{"document":{"slug":"rec-20261116-5343-3","title":"Att-B_Large-Loads_Redlines","issued":"2026-11-16","accession":"20261116-5343","docket":"ER27-532-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"California Independent System Operator Corporation","kind":"attachment","file":"sources/filings/text/20261116-5343_003.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5343","tier":"record","parent":"rec-20261116-5343","sha256":"1d55486cbb3cc014df7aa3cabe1fb1176b7b35654855201c2120106cd6dab291","pages":19,"tokens":5170,"emptyPages":[],"textThemes":["study","colo","cost","flex"]},"pages":[{"page":1,"startToken":0,"endToken":16,"text":"Attachment B – Tariff Redlines \nLarge Loads Tariff Amendment  \nCalifornia Independent System Operator Corporation \nNovember 16, 2026"},{"page":2,"startToken":16,"endToken":229,"text":"Note: Grey highlighted text represents tariff revisions pending approval in docket number ER26-704. \n \nSection 4 \n \n* * * * * \n \nSection 4.19 \nLarge Loads \nConsistent with any Local Regulatory Authority requirements, Large Loads and Loads may participate in \nthe CAISO Markets using any model where they are capable of complying with the CAISO Tariff \nrequirements, including without limitation as Proxy Demand Resources, Reliability Demand Response \nResources, Participating Loads, Load-Serving Entities, and Non-Generator Resources. Large Loads may \nparticipate alone or in permissible aggregations, including with co-located Generating Units.  Large Loads \nand Loads participating in the CAISO Markets are eligible for all rights and subject to all obligations of the \nCAISO Tariff under those participation models.   Large Loads and Loads are eligible to provide, without \nlimitation, Demand Response Energy, Curtailable Demand, Resource Adequacy Capacity, and Ancillary \nServices consistent with their participation model and subject to the requirements of the CAISO Tariff. \n \n* * * * * \n \nSection 11 \n \n* * * * * \n \nSection 11.37 Large Load Requirements \nThe Scheduling Coordinator representing any Large Load pursuant to Section 25.7.3 will provide the \nCAISO Settlement Quality Meter Data on the gross Demand of the Large Load, excluding any offsetting \nEnergy, including from co-located or behind-the-meter generation.  The CAISO will charge the applicable \nScheduling Coordinator based on this Meter Data the hourly user rate for Regulation Down Reserve,"},{"page":3,"startToken":229,"endToken":538,"text":"Regulation Up Reserve, and Reliability Services Costs.  In calculating the rates for these charges, the \nCAISO will include all separately submitted volumes for Large Loads.   \n \n* * * * * \n \nSection 24 \n24. \nComprehensive Transmission Planning Process \n24.1 \nOverview \nThe CAISO will develop a comprehensive Transmission Plan and approve transmission solutions using \nthe Transmission Planning Process set forth in this Section 24.  For purposes of this Section 24, \ntransmission solutions include both entirely new transmission facilities and upgrades or additions to \nexisting transmission facilities that are proposed, considered, and/or specified in the comprehensive \nTransmission Plan during Phase 2 to meet an identified need determined by the CAISO.  The CAISO will \nconsider the use of alternative transmission technologies including dynamic line ratings, advanced power \nflow control devices, advanced conductors, and transmission switching when evaluating transmission \nsolutions for new regional transmission facilities, Large Loads, upgrades to existing transmission facilities, \nand Long-Term Regional Transmission Facilities.  Alternatives to transmission solutions are referred to as \nnon-transmission solutions.  Solutions to meet an identified need can be either transmission solutions or \nnon-transmission solutions.  The CAISO will analyze the need for transmission solutions in accordance \nwith the methodologies and criteria set forth in this Section 24, the Transmission Control Agreement, and \nthe applicable Business Practice Manuals.  The comprehensive Transmission Plan will identify Merchant \nTransmission Facilities meeting the requirements for inclusion in the Transmission Plan and transmission \nsolutions needed (1) to maintain System Reliability; (2) to satisfy the requirements of a Location \nConstrained Resource Interconnection Facility; (3) to maintain the simultaneous feasibility of allocated \nLong-Term CRRs; (4) as additional components or expansions to LGIP Network Upgrades are identified \npursuant to Section 24.4.6.5; (5) to meet state, municipal, county and federal policy requirements and \ndirectives, including renewable portfolio standards policies; and (6) to reduce congestion costs, \nproduction supply costs, transmission losses, or other electric supply costs resulting from improved"},{"page":4,"startToken":538,"endToken":861,"text":"access to cost-effective resources.   \nBeginning in 2027, the CAISO will transition to two complementary transmission planning cycles: (a) a \ncomprehensive transmission plan performed biennially (every two years) with the first biennial \ncomprehensive transmission plan to be issued in 2030; and (b) a Long-Term Regional Transmission Plan \nperformed every four years, with a plan first issued in 2030, and further described in Section 24.11.  \nAdditionally, the CAISO will perform reliability studies in each year a comprehensive Transmission Plan is \nnot issued to ensure continued reliability of the CAISO controlled grid and to comply with Applicable \nReliability Criteria, CAISO Planning Standards and state mandated resource adequacy study \nrequirements. This is further described in Section 24.3.3.1.  For purposes of this Section 24, when \nreferring to the comprehensive Transmission Planning Process, the term “the year X planning cycle” will \nrefer to the comprehensive Transmission Planning Process initiated during year X-2 to complete a \ncomprehensive Transmission Plan in year X.  For purposes of this Section 24, when referring to the Long-\nTerm Regional Transmission Planning process, the term “the year Y planning cycle” will refer to the Long-\nTerm Regional Transmission Planning process initiated during year Y-3 to complete a comprehensive \nLong-Term Plan in year Y. \n \n* * * * * \n \n24.3.1 Inputs to the Unified Planning Assumptions and Study Plan  \nThe CAISO will develop Unified Planning Assumptions and a Study Plan using information and data from \nthe approved Transmission Plans developed in the previous planning cycles.  The CAISO will consider \nthe following in the development of the Unified Planning Assumptions and Study Plan: \n(a) \nWECC base cases, as may be modified for the relevant planning horizon;  \n(b) \nTransmission upgrades and additions approved by the CAISO in past Transmission \nPlanning Process cycles, including upgrades and additions which the CAISO has \ndetermined address transmission needs in the comprehensive Transmission Plan \ndeveloped in the previous planning cycle; \n(c) \nLong-Term Regional Transmission Facilities approved by the CAISO in past Long-Term"},{"page":5,"startToken":861,"endToken":1123,"text":"Planning cycles; \n(d) \nCategory 2 policy-driven transmission upgrades and additions from a prior planning cycle \nas described in Section 24.4.6.6; \n(e) \nLocation Constrained Resource Interconnection Facilities conditionally approved under \nSection 24.4.6.3;  \n(f) \nNetwork Upgrades that were not otherwise included in the comprehensive Transmission \nPlan from the previous biennial cycle, and that meet the qualifying criteria described in \nSection 24.4.6.5; \n(g) \nOperational solutions validated by the CAISO in the Local Capacity Technical Study \nunder Section 40.3.1;  \n(h) \nPolicy requirements and directives, as appropriate, including programs initiated by state, \nfederal, municipal and county regulatory agencies;  \n(i) \nEnergy Resource Areas or similar resource areas identified by Local Regulatory \nAuthorities;  \n(j) \nDemand response programs that are proposed for inclusion in the base case or \nassumptions for the comprehensive Transmission Plan;  \n(k) \nAlternative transmission technologies in addition to generation and other non-\ntransmission alternatives that are proposed for inclusion in planning studies as \nalternatives to or that incorporate transmission additions or upgrades;  \n(l) \nBeginning with the 2011/2012 planning cycle, Economic Planning Study requests \nsubmitted in comments on the draft Unified Planning Assumptions and Study; \n(m) \nPlanned facilities in interconnected Balancing Authority Areas;  \n(n) \nThe most recent Annual Interregional Information provided by other Planning Regions;  \n(o) \nImport Capability expansion requests submitted in comments on the draft Unified \nPlanning Assumptions and Study; and \n(p) \nSubscriber Participating TO transmission facilities, and any generation facilities receiving \nSubscriber Rights and requesting to interconnect to the CAISO Controlled Grid over \nSubscriber Participating TO transmission facilities, that have met the following criteria:"},{"page":6,"startToken":1123,"endToken":1374,"text":"1. \nThe Applicant Participating Transmission Owner Agreement has been executed; \n2. \nThe generator interconnection agreement with the Subscriber is executed;  \n3. \nThe Subscriber Participating TO has provided written notice to the CAISO that \nConstruction Activities regarding the Subscriber Participating TO transmission \nfacilities have begun; and \n4. \nTransmission interconnection studies required by the interconnecting \nTransmission Owner(s) have begun. \n(q) \nPlanned and forecasted Large Loads and load growth generally, including: \n1. Transmission additions or upgrades planned pursuant to all Participating TO tariff \ninterconnection processes; \n2. Transmission additions or upgrades to support public policy requirements or \ndirectives; and \n3. The most recent Large Load data provided under Section 24.19.1. \n \n* * * * * \n \n24.19 \nLoad Considerations  \nThroughout the Transmission Planning Process, the CAISO will review transmission additions or \nupgrades proposed by the Participating TOs as transmission solutions for public policies selected for \nconsideration in the current planning cycle.  The Transmission Plan will identify any planned transmission \nadditions or upgrades for Large Loads or other load growth that indicate high operational risk or \nuncertainty based on NERC Reliability Standards.  The CAISO will review all other transmission additions \nor upgrades for Large Loads and other load growth on a monthly basis pursuant to Section 25.7. \n24.19.1  \nLarge Load Data \nThe Transmission Plan will include data specifically related to Large Loads, including: \n1. Aggregate amounts of proposed and completed Large Load additions on the CAISO \nControlled Grid by Transmission Zone; and \n2. Planned Network Upgrades and their estimated costs needed to accommodate Large Loads,"},{"page":7,"startToken":1374,"endToken":1636,"text":"identified by type of equipment and Network Upgrade. \n \n* * * * * \n \nSection 25 \n25. \nInterconnection of Generating Units, Large Loads, and Facilities  \n25.1 \nApplicability \nThis Section 25.1 applies to: \n(a) \neach new Generating Unit that seeks to interconnect to the CAISO Controlled Grid; \n(b) \neach existing Generating Unit connected to the CAISO Controlled Grid that will be \nmodified with a resulting increase in the total capability of the power plant; \n(c) \neach existing Generating Unit connected to the CAISO Controlled Grid that will be \nmodified without increasing the total capability of the power plant but has changed the \nelectrical characteristics of the power plant such that its re-energization may violate \nApplicable Reliability Criteria; \n(d) \neach existing Generating Unit connected to the CAISO Controlled Grid whose total \nGeneration was previously sold to a Participating TO or on-site customer End User but \nwhose Generation, or any portion thereof, will now be sold in the wholesale market, \nsubject to Section 25.1.2;  \n(e) \neach existing Generating Unit that is a Qualifying Facility and that is converting to a \nParticipating Generator without repowering or reconfiguring the existing Generating Unit, \nsubject to Section 25.1.2;  \n(f) \neach existing Generating Unit connected to the CAISO Controlled Grid that proposes to \nrepower its Generating Unit pursuant to Section 25.1.2; and \n(g) \nGenerating Units interconnecting to the CAISO Controlled Grid over a Subscriber \nParticipating TO transmission facilities using Subscriber Rights are required to apply for \nTP Deliverability under Section 25.1 once (1) the Subscriber Participating TO \ntransmission facilities have completed their transmission interconnection studies with all"},{"page":8,"startToken":1636,"endToken":1944,"text":"interconnecting Transmission Owner(s), (2) Subscriber(s) have executed the Generator \nInterconnection Agreement, (3) the Subscriber Participating TO has committed to \nproceed with Construction Activities regarding the Subscriber Participating TO \ntransmission facilities, and (4) the applicant provides a notice in writing to the applicable \ninterconnecting Transmission Owners that it is proceeding with Construction Activities. \nOnce these criteria have been completed, the Generating Unit must apply as follows: \n(1) each Generating Unit possessing Subscriber Rights and receiving \nDeliverability from TPP-approved Network Upgrades shall apply for TP \nDeliverability allocation through the submission of a Subscriber Participating TO-\nspecific deliverability allocation request and does not submit an Interconnection \nRequest under Section 25; \n(2) each Generating Unit that does not meet the criteria under Section 25.1(g)(1) \nshall be treated in accordance with Section 25.1(a).   \n25.1.1 Interconnection Request and Generating Unit Requirements  \nThe owner of a Generating Unit described in Section 25.1 (a), (b), (c), or (g), or its designee, shall be an \nInterconnection Customer required to submit an Interconnection Request and comply with Appendix KK \nunless the Generating Unit will not inject Energy onto the CAISO Controlled Grid and instead serve a co-\nlocated End User, as permitted by the Local Regulatory Authority.  Subject to the requirements of their \ntariff and the Local Regulatory Authority, the interconnecting Participating TO for any Generating Units \nsubject to this exemption will ensure the Generating Units have sufficient control technologies, tested and \nvalidated by the Participating TO, to ensure no material impact on the CAISO Controlled Grid.   \n \n* * * * * \n \n25.5 \nModifications to Generating Facilities  \nPursuant to the modification provisions of their GIAs, Generating Facilities that have achieved their \nCommercial Operation Date may make modifications to their Generating Facilities where the CAISO and \nthe Participating TO are notified at least ninety (90) calendar days in advance of commencement of work"},{"page":9,"startToken":1944,"endToken":2300,"text":"and sufficient information is provided such that the CAISO and the Participating TO(s) have determined \nthat Section 25.1 does not apply to the modification. \n25.5.1 \nPrior to making any modification after the Generating Facility’s Commercial Operation Date, including the \naddition of a co-located load or Large Load, the Generating Unit owner must first request that the CAISO \nevaluate whether Section 25.1 would apply to the modification. In response to the Generating Unit \nowner's request, the CAISO, in coordination with the affected Participating TO, will evaluate the proposed \nmodification. The CAISO may engage the services of the applicable Participating TO to assess the \nmodification.  The CAISO will inform the Generating Unit owner in writing whether how Section 25.1 \nwould apply to the modification and therefore be denied. Costs incurred by the Participating TO and the \nCAISO (if any) shall be borne by the party making the request under Section 25.5, and such costs shall \nbe included in any CAISO invoice for modification assessment activities. \nThe addition of a co-located load or Large Load will not necessarily affect the Qualifying Capacity, Net \nQualifying Capacity, Deliverability Status, or eligibility to provide Energy, Ancillary Services, or Resource \nAdequacy Capacity of a Generating Unit.  Any effect will be determined under the otherwise applicable \nCAISO Tariff, modification results, and Local Regulatory Authority requirements. \n \n* * * * * \n \n25.7 \nLarge Load Interconnections \nEnd Users, including Large Loads, interconnect to the CAISO Controlled Grid pursuant to Participating \nTO and retail tariffs in accordance with Local Regulatory Authority requirements. The CAISO will not \nconsider any Load a Large Load subject to the CAISO Tariff where the Load is operational or has a \ncomplete request with the Participating TO before February 16, 2027 unless and until the Load modifies \nor increases itself thereafter and would be a Large Load, as dictated by the Participating TO tariffs; or if \nthe Load elects to become a Large Load subject to the CAISO Tariff. \nThe CAISO will coordinate with the Participating TOs and any Affected System to account for Large Load \ninterconnections to the CAISO Controlled Grid in all Interconnection Studies. Consistent with the RIS,"},{"page":10,"startToken":2300,"endToken":2646,"text":"Participating TO tariffs, and Good Utility Practice, the CAISO and Participating TOs will identify Network \nUpgrades and Interconnection Facilities best reflecting the combined topology of Interconnection \nCustomer and Large Load interconnections.  On a monthly basis, the CAISO will review transmission \nadditions or upgrades planned by the Participating TOs to interconnect Loads and Large Loads pursuant \nto their Participating TO tariff processes.  The CAISO will identify any planned transmission additions or \nupgrades that indicate high operational risk or uncertainty based on NERC Reliability Standards.  \n25.7.1 Participating TO Requirements \nParticipating TOs will apprise the CAISO of Large Load interconnections through their inputs to the Base \nCase, Interconnection Studies, and Transmission Planning Process. Prior to the synchronization of any \nLarge Load to the CAISO Controlled Grid, the Participating TO will provide the following information for \nthe Large Load:  Load type, variable or flat load designation, expected hourly operating profile, points of \ninterconnection and withdrawal, MW capacity, minimum and maximum operating levels, expected CAISO \nmarket participation model (if any), curtailment and ramping capabilities, and behind-the-meter generation \ncapacity and characteristics (if any). The Participating TO will require each Large Load to have \ncontinuous dynamic disturbance recording data and storage on the high-side of the main power \ntransformer(s) or common point of connection(s) to determine the following electrical quantities for the \nLarge Load:  \n1.  \nPhase-to-neutral voltage for each phase.  \n2.  \nEach phase current and the residual or neutral current.  \n3.  \nReal power and reactive power flows expressed on a three-phase basis corresponding to \nall circuits where current measurements are required; and  \n4.  \nFrequency. \nThe Participating TO also must ensure it can disconnect or otherwise isolate the Large Load in the event \nof a Contingency, imminent or actual System Emergency, to maintain System Reliability. This Section \n25.7.1 and its subsections will not prevent the operation of a load shedding program or Remedial Action \nScheme directed or required by the CAISO or applicable Participating TO. Where such programs or \nschemes require disconnection or reduction of the Large Load, those requirements will supersede the \nride-through requirements of this Section."},{"page":11,"startToken":2646,"endToken":2956,"text":"25.7.1.1 Frequency Ride-Through Requirements \nThe Participating TO will require each Large Load to remain electrically connected to the CAISO \nControlled Grid and ride through system frequency disturbances as specified: \nFrequency (Hz) \nMinimum Ride-through Requirement \nf >61.8 \nMay trip \n61.2 < f ≤ 61.8 \n299 seconds \n58.8 ≤ f ≤ 61.2 \nContinuous operation \n57.0 ≤ f < 58.8 \n299 seconds \nf < 57.0 \nMay trip \n \nFrequency measurements used to determine compliance with this Section will be taken at the high-\nvoltage side of the Large Load's main power transformer. Frequency calculations will be based on \nmeasurements obtained over an appropriate time window for reliable frequency determination. \nInstantaneous or single-point frequency measurements will not be used to initiate frequency-based \nprotection or control actions. \n25.7.1.2 Voltage Ride-Through Requirements \nThe Participating TO will require each Large Load to remain electrically connected to the CAISO \nControlled Grid and ride through system voltage disturbances as specified: \nVoltage (per unit) \nMinimum Ride-through Requirement \nV > 1.2 \nMay trip \n1.1 < V ≤ 1.2  \n2.0 seconds \n0.9 ≤ V ≤ 1.1 \nContinuous operation \n0.7 ≤ V < 0.9 \n6.0 seconds \n0.5 ≤ V < 0.7 \n3.0 seconds \n0.25 ≤ V < 0.5 \n1.2 seconds \nV < 0.25 \n0.15 seconds \n \nFor purposes of this Section, the voltage base used for per-unit calculations will be the nominal phase-to-\nphase or phase-to-ground transmission system voltage, as applicable. Compliance with the voltage ride-\nthrough requirements will be evaluated using the maximum or minimum fundamental-frequency root-\nmean-square (RMS) voltage, measured phase-to-phase or phase-to-neutral at the high-voltage side of \nthe Large Load's main power transformer, as applicable. Voltage-based protection or control settings that \ninitiate instantaneous tripping based on voltage measurements filtered over periods shorter than one (1) \nelectrical cycle will not be permitted. \n25.7.1.3 Post-Fault Active Power Recovery Requirements"},{"page":12,"startToken":2956,"endToken":3315,"text":"The Participating TO will require each Large Load to restore its active power consumption following a \nsystem fault or voltage disturbance. Following a fault or voltage disturbance, the Large Load will recover \nto at least ninety percent (90%) of its pre-disturbance active power consumption within three (3) seconds \nafter the post-fault voltage at the point of interconnection recovers to 0.90 per unit or greater. Where a \nRemedial Action Scheme requires the disconnection or reduction of all or a portion of the Large Load \nfollowing a fault, the minimum required active power recovery will be ninety percent (90%) of the \nremaining pre-disturbance active power consumption after accounting for the load reduction required by \nthe Remedial Action Scheme. Compliance with this requirement will be evaluated based on the aggregate \nactive power consumed from the transmission system by the Large Load at the point of interconnection. \nFollowing the initial recovery, sustained or repeated reductions in active power consumption attributable \nto the disturbance will not be permitted. \n25.7.1.4 Ramp-Rate Limitations \nThe Participating TO will require each Large Load to limit changes in its active power consumption during \nnormal operating conditions such that the average active power ramp rate, measured at the point of \ninterconnection over a rolling ten (10)-minute interval, does not exceed twenty (20) megawatts per minute \n(MW/min).  The ramp-rate limitation will apply to both increases and decreases in active power \nconsumption during normal operation, including startup, shutdown, routine operational changes, and \nrestoration of load following outages. The ramp-rate limitation will not apply to automatic responses to \nsystem faults or disturbances that are required for equipment protection or compliance with this Section \n25.7.1.  \n25.7.2  Flexible Interim Load Interconnection (FILI)  \nThe CAISO will facilitate the following flexible Large Load interconnection service provided under \nParticipating TO tariffs: \n(a) \nFlexible Interim Load Interconnection: Curtailable, interim interconnection service for a \nLarge Load provided by the CAISO and Participating TO, enabling the Large Load to \ninterconnect prior to the completion of the Large Load’s Network Upgrades or \nInterconnection Facilities.  \nPrior to the energization of the Large Load, the CAISO, Participating TO, and Large Load or its authorized"},{"page":13,"startToken":3315,"endToken":3605,"text":"agent will execute an agreement describing the circumstances in which the Large Load receiving FILI \nmay be temporarily curtailed, and the mechanism used to perform the curtailment.  At a minimum, the \nagreement will specify: \n(a) \nThe circumstances, Contingencies, or operating conditions in which the Large Load \nwould be curtailed \n(b) \nThe mechanism used to perform the curtailment \n(c) \nThe entity responsible for performing the curtailment \n(d) \nThe notification method, response time, duration, restoration, testing, and verification \nrequirements \n(e) \nInterim operating limits both in and out of curtailable events \n(f) \nThe Network Upgrades or Interconnection Facilities required to conclude the FILI \nThe CAISO will post these agreements on the CAISO Website. The CAISO Base Case, Full Network \nModel, and Operating Procedures will account for such Large Loads as applicable.   \n25.7.3  Load Serving Entity Scheduling Coordinator Requirements \nThe Scheduling Coordinator representing the Load Serving Entity for the Large Load will include the \nLarge Load in its Bids, Scheduled Demand, and Meter Data, as applicable, for that area.  The Scheduling \nCoordinator also must provide the CAISO the following, specific to each Large Load it represents: \n1. \nDaily and hourly forecast data otherwise required for the CAISO Forecast of CAISO \nDemand;  \n2. \nAny real-time, material deviations from provided forecasts, including changes resulting \nfrom energization activities, material operational changes, curtailments, Outages, \nderates, operating limits, operating envelopes, or co-located generation impacts that \nmaterially affect expected Demand; \n3. \nOperational status and real-time consumption to the CAISO in accordance with the \nCAISO’s standards for direct telemetry and consistent with the requirement for telemetry \nset forth in Section 7.6.1. \nWithout limitation, the applicable Load Serving Entity, Utility Distribution Company, MSS Operator, Large \nLoad, and Scheduling Coordinator may satisfy the requirements of this Section through coordinated"},{"page":14,"startToken":3605,"endToken":3969,"text":"arrangements that clearly assign each CAISO Tariff obligation and avoid duplicative submissions. The \napplicable arrangement must identify the Scheduling Coordinator responsible for submitting Bids, \nScheduled Demand, Meter Data, forecasts, and real-time operational updates for the Large Load. The \nCAISO must verify the arrangement will comply with this Section before its use.  \n25.7.3.1 \nLarge Load Scheduling Coordinator Requirements \nConsistent with CAISO Tariff and Local Regulatory Authority requirements, Large Loads may participate \nin the CAISO Markets solely, or in aggregations with other resources, as their own Load Serving Entity, a \nNon-Generator Resource, or a Participating Load.  Such Large Loads may elect to comply with the \nrequirements of Section 25.7.3 and participate in the CAISO Markets through their own Scheduling \nCoordinator in lieu of their Load Serving Entity Scheduling Coordinator.  A Large Load participating as a \nProxy Demand Resource or Reliability Demand Response Resource will have the Load Serving Entity \nScheduling Coordinator comply with Section 25.7.3 and submit Scheduled Demand including the Large \nLoad, but may have the Demand Response Provider or other Scheduling Coordinator comply with \nSection 4.13. \nNothing in this Section 25 or the CAISO Tariff will affect the eligibility of an End-Use Customer to be \ntreated as a Direct Access End-User, consistent with Section 2.2 of the CAISO Tariff. \n25.7.4 Reliability Events \nAfter a disturbance or other reliability event involving a Large Load, any associated Interconnection \nCustomer, Scheduling Coordinator, and Participating TO must comply with any CAISO, Regional Entity, \nor Reliability Coordinator data request related to the event. \n25.7.5 Energy Storage and Large Loads \nLoads, Large Loads, and energy storage may be co-located. Consistent with Section 10.1.3.2, to avoid \nthe commingling of wholesale and retail withdrawals, Interconnection Customers must ensure loads and \nLarge Loads are metered separately and independently from any co-located energy storage participating \nin the CAISO Markets.  Loads and Large Loads nonetheless may net any withdrawals against non-\nparticipating generation and storage, as permitted by the Local Regulatory Authority.  Nothing in this \nSection will contradict the netting permitted by Section 10.1.3 of the CAISO Tariff. \n25.7.6 Co-located Generating Units and Large Loads"},{"page":15,"startToken":3969,"endToken":4284,"text":"The CAISO and Participating TOs will conduct all Interconnection Studies for Generating Units co-\nlocating with Large Loads to account for their net impact on the CAISO Controlled Grid, as requested by \nthe Interconnection Customer.  Interconnection Customers for such configurations may avail themselves \nof all rights and services in the RIS and CAISO Tariff.  The CAISO and Participating TO will produce \nInterconnection Study results reflecting the combined presence of the Generating Units and co-located \nLarge Loads. The Interconnection Service Capacity and Deliverability Status will reflect the combined \noperation established in the Interconnection Studies. The CAISO and Participating TO will memorialize \nthe combined operation in the GIA.  To be considered in the Cluster Study, the Interconnection Customer \nmust have submitted the request for the interconnection of the Large Load to the Participating TO \npursuant to its tariff by the close of the CAISO’s Cluster Application Window.  \nFor any conflict between the CAISO tariff and the Participating TO tariff pertaining to the interconnection \nof the Generating Unit, the CAISO tariff will apply.  For any conflict between the CAISO tariff and the \nParticipating TO tariff pertaining to the interconnection of the Large Load, the Participating TO tariff will \napply.  \nWithout limitation, Interconnection Customers with co-located Generating Units and Large Loads must \nmake all applicable Interconnection Study Deposits, Commercial Readiness Deposits, and GIA Deposits \nin the RIS and CAISO Tariff.  Network Upgrade and Interconnection Facility assignments and cost \nallocations pursuant to the RIS will assume they are for the Generating Facility unless the CAISO and \nParticipating TO agree that the Network Upgrade or Interconnection Facility is for the Large Load only.  \nNothing in the CAISO Tariff should be interpreted to contradict or exempt the Large Load from its cost \nresponsibility obligations pursuant to the Participating TO tariff.     \n \n* * * * * \n \nAppendix A \n \n- Flexible Interim Load Interconnection (FILI)  \nCurtailable, interim interconnection service for a Large Load provided by the CAISO and Participating TO,"},{"page":16,"startToken":4284,"endToken":4407,"text":"enabling the Large Load to interconnect prior to the completion of the Large Load’s Network Upgrades or \nInterconnection Facilities.  \n \n- Large Load \nAn End User located at a single site behind one or more points of interconnection to the CAISO \nControlled Grid, and that has a peak load of 50 MW or greater. The CAISO will not consider any Load a \nLarge Load subject to the CAISO Tariff where the Load is operational or has a complete request with the \nParticipating TO before February 16, 2027 unless and until the Load modifies or increases itself thereafter \nand would be a Large Load, as dictated by the Participating TO tariffs; or if the Load elects to become a \nLarge Load subject to the CAISO Tariff."},{"page":17,"startToken":4407,"endToken":4612,"text":"Appendix KK \n \n* * * * * \n \n2.4 \n Interconnection Service and Studies \n \n* * * * * \n \n2.4.4 \nLarge Loads \nEnd Users, including Large Loads, interconnect to the CAISO Controlled Grid pursuant to \nParticipating TO tariffs.  The CAISO will coordinate with the Participating TOs to account for \nLarge Load interconnections to the CAISO Controlled Grid in all Interconnection Studies. \nConsistent with this RIS, Participating TO tariffs, and Good Utility Practice, the CAISO and \nParticipating TOs will identify Network Upgrades and Interconnection Facilities best reflecting the \ncombined topology of Interconnection Customer and Large Load interconnections.  As described \nin Section 25.7 of the CAISO tariff, the CAISO and Participating TOs will conduct all \nInterconnection Studies for Generating Units co-locating with Large Loads to account for their net \nimpact on the CAISO Controlled Grid, as requested by the Interconnection Customer.  \nInterconnection Customers for such configurations may avail themselves of all rights and services \nin this RIS. For any conflict between the CAISO tariff and the Participating TO tariff pertaining to \nthe interconnection of the Generating Unit, the CAISO tariff will apply. For any conflict between \nthe CAISO tariff and the Participating TO tariff pertaining to the interconnection of the Large Load, \nthe Participating TO tariff will apply.  \n \n* * * * * \n \nSection 3 \nInterconnection Requests \n3.1 \nGeneral"},{"page":18,"startToken":4612,"endToken":4912,"text":"* * * * * \n \nInterconnection Customers may request Interconnection Service Capacity below the Generating Facility \nCapacity, including to account for co-located Large Load. The CAISO will study these requests for \nInterconnection Service at the level of Interconnection Service Capacity requested for purposes of \nInterconnection Studies, Network Upgrades, and associated costs. If the Generating Facility Capacity \nrequires additional Network Upgrades beyond the Interconnection Service Capacity, the CAISO will \nprovide a detailed explanation of why the additional Network Upgrades are necessary. Any \nInterconnection Facility and/or Network Upgrade cost required for safety and reliability will be assigned to \nthe Interconnection Customer and eligible for reimbursement consistent with the treatment of \nInterconnection Facilities and Network Upgrade provided in this RIS. Interconnection Customers may be \nsubject to additional control technologies, as well as testing and validation of those technologies \nconsistent with Article 6 of the GIA and Article 2 of the SGIA. The necessary control technologies and \nprotection systems shall be established in Appendix C of that executed, or requested to be filed \nunexecuted, GIA. \n \n* * * * * \n \n3.6  \nInternet Posting  \nThe CAISO will maintain on the CAISO Website a list of all Interconnection Requests. The list will identify, \nfor each Interconnection Request: (i) the maximum summer and winter megawatt electrical output; (ii) the \nlocation by county and state; (iii) the station or transmission line or lines where the interconnection will be \nmade; (iv) the most recent projected Commercial Operation Date; (v) the status of the Interconnection \nRequest, including whether it is active or withdrawn; (vi) the availability of any studies related to the \nInterconnection Request; (vii) the date of the Interconnection Request; (viii) the type of Generating Facility \nto be constructed (e.g., combined cycle, combustion turbine, wind turbine, and fuel type); (ix) requested \nDeliverability statuses, and (x) project name, and (xi) MW capacity of any planned co-located load,"},{"page":19,"startToken":4912,"endToken":5170,"text":"excluding Station Power load. Except in the case of an Affiliate, the list will not disclose the identity of the \nInterconnection Customer until the Interconnection Customer executes a GIA or requests that the \napplicable Participating TO(s) and the CAISO file an unexecuted GIA with FERC. The CAISO shall post \non the CAISO Website an advance notice whenever a Scoping Meeting will be held with an Affiliate of a \nParticipating TO. \n \n* * * * * \n \n6.7.2.9  \nCo-located Load Modifications \nThe Interconnection Customer may request, and the CAISO and Participating TO will evaluate, the \nremoval of co-located load from an Interconnection Request if the removal does not increase the \nrequested Interconnection Service level. The CAISO and Participating TO must evaluate such \nmodifications prior to deeming them a Material Modification, but only if the Interconnection Customer \nsubmits them prior to the return of the executed Interconnection Facilities Study Agreement by the \nInterconnection Customer to the CAISO.  Interconnection Customers seeking to add co-located load to an \nInterconnection Request after the commencement of the Cluster Study may request to do so pursuant to \nSection 6.7.2.3, including as a request to downsize the Interconnection Service level pursuant to Section \n6.7.2.7.  For any co-located load addition or removal pursuant to the Participating TO tariff, if the CAISO \nand Participating TO determine that the change is a Material Modification or otherwise cannot be \nreflected in the Generating Facility’s Interconnection Study results, the CAISO and Participating TO will \nnote the change in the GIA, but without modifying the Interconnection Study results.  \n \n* * * * *"}],"sections":[{"p":1,"at":0,"title":"Attachment B – Tariff Redlines","method":"printed heading","endPage":19,"endAt":1704,"startToken":0,"endToken":5170}]}