{"document":{"slug":"rec-20261116-5343-6","title":"Att-E_Board-Memo_Large-Load","issued":"2026-11-16","accession":"20261116-5343","docket":"ER27-532-000","group":"CAISO and California transmission owners’ large-load tariff revisions","filer":"California Independent System Operator Corporation","kind":"attachment","file":"sources/filings/text/20261116-5343_006.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5343","tier":"record","parent":"rec-20261116-5343","sha256":"47279bbed51f0113eb5a23f7f0c44e6c59463389e52cd012f63fe44a6711a9b8","pages":7,"tokens":1273,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":16,"text":"Attachment E – Board Memorandum  \nLarge Loads Tariff Amendment  \nCalifornia Independent System Operator Corporation \nNovember 16, 2026"},{"page":2,"startToken":16,"endToken":268,"text":"\u0000\u0001\u0002\u0003\u0004\u0005\u0006\u0007\b\t\n\u000b\f\n\u0004\u000e\u000f\u0002\u0010\u0011\u000b\n\n\u0012\n\u0002\f\u0013\u0014\u0015\u0016\u0017\u0018\n\u0000\u0000\u0000\u0000\u0000\u0000\u0000\u0000\u001b\u001c\u001d\u001e\u001f !\"#\u001d\n%&'\n\u0004\u000e\u000f\u0000)\u0016\f\n*\u0000\u0016\u0017\u0000+\u0016,\u0014\n-\u0016\n.\u0000\u0000/0&1' \u0007\u0014\n\u000b\u0000\t\n\u000b\u000b\f\n2\u00003\n\u0012\u0014\u0000\u0002\n\u0014.\n*\u0014-4\u0000\u0001\n\f-.5\n..\n\u0016-\u0000\u0002\u000b\f--\n-\u0013\u0000\f-*\u0000\u0004-\u0017\n\f.4\n\u0010\u00124\u0010\n\u0014\u0000\u0005\u0014,\u0014\u000b\u001665\u0014-4\u0000789:' \u000f\u00124\u0016\u0011\u0014\n\u0000;;2\u0000;<;\u0018\u0000=:'\n=:>?&@>:\u00009&\u0000/A=B\u0000C80D:\u0000C&8E>\u0000F0E:0\u00009&\u0000GH&I\u0000B8J>:\u0000\u0000KLMNOPOQRSTUVO\u0000RPWVMRPN\u0000XYZ\u0000[QSRU\u0000Q\\\u0000]Q^PRTQRN\u0000S_`MQTa\u0000AbABc%deA\u0000Gcffg=h\u0000\u0001i\u0014j\f\n\u0013\u0014\u0000j\u0016\f*\u0000k-i\f-\u0012\u00145\u0014-4.\u0000*\n\f\u00174\u0000\u0017\n-\f\u000b\u00006\n\u00166\u0016.\f\u000b\u0000\f-*\u0000\u00106\u0012\u00165\n-\u0013\u0000\u0017\n\u000b\n-\u0013\u0000\n\u0014.6\u0016-*.\u00004\u0016\u00004i\u0014\u0000l\u0014*\u0014\n\f\u000bk-\u0014\n\u0013m\u0000n\u0014\u0013\u0010\u000b\f4\u0016\nm\u0000o\u001655\n..\n\u0016-\u0000plknoq\u0000\u000f\n*\u0014\n\u00004\u0016\u0000\u000ei\u0016r\u0000o\f\u0010.\u0014\u0000\u0016-\u0000j\f\n\u0013\u0014\u0000j\u0016\f*.\b\u0000\u0001\fs\u0014-4\u0016\u0013\u00144i\u0014\n2\u00004i\u0014\u0000\u0004\u000e\u000f\u0000\f-*\u00006\f\n4\n\u0012\n6\f4\n-\u0013\u00004\n\f-.5\n..\n\u0016-\u0000\u0016r-\u0014\n\u0000\u0017\n\u000b\n-\u0013.\u00006\n\u0016,\n*\u0014\u00004i\u0014\u00004\f\n\u0017\u0017t\n\u000b\u0014,\u0014\u000b\u0012\u000b\f\n4m2\u0000\u0012\u0010.4\u00165\u0014\n\u00006\n\u00164\u0014\u00124\n\u0016-.2\u0000\f-*\u0000\u00166\u0014\n\f4\n\u0016-\f\u000b\u00004\u0016\u0016\u000b.\u00004i\u0014\u0000\u000f\n*\u0014\n\u0000.\u0014\u0014s.\b\u0000\u0001i\u0014m\u0000\n\u00146\n\u0014.\u0014-4\u0000\u0014,\u0016\u000b\u00104\n\u0016-\u0000r\n4i\u0016\u00104\u0000\n\u0014u\u0010\n\n-\u0013\u0000\n\u0014,\u0016\u000b\u00104\n\u0016-\b\u0000\u0001i\u0014\u0000\n\u0014.\u0010\u000b4\u0000\n.\u0000\f\u0000\u0012\u001656\n\u0014i\u0014-.\n,\u0014\u0000-\u0014\f\nt\n4\u0014\n5\n\u0014.6\u0016-.\u0014\u00004\u0016\u00004i\u0014\u0000\u000f\n*\u0014\n\u00004i\f4\u0000\u0012\f-\u0000\f\u0012\u0012\u0014\u000b\u0014\n\f4\u0014\u0000,\n\f\u0011\u000b\u0014\u0000\u000b\f\n\u0013\u0014t\u000b\u0016\f*\u00006\n\u0016v\u0014\u00124.\u0000r\n4i\u0016\u00104\u0000\u0012\u001656\n\u00165\n.\n-\u0013\u0000\n\u0014\u000b\n\f\u0011\n\u000b\n4m2\u0000\f\u0017\u0017\u0016\n*\f\u0011\n\u000b\n4m2\u0000\u0016\n\u0000-\u0016-t*\n.\u0012\n5\n-\f4\u0016\nm\u0000\f\u0012\u0012\u0014..\b\u0000\u0000\u0004-4i\u0014*\n\f\u00174\u0000\u0017\n-\f\u000b\u00006\n\u00166\u0016.\f\u000b2\u00004i\u0014\u0000\u0004\u000e\u000f\u0000*\u0014.\u0012\n\u0011\u0014.\u0000\u0017\n,\u0014\u0000s\u0014m\u0000\f\n\u0014\f.\u0000ri\u0014\n\u0014\u0000\u0004\u000e\u000f\u0000\u000b\u0014\f*\u0014\n.i\n6\u0000\f-*\u0000\u0014-\u0013\f\u0013\u00145\u0014-4\u0000\n.\u0000-\u0014\u0012\u0014..\f\nm\u00004\u0016\u0000\u0014-\f\u0011\u000b\u0014\u0000\n--\u0016,\f4\n\u0016-\u0000ri\n\u000b\u0014\u00006\n\u00164\u0014\u00124\n-\u0013\u0000\u0012\u0010.4\u00165\u0014\n.\u0000\f-*\u0000\u0014-.\u0010\n-\u0013\u0000.\f\u0017\u0014\f-*\n\u0014\u000b\n\f\u0011\u000b\u0014\u0000.\u0014\n,\n\u0012\u0014w\u0000\u0015\b\u0002\n\u0016\u0012\u0014*\u0010\n\u0014.\u00004\u0016\u0000\n56\n\u0016,\u0014\u0000\u0012\u0016\u0016\n*\n-\f4\n\u0016-\u0000\n\u0014\u000b\f4\u0014*\u00004\u0016\u0000\u000b\u0016\f*\u0000\n-4\u0014\n\u0012\u0016--\u0014\u00124\n\u0016-\u0000\f66\u000b\n\u0012\f4\n\u0016-.2\u0000.4\u0010*\n\u0014.2\u00004\u0014\u0012i-\n\u0012\f\u000b\u0000.4\f-*\f\n*.2\u0000\f-*\u0000\u00166\u0014\n\f4\n\u0016-\f\u000b\u0000\n\u0014u\u0010\n\n\u00145\u0014-4.\u0000\u0017\u0016\n\u0000\f\u0012\u0012\u0010\n\f4\u0014\u0000\u000b\u0016-\u0013t4\u0014\n5\u00006\u000b\f--\n-\u0013\u0000\f-*\u0000-\u0014\f\nt4\u0014\n5\u0000\n\u0014\u000b\n\f\u0011\n\u000b\n4m\b\u0000\u0000;\bxr\u0016\ns\f\u0011\u000b\u0014\u0000\u0017\n\f5\u0014r\u0016\ns\u00004\u0016\u00006\n\u0014,\u0014-4\u0000\u0012\u0016.4\u0000.i\n\u00174\n-\u00132\u0000\f-*\u00004i\n\u0016\u0010\u0013i\u0000ri\n\u0012i\u00004i\u0014\u00006\f\n4\n\u0012\n6\f4\n-\u0013\u00004\n\f-.5\n..\n\u0016-\u0000\u0016r-\u0014\n.\u0000\u0012\f-\u0000*\u0014,\u0014\u000b\u00166\u0000v\u0010.4\u0000\f-*\u0000\n\u0014\f.\u0016-\f\u0011\u000b\u0014\u0000*\u00146\u0016.\n42\u0000\u0017\n-\f-\u0012\n-\u00132\u0000\f-*\u0000\u00164i\u0014\n\u0000\u0012\u0016.4\f\u000b\u000b\u0016\u0012\f4\n\u0016-\u0000.4\n\u0010\u00124\u0010\n\u0014.\u0000r\n4i\n-\u00004i\u0014\n\n\u00004\f\n\u0017\u0017.\b\u0000y\b\u0002\f\n\f\u000b\u000b\u0014\u000b\u0000\n-\u0017\u0016\n5\f4\n\u0016-\u0000\f-*\u0000\f66\u000b\n\u0012\f4\n\u0016-\u0000\n\u0014u\u0010\n\n\u00145\u0014-4.\u0000\u0017\u0016\n\u0000\u0012\u0016t\u000b\u0016\u0012\f4\u0014*\u0000\u000b\u0016\f*\u0000\f-*\u0000\u0013\u0014-\u0014\n\f4\n\u0016-\u0000z{{z|}~~|\u0000|\u0000~\u0000\u0000\n\u0014.\u0016\u0010\n\u0012\u0014\u0000\n-4\u0014\n\u0012\u0016--\u0014\u00124\n\u0016-\u00006\n\u0016\u0012\u0014..\u00004\u0016\u0000\f\u000b\n\u0013-\u0000r\n4i\u00006\f\n4\n\u0012\n6\f4\n-\u00134\n\f-.5\n..\n\u0016-\u0016r-\u0014\n\u000b\u0016\f*\n-4\u0014\n\u0012\u0016--\u0014\u00124\n\u0016-.4\u0010*\n\u0014.\b"},{"page":3,"startToken":268,"endToken":470,"text":"\u0000\u0001\u0002\u0003\u0004\u0005\u0006\u0007\t\u0003\n\n\u000b\f\n\u0003\n\u000e\u0001\u000f\u0010\u0011\u0003\u0012\n\u0001\u000b\u0013\u0014\u0015\u0016\u0017\u0018\n\u0019\u0007\u001a\n\u0014\u001b\u001c\u001d\n\u0014\t\u001c\u001e\u001f\u0014\f\u001c \t\n\u0016\u000b!\t\u001c\u001e\u001f\u0014\f\"\u0016\u001e\u001e\u0014\"\u001f\u001c\u0016\u001e\t#\u001a\u0003\u0011\u0003$\t%\u0014\f&\u001c\"\u0014\t\u001f\u0016\t\u000b\n\n\u0016'\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b!%\t\u001f\u0016\t\n\u001c\u001e\u001f\u0014\f\"\u0016\u001e\u001e\u0014\"\u001f\t()\u001c\"*\n+\t\u001f\u0016\t\u001f,\u0014\t\u001f\f\u000b\u001e% \u001c%%\u001c\u0016\u001e\t%+%\u001f\u0014 \t',\u001c\n\u0014\t'\u000b\u001c\u001f\u001c\u001e\u0013\t\u0017\u0016\f\t\u001e\u0014\u001f'\u0016\f*\t)-\u0013\f\u000b!\u0014\t\n\"\u0016 -\n\u0014\u001f\u001c\u0016\u001e\u0007\t\n.\u0007\u001a)\u001f)\f\u0014\t-\u0016\n\u001c\"+\t!\u0014&\u0014\n\u0016- \u0014\u001e\u001f\t\u001f\u0016\t%\u001f)!+\t\u0013\u0014\u001e\u0014\f\u000b\u001f\u001c\u001e\u0013\t\u0017\u000b\"\u001c\n\u001c\u001f\u001c\u0014%\t%\u0014\f&\u001c\u001e\u0013\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b!%\t'\u001c\u001f,\t\n\u0014\n\u0014\"\u001f\f\u001c\"\u000b\n\n+\t-\f\u0016\u001b\u001c \u000b\u001f\u0014\t\u0013\u0014\u001e\u0014\f\u000b\u001f\u001c\u0016\u001e\u0007\t\n/0123467897\t:;8\t<=9\t>?634\t87:@<\t@A;:B\tC7DCD4:B\t7\u0014%-\u0014\"\u001f\t\u001f,\u0014\t\")\f\f\u0014\u001e\u001f\t\u000b%%\u001c\u0013\u001e \u0014\u001e\u001f\t\u0016\u0017\t\n\f\u0014%-\u0016\u001e%\u001c\u001d\u001c\n\u001c\u001f\u001c\u0014%\t\u0017\u0016\f\t\u001f,\u0014\t%+%\u001f\u0014 \t\u001c\u001e\t',\u001c\",\t-\u000b\f\u001f\u001c\"\u001c-\u000b\u001f\u001c\u001e\u0013\t\u001f\f\u000b\u001e% \u001c%%\u001c\u0016\u001e\t\u0016'\u001e\u0014\f%\t-\f\u001c \u000b\f\u001c\n+\t\n \u000b\u001e\u000b\u0013\u0014\u001f,\u0014\t\n\u0016\u000b!\t\u001c\u001e\u001f\u0014\f\"\u0016\u001e\u001e\u0014\"\u001f\u001c\u0016\u001e\t%\u001f)!+\t\u000b\u001e!\t\u0017\u001c\u001e\u000b\u001e\"\u001c\u001e\u0013E\t%\u0016\t<=9\t>?634\t!\f\u000b\u0017\u001f\t\u0017\u001c\u001e\u000b\n\t-\f\u0016-\u0016%\u000b\n\t\n:88794494\t<DCAF4\t<=:<\tA;<9749F<\tGA<=\t<=9\t>?634\tFD79\t@H;F<AD;4I\tC7D:F<AJ9\t<7:;4KA44AD;\t\n-\n\u000b\u001e\u001e\u001c\u001e\u0013E\t\"\u0016L\n\u0016\"\u000b\u001f\u0014!\t\u0013\u0014\u001e\u0014\f\u000b\u001f\u0016\f\t\u001c\u001e\u001f\u0014\f\"\u0016\u001e\u001e\u0014\"\u001f\u001c\u0016\u001eE\t\u000b\u001e!\t\u0016-\u0014\f\u000b\u001f\u001c\u0016\u001e\u000b\n\t\f\u0014\n\u001c\u000b\u001d\u001c\n\u001c\u001f+\u0007\t\u0000,\u0014\t\u0003\n\u000e\t\n\u0014\u001b-\u0014\"\u001f%\u000b!!\u001c\u001f\u001c\u0016\u001e\u000b\n\t\"\u0016 -\n\u0014 \u0014\u001e\u001f\u000b\f+\t\"\u0016 -\n\u001c\u000b\u001e\"\u0014\t\u001c\u001e\u0017\u0016\f \u000b\u001f\u001c\u0016\u001e\t\u0017\f\u0016 \t-\u000b\f\u001f\u001c\"\u001c-\u000b\u001f\u001c\u001e\u0013\t\n\u001f\f\u000b\u001e% \u001c%%\u001c\u0016\u001e\t\u0016'\u001e\u0014\f%\t\u001f\u0016\t\u0014\u001e%)\f\u0014\t\u000b\t\"\u0016\u0016\f!\u001c\u001e\u000b\u001f\u0014!\t\u000b\u001e!\t%\u0014\u000b \n\u0014%%\t-\f\u0016\"\u0014%%\t\u001f\u0016\t\u001c\u001e\u001f\u0014\f\"\u0016\u001e\u001e\u0014\"\u001f\t\n\u001e\u0014'\n\u000b\f\u0013\u0014\t\n\u0016\u000b!%\u0007\t\nMNOPQR\tTUVT\tTUP\tWXY\tZNV[Q\tN\\\t]NOP[^N[_\tV``[NOP_\tTUP\t`[N`N_PQ\t\naV[bP\taNVQ_\tP^UV^cPdP^T_R\tV_\tQP_c[efPQ\te^\tTUP\tdPdN[V^Qgd\tQVTPQ\t\nYcTNfP[\thhR\thihjk\tV^Q\t\nMNOPQR\tTUVT\tTUP\tWXY\tZNV[Q\tN\\\t]NOP[^N[_\tVgTUN[elP_\tMV^VbPdP^T\tTN\t\ndVmP\tVaa\t^PcP__V[n\tV^Q\tV``[N`[eVTP\t\\eae^b_\toeTU\tTUP\tpPQP[Va\tq^P[bn\t\nrPbgaVTN[n\tsNdde__eN^\tTN\ted`aPdP^T\tTUP\t`[N`N_VaR\te^cagQe^b\tV^n\t\n\\eae^b_\tTUVT\ted`aPdP^T\tTUP\tNOP[V[cUe^b\te^eTeVTeOP\tfgT\tcN^TVe^\tQe_c[PTP\t\n[POe_eN^_\tTN\te^cN[`N[VTP\tsNdde__eN^\tbgeQV^cP\te^\tV^n\te^eTeVa\t[gae^b\tN^\t\nTUP\t`[N`N_PQ\tTV[e\\\\\tVdP^QdP^Tt\t\nvwxyzxxw{|\t}|v\t}|}~xwx\t\t\n\u000e\u001e)\u001e\u0014E\t\u0015\u0015\u0018E\t\u001f,\u0014\t\u001a\u0014!\u0014\f\u000b\n\t\u001e\u0014\f\u0013+\t\u0014\u0013)\n\u000b\u001f\u0016\f+\t\u0012\u0016  \u001c%%\u001c\u0016\u001e\t#\u001a\u0012$\t\u001c%%)\u0014!\t%\u001c\u001b\t\n\u001f\u000b\u001c\n\u0016\f\u0014!\u0016\f!\u0014\f%\t\u001f\u0016\t%,\u0016'\t\"\u000b)%\u0014\t)\u001e!\u0014\f\t\n\u0014\"\u001f\u001c\u0016\u001e\t\u0015\u0018\t\u0016\u0017\t\u001f,\u0014\t\u001a\u0014!\u0014\f\u000b\n\t\u0001\u0016'\u0014\f\t\"\u001f\t\u001f\u0016\t\u0014\u000b\",\t\u0016\u0017\t\n\u001f,\u0014%\u001c\u001b\f\u0014\u0013\u001c\u0016\u001e\u000b\n\t\u0013\f\u001c!\t\u0016-\u0014\f\u000b\u001f\u0016\f%\t)\u001e!\u0014\f\t\u001c\u001f%\t)\f\u001c%!\u001c\"\u001f\u001c\u0016\u001eE\t\u001c\u001e\"\n)!\u001c\u001e\u0013\t\u001f,\u0014\t\u0003\n\u000e\u0007\t\u001e\t\u0016\f!\u0014\f\t\u001f\u0016\t%,\u0016'\t\n\"\u000b)%\u0014\u001c%\u000b\t-\f\u0014\n\u001c \u001c\u001e\u000b\f+\t\u0017\u001c\u001e!\u001c\u001e\u0013\t\u001f,\u000b\u001f\t\u000b\t\u001f\u000b\f\u001c\u0017\u0017\t \u000b+\t\u001d\u0014\t)\u001e)%\u001f\t\u000b\u001e!\t)\u001e\f\u0014\u000b%\u0016\u001e\u000b\u001d\n\u0014E\t-\n\u000b\"\u001c\u001e\u0013\t\u001f,\u0014\t\n\u0016\u001e)%\u0016\u001e\u001f,\u0014\t\f\u0014\"\u001c-\u001c\u0014\u001e\u001f\t\u001f\u0016\t!\u0014\u0017\u0014\u001e!\t\u0016\f\t \u0016!\u001c\u0017+\t\u001c\u001f%\t\u001f\u000b\f\u001c\u0017\u0017\t\u000b%\t\u001e\u0014\u0014!\u0014!\u0007\t\u0000,\u0014\t\u0016\f!\u0014\f\t\u001f\u0016\t%,\u0016'\t\"\u000b)%\u0014\t\n#\u000e\f!\u0014\f$!\u001c\f\u0014\"\u001f\u0014!\t\u001f,\u0014\t\u0003\n\u000e\u0005\u0000\u000e%\t\u0017\u0016\")%\u0014%\t\u0016\u001e\t\u0017\u001c&\u0014\t\"\u0014\u001e\u001f\f\u000b\n\t\"\u0016\u001e\"\u0014\f\u001e%E\t',\u001c\",\t\u001f,\u0014\t\u0003\n\u000e\t\n\u000b!!\f\u0014%%\u0014!\t\u001c\u001e\t\u001c\u001f%\t!\f\u000b\u0017\u001f\t\u0017\u001c\u001e\u000b\n\t-\f\u0016-\u0016%\u000b\n\u0007\t\u0000,\u0014\t\u0003\n\u000e\t\u000b\n%\u0016\tK9<\t<=9\t@A74<\tD@\t<=9\t2DKKA44AD;34\t\n\"\u0016 -\n\u001c\u000b\u001e\"\u0014\t\f\u0014()\u001c\f\u0014 \u0014\u001e\u001f%\t'\u001c\u001f,\t%)\u001d \u001c%%\u001c\u0016\u001e\t\u0016\u0017\t\u000b\u001e\t\u0003\u001e\u0017\u0016\f \u000b\u001f\u001c\u0016\u001e\u000b\n\t\u0014-\u0016\f\u001f\t\u0016\u001e\t\u0014%\u0016)\f\"\u0014\t\n\n)\u0017\u0017\u001c\"\u001c\u0014\u001e\"+E\n\t!\u0014%\"\f\u001c\u001d\u001c\u001e\u0013\t\f\u0014\"\u0014\u001e\u001f\t\u000b\u001f\u001f\u0014\u001e\u001f\u001c\u0016\u001e\t\u001f\u0016\t\f\u0014%\u0016)\f\"\u0014\t\u000b!\u0014()\u000b\"+\t#$E\t\u0013\u0014\u001e\u0014\f\u000b\u001f\u001c\u0016\u001e\t\n!\u0014&\u0014\n\u0016- \u0014\u001e\u001fE\t\u001f\f\u000b\u001e% \u001c%%\u001c\u0016\u001e\t\u0014\u001b-\u000b\u001e%\u001c\u0016\u001eE\t\u000b\u001e!\t\n\u0016\u000b!\t\u000b\u001e!\t\u0013\u0014\u001e\u0014\f\u000b\u001f\u0016\f\t\u001c\u001e\u001f\u0014\f\"\u0016\u001e\u001e\u0014\"\u001f\u001c\u0016\u001e\t\n-\f\u0016\"\u0014%%\u0014%\u0007\t\t\t\n\t\n\u0003\n\u000e\u0003\u001e\u0017\u0016\f \u000b\u001f\u001c\n\u0016\u001e\u000b\n\u0014-\u0016\f\u001fL\u0011\u000b\f\u0013\u0014\u0011\u0016\u000b!%\u000b\u001e!\u0012\u0016L\n\u0016\"\u000b\u001f\u0014!\u0011\u0016\u000b!%\u000b\u001f,\u001f\u001f-%\u0005\u0005'''\u0007\"\u000b\u001c\n%\u0016\u0007\"\u0016 \u0005!\u0016\") \u0014\u001e\u001f%\u0005)\nL\n\u0015L\u0015\u0015\u0018L\u001c\n\u001e\u0017\u0016\f \u000b\u001f\u001c\n\u0016\u001e\u000b\nL\f\u0014-\u0016\f\u001fL\n\u000b\f\u0013\u0014L\n\u0016\u000b!%L\u000b\u001e!L\"\u0016L\n\u0016\"\u000b\u001f\u0014!L\n\u0016\u000b!%L\u0014\n\u0015\u0018L\u0007-!\u0017\u0007"},{"page":4,"startToken":470,"endToken":536,"text":"\u0000\u0001\u0002\u0003\u0004\u0005\u0006\u0007\t\u0003\n\n\u000b\f\n\u0003\n\u000e\u0001\u000f\u0010\u0011\u0003\u0012\n\u0001\u000b\u0013\u0014\u0015\u0016\u0017\u0018\n\u0019\u001a\u001b\u001c\f\u0014\u001d\u001e\u0014\u001b\t\u001f \t!\"#\u0012$\t\u001e%\u0014\t\u0003\n\u000e\t\u001c\u001a\t\u001d\u0016\u0016\f\u001b\u001c&\u000b\u001e\u001c&\u0013\t\u001d\n\u0016\u001a\u0014\n \t'\u001c\u001e%\t\u001a\u001e\u000b\u001e\u0014\t\u0014&\u0014\f\u0013 \t\u000b\u0013\u0014&\u001d\u001c\u0014\u001a\t\u001e\u0016\t\n\u001d\u0016()\n\u0014(\u0014&\u001e\t\u001e%\u0014\u001c\f\t\f\u0014\u0013*\n\u000b\u001e\u0016\f \t)\f\u0016\u001d\u0014\u0014\u001b\u001c&\u0013\u001a$\t\u000b\u001a\t'\u0014\n\n\t\u000b\u001a\t'\u001c\u001e%\t\u001e%\u0014\t)\u000b\f\u001e\u001c\u001d\u001c)\u000b\u001e\u001c&\u0013\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\n\u0016'&\u0014\f\u001a\u001e\u0016\t\u0014&\u001a*\f\u0014\t\u000b\t\u0017\u000b\u001c\f\t\u000b&\u001b\t\u001d\u0016&\u001a\u001c\u001a\u001e\u0014&\u001e\t\u000b))\n\u001c\u001d\u000b\u001e\u001c\u0016&\t\u0016\u0017\t\f\u0014+*\u001c\f\u0014(\u0014&\u001e\u001a\t\u000b&\u001b\t)\f\u0016\u001d\u0014\u001b*\f\u0014\u001a\t\n\u000b\u001d\f\u0016\u001a\u001a\u001e%\u0014\t\u0003\n\u000e\t\u001a \u001a\u001e\u0014(\u0007\t\n*\u001d%\t\u001d\u0016()\n\u0014(\u0014&\u001e\u000b\f\u001c\u001e \t\u001c\u001a\t\u001d\f\u001c\u001e\u001c\u001d\u000b\n\t\u001e\u0016\t\u0014&\u000b\u001f\n\u001c&\u0013\t)\f\u0016\u000b\u001d\u001e\u001c,\u0014\t)\n\u000b&&\u001c&\u0013$\t\n\u001d\u0016&\u001a\u001c\u001a\u001e\u0014&\u001e\t\u001a\u001e*\u001b $\t\u0017\u000b\u001a\u001e\u0014\f\t\u001d\u0016&&\u0014\u001d\u001e\u001c\u0016&\u001a$\t\u000b&\u001b\t\f\u0014\n\u001c\u000b\u001f\n\u0014\t\u0016)\u0014\f\u000b\u001e\u001c\u0016&\u001a\t\u0016\u0017\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001b\u001a$\t\u000b\n\n\t'%\u001c\n\u0014\t\n)\f\u0016\u001e\u0014\u001d\u001e\u001c&\u0013\t\u001d*\u001a\u001e\u0016(\u0014\f\u001a\t\u0017\f\u0016(\t*&\f\u0014\u000b\u001a\u0016&\u000b\u001f\n\u0014\t\u001d\u0016\u001a\u001e\t\u001a%\u001c\u0017\u001e\u001c&\u0013\u0007\t\n\u0000%\u0014)\f\u0016)\u0016\u001a\u000b\n\t\u000b\u001b\u001b\f\u0014\u001a\u001a\u0014\u001a\t\u0017\u001c,\u0014\t-\u0014 \t\u001e\u0016)\u001c\u001d\u001a\t\u0017\f\u0016(\t\u001e%\u0014\t!\"#\u0012\t\u000e\f\u001b\u0014\f\u0007\t\n\t\n./1234\t56789:2668:7526\t3;;<5:37526=>\t=7?458=>\t78:@65:3<\t=7364394=>\t364\t\n2;89375263<\t98A?598B867=/\t\n\t\u000b&\u000b\u0013\u0014(\u0014&\u001e\t\u0017\u001c\f\u001a\u001e\t)\f\u0016)\u0016\u001a\u0014\u001a\t\u001e\u0016\t\u001b\u0014\u0017\u001c&\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001b\u001a\t\u000b\u001a\t\u0014&\u001b\t*\u001a\u0014\f\u001a\t\u001f\u0014%\u001c&\u001b\t)\u0016\u001c&\u001e\u001a\t\u0016\u0017\t\n\u001c&\u001e\u0014\f\u001d\u0016&&\u0014\u001d\u001e\u001c\u0016&\t'\u001c\u001e%\t)\u0014\u000b-\t\n\u0016\u000b\u001b\t\u0016\u0017\tCD\t\tE\t\u0016\f\t\u0013\f\u0014\u000b\u001e\u0014\f\t\u000b&\u001b\t\u001c&\u001e\u0014\f\u001d\u0016&&\u0014\u001d\u001e\u001c&\u0013\t\u001e\u0016\t\u001e%\u0014\t\n\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u001a \u001a\u001e\u0014($\t&\u000b(\u0014\n \t\u001e%\u0014\t\u0003\n\u000e\t\u001d\u0016&\u001e\f\u0016\n\n\u0014\u001b\t\u0013\f\u001c\u001b\u0007\t\u0000%\u001c\u001a\t\u001b\u0014\u0017\u001c&\u001c\u001e\u001c\u0016&\tFGHIGJKH\tMNOPQH\t\nR*\f\u001c\u001a\u001b\u001c\u001d\u001e\u001c\u0016&\u000b\n\t\u000b*\u001e%\u0016\f\u001c\u001e \t\u0016,\u0014\f\t\u001e%\u0014\t\u001c&\u001e\u0014\f\u001a\u001e\u000b\u001e\u0014\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u001a \u001a\u001e\u0014(\t'\u001c\u001e%\u0016*\u001e\t\u001c&\u0017\f\u001c&\u0013\u001c&\u0013\t\u0016&\t\u001e%\u0014\t\nSKTKGQHTUKVWFXKY\tWZGF\tFGKTX[\tHGFZXJG\tT\\]\tKVG\t]XHKFX^UKXW\\\tHYHKG_\u0007\t\t\t\u000b&\u000b\u0013\u0014(\u0014&\u001e\t\n\f\u0014\u001d\u0016\u0013&\u001c`\u0014\u001a\t\u001e%\u000b\u001e\tKVG\taSbQH\tIFWIWHG]\t\u001b\u0014\u0017\u001c&\u001c\u001e\u001c\u0016&\t\u001b\u0016\u0014\u001a\t&\u0016\u001e\t\u0014&\u001d\u0016()\u000b\u001a\u001a\t\u000b\n\n\t\n\u0016\u000b\u001b\t\u001d\u0016&&\u0014\u001d\u001e\u001c\u0016&\u001a\t\n\u001e%\u000b\u001e(\u000b \u001d\u0016&&\u0014\u001d\u001e\t\u001e%\f\u0016*\u0013%\t\u001e%\u0014\t\u001b\u001c\u001a\u001e\f\u001c\u001f*\u001e\u001c\u0016&\t\u0013\f\u001c\u001b\t\u000b&\u001b\t\u001c()\u000b\u001d\u001e\t\u001e%\u0014\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u001a \u001a\u001e\u0014($\t&\u0016\f\t\n'\u0016*\n\u001b\u001c\u001e\u001c&\u001d\n*\u001b\u0014\t\n\u0016\u000b\u001b\u001a\t\n\u0014\u001a\u001a\t\u001e%\u000b&\tCD\t\tE\t\u001e%\u000b\u001e\t\u001d\u0016&&\u0014\u001d\u001e\t\u001b\u001c\f\u0014\u001d\u001e\n \t\u001e\u0016\t\u001e%\u0014\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u001a \u001a\u001e\u0014(\u0007\t\n\u0019\u001a\u001e%\u0014\u0003\n\u000e\t\u001b\u0014,\u0014\n\u0016)\u001a\tKTFXcc\tIFWZXHXW\\H\tKW\tT]]FGHH\tMNOPQH\tHIGJXcXJ\tJW\\JGF\\H\tcWF\t[TFdG\t[WT]\t\n\u001d\u0016&&\u0014\u001d\u001e\u001c\u0016&\u001a\t\u001e\u0016\t\u001e%\u0014\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u001a \u001a\u001e\u0014($\t\t\u000b&\u000b\u0013\u0014(\u0014&\u001e\t\u001c\u001a\t\u001e\u000b-\u001c&\u0013\t\u001d\u000b\f\u0014\t\u001e\u0016\t\u0014&\u001a*\f\u0014\t\u001e%\u0016\u001a\u0014\t\n)\f\u0016,\u001c\u001a\u001c\u0016&\u001a\t\u000b\f\u0014\t)\f\u0016)\u0014\f\n \t\u001c&\u001e\u0014\u0013\f\u000b\u001e\u0014\u001b\t\u001c&\u001e\u0016\t\u001e%\u0014\t\u0016,\u0014\f\u000b\n\n\t\u001e\u000b\f\u001c\u0017\u0017\t\u0017\f\u000b(\u0014'\u0016\f-\u0007\t!\u0016\f\t\u0014e\u000b()\n\u0014$\t\n(\u000b&\u000b\u0013\u0014(\u0014&\u001e\t\u001d\n\u000b\f\u001c\u0017\u001c\u0014\u001a\t\u001e%\u000b\u001e\t\u001e%\u0014\t\u0003\n\u000e\t'\u001c\n\n\t\u001d\u0016&\u001e\u001c&*\u0014\t\u001e\u0016\t\u001a\u001e*\u001b \t\u001c()\u000b\u001d\u001e\u001a\t\u001e\u0016\t\u001e%\u0014\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\n\u001a \u001a\u001e\u0014(\u0016\u0017\t\u000b& \t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001b\t\u001e%\u000b\u001e\t\u001d\u0016&&\u0014\u001d\u001e\u001a\t\u001e\u0016\t\u001e%\u0014\t\u001b\u001c\u001a\u001e\f\u001c\u001f*\u001e\u001c\u0016&\t\u001a \u001a\u001e\u0014(\t\u0016\f\t\n\u0016\u000b\u001b\t\u001e%\u000b\u001e\t\u0017\u000b\n\n\u001a\t\u001f\u0014\n\u0016'\t\n\u001e%\u0014CD\tE\t)\u0014\u000b-\t\n\u0016\u000b\u001b\t\u001e%\f\u0014\u001a%\u0016\n\u001b\t\u001f*\u001e\t\u001d\u0016&&\u0014\u001d\u001e\u001a\t\u001e\u0016\t\u001e%\u0014\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u001a \u001a\u001e\u0014(\u0007\t\u0000%\u0014\t\u0003\n\u000e\t'\u001c\n\n\t\n\u001d\u0016&\u001e\u001c&*\u0014\u001e\u0016\t'\u0016\f-\t'\u001c\u001e%\t\u0006\"#\u0012\t\u000b&\u001b\t\u0016\u001e%\u0014\f\t\f\u0014\u0013*\n\u000b\u001e\u0016\f\u001a\t\u001e\u0016\t\u000b\u001b\u001b\f\u0014\u001a\u001a\t\u001a(\u000b\n\n\u0014\f\t\u000b&\u001b\t\u001b\u001c\u001a\u001e\f\u001c\u001f*\u001e\u0014\u001b\t\n\n\u0016\u000b\u001b\u001a\u001c&\u001e%\u0014\t\u0017*\u001e*\f\u0014\u0007\t\n\u0000%\u0014\u0003\n\u000e\u000b\n\u001a\u0016\t)\f\u0016)\u0016\u001a\u0014\u001a\t\u0014&%\u000b&\u001d\u0014\u001b\t\u000b&\u001b\t\u0016&\u0013\u0016\u001c&\u0013\t\u001d\u0016\u0016\f\u001b\u001c&\u000b\u001e\u001c\u0016&\t'\u001c\u001e%\t\u001e%\u0014\t)\u000b\f\u001e\u001c\u001d\u001c)\u000b\u001e\u001c&\u0013\t\n\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u0016'&\u0014\f\u001a\t\u0016&\t\u001e%\u0014\t\n\u0016\u000b\u001b\t\u000b&\u001b\t\f\u0014\u001a\u0016*\f\u001d\u0014\t\u001c&\u001e\u0014\f\u001d\u0016&&\u0014\u001d\u001e\u001c\u0016&\t)\f\u0016\u001d\u0014\u001a\u001a\u0014\u001a\t\u000b&\u001b\t\u0014e)\u0014\u001d\u001e\u001a\t\n\u001e%\u0014)\u000b\f\u001e\u001c\u001d\u001c)\u000b\u001e\u001c&\u0013\t\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u0016'&\u0014\f\u001a\t\u001e\u0016\t\u000b\n\u001c\u0013&\t\u001e%\u0014\u001c\f\t\n\u0016\u000b\u001b\t\u000b))\n\u001c\u001d\u000b\u001e\u001c\u0016&\t)\f\u0016\u001d\u0014\u001a\u001a\u0014\u001a\t'\u001c\u001e%\t\u001e%\u0014\t\naSbQHFGHWUFJG\tX\\KGFJW\\\\GJKXW\\\tIFWJGHH\tKW\tG\\HUFG\t\u001a*\u0017\u0017\u001c\u001d\u001c\u0014&\u001e\t,\u001c\u001a\u001c\u001f\u001c\n\u001c\u001e \t\u0017\u0016\f\t\u001e%\u0014\t\u0003\n\u000e\t\u001e\u0016\t)\n\u000b&\t\n\u0017\u0016\f&\u0014'\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001b\u001a\t\u000b&\u001b\t(\u000b\u001c&\u001e\u000b\u001c&\t\f\u0014\n\u001c\u000b\u001f\u001c\n\u001c\u001e \t\u0016&\u001d\u0014\t\u001e%\u0014 \t\u000b\f\u0014\t\u001c&\u001e\u0014\f\u001d\u0016&&\u0014\u001d\u001e\u0014\u001b\u0007\t\t\n\u0000%\u0014\u0003\n\u000e'\u001c\n\n\t\u0014&%\u000b&\u001d\u0014\t\u001c\u001e\u001a\t)\f\u0016\u001d\u0014\u001a\u001a\t\u0017\u0016\f\t\f\u0014,\u001c\u0014'\u001c&\u0013\t\u000b&\u001b\t\u001b\u0016\u001d*(\u0014&\u001e\u001c&\u0013\t\n\u0016\u000b\u001b\t\u001c&\u001e\u0014\f\u001d\u0016&&\u0014\u001d\u001e\u001c\u0016&\t\n\f\u0014+*\u0014\u001a\u001e\u001a\u001e%\f\u0016*\u0013%\t\u001d\u0016&\u001d*\f\f\u0014&\u001d\u0014\t\u001c&\t\u001e%\u0014\t\u0000\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\t\u0001\n\u000b&&\u001c&\u0013\t\u0001\f\u0016\u001d\u0014\u001a\u001a\t\u001e\u0016\t\u0014&\u001a*\f\u0014\t\f\u0014\n\u001c\u000b\u001f\u001c\n\u001c\u001e \t\n\u000b&\u001b\u001d\u0016&\u001a\u001c\u001a\u001e\u0014&\u001d \t'\u001c\u001e%\t\n\u0016&\u0013f\u001e\u0014\f(\t)\n\u000b&\u001a\u0007\t\n)\u0014\u001d\u001c\u0017\u001c\u001d\u000b\n\n $\t\u001e%\u0014\t\u0003\n\u000e\t'\u001c\n\n\t\f\u0014,\u001c\u0014'\t\u000b& \t\u001a)\u0014\u001d\u001c\u0017\u001c\u001d\t\u0016*\u001ef\n\u0016\u0017f\u001d \u001d\n\u0014\u001e\f\u000b&\u001a(\u001c\u001a\u001a\u001c\u0016&\u000b\u001b\u001b\u001c\u001e\u001c\u0016&\u001a\u0016\f*)\u0013\f\u000b\u001b\u0014\u001a\u000b\u001a\u001a\u0016\u001d\u001c\u000b\u001e\u0014\u001b'\u001c\u001e%\n\u000b\f\u0013\u0014\n\u0016\u000b\u001b\u001a\u0016&\u000b(\u0016&\u001e%"},{"page":5,"startToken":536,"endToken":676,"text":"\u0000\u0001\u0002\u0003\u0004\u0005\u0006\u0007\t\u0003\n\n\u000b\f\n\u0003\n\u000e\u0001\u000f\u0010\u0011\u0003\u0012\n\u0001\u000b\u0013\u0014\u0015\u0016\u0017\u0018\n\u0019\u000b\u001a\u001b\u001a\u001b\u001c\u0016\f\u001d\u0014\f\t\u001e\u0016\t\u000b\u001f\u001f\u0016  \u0016\u001d\u000b\u001e\u0014\t!\"#$%&\t\u0018'()'\t\u001d\u000b*\t+\f\u0016\u001f\u0014\u001a\u001a\t\f\u0014,-\u001b\f\u0014 \u0014\u001c\u001e\t\u0017\u0016\f\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\n\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u0016.\u001c\u0014\f&%\t\n\u0016\u000b\u001d\t\u001b\u001c\u001e\u0014\f\u001f\u0016\u001c\u001c\u0014\u001f\u001e\u001b\u0016\u001c\t\u001a\u001e-\u001d\u001b\u0014\u001a\u0007\t\n\u0003\u001c\u000b\u001d\u001d\u001b\u001e\u001b\u0016\u001c/\t\u001e0\u0014\t\u0003\n\u000e\t+\f\u0016+\u0016\u001a\u0014\u001a\t\u001e0\u0014\t\u0017\u0016\n\n\u0016.\u001b\u001c\u0013\t\u001e\u0014\u001f0\u001c\u001b\u001f\u000b\n\t\f\u0014,-\u001b\f\u0014 \u0014\u001c\u001e\u001a1\t\n2 3\u0014,-\u001b\f\u0014\t0\u0016-\f\n*\t\u0017\u0016\f\u0014\u001f\u000b\u001a\u001e\u001a/\t\u001e\u0014\n\u0014 \u0014\u001e\f*/\t\u000b\u001c\u001d\t\u0016\u001e0\u0014\f\t\u0016+\u0014\f\u000b\u001e\u001b\u0016\u001c\u000b\n\t\u001d\u000b\u001e\u000b\t\u001c\u0014\u001f\u0014\u001a\u001a\u000b\f*\t\u001e\u0016\t\n+\f\u00164\u001b\u001d\u0014\t\u001e0\u0014\t\u0003\n\u000e\t.\u001b\u001e0\t\u001a-\u0017\u0017\u001b\u001f\u001b\u0014\u001c\u001e\t\u0016+\u0014\f\u000b\u001e\u001b\u0016\u001c\u000b\n\t4\u001b\u001a\u001b\u0019\u001b\n\u001b\u001e*5\t\n2 \u000f\u001e\u001b\n\u001b6\u0014\t\u001f\u0016  -\u001c\u001b\u001f\u000b\u001e\u001b\u0016\u001c\t+\f\u0016\u001e\u0016\u001f\u0016\n\u001a\t\u0017\u0016\f\t\u001e0\u0014\t\u0003\n\u000e\t\u001e\u0016\t\u001f\u0016\u0016\f\u001d\u001b\u001c\u000b\u001e\u0014\t.\u001b\u001e0\t\u001e0\u0014\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\n\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u0016.\u001c\u0014\f\t\u001e\u0016\t\f\u0014 \u0016\u001e\u0014\n*\t\u001d\u001b\u001a\u001f\u0016\u001c\u001c\u0014\u001f\u001e\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\u001a\t.0\u0014\u001c\t\u001c\u0014\u001f\u0014\u001a\u001a\u000b\f*\t\u001e\u0016\t\n \u000b\u001b\u001c\u001e\u000b\u001b\u001c\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u001a*\u001a\u001e\u0014 \t\f\u0014\n\u001b\u000b\u0019\u001b\n\u001b\u001e*/\t\u000b\u001c\u001d5\t\n2 7\u001a\u001e\u000b\u0019\n\u001b\u001a0\t\f\u0014,-\u001b\f\u0014 \u0014\u001c\u001e\u001a\t\u0017\u0016\f\t \u000b\u001b\u001c\u001e\u000b\u001b\u001c\u001b\u001c\u0013\t\u001f\u0016  -\u001c\u001b\u001f\u000b\u001e\u001b\u0016\u001c\t\u001f0\u000b\u001c\u001c\u0014\n\u001a\t\u0019\u0014\u001e.\u0014\u0014\u001c\t\u001e0\u0014\t\n\u0003\n\u000e\t\u000b\u001c\u001d\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u001f-\u001a\u001e\u0016 \u0014\f\u001a\t\u001a\u0014\f4\u001b\u001c\u0013\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\u001a\u0007\t\n8\u0016\f\u0016+\u0014\f\u000b\u001e\u001b\n\u0016\u001c\u000b\n\t\u000b.\u000b\f\u0014\u001c\u0014\u001a\u001a/\t\u001e0\u0014\t\u0003\n\u000e\t\u000b\n\u001a\u0016\t+\f\u0016+\u0016\u001a\u0014\u001a\t\u001e\u0016\t\f\u0014,-\u001b\n\f\u0014\t\u001a+\u0014\u001f\u001b\n\u0017\u001b\n\u001f\t\u001b\u001c\u0017\u0016\f \u000b\u001e\u001b\u0016\u001c\t\u0017\f\u0016 \t\n+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u0016.\u001c\u0014\f\u001a\t\u001d-\f\u001b\u001c\u0013\t\u001e0\u0014\t\u001b\u001c\u001e\u0014\f\u001f\u0016\u001c\u001c\u0014\u001f\u001e\u001b\u0016\u001c\t+\f\u0016\u001f\u0014\u001a\u001a\u0007\t\n9:<=>?\t?@AB>CA@DBEF\tABG\tEH>?=ID@\tC@=?DE?J=B\t\n\u00000\u0014\u0003\n\u000e\u0014K+\u0014\u001f\u001e\u001a\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u0016.\u001c\u0014\f\u001a\t\u001e\u0016\t\u0014\u001a\u001e\u000b\u0019\n\u001b\u001a0\tL-\u001a\u001e\t\u000b\u001c\u001d\t\f\u0014\u000b\u001a\u0016\u001c\u000b\u0019\n\u0014\t\n+\f\u00164\u001b\u001a\u001b\u0016\u001c\u001a\t\u001b\u001c\t\u001e0\u0014\u001b\f\t\u001e\u000b\f\u001b\u0017\u0017\u001a\t\u001b\u001c\t\u0016\f\u001d\u0014\f\t\u001e\u0016\t+\f\u00144\u0014\u001c\u001e\t\u001f\u0016\u001a\u001e\t\u001a0\u001b\u0017\u001e\u001b\u001c\u0013\t\u0017\f\u0016 \t\u0016\u001c\u0014\t\u001f-\u001a\u001e\u0016 \u0014\f\t\u001e\u0016\t\u000b\u001c\u0016\u001e0\u0014\f\u0007\t\n\u00000\u0014\u0003\n\u000e\u001b\u001a\t\u001f\n\u000b\f\u001b\u0017*\u001b\u001c\u0013\t0\u0016.\t+\f\u0016+\u0014\f\t\u001b +\n\u0014 \u0014\u001c\u001e\u000b\u001e\u001b\u0016\u001c\t\u0016\u0017\t\u001e0\u0014\t\u0014K\u001b\u001a\u001e\u001b\u001c\u0013\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u000b\u001f\u001f\u0014\u001a\u001a\t\n\u001f0\u000b\f\u0013\u0014\u001aM\u0000N\u0012O\t.\u001b\n\n\t+\f\u00144\u0014\u001c\u001e\t-\u001c\f\u0014\u000b\u001a\u0016\u001c\u000b\u0019\n\u0014\t\u001f\u0016\u001a\u001e\t\u001a0\u001b\u0017\u001e\u001b\u001c\u0013\t\u0019\u0014\u001e.\u0014\u0014\u001c\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\nPQRS&TU&&UVS\tVXSYQ&%\t\u001f-\u001a\u001e\u0016 \u0014\f\t\u0019\u000b\u001a\u0014\u001a\u0007\t8\u000b\u001b\f\t\u000b\u001f\u001f\u0016-\u001c\u001e\u001b\u001c\u0013\t\u0016\u0017\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\n\u0016.\u001c\u0014\f\f\u00144\u0014\u001c-\u0014\t\f\u0014,-\u001b\f\u0014 \u0014\u001c\u001e\u001a\t\u000b\u001c\u001d\t\u000b\u001c\u001c-\u000b\n\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\f\u00144\u0014\u001c-\u0014\t\u001f\f\u0014\u001d\u001b\u001e\u001a\t.\u001b\n\n\t\u0014\u001c\u001a-\f\u0014\t\u001e0\u000b\u001e\t\n\u0016\u001c\n*\u001e0\u0014\f\u00144\u0014\u001c-\u0014\t\f\u0014,-\u001b\f\u0014 \u0014\u001c\u001e\t\u001c\u0014\u001e\t\u0016\u0017\t\u001f\u0016\u001c\u001e\f\u001b\u0019-\u001e\u001b\u0016\u001c\u001a\t\u001e0\u000b\u001e\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u0016.\u001c\u0014\f\u001a\t\n\f\u0014\u001f\u0014\u001b4\u0014\u0017\f\u0016 \t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\u001a\t\u001b\u001a\t-\u001a\u0014\u001d\t\u001e\u0016\t\u001d\u0014\u001e\u0014\f \u001b\u001c\u0014\t\u001e0\u0014\t\f\u0014\u0013\u001b\u0016\u001c\u000b\n\t0\u001b\u00130(4\u0016\n\u001e\u000b\u0013\u0014\t\u0000N\u0012\t\u001a\u0014\u001e\t\u0019*\t\u001e0\u0014\t\n\u0003\n\u000e\u000b\u001c\u001d\f\u0014\u001f\u00164\u0014\f\u0014\u001d\t\u000b\u001f\f\u0016\u001a\u001a\t\u000b\n\n\t\n\u0016\u000b\u001d\u001a\t\u000b\u001c\u001d\t\u0014K+\u0016\f\u001e\u001a\u0007\t\t\nZSQY&[VS&Y\tPV\t!\"#$%&\tQY\\]Y&P\t^VQ\tUT[QV_Y`\tPQRS&[RQYSab\tRQV]S`\taV&P&c\tPdY\tZef\tXUgg\t\n+-\u0019\n\u001b\u001f\n*+\u0016\u001a\u001e\t\u000b\u0013\u0013\f\u0014\u0013\u000b\u001e\u0014\t\u000b \u0016-\u001c\u001e\u001a\t\u0016\u0017\t+\f\u0016+\u0016\u001a\u0014\u001d\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\t\u000b\u001d\u001d\u001b\u001e\u001b\u0016\u001c\u001a\t\u001b\u001c\t\u001e0\u0014\t\u0003\n\u000e\t\u0016+\u0014\f\u000b\u001e\u001b\u001c\u0013\t\n\u000b\f\u0014\u000b5+\n\u000b\u001c\u001c\u0014\u001d\t\u001c\u0014\u001e.\u0016\fh\t-+\u0013\f\u000b\u001d\u0014\u001a\t\u001c\u0014\u0014\u001d\u0014\u001d\t\u001e\u0016\t\u000b\u001f\u001f\u0016  \u0016\u001d\u000b\u001e\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\u001a5\t\u000b\u001c\u001d\t\u001f\u0016\u001a\u001e\t\n\u0014\u001a\u001e\u001b \u000b\u001e\u0014\u001a\t\u0017\u0016\f\t\u0014\u000b\u001f0\t+\n\u000b\u001c\u001c\u0014\u001d\t\u001c\u0014\u001e.\u0016\fh\t-+\u0013\f\u000b\u001d\u0014\t\u001b\u001d\u0014\u001c\u001e\u001b\u0017\u001b\u0014\u001d\t\u000b\u001a\t\u001c\u0014\u0014\u001d\u0014\u001d\t\u0017\u0016\f\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\u001a\u0007\t\ni:jBAklJBm\tE=nl=EA?DG\tlA@mD\tl=AG>\tABG\tmDBD@A?J=B\t\n\t\u000b\u001c\u000b\u0013\u0014 \u0014\u001c\u001e\t+\f\u0016+\u0016\u001a\u0014\u001a\t\u001e\u0016\t\u001f\f\u0014\u000b\u001e\u0014\t\u000b\t\u001e\f\u000b\u001c\u001a+\u000b\f\u0014\u001c\u001e\t+\u000b\u001e0.\u000b*\t\u0017\u0016\f\t\u001e0\u0014\t\u0003\n\u000e\t\u000b\u001c\u001d\t+\u000b\f\u001e\u001b\u001f\u001b+\u000b\u001e\u001b\u001c\u0013\t\n\u001e\f\u000b\u001c\u001a \u001b\u001a\u001a\u001b\u0016\u001c\t\u0016.\u001c\u0014\f\u001a\t\u001e\u0016\t\u001a\u001e-\u001d*\t\u001f\u0016(\n\u0016\u001f\u000b\u001e\u0014\u001d\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\u001a\t\u000b\u001c\u001d\t\u0013\u0014\u001c\u0014\f\u000b\u001e\u001b\u0016\u001c\t\u001e\u0016\u0013\u0014\u001e0\u0014\f\u0007\t\u00000\u0014\u001a\u0014\t\n+\f\u0016\u001f\u0014\u001d-\f\u0014\u001a\t+\f\u00164\u001b\u001d\u0014\t\u001f\n\u000b\f\u001b\u001e*\t\u0017\u0016\f\t\u0019\u0016\u001e0\t\u0013\f\u0014\u0014\u001c\u0017\u001b\u0014\n\u001d\t+\f\u0016L\u0014\u001f\u001e\u001a\t\u000b\u001c\u001d\t\u0014K\u001b\u001a\u001e\u001b\u001c\u0013\t\u0013\u0014\u001c\u0014\f\u000b\u001e\u0016\f\u001a/\t\u0014\u001c\u000b\u0019\n\u001b\u001c\u0013\t\n\u0017\u000b\u001a\u001e\u0014\f\u000b\u001c\u001d\t \u0016\f\u0014\t\u0014\u0017\u0017\u001b\u001f\u001b\u0014\u001c\u001e\t\u001a\u001e-\u001d\u001b\u0014\u001a\t\u0017\u0016\f\t\u001f\u0016(\n\u0016\u001f\u000b\u001e\u0014\u001d\t\u0017\u000b\u001f\u001b\n\u001b\u001e\u001b\u0014\u001a\u0007\t\t\u000b\u001c\u000b\u0013\u0014 \u0014\u001c\u001e\t+\f\u0016+\u0016\u001a\u0014\u001a\t\u001e\u0016\t\n\u001d\u0016\u001f- \u0014\u001c\u001e\u0014K\u001b\u001a\u001e\u001b\u001c\u0013\u0003\n\u000e\u000b\u001c\u001d\n\u001e\u000b\u001e\u0014\f-\n\u0014\u001a\u001e0\u000b\u001e\u000b\n\n\u0016.\u0016\u001c\u001a\u001b\u001e\u0014\u0013\u0014\u001c\u0014\f\u000b\u001e\u001b\u0016\u001c.\u001b\u001e0\u0016-\u001e\u000b\u001c\u0003\n\u000e\n\u001a\u001e-\u001d*\u001a\u0016\n\u0016\u001c\u0013\u000b\u001a\u001b\u001e\u0016\u001c\n*\u001a\u0014\f4\u0014\u001a\u0016\u001c\u001a\u001b\u001e\u0014\n\u0016\u000b\u001d\u0007\u000e\u001c\u001e0\u0014\u0016\u001e0\u0014\f0\u000b\u001c\u001d/\u0013\u0014\u001c\u0014\f\u000b\u001e\u001b\u0016\u001c\u001e0\u000b\u001e.\u001b\n\n\u001b\u001cL\u0014\u001f\u001e\n\u0014\u001c\u0014\f\u0013*\u0016\u001c\u001e\u0016\u001e0\u0014\u0013\f\u001b\u001d.\u001b\n\n\f\u0014,-\u001b\f\u0014\u000b\u001c\u0003\n\u000e\u001b\u001c\u001e\u0014\f\u001f\u0016\u001c\u001c\u0014\u001f\u001e\u001b\u0016\u001c\u001a\u001e-\u001d*\u001e\u0016\u001d\u0014\u001e\u0014\f \u001b\u001c\u0014\u001e0\u0014\u001b +"},{"page":6,"startToken":676,"endToken":756,"text":"\u0000\u0001\u0002\u0003\u0004\u0005\u0006\u0007\t\u0003\n\n\u000b\f\n\u0003\n\u000e\u0001\u000f\u0010\u0011\u0003\u0012\n\u0001\u000b\u0013\u0014\u0015\u0016\u0017\u0018\n\u0016\u0019\u001a\u001b\u0014\u0013\f\u001c\u001d\t\u000b\u0019\u001d\t\u000b\u0019\u001e\t\u000b\u0017\u0017\u0014\u001f\u001a\u0014\u001d\t \u001e \u001a\u0014! \u0007\t\"\u0016#\u0014$\u0014\f%\t\u001a\u001b\u0014\t\u0003\n\u000e\t\u0013\u0014\u0019\u0014\f\u000b\u001a\u0016\f\t \u001a&\u001d\u001e\t'\f\u0016\u001f\u0014  \t#\u001c\n\n\t\n())*+,-./0\t2,/3\t/30\t4.*/,(,4./,-5\t/*.-67,66,)-\t)2-0*86\t9).+\t6/:+;\t4*)(066\t/)\t,+0-/,<;\t/30\t\n!\u0016 \u001a\u001f\u0016 \u001a=\u0014\u0017\u0017\u0014\u001f\u001a\u001c$\u0014\t\u001a\f\u000b\u0019 !\u001c  \u001c\u0016\u0019\t \u0016\n&\u001a\u001c\u0016\u0019 \t\u0017\u0016\f\t\u001a\u001b\u0014\u001c\f\t \u001b\u000b\f\u0014\u001d\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019\u0007\t\n\u0003\u0019\u000b\u001d\u001d\u001c\u001a\u001c\u0016\u0019%\t\u001a\u0016\t\u000b\u001d\u001d\f\u0014  \t\u001f\u0016\u0019\u001f\u0014\f\u0019 \t\u000b\f\u0016&\u0019\u001d\t\u0013\u0014\u0019\u0014\f\u000b\u001a\u001c\u0016\u0019\t#\u001c\u001a\u001b\u001d\f\u000b#\u001c\u0019\u0013\t\u0017\f\u0016!\t\u001a\u001b\u0014\t\u0003\n\u000e\t!\u000b\f>\u0014\u001a\t\u001a\u0016\t\n \u0014\f$\u0014\u0016\u0019 \u001c\u001a\u0014\t\n\u0016\u000b\u001d%\t\u001a\u001b\u0014\t\u0003\n\u000e\t\u001f\n\u000b\f\u001c\u0017\u001c\u0014 \t\u001a\u001b\u0014\t\f\u0014\u001f\u0014\u0019\u001a\n\u001e\t\u001d\u0014$\u0014\n\u0016'\u0014\u001d\t'\u0016\n\u001c\u001f\u001e\t\f\u0014?&\u001c\f\u001c\u0019\u0013\t\u0013\u0014\u0019\u0014\f\u000b\u001a\u0016\f \t\u001a\u0016\t\n\u0019\u0016\u001a\u001c\u0017\u001e\u001a\u001b\u0014\t\u0003\n\u000e\t\u001c\u0017\t\u001a\u001b\u0014\u001e\t\u001c\u0019\u001a\u0014\u0019\u001d\t\u001a\u0016\t\f\u0014'\u0016#\u0014\f\t\u0016\f\t\f\u0014\u001a\u001c\f\u0014\t\u0017\f\u0016!\t\u001a\u001b\u0014\t\u0003\n\u000e\t \u001e \u001a\u0014!\t \u0016\t\u001a\u001b\u0014\t\u0003\n\u000e\t\u000b\u0019\u001d\t\n\u0016\u001a\u001b\u0014\f \u001b\u000b$\u0014\t\u0017&\n\n\t\u000b#\u000b\f\u0014\u0019\u0014  \t\u000b\u0019\u001d\t\u001f\u000b\u0019\t&\u0019\u001d\u0014\f \u001a\u000b\u0019\u001d\t\u001a\u001b\u0014\t\u001c!'\n\u001c\u001f\u000b\u001a\u001c\u0016\u0019 \t\u0016\u0017\t &\u001f\u001b\t\u000b\u001f\u001a\u001c\u0016\u0019 \t\u0016\u0019\t\n@\u0014 \u0016&\f\u001f\u0014\tA\u001d\u0014?&\u000b\u001f\u001e\u0007\t\t\n\u0012\u0016\u0019 \u001c \u001a\u0014\u0019\u001a\t#\u001c\u001a\u001b\t\u001a\u001b\u0014\t\u000e\f\u001d\u0014\f%\t\t\u000b\u0019\u000b\u0013\u0014!\u0014\u0019\u001a\t\u000b\n \u0016\t'\f\u0016'\u0016 \u0014 \t\u001a\u0016\t\f\u0014?&\u001c\f\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d \t\u001f\u0016=\n\u0016\u001f\u000b\u001a\u0014\u001d\t\n2,/350-0*./,)-\t/)\t70/0*\t/30\t9).+86\t+07.-+\t,-+040-+0-/\t)<\t)<<60//,-5\t0-0*5;\t6)\t/30;\t\n\u001f\u000b\u0019B\u0014\u000b  \u0014  \u0014\u001d\t\u001a\u001b\u0014\u001c\f\t\u001d&\u0014\t\u001f\u001b\u000b\f\u0013\u0014 \t\u0017\u0016\f\t\u000b\u0019\u001f\u001c\n\n\u000b\f\u001e\t \u0014\f$\u001c\u001f\u0014 \u0007\t\nCDFGHIJKGH\tLMNHOJP\tQRST\tLMNHOURMMHUNJRM\tVFLQLW\tXHOYJUH\t\n\t\u000b\u0019\u000b\u0013\u0014!\u0014\u0019\u001a\t'\f\u0016'\u0016 \u0014 \t\u001a\u0016\t\u001f\f\u0014\u000b\u001a\u0014\t\u000b\t\u0017\n\u0014Z\u001cB\n\u0014\t\u001c\u0019\u001a\u0014\f\u001c!\t\n\u0016\u000b\u001d\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019\t[\\\u0003\u0011\u0003]\t\u0016\u0017\u0017\u0014\f\u001c\u0019\u0013\t\n\u001a\u001b\u000b\u001a#\u0016&\n\u001d\t\u0014\u0019\u000bB\n\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d \t\u001a\u0016\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\t\u0017\n\u0014Z\u001cB\n\u001e\t\u000b\u0019\u001d\t\f\u0014\u001f\u0014\u001c$\u0014\t \u0014\f$\u001c\u001f\u0014\t&'\t\u001a\u0016\t\u000b\t\u001f\u0014\f\u001a\u000b\u001c\u0019\t\n\n\u0014$\u0014\nB\u000b \u0014\u001d\t\u0016\u0019\t\u0013\f\u001c\u001d\t\u001f\u0016\u0019\u001d\u001c\u001a\u001c\u0016\u0019 \t\u000b\u0019\u001d\t\u001f\u0016\u0019 \u001a\f\u000b\u001c\u0019\u001a \t&\u0019\u001a\u001c\n\t\u0019\u0014\u001a#\u0016\f>\t&'\u0013\f\u000b\u001d\u0014 \t\u000b\f\u0014\t\u001f\u0016!'\n\u0014\u001a\u0014%\t\u000b\u001a\t\n#\u001b\u001c\u001f\u001b\u001a\u001c!\u0014\t\u001a\u001b\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\t#\u0016&\n\u001d\t #\u001c\u001a\u001f\u001b\t\u0016$\u0014\f\t\u001a\u0016\t\f\u0014\u001f\u0014\u001c$\u001c\u0019\u0013\t\u0017\u001c\f!\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019\t \u0014\f$\u001c\u001f\u0014\u0007\t\n\u0000\u001b\u001c #\u001c\n\n\n\u001c>\u0014\n\u001e\tB\u0014\t\u000b\tB\u0014 '\u0016>\u0014\t\u0016'\u001a\u001c\u0016\u0019\t\u0017\u0016\f\t\u0014\u000b\u001f\u001b\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d\tB\u000b \u0014\u001d\t\u0016\u0019\t\u001c\u001a \t'\u0016\u001c\u0019\u001a\t\u0016\u0017\t\n\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019\t\u000b\u0019\u001d\t\u001a\u001b\u0014\t\u001f\u0016\u0019 \u001a\f\u000b\u001c\u0019\u001a \t\u001c\u001a\t\u0017\u000b\u001f\u0014 %\t\u000b\u0019\u001d\t\u001a\u0016\tB\u0014\t\u001d\u0014$\u0014\n\u0016'\u0014\u001d\t\u001a\u001b\f\u0016&\u0013\u001b\t\u000b\t\u001f\u0016\u0019\u001a\f\u000b\u001f\u001a&\u000b\n\t\n\u000b\u0013\f\u0014\u0014!\u0014\u0019\u001a\t#\u001c\u001a\u001b\t\u001a\u001b\u0014\t'\u000b\f\u001a\u001c\u001f\u001c'\u000b\u001a\u001c\u0019\u0013\t\u001a\f\u000b\u0019 !\u001c  \u001c\u0016\u0019\t\u0016#\u0019\u0014\f\u0007\t\u0000\u001b\u001c \t\u0016'\u001a\u001c\u0016\u0019\t'\f\u0016$\u001c\u001d\u0014 \t\u0017\n\u0014Z\u001cB\u001c\n\u001c\u001a\u001e\t\u001a\u0016\t\n\u001a\u001b\u0014'\u000b\f\u001a\u001c\u001f\u001c'\u000b\u001a\u001c\u0019\u0013\t\u001a\f\u000b\u0019 !\u001c  \u001c\u0016\u0019\t\u0016#\u0019\u0014\f %\t\u0003\n\u000e%\t\u000b\u0019\u001d\t\u001d\u0014$\u0014\n\u0016'\u0014\f \t\u001a\u0016\t\u001f& \u001a\u0016!\u001c^\u0014\t \u0016\n&\u001a\u001c\u0016\u0019 \u0007\t\u0000\u001b\u0014\t\n\u0003\n\u000e\u001c \u0016\u0017\u0017\u0014\f\u001c\u0019\u0013\t\u001a\u001b\u001c \t\u0017\f\u000b!\u0014#\u0016\f>%\t#\u001b\u001c\u001f\u001b\t#\u001c\n\n\t\f\u0014?&\u001c\f\u0014\t\u001f& \u001a\u0016!\u0014\f= '\u0014\u001f\u001c\u0017\u001c\u001f\t \u001a&\u001d\u001e\t\f\u0014 &\n\u001a \t\u0017\f\u0016!\t\n\u001a\u001b\u0014'\u000b\f\u001a\u001c\u001f\u001c'\u000b\u001a\u001c\u0019\u0013\t\u001a\f\u000b\u0019 !\u001c  \u001c\u0016\u0019\t\u0016#\u0019\u0014\f \t\u001a\u0016\t\u0016'\u0014\f\u000b\u001a\u001c\u0016\u0019\u000b\n\u001c^\u0014\u0007\t\n\u0000\u001b\u0014\u0003\n\u000e#\u001c\n\n\t\u0014Z'\n\u0016\f\u0014\t\u000b\t'\u0014\f!\u000b\u0019\u0014\u0019\u001a\t\u0017\n\u0014Z\u001cB\n\u0014\t\n\u0016\u000b\u001d\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019\t\u0016'\u001a\u001c\u0016\u0019\t\u001a\u0016\t\u0014\u0019\u000bB\n\u0014\t\n\u000b\f\u0013\u0014\t\n\n\u0016\u000b\u001d \u001a\u0016\u0016'\u0014\f\u000b\u001a\u0014\t\u0017\n\u0014Z\u001cB\n\u001e\t\u001c\u0019\t\u000b\t\u0017&\u001a&\f\u0014\t \u001a\u000b>\u0014\u001b\u0016\n\u001d\u0014\f\t\u001c\u0019\u001c\u001a\u001c\u000b\u001a\u001c$\u0014\u0007\t\n_DF`N`OH\tURMaJTHOSNJRM\tRb\tJMNHOURMMHUNJRM\tRb\tGSOcH\tGRSTa\tdJNe\tHGHUNOJUSGGf\t\ngORIJPSNH\tcHMHOSNJRM\t\n\u0000\u001b\u0014\u0003\n\u000e#\u001c\n\n\t\u0014Z'\n\u0016\f\u0014\t'\f\u0016$\u001c \u001c\u0016\u0019 \t\u0017\u0016\f\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019\t\u001f& \u001a\u0016!\u0014\f \t\u001a\u0016\t \u0014\f$\u0014\t\u0014\n\u0014\u001f\u001a\f\u001c\u001f\u000b\n\n\u001e\t\n'\f\u0016Z\u001c!\u000b\u001a\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b\u001d \t\u001c\u0019\t\u000b\t\u0017&\u001a&\f\u0014\t \u001a\u000b>\u0014\u001b\u0016\n\u001d\u0014\f\t\u001c\u0019\u001c\u001a\u001c\u000b\u001a\u001c$\u0014\u0007\t\u0010\u000b \u0014\u001d\t\u0016\u0019\t \u001a\u000b>\u0014\u001b\u0016\n\u001d\u0014\f\t\u0017\u0014\u0014\u001dB\u000b\u001f>%\t\n\u001a\u001b\u0014\u0003\n\u000e\u001c\u0019\u001a\u0014\u0019\u001d \t\u001a\u0016\t'\f\u001c\u0016\f\u001c\u001a\u001c^\u0014\t\u001a\u001b\u0014\t!\u0016\f\u0014\t\u001f\u0016!!\u0016\u0019\t \u001a\u000b\u0019\u001d=\u000b\n\u0016\u0019\u0014\t\u000b\u0019\u001d\t\u001f\u0016=\n\u0016\u001f\u000b\u001a\u0014\u001d\t\n\u0016\u000b\u001d\t\u000b\u0019\u001d\t\n\u0013\u0014\u0019\u0014\f\u000b\u001a\u0016\f\t\u001c\u0019\u001a\u0014\f\u001f\u0016\u0019\u0019\u0014\u001f\u001a\u001c\u0016\u0019 \t#\u001c\u001a\u001b\t\u001a\u001b\u001c \t'\f\u0016'\u0016 \u000b\n\t\u000b\u0019\u001d\t\u0017\u001c\n\u001c\u0019\u0013\t\u000b\u0019\u001d\t#\u001c\n\n\t\u0017\u0016\u001f& \t\u0016\u0019\t'\f\u0016Z\u001c!\u000b\u001a\u0014\t\n\u0016\u000b\u001d\t\n\u000b\u0019\u001d\u0013\u0014\u0019\u0014\f\u000b\u001a\u001c\u0016\u0019\t\u000b\f\f\u000b\u0019\u0013\u0014!\u0014\u0019\u001a \t\u0016\u0019\u001f\u0014\t\u001a\u001b\u0014\t'\f\u0016\u001f\u0014  \t\u0017\u0016\f\t\u001f\u0016=\n\u0016\u001f\u000b\u001a\u001c\u0016\u0019\t\u001c \t&\u0019\u001d\u0014\f#\u000b\u001e\u0007\t\t\nhiXLjLikX\tiF\tjlm\thnojLmX"},{"page":7,"startToken":756,"endToken":1273,"text":"\u0000\u0001\u0002\u0003\u0004\u0005\u0006\u0007\t\u0003\n\n\u000b\f\n\u0003\n\u000e\u0001\u000f\u0010\u0011\u0003\u0012\n\u0001\u000b\u0013\u0014\u0015\u0016\u0017\u0015\n\u0018\u0019\u001a\u001b\u001c\u001d\u001e \u001d\u001a\u001d\t!\u001d\"\u001d\u001a\u0019##$\t\u001e%&&'\u001a\u001b\u001c(\u001d\t')\t\u001b*\u001d\t+,-.\u001e\t/0\f\u000b1\t2\f\u00162\u0016/\u000b\n\t\u000b34\t4\f\u000b\u00170\t\u001753\u000b\n\t2\f\u00162\u0016/\u000b\n\u0007\t\n\u0001\u000b\f05\u0014/\u0014627\u000b/58\u00144\t07\u0014\t562\u0016\f0\u000b39\u0014\t\u0016\u0017\t4\u0014:\u0014\n\u0016253\u0013\t\u000b44505\u00163\u000b\n\t4\u00140\u000b5\n\t\u00163\t/2\u001495\u001759\t\u0014;\u000b62\n\u0014/\t\n\u000b342\f\u00169\u0014//\u0014/\t0\u0016\t9\n\u000b\f5\u0017<\t07\u0014\t0\u0016259/\t2\f\u00162\u0016/\u00144\t53\t07\u0014\t4\f\u000b\u00170\t\u001753\u000b\n\t2\f\u00162\u0016/\u000b\n\u0007\t\u00007\u0014\t\u0003\n\u000e\t530\u001434/\t\n0\u00169\u00163:\u00143\u0014\t1\u0016\f=53\u0013\t\u0013\f\u0016>2/\t\u000b34\t4\u0014:\u0014\n\u00162\t\u000b44505\u00163\u000b\n\t\u0013>54\u000b39\u0014\t53\t07\u0014\t?>/53\u0014//\t2\f\u000b9059\u0014\t\n6\u000b3>\u000b\n\u0016:\u0014\f\t07\u0014\t9\u0016653\u0013\t6\u0016307/\t0\u0016\t9\n\u000b\f5\u0017<\t05653\u0013\t\u000b34\t562\n\u00146\u001430\u000b05\u00163\t4\u00140\u000b5\n/\u0007\t\u00033\t\u000b44505\u00163@\t\n07\u0014\u0003\n\u000e5/\t9\u0016\u0016\f453\u000b053\u0013\t9\n\u0016/\u0014\n<\t1507\t07\u0014\t2\u000b\f05952\u000b053\u0013\t0\f\u000b3/65//5\u00163\t\u001613\u0014\f/\t\u000b/\t07\u0014<\t\n4\u0014:\u0014\n\u0016207\u00145\f\t0\u000b\f5\u0017\u0017\t\u00175\n53\u0013/\t\u000b34\t\u0014;2\u001490/\t0\u0016\t/\u0014\u0014\t\u000b44505\u00163\u000b\n\t4\u00140\u000b5\n\t\u00163\t7\u00161\t07\u00145\f\t2\f\u00169\u0014//\u0014/\t15\n\n\t\n\u0019#\u001c!\" \u001c\u001b*\tABCD.\u001e\tE\u001c\u001a\u001dF\u001b\u001c'\"\t\u0019\"E\t\u001b*\u001d\t+,-.\u001e\t&\u001a'&'\u001e\u0019#G\tABCD.\u001e\t'\u001aE\u001d\u001a\t \u0019\u001e\tF#\u001d\u0019\u001a\t\u001b*\u0019\u001b\t\n9\u001662\n5\u000b39\u0014\t/7\u0016>\n4\t3\u00160\t45/\f>20\t\u0014;5/053\u0013\t9\u001666\u0014\f95\u000b\n\t\u000b\f\f\u000b3\u0013\u00146\u001430/\u0007\t\n\u00007\u0014\u0003\n\u000e\f\u00149\u00145:\u00144\t9\u001666\u001430/\t\u0017\f\u00166\t/\u0014:\u0014\f\u000b\n\t2\u000b\f05\u0014/@\t539\n>453\u0013\t\n\u0016>07\u0014\f3\t\u0012\u000b\n5\u0017\u0016\f35\u000b\tH45/\u00163\t\n\u000b34\u0012\u000b\nI4:\u00169\u000b0\u0014/@\t/>\u0013\u0013\u0014/053\u0013\t07\u000b0\t07\u0014\t\u0003\n\u000e\t0\u000b=\u0014\t\u000b3\t\u0014;2\u000b34\u00144\t\f\u0016\n\u0014\t\u00163\t/\u0014:\u0014\f\u000b\n\t5//>\u0014/\t\n\f\u0014\n\u000b0\u001440\u0016\t\n\u0016\u000b4\t530\u0014\f9\u001633\u0014905\u00163\t/0>45\u0014/\t\u000b34\t2\f\u0014:\u0014305\u00163\t\u0016\u0017\t9\u0016/0J/75\u0017053\u0013\u0007\t\t\u000b3\u000b\u0013\u00146\u001430\t\n?\u0014\n5\u0014:\u0014/07\u0014\t\u0003\n\u000e\t7\u000b/\t/0\f>9=\t07\u0014\t\f5\u001370\t?\u000b\n\u000b39\u0014\t53\t0\u0014\f6/\t\u0016\u0017\t07\u0014\t45:5/5\u00163\t\u0016\u0017\t\f\u0014/2\u00163/5?5\n505\u0014/\t\n150707\u00142\u000b\f05952\u000b053\u0013\t0\f\u000b3/65//5\u00163\t\u001613\u0014\f/\u0007\t\n\u0001\u000b95\u001759K\u000b/\t\u0002\tH\n\u001490\f59\t3\u00160\u00144\t9\u001639\u0014\f3/\t1507\t07\u0014\t/9\u00162\u0014\t\u0016\u0017\t07\u0014\t\u0003\n\u000e\t4\f\u000b\u00170\t\u001753\u000b\n\t2\f\u00162\u0016/\u000b\n\t\n?\u000b/\u00144\u00163\t50/\t\u001c\"\u001b\u001d\u001a&\u001a\u001d\u001b\u0019\u001b\u001c'\"\t')\t\u001b*\u001d\t+,-.\u001e\tE\u001d)\u001c\"\u001c\u001b\u001c'\"\t')\t#\u0019\u001a!\u001d\t#'\u0019E\u001e\u0007\t\u00007\u0014\t\u0003\n\u000e\t5/\t9\u001666500\u00144\t0\u0016\t\n\f\u0014/2\u00149053\u0013\tABCD.\u001e\tL%\u001a\u001c\u001eE\u001cF\u001b\u001c'\"\u0019#\tF'\"\u001e\u001cE\u001d\u001a\u0019\u001b\u001c'\"\u001eM\t\u000b34\t5/\t1\u0016\f=53\u0013\t1507\t\u0001K\u0002H@\t07\u0014\t\u0012\u0001\u000f\u0012@\t\n\u000b34\u001607\u0014\f\t/0\u000b=\u00147\u0016\n4\u0014\f/\t\u00163\t9\u00163/\u00143/>/\t0\u000b\f5\u0017\u0017\t\n\u000b3\u0013>\u000b\u0013\u0014\t07\u000b0\t\f\u0014/2\u001490/\tN>\f5/45905\u00163\u000b\n\t\n53\u0014/\u0007\t\n\u0018OPB.\u001eF'\"F\u001d\u001a\"\u001e\t \u001c\u001b*\t\u001b*\u001d\tE\u001d)\u001c\"\u001c\u001b\u001c'\"\tF\u0019\u001a\u001a\u001c\u001dE\t\u001b*\u001a'%!*\t\u001c\u001b\u001e\tF'QQ\u001d\"\u001b\u001e\t'\"\t\u0019##\t'\u001b*\u001d\u001a\t\u001d#\u001dQ\u001d\"\u001b\u001e\t\n')\u001b*\u001d+,-.\u001e\t&\u001a'&'\u001e\u0019#M\t \u001c\u001b*\t\u001e%&&'\u001a\u001b\t)'\u001a\t(\u0019\u001a\u001c'%\u001e\t\u001d#\u001dQ\u001d\"\u001b\u001e\t')\t\u001b*\u001d\t&\u001a'&'\u001e\u0019#\tF'\"E\u001c\u001b\u001c'\"\u001dE\t\n%&'\"\u0018OPB.\u001e\tE\u001d)\u001d\"\u001e\u001d\t')\t\u001b*\u001d\u001c\u001a\t&'\u001e\u001c\u001b\u001c'\"\t'\"\t\u001b*\u001d\tE\u001d)\u001c\"\u001c\u001b\u001c'\"G\t\n\u00033\u000b44505\u00163@\t/\u0014:\u0014\f\u000b\n\t/0\u000b=\u00147\u0016\n4\u0014\f/\t/\u0016>\u001370\t9\u001666506\u001430/\t\u0017\u0016\f\t\u000b\t3\u00141\t/0\u000b=\u00147\u0016\n4\u0014\f\t53505\u000b05:\u0014\t0\u0016\t\n9\u00163/54\u0014\f2\u0014\f6\u000b3\u001430\t\u0017\n\u0014;5?\n\u0014\t530\u0014\f9\u001633\u0014905\u00163\t/\u0014\f:59\u0014\t\u0017\u0016\f\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b4/\t/\u0014\u0014=53\u0013\t0\u0016\t\u00162\u0014\f\u000b0\u0014\t\n\u0017\n\u0014;5?\n<53\t\u0016\f4\u0014\f\t0\u0016\t\u000b:\u001654\t3\u001401\u0016\f=\t>2\u0013\f\u000b4\u0014/@\t\u000b/\t1\u0014\n\n\t\u000b/\t530\u0014\f9\u001633\u0014905\u00163\t\u0016\u0017\t\u0014\n\u001490\f59\u000b\n\n<\t\n2\f\u0016;56\u000b0\u0014\t\n\u0016\u000b4/\t\u000b34\t\u0013\u00143\u0014\f\u000b05\u00163\u0007\t\u00007\u0014\t\u0003\n\u000e\t7\u000b/\t539\n>4\u00144\t\u000b\t/0\u000b=\u00147\u0016\n4\u0014\f\t53505\u000b05:\u0014\t0\u0016\t\n\u000b44\f\u0014//07\u0014/\u0014\t50\u00146/\t\u00163\t50/\t4\f\u000b\u00170\t\u00033\u0017\f\u000b/0\f>90>\f\u0014\t\u0001\u0016\n59<\tR\u0016\u000b46\u000b2\t\u000b34\t\u0014;2\u001490/\t0\u0016\t?\u0014\u001353\t\n2\u0016\n59<4\u0014:\u0014\n\u001626\u001430\t53\t\u0014\u000b\f\n<\tSTSU\u0007\t\nWXYWZ[\\]XY\t\n\t\u000b3\u000b\u0013\u00146\u001430\t\f\u00149\u001666\u001434/\t\u000b22\f\u0016:\u000b\n\t\u0016\u0017\t07\u0014\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b4\t4\f\u000b\u00170\t\u001753\u000b\n\t2\f\u00162\u0016/\u000b\n\t\u000b34\t\n\u0017\u0016\f079\u0016653\u0013\tST^\t\u00175\n53\u0013\t1507\t_HR\u0012\u0007\t\u000075/\t2\f\u00162\u0016/\u000b\n\t15\n\n\t\u00143/>\f\u0014\t9\u00163053>\u00144\t2\f\u0016\u000b905:\u0014\t\n2\n\u000b3353\u0013\u000b34\t/0>4<\t\u0016\u0017\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b4/@\t2\f\u00160\u001490\t9>/0\u00166\u0014\f/\t\u0017\f\u00166\t53\u000b22\f\u00162\f5\u000b0\u0014\t9\u0016/0\t/75\u0017053\u0013@\t\n\u00143\u000b?\n\u0014\u0017\u000b/0\u0014\f\t530\u0014\f9\u001633\u0014905\u00163\t\u0016\u0017\t\n\u000b\f\u0013\u0014\t\n\u0016\u000b4/@\t\u000b34\t\u00143/>\f\u0014\t9\u00163053>\u00144\t\f\u0014\n5\u000b?\n\u0014\t\u00162\u0014\f\u000b05\u00163/\t\n\u000b/?\u001607\n\u0016\u000b4/\t\u000b34\t\f\u0014/\u0016>\f9\u0014/\t?\u00149\u00166\u0014\t6\u0016\f\u0014\t4<3\u000b659\u0007"}],"sections":[{"p":1,"at":0,"title":"Attachment E – Board Memorandum","method":"printed heading","endPage":7,"endAt":2607,"startToken":0,"endToken":1273}]}