large Load or an Eligible Customer on behalf \nof a Large Load, for Transmission Service and/or delivery service, as appropriate, pursuant to \nSection 5 of the NYISO OATT, as defined therein.  Second, the NYTOs propose to revise the \ndefinition of “Transmission Service Charge” (“TSC”) in Section 1.20 to clarify that, for the \navoidance of doubt, the TSC is separate and apart from the Retail Transmission Service Charge.  \nTogether, these changes distinguish the wholesale TSC from the retail delivery charges that all \nretail customers, including Eligible Customers serving Large Loads, pay under the NYPSC- or \nLIPA Board of Trustees-approved retail tariffs referenced in Section 5.  Finally, the NYTOs \npropose cross-references to Section 5 of the NYISO OATT in the pro forma TSA. \n \n3. \nRequest for Relief \n \nThe NYTOs respectfully urge the Commission: \n \n• To accept the proposed revisions to Section 5 of the NYISO OATT to update the NYPSC \nrate designations incorporated by reference and applicable to retail access delivery \nservice, including service for Large Loads, as amended from time to time;  \n \n• To provide the NYPSC time to work within its Large Load proceeding commenced in \nFebruary 2026, with a white paper including recommendations from DPS Staff due no \n \n63  \nPanel Testimony at 24.  \n64  \nId. at 26-27. \n65  \nId. at 27; see NYISO Companion Filing, proposed § 44.16.9 – Appendix 9.  \n66  \nPanel Testimony at 27.  \n67  \nId."},{"page":27,"startToken":12362,"endToken":12811,"text":"November 16, 2026 \nPage 27 \n \n \nlater than February 2027, to determine whether any of the Large Load embedded cost \ndelivery rates should be modified in the first instance;  \n \n• To provide the NYTOs time to consider and act on any such NYPSC determinations if \nchanges to the currently effective delivery rates are warranted and to make an amendment \nfiling under Section 205 of the FPA with this Commission if any is deemed necessary or \nappropriate.  In undertaking that review, the NYTOs will also consider whether relevant \nNYPSC determinations warrant changes to the default Network Upgrade cost allocation \nand recovery methodology proposed in the CRA and, where appropriate, may pursue \nsuch changes through a subsequent filing under Section 205; and \n \nThe NYTOs commit to make an informational or Section 205 filing with the Commission \nconcerning any changes in rates that would apply to Large Load Customers, depending on the \nrates established or approved by the NYPSC or any guidance the NYPSC provides.  The NYTOs \ncommit to make any necessary filing with the Commission before the Facilities Studies for Large \nLoad Customers in the first LLIP Cluster under the NYISO’s new rules are issued and intend to \nmake the filing at least 60 days before the proposed effective date of any new rates. \n \nF. \nOperating Terms Applicable to Non-Firm Transmission Withdrawal \nService and Paired or Behind-the-Meter Generation Supplies \nThe NYTOs propose revisions to the NYISO’s proposed Attachment LL to establish \noperating requirements that apply to Large Loads interconnected under the LLIP, including Large \nLoads that take Non-Firm Transmission Withdrawal Service at a level below their maximum \npotential withdrawal and Large Loads paired with Co-Located or Partner Resources.  The NYISO \nsection 205 filing establishes how Non-Firm Transmission Withdrawal Service is studied, \nscheduled, and dispatched in the NYISO-administered markets.  It does not, however, fully address \nthe operating authority the NYTOs need to maintain bulk and local system reliability, including \non non-Bulk Electric System facilities and in conditions outside the NYISO’s operational visibility \nor direct control.  The proposed revisions fill that gap.  They complement the NYISO section 205 \nfiling and do not displace the NYISO’s scheduling and dispatch authority under the NYISO \nServices Tariff. \nFirst, the NYTOs propose to limit the circumstances in which Non-Firm Transmission \nWithdrawal Service may be offered.  Under proposed Section 44.8.2.4.5, Non-Firm Transmission \nWithdrawal Service may be offered only where thermal transmission constraints on Business \nManagement System-secured facilities under N-1 and N-1-1 conditions, and/or resource adequacy \nviolations, prevent the offering of Firm Transmission Withdrawal Service.  In order to maintain \nreliability, Non-Firm Service may not be used to mitigate voltage, stability, oscillatory stability, \nshort-circuit, cascading, or other non-thermal reliability concerns, and may not rely on a Special"},{"page":28,"startToken":12811,"endToken":13324,"text":"November 16, 2026 \nPage 28 \n \n \nProtection System or Remedial Action Scheme.68  This limitation ensures that Non-Firm Service \nis used only for constraints that economic scheduling and dispatch can reliably manage. \nSecond, the NYTOs propose new Section 44.14.3.5, which sets out the operating \nrequirements that apply to each Large Load from initial energization through disconnection, under \nnormal, abnormal, and emergency conditions, whether the Large Load takes Firm Transmission \nWithdrawal Service, Non-Firm Transmission Withdrawal Service, or both.69  The NYTOs also \npropose a new defined term, “Large Load Operating Action,” to describe the actions a \nTransmission Owner may take under that section.  Section 44.14.3.5 confirms that nothing in \nAttachment LL or the NYISO Services Tariff limits a Transmission Owner’s retained authority to \naddress bulk and local system reliability.  It also requires each CTO to set out in its procedures the \napplicable communications requirements, operator authority, curtailment and restoration \nprocedures, loss-of-telemetry and loss-of-communications actions, and performance enforcement \nmeasures.70 \nUnder proposed Section 44.14.3.5.2, under normal conditions the NYISO will continue to \nschedule and dispatch economically a Large Load’s Non-Firm Transmission Withdrawal Service.  \nUnder abnormal conditions, a Transmission Owner may request that the NYISO reduce the \ndispatch of a Large Load’s Non-Firm withdrawals using the NYISO’s existing Out-of-Merit and \nDay-Ahead Reliability Unit procedures, in the same manner that Transmission Owners request \nsuch actions for Generators.  A CTO may directly order a Large Load to ramp down or curtail its \nNon-Firm withdrawals only if a NYISO-implemented reduction cannot be achieved in time, or if \neconomic dispatch does not reduce withdrawals enough, to address an actual or imminent \nreliability condition.  In that case, the Large Load must comply within ten (10) minutes, the CTO \nmust notify the NYISO immediately, and the order must be limited in extent and duration to what \nis reasonably necessary.71 \nProposed Sections 44.14.3.2 and 44.14.3.5.3 provide that the CTO or, where the Franchise \nUtility is not the CTO, the Franchise Utility may disconnect a Large Load in whole or in part where \nnecessary to maintain or restore bulk or local system reliability.  The NYTOs also propose new \ndefined terms for “Franchise Utility” and “Retail Tariff” to reflect that retail service to a Large \nLoad may be provided by an entity other than the CTO.72  Disconnections must be coordinated in \nadvance with the NYISO and the Franchise Utility for non-urgent situations, such as maintenance \noutages, and in all other cases must be reported as soon as practicable.  Each disconnection must \nfollow defined communication protocols.  If a CTO determines, consistent with Good Utility \nPractice, that a requested disconnection would create or worsen a reliability problem, it may defer \nor modify the request only to the extent necessary while the NYISO and the affected Transmission \n \n68  \nSee Attachment A, § 44.8.2.4.5.   \n69  \nSee Attachment A, § 44.14.3.5.   \n70  \nSee Attachment A, § 44.14.3.5.1(ii).  \n71  \nSee Attachment A, § 44.14.3.5.2(iv).  \n72  \nSee Attachment A, § 44.1."},{"page":29,"startToken":13324,"endToken":13875,"text":"November 16, 2026 \nPage 29 \n \n \nOwners coordinate an alternative.  A disconnection directed by the NYISO in an Emergency State \nmust still be implemented unless it would endanger persons or equipment. \nThe proposed revisions also:  (i) set out the actions to be taken upon loss of telemetry or \ncommunications (Section 44.14.3.5.4); (ii) state each Large Load’s obligations, including \ncompliance with dispatch and operator instructions, maintaining a 24-hour operating contact, \nobserving ramp and step limits, and providing timely notice of unplanned changes in withdrawal, \nincluding transfers to on-site generation (Section 44.14.3.5.5); (iii) require restoration to be \ncoordinated with the CTO and, for Non-Firm Service, to be consistent with NYISO dispatch \n(Section 44.14.3.5.6); (iv) provide for performance enforcement, cost reimbursement, and possible \nreview of repeated non-compliance through a Load Modification Request (Section 44.14.3.5.7); \n(v) preserve a Franchise Utility’s rights under its Retail Tariff (Section 44.14.3.5.8); (vi) establish \na process for Transmission Owners and Franchise Utilities to ask the NYISO to act on a Large \nLoad that is not meeting applicable performance requirements, including ramp rate requirements, \nand allow the CTO to order a Large Load to hold, limit, or ramp its withdrawals when ramp or \nstep limits are exceeded or reliability is threatened (Section 44.14.3.5.9); and (vii) allow a \nTransmission Owner to ask the NYISO to model local transmission constraints, including \nconstraints on non-Bulk Electric System facilities, in its scheduling and dispatch (Section \n44.14.3.5.10). \nThe NYTOs also propose conforming changes.  Section 44.14.1 is revised to cross-\nreference the new operating requirements in the interconnection agreement provisions.  Section \n44.8.3.3 is revised to clarify that the normal operating procedures that may allow a Large Load to \nenter service before Network Upgrades are complete include the Large Load Operating Actions, \nand that the Large Load must comply with any interim operating limitations set by the NYISO, \nthe CTO, or the ATO as a condition of entering service.  In addition, Section 44.8.3.1.1 is revised \nto clarify that the withdrawal of Energy by a retail load in the Long Island Transmission District \nremains subject to the LIPA Tariff for Electric Service.  Non-Firm Transmission Withdrawal \nService will not be available to Large Loads taking service under that tariff unless and until the \ntariff is amended under applicable law.73 \nThe proposed operating provisions are just and reasonable and not unduly discriminatory \nor preferential.  Large Loads that take less-than-firm transmission service, or that rely on paired or \nbehind-the-meter supply, can change their withdrawals quickly and in large amounts.  Those \nchanges can affect transmission facilities that the NYISO does not monitor or control.  The \nproposed provisions give the NYTOs clear, transparent, and limited authority to manage those \neffects, consistent with their reliability obligations under North American Electric Reliability \nCorporation, Northeast Power Coordinating Council, Inc., and New York State Reliability \nCouncil, L.L.C. reliability standards.  The provisions rely on the NYISO’s market procedures \nwherever practicable, apply on the same terms to Large Loads taking Firm and Non-Firm Service, \nand give Eligible Customers clear notice, before they interconnect, of the operating conditions that \napply to their service. \n \n73  \nSee Attachment A, § 44.8.3.1.1."},{"page":30,"startToken":13875,"endToken":14428,"text":"November 16, 2026 \nPage 30 \n \n \nG. \nInterconnection Study Provisions and Pro Forma Facilities Study and \nInterconnection Agreements \nIn its filing under section 205, the NYISO proposes to retain the existing structure of the \nFacilities Study for new Firm Withdrawal Service and Non-Firm Withdrawal Service.  \nSpecifically, the Facilities Study will remain a bilateral study outside the NYISO’s study \nprocedures, performed under separate two-party agreements between the Large Load Customer \nand the CTO and, as needed, each ATO.  The NYISO will not be a party to the Facilities Study.  \nFurther, under the NYISO’s proposal, the NYTOs will continue to be responsible for determining \nthe cost allocation of Network Upgrades identified through the study process.  In doing so, the \nNYTOs may use the impact allocation findings developed in the NYISO’s studies to determine \nthe appropriate cost allocation for Network Upgrades during the Facilities Study. \nThe NYTOs also propose two definitional changes to Section 44.1 of Attachment LL to \nsupport the Facilities Study and the related agreements.  First, the definition of “Connecting \nTransmission Owner” is revised to make clear that the CTO includes a Franchise Utility that meets \nthe definition’s ownership and Transmission Service criteria.  Second, the NYTOs propose a new \ndefined term, “Large Load Customer,” meaning the Eligible Customer acting as agent for the Large \nLoad, or the Large Load customer itself, that is responsible for the Large Load Project under \nAttachment LL, including for purposes of the Facilities Study, the posting of security, and the \ninterconnection and construction agreements.  Because an Eligible Customer may act as agent for \na Large Load, the new term identifies the entity that is contractually and financially responsible \nfor the project, so that the Transmission Owners can tender study, cost recovery, security, and \ninterconnection agreements to that entity.74 \nBecause the NYISO section 205 filing leaves the Facilities Study as a bilateral process \noutside the NYISO’s study procedures, the NYTOs are proposing, as part of this filing, a pro forma \nFacilities Study Agreement to govern that process.  The pro forma Facilities Study Agreement \nmay be used by each Transmission Owner acting as the CTO or an ATO, and provides a uniform \nframework for the Facilities Study performed in two parts:  Part 1, which addresses Transmission \nOwner Attachment Facilities and local Network Upgrades and proceeds in parallel with the \nNYISO’s Assessment of Load Integration (“ALI”), and, as needed, Part 2, which addresses non-\nlocal Network Upgrades and alignment with the ALI results once the NYISO provides them.  \nUnder Section 44.8.2.4.1 of Attachment LL of the NYISO OATT, the NYISO is responsible for \nidentifying bulk system violations associated with each LLIP Cluster and for each violation to \nwhich more than one Large Load contributes, each Large Load’s contribution to the violation.  \nEach CTO and ATO shall determine violations on non-bulk system facilities and each Large \nLoad’s contribution to each violation.  Each CTO and ATO shall identify upgrades to address all \nsuch violations identified by the NYISO or the CTO or ATO itself and provide non-binding cost \nestimates and estimates of time to construct the upgrades and each CTO or ATO shall identify and \nestimate the cost of Attachment Facilities and Upgrades and estimates of the time to construct.  \nSuch cost estimates shall include the cost of the equipment, engineering, procurement, and \n \n74  \nSee Attachment A, § 44.1."},{"page":31,"startToken":14428,"endToken":15006,"text":"November 16, 2026 \nPage 31 \n \n \nconstruction work (including overheads) for the Attachment Facilities and Network Upgrades \nneeded to implement the conclusions of the ALI.  Because the Facilities Study proceeds in parallel \nwith the ALI, the pro forma Facilities Study Agreement permits the study to be updated, at the \nLarge Load Customer’s expense and with a commensurate schedule extension, to incorporate \nadditional Network Upgrades and Attachment Facilities identified as the ALI progresses. \nAmong other things, the pro forma Facilities Study Agreement:  (i) establishes the scope \nof the Facilities Study and the data the Large Load Customer must provide, and confirms that the \nstudy is for planning and estimation purposes only and does not reserve capacity, queue position, \nor priority; (ii) requires the Large Load Customer to post a fixed Study Deposit based on the size \nof the Large Load Project ($300,000 for projects of 50 MW to 199 MW, $350,000 for projects of \n200 MW to 499 MW, and $400,000 for projects of 500 MW and above) within ten (10) business \ndays of execution, subject to withdrawal of the project without a cure period if the deposit is not \ntimely posted, and to pay the Transmission Owner’s actual, documented, and reasonably incurred \nstudy costs, with notice if costs are expected to exceed the Study Deposit by more than 30%; (iii) \nprovides that the Transmission Owner will use reasonable efforts to complete the Facilities Study \nwithin twelve (12) months (six (6) months for Attachment Facilities and local Network Upgrades \nand six (6) months for non-local Network Upgrades), beginning on the later of receipt of the Study \nDeposit or a complete study data package; (iv) sets out a process for a draft report, a results \nmeeting, Large Load Customer comments for the Transmission Owner’s consideration, and \nissuance of a final report; (v) provides for refunds of any excess deposit and the resolution of \ndisputed invoices; (vi) permits changes required by changes in Good Utility Practice, Applicable \nLaws and Regulations, Transmission Owner procedures and standards, or Governmental Authority \ndirectives; (vii) permits termination for, among other things, the Large Load Customer’s failure to \npay, to provide required information, or to post the security required under Attachment LL based \non the Facilities Study; and (viii) makes clear that it is an agreement to perform a study only, with \nany engineering, procurement, construction, or interconnection to be governed by separate \nagreements, which may include a Security Agreement, a transmission service agreement, a cost \nrecovery agreement, an engineering and procurement agreement, and/or an interconnection \nagreement.  \nThe NYTOs also propose conforming revisions to Attachment LL to integrate the Facilities \nStudy Agreement into the NYISO’s study timeline.  Under revised Section 44.12.1.2, the CTO and \neach ATO will tender a Facilities Study Agreement in the form set forth in Appendix 8 of \nAttachment LL to the Eligible Customer acting as agent for the Large Load, or to the Large Load \nCustomer itself.  In the Facilities Study Agreement, the Large Load Customer agrees to reimburse \nthe Transmission Owner(s) for performing the Facilities Study and to provide the study deposit \neach Transmission Owner requires.  The Large Load Customer must execute a Facilities Study \nAgreement with each applicable Transmission Owner and return it within ten (10) calendar days \nof the Transmission Owner’s tender, and must pay the study deposit required by each applicable \nTransmission Owner within ten (10) business days after execution of the agreement.75 \n \n75  \nSee Attachment A, § 44.12.1.2."},{"page":32,"startToken":15006,"endToken":15589,"text":"November 16, 2026 \nPage 32 \n \n \nIf the Large Load Customer fails to timely execute and return the agreement or to timely \npay the study deposit, the applicable Transmission Owner will notify the NYISO, and the NYISO \nwill withdraw the Large Load Project from the Load Queue and from the Group for the ALI and \nFacilities Study pursuant to Section 44.7.3, without a withdrawal cure period.  Section 44.7.3.1 is \nrevised to confirm that the general fifteen (15) Business Day cure period does not extend these \ndeadlines.  Section 44.10.4.4 is revised to provide for withdrawal where the Large Load Customer \nfails to satisfy these Transmission Owner requirements, and to require the Transmission Owner to \nnotify the NYISO in writing within [two (2)] Business Days of the failure.76 \nIn addition, Section 44.6.8 is revised to confirm that the information the NYISO, a CTO, \nor an ATO may request from an Eligible Customer includes information needed to perform the \nFacilities Study, which the Eligible Customer must submit within five (5) business days of the \nrequest.  Where a CTO or ATO requested the information and the Eligible Customer fails to \nprovide it on time, the Transmission Owner may notify the NYISO in writing, identifying the \nrequest, the information not provided, and any resulting delay to the study of other Large Load \nProjects in the Group.  The NYISO will then, within five (5) business days, confirm the failure, \ndeem the Large Load Integration Request withdrawn, and remove the Large Load Project from the \nGroup.  Together, these provisions keep a Large Load Project that does not timely commit to the \nFacilities Study from delaying the study of other projects in the same Group. \nFor each Upgrade associated with a violation to which more than one Large Load in an \nLLIP cluster of projects (a group of projects analyzed together under the LLIP or an “LLIP \nCluster”) contributes, the applicable Transmission Owner shall use the contribution factors for \n[BES] violations the NYISO identified in the ALI and the contribution factors the Transmission \nOwner itself determined for non-BES violations in determining allocation of upgrade costs on an \nupgrade-specific and Large Load-specific basis.  A pro forma Facilities Study Agreement will \nprovide Eligible Customers with transparency and consistency across the NYTOs’ service \nterritories, ensure that the costs of Network Upgrades are allocated in a manner consistent with \ncost causation principles, and coordinate with the NYISO’s study process so that Eligible \nCustomers can proceed to security posting (under a Security Agreement discussed above) and \nexecution of the Interconnection Agreement in a timely manner.  \nFollowing completion of the Facilities Study, the NYISO section 205 filing provides that \nthe Eligible Customer may elect to proceed with the interconnection of its Large Load Project by:  \n(i) entering into an interconnection agreement with the CTO to whose system the Eligible \nCustomer proposes to interconnect, and (ii) as applicable, entering into construction agreement(s) \nfor Network Upgrades with any ATO(s) or Affected System Operator(s) on whose system a \nNetwork Upgrade is required in connection with the Large Load Project.77  The NYTOs propose \nto revise Section 44.14.1 to provide that the interconnection agreement will be in the form set forth \nin Appendix 11 of Attachment LL, and that these agreements must identify any required \nAttachment Facilities and Network Upgrades and specify the Large Load Project’s cost \n \n76  \nSee Attachment A, § 44.10.4.4. \n77  \nSee NYISO Companion Filing, proposed OATT Section 44.14.1."},{"page":33,"startToken":15589,"endToken":16135,"text":"November 16, 2026 \nPage 33 \n \n \nresponsibility for those facilities consistent with the terms of the applicable Transmission Owner’s \nCRA and Security Agreement in the forms set forth in Appendices 9 and 10 of Attachment LL, \nrespectively.78  Conforming revisions to Sections 44.2.2 and 44.12.1.8 likewise reference these \npro forma forms, and new Sections 44.16.8 through 44.16.11 add the pro forma Facilities Study \nAgreement, CRA, Security Agreement, and pro forma Large Load Interconnection Agreement \n(“Interconnection Agreement”) as Appendices 8 through 11 to Attachment LL.79  The NYISO does \nnot intend to be a signatory to the interconnection agreement. \nThe NYISO section 205 filing requires the Eligible Customer and the CTO to enter into an \ninterconnection agreement.  The NYTOs are proposing, as part of this filing, a pro forma \nInterconnection Agreement to govern the interconnection of Large Load Projects following the \nFacilities Study because it implicates the costs the NYTOs are entitled to recover pursuant to their \nreserved rights under the NYISO-TO Agreement and directly affects retail access.  The pro forma \nInterconnection Agreement is a two-party agreement between the Transmission Owner and the \nLarge Load Customer, which must be the same legal entity that executes the pro forma CRA and \nthe separate pro forma Large Load Security Agreement, and it operates together with those \nagreements as Related Agreements. \nAmong other things, the pro forma Interconnection Agreement:  (i) conditions construction \nand interconnection activities on completion of the System Impact Study and Facilities Study and \nother required engineering, design and special studies, execution of the CRA, the Large Load \nSecurity Agreement, any related construction or cost reimbursement agreements, and any required \ntransmission service agreement, receipt of required deposits and advance payments, receipt of all \nrequired regulatory approvals, and completion of the initial operating documents; (ii) provides load \ninterconnection service at the Point of Interconnection up to a Maximum Load Facility Peak \nDemand that may not exceed the amount studied in the System Impact Study and Facilities Study, \nand requires additional study and Transmission Owner approval before any Material Modification; \n(iii) requires the Large Load Customer to provide a monthly Load Ramp Projection and to update \nit every five years within limits, and sets out mechanisms to reduce interconnection rights where \nthe load fails to meet a Minimum Committed Load and to address Exceedance Events in which \nthe load exceeds its studied load limits; (iv) identifies the Attachment Facilities and Network \nUpgrades determined in the Facilities Study and addresses their engineering, procurement, and \nconstruction; (v) provides that the Large Load Customer’s responsibility for, and the recovery of, \nthe costs of the Network Upgrades and the Transmission Owner Attachment Facilities will be \ngoverned exclusively by the CRA, and that the posting and maintenance of security will be \ngoverned exclusively by the Large Load Security Agreement; (vi) establishes conditions to \nenergization and Permission to Operate, together with operational, metering, telemetry, insurance \nand cyber-security requirements and the Transmission Owner’s rights to interrupt or disconnect \nservice for safety, reliability, and emergencies; (vii) establishes an initial term of fifteen (15) years \n(or, if longer, the term of the CRA) and provides that early termination by the Large Load \nCustomer triggers the Net Present Value Residual Charge under the CRA; and (viii) makes clear \n \n78  \nId.  \n79  \nId."},{"page":34,"startToken":16135,"endToken":16616,"text":"November 16, 2026 \nPage 34 \n \n \nthat it does not provide Transmission Service or the sale of energy, which remain subject to the \napplicable Tariff and the Transmission Owner’s retail tariff. \nThe proposed pro forma Interconnection Agreement provides Large Load Customers \ntransparency and consistency to the extent of interconnection terms and conditions common to the \nNYTOs.  Because the Interconnection Agreement ties service levels to studied load and defers \nNetwork Upgrade and Transmission Owner Attachment Facility cost responsibility and security \nto the CRA and Large Load Security Agreement, it also protects against the risk of shifting costs \nto other transmission customers that the Commission identified in the Show Cause Order.  \nIV. \nEFFECTIVE DATE AND REQUESTS FOR WAIVER \nThe NYISO (on the NYTOs’ behalf) is submitting the enclosed Tariff revisions in eTariff \nformat in accordance with the requirements of Order No. 714 and a requested effective date of \nFebruary 1, 2027, though many tariff sheets apply to only those customers and activities under the \nNYISO’s new LLIP and will not affect prior and pending interconnection processes.80  \nThe NYTOs request an effective date for the revisions to Attachment LL and Attachment \nB of Section 8 of the NYISO OATT of February 1, 2027, as consistent with the NYISO section \n205 Filing.  \nThe NYTOs request an effective date for the amendments to Section 5 of the NYISO \nOATT of February 1, 2027, while recognizing that the first LLIP Cluster under the NYISO’s new \nrules contained in Attachment LL will not complete Facilities Studies until Q3 2028.  Accordingly, \nthe rates, terms and conditions of Section 5 will not apply to new Large Loads going through the \nfirst LLIP Cluster applying the new rules until some time after Q3 2028. \nThe NYTOs request an effective date for the Pro Forma Facilities Study Agreement, \napplicable to the first Cluster under the NYISO’s new LLIP, of February 1, 2027.   \nThe NYTOs request an effective date for the Pro Forma Large Load Security Agreement, \nPro Forma Interconnection Agreement and Pro Forma Large Load Cost Recovery Agreement of \nMay 1, 2028, a date at least 60 days in advance of completion of the first Facilities Study under \nthe NYISO’s new LLIP and to allow the NYPSC time to advance its ongoing proceeding on Large \nLoads so that the NYTOs may consider how best to try to satisfy both the NYPSC and this \nCommission with respect to the content of those pro forma agreements.    \nTo the extent that any of these effective dates are more than 120 days in the future, the \nNYTOs seek waiver, for good cause, of the requirement in section 35.3(a)(1) of the Commission’s \nregulations that rate schedules be filed no more than 120 days prior to the date on which service is \nto commence.   \n \n80  \nElec. Tariff Filings, Order No. 714, 124 FERC ¶ 61,270 (2008), clarified, Order No. 714-A, 147 FERC ¶ \n61,115 (2014)."},{"page":35,"startToken":16616,"endToken":16901,"text":"November 16, 2026 \nPage 35 \n \n \nFinally, the NYTOs request waiver of any other applicable requirement of 18 C.F.R. Part \n35 that is found not to be completely satisfied by this filing. \nV. \nCOMMUNICATIONS \nAll communications and correspondence regarding this filing should be forwarded to the \nfollowing individuals, whose names should be placed on the Commission’s service list:81 \nWilliam R. Derasmo \nMiles H. Kiger  \nAntonia M. Douglas \nBenjamin L. Duwve \nTROUTMAN PEPPER LOCKE LLP \n401 9th Street, N.W., Suite 1000 \nWashington, D.C. 20004 \n(202) 274-2886 \nwilliam.derasmo@troutman.com \nmiles.kiger@troutman.com \nantonia.douglas@troutman.com \nbenjamin.duwve@troutman.com \n \nMarina Chu \nRegulatory Attorney – Regulatory Affairs \nCentral Hudson Gas & Electric Corporation \n284 South Avenue \nPoughkeepsie, NY 12601 \nmchu@cenhud.com \n \nPhillip D. Demanchick Jr. \nSenior Counsel \nNew York State Electric & Gas Corporation \nRochester Gas and Electric Corporation \n180 South Clinton Avenue \nRochester, NY 14604 \nphillip.demanchick@avangrid.com \n \nChristopher J. Novak \nSenior Counsel \nNational Grid USA \n170 Data Drive \nWaltham, MA 02451 \nchris.novak@nationalgrid.com \n \n \nSusan J. Kimball \nAssociate Counsel \nJoshua A. Kirstein \nSenior Attorney \nConsolidated Edison Co. of New York, Inc. \nOrange and Rockland Utilities, Inc. \n4 Irving Place \nNew York, NY 10003 \nkimballs@coned.com \nkirsteinj@coned.com \nVI. \nCONTENTS OF THE FILING \nIn addition to this transmittal letter, this filing includes the following components: \n1. Attachments A (clean) and B (marked): Tariff amendments to new Attachment LL of the \nOATT.  Attachment LL is being contemporaneously filed by the NYISO, and the NYTOs \n \n81  \nThe NYTOs respectfully request waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two individuals to \nbe designated for service on the official service list in this proceeding."},{"page":36,"startToken":16901,"endToken":17168,"text":"November 16, 2026 \nPage 36 \n \n \nare sponsoring the following revisions to Attachment LL:  Section 44.1; Sections 44.2.2, \n44.6.8, 44.7.3.1, 44.8.2.4.5, 44.8.3.1.1, 44.8.3.3, 44.10.4.4, 44.12.1.2, 44.12.1.8, 44.14.1, \nand 44.14.3.2; new Section 44.14.3.5; and new Sections 44.16.8 through 44.16.11 \n(Appendices 8 through 11 to Attachment LL); \n2. Attachments C (clean) and D (marked): Tariff amendments revising Section 5 of the \nOATT, the definitions in Sections 1.18 and 1.20 of the OATT, and Attachment B of Section \n8 of the OATT; \n3. Attachment E: Pro Forma Large Load Cost Recovery Agreement; \n4. Attachment F: Pro Forma Large Load Security Agreement; \n5. Attachment G: Pro Forma Large Load Facilities Study Agreement; \n6. Attachment H: Pro Forma Large Load Interconnection Agreement; and \n7. Attachment I: Panel Testimony and exhibit of Brian McNierney, Carol Teixeira, Yan \nFlishenbaum, and Stacy Powers.  \n \nVII. \nSERVICE \nCopies of this filing have been served on all customers under the NYISO OATT and the \nNYPSC.82  This filing also will be posted in conformance with the Commission’s regulations.83 \nVIII. CONCLUSION \nWHEREFORE, for the foregoing reasons, the NYTOs respectfully request that the \nCommission accept as just and reasonable and not unduly discriminatory or preferential the Tariff \nprovisions and pro forma agreements proposed herein with the above-specified effective dates. \n[Signatures on following page] \n \n82  \n18 C.F.R. § 35.13(b)(3) (2025). \n83  \nId. § 35.2(e)."},{"page":37,"startToken":17168,"endToken":17268,"text":"November 16, 2026 \nPage 37 \n \n \nRespectfully submitted, \n \n \n \n \n \n \n \n/s/ William R. Derasmo  \nWilliam R. Derasmo \nMiles H. Kiger  \nAntonia M. Douglas \nBenjamin L. Duwve \nTROUTMAN PEPPER LOCKE LLP \n \nCounsel to the New York Transmission Owners \n \n \n \n \n \n        \n/s/ Marina Chu \nMarina Chu \nCentral \nHudson \nGas \n& \nElectric \nCorporation \n \n/s/ Phillip D. Demanchick Jr. \nPhillip D. Demanchick Jr. \nNew \nYork \nState \nElectric \n& \nGas \nCorporation \nRochester Gas and Electric Corporation \n \n/s/ Christopher J. Novak \nChristopher J. Novak \nNational Grid USA \n \n \n/s/ Susan J. Kimball \nSusan J. Kimball  \nJoshua A. Kirstein \nConsolidated Edison Co. of New York, Inc. \nOrange and Rockland Utilities, Inc. \n \n \nDated: November 16, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":900,"startToken":0,"endToken":549},{"p":2,"at":900,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":4,"endAt":1877,"startToken":549,"endToken":1659},{"p":4,"at":1877,"title":"II. BACKGROUND","method":"printed heading","endPage":4,"endAt":1894,"startToken":1659,"endToken":1661},{"p":4,"at":1894,"title":"A. The Large Load Show Cause Order","method":"printed heading","endPage":6,"endAt":1828,"startToken":1661,"endToken":2592},{"p":6,"at":1828,"title":"B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement","method":"printed heading","endPage":8,"endAt":221,"startToken":2592,"endToken":3301},{"p":8,"at":221,"title":"C. Stakeholder Processes","method":"printed heading","endPage":8,"endAt":1478,"startToken":3301,"endToken":3483},{"p":8,"at":1478,"title":"III. PROPOSED TARIFF REVISIONS AND PRO FORMA AGREEMENTS","method":"printed heading","endPage":10,"endAt":1476,"startToken":3483,"endToken":4296},{"p":10,"at":1476,"title":"A. Jurisdictional Status of this Filing","method":"printed heading","endPage":14,"endAt":1474,"startToken":4296,"endToken":6067},{"p":14,"at":1474,"title":"B. Network Upgrade Cost Recovery","method":"printed heading","endPage":19,"endAt":1359,"startToken":6067,"endToken":8665},{"p":19,"at":1359,"title":"C. Large Load Security Agreement","method":"printed heading","endPage":20,"endAt":1241,"startToken":8665,"endToken":9117},{"p":20,"at":1241,"title":"D. Revenue Crediting","method":"printed heading","endPage":20,"endAt":2217,"startToken":9117,"endToken":9272},{"p":20,"at":2217,"title":"E. Transmission Service Charges","method":"printed heading","endPage":26,"endAt":2053,"startToken":9272,"endToken":12257},{"p":26,"at":2053,"title":"Request for Relief","method":"printed heading","endPage":27,"endAt":1311,"startToken":12257,"endToken":12572},{"p":27,"at":1311,"title":"F. Operating Terms Applicable to Non-Firm Transmission Withdrawal","method":"printed heading","endPage":30,"endAt":32,"startToken":12572,"endToken":13880},{"p":30,"at":32,"title":"G. Interconnection Study Provisions and Pro Forma Facilities Study and","method":"printed heading","endPage":34,"endAt":747,"startToken":13880,"endToken":16243},{"p":34,"at":747,"title":"IV. EFFECTIVE DATE AND REQUESTS FOR WAIVER","method":"printed heading","endPage":35,"endAt":186,"startToken":16243,"endToken":16649},{"p":35,"at":186,"title":"V. COMMUNICATIONS","method":"printed heading","endPage":35,"endAt":1400,"startToken":16649,"endToken":16822},{"p":35,"at":1400,"title":"VI. CONTENTS OF THE FILING","method":"printed heading","endPage":36,"endAt":916,"startToken":16822,"endToken":17077},{"p":36,"at":916,"title":"VII. SERVICE","method":"printed heading","endPage":36,"endAt":1112,"startToken":17077,"endToken":17110},{"p":36,"at":1112,"title":"VIII. CONCLUSION","method":"printed heading","endPage":37,"endAt":732,"startToken":17110,"endToken":17268}]}