{"document":{"slug":"rec-20261116-5343-4","title":"Att-C_Draft-Final-Proposal-Large-Load","issued":"2026-11-16","accession":"20261116-5343","docket":"ER27-532-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"California Independent System Operator Corporation","kind":"attachment","file":"sources/filings/text/20261116-5343_004.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5343","tier":"record","parent":"rec-20261116-5343","sha256":"7e4bf4d2acd236a801ff311a0a4be6a668d37025287a18a74b6b31609f6e16f8","pages":72,"tokens":27395,"emptyPages":[],"textThemes":["study","colo","cost","flex"]},"pages":[{"page":1,"startToken":0,"endToken":16,"text":"Attachment C – Final Proposal \nLarge Loads Tariff Amendment  \nCalifornia Independent System Operator Corporation \nNovember 16, 2026"},{"page":2,"startToken":16,"endToken":37,"text":"Large Load Enhancements \n \nDraft Final Proposal \n \nSeptember 24, 2026 \n \n \n \n \n \n \n \n \n \nPrepared by: \n \nSarah Goldmuntz  \nDanielle Mills \nBill Weaver \n \nCalifornia Independent System Operator"},{"page":3,"startToken":37,"endToken":182,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 2 \n  \nTable of Contents \nI. \nExecutive Summary ..................................................................................................... 3 \n1. \nIntroduction and Background....................................................................................... 5 \nA. \nTransmission Service to Eligible Customers on Behalf of Large Loads . 10 \n1. \nDefinition of Large Load ................................................................................... 13 \n2. \nLarge Load Application Process ...................................................................... 17 \n3. \nLarge Load Interconnection Study Procedures ............................................... 21 \n4. \nOperational Requirements ............................................................................... 29 \n5. \nLarge Load Service Agreements ..................................................................... 40 \nB. \nCost Shifting Among Transmission Customers ....................................... 41 \n1. \nRoles and Responsibilities ............................................................................... 41 \n2. \nData Transparency ........................................................................................... 45 \nC. \nCo-Location Arrangements and Load with Behind-the-Meter Generation49 \n1. \nTerminology ...................................................................................................... 49 \n2. \nServing Co-Located Loads .............................................................................. 51 \n3. \nCost Allocation for Co-Located Loads ............................................................. 59 \nD. \nExtending New Transmission Services to Eligible Customers Taking Service on \nBehalf of Flexible Large Loads .............................................................................. 63 \nE. \nInterconnection Customers Serving Electrically Proximate Large Load and Co-\nLocated Load .......................................................................................................... 68 \n2. \nInitiative Timeline and Next Steps ............................................................................. 70 \n3. \nDecisional Classification ............................................................................................ 70"},{"page":4,"startToken":182,"endToken":529,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 3 \n  \nI. \nExecutive Summary \nServing the epicenter of the data-driven economy, the California Independent System \nOperator (CAISO) offers this proposal to establish new procedures for fast and reliable \ninterconnection of new large loads.  \n \nCalifornia faces a projected surge in electricity demand over the next decade, driven in \npart by new large loads such as data centers. The CAISO coordinates closely with local, \nstate and federal regulatory authorities, utilities, and stakeholders to ensure timely \naccess to power for new large loads. This coordination includes anticipating demand \ngrowth, exploring the complexities of co-located and flexible loads, ensuring equitable \ncost allocation, and considering new technical requirements to account for changing \noperational profiles. The actions described in this draft final proposal will ensure that the \nCAISO and its Participating Transmission Owners (PTOs) facilitate economic growth \nand innovation without compromising the overall reliability or affordability of the system. \n \nThis paper responds to the Federal Energy Regulatory Commission (FERC) Order to \nShow Cause on Large Loads and describes five key areas where CAISO leadership \nand engagement is necessary to enable innovation while protecting customers and \nensuring safe and reliable service: \nA. Developing procedures to improve coordination related to load interconnection \napplications, studies, technical standards, and operational requirements for \naccurate long-term planning and near-term reliability.  \nB. Upholding a workable framework for the PTOs to develop just and reasonable \ndeposit, financing, and other cost allocation structures within their tariffs. \nC. Establishing parallel information and application requirements for co-located \narrangements in the CAISO’s generator interconnection process to align with \nPTO load interconnection studies. \nD. Creating a framework for new interconnection service to allow large loads to \ninterconnect quickly to the transmission system while waiting for network \nupgrade completion. \nE. Considering the need for a process to study generating facilities serving \nelectrically proximate large loads. \nRespecting the current assignment of responsibilities for the system, in which PTOs \nprimarily manage the load interconnection process, this draft final proposal addresses \ntopics that intersect with some of the CAISO’s core functions; proactive transmission \nplanning, generator interconnection, and operational reliability."},{"page":5,"startToken":529,"endToken":640,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 4 \n  \nThe CAISO continues to engage the PTOs in the development of this proposal and has \nmade clear its expectations that the PTOs will timely develop consistent and conforming \npolicies and procedures under their transmission tariffs, in service of an enhanced \nplanning regime that provides visibility and transparency to all parties to uphold the \nCAISO’s commitment to reliability. To give the PTOs direction for their filings, the \nCAISO proposes consistent minimum standards throughout this draft final proposal. In \naddition, the CAISO is closely coordinating with state and local regulatory authorities \nregarding this proposal and future large load enhancements going forward."},{"page":6,"startToken":640,"endToken":1060,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 5 \n  \n1. Introduction and Background \n \nThis Large Loads Enhancements draft final proposal constitutes a major step forward \nfor the CAISO and Participating Transmission Owners (PTOs) charting a course to \nenable development and timely interconnection of new large loads, including data \ncenters and other computing loads, onto the CAISO system. The concepts proposed \nrest on a foundation of highly integrated planning and coordination among the CAISO, \nPTOs, state energy agencies, and local regulatory authorities, and provide a framework \nupon which the PTOs will layer their own processes to serve new large loads while \nupholding and reinforcing the CAISO’s commitment to reliability.   \n \nThe CAISO opened this stakeholder initiative with the intent of clarifying roles and \nresponsibilities in anticipation of accelerating large load inquiries and load \ninterconnection requests coming to the PTOs. In 2025, the CAISO began regular \nengagement with the PTOs and formed a Large Load Technical Requirements Working \nGroup (LLTRWG) to explore possible technical standards to ensure reliable operations \nas new large loads interconnect to the CAISO system. The CAISO’s Issue Paper, \nposted in January 2026, described current roles, considerations, and processes for \nlarge loads, including transmission and resource planning, transmission service \nofferings, cost allocation and responsibility, technical requirements and standards, \noperational requirements, and related issues.1 The CAISO has continued to monitor and \nengage in state and federal regulatory discussions regarding large loads and explored \ncentral issues and procedural steps that require additional transparency or new \nproducts. On June 15, 2026, the CAISO issued a Large Loads Technical Requirements \nStraw Proposal on behalf of the LLTRWG in order to stay ahead of any potential \noperational concerns that large loads may present.  \n \nOn June 18, 2026, the Federal Energy Regulatory Commission (FERC or the \nCommission) issued six tailored orders to show cause under Section 206 of the Federal \nPower Act to each of the six regional grid operators under its jurisdiction, including the \nCAISO. The order to show cause (Order) directed at CAISO focuses on five central \nconcerns, all of which are addressed in this draft final proposal. The CAISO met the first \nof the Commission’s compliance requirements with submission of an Informational \nReport on Resource Sufficiency, describing recent attention to resource adequacy (RA), \ngeneration development, transmission expansion, and load and generator \ninterconnection processes.2  \n \n1  \nSee CAISO Large Loads Issue Paper at https://www.caiso.com/documents/issue-paper-large-\nload-consideration-jan-20-2026.pdf. \n2  \nSee CAISO Informational Report - Large Loads and Co-located Loads at \nhttps://www.caiso.com/documents/jul-20-2026-informational-report-large-loads-and-co-located-loads-\nel26-71.pdf."},{"page":7,"startToken":1060,"endToken":1469,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 6 \n  \n \nAs directed by the Commission, the CAISO is coordinating closely with state energy \nagencies to complement their regulatory proceedings, as well as with the PTOs to \nensure a fair and consistent application of requirements and procedures across the \nCAISO system. Such consistency is critical to enabling reliable and timely \ninterconnection, energization, and operations of new large loads. \n \nTo anticipate and enable increasing load growth, the CAISO works with the state energy \nagencies, utilities, and stakeholders in its footprint. A 2022 Memorandum of \nUnderstanding (MOU) between the California Energy Commission (CEC), California \nPublic Utilities Commission (CPUC), and the CAISO tightened the linkages between \nresource and transmission planning, interconnection, and procurement so California is \nequipped to meet its reliability needs and state energy policy objectives.3 This \nframework has allowed the CAISO and the PTOs to meet the increasing demand \nforecasted for the state. As of January 2026, the CEC forecasts that data center load in \nthe CAISO-managed grid will increase by 1.8 gigawatts (GW) by 2030 and 4.7 GW by \n2035.4 The CAISO also is aware that utilities are receiving an increasing number of \nlarge load interconnection and service applications, and is committed to staying ahead \nof the curve, with the timely serving of new energy demand reliably and affordably.  \n \nTo date, California’s integrated resource planning efforts have resulted in more than 37 \nGW of nameplate new generation and storage capacity coming online to serve CAISO \nload since 2020.5 The close coordination between the CAISO, state agencies, and local \nregulatory authorities on demand forecasts and resource planning provides a pathway \nfor proactive transmission planning that anticipates emerging large load growth by \naligning that growth with commensurate resource and infrastructure development to \nserve new loads.   \n \nThe current assignment of transmission responsibilities for the system under the \nCAISO’s operating control gives lead responsibilities for resource (generator and \nstorage) interconnection and transmission expansion planning to the CAISO, while \n \n3  \nSee Memorandum of Understanding Between the California Public Utilities Commission and the \nCalifornia Energy Commission and the California Independent System Operator Regarding Transmission \nand Resource Planning and Implementation at https://www.caiso.com/Documents/ISO-CEC-and-CPUC-\nMemorandum-of-Understanding-Dec-2022.pdf.  \n4 California Energy Demand 2025 Hourly Forecast – CAISO – Planning Scenario: \nhttps://efiling.energy.ca.gov/GetDocument.aspx?tn=268127&DocumentContentId=105135.  \n5  \nSee CPUC Resource Tracking Data Reports at https://www.cpuc.ca.gov/industries-and-\ntopics/electrical-energy/summer-2021-reliability/tracking-energy-development/cpuc-resource-tracking-\ndata-reports."},{"page":8,"startToken":1469,"endToken":1955,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 7 \n  \nutilities, specifically the PTOs, hold the lead role for load connections.6 These \nrelationships are set out in the FERC-approved tariffs of the CAISO and the PTOs and \nthe CAISO transmission control agreement. To date, most of the load interconnections \nhave been distribution-system connections informed by the utilities’ distribution system \nrequirements, with third-party customer connections managed with the utilities. This \nstructure has efficiently and effectively enabled the utilities to manage both their PTO \nresponsibilities for transmission connections regulated by FERC and their state-\njurisdictional responsibilities for rates and charges that apply to end-use customers.  \n \nHowever, the CAISO and the PTOs recognize that there is an increase in load \ninterconnection requests for transmission-system connections that raise questions \nabout the roles and responsibilities of the CAISO and the PTOs. FERC’s Order raises \nmany of these questions. This draft final proposal addresses the issues the Commission \nraises in the Order that directly pertain to the CAISO’s responsibilities to anticipate and \nplan for new additions to the CAISO system, provide transmission service, and maintain \nreliable operations of the grid. This document highlights several issues that will require \nsignificant coordination among the PTOs to develop consistent tariff policies and \nprocedures that conform to the framework the CAISO proposes. The draft final proposal \nalso continues to respect the distinct roles of the CAISO versus the various types of \nPTOs, while complying with the requirements the Commission describes in its Order. \n \nThe CAISO is also conducting other stakeholder initiatives that will provide additional \nbenefits to reliability, market efficiency, and affordability, as described below. These \nstakeholder initiatives include the CAISO’s ongoing work on Resource Adequacy, \nDemand and Distributed Energy Market Integration (DDEMI); and Interconnection \nProcess Enhancements \n \nThe CAISO also engages in state-level coordination efforts regarding large loads as \nCalifornia agencies are implementing state law related to data centers and examining \nthe implications of large loads in resource planning and procurement, interconnection, \n \n6  \nAt times in this draft final proposal, the CAISO will distinguish between utility responsibilities as \nparticipating transmission owner (PTO), utility distribution company (UDC), or load-serving entity, as all \ncarry different responsibilities depending on the type of load and regulatory topic in question. Utility \ndistribution company refers to an entity that owns a distribution system for the delivery of energy to and \nfrom the CAISO-controlled grid, and that provides regulated retail electric service to Eligible Customers, \nas well as regulated procurement service to those end-use customers who are not yet eligible for direct \naccess, or who choose not to arrange services through another retailer. PTO refers to a party to the \nTransmission Control Agreement who has placed its transmission assets and Entitlements under the \nCAISO’s Operational Control in accordance with the Transmission Control Agreement. Load-serving \nentities are responsible for serving retail electricity customers and, in California, this include investor-\nowned utilities, community choice aggregators, publicly owned utilities, and electric service providers."},{"page":9,"startToken":1955,"endToken":2402,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 8 \n  \nretail rate design, and energization,7 with open proceedings at the CPUC and in certain \ndockets at the CEC. The CAISO also recognizes that California recently enacted \nseveral pieces of legislation related to data centers, which could have implications for \nlarge loads connecting to the distribution system. The CAISO will continue to work with \nthe state energy agencies and PTOs to address the new statutory requirements.  \n \nAs described throughout this draft final proposal and in the CAISO’s 30-day \nInformational Report8 on resource adequacy to serve large loads, current State planning \nforecasts and procurement trajectories indicate that California can accommodate the \nlarge load growth reflected in the adopted demand forecast, provided planned resource \nadditions, procurement and transmission development continue to materialize. As a risk \nmitigation tool for capacity constraints, however, the CAISO is exploring the concept \nthrough which local regulatory authorities (LRAs), load-serving entities (LSEs), Utility \nDistribution Company (UDC), a metered sub-system (MSS), and PTO would work with \nthe CAISO to develop a framework for curtailing large loads under tight grid conditions, \nbefore a reliability event. The CAISO recognizes the jurisdictional complexities of this \napproach and plans to work collaboratively with the LRAs, including the CPUC, and \nLSEs to identify the necessary requirements to enable such a framework. In exploring a \npotential framework, the CAISO would continue its collaboration with the CEC and the \nCPUC to understand any implications on the integrated planning framework. \nDiscussions around this curtailment approach are separate and distinct from the \nCAISO’s response to the Order; as such, the CAISO will continue to explore it in a \nfuture policy initiative. \n \nThe CAISO also notes that the North American Electric Reliability Corporation (NERC) \nis actively advancing industry-wide efforts to address reliability impacts of large loads, \nparticularly large computational loads, such as data centers. In May 2026, NERC issued \na Level 3 Essential Actions Alert addressing large load modeling and data, system \nstudies, commissioning, ride-through performance, and monitoring. In addition, under \nNERC Project 2026-02 – Computational Loads, on August 19, 2026, NERC posted new \nand revised Reliability Standards for formal industry comment and ballot. These \nstandards, together with related revisions to NERC registration criteria and other \nongoing NERC initiatives, are intended to establish a longer-term reliability framework \nfor computational load. The CAISO is actively participating in these efforts and \ncoordinating its large load technical requirements with the evolving NERC framework.9 \n \n7  \nThe CPUC refers to load interconnection as “energization.” \n8  \nSee Informational Report - Large Loads and Co-located Loads at \nhttps://www.caiso.com/documents/jul-20-2026-informational-report-large-loads-and-co-located-loads-\nel26-71.pdf.  \n9  \nSee Large Load Technical Requirements - Straw Proposal at \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/Large-Load-Technical-Requirements-Straw-\nProposal-Jun-15-2026.pdf."},{"page":10,"startToken":2402,"endToken":2815,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 9 \n  \n \nThe CAISO will seek to implement the proposed changes expeditiously upon the \nCommission’s approval. As the Order requires, the CAISO will describe how it will timely \nimplement the measures described below while avoiding disruption of existing \ncommercial arrangements. In its filing, the CAISO will clearly identify a reasonable \neffective date to apply to new large load interconnection applications and accommodate \nexisting commercial arrangements. \n \nThe CAISO has an essential role in planning for and maintaining reliable operations of \nthe CAISO-controlled grid and in facilitating consistent approaches to large load \ninterconnections among the PTOs. Considering the urgency of onboarding new large \nloads and the required timeline to submit a filing to FERC under Federal Power Act \nSection 205, the CAISO issues this draft final proposal for stakeholder consideration. \n \nStakeholder Process and Feedback on the Large Loads Straw Proposal \n \nThe CAISO received comments on the straw proposal from ACP-California (ACP-\nCalifornia), AltaGas, Antora Energy (Antora), Bay Area Municipal Transmission Group \n(BAMx), California Community Choice Association (CalCCA), the California Department \nof Water Resources – State Water Project (CDWR), the California Public Utilities \nCommission (CPUC), the Public Advocates Office of the CPUC (Cal Advocates), \nConstellation, Google, GridLiance West (GridLiance), IGNIS Energy USA (IGNIS), \nIndependent Energy Producers Association (IEPA), KritiGrid, Lotus Infrastructure \nPartners (Lotus), LS Power Grid California (LSPGC) and DesertLink, Microsoft, NextEra \nEnergy Resources (NextEra), Northern California Power Agency (NCPA), Pacific Gas \nand Electric Company (PG&E), Pattern Energy (Pattern), San Diego Gas and Electric \n(SDG&E), Solar Energy Industries Association (SEIA), Southern California Edison \n(SCE), State Water Contractors (SWC), Tesla, Trimark Associates (Trimark), Valley \nElectric Association (VEA), Viridon California (Viridon), and Voltus. These stakeholder \ncomments informed the draft final proposal and are addressed as appropriate and by \ntopic in the subsequent sections of the draft final proposal.  \n \nStakeholder comments centered on two topics. First, most stakeholders requested to \nsee the PTO proposals before each PTO files tariff revisions at FERC. Second, \nstakeholders requested to see more implementation details from both the CAISO and \nPTOs. The CAISO recognizes that its draft final proposal relies on complementary tariff \nupdates from the PTOs. Over the past several months, the CAISO has communicated \nits understanding of roles and responsibilities clearly with the PTOs, with general \nconsensus on expectations. Throughout this proposal, the CAISO identifies areas that it \nviews as PTO-led and reinforces the previously communicated expectations to \nstakeholders to ensure alignment. To that end, the CAISO expects to continue to"},{"page":11,"startToken":2815,"endToken":3198,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 10 \n  \ncoordinate closely with the PTOs in the remaining weeks leading up to the compliance \nfiling. In addition, the CAISO expects the PTOs to avail themselves to stakeholder \ninquiries regarding their efforts to update tariffs, pursuant to the Order.  \n \nThe CAISO also appreciates the general stakeholder consensus that there will need to \nbe ongoing coordination work on the implementation details. Some of those areas are \naddressed below, and the CAISO will continue engaging stakeholders on these matters \ngoing forward. Stakeholder feedback on this draft final proposal will help to inform the \nCAISO’s filing at FERC in response to the Order. \n \nA. Transmission Service to Eligible Customers on Behalf of \nLarge Loads \nThe Commission directed the CAISO and the PTOs to either show cause as to why \ntheir FERC-jurisdictional tariffs remain just and reasonable and not unduly \ndiscriminatory or preferential without provisions addressing the five categories set out in \nthe Order, or to explain what changes to their tariffs would remedy the identified \nconcerns. The first category included provisions addressing the application process, \nstudy procedures, and ongoing operational requirements that apply to “Eligible \nCustomers” seeking transmission service on behalf of large loads.10 \n \nThe CAISO agrees with the Commission that additional clarity and information \nrequirements are necessary within the CAISO tariff, especially if interim or non-firm \nservice is being considered to facilitate “speed-to-power,” or accelerated large load \ninterconnections. Further, the CAISO encourages consistency among the PTOs in key \nareas related to large load interconnection application, study, and operations.    \n \nIn addition, the CAISO proposes a series of operational requirements, which it will \ncontinue to develop in coordination with the PTOs and the LLTRWG, and in parallel with \nthe NERC’s efforts to develop technical standards for the reliable operation of large \nloads. \n \nWhile recognizing some changes to the CAISO tariff are needed to address the \nCommission’s concerns with regard to the first category in the Order, the CAISO does \nnot propose significant changes to the roles and responsibilities associated with large \nload interconnection applications or studies. The current framework of shared \nresponsibilities among the CAISO and the PTOs remains an efficient and effective \nmechanism to achieve the aims FERC outlines in the Order. The PTOs remain largely \n \n10  \nOrder to Show Cause at P 3."},{"page":12,"startToken":3198,"endToken":3581,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 11 \n  \nresponsible for processing applications and studying new large loads, while the CAISO \nremains responsible for reviewing those studies and ensuring alignment with \ntransmission planning activities. The CAISO notes the importance of this clarity of roles \nand consistency as it relates to large load interconnections and operations on the \nsystem and believes the proposed tariff enhancements below complement the load and \nresource planning process described in the December 2022 MOU between the CAISO, \nCPUC, and CEC. The CAISO believes that this framework, with some clarification and \nnew information and operational requirements, will address the concerns the \nCommission described in the first category in the Order. \n \nBackground and Stakeholder Comment \n \nThe CAISO agreed with the Order’s direction to provide additional clarity in its tariff for \nits part of providing service to large loads, while expecting the PTOs to collectively \ndevelop their own consistent set of Tariff reforms to clarify their load interconnection \nprocesses and communications, and to align their proposals with the CAISO’s \nprocesses.  \n \nLoad interconnection process and responsibilities across PTOs \n \nACP-California recommended the CAISO take a more active role in guiding the \ndevelopment and alignment of application and study process across all PTO-types. \nNextEra suggested a guiding principle that implementation of the large load \ninterconnection framework will not adversely affect the timelines, resources, or \neffectiveness of the CAISO’s generator interconnection or transmission activities. The \nCAISO engaged in frequent discussions with all PTO types on this topic prior to the \nOrder and will continue to encourage alignment of the application and study processes \nacross the PTOs. It should be noted here that the PTOs currently manage the majority \nof activities associated with load interconnection and the Commission has not indicated \na need for the CAISO to take over the load interconnection process from the PTOs, and \nthe CAISO does not propose to do so.  \n \nMicrosoft encouraged the CAISO to prioritize four reforms in this initiative: study \ntimelines, PTO coordination, energization timeline certainty, and cost transparency. \nMicrosoft suggested that the CAISO, PTOs, and applicable state-jurisdictional \nprocesses should clearly define and coordinate their respective responsibilities so \ncustomers can receive greater certainty regarding available service and energization \ndates. The CAISO appreciates this feedback and is working to address all four reforms \nin partnership with the PTOs."},{"page":13,"startToken":3581,"endToken":4061,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 12 \n  \nGridLiance, IEPA, and LSPGC and DesertLink sought further guidance on how the \nproposed large load interconnection framework would apply to non-load-serving PTOs, \nnoting that the absence of detail creates uncertainty for both non-load serving PTOs \nand developers. GridLiance also cautioned against a critical gap that could create \njurisdictional uncertainty and discourage large load interconnection in non-load-serving \nPTO territories, suggesting instead that the CAISO establish a consistent framework \napplicable to non-load-serving PTOs. PG&E suggested that the large load \ninterconnection process be administered by each PTO based on the distribution service \nterritory where the large load is located, acknowledging that implementation details may \nvary across PTO service territories and whether a PTO is also a UDC. From PG&E’s \nperspective, non-load serving PTOs would not process retail large load interconnections \nand would continue to offer traditional wholesale load interconnection service to Eligible \nCustomers pursuant to Section 10 of their respective transmission owner (TO) tariffs. \nThe CAISO understands that some stakeholders would like the CAISO to resolve this \ndispute and appreciates the concern. However, the CAISO reiterates that the PTOs are \nmuch more familiar with the current load interconnection processes and responsibilities \nthan the CAISO and are therefore in a better position to negotiate a process that \nclarifies roles and responsibilities. The CAISO encourages all PTOs, both load-serving \nPTOs and non-load-serving PTOs, to negotiate a fair and efficient process with clear \nroles and responsibilities for large load study and interconnection processes in their \nfilings. \n \nACP-California suggested that the CAISO ensure that end-use customers are provided \nwith the information and access they need to assess and select transmission \ninterconnection options, including on points of interconnection on non-LSE PTO \nfacilities. The CAISO expects the PTOs to describe how this information will be made \naccessible to end-use customers as part of their filings in response to the Order. \n \nBAMx reiterated that municipal and other non-PTO utilities must have a meaningful role \nin the study and planning processes that determine the impact of these large loads on \nthe reliability of the grid, and the allocation of costs related to the interconnection of \nthese loads. BAMx recommended that CAISO concurrence should require affected \nsystem screening and coordination with non-PTOs before concurrence to protect non-\nPTO import capability and reliability. CDWR and NCPA expressed particular interest in \nany affected systems processes that are developed for load interconnections as well as \nmore clarity on the co-located load interconnection process being developed by the \nPTOs in consultation with the CAISO. CDWR stated its concern about the potential \nimpacts new computational loads could have, especially on CDWR’s large pumping \nplants, which consist of synchronous large rotating mass. NCPA suggested that the \nCAISO require its PTOs to adopt a consistent, transparent, affected system study \nprocess that applies to all PTOs and is overseen by the CAISO. The CAISO notes that"},{"page":14,"startToken":4061,"endToken":4401,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 13 \n  \naffected system processes for load studies are and will continue to be addressed in the \nPTO’s tariffs, and these roles are not expected to change.  \n \nThe CAISO reiterates that it does not regulate the PTOs on matters of load \ninterconnection. The Commission may opt to direct the CAISO to require the PTOs to \nadopt a consistent methodology for interconnecting loads, but the CAISO currently \nexpects the PTOs to organize themselves to develop sufficiently consistent and \ncomplementary tariff provisions that align with the CAISO’s processes. Specifically, the \nCAISO expects that each PTO’s tariff will provide consistent processes that clarify the \nprocess for Eligible Customers seeking service, establish how non-load-serving PTOs \ncoordinate with load-serving PTOs, and detail how affected system issues are \ncoordinated with non-PTO utilities.  \n \nPG&E supported the CAISO’s approach of preserving the existing allocation of \ninterconnection and study responsibilities.  \n \n1. \nDefinition of Large Load \nFERC noted in the Order that the CAISO and PTO tariffs lack a definition of large load, \nas a new category of load.11 The Commission directed the CAISO and PTOs to create \nan appropriate definition, including a load size and interconnection voltage threshold, \nbased on the characteristics of CAISO’s transmission system. The Commission \nsuggested that a potentially reasonable definition would be “a new commercial or \nindustrial customer, located at a single site behind one or more points of \ninterconnection, and that has a peak load of 50 MW or greater, interconnects to the \ntransmission system at a voltage level of greater than 69 kV, and is not part of a co-\nlocation arrangement.”12 \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO recommended the following definition for large load: \n“An End User located at a single site interconnecting to the CAISO Controlled Grid, and \nthat has a peak load of 50 MW or greater,” while indicating that the definition could \nevolve to account for future NERC standards.   \n \n11  \nOrder to Show Cause at P 58. \n12  \nId. at P 57."},{"page":15,"startToken":4401,"endToken":4851,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 14 \n  \n \nSeveral stakeholders, including the CPUC, IEPA, LSPGC, SDG&E, SEIA, SCE, and \nViridon broadly supported the CAISO’s proposed definition of large loads, and many \nstakeholders agreed that alignment with NERC standards is critical. \n \nTypes of large loads \n \nMany stakeholders, including AltaGas and the CPUC, did not see a need for the CAISO \nto specify certain types of large loads (e.g. computational). CDWR recommended that \nthe CAISO specifically state in the tariff that the definition applies only to new large load \ninterconnections. The CAISO reiterates that the policies proposed in this initiative will \nbegin to apply for new large loads only, and after resulting tariff revisions become \napproved and effective.  \n \nDirect connection to the CAISO-controlled grid \n \nAltaGas, SDG&E, SCE, and others agreed that specifying connection to the CAISO-\ncontrolled grid is preferable to using a specific voltage level for defining large loads. The \nCPUC did not suggest a specific voltage level but notes that most large loads would be \nbetter served at higher transmission voltages. SDG&E and SCE agreed that the \ndefinition should be based on the connection to the CAISO-controlled grid rather than \nrelying on a transmission voltage threshold, noting that some large loads may connect \nthrough distribution facilities that are not under CAISO operational control and may fall \nunder state or local regulatory jurisdiction. The CAISO agrees with SDG&E and SCE \nand proposes to clarify that large loads to which the draft final proposal applies must be \ndirectly connected through a point of interconnection to the CAISO-controlled grid. \n \nPG&E and BAMx argued that the phrase “interconnecting to the CAISO-controlled grid” \nwas ambiguous as written because end users do not connect directly to CAISO-\ncontrolled facilities but rather are served by Eligible Customers via points of \ninterconnection with the CAISO-controlled grid. To ensure uniform application, PG&E \nrecommended a final proposed definition that includes all loads above the MW \nthreshold that affect the CAISO transmission system, i.e., loads above the MW \nthreshold served by an Eligible Customer via a point of interconnection on the CAISO-\ncontrolled grid. PG&E also recommended that the CAISO consider a 50 kV threshold at \nthe end user’s retail point of interconnection to the UDC as an additional measure to \ndistinguish between customers that will have a high impact on the CAISO grid and \nthose that will not. The CAISO believes that PG&E’s proposed definition creates \nadditional ambiguity because it seems to include intervening assets that may be first \nconnected to the distribution system. It is also likely to lead to ongoing disputes about \nthe meaning of “affecting” the CAISO transmission system. The CAISO recognizes the"},{"page":16,"startToken":4851,"endToken":5298,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 15 \n  \nclear jurisdictional boundary that the Commission initially suggested in the Order, that \nany large load must be directly connected to the transmission system. Therefore, the \nCAISO declines to adopt PG&E’s proposal and proposes to specify that the point of \ninterconnection must be to the CAISO-controlled grid whether that end user’s facilities \nare directly connected to the transmission system or through radial/non-network \ninterconnection facilities. The CAISO clarifies, however, that to the extent that \ndistribution-connected or non-PTO connected loads create a need for network upgrades \nelsewhere on the system, those upgrades can be considered in the CAISO transmission \nplanning process (TPP). \n \nThe CAISO understands that distribution-connected and non-PTO connected loads can \nimpact the transmission system. The CAISO may address these instances in the future, \nincluding through the DDEMI Initiative. The PTOs, likewise, may address cost allocation \nimpacts from such loads through both their FERC and CPUC tariffs. But, as discussed \nat length in the Order, FERC has jurisdiction over wholesale electricity sales and the \ntransmission in interstate commerce. The Order is premised on FERC’s duty to remedy \nthe potential for undue discrimination in transmission access by regulating \ninterconnections to the transmission system, not the distribution system, which is left to \nthe states. The CAISO’s large load definition is thus similarly limited by FERC’s \njurisdiction. The CAISO may not assert substantial rules on distribution-connected loads \nfor the same reason that FERC has not asserted rules on them: distribution-connected \nretail customers are not jurisdictional to FERC under the Federal Power Act.  \n \nThe CAISO nonetheless seeks to clarify the large load definition to recognize that there \ncan be interconnection facilities between the actual load and the CAISO-controlled grid. \nThe CAISO’s draft tariff revisions likewise modify the definitions of Point of \nInterconnection and Interconnection Facilities to recognize the same.  \n \nLoad-peak \n \nSeveral stakeholders expressed support or comfort with the 50 MW load-peak threshold \nin the straw proposal. PG&E suggested reducing the load-peak threshold to 20 MW. \nBAMx, the CPUC, and Constellation suggested that the lack of apparent gaming is not \nsufficient reason to assume load projects will not need clear direction or enforcement to \ndiscourage them from breaking up projects to avoid large load treatment. Constellation \nsuggested that the CAISO clarify how it will apply the 50 MW threshold to phased \nprojects, expansions of existing facilities, and multiple loads that share a point of \ninterconnection. BAMx recommended an aggregation rule for commonly-owned or \nelectrically proximate loads, together with a look-back mechanism for staged additions. \nThe CAISO recognizes that any arbitrary cutoff creates some incentive to avoid the \nload-peak threshold. This reality is inescapable regardless of where the cutoff lies."},{"page":17,"startToken":5298,"endToken":5758,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 16 \n  \nHowever, the CAISO believes that the 50 MW threshold it proposed is based on the \npotential impact to the grid. Disaggregation and phasing cases may be addressed by \ndeterminations of whether the loads actually share a site, interconnection facilities, etc., \nand actually comprise a single load. Just as a single generating facility may consist of \nmany generating units with their own meters and resource identifications, developers \nare unlikely to escape the large load threshold by trying to create the appearance of \nmultiple loads. At the same time, the CAISO does not want to stifle developers and \nLSEs’ flexibility to set up multiple meters and disaggregate facilities within a single large \nload campus. As such, the CAISO believes it can address these cases in the future on a \ncase-by-case basis, as it does today with generator interconnections. \n \nCalAdvocates noted that interconnecting to the CAISO-controlled grid would eliminate \nthe need for a capacity threshold because customers interconnecting to the \ntransmission system would be large enough to pose unique challenges to the \ninterconnected system. The CAISO appreciates this point but views the capacity floor \nas a useful determinant and is aligned with what FERC identifies in the Order. As noted \nelsewhere, the CAISO does review both distribution- and transmission-interconnected \nloads of different sizes as a part of the TPP process.   \n \nLSPGC and Desert Grid suggested clarifying that the Eligible Customer is the entity \ndirectly connected to the CAISO-controlled grid and a qualifying end user has a peak \nload of at least 50 MW and is served by the Eligible Customer. The CAISO declines to \ninclude the term “Eligible Customer” in its definition of large loads to avoid unnecessary \nconfusion. The CAISO believes that including Eligible Customer within the large load \ndefinition could introduce confusion, including because the CAISO tariff does not use \nEligible Customer, and introducing it here could require other changes to the CAISO \ntariff, and because FERC Order No. 888 has a clear definition for Eligible Customer.  \n \nProposal \n \nThe CAISO proposes to include a definition of “Large Load” in the CAISO tariff; \nhowever, the CAISO believes it may be premature to do so at this point, while NERC is \ndeveloping similar, potentially overlapping, terms for computational loads. As such, the \nCAISO’s proposed definition may shift in the coming months to avoid regulatory \nconflicts between its definition and NERC’s. Aligning with future NERC standards will \navoid creating dual or conflicting regulatory requirements for the same loads. \nNevertheless, the CAISO describes below the principles it believes are helpful in \ndefining large loads.  \n \nThe CAISO proposes that a potential definition could be: “An End User located at a \nsingle site whose Point(s) of Interconnection is/are to the CAISO-Controlled Grid, and"},{"page":18,"startToken":5758,"endToken":6177,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 17 \n  \nthat has a peak load of 50 MW or greater.”13 The CAISO likewise proposes to add large \nloads to its definitions of Interconnection Facilities and Point of Interconnection to clarify \nhow all three terms work together.  \n \nSimilar to generating facilities, the CAISO proposes to continue to adhere to FERC and \nCalifornia regulations on what constitutes a “site.” The CAISO expects the large load \ndefinition will adequately apply to large loads comprised of distinct loads, even if they \nhave separate retail meters, which will address concerns expressed regarding loads \npursuing multiple connections to avoid pre-determined and specified MW threshold. \nOperationally, such loads would still have the same impact on the CAISO transmission \nsystem. \n \nThe CAISO believes that its proposed large load definition addresses the issues in the \nOrder and coheres with FERC’s jurisdiction to address them. The CAISO may develop \nother terms in the future to address other load types and locations. The Midcontinent \nIndependent System Operator (MISO), for example, has proposed a 50 MW generic \nlarge load class as well as a 20 MW computational load class. The CAISO may follow \nthis course in the future, depending on the Order proceeding and NERC’s \ndevelopments. At this time, however, the CAISO’s intent is to comply with the Order \nwithout overburdening developers with what could become duplicative or onerous \nregulations.   \n2. \nLarge Load Application Process \nThe Commission suggested that the CAISO and the PTOs lack clear and consistent \nprovisions establishing the application process and study procedures that will be used \nwhen the CAISO and/or the PTOs evaluate the provision of transmission service to \nEligible Customers on behalf of large loads, including an application process, \napplication fee and readiness requirements, and information and data requirements.14 \nThe Order also suggested that the CAISO and PTO tariffs lack appropriate study \nprovisions to recognize the unique operational characteristics of large loads that are \nwilling and able to limit their energy withdrawals under certain conditions to lessen or \navoid the need for network upgrades.15 \n \n \n13  \nAppendix A to the CAISO tariff defines an End User as “A consumer of electric power who \nconsumes such power to satisfy a Load directly connected to the CAISO Controlled Grid, a Distribution \nSystem…” It defines the CAISO Controlled Grid as “The system of transmission lines and associated \nfacilities of the Participating TOs that have been placed under the CAISO’s Operational Control.”  \n14  \nOrder to Show Cause at P 58. \n15  \nId. at P 59."},{"page":19,"startToken":6177,"endToken":6542,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 18 \n  \nIn addition, the Commission noted that accurate models using Electromagnetic \nTransient (EMT) studies may help to ensure that transmission service needed on behalf \nof large loads can be provided without compromising reliability and suggests clarity and \nconsistency in the evaluation of alternative transmission technologies (ATTs) as \npotential solutions to accommodate an Eligible Customer’s request for transmission \nservice on behalf of a large load.16 To the extent that traditional network upgrades are \nselected over ATTs, the Commission recommended demonstration of why ATTs were \nnot selected.17 \n \nFinally, the Commission directed the CAISO and the PTOs to explain whether their \ntariffs sufficiently address identification of Direct Assignment Facilities and Network \nUpgrades (as the Order defines) necessary to reliably provide transmission service to \nEligible Customers on behalf of large loads; include provisions for a 60-90-day timeline \nto study the unique operational characteristics of large loads; and include a study \ndeadline to assess large loads.18 \n \nBackground and Stakeholder Comment \n \nThe CAISO proposed enhancements to data sharing and ongoing coordination with \nPTOs who lead the load interconnection application and study process, while noting that \nthe PTOs should develop consistent load application processes to support efficiency, \nvisibility, and planning. \n \nStudy process for co-location agreements with exporting generators \n \nAltaGas suggested clarification that the generation component of new large load \ngeneration/storage combinations planning to discharge energy into the grid would \ninterconnect under the CAISO tariff, including cluster-study processes and listings in the \nqueue, and requested clarity on how the relatively recent generator interconnection \nrequest intake and study rules would apply to these combinations. \n \nAltaGas further noted that the application process is not clear if an existing resource \nadding a large load to its site might still discharge energy into the grid (see discussion \nbelow about RA status retention for the resource). This would seem similar to the above \nsituation where a new large load-resource combination would inject energy into the grid, \nbut that new combination type must apply under CAISO tariffs. The CAISO confirms \nthat existing generators planning to add large loads to their current interconnection \n \n16  \nId. \n17  \nId. at P 61. \n18  \nId. at P 62."},{"page":20,"startToken":6542,"endToken":6919,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 19 \n  \narrangements would interconnect under PTO Tariffs, even if they plan to continue to \ndischarge energy into the grid. The CAISO encourages these generators to come to the \nCAISO to update their Generator Interconnection Agreement (GIA), master file, or seek \na post-COD modification if necessary. \n \nStudy transparency  \n \nBAMx and the CPUC encouraged the CAISO to clearly require standardized, \ntransparent study framework with common base cases, assumptions, and criteria \nacross wholesale interconnection studies and PTO retail load-cluster studies, with the \nCPUC noting that the straw proposal lacked any enforcement details pertaining to \napplication process, study requirements, and timelines. BAMx notes that (i) FERC has \nplaced the TO Tariffs directly at issue in this §206 proceeding and may itself direct \nstandardized study provisions. BAMx also points out that the CAISO independently \npossesses authority under the Transmission Control Agreement and its own tariff to \ncondition concurrence, transmission planning process treatment, and transmission \naccess charge (TAC) cost recovery on studies performed using common base cases, \nassumptions, and criteria. The CAISO understands these concerns but notes that the \nPTOs will develop sufficiently similar rules to meet their requirements to comply with the \nOrder. Large loads have interconnected and continue to interconnect in California \nwithout jeopardizing base cases, cost recovery, or reliability, and the CAISO believes its \ncontinuing work with the PTOs, regulators, and stakeholders will maintain this status \nquo. \n \nRegarding EMT studies, the CPUC noted that the need for study data is being \nevaluated in other forums such as IEEE 1547.7 and NERC and suggests that the \nCAISO should take the lead role in preparing and maintaining the State’s EMT data. \n \nProposal \n \nThe CAISO reiterates that the existing load interconnection process is conducted \nefficiently and effectively by the PTOs. For this reason, the CAISO proposes enhanced \nand ongoing coordination with the PTOs on the load and resource interconnection \nprocesses and expects the PTOs to align their load application processes with the \nCAISO’s resource interconnection process to ensure the level of visibility necessary for \nthe CAISO to plan for new large loads and maintain reliability once they are \ninterconnected.  \n \n \nThe CAISO suggests that the PTOs develop consistent application processes, study \nrequirements, and agreements to ensure sufficient transparency in the load application"},{"page":21,"startToken":6919,"endToken":7381,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 20 \n  \nand study process. It is important for the PTOs to maintain some degree of consistency \nin their respective tariffs so the CAISO has a greater certainty around the consistency of \ndata and operational details received by the PTOs in the load applications  \n \nThe CAISO currently evaluates relevant alternative transmission technologies (ATTs) in \nits transmission planning process, which is the primary process through with the CAISO \nensures service to new large load interconnection requests. The CAISO’s evaluation \nroutinely includes static synchronous compensators, static VAR compensators19, \nadvanced power flow control devices, transmission switching, synchronous condensers, \nvoltage source converters, advanced conductors, and tower lifting. The CAISO \nunderstands that transmission providers must consider ATTs at all times. As a \ntransmission provider, the CAISO must include in the generator interconnection cluster \nstudy report an explanation of the results of the evaluation of the enumerated ATTs for \nfeasibility, cost, and time savings as an alternative to a traditional network upgrade.  \n \nTherefore, the CAISO supports and has broadly adopted the practice of duly \nconsidering and assigning ATTs to meet identified system needs, including when \ntriggered by new loads interconnecting to the CAISO grid. The CAISO documents \nconsideration of such technologies in its annual Transmission Plan. This has been the \npractice in CAISO for several years and was recently memorialized in the CAISO’s tariff \nin compliance with FERC Order Nos. 2023 and 1920 (pending FERC approval).20 To \nrespond to the Order and the large load interconnection context specifically, the CAISO \nproposes to clarify these considerations through consistent language in the CAISO \ntariff, which the CAISO expects the PTOs will similarly include in their tariffs. Rather \nthan providing standardized documentation of the detailed rationale each time a \ntraditional transmission technology is approved over the use of ATTs, the CAISO \nproposes to continue to report annually on the approvals of ATTs within each \ntransmission plan. The CAISO will continue to set out the alternatives that were \nconsidered in the selection of all preferred transmission solutions, whether ATTs or \nother more conventional solutions, to the reasonable depth necessary given the nature \nof the transmission need. This approach has worked well in the generator \ninterconnection study process, enabling the consideration and use of ATTs and grid-\nenhancing technologies (GETs) without slowing down studies. \n \nWith regard to the Commission’s ATTs-related modeling requirements, the CAISO \ncoordinates annually with the transmission owners during the annual transmission \nplanning process on the feasibility of ATTs, particularly evaluating the application of \nadvanced conductors and flow control devices. The CAISO notes that Dynamic Line \n \n19  \nVAR refers to voltampere reactive, which is the unit used to measure reactive power in an AC \nelectrical grid.  \n20  \nSee, e.g., Section 6.2 of Appendix KK to the CAISO tariff."},{"page":22,"startToken":7381,"endToken":7834,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 21 \n  \nRating (DLR) refers to a transmission line rating varying based on local conditions, such \nas ambient air temperature, wind speed, cloud cover, solar heating, and precipitation, \netc., rather than a static rating assumption. DLRs can provide additional capacity for a \ntransmission line. In the CAISO's production cost simulation, many congestions were \nobserved in the evening or in lower-temperature months. Such congestion can be \npotentially mitigated or reduced by adopting DLRs for the lines. In the CAISO’s most \nrecent planning cycle, DLRs were not modeled in production cost modeling cases, since \nit not only requires operational history data of weather conditions and line ratings, but \nalso requires software and modeling enhancement to accommodate the data in \nproduction cost model. The CAISO is coordinating with the PTOs, the Western \nElectricity Coordinating Council (WECC), and the software vendor of GridView to \nexplore the feasibility and possibility of implementing dynamic line rating in production \ncost models in future planning cycles. \n \nAs a general matter, the CAISO recognizes that the Order implicates various types of \nPTOs, including non-load-serving PTOs and approved project sponsors that could be \nimpacted by large load interconnection requests but are not load-serving entities and do \nnot have retail interconnection tariffs. The CAISO expects the PTOs to work together to \nclarify and develop complementary roles and responsibilities in their respective tariffs \nregarding requests for interconnections to non-load-serving PTO facilities.   \n3. \nLarge Load Interconnection Study Procedures \nThe Commission highlighted a lack of clarity and consistency regarding the study of the \nprovision of transmission service to Eligible Customers on behalf of large loads.21 \nFurther, the Commission noted that, while it does not seek to alter the allocation of \nrights and responsibilities between CAISO and PTO tariffs, the CAISO’s and PTO’s \ntariffs may not clearly specify which entity will be responsible for studying the provision \nof transmission service to Eligible Customers on behalf of large loads.22 The Order \nsuggested that additional study considerations may be necessary to address the unique \noperational and reliability challenges presented to the transmission system by providing \ntransmission service to Eligible Customers on behalf of large loads.23 The Commission \nnoted that clear and consistent study processes may be necessary to fully capture the \ntransmission system impacts of providing such transmission service, which could result \nin significant operational risks for the transmission system,24 and suggested that tariff \nprovisions may prevent disputes over a variety of issues, e.g. study timelines and \ndelays, how the transmission service needed on behalf of the large load is studied, what \n \n21  \nOrder to Show Cause at P 51. \n22  \nId. at P 51. \n23  \nId. at P 52.  \n24  \nId. at P 53."},{"page":23,"startToken":7834,"endToken":8174,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 22 \n  \ntypes of network upgrades are considered, and how required network upgrades to \nprovide the requested transmission service are determined.25  \n \nFinally, the Commission suggested that the CAISO and PTO tariffs fail to deter \nspeculative or duplicative requests for transmission service by Eligible Customers on \nbehalf of large loads.26 \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO proposed coordination enhancements included a \nmore robust data exchange process between PTOs and the CAISO. The CAISO noted \nthat the PTOs should align their load interconnection studies with the CAISO’s \ntransmission planning process timelines, as feasible, and further proposed that it would \nclarify when and how it accounts for new load additions, including in the TPP \nconcurrence process.  \n \nStakeholders generally supported the comprehensive coordination the CAISO proposed \nwith utilities, regulators, NERC, and WECC. Several expressed concerns or asked \nquestions regarding the PTO ability to complete studies within 60-90 days. \nMicrosoft noted that following completion of the studies, customers should be provided \nwith available options regarding firm, non-firm, or temporary non-firm service, project \nphasing, the use of GETs or ATTs, and any associated operational requirements, \ntogether with an estimate of project cost and schedule. Providing this information early \nin the process will give customers greater certainty regarding project feasibility, cost, \nand timing and will allow them to make informed investment and development \ndecisions. The CAISO agrees with these objectives. \nThe CPUC recommended a high large load sensitivity in the annual CAISO TPP that \naggregates active load-cluster requests (e.g., Group 1 and Group 2) above a threshold, \nso cumulative reliability and congestion effects are assessed before energization rather \nthan merely reported. The CAISO notes that PTOs already study all active load \ninterconnection requests within their interconnection study, which provides insight on \nthe cumulative impact of the requests. \n \nCal Advocates suggested that the CAISO should refrain from using its concurrence \nprocess for approving transmission projects for large load interconnections, noting that \n \n25  \nId. at P 54. \n26  \nId. at P 55."},{"page":24,"startToken":8174,"endToken":8617,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 23 \n  \nthe proposed clarifications to the concurrence process give PTOs an opportunity to \ninject speculative loads into transmission planning and could impair the state’s aim to \ncoordinate resource planning. Cal Advocates also noted that CAISO’s concurrence \nprocess does not include any transparent evaluation of alternative transmission \ntechnologies, like GETs or energy storage. The CAISO’s concurrence review does \ninclude GETs in potential alternative options for both local upgrades that move forward \nas load interconnection upgrades and area upgrades that are reviewed in the TPP.  \n \nMore generally, the CAISO notes that the concurrence process provides important \nvalidation of the assumptions used in planning and confirms that proposed load \ninterconnections and associated network upgrades do not create adverse reliability \nimpacts to the regional system. The concurrence process also helps ensure that new \ninfrastructure is appropriately sized, timed, and initiated based on credible and \ncoordinated planning to meet forecasted load growth. The CAISO’s planning framework \nidentifies and mitigates area-wide impacts driven by significant new load growth. In \nparallel, the PTOs continue to advance the local and interconnection-driven network \nupgrades needed to reliably serve retail customers and safely integrate new large loads \nunder the PTOs’ obligation to serve them. This coordinated approach, whereby the \nCAISO addresses area-wide impacts through the Transmission Planning Process and \nPTOs advance local network reinforcements associated with load interconnections \nthrough the load interconnection process, is essential to facilitating the timely integration \nof new loads and minimizing reliance on operational workarounds.  \n \nConstellation suggested that the study framework should clearly explain the respective \nresponsibilities of CAISO, the PTO, and the interconnection customer. It should also \nestablish clear application requirements, a delineation of the studies to be conducted, \nstudy milestones and timelines, data-sharing procedures, and timelines for \ncommunicating material changes to study assumptions or required upgrades. \nConstellation also requested that customers receive access to the assumptions, \nmethods, and results that support material upgrade or operating requirements, subject \nto appropriate confidentiality protections. The CAISO agrees that a clearly articulated \nstudy framework is necessary and intends to share all details around the process, as \nwell as details on assumptions, methods, and results once its tariff revisions are filed. \nAfter filing these proposed tariff changes with the Commission, the CAISO proposes to \nconvene regular working group meetings to communicate the PTO-CAISO load \ninterconnection application and study framework to stakeholders, to begin working on \nimplementation details, and on sharing assumptions, methods, and others, as feasible. \n \nPG&E suggested that PTOs should retain the flexibility to conduct studies either \nsequentially or in clusters, and notes that additional details around study procedures \nand upgrade determinations methodologies be developed through PTO tariff revisions."},{"page":25,"startToken":8617,"endToken":9038,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 24 \n  \nThe CAISO looks forward to continued collaboration on these procedures to ensure \nalignment prior to filing proposed tariff changes with the Commission and, ultimately, as \nthe CAISO and PTOs work through implementation details.  \n \nLong-term load forecasting \nCalCCA noted that even if the primary responsibility for protecting against speculative \nload is best suited for the PTO, the CAISO still must ensure that it adopts tariff \nprovisions that maximize the ability of the CAISO to validate new load additions and \nminimize the potential for approving transmission build out based upon inaccurate \nforecasts. The CAISO agrees and will continue to provide input into the load forecasting \nprocess with the CEC and in discussions with the PTOs. \n \nDeterring speculative load interconnection requests for transmission service \nThe CPUC and Cal Advocates suggested that the straw proposal lacks any \nenforcement details pertaining to requirements to deter speculative load interconnection \nrequests. Cal Advocates suggested that the CAISO refrain from studying and approving \nnetwork upgrades for large loads until the large load completes readiness requirements. \nCal Advocates noted that large load data center applications with signed agreements \nwith the utility for electric service are included in the highest confidence group in the \nCEC’s data center forecast. Cal Advocates stated that the CEC’s current confidence \ngroups may be insufficient to curb speculative load additions. The CAISO notes that the \nCEC is currently reviewing its data center forecast confidence level definitions in the \n2026 Integrated Energy Policy Report process.  \n \nThe CAISO reiterates that the PTOs have methods to evaluate the viability of specific \nload interconnection requests, and the CAISO expects PTOs to substantiate those \nmethods in their proposed tariff filings. The CAISO will work with PTOs during the study \nprocess to further consider the viability of these requests in the transmission planning \nprocess and through concurrence. \n \nConsideration of Advanced Transmission Technologies  \n \nThe CPUC noted that the need for EMT study data is also being evaluated in other \nforums such as IEEE 1547.7 and NERC. State entities will need to formulate how these \ndata will be collected and stored to ensure their consistent availability at a central, \nknown location when required. The CPUC suggested that CAISO take a lead role in \npreparing and maintaining the state’s EMT data. Voltus asked CAISO and PTOs to \napply a technology-neutral standard for ATTs that would include contracted demand \nresponse and distributed energy resources (DR/DER) in the same way CAISO already \nevaluates hardware options: in the generator interconnection cluster study, in CAISO's"},{"page":26,"startToken":9038,"endToken":9479,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 25 \n  \nannual Transmission Plan reporting, and in the concurrence process. The CAISO \nincorporates demand response and distributed energy resources into the transmission \nplanning process via the CEC’s statewide demand forecasting efforts. Both types of \nresources with the appropriate attributes are considered as inputs to the transmission \nplanning process to reduce the need for new transmission. The CAISO proposes \nclarifying how demand response and distributed energy resources are included in these \nprocesses in its tariff. \n \nProposal \nAs a minimum standard, the CAISO expects the PTOs to develop consistent study \nprocedures to be completed within 60 to 90 days, as required by the Commission. In \naddition, the CAISO proposes a number of data requirements for the large load \ninterconnection study procedures, described in Section A.4, to ensure the CAISO has \nthe necessary information to account for such flexibility. \n \nThe CAISO agrees with the Commission’s concerns in the Order that information in the \nlarge load interconnection study process regarding a large load’s willingness to limit \nenergy withdrawals under certain conditions is important for the CAISO’s planning and \noperational purposes. The CAISO therefore proposes a framework for agreements \nunder which large loads commit to limiting energy withdrawals under the flexible load \ninterconnection service offerings described in Section D of this draft final proposal.  \nThe CAISO proposes to clarify in its tariff that the current process requires load \ninterconnection requests to be submitted to the appropriate PTO pursuant to the PTO \ntariffs. The CAISO currently accounts for those load interconnection requests in the \nannual TPP and to some extent in the CAISO Resource Interconnection Standards \n(RIS). The CAISO proposes both clarifying and continuing this process in its tariff. In \naddition, the CAISO proposes enhanced data sharing and process alignment between \nthe CAISO and the PTOs to further streamline the load interconnection request and \nstudy process. \n \nAs noted earlier in this draft final proposal, the CAISO does not propose changing the \nallocation of rights and responsibilities for studying large load interconnection requests \nfrom the framework in place today: the PTOs will continue to manage the bulk of the \nstudy responsibilities. This has been a highly efficient and effective process, to date, \nand the CAISO expects that it can continue to be so with the influx of large load \ninterconnection requests. The CAISO encourages the PTOs to align their load \ninterconnection study procedures among themselves and with the CAISO resource \ninterconnection standards and TPP for enhanced clarity and consistency for customers. \nThis PTO alignment will enable the CAISO and PTOs to fully capture the transmission \nsystem impacts of providing such transmission service by applying consistent study"},{"page":27,"startToken":9479,"endToken":9886,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 26 \n  \nparameters, and to minimize operational risks to the system through a common study \nframework.  \n \nThe CAISO agrees with the Commission and proposes some tariff enhancements to \nensure greater coordination and visibility between the CAISO and PTOs regarding the \nload interconnection study results. This will require continued coordination with the \nPTOs during the study process and will be particularly important for co-located loads \nand generation, discussed in Section C of this draft final proposal, as well as with the \nprovision of flexible interim load interconnection (FILI) service, discussed further in \nSection D of this draft final proposal. \n \nThe CAISO acknowledges multiple possible configurations of large loads and co-\nlocated loads, each of which may necessitate unique information to fully mitigate \noperational or reliability concerns. These various configurations are described in Section \nC of this draft final proposal on co-located loads. Each will have different implications on \nthe CAISO’s generator interconnection study requirements. Co-located loads with \nexporting generation (existing or new), for example, will need parallel review by the \nCAISO and the relevant PTO.  \n \nThus, the CAISO proposes a new requirement for co-located loads and generation to \nprovide comprehensive information on both the load and generation in the CAISO’s \nresource interconnection process, in addition to the PTO load interconnection \napplication process. The CAISO proposes to establish procedures for the CAISO and \nPTOs to exchange and compare information to ensure the respective studies of the load \nand generator are consistent with the customer’s requested mode of operation and type \nof service requested.   \n \nIn light of the need for coordination between the CAISO’s resource interconnection \nstudy process (in which the studies are conducted primarily by the PTOs) and load \ninterconnection studies, the CAISO expects PTOs to propose enhanced alignment of \ntheir load interconnection request windows and study timelines with the CAISO \nprocesses. This is needed for all the information to be communicated back to the \nCAISO in a timely and consistent manner to inform the CAISO’s broader transmission \nplanning, resource interconnection, and deliverability allocation procedures. The CAISO \nnotes that its resource interconnection timeline and transmission planning timelines are \nrelatively bound in its tariff as required by FERC Order Nos. 2023, 1000, and 1920, and \nthe MOU with the California state energy agencies. Therefore, the CAISO expects the \nPTOs will need to update their tariffs to align study processes with one another and in \nconsideration of other related CAISO processes."},{"page":28,"startToken":9886,"endToken":10312,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 27 \n  \nTo ensure clarity on behalf of stakeholders, the CAISO encourages the PTOs to \nestablish tariff revisions describing study timelines and procedures for the transmission \nservice needed on behalf of large loads, types of network upgrades considered, and \nmethods to determine required network upgrades to provide the requested transmission \nservice.27 The CAISO believes that a high degree of consistency would be useful across \nPTO tariffs to ensure timeline alignment, process efficiencies, and utility of data. In \naddition, the CAISO proposes to define in its tariff any instances when the CAISO would \nreject load interconnection study results or decline to consider or approve associated \ntransmission solutions through the TPP; these conditions include instances when PTO \nstudy results indicate high operational risk or uncertainty, or would interfere with CAISO \ncompliance with balancing authority, transmission operator, or reliability coordinator \nreliability standards.   \n \nThe most effective way to ensure load associated with new large load interconnections \nis reflected in CAISO’s TPP is to work with CEC to reflect this new load in CEC’s \ndemand forecast before CEC finalizes its forecast in the December timeframe each \nyear. While the aim is for load forecasts incorporated into CAISO’s TPP to include all \nanticipated load, there are instances where new load seeks to interconnect after \ndevelopment of the demand forecast and CPUC resource portfolios that the CAISO \nincorporates into its TPP. Currently, to address these instances, the PTOs may submit \nproposals for the CAISO’s concurrence in the transmission plan. The concurrence for \nload interconnections only considers the transmission component of the load \ninterconnection (i.e., the network upgrades). The CAISO reviews and provides \nconcurrence that the load interconnection and potential network upgrades to \ninterconnect the load meet the transmission reliability requirements and are consistent \nwith the long-term transmission plans in the area.  \n \nTo address FERC’s Order, the CAISO proposes to clarify within its tariff how the \nconcurrence process addresses local network needs associated with large load \ninterconnections. Specifically, the CAISO will conduct an engineering review for \nreliability and operations of PTO-proposed solutions.   \n• Proposed solutions with previously-approved network upgrades or upgrades \nidentified in the load interconnection study with an expected in-service date later \nthan the large load interconnection date, would not be eligible to receive firm \nservice until the network upgrade is placed into service. These projects would be \ncandidates for the FILI process. \n• \nLocal network upgrades would be identified by the PTO in the load \ninterconnection study with cost responsibility determined pursuant to the \napplicable PTO tariff. \n \n27  \nId. at P 54."},{"page":29,"startToken":10312,"endToken":10761,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 28 \n  \n• \nArea network upgrades would need to be studied in the Transmission Planning \nProcess. If the TPP identifies the need for the upgrade, the large load would be a \ncandidate for FILI. \n \nThe CAISO also proposes to specify in its tariff a process for reviewing and \ndocumenting load interconnection requests through concurrence in the Transmission \nPlanning Process to ensure reliability and consistency with long-term plans. The CAISO \nwill review potential out-of-cycle transmission additions or upgrades to accommodate \nLarge Loads on a monthly basis, and to fit within the 60-90 day process for PTO load \ninterconnection studies. \n \nIn addition, consistent with existing planning processes, the CAISO proposes that it will \ncontinue to evaluate transmission system impacts of distribution-connected loads where \nthose loads trigger a need for transmission network upgrades on the CAISO controlled \ngrid. This proposal is consistent with current processes, under which the CAISO studies \ninstances in which load interconnections trigger network upgrades their impacts on the \nsystem as part of the TPP via the concurrence process. The proposal affirms this \napproach, and maintains current roles and responsibilities, regardless of whether the \nload addition is transmission- or distribution-connected.  \n  \nAs discussed in Section A.2, (Large Load Application Process), the CAISO requests \nthat the PTOs clarify in their tariffs the responsibilities of non-load serving PTOs’ \nfacilities receiving load interconnection applications from the LSE, and which party will \nlead the study process. If a PTO uses this concurrence process, the CAISO also \nexpects the PTO to inform the CEC of its load interconnection so the CEC can account \nfor this load in its demand forecast in subsequent forecast cycles.   \n \nRegarding FERC’s concerns regarding speculative or duplicative large load \ninterconnection requests, the CAISO agrees that its tariff does not deter such requests \nper se but suggests that the responsibility to do so is more appropriately held by the \nPTOs and therefore should be addressed through revisions to the PTOs’ tariffs. For \nCAISO planning purposes, the CAISO notes that the CEC’s Integrated Energy Policy \nReport (IEPR) long-term demand forecast includes information on applications for \nservice submitted to utilities and applies adjustments to requested capacity based on \nutilization factors, confidence levels, and ramping assumptions.9 Confidence levels are \ndetermined based on the status of project applications, and take into account the \npotential for duplicative requests, among other factors. If projects have signed \nagreements with the utility for electric service, they are included in the highest \nconfidence group. The CEC demand forecast projects capacity and energy needs of \nnew loads, and these new loads have been incorporated into the statewide planning \nprocesses for the past several years. The state’s integrated resource planning and the"},{"page":30,"startToken":10761,"endToken":11124,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 29 \n  \nCAISO’s TPP incorporate this information. This is one mechanism to guard against \nspeculative or duplicative large load interconnection requests forming the basis of \ninfrastructure planning in the CAISO. Additional mechanisms may be appropriate in the \nPTOs’ tariffs. \n4. \nOperational Requirements  \nThe Commission preliminarily found in the Order that the CAISO’s and PTOs’ tariffs \nappear to be unjust and unreasonable because they lack provisions addressing ongoing \noperational requirements for Eligible Customers taking transmission service on behalf of \nlarge loads.28 The Commission enumerated specific examples, including the lack of \nprovisions governing hourly forecasts, telemetry data, equipment to enable the CAISO \nto monitor large loads; requiring the transmission customer to enable the CAISO to \nremotely disconnect large loads when necessary to maintain reliability; ramp rate or \nride-through requirements; and control technologies and/or protection systems that may \nbe necessary to limit Eligible Customer’s withdrawals from the transmission system.29 \n \nBackground and Stakeholder Comment \n \nSeveral stakeholders supported clearly defined operational requirements for large loads \nwhere requirements are necessary to support grid operations, including Tesla, \nMicrosoft, Constellation, and BAMx. CalCCA requested that the CAISO clearly articulate \nthe underlying issue these information requirements are proposed to mitigate to allow \nfor a more informed discussion of the appropriate data requirements and best methods \nfor obtaining the data before adopting final requirements, noting that much of the \nproposed information will originate with the large load customer and may include \ncommercially sensitive operational information. Tesla asked the CAISO to keep \nrequirements performance-based and technology-neutral. LSPGC and DesertLink noted \nthat non-load-serving PTOs may not have access to the information required to be \nshared with the CAISO in the straw proposal. \n \nThe CAISO appreciates stakeholder support for clearly defined operational \nrequirements for large loads. The LLTRWG continues to evaluate and document the \ntechnical rationale, intended use, and relevant industry practices supporting each \nrequirement. The LLTRWG will continue to refine the proposed requirements as \nappropriate, including ensuring that they are performance-based and technology-\nneutral. The CAISO will continue to seek opportunities for coordination and \ntransparency, as appropriate, without sharing commercially sensitive information.  \n \n28  \nOrder to Show Cause at P 63. \n29  \nId."},{"page":31,"startToken":11124,"endToken":11458,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 30 \n  \n \nNeed for Additional Forecasting, Telemetry, and Operational Visibility Requirements \n \nCDWR, Constellation, Microsoft, KiritiGrid, BAMx, PG&E, and Viridon generally \nsupported CAISO's proposal to establish enhanced forecasting, telemetry, and \noperational data requirements for large loads, noting that these resources often exhibit \ncharacteristics that differ from traditional conforming load and may require additional \ndata to support reliable operations. CDWR specifically supported efforts to address \nforecasting gaps associated with large loads, while BAMx emphasized that forecasting \nshould reflect the operating characteristics of the service being provided.  \n \nThe CAISO agrees that large loads require additional operational visibility beyond \nexisting forecasting approaches. As large loads become a more significant component \nof system demand, the CAISO intends to establish requirements that provide visibility \ninto expected load behavior, outages, operating limits, and operational flexibility while \nremaining focused on information necessary to support reliable grid operations. \n \nForecasting Requirements, Data Requirements, and Implementation \n \nCDWR, SCE, Constellation, Trimark, and the CPUC requested additional details \nregarding forecasting requirements, telemetry specifications, reporting timelines, \nforecast accuracy expectations, data exchange protocols, and implementation \nprocesses. CDWR requested further details regarding forecast requirements and \ntelemetry obligations. SCE sought additional discussion regarding forecast accuracy \nstandards and implementation mechanics. Constellation requested greater clarity \nregarding integration of forecasts into day-ahead and real-time processes. Trimark \nrequested more specificity regarding telemetry architecture and communications \nprotocols. The CPUC requested additional clarity regarding reporting schedules and \ncoordination processes. The CAISO acknowledges these requests and agrees that \nadditional implementation detail will be necessary as the proposal progresses. While \nthis initiative is intended to establish the operational requirements necessary to address \nthe Commission's concerns, more detailed implementation requirements will be \ndeveloped through business practice manuals and implementation working groups, \nincluding clarification regarding required information, submission timing, and reporting \nprocesses. \n \nRoles and Responsibilities for Forecasting and Data Submission \n \nStakeholders expressed differing views regarding responsibility for providing large load \nforecasts, telemetry, outage information, and other operational data. Constellation, \nViridon, and PG&E generally supported utilizing existing LSE and Scheduling"},{"page":32,"startToken":11458,"endToken":11822,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 31 \n  \nCoordinator structures for operational forecasting and market-related communications, \nwhile NCPA argued that these responsibilities should instead reside with PTOs or large \nload customers because PTOs generally maintain the contractual relationships \nnecessary to obtain and validate the information. ACP-CA, Lotus, and SDG&E similarly \nraised concerns regarding responsibilities applicable to non-IOU entities and forecasting \nsubmissions.  \n \nThe CAISO clarifies that the Scheduling Coordinator representing the LSE’s service \narea for the large load will include the large load in its Bids, Scheduled Demand, and \nMeter Data, as applicable, for that area. Where permitted by the applicable Local \nRegulatory Authority, a large load may elect to participate directly through its own \nScheduling Coordinator consistent with proposed tariff language. \n \nCoordination Across PTOs, UDCs, LSEs, and Non-IOU Entities \n \nACP-California, CPUC, Microsoft, Viridon, PG&E, and VEA requested additional clarity \nregarding coordination and information-sharing responsibilities among PTOs, UDCs, \nLSEs, Scheduling Coordinators, and large load customers. ACP-California emphasized \nthe need to ensure the requirements are workable for non-LSE PTOs, municipal utilities, \nand UDCs. The CPUC highlighted the need for transparency and coordination across \nmultiple PTO territories to guard against speculative interconnection requests, Microsoft \nencouraged coordination and avoidance of duplicative obligations, Viridon and PG&E \nsupported a formal information-sharing framework, and VEA requested flexibility for \nentities other than the LSE to schedule large load demand.  \n \nThe CAISO agrees that successful implementation will require coordination among \nPTOs, UDCs, LSEs, Scheduling Coordinators, and large load customers. The CAISO \nintends to identify the operational information necessary to support reliable grid \noperations and establish clear requirements regarding the information that must be \nprovided to the CAISO. The CAISO continues to expect that Scheduling Coordinators \nand LSEs will be responsible for coordinating the collection and submission of required \noperational forecasting information within existing market frameworks. The CAISO's \nobjective is to establish clear and consistent information-sharing requirements while \navoiding duplicative reporting obligations and ensuring that entities with operational \nresponsibilities have access to the information needed to support reliable system \noperations. \n   \nAlignment Between Forecasting, Flexibility Products, and Planning Assumptions \n \nBAMx, the CPUC, and KiritiGrid argued that forecasting requirements should \nappropriately reflect the flexibility, curtailment rights, and operating characteristics"},{"page":33,"startToken":11822,"endToken":12183,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 32 \n  \nassociated with the service being provided and maintain consistency with planning and \ninterconnection assumptions. BAMx asserted that forecasting should be aligned with the \napplicable service type and updated as service characteristics change, KiritiGrid \nsupported forecasting requirements while emphasizing the importance of information \nregarding expected curtailment exposure, and the CPUC requested additional clarity \nregarding the relationship between upgrades, planning assumptions, and operational \nprocesses. The CAISO agrees that operational forecasting requirements should reflect \nthe operating characteristics of the service being provided, including applicable \noperating limits, outages, derates, and available flexibility. The CAISO expects \nsubmitted schedules to accurately reflect the operational capabilities and constraints \napplicable to the load, including any flexibility associated with the applicable service \ntype. This information is necessary to support reliable system operations and situational \nawareness. The CAISO intends to ensure that forecasted operational information \naccurately reflects expected operating conditions and material changes in load \ncharacteristics. \n \nImplementation Timing and Market System Readiness \n \nPG&E, CDWR, and SCE raised concerns regarding implementation timing, software \nmodifications, business process changes, and the ability of existing systems to \naccommodate new forecasting requirements. PG&E noted that substantial software and \nprocess modifications may be required and expressed concerns regarding \nimplementation by 2027, CDWR highlighted existing functionality gaps related to real-\ntime scheduling adjustments, and SCE requested additional discussion regarding \nimplementation pathways and operational impacts. The CAISO acknowledges these \nconcerns and recognizes that some forecasting, telemetry, and operational visibility \nrequirements may require systems development, process enhancements, and \nadditional coordination among market participants. Consistent with stakeholder \nfeedback, the CAISO will further clarify implementation details, including data \nrequirements, submission mechanisms, and implementation timelines. This will be done \nthrough business practice manuals and implementation working groups prior to \nimplementation. \n \nGeneral Support for Technical Requirements and Continued Technical Development \n \nBAMx, Constellation, PG&E, SCE, SDG&E, VEA, and Tesla generally supported the \ntechnical requirements developed through the LLTRWG, including ride-through \ncapabilities, post-fault active power recovery, ramp-rate limitations, telemetry, \nmonitoring, modeling, commissioning requirements, and future technical development \nefforts. The CAISO believes the proposed requirements represent an important step \ntoward ensuring the reliable interconnection and operation of large loads. As stated"},{"page":34,"startToken":12183,"endToken":12502,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 33 \n  \nabove, the CAISO intends to continue evaluating implementation considerations as \nproposal development progresses and will seek practical approaches that achieve the \nintended reliability benefits while allowing sufficient time for required systems and \nprocess modifications. Consistent with stakeholder feedback, the CAISO will further \nclarify implementation details, including data requirements, submission mechanisms, \nand implementation timelines, through business practice manuals, and implementation \nworking groups prior to implementation. \n \nNeed for Consistency Across PTOs, NERC Standards, Tariffs, and Planning Standards \n \nThe CPUC, Constellation, Microsoft, LSPGC and Desert Link, and SDG&E requested \nthat technical requirements be implemented consistently across PTOs and aligned with \nevolving NERC reliability standards, CAISO tariffs, business practice manuals, and \nplanning standards. The CPUC and Constellation emphasized alignment with NERC \nstandards, Microsoft requested clear documentation and coordination across PTOs, \nLSPGC and Desert Link recommended incorporation of system-wide requirements into \nCAISO Planning Standards, and SDG&E requested clarification regarding where \nrequirements would ultimately be codified. The CAISO agrees that consistency, \ntransparency, and coordination are important objectives and intends to continue \ncollaborating with industry reliability efforts while evaluating the appropriate \nmechanisms for implementation through tariff provisions, business practice manuals, \nplanning processes, and other governing documents as appropriate. \n \nTechnical Telemetry, Phasor Measurement Unit (PMU), Communications, and \nMonitoring Specifications \n \nTrimark, ACP-California, and Microsoft requested additional details regarding telemetry \nrequirements, PMU deployment, monitoring obligations, communications architectures, \ndata protocols, and performance standards. Trimark specifically requested technical \nspecifications regarding telemetry data requirements, communications architecture, \nredundancy standards, and PMU requirements. ACP-California highlighted \nimplementation and cost recovery considerations associated with monitoring and \ntelemetry equipment, and Microsoft requested that requirements avoid duplicative \ntelemetry and compliance obligations.  \n \nThe CAISO acknowledges these requests and intends to continue working with PTOs \nand stakeholders to develop appropriate technical specifications and communications \nrequirements while leveraging existing infrastructure where practical and avoiding \nunnecessary duplication of monitoring, reporting, or communications obligations. \n \nCost Allocation for Technical Requirements"},{"page":35,"startToken":12502,"endToken":12880,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 34 \n  \n \nBAMx and ACP-California commented that costs associated with technical compliance \nrequirements, monitoring equipment, telemetry, and related infrastructure should \ngenerally be assigned to the large load customer creating the need for those \nrequirements. BAMx specifically recommended allocating compliance costs to the large \nload, while ACP-California highlighted implementation and cost recovery considerations \nassociated with monitoring and telemetry requirements. The CAISO acknowledges \nthese comments and notes that the purpose of this part of the initiative is to establish \nthe technical requirements necessary to support reliable operation of the system.  \n \nEMT Studies, Modeling Requirements, and Load Characterization \n \nCDWR requested additional rigor related to EMT studies and sought assurance that \nchanging load characteristics would continue to be accurately represented after \ninterconnection. CDWR encouraged broader application of EMT studies and questioned \nhow load characteristics would continue to be represented when software, hardware, \ncustomer composition, or operating practices evolve over time. \n \nThe CAISO agrees that accurate modeling and appropriate study methodologies are \nimportant to evaluating the reliability impacts of large loads. Consistent with the ongoing \ntechnical requirements effort, EMT studies will be performed where warranted based on \nsystem conditions, project characteristics, and engineering judgment. The CAISO also \nagrees that material changes in large load operating characteristics may have reliability \nimplications and intends to maintain sufficient visibility into those characteristics to \nsupport ongoing reliability assessments and operational decision-making. \n \nAdditional Technical Requirements for Large Loads with FILI Service  \n \nSeveral stakeholders identified additional technical requirements that may be \nappropriate for FILI and FLIP service. Antora, BAMx, ACP-California and others \nemphasized the need for clearly defined and enforceable curtailment performance, \nincluding response times and operating limits, supported by appropriate telemetry, \ncommunications, controls, and verification. Antora also suggested capabilities such as \nautomatic emergency curtailment and remote disconnection, while BAMx emphasized \nensuring that the flexibility assumed in planning is consistent with actual operating \nperformance and re-verified when the service arrangement changes. The CAISO \nappreciates stakeholder feedback regarding additional technical requirements for FILI \nservice, and proposes additional details in the proposal below and in Section D. The \nCAISO agrees that any flexibility relied upon in planning and operations should be \nsupported by appropriate performance, monitoring, communication, and control \ncapabilities to ensure that curtailment can be implemented and verified when required."},{"page":36,"startToken":12880,"endToken":13246,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 35 \n  \nThe CAISO will continue to coordinate with the PTOs to determine the appropriate \nrequirements and where those requirements should be established. \n \nRemote Disconnection and Communications Requirements \n \nStakeholders generally supported maintaining reliable communication channels but \nexpressed differing views regarding whether the CAISO should possess authority or \ncapability to directly disconnect large loads. SDG&E, SCE, and Viridon argued that \nPTOs, UDCs, or retail service providers should continue to execute physical \ndisconnection actions pursuant to CAISO instructions, citing customer relationships, \njurisdictional considerations, and existing operational practices. The CPUC emphasized \nthe importance of reliable communications and control capabilities during major \ndisturbances, while PG&E noted that some large loads may require monitoring, control, \nand automated load reduction capabilities to support reliable operations. The CAISO \nagrees that reliable communication channels are important to maintaining system \nreliability and notes that existing reliability procedures already rely on the CAISO issuing \noperating instructions while PTOs execute required switching actions. The CAISO does \nnot envision direct physical disconnection of large loads by CAISO personnel and \nexpects any necessary load reduction or disconnection actions to continue to be \nimplemented through established coordination procedures between the CAISO and the \napplicable PTO or other responsible entity. \n \nProposal  \n \nThe CAISO agrees that the operational requirements the Commission identifies in the \nOrder are necessary. The CAISO has been exploring these issues through discussions \nwith PTO representatives in the LLTRWG, and through engagement with NERC. The \nLLTRWG was established by the CAISO and utilities interconnecting large loads to \ndevelop consistent technical requirements for the reliable interconnection and operation \nof large data center loads connected to the CAISO-controlled grid. The resulting Large \nLoad Technical Requirements Straw Proposal, released on June 15, 2026, focuses on \nthe technical characteristics needed to maintain system reliability as large data center \nloads, including AI-training data centers, continue to grow within the CAISO footprint.30 \nThe Large Loads Technical Requirements Straw Proposal complements broader \nstakeholder efforts addressing planning, transmission service, market, and operational \nconsiderations, and is intended to remain aligned with evolving NERC Reliability \nStandards and industry practices.  \n \n \n30  \nSee Large Load Technical Requirements - Straw Proposal at \nhttps://stakeholdercenter.caiso.com/InitiativeDocuments/Large-Load-Technical-Requirements-Straw-\nProposal-Jun-15-2026.pdf"},{"page":37,"startToken":13246,"endToken":13542,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 36 \n  \nThe Large Loads Technical Requirements Straw Proposal proposes technical \nrequirements in the following areas, which the CAISO intends to continue to further \ndevelop through ongoing discussions with the LLTRWG and based on stakeholder \ncomments in response to the Large Loads Technical Requirements Straw Proposal:  \n \n• \nFrequency ride-through  \n• \nVoltage ride-through  \n• \nRamp-rate limitations  \n• \nMonitoring and telemetry  \n• \nPost-fault active power recovery  \n• \nModeling data requirements  \n• \nCommissioning, including data verification and model validation  \n \nThe Large Loads Technical Requirements Straw Proposal is intended to establish \ntechnical reliability requirements for the reliable interconnection and operation of large \nloads. Many of the proposed requirements address the technical operational concerns \nthe Commission identifies in the Order. The Large Loads Technical Requirements Straw \nProposal also identifies areas for which the LLTRWG is currently developing technical \nrequirements that the Commission does not mention in the Order, including low- and \nhigh-frequency cycling, constant power operation, power quality, dynamic reactive \npower support, phase-angle jump ride-through, protection requirements, and other \nemerging technical considerations. \n \nBased on discussions within the LLTRWG and coordination between the CAISO and \nparticipating PTOs, the CAISO proposes that the following requirements be addressed \nthrough the CAISO Tariff: \n• \nEstablish ramp-rate requirements; \n• \nEstablish frequency and voltage ride-through requirements; \n• \nRequire hourly forecasts, telemetry, and other operational data necessary to \nprovide the CAISO with sufficient operational visibility; \n• \nUtilize communication protocols for the CAISO to coordinate with the PTO to \nremotely disconnect large loads when necessary to maintain transmission \nsystem reliability, and; \n• \nEstablish requirements for maintaining communication channels between the \nCAISO and transmission customers serving large loads. \n \nThe CAISO proposes that the following requirements be addressed through the PTO \ntariffs: \n• \nRequire installation of phasor measurement units (PMUs) or similar high-speed \nmonitoring equipment, with associated costs assigned to the transmission \ncustomer, and;"},{"page":38,"startToken":13542,"endToken":14002,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 37 \n  \n• \nEstablish requirements for control technologies and/or protection systems, when \nnecessary, to limit large load withdrawals from the transmission system. \n \nThe LLTRWG continues to refine the technical requirements based on stakeholder \nfeedback, additional system studies, operating experience, and the ongoing \ndevelopment of NERC Reliability Standards for computational loads. As the work \nprogresses, the CAISO and participating utilities will determine the appropriate \nimplementation mechanisms. Depending on the nature of each requirement, \nimplementation may occur via changes to the CAISO tariff, PTOs’ tariffs, utility \ninterconnection handbooks, Business Practices Manuals, and/or future NERC Reliability \nStandards, providing a coordinated framework for reliable integration of large loads \nwithin the CAISO-controlled grid. For example, depending on the results of large load \ninterconnection studies, and the type of service provided to the large load \ninterconnection customer (i.e. firm service or FILI), the CAISO and/or relevant PTO may \nrequire additional monitoring, control, or protective systems beyond those required by \nthe CAISO to maintain reliability. Such systems may include automated schemes \ndesigned to reduce or disconnect portions of the large load during abnormal system \nconditions. The CAISO notes that it does not have direct control of switches, so the \nPTOs would need to make sure they have control at the right level. In other words, \nthese requirements would be implemented at the PTO rather than at the CAISO level. \n \nTo ensure the ongoing visibility and operational control necessary to provide reliable \ntransmission service, the CAISO also proposes tariff provisions enabling data \nexchanges with the PTOs and LSEs to ensure access to the following large load \ninterconnection information. Static information about the large loads will come from the \nPTOs near the end of the interconnection process (similar to the new resource \nimplementation process for generators). Day-ahead and real-time information will come \nfrom the LSE scheduling coordinator responsible for the large load’s demand.31  \n \nFor each large load, the CAISO proposes to require the following information from the \nPTOs during, or at the end of, the interconnection process: \n• Information on whether the Eligible Customer is enrolled in a flexible \ninterconnection program, described below in Section D of this draft final proposal; \n• Load type; \n• Variable or flat load designation; \n• Expected hourly operating profile; \n \n31  \nThe CAISO does not propose that the large load be required to have its own scheduling \ncoordinator, nor that large loads be considered as their own LSEs. Rather, large load demand would be \nscheduled by their LSE similar to non-large load demand, and that same LSE would report any material \ndata for the large load. If the large load participates in a CAISO demand response program, then it would \na demand response provider and scheduling coordinator to represent it in the CAISO markets."},{"page":39,"startToken":14002,"endToken":14265,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 38 \n  \n• Location of service; \n• Point of delivery; \n• Connected capacity; \n• Minimum operating level; \n• Maximum operating level; \n• Utility program information;  \n• Any market participation status or expected participation in demand response \nprograms; \n• Maximum operating demand; \n• Minimum operating demand; \n• Curtailment capability; \n• Expected hourly flexibility capability; \n• Ramp-up capability; \n• Ramp-down capability; \n• Expected operating information sufficient to characterize expected load behavior; \nand  \n• For co-located generation that is not exporting or CAISO-participating, all \ngeneration characteristics \n \nThe PTO will be expected to inform the CAISO of any material changes after \nenergization. Any co-located participating generators will still go through the CAISO \ninterconnection and new resource implementation process.  \n \nAdditionally, the CAISO proposes that the large load’s load-serving entity’s scheduling \ncoordinator will provide the CAISO with the following data specific to each large load: \n• Forecast submission requirements,32 which will be incorporated into applicable \nbalancing authority area demand forecasts and operational studies: \no Hourly forecasts of expected load consumption for the Operating Day and \na rolling 7-day period following the Operating Day \no Day-Ahead Forecasts to be submitted no later than 0700 prevailing Pacific \ntime on the day prior to the Operating Day \no Forecasts at the individual large load identifier level \no The schedules are expected to reflect the resource's anticipated operating \ncapability, including planned outages, forced outages, derates, and \napplicable operating limits, including operating envelopes, to ensure \nschedules remain aligned with expected operating conditions. \n \n32  \nThe CAISO tariff will establish conditions under which an interconnecting transmission operator \nmust obtain a schedule/forecast from the Eligible Customer to provide to the CAISO."},{"page":40,"startToken":14265,"endToken":14542,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 39 \n  \n• Real-time forecast updates: Updated forecasts whenever expected consumption \nof the large load materially deviates from previously submitted day-ahead \nforecasts, including: \no Expected energization activities \no Material changes in operations \no Curtailments \no Facility outages \no Co-located generation impacts on the load forecast \no Other known events affecting expected consumption \n• Telemetry data:  \no Operational status \no Real-time consumption \n• Expected outages: \no Planned outages \no Forced outages \no De-rates \no Other operating conditions that materially affect expected consumption \n \nAs described above, the CAISO generally proposes to obtain large load data from the \nPTOs during the interconnection process and the load-serving entities representing the \nlarge load’s demand in market timeframes. The CAISO does not currently propose \nrequiring large loads to have their own scheduling coordinator or other direct \nrelationship with the CAISO; however, this framework may need to change to remain \nconsistent with ultimate NERC requirements for computational loads.  \n \nThe CAISO also notes that it will require the PTO, load-serving entity (LSE), scheduling \ncoordinators, or other appropriate parties to work with the CAISO to provide all available \ndata on any reliability event. Similar to participating generator requirements, this \nrequirement will ensure the CAISO, utilities, regulators, NERC, and WECC have \nsufficient data to conduct meaningful post-event analyses. \n \nThe CAISO also notes that, to the extent that software changes are necessary, the \nCAISO may require additional time beyond 2026 to select a vendor and develop, test, \nand implement the solution. However, the CAISO would seek to begin implementing the \nnecessary software changes in 2027, with automation capabilities deployed on a \nphased basis and full automation targeted for completion by 2030."},{"page":41,"startToken":14542,"endToken":14913,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 40 \n  \n5. \nLarge Load Service Agreements  \nThe Commission preliminarily found in the Order that the CAISO and PTO tariffs lack \npro forma provisions in a transmission service agreement, or other applicable \nagreement, to memorialize the technical and operational terms the Order describes.33  \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO stated its expectation that the PTOs would develop \npro forma agreements to address large load operations and cost shifting prevention. \nPG&E supported PTO development of pro forma agreements to address large load \noperations and cost-shifting prevention, noting that for large loads seeking FILI service \nrequests, PTOs could either develop a single study agreement with a flexible service \naddendum, or separate agreements for firm and flexible interconnection service. The \nCAISO supports either of these options as long as they are consistently developed \namong PTOs. \n \nProposal \n \nThe CAISO proposes that the PTOs develop a consistent pro forma agreements to \nmemorialize the technical and operational terms the Order describes. At this time, it is \nnot clear whether the CAISO should always be a signatory to a three-party agreement \nfor large load interconnections. For example, the CAISO likely would not have any roles \nor responsibilities for the financing and construction of simple network upgrades needed \nfor large loads receiving firm interconnection service. Such arrangements could be \neffectuated through a two-party interconnection agreement between the PTO and the \nlarge load developer, as performed today. On the other hand, for a large load \nrequesting non-firm interconnection service, the PTO may need the CAISO to help \nmemorialize and sign on to the operational procedures necessary to provide that \nservice through new pro forma non-firm service agreements or utilizing the PTO’s two-\nparty interconnection agreement. For co-located large loads with exporting generation, \nthe CAISO will need to be a party to a pro forma agreement that bridges the pro forma \nLarge Generator Interconnection Agreement (LGIA) with the pro forma large load \ninterconnection agreement or negotiate a non-conforming LGIA to account for certain \ndetails of the co-located large load interconnection on an individual basis. The \ndeveloper also would be expected to execute a CAISO pro forma Participating \n \n33  \nOrder to Show Cause at P 64."},{"page":42,"startToken":14913,"endToken":15292,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 41 \n  \nGenerator Agreement for the generator, but not a Participating Load Agreement for the \nlarge load.34 \nB. Cost Shifting Among Transmission Customers \n1. \nRoles and Responsibilities \nThe Commission laid out key objectives regarding cost allocation of infrastructure \nneeds35 attributable to Eligible Customers taking transmission service on behalf of large \nloads: improved transparency regarding the assignment of network upgrades and their \nassociated costs; and development of a pro forma cost recovery agreement between \nthe CAISO, the relevant PTO, and the Eligible Customer taking transmission service on \nbehalf of large loads. The Commission states that improved transparency will provide \nimportant information to state public utility commissions and other state regulators, \nenabling them to identify which transmission costs are caused by which transmission \ncustomers to appropriately sub-allocate costs at the retail level. According to the \nCommission, a pro forma cost recovery agreement would ensure that Eligible \nCustomers bear the risk and are ultimately responsible for the costs incurred to provide \ntransmission service, including the cost of network upgrades.  \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, CAISO proposed that PTO tariffs should set forth cost allocation \nrules and that PTOs should lead in the development of pro forma agreements regarding \nassignments of network costs. Further the CAISO emphasized that, coupled with \nenhanced PTO cost-allocation rules, the existing TAC can sufficiently prevent cost-\nshifting.  \n \nPro forma agreements and standardized frameworks  \n \nIEPA, ACP-California, VEA, CPUC, and Microsoft recommended that there should be a \nconsistent cost-allocation and recovery framework, with IEPA, ACP-California, VEA, \nand the CPUC stating that the CAISO should develop a framework for allocation of \n \n34  \nThe Participating Load Agreement is for loads receiving wholesale service, which are not relevant \nto this initiative at this time.  \n35  \nThe FERC Order to Show Cause defined network upgrades as follows: The term network \nupgrades is used throughout this order to refer to modifications or additions to transmission-related \nfacilities that are integrated with and support the overall transmission system. See pro forma OATT § 1.27 \n(Definitions – Network Upgrades). We note that CAISO’s definition of Network Upgrades applies only to \nadditions, modifications, and upgrades required to accommodate the interconnection of generating \nfacilities. See CAISO Tariff, app. A (Definitions), Network Upgrades (0.0.0). (Footnote 13)"},{"page":43,"startToken":15292,"endToken":15744,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 42 \n  \nFERC-jurisdictional transmission costs that the CAISO and PTOs should then \nimplement through their tariffs. The CPUC encouraged the CAISO to establish minimum \nrequirements for determining cost allocation based on causation. Microsoft \nrecommends that a framework should include safeguards against duplicative cost-\nrecovery that disallows PTOs from recovering local upgrades that the large customer \nalready paid for upfront. Viridon noted that not all PTOs have direct relationships with \nretail ratepayers and that the pro forma agreements should have consistent principles to \nprotect customers against cost shifting. Viridon and PG&E agreed with the CAISO’s \nproposal for PTOs to lead the pro forma agreement. SDG&E, CDWR, VEA, and the \nCPUC recommended that the CAISO be a party to pro forma cost-recovery agreements \nfor large loads.  \n \nThe CAISO agrees with stakeholders that there is a need for a consistent approach to \ncost-allocation and recovery but maintains that these provisions are most appropriately \naddressed in PTO tariffs. While the CAISO anticipates signing certain pro forma \nagreements involving large loads, as mentioned in the straw proposal, it does not \nexpect to sign every agreement between a PTO and a large load developer. At this \ntime, the CAISO does not intend to establish a cost-recovery and allocation framework \nfor the PTOs to use in their tariffs, though it recognizes that one may become necessary \nif inconsistencies emerge among PTO tariff provisions. The CAISO additionally \nrecognizes the ultimate need to bring non-FERC jurisdictional PTOs into alignment with \nthe cost allocation framework of the FERC-jurisdictional PTOs. The CAISO proposes to \naddress this framework in a future CAISO stakeholder initiative and filing, once greater \ncertainty exists around the mechanisms the PTOs propose to adopt to prevent cost-\nshifting under this Order.  \n \nAssignment of costs \n \nStakeholders provided different recommendations for how or whether to assign costs \nassociated with network upgrade costs attributed to large loads. BAMx and NCPA \nrecommended that single large load customers driving network upgrades should be \nrequired to pay for those upgrades, and Constellation also supported assigning \ninfrastructure costs to customers whose infrastructure requests cause those costs. \nCDWR generally supported the CAISO’s efforts to ensure new large loads bear \nequitable responsibility for costs incurred for interconnection and use of the \ntransmission system. Cal Advocates recommended that the CAISO update the straw \nproposal to reflect that PTOs have not established interconnection terms requiring large \nloads to pay for network upgrade costs that address cost shifting. The CPUC was \nconcerned that the straw proposal did not lay out upstream mechanisms to allocate \ncosts to large load customers and recommended that the CAISO and PTOs take \nmeasures to ensure that cost estimates are accurate and that credit and minimum"},{"page":44,"startToken":15744,"endToken":16211,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 43 \n  \ncontributions align with costs to be incurred serving large loads. Google and Microsoft \nsimilarly advocated that customers pay for local upgrades directly driven by large loads, \nwith network upgrades that provide broad system benefits recovered through the TAC. \nIEPA suggested that the CAISO update the proposal to outline how a large load \ngenerator paying for the entirety of a network upgrade that is made available to other \nusers will be reimbursed. Related to the amount that PTOs include into their total \nrevenue requirement, and therefore what’s recovered through the TAC, SDG&E and \nPG&E supported the CAISO’s proposal. SCE was still evaluating whether it believes \nthat the CAISO can comply with FERC’s Order without modifying its tariff to prevent the \nsocialization of high-voltage transmission network upgrades associated with large loads. \nNCPA and CDWR encouraged the CAISO to exercise tariff authority to oversee what \ncosts and network upgrades are included in the TAC and in wheeling charges. BAMx \nrecommended the CAISO re-start its 2018 TAC Structure Enhancements.  \n \nThe CAISO appreciates and shares stakeholder concerns around cost-shifting and \noffers an explanation below of how such cost-shifts can be avoided and that this can be \naccomplished most effectively without fundamental changes to the CAISO TAC.  \n \nThe CAISO emphasizes that the PTOs are responsible for establishing tariffs for their \ncustomers that do not result in cost-shifting between customers of the PTO, with a \nparticular focus on network costs. \n \nThe CAISO also understands that concerns may remain in instances where one PTO \nwith significantly more large load interconnections may incur network costs that drive up \nthe regional high voltage TAC across the CAISO footprint, and describes a solution \nbelow, which is available to the CAISO and PTOs under the current structure and \nCAISO processes. \n \nStakeholders also provided input on network costs incurred for load that does not \nmaterialize as expected, though there was directional alignment among BAMx, SDG&E, \nSWC, LS Power and DesertLink, Cal Advocates, and PG&E that there should be some \nmechanisms in place to protect ratepayers in these instances. Cal Advocates and BAMx \nadvocated a longer payback period to recover upfront costs until load materializes. \nSWC encouraged the CAISO, PTOs, and stakeholders to determine an appropriate \npayback period and BAMx proposed aligning reimbursement periods with the durability \nof the load. SDG&E advocated that the CAISO’s FERC submission should state that an \nadvanced funding requirement satisfies FERC’s requirement that the Eligible Customer \nis responsible for network upgrades and, specifically, that large loads are responsible \nfor the full costs of the network upgrades if the load doesn’t materialize. LSPGC and \nDesertLink supported large load demand that does not materialize should bear risk and \ncost responsibility for network upgrades but should be eligible for reimbursement if the"},{"page":45,"startToken":16211,"endToken":16649,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 44 \n  \nload materializes, with PG&E providing a similar comment that non-large load \ncustomers can be protected from cost shifts with financial assurances and monetary \nprotections. Lastly, Google recommended that the PTOs implement standardized \nratepayer safeguards, such as minimum demand commitments. As stated earlier, the \nCAISO shares concerns about cost-shifting that could result from serving large loads, \nincluding in cases where a large load’s demand does not materialize as expected, \npotentially exposing other customers to these costs. The CAISO expects that the PTO \ntariffs will sufficiently address this risk and expects alignment among the different PTO \ntariffs to account for this risk.  \n \nProposal \n \nThe CAISO shares the objectives of the Order to prevent cost shifting among \ntransmission customers and to ensure that large loads bear equitable risk and \nresponsibility for costs incurred to interconnect, including the cost of network upgrades \nattributed to the large loads. The CAISO understands the importance of maintaining \naffordability while addressing large load integration. \n \nThe CAISO sees value in development of a pro forma cost recovery agreement and is \nworking closely with the PTOs, which are leading development of this agreement, and \ncost allocation rules generally.36 The CAISO believes it is prudent for cost allocation \nrules to be set forth in the PTO tariffs rather than the CAISO tariff. As discussed herein, \nthe PTOs will continue to manage large load interconnections through their tariffs. Many \nof the PTOs also have a direct relationship with their retail ratepayers and the regulators \nof those ultimate rates, including the CPUC. Additionally, the PTOs have worked on \nthese cost allocation issues and have more expertise in cost allocation than the CAISO, \nincluding on large loads. Finally, it is the PTOs that will construct and own the network \nupgrades if required for the large load interconnection. As such, the CAISO does not \npropose to issue a new “top-down” cost allocation solution through its own tariff. The \nCAISO believes that the PTOs may develop their own proposals to address any cost \nshifting, and that the current transmission revenue requirement and credit mechanisms \nin the TAC can accommodate those proposals. The CAISO proposes some metering \nand settlement changes in Section C of the tariff to account for co-located large loads \nand generation.  \n \nThe CAISO recognizes the primary role of the PTOs in establishing just and reasonable \nprovisions in their tariffs applicable to the large load customer taking transmission \n \n36  \nThe cost recovery agreement could be part of the pro forma load interconnection agreement. \nThey are discussed separately here because the Order to Show Cause discusses them as separate \nissues."},{"page":46,"startToken":16649,"endToken":17071,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 45 \n  \nservice on behalf of the end-use customer in order to prevent cost shifting among \ncustomers.  \n \nThe concern is that, to the extent that one PTO (PTO-A) interconnects more large loads \nthan another PTO (PTO-B), the network upgrade costs attributed to large loads in PTO-\nA may drive up PTO-A’s annual transmission revenue requirement that is then summed \nwith all other PTOs’ annual revenue requirements to calculate the CAISO’s regional \nhigh-voltage TAC that is applied to all UDCs and MSSs equally. This could become \ninequitable if the contributions or revenues recovered by the UDC or MSS from the end-\nuse customer are not also used to reduce cost recovery from the entire CAISO \ncustomer base through the CAISO’s TAC. However, the FERC System of Accounts and \nthe requirements in the CAISO tariff already covers this issue.   \n \nTo manage concerns around cost shifting caused by one PTO having a greater number \nof large load interconnections than other PTOs, the CAISO proposes the following: All \nPTOs should take into account the impact of construction contributions, revenues, or \nother cost offsets37 associated with network upgrade costs directly attributed to large \nloads and paid for by the large load customer through the UDC or MSS in determining \nits transmission revenue requirement and its annual transmission revenue credits. This \nwill ensure that only the revenue requirement net of those contributions or revenue \noffsets is used to determine the regional high-voltage TAC set by the CAISO and \nrecovered across all loads and exports.  \n2. \nData Transparency \nIn the Order, the Commission highlighted the need for “the provision of data on CAISO’s \nwebsite in a single location, and in an easily accessible format that is searchable and \nallows users to filter the data, on transmission service provided to Eligible Customers on \nbehalf of large loads, for network upgrades evaluated in the local transmission planning \nprocess that are needed to accommodate transmission service to Eligible Customers on \nbehalf of those large loads, and the costs for those network upgrades.”38  \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO proposed measures to provide additional data to \nincrease transparency related to large loads. Google, NCPA, Viridon, SEIA, KritiGrid, \nPG&E, and BAMx supported the CAISO’s proposal to publicly post additional data \nrelated to large loads and to memorialize the changes in the tariff. Those stakeholders, \n \n37  \nThis includes financial security, minimum demand charges, exit fees, and similar mechanisms the \nOrder mentions. \n38  \nOrder to Show Cause at P 46."},{"page":47,"startToken":17071,"endToken":17533,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 46 \n  \nalong with CalCCA, requested that the CAISO post additional and more granular data. \nPG&E recognized that PTOs will have to provide data to the CAISO and expects that \ndata transparency will be similar to the transparency in the generator interconnection \nprocess and supports the CAISO proposal to enhance transparency regarding large \nload interconnections. BAMx supported increased data transparency and requested that \nthe CAISO regularly disclose data so that stakeholders could evaluate cost exposure, \nincluding which upgrades are customer-financed and which are recovered via the TAC, \nthe aggregate cost and TAC-recovered portion of each project, and the cumulative \ninterconnection impacts of large load interconnections across PTOs. KritiGrid \nrecommended adding expected curtailment exposure as a fourth category to the \nproposed data framework. Google requested that the CAISO provide granular, up-to-\ndate data, with the necessary masking needed to protect customer confidentiality. \nViridon recommended that large load interconnection requests be visible in the TPP \nstakeholder process rather than just through the CEC’s demand forecast and suggests \nthat affected PTOs should receive notice of large load interconnection requests that \ncould impact the non-load-serving PTO. CalCCA commented that the CAISO should \nensure that its processes and procedures are transparent and provide data that are \nsufficiently granular. CalCCA further requested that the CAISO develop a process that \nallows CCAs and other stakeholders to access information on proposed load additions \nto allow external vetting. SDG&E notes that the Order does not require PTOs to \nmaintain spreadsheet with large load additions, noting that it does not plan to develop or \nmaintain a large load interconnection queue spreadsheet.   \n \nSCE, CalCCA, Microsoft, SWC, VEA, the CPUC, and Cal Advocates requested \nadditional granularity about large load additions, including when they trigger \ntransmission network upgrades. CalCCA and the CPUC both suggested that CAISO’s \nproposal to use aggregate data is insufficient, with the former asserting that these data \nmay not be adequate to protect against duplicative or speculative load and with the \nlatter stating it does not meet the Order’s transparency directive. SCE requested \nadditional details on how the CAISO will determine when planned network upgrades are \nneeded to accommodate large loads, identified by type of equipment and upgrade. VEA \nrequested annual monitoring and public reporting of all large load-driving additions to \nPTOs’ revenue requirements. Related to transmission upgrades, Microsoft suggested \nthat the CAISO identify estimated costs, including the assumptions used to derive those \ncosts, expected construction schedules, and required upgrades. Microsoft further \nsuggested that the CAISO should distinguish project-specific upgrades from broader \nsystem upgrades and explain how changes in a project’s scope and timing affect \ncustomer responsibility.  \n \nThe CPUC opposed the use of concurrences as currently employed in the TPP, \nrecommending that the CAISO clearly differentiate upgrades that serve specific"},{"page":48,"startToken":17533,"endToken":17958,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 47 \n  \ncustomers from those benefiting the greater grid. The CAISO reiterates a fundamental \npremise of transmission cost allocation: that customers pay transmission costs to the \nextent they benefit from the transmission. Although a network upgrade may be built as a \nresult of a large load interconnection, the network upgrade itself may benefit a larger \nclass of ratepayers. For high-voltage transmission network upgrades, for example, all \nCAISO ratepayers may benefit. On the other hand, a network upgrade that does not \nbenefit certain ratepayers should not have its costs allocated to them. Low-voltage \ntransmission network upgrades are only allocated to their PTO territory for this reason.39 \nAnd there are always cases where the CAISO and PTOs may file non-conforming \ninterconnection agreements to reflect that the interconnection customer alone benefits \nfrom an upgrade and thus receives all of its costs. Nothing in this initiative proposes to \nchange these fundamental constructs.  \n \nSWC encouraged transparency among the CAISO, PTOs, data center developers, and \nmarket participants throughout the planning, interconnection, and cost-recovery process \nto safeguard against cost-shifting. Cal Advocates stated that the CAISO’s current \nproposal does not provide enough transparency to determine if the network upgrade \nwould be required if not for the large load and recommends that the CAISO establish a \nclear timeline for data releases that align with the TPP or a separate and dedicated \nprocess for large loads, the portion of each network upgrade the large load needs for \nservice, and the cost estimate for each upgrade.  \n \nThe CAISO recognizes stakeholder interest in access to granular data related to large \nloads additions and supports transparency. The CAISO also notes that forecasting and \nstudying specific large load additions occurs through PTO processes and through the \nCEC’s IEPR process. Lastly, as several stakeholders noted, there are data privacy \nrequirements that limit what project-specific information any entity, including the CAISO, \ncould share. Accordingly, the CAISO’s proposed data transparency enhancements, \ncoupled with those mentioned related to the TPP concurrence process, will address \nmost stakeholders requested data additions without violating data privacy requirements, \nand satisfies FERC’s direction on transparency and access. Further, the CAISO \ncontinues to encourage the load interconnecting PTOs to maintain sufficient \ntransparency about large load applications to ensure that stakeholders can accurately \nassess these additions, as called for in the Order.  \n \nProposal \n \n \n39 In other words, the transmission access charge is not a single charge, but many: the regional access \ncharge for high-voltage network upgrades(200 kV+), and the many individual local access charges for \nlow-voltage network upgrades."},{"page":49,"startToken":17958,"endToken":18337,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 48 \n  \nThe CAISO agrees that cost data should be transparent and can be provided on the \nCAISO website in a searchable format. This is important both to aid large load \ndevelopers in making efficient siting decisions as well as to provide information critical \nfor state regulators to ensure fair cost allocation at the retail level.  \n \nFor large load developers, the CAISO notes that for the generator interconnection study \nprocess, the CAISO already provides each PTO’s per unit cost guide for all network \nupgrade cost components.40 These guides are updated and shared with stakeholders \nannually based on the latest industry cost estimates. The CAISO proposes to use the \nper unit cost guides or enhance them as needed to ensure large load developers can \neasily obtain cost data. \n \nFor state regulators and stakeholders, per the Commission’s direction,41 the CAISO also \nproposes to clarify in the TPP where network upgrades were needed to accommodate \nboth general load growth and large load interconnection specifically. Large load growth \nhas already been incorporated into the CEC, CPUC, and CAISO forecasting and \nplanning processes, as detailed in the CAISO’s Informational Report on Resource \nSufficiency already submitted to the Commission.42 The CAISO also proposes to \npublicly post: \n \n1. Aggregate amounts of proposed large load additions in the CAISO operating \narea, including the aggregate amounts in each transmission pricing zone; \n2. Planned network upgrades needed to accommodate Eligible Customers taking \ntransmission service on behalf of large loads, identified by type of equipment and \nnetwork upgrade (e.g., new substation, reconductoring, a new high-voltage \ntransmission line) for each transmission service request; and \n3. Cost estimates for each planned network upgrade identified as needed for large \nloads, as described in (2).43 \n \nThe CAISO proposes to memorialize these transparency requirements in its tariff. The \nCAISO also encourages the PTOs to memorialize tariff requirements to adopt large load \nqueue spreadsheets as it does for wholesale generator interconnection customers. The \n \n40  \nSee CAISO Current cost guides at https://www.caiso.com/library/current-cost-guides. \n41  \nOrder to Show Cause at P 72. \n42  \nSee CAISO Informational Report - Large Loads and Co-located Loads at \nhttps://www.caiso.com/documents/jul-20-2026-informational-report-large-loads-and-co-located-loads-\nel26-71.pdf. \n43  \nOrder to Show Cause at P 75."},{"page":50,"startToken":18337,"endToken":18717,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 49 \n  \nCAISO likewise proposes to include in its queue report whether the interconnection \ncustomer proposes to include a large load, and its capacity.44 \nC. Co-Location Arrangements and Load with Behind-the-Meter \nGeneration \n1. \nTerminology \nFor purposes of the Order, the Commission defined “co-located load” as “end-use \ncustomer load that is physically connected to the facilities of an existing or planned \ngenerating facility on the generator interconnection customer’s side of the point of \ninterconnection to the RTO/ISO’s transmission system.”45 FERC further defined \n“Behind-the-Meter Generation” as “a generating facility that delivers energy to load \nwithout using the transmission system or any distribution facilities.”46 The Commission \ndid not explicitly suggest that the CAISO or PTO tariffs were unjust and unreasonable \nbecause they lack definitions of co-located loads or behind-the-meter generation. \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO agreed with the Commission’s definitions for co-\nlocated load or behind-the-meter generation and did not propose to explicitly define \nthose in its tariff.  \n \nSome stakeholders disagreed with the CAISO not creating formal tariff definitions for \nco-located load or behind-the-meter generation or otherwise requested various \nclarifications. While PG&E agreed that there was a general understanding of the terms, \nit encouraged the CAISO to develop a definition that could capture the existing breadth \nof arrangements to avoid future ambiguities and noted that the Commission may \ndisagree that there is not a need for a tariff definition. AltaGas disagreed with the \nCAISO that co-located load and behind-the-meter generation have plain meanings that \ndid not require formal tariff definitions and stated there was no reason to restrict co-\nlocation to a single site if the large load and resource share the same interconnection \nfacility. The CPUC asserted that some terms remained undefined or unclear, including \ndate of service, time of installation, and operator of co-located generation. The CAISO \nrecognizes that there is no stakeholder consensus on creating formal tariff definitions for \nco-located loads or behind-the-meter generation and notes that strictly defining those \ncould exclude future large load co-location arrangements. Thus, at this time, the CAISO \n \n44  \nSee CAISO Generator interconnection at https://www.caiso.com/generation-\ntransmission/generation/generator-interconnection.  \n45  \nOrder to Show Cause at P 88. \n46  \nId. at P 89."},{"page":51,"startToken":18717,"endToken":19168,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 50 \n  \ndoes not find it prudent to formally define these in its tariff. To the extent that terms \nremain unclear and could confuse co-location arrangements, the CAISO will address \nthose in the future.   \n \nACP-California and SDG&E commented that they saw value in the CAISO including \nadditional examples of how co-located load and generation arrangements would be \ntreated through CAISO interconnection process and recommends that the CAISO \nprovide more descriptions of arrangements that could work under the CAISO’s tariff. As \nstated at the August 19th stakeholder workshop, the CAISO welcomes stakeholders \nwith specific questions about co-location arrangements reaching out to the CAISO. The \nCAISO agrees that further clarity could be helpful, especially between the PTO and \nCAISO interaction and proposes that, for co-location arrangements, the CAISO tariff will \napply to the generation, and the PTO tariff will apply to the load.   \n \nSeveral stakeholders recommended specific clarifications or asked for changes to parts \nof the proposals related to co-located agreements. ACP-California and NextEra \nrequested continued coordination between CAISO and PTOs to ensure that load and \ngeneration interconnection work does not create redundant network upgrades. SEIA \ndisagreed with the CAISO omitting a Bring Your Own Generation (BYOG) proposal and \nrecommended that the CAISO either update that framing or adopt a BYOG framework \nmodeled on Southwest Power Pool’s (SPP) High Impact Large Load Generation \nAssessment (HILLGA). Google recommended that the CAISO adopt an established \nsurplus and provisional interconnection mechanism to allow large loads to pair with co-\nlocated clean energy. The CAISO appreciates the recommendation and has updated \nthe proposal to reflect details the CAISO can provide at this time. However, the CAISO \nreiterates that many of the fundamental details of the load interconnection application \nand study process, including the process for co-located loads, need to be articulated by \nthe PTOs. The CAISO looks forward to working with PTOs and seeing these details in \nthe coming weeks as all parties develop their filings for the Commission. Regarding the \nsuggestion that the CAISO impose a BYOG requirement, the CAISO highlights \nCalifornia’s unique planning structure and MOU with the state agencies and clarifies \nthat it does not have procurement authority to consider such a requirement at this time. \nIn addition, CAISO does not see evidence of a need for a BYOG requirement at this \ntime given the state’s forward resource, transmission, and procurement planning \nregime. Regarding the recommendation to establish provisional interconnection \nmechanism, the CAISO recognizes that there are multiple co-location arrangements, \nincluding potential arrangements that could be considered. The CAISO expects to \ncontinue conversations with the PTOs about this, as well as to consider the potential for \nthese arrangements in a future stakeholder process."},{"page":52,"startToken":19168,"endToken":19631,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 51 \n  \n \nProposal \n \nThe CAISO generally agrees with both definitions proposed by the Commission; \nhowever, the CAISO would exclude from discussion station power load and the \ngeneration that exclusively serves station power load. The CAISO believes the \nCommission is focused on typical end-user loads and not loads facilitating wholesale \npower.47 The CAISO does not believe it is necessary to create formal tariff definitions for \nco-located load or behind-the-meter generation and is not proposing to do so. Both \nterms already have plain meanings, and behind-the-meter is already used frequently \nthroughout the CAISO tariff, including for different configurations based on whether the \nmeter is a CAISO meter or a retail end-user meter. Thus, providing a definition may \nhave inadvertent consequences to the extent it differs in any meaningful respect from \nthe use of these terms currently. The CAISO may provide clarifications if needed in its \nbusiness practice manuals. \n2. \nServing Co-Located Loads \nThe Commission stated in the Order that the CAISO’s tariff does not contain provisions \naddressing with sufficient clarity and consistency the rates, terms, and conditions of \nservice that apply to interconnection customers serving co-located load.48 The \nCommission included, “the scope of the analyses CAISO performs as part of its existing \nstudy process to evaluate the impacts of co-location arrangements, which may need to \naccount for any potential dynamic impacts of co-located load and any potential impacts \nof requests to modify an existing generating facility’s interconnection service level to \nserve co-located load on transmission system reliability.”49 The Commission noted that \nin one of its recent orders on co-located load in the PJM Interconnection (PJM), it found \nthat it was necessary to clarify that interconnection customers seeking to use new \ngenerating facilities to serve co-located load may: (1) request interconnection service at \na level below the generating facility’s maximum facility output; (2) use existing \nprocedures to accelerate interconnection requests that satisfy certain tariff criteria; and \n(3) request provisional interconnection service and surplus interconnection service.50 \nThe Commission additionally noted that interconnection customers should have a \n \n47  \nThe CAISO will continue to expect station power load to be metered separately from other loads \nand generation, consistent with local regulatory authority requirements.  \n48  \nOrder to Show Cause at P 93. The Order to Show Cause has similar discussions of co-located \nloads in Section E, Interconnection Customers Serving Electrically Proximate Large Load and Co-Located \nLoad; however, the CAISO includes all co-location-related proposals here for concision. \n49  \nId. at P 96. \n50  \nPJM Interconnection, L.L.C., 193 FERC ¶ 61,217 at PP 231-235 (2025) (PJM Co-Location \nOrder). PJM’s compliance filing proposing revisions in response to these directives was accepted in part \non April 16, 2026. PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 (2026)."},{"page":53,"startToken":19631,"endToken":20007,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 52 \n  \nmeans of knowing the appropriate mechanism for setting forth the terms and conditions \nof co-location arrangements. The Commission also expressed concern that “without an \nEligible Customer designated to take transmission service on behalf of a co-located \nload, there is no mechanism for CAISO to address situations in which a co-located load \nwithdraws energy from the transmission system.”51 \n \nBackground and Stakeholder Comment \n \nThe CAISO initially proposed clarifying how co-located large loads and generation could \ninterconnect and operate within the CAISO-controlled grid and included proposed data \nrequirements and other process updates that could be required to accommodate these \narrangements. \n \nLarge loads co-location framework \n \nPG&E, IEPA, ACP-California, Pattern, SCE, and Google generally agreed with the \nCAISO’s co-location framework, while requesting clarifications and modifications to the \nCAISO’s proposal on co-located generation and load going through the CAISO’s \ninterconnection process. PG&E supported the CAISO’s proposal and seeks clarification \non the sequencing of the load and generation study components of co-location \nagreements, recommending that the two studies be conducted concurrently. PG&E \nfurther recommended that the CAISO require that new or existing large loads proposing \nto co-locate with new generation that may export to the grid to require a CAISO \ninterconnection study under the CAISO’s Resource Interconnection Standards. The \nCAISO agrees that there is a need to work closely with PTOs on timing and sequencing \nfor studying load and generation and expects to work closely with these entities to align \nprocesses.  \n \nStudy process for co-located arrangements \n \nSome stakeholders either requested specific clarifications on CAISO’s proposal to study \nco-located generation and load or otherwise requested changes to the proposal that \nload and generation stay together through the study process or otherwise re-enter the \nqueue if there are changes. ACP-California and NextEra urged the CAISO to identify \npoints in the generator interconnection process when a load could be removed from the \nstudy process without the associated generator losing its spot in the queue. PG&E \nsought clarification regarding the scope of the restriction on request modifications, \nincluding whether changes to a large load that increase the co-located facility's net \nmegawatt exports to the CAISO-controlled grid would be prohibited or otherwise subject \n \n51  \nOrder to Show Cause at P 96."},{"page":54,"startToken":20007,"endToken":20474,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 53 \n  \nto the restriction. ACP-California further recommended that the CAISO look at ways to \nimprove the study process and procedures for co-located generation and load and IEPA \nproposed that the CAISO initiate a dedicated initiative to study load and generation \ninterconnection process to ensure maximum coordination with the PTOs. SCE \nrequested that the CAISO clarify the study or restudy process if the owner of a co-\nlocated generator changes from non-exporting to exporting and states that the CAISO \nTariff should not allow necessary short circuit studies to be bypassed even if the \ngenerator is not injecting into the CAISO controlled grid. The CAISO recognizes that \nlarge load co-location arrangements could change and proposes allowing \nInterconnection Customers to remove co-located loads from an interconnection request \nin the study process if that removal does not increase the request Interconnection \nService level. The CAISO and PTO would evaluate whether the requested change is a \nMaterial Modification in determining whether it can accommodate the request as is or \nwhether that project would have to re-enter the queue.  \n \nLarge loads co-located with existing generation \n \nStakeholders requested clarifications or refinements to the CAISO proposal for \ngenerators currently interconnected to the CAISO-controlled grid that would serve large \nloads. Constellation supported CAISO’s proposal to not apply a rigid framework to co-\nlocation arrangements and should clarify the pathway via tariff changes. Specifically, \nConstellation proposed that the CAISO update its tariff to clarify the circumstances \nunder which a generator serving co-located load would lose, retain, or partially retain \nwholesale market participation rights; whether Retirement Scenario 3 applies where a \ngenerator continues providing wholesale services; how co-located load will be treated if \nthe associated large load reduces consumption; whether interruptible or dispatchable \nco-located load may participate through a CAISO market construct or as demand \nresponse; how verified load flexibility will affect interconnection and market participation \nrights; whether existing amendment and modification processes can accommodate \nthese arrangements; and the applicable study, operational, metering, telemetry, and \nverification requirements. IEPA, similarly, encouraged the CAISO to establish a tariff \npathway for existing generation resources seeking to serve co-located load with \ncontinuing to provide wholesale energy and reliability service and to provide greater \nclarity on how existing interconnection, amendment, and modification processes may be \nused to accommodate large loads. The CPUC recommended that the state discourages \npairing large loads with existing generation while AltaGas advocated that there is a \nbenefit to the CAISO system by locating large loads at existing generation \ninterconnection sites. AltaGas noted that the co-located configurations offer the \nopportunity to consider a different model: generators that primarily serve associated \nload but (through curtailment of the load or other means) may offer into the market \nand/or follow CAISO Dispatch Instructions when needed and thus may be permitted to"},{"page":55,"startToken":20474,"endToken":20929,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 54 \n  \nretain their net qualifying capacity list and resource adequacy (RA) status. Microsoft \nstated that the CAISO should preserve workable co-location options and avoid rules \nthat foreclose future onsite generation or storage configurations. Trimark recommended \nthat the CAISO provide additional clarification regarding how the New Resource \nImplementation (NRI) process, including which part of the NRI process applies to co-\nlocated large loads, whether a separate resource ID will be required, whether a \nseparate points list will be created for the large load portion of a co-location application, \nand what telemetry points will be required for large loads.  \n \nThe CAISO agrees that continued market participation of generators is one of several \noptions but confirms that existing generators “leaving the grid” to serve associated loads \nmust go through the CAISO resource retirement process so that the CAISO can prevent \nany adverse RA impacts. The CAISO would consider continued market participation \nand RA eligibility in that process. Related to market participation for existing generators \nco-locating with a new large load addition, the CAISO notes that resource adequacy \nrequirements are addressed under existing rules and any future modifications would be \nconsidered through resource adequacy policy initiatives. Potential enhancements to \nlarge load market participation, including participation through demand response, price-\nresponsive load, and other market mechanisms, are being explored through the DDEMI \ninitiative. As noted in other parts of this draft final proposal, the CAISO further \nrecognizes that there are implementation details that will likely require additional \ncoordination among the CAISO, PTOs, large load developers, and others. In the \ncoordination that will continue after the CAISO files its proposed tariff changes, the \nCAISO may consider if additional clarity is needed for specific co-location arrangements \nas projects materialize.  \n \nAccounting for co-location agreements \n \nCDWR and the CPUC raised a related point on co-location: CDWR noted that the straw \nproposal does not address how large loads co-located with generation would be treated \nif that generation is not available and stating that the CAISO should have a mechanism \nin place that ensures that the full load has been studied and costs assessed \nconsistently with load take generation beyond the co-location addition. The CPUC and \nCDWR questioned instances where generation co-located with large loads does not \nserve load as expected. The CPUC advocated for the CAISO to demonstrate that its \nplanning processes account for the possibility that co-located generation could go offline \nand expose the full load to the transmission system, including resource adequacy \nexposure. CDWR encouraged the CAISO to have mechanisms in place to ensure that \nthe full load, regardless of co-location agreement, has been studied to determine what \ntransmission services are needed for these loads. The CAISO agrees with the need to"},{"page":56,"startToken":20929,"endToken":21296,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 55 \n  \nensure that load is backed with sufficient resources and will continue coordinating with \nthe CPUC and other local regulatory agencies on resource adequacy.  \n \nOperational considerations \n \nThe CPUC and IGNIS raised concerns regarding co-located generation and large load \narrangements. The CPUC expressed concern that such configurations could introduce \noperational complexity, reliability risks, safety concerns, and incentives for the return of \nretired generation facilities, while IGNIS cautioned against the future introduction of site-\ndefinition criteria based on physical proximity or other factors that may not be reflected \nin existing regulatory definitions. The CAISO recognizes that co-located generation and \nlarge load configurations can present unique operational, planning, and reliability \nconsiderations. However, the purpose of this initiative is not to establish a \ncomprehensive framework governing co-location arrangements or modify existing \nregulatory definitions. The CAISO will continue to monitor developments in this area and \nevaluate associated reliability implications through ongoing stakeholder and reliability \nprocesses. \n \nProposal \n \nThe CAISO proposes to clarify how co-located large loads and generation may \ninterconnect to and operate within the CAISO-controlled grid. Such clarifications will \nrequire discussion and agreement with the PTOs. The CAISO reiterates that the PTOs \nwill continue to govern and study all load interconnection requests pursuant to their \ntariffs. The CAISO, likewise, will continue to govern and study wholesale generation \ninterconnection requests. Despite the Commission’s concerns, large loads and co-\nlocated configurations have materialized in California under the current tariffs. \n \nNevertheless, the CAISO proposes to clarify in its tariff co-location arrangements that \nwould not require a CAISO resource interconnection request and could be \naccommodated through applicable PTO or CPUC-jurisdictional retail interconnection \ntariffs, such as Rule 21.52 These would include large loads with back-up generation only \nto be used during outages or islanding, and large loads with non-exporting behind-the-\nmeter generation.53 The CAISO notes that both categories would require sufficient \ncontrol technologies to ensure they do not impact the transmission grid.   \n \n \n52  \nSee CPUC’s Electric Rule 21: Generating Facility Interconnections for more information on each \nCPUC jurisdictional LSEs’ Rule 21 tariff at https://www.cpuc.ca.gov/Rule21/.  \n53  \nThe sequencing likewise would not impact whether a CAISO interconnection study would be \nrequired."},{"page":57,"startToken":21296,"endToken":21742,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 56 \n  \nThe CAISO proposes that new or existing large loads seeking to co-locate with new \ngeneration that may export energy to the transmission grid54 will require a CAISO \ninterconnection study under the CAISO’s Resource Interconnection Standards, \nAppendix KK to the CAISO tariff. This means that such resource interconnection \nrequests would be screened and compete for capacity in the next cluster study based \non the CAISO’s scoring criteria.55 However, all scoring, financial requirements, and \nstudy results would be based on the requested capacity figures the developer provides, \nso the developer may significantly limit the generation potentially to be exported based \non how much generation will serve the large load. The CAISO tariff will require it to work \nwith the PTOs to produce study results that reflect the combined impact of the co-\nlocated large load and generation, as requested by the developer. This is a simple \nextension of current rules that allow interconnection customers to be studied for a \nspecific interconnection capacity even if their generating capacity is higher. \nInterconnection requests with co-located large loads may avail themselves of all rights \nunder the Resource Interconnection Standards, including surplus interconnection \nservice, grid enhancing technologies, phasing, etc.  \n \nDespite the ubiquity of co-located resources in California, to date, the CAISO has not \nreceived any interconnection requests for co-located load with exporting or participating \ngeneration, nor has any developer asked for such an option. The CAISO may be in a \ndifferent situation than other regions that needed to impose bring-your-own generation \nrequirements to address capacity market issues. Because the CAISO does not have a \nbring-your-own generation requirement and LSEs are not required to procure new \ncapacity to interconnect new loads, developers have been less interested in co-locating \nload and participating generation. Additionally, to the extent large loads have brought \ngeneration to serve onsite load, they have elected to do so through tariffs for net energy \nmetering, obviating the need for a CAISO interconnection request.  \n \nIn addition to the information required in the CAISO resource interconnection request \nprocess, and the large load operational requirements discussed in Section A.4, the \nCAISO may require the following operational information for co-located resources, if \napplicable: \n• Expected presence of co-located load;  \n• Range of energy consumption characteristics of the load; \n• Minimum and maximum generator operating capabilities; \n• Generator operating characteristics when the load is at its minimum level; \n• Market participation status, if any; and,  \n \n54  \nFrequently, constantly, or even rarely, such as in the event the Large Load is offline. \n55  \nAs Energy Only or Deliverable. Energy Only interconnection customers not seeking \nreimbursement for network upgrades are not screened and proceed directly to the cluster study."},{"page":58,"startToken":21742,"endToken":22197,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 57 \n  \n• Any load services requested when the generator is off-line \n \nFor co-located large loads and wholesale energy storage, the CAISO notes that the \nstorage and large loads would need to be separate operationally, and all study results \nwould reflect the same. Energy storage resources are fully dispatchable and have \nseparate wholesale meters and settlement. Their energy could not be commingled with \nthe large load such that the large load could take power effectively at a wholesale rate. \nThe large load could otherwise net its withdrawals against behind-the-meter/non-\nparticipating generation and storage.56 \n \nAll network upgrade commercial readiness deposit and generator interconnection \nagreement deposit requirements would treat all network upgrades and interconnection \nfacilities as if they were required for the generation only. However, the PTO also may \napply any unique deposit or financing requirements for the network upgrades and \nfacilities required for large loads, as discussed in Section B.1 regarding cost allocation.   \n \nThe CAISO also proposes to require co-located load and exporting generation studies \nto begin the cluster study process with the large load assumptions, but to allow \nInterconnection Customers interconnection customers to request removal of large load \nchanges for the PTOs and the CAISO to evaluate whether the requested change is a \nmaterial modification. (The removal or change to the Large Load would be under the \nPTO tariff.) In other words, after the commencement of the cluster study, the \ninterconnection customer may request to remove the large load as a modification, and \nthe CAISO and PTOs will evaluate whether the requested change can be \naccommodated. Likewise, interconnection customers already in the queue could \nrequest to add large loads as modifications, subject to PTO and CAISO evaluation, \nincluding through downsizing requests as necessary. The CAISO and PTO will assess \nwhether either change would require complete re-studies and could not be \naccommodated during the study process, or if the requested modifications are material. \nThis is not to say that the CAISO proposes to prohibit the addition of large loads to \nexisting generation or in-progress interconnection requests; only that the \ninterconnection customer would need to do so through the PTO tariff, and the \ngeneration interconnection study results may not be able to reflect the combined \nconfiguration if changed substantially after studies commence.  \n \nIf an online CAISO generator seeks to add a large load to its site, the developer would \nsubmit the large load interconnection request to the PTO pursuant to its tariff. When \nready to reflect the large load, the interconnection customer could request a post-\n \n56  \nIn other words, the CAISO does not propose any change to the status quo for separating \nwholesale generation/storage and retail load or net energy metering generation/storage."},{"page":59,"startToken":22197,"endToken":22582,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 58 \n  \ncommercial operation date (COD) modification57 or use the Master File change process \nas needed to assess and capture changes currently allowed under these processes.58 \nThe CAISO, PTO, and interconnection customer could likewise amend the generator \ninterconnection agreement to reflect the large load and any configuration changes.  \n \nThe CAISO reiterates its policy recently approved by the CAISO Board of Governors in \nthe Interconnection Service Capacity and Deliverability Retention for Non-Operating \nGenerating Facilities stakeholder initiative:59 \n \nThe ISO considers any generation that is subject to a [Participating \nGenerator Agreement] and intends to terminate participation in the ISO \nwholesale market but continues generating to serve load through \napplicable retail programs, to also be subject to the retirement process as \na generator that is permanently retiring (Retirement Scenario 3). This \nwould include, for example, distribution-connected or transmission-\nconnected participating resources that wish to exit from the ISO markets \nto serve onsite load. Although such generators will continue to produce \nelectricity, their exit from the wholesale markets will be treated as a \nretirement, including triggering a reliability-must-run review. \n \nThe CAISO does not propose to change its current constructs under Order No. 888 for \neligible customers to obtain transmission service. The CAISO does not have a forward \ncapacity market, nor are LSEs required to procure capacity to obtain transmission \nservice. Transmission service will thus continue to be assumed through an \ninterconnection request, accounting for the large load’s ability to limit its energy \nwithdrawals or injections.60 The large load’s LSE will schedule the large load’s demand \nwith the rest of the LSE’s demand through the CAISO markets, just as it does today. \nThis will continue to enable large loads, co-located or not, to interconnect rapidly and \nwithout extra steps for transmission service. No large load developer to date has \nrequested otherwise. \n \nThe CAISO notes that both loads and generation associated with co-located loads can \nbe eligible for resource adequacy or demand response programs pursuant to current \n \n57  \nSection 25.5 of the CAISO tariff. \n58  \nSee CAISO Master File at https://www.caiso.com/systems-applications/portals-\napplications/master-file.  \n59  \nSee CAISO’s Interconnection service capacity and deliverability retention for non-operating \ngenerating facilities initiative at \nhttps://stakeholdercenter.caiso.com/StakeholderInitiatives/Interconnection-Service-Capacity-\nDeliverability-Retention-for-Non-Operating-Generating-Facilities.   \n60  \nOrder to Show Cause at P 94."},{"page":60,"startToken":22582,"endToken":22979,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 59 \n  \nprogram rules.61 The CAISO does not propose changes to the eligibility criteria for \nparticipation in any of these programs. Participation in demand response programs \nremains a possibility for large loads. The CAISO is exploring such opportunities in the \nDDEMI initiative.   \n3. \nCost Allocation for Co-Located Loads \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO included a proposal to appropriately meter and assess \nregulation and black start services for co-located loads, opted not to revise the current \nconstruct for behind-the-meter generation, gross load, and the TAC, and proposed \nenabling flexibility for large loads to take transmission services that align with their use \nof the transmission system (addressed in Section D). \n \nGoogle and PG&E generally supported CAISO’s proposal for cost allocation for co-\nlocated loads. CDWR commented that the CAISO did not address how netting behind-\nthe-meter generation against load for TAC assessments interacts with how co-located \nloads are studied and assessed for interconnection service. The CPUC asserted that \nthe CAISO did not address FERC’s direction for how netting rules for behind-the-meter \ngeneration for systems greater than 50 MW should be changed in the TAC. The CAISO \nappreciates the complexities and concerns around cost-allocation, which extend to co-\nlocation arrangements. As mentioned in Section B, the CAISO recognizes that PTOs \nwill be responsible for establishing tariffs that prevent cost-shifting among customers, \nincluding for co-location arrangements, while the CAISO transmission revenue \nrequirement and TAC will continue to uphold equitable accounting and prevent cost-\nshifting between PTOs.  \na) \nAncillary Service Charges \nIn the Order, the Commission stated that the CAISO tariff does not appear to include a \nmechanism to charge large loads, and co-located loads in particular, for ancillary \nservices commensurate with their use of such services, particularly if such customers \ndo not withdraw energy from the transmission system.62 Specifically, the Commission \nnoted that co-located loads may unjustly benefit from regulation and black start \nservices.63 \n \n61  \nSection 40 of the CAISO tariff establishes rules about eligible capacity and uses criteria provided \nby the CPUC and other Local Regulatory Authorities determine what projects are RA-eligible. \n62  \nOrder to Show Cause at PP 98-99 (“As noted in the PJM Co-Location Order, this introduces the \nrisk that costs may be allocated entirely to other transmission customers and passed through to \nresidential customers, among others”).   \n63  \nId."},{"page":61,"startToken":22979,"endToken":23401,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 60 \n  \n \nProposal \n \nThe CAISO agrees that assessing ancillary service costs on a net $/MWh basis to \nLSEs’ measured demand would enable a large load co-located with behind-the-meter \ngeneration to avoid an appropriate share of its costs for regulation and black start \nservices.64 That said, the CAISO already has separate rates to assess regulation65 and \nblack start services.66 The issue thus becomes how to appropriately meter and assess \nthose rates onto co-located large loads. The CAISO proposes to address this issue by \nrequiring the PTOs to sub-meter each co-located large load independent of any onsite \ngeneration.67 Scheduling coordinators for the LSEs serving those loads would then be \nrequired to report those meter values separately for the relevant charge codes. Each \nlarge load with co-located generation would thus pay on a gross load basis for \nregulation and black start services. This solution not only results in just and reasonable \ncost allocation, it is also relatively simple to implement because the CAISO and PTOs \nwould not be required to calculate and assess new rates, nor would the CAISO need to \ncreate new settlement charge codes. \n \nb) \nTransmission Access Charges \nThe Commission preliminarily found in the Order that the CAISO tariff may be unjust \nand unreasonable because it allows load with behind-the-meter generation to net its \ngeneration against its load for purposes of calculating Regional Access Charges.68 The \nCommission explained its thinking based on the PJM co-location proceeding:  \n \nIn the PJM Co-Location Order, the Commission found that PJM’s BTMG \nrules, which allowed load-serving entities that provide service to loads \nwith qualifying BTMG to reduce their costs by netting output from BTMG \nin the calculation of their peak demand for the purpose of determining \nNITS charges, were unjust and unreasonable.  The Commission \nconcluded that PJM’s BTMG rules were no longer consistent with cost \ncausation principles because large loads configured in a BTMG \narrangement with significant generation will raise cost shifting concerns \n \n64  \nLikewise, if the rate were assessed on a net meter basis to co-located load and participating \ngeneration, the result would be the same. \n65  \nSection 11.10.2.1 of the CAISO tariff. \n66  \nSection 11.4.2 of the CAISO tariff. The PTOs assess the costs of black start services through \ntheir PTO tariffs. \n67  \nThe CAISO could have an exemption for co-located loads connected behind generators subject \nto the CAISO’s Net Scheduled Participating Generator Agreement (PGA) or Qualifying Facility PGA. \n68  \nOrder to Show Cause at P 102."},{"page":62,"startToken":23401,"endToken":23879,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 61 \n  \ncompared to loads pursuing smaller amounts of netting.  The \nCommission also found that such rules could lead to reliability and \nresource adequacy risks because PJM is obligated to serve transmission \ncustomers using BTMG but does not consider such customers in \ntransmission and resource adequacy planning.69 \n \nThe Commission then noted that it is “similarly concerned that CAISO’s Tariff allows \nEligible Customers that provide service to loads with BTMG to reduce their network \nservice charges because the definition of gross load,70 which is used to calculate the \nRegional Access Charge, excludes load of a retail customer served by its own onsite \ngenerating unit or energy storage device.” The Commission directed the CAISO to \nexplain whether the tariff remains just and reasonable even though it allows netting of \nbehind-the-meter generation from gross load for purposes of determining Regional \nAccess Charges for loads with behind-the-meter generation, or to propose tariff \nrevisions. The Commission also stated the CAISO may explain why it remains just and \nreasonable for customers that fall below a new megawatt materiality threshold for the \namount of load at a particular electrical location that network customers may net using \nbehind-the-meter generation.71 \n \nProposal \n \nThe CAISO does not propose to revise its current constructs for behind-the-meter \ngeneration, gross load, and the transmission access charges.72 Behind-the-meter \ngeneration is far more abundant in California than in PJM, so the CAISO and California \npolicymakers have considered this issue far more extensively. For example, in 2020, \nFERC approved the CAISO’s proposal to amend its definition of Gross Load – the billing \n \n69  \nId. \n70  \nAppendix A to the CAISO tariff defines Gross Load as “Demand (adjusted for distribution losses) \nof End-Use Customer Loads directly connected to the transmission facilities or directly connected to the \nDistribution System of a Utility Distribution Company or MSS Operator located in a PTO Service Territory, \nor End Use Customer Loads directly connected to the Distribution System or transmission facilities of an \nEDAM Transmission Service Provider in an EDAM Entity Balancing Authority Area. Gross Load includes \nLoad served by Excess Behind the Meter Production. Excess Behind the Meter Production shall not be \nnetted against End-Use Customer Load in determining Gross Load.” The definition also provides a list of \ncertain loads excluded, including “Load of an individual retail customer served by its own onsite \nGenerating Unit or energy storage device, or as authorized by Section 218 of the California Public Utilities \nCode;” and “Onsite Load served by a qualifying small power production facility or qualifying cogeneration \nfacility, as those terms are defined in the FERC's regulations implementing Section 201 of the Public \nUtility Regulatory Policies Act of 1978.” \n71  \nOrder to Show Cause at P 102. \n72  \nAlthough the Commission focuses on the regional access charge, the same logic could apply to \nthe local access charge as well."},{"page":63,"startToken":23879,"endToken":24301,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 62 \n  \ndeterminant for transmission access charges – to include load served by excess \nbehind-the-meter production, i.e., behind-the-meter energy that exceeds the onsite \nload.73 The CAISO amended this policy to ensure uniform settlement practices, and to \nensure LSEs were allocated the correct costs of their use of the transmission system, \nwhich includes use by excess behind-the-meter generation.   \n \nThe CAISO did not propose to assess transmission access charges based on gross \nload figures that included load served onsite by its own behind-the-meter generation. \nNeither the CAISO nor stakeholders in 2020 believed such loads use the transmission \ngrid in proportion to those load figures. To the contrary, a benefit rooftop solar, onsite \nstorage, and other behind-the-meter generation is to reduce the use of the grid and the \ngeneration across it. The CAISO does not believe this rationale has changed in light of \nlarge loads.  \n \nPerhaps more critically, the CAISO’s transmission access charges are fundamentally \ndifferent than the PJM transmission charges that concerned the Commission. PJM \ncalculates and assesses its transmission charges based on certain peak demand \nfigures. A large load with behind-the-meter generation thus could mask all of its \ntransmission usage simply by producing generation equal to its demand during that \npeak period. In contrast, the CAISO assesses its transmission access charges 24/7 to \neach UDC based on their gross load, which consists of total end-user demand \naccounting for losses and excess behind-the-meter production. As such, the CAISO \nwould allocate costs to each large load with behind-the-meter generation to the extent \nthe large load used the transmission system, as reflected by its metered load. In other \nwords, any energy withdrawal by the large load would be reflected in the gross load. \nThe LSE can then easily pass down the costs of that use in the retail bill, just as every \nCalifornian with rooftop solar or home storage is billed today. Thus, the CAISO does not \nbelieve that changes to its tariff are needed to address concerns raised by FERC in the \nOrder. \nc) \nTransmission Service Charges \nThe Commission preliminarily found in the Order that the CAISO tariff lacks \ntransmission services that would reflect the ability of Eligible Customers on behalf of \nlarge loads to take transmission services that align with their use of the transmission \nsystem, which may result in inefficient and costly transmission buildout and costs paid \nby transmission customers.74  \n \n73  \nCal. Indep. Sys. Operator Corp., Docket No. ER21-190-000 (Dec. 23, 2020).  \n74  \nOrder to Show Cause at P 102."},{"page":64,"startToken":24301,"endToken":24673,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 63 \n  \n \nProposal \n \nThe CAISO agrees that enabling flexibility will offer cost savings by avoiding \nunnecessary network upgrades, both on an interim and permanent basis. The CAISO \ndiscusses its proposed new service options in Section D, below. \nD. Extending New Transmission Services to Eligible Customers \nTaking Service on Behalf of Flexible Large Loads   \nIn the Order, the Commission preliminarily found that the CAISO tariff may be unjust \nand unreasonable because it does not include transmission services that reflect Eligible \nCustomers taking transmission service on behalf of flexible large loads that are willing \nand able to limit their use of the transmission system under certain conditions, \nsuggesting that “firm use” is essentially the only type of transmission service available in \nthe CAISO. The Commission encouraged new transmission services be made available \nto reflect the operational reality that large loads may use the transmission system to \ndiffering extents and certain large loads are willing and able to limit their use of the \ntransmission system under certain conditions.75 At the same time, the Commission \nstated, “In the alternative, CAISO may explain whether, given that CAISO does not offer \nthe transmission services required by Order No. 888, CAISO’s existing transmission \nservice framework addresses the concerns described herein, or explain what specific \nchanges to its existing transmission service framework would effectively provide the \nsame range of transmission service options for flexible large loads as in the PJM Co-\nLocation Order.”76 The Commission then explained that the customer “must have \nnecessary control technologies and/or protection systems, which may include a special \nprotection scheme, to limit its energy withdrawals to its approved level,” which are \ntypical elements of interconnection service.77 \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO proposed creation of two new flexible interconnection \nservice offerings – one offered on an interim basis and one offered for permanent use, \nto shorten interconnection timelines and reduce interconnection costs, respectively. \nACP-California, Constellation, IEPA, Microsoft, NextEra, PG&E, SCE, SEIA, Viridon, \nPattern, and BAMx all expressed support for the flexible interconnection concepts. \nKritiGrid noted that comments on the CAISO’s Issue Paper indicated significant support \n \n75  \nId. at P 104. \n76  \nId. at P 103. \n77  \nId."},{"page":65,"startToken":24673,"endToken":25108,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 64 \n  \nfor exploration of flexible transmission service products. Generally, stakeholders \nsupported both the interim and permanent flexible interconnection service concepts, \nwith stakeholders expressing more comfort with and need for the FILI option and \nsuggesting that the CAISO continue to explore phasing in a more permanent option in \nthe future. KritiGrid and BAMx both expressed caution with the permanent offering, such \nas how such load interconnections would be financed and concern that developers \nwould seek to transition from the permanent option to firm service as a means to reduce \ninterconnection costs. SDG&E and PG&E shared these concerns. \n \nThe CAISO agrees that both offerings are worth pursuing, however only proposes to \nadvance the interim option within this stakeholder initiative. The CAISO agrees with \nMicrosoft, PG&E, SDG&E, and SCE that it should prioritize the interim option before the \npermanent option. The CAISO still sees potential in the permanent offering and commits \nto exploring it in a future initiative.  \n \nMany stakeholders, including ACP-California, Constellation, IEPA, and Microsoft, \nsuggested additional details on the roles and responsibilities associated with \nimplementing a flexible interconnection service, the study process for flexible \ninterconnection, curtailment rules and obligations, operational requirements, control \ntechnologies, and cost allocation protections prior to implementation. Microsoft noted \nthat development of a flexible service product should not divert time or resources from \nthe higher-priority issues of study timelines, PTO coordination, energization certainty, \nand cost transparency. The CAISO sees value in development of this approach but \napplies this rationale to the decision to defer the permanent offering to a future initiative. \n \nWhile SDG&E agreed to continue exploring the flexible offerings, SDG&E noted that the \nFERC Order did not identify deficiencies in PTO tariffs, so the CAISO should not \nindicate that the PTOs will create new flexible load interconnection services. SDG&E \nnoted that it can already provide transmission-level interim load interconnection \narrangements through its existing processes and suggested further consideration of the \nimplications of compensation for accepting flexible service.  \n \nSCE broadly agreed that PTOs should offer some version of interim flexible service \nunder their respective tariffs. PG&E noted that as part of this stakeholder process, the \nCAISO and PTOs that will offer a FILI service should determine what data, information, \nand operational control, if any, the CAISO should receive or exercise to facilitate the \nCAISO’s role in ensuring transmission system reliability. The CAISO agrees with PG&E \nthat the PTOs will offer the service and expects consistent implementation details \nacross the PTO Tariffs. Specifically, PG&E expected PTOs to develop the following \ndetails of FILI:"},{"page":66,"startToken":25108,"endToken":25449,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 65 \n  \n• An overall framework in the PTO’s and CAISO’s respective tariffs, as \nappropriate, that identifies the roles and responsibilities for all impacted \nparties;  \n• A pro forma Flexible Interconnection Service Addendum to the pro forma \nLarge Load Interconnection Agreement (or, alternatively, a standalone pro \nforma Flexible Interconnection Agreement) that identifies the roles and \nresponsibilities for impacted parties that will identify customer- and site-\nspecific equipment and systems necessary to operationalize FILI service;  \n• Study methodologies that recognize the unique operational characteristics of \nflexible large loads;  \n• Operational requirements, including curtailment implementation mechanisms \nand data reporting;  \n• Cost responsibility provisions, including any financial security during the \nconditional service period;  \n• Transition-to-firm provisions for FILI that specify the automatic conversion to \nfirm service upon network upgrade completion;  \n• Coordination mechanisms between flexible interconnection service and the \nPTO study process; and \n• Operational requirements to manage longer-duration curtailments (to be \nexplored by the CAISO and PTOs). \nThe CAISO generally agrees with PG&E’s characterization of PTO responsibilities as it \nrelates to FILI and suggests additional clarity below for consideration by the PTOs in \ndevelopment of their tariffs. \n \nViridon suggested that curtailment obligations must be enforceable and the chain of \nauthority clear: the CAISO directs, the UDC/LSE implements the curtailment with the \nend-use customer, and the interconnecting PTO acts only pursuant to CAISO or \nReliability Coordinator operating instructions. The CAISO agrees that further clarification \nof roles is required and provides additional detail below. In addition, the CAISO expects \nto convene a working group to implement these concepts after filing with the \nCommission. \n \nBAMx supported a cap on the FILI service to avoid it becoming a permanent substitute \nfor needed transmission upgrades. The CAISO is reluctant to place a one-sized-fits-all \ntime limitation on what is intended to be a bespoke solution tied to the specific \ndevelopment timeline of the associated network upgrade but expects that the load will \nbegin receiving transmission service as soon as the associated network upgrades are \ncomplete. The CAISO points to its Transmission Development Forum and other"},{"page":67,"startToken":25449,"endToken":25775,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 66 \n  \nstatewide efforts to ensure timely completion of network upgrades as a means to track \nnetwork upgrade completion and ensure continued progress. \n \nConstellation and IEPA noted that while the offerings are intended to be customized to \nspecific load interconnection requests, the following details will be helpful: \n• Curtailment triggers and operating conditions; \n• How curtailment parameters will be established; \n• Deployment priorities; \n• Scheduling treatment; \n• The relationship between operational restrictions and study assumptions;  \n• Potential interactions with scheduling, dispatch, and price formation; and \n• How the FILI (and FLIP) may apply to co-located load arrangements and \nexisting generation resources, particularly where load flexibility can reduce \ntransmission impacts or support continued wholesale market participation. \n \nCosts \n \nThe CPUC noted that CAISO has not committed to modeling market impacts of flexible \nvs. non-flexible large loads, which is important for the CPUC to accurately assess \nlocational marginal price upward shifts, congestion cost increases, or local ancillary \nservice procurement costs driven by non-flexible data center demands. Both class \nrevenue allocation and non-compliance penalty design require detailed market impact \ninformation beyond what the CAISO has committed to providing in its straw proposal.  \n \nControl measures \nCal Advocates noted that the CAISO did not propose requirements necessary to ensure \nbenefits materialize from flexible agreements and flow to system users. Cal Advocates \nstates that any non-firm service agreement between the CAISO and a PTO or large \nload should establish the curtailable amount of a customer’s load and include control \nrequirements for the curtailment to be implemented. \nProposal  \n \nThe CAISO proposes to create a new flexible interconnection service option that will \nenable large loads and co-located loads to limit their energy withdrawals or injections \nuntil their network upgrades are placed into service. The CAISO believes this will \nprovide large load developers with the option to interconnect quickly through \nenforceable physical and operational controls to prevent transmission congestion. PTOs \nwill play a key role in defining and implementing this interconnection service offering."},{"page":68,"startToken":25775,"endToken":26195,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 67 \n  \nThe CAISO does not propose to create new “transmission services” or more \nresponsibilities around eligible customers, which would require redesigning transmission \nand interconnection service entirely. The CAISO does not believe such a redesign is \nwarranted, and the Commission expressly invites the CAISO to explain alternative \nservice frameworks that may enable similar flexibility.78 \n \nMoreover, in real time, LSEs can schedule demand as needed, including for customers \nlimiting their use of the transmission system. With the operational data and process \ndescribed in Section A.4, the CAISO can accommodate flexible loads without creating \nnew separate classes of transmission service. This would also enable the PTOs to \nprovide bespoke interconnection configurations for large loads, saving ratepayers from \nthe costs of network upgrades that conform to specific “transmission services.” The \nCAISO believes this course of action is consistent with developers’ desires to \ninterconnect quickly and affordably.  \n \nIn addition to the CAISO’s current generic firm service, the CAISO proposes to create a \nnew Flexible Interim Load Interconnection (FILI) service to be implemented in close \ncoordination with the PTOs, that will enable faster interconnections while mitigating \ntransmission constraints. The CAISO clarifies that this interconnection service offering is \nnot intended to address supply constraints.   \n \nThe proposed FILI offering would enable large loads to interconnect flexibly and receive \nservice up to a certain level based on grid conditions and constraints until network \nupgrades are complete, at which time the large load would switch over to receiving firm \nservice. This will likely be a tailored option for each large load based on its point of \ninterconnection and the constraints it faces, and to be developed through a contractual \nagreement with the PTO. For example, some FILIs may require little flexibility for a \nlimited time because there are few, less probable contingencies. Others may require \nmore flexibility because of transmission constraints that require network upgrades with \nlonger timelines. The FILI option provides flexibility to the PTOs, CAISO, and \ndevelopers to customize solutions. For this reason, CAISO declines to propose any kind \nof temporal or capacity cap on this interconnection service offering. \n \no This flexible interconnection service may include a number of tools or \nmeasures, including but not limited to a Remedial Action Scheme (RAS), PTO \noperator curtailment, or managing to a present schedule. The PTO may \nrequest automated schemes, such as a RAS, for FILI that are limited by the \ntransmission overload under N-1-1, with CAISO and Reliability Coordinator \n(RC) concurrence, or \n \n78  \nId. at P 101."},{"page":69,"startToken":26195,"endToken":26583,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 68 \n  \no The PTO will do its own load curtailment for FILI that is limited by transmission \noverload under N-1-1 after the first N-1 were to occur. \no If a RAS is considered but cannot be reliably operated, or is found to have \nsignificant market implications, the CAISO will not enable that option.  \n \nThe CAISO plans to continue to address a number of market implications of the FILI \napproach in a continued stakeholder initiative, including the following.  \n• Visibility of FILI service to the CAISO to prevent unintended market interactions.  \n• Requirements for data exchange to maintain communication protocols between \nthe CAISO and the PTOs serving large loads.  \n \nTo manage coordination of development of this interconnection service offering, the \nCAISO will convene working groups with the PTOs, large load customers, and other \ninterested stakeholders to maximize consistency and clarify roles and responsibilities.  \n \nThe CAISO does propose control technologies and/or protection systems associated \nwith this new service offering, which are discussed in Section A.4. \n \nAlthough the CAISO is not proposing to advance the permanent flexible interconnection \noffering, FLIP, in this draft final proposal, the CAISO does commit to further exploration \nof this permanent offering in a future stakeholder initiative.  \n \nThe CAISO does propose control technologies and/or protection systems associated \nwith this new service offering, which are discussed in Section A.4. \nE. Interconnection Customers Serving Electrically Proximate \nLarge Load and Co-Located Load \nThe Commission preliminarily found in the Order that the CAISO tariff appears to be \nunjust and unreasonable because it does not contain provisions allowing an \ninterconnection customer to seek the generator interconnection service(s) that reflects \nthe operational dynamics of serving either: (1) an electrically proximate large load; or (2) \na co-located load, as defined in the Order, that has a high peak load (i.e., large co-\nlocated loads that are 50 MW or greater).79 The Commission defined an “electrically \nproximate large load” as a large load “sufficiently electrically close to the interconnection \ncustomer’s requested point of interconnection, such that the impact on the transmission \nsystem of the combination of the generating facility and the load, with the exception of \nthe transmission facilities between the two, will be effectively the same as if they were \n \n79  \nOrder to Show Cause at P 113."},{"page":70,"startToken":26583,"endToken":26939,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 69 \n  \nlocated at the same substation (e.g., large load that is located no more than two \nsubstations from the generating facility).”80  \n \nBackground and Stakeholder Comment \n \nIn the straw proposal, the CAISO did not propose creation of new provisions for \ninterconnection customers to serve electrically proximate large loads. PG&E, SDG&E, \nand Microsoft agreed with this approach. The CPUC recommended that the CAISO \nadopt a process for jointly evaluating proximate load and generation in order to avoid \ncostly network upgrades while preserving system reliability and providing operational \nbenefits. Other stakeholders, primarily in the generation development community, urged \nthe CAISO to consider service to electrically proximate loads. Developers such as \nAltaGas, NextEra, and SEIA noted that that large load development is in its early stages \nand will evolve and suggested that enabling interconnection customers to serve \nproximate loads would increase customer optionality, reduce transmission impacts, and \naccelerate service to large loads. Nearly all stakeholders suggested consideration of \nthis pathway in a future related initiative.  \n \nThe CAISO notes that it currently has a process for connecting generator \ninterconnection request applications to non-load-serving entities (e.g. commercial and \nindustrial consumers) in its generator interconnection process, which awards “points” in \nthe interconnection scoring process to projects that have a commercial arrangement \nwith a non-load-serving entity off-taker. While this process does not require any \nelectrical or geographic requirements, it seeks to tie generation projects to loads to the \nextent that they have a commercial arrangement with the goal of enabling large loads to \nprocure generation. The CAISO agrees with many stakeholders that it is worth \ncontinuing to explore the potential benefits of proximate loads, however the CAISO \ndoes not propose development of this option in this paper. \n \nProposal \n \nThe CAISO proposes considering provisions for interconnection customers to serve \nelectrically proximate large loads in a future stakeholder initiative. The CAISO intends to \nprioritize the more common stand-alone and co-located load and generator \ninterconnections with this proposal and filing and will focus on proximate load and \ngeneration arrangements once the process for co-location is underway.  \n \n \n80  \nId. at P 112."},{"page":71,"startToken":26939,"endToken":27232,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 70 \n  \n2. Initiative Timeline and Next Steps \nThe CAISO’s Large Loads Stakeholder Initiative is the primary vehicle for developing \nthe CAISO tariff revisions necessary to comply with the Commission’s Order. The \nCAISO refocused the initiative on the issues the Commission identified. Given the \ntimeline described in the Order, the CAISO expedited the stakeholder initiative. The \nCAISO will seek Board of Governors approval at the CAISO Board’s October 28, 2026 \nmeeting. While the stakeholder initiative will be expedited, the CAISO is hosting \nworkshops and soliciting stakeholder feedback on the proposals to better inform the \npolicy outcomes. \n \nAction \nTentative date  \nPost Straw Proposal \nAugust 12, 2026 \nStakeholder workshop \nAugust 19, 2026 \nComments due \nSeptember 2, 2026 \nPost Draft Final Proposal \nSeptember 24, 2026 \nStakeholder workshop \nOctober 1, 2026 \nComments due \nOctober 15, 2026 \nCAISO Board of Governors Decision \nOctober 28, 2026 \n \n3. Decisional Classification \nThis initiative proposes certain tariff amendments to enhance the process for studying \nand approving interconnection requests. CAISO staff believe that these proposed tariff \nchanges will go to the Board of Governors only and that the Western Energy Markets \n(WEM) Governing Body will have no role in the decision.  \n \nThe WEM Governing Body has primary authority over any  \n \nproposal to change or establish a tariff rule applicable to the WEIM/EDAM \nEntity balancing authority areas, WEIM/EDAM Entities, or other market \nparticipants within the WEIM/EDAM Entity balancing authority areas, in \ntheir capacity as participants in WEIM/EDAM… The scope of this joint \nauthority excludes, without limitation, any other proposals to change or \nestablish tariff rule(s) applicable only to the CAISO balancing authority \narea or to the CAISO-controlled grid.81 \n \n \n81  \nCharter for WEIM and EDAM Governance § 2.2.1."},{"page":72,"startToken":27232,"endToken":27395,"text":"Large Loads Enhancements  \nDraft Final Proposal \nISO/TPID \nISO Public \nPage 71 \n  \nThe tariff changes proposed here would not be “applicable to the WEIM/EDAM Entity \nbalancing authority areas, WEIM/EDAM Entities, or other market participants within the \nWEIM/EDAM Entity balancing authority areas, in their capacity as participants in \nWEIM/EDAM.” Rather, they would be applicable “only to … the CAISO-controlled grid.”  \n \nAccordingly, these proposed changes to implement these enhancements would fall \noutside the scope of the WEM Governing Body’s primary authority. The WEM \nGoverning Body also has an advisory role that extends to any “proposals to change or \nestablish tariff rules that would apply to the real-time and/or day-ahead market but are \nnot within the scope of its primary authority.” This initiative, however, does not propose \nchanges to the rules of the real-time or day-ahead markets. Stakeholders are \nencouraged to submit a response in their written comments to the proposed \nclassification as described above, particularly if they have concerns or questions."}],"sections":[{"p":1,"at":0,"title":"Attachment C – Final Proposal","method":"printed heading","endPage":3,"endAt":82,"startToken":0,"endToken":49},{"p":3,"at":82,"title":"Table of Contents","method":"printed heading","endPage":3,"endAt":1300,"startToken":49,"endToken":118},{"p":3,"at":1300,"title":"C. Co-Location Arrangements and Load with Behind-the-Meter Generation49","method":"printed heading","endPage":3,"endAt":1716,"startToken":118,"endToken":141},{"p":3,"at":1716,"title":"D. Extending New Transmission Services to Eligible Customers Taking Service on","method":"printed heading","endPage":3,"endAt":1911,"startToken":141,"endToken":158},{"p":3,"at":1911,"title":"E. Interconnection Customers Serving Electrically Proximate Large Load and Co-","method":"printed heading","endPage":4,"endAt":82,"startToken":158,"endToken":194},{"p":4,"at":82,"title":"I. Executive Summary","method":"printed heading","endPage":4,"endAt":1396,"startToken":194,"endToken":377},{"p":4,"at":1396,"title":"A. Developing procedures to improve coordination related to load interconnection","method":"printed heading","endPage":4,"endAt":1613,"startToken":377,"endToken":401},{"p":4,"at":1613,"title":"B. Upholding a workable framework for the PTOs to develop just and reasonable","method":"printed heading","endPage":4,"endAt":1772,"startToken":401,"endToken":424},{"p":4,"at":1772,"title":"C. Establishing parallel information and application requirements for co-located","method":"printed heading","endPage":4,"endAt":1966,"startToken":424,"endToken":447},{"p":4,"at":1966,"title":"D. Creating a framework for new interconnection service to allow large loads to","method":"printed heading","endPage":4,"endAt":2143,"startToken":447,"endToken":472},{"p":4,"at":2143,"title":"E. Considering the need for a process to study generating facilities serving","method":"printed heading","endPage":11,"endAt":731,"startToken":472,"endToken":2926},{"p":11,"at":731,"title":"A. Transmission Service to Eligible Customers on Behalf of","method":"printed heading","endPage":42,"endAt":185,"startToken":2926,"endToken":14941},{"p":42,"at":185,"title":"B. Cost Shifting Among Transmission Customers","method":"printed heading","endPage":50,"endAt":231,"startToken":14941,"endToken":18372},{"p":50,"at":231,"title":"C. Co-Location Arrangements and Load with Behind-the-Meter","method":"printed heading","endPage":64,"endAt":323,"startToken":18372,"endToken":24348},{"p":64,"at":323,"title":"D. Extending New Transmission Services to Eligible Customers","method":"printed heading","endPage":69,"endAt":1561,"startToken":24348,"endToken":26427},{"p":69,"at":1561,"title":"E. Interconnection Customers Serving Electrically Proximate","method":"printed heading","endPage":72,"endAt":1082,"startToken":26427,"endToken":27395}]}