{"document":{"slug":"rec-20261118-5238","title":"Motion for Leave to Answer and Answer of Geronimo Power, LLC to the answer of Midcontinent Independent System Operator, Inc. filed on 11/09/2026","issued":"2026-11-18","accession":"20261118-5238","docket":"ER27-25-000","group":"MISO Large Load Addition Resource Study (LARS)","filer":"GERONIMO POWER, LLC","kind":"answer","file":"sources/filings/text/20261118-5238_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261118-5238","tier":"record","sha256":"0b429cdcee2bd78d622188c40ba8ef017995e1bc2e38e139b45e734803918105","pages":11,"tokens":3345,"emptyPages":[],"textThemes":["colo","study","proximate"]},"pages":[{"page":1,"startToken":0,"endToken":360,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nMidcontinent Independent System  \nOperator, Inc. \n) \n) \n) \n) \n \nDocket No. ER27-25-000 \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nGERONIMO POWER, LLC \n \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC” \nor “Commission”) Rules of Practice and Procedure,1 Geronimo Power, LLC (“Geronimo Power”) \nhereby moves for leave to answer2 and files this answer to the answer3 of the Midcontinent \nIndependent System Operator, Inc. (“MISO”) regarding its Large Load Addition Resource Study \nProcess (“LARS”) proposal.4 \nI. \nANSWER \nGeronimo Power agrees with MISO’s assessment that the significant load growth that \nMISO is experiencing requires MISO to adopt new processes to integrate new large loads and \nserve their demand.5  Geronimo Power’s comments in this proceeding commended MISO for its \n \n1 18 C.F.R. §§ 385.212 and 385.213. \n2 Geronimo Power acknowledges that the Commission’s Rules of Practice and Procedure do not typically \nallow answers to answers.  However, the Commission has accepted answers in the past when they have (i) assisted \nthe Commission in understanding the issues presented, (ii) provided additional information for the Commission’s \ndecision-making process, and (iii) helped ensure a complete and accurate record.  See, e.g., PJM Interconnection, \nL.L.C., 181 FERC ¶ 61,162, at P 29 (2022); Canal Generating LLC, 181 FERC ¶ 61,157, at P 14 (2022); Equitrans, \nL.P., 134 FERC ¶ 61,250, at P 6 (2011); Cal. Indep. Sys. Operator Corp., 132 FERC ¶ 61,023, at P 16 (2010).  In this \nproceeding, Geronimo Power’s answer will help the Commission understand the issues presented by MISO’s filing \nand provide further information related to the issues in this proceeding to inform the Commission’s decision-making \nprocess.  Geronimo Power therefore respectfully requests leave to file this answer and asks the Commission to consider \nthis answer in its deliberations in this proceeding. \n3 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Motion for Leave to Answer and \nAnswer of the Midcontinent Independent System Operator, Inc. (Nov. 9, 2026) (“MISO Answer”).  \n4 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Large Load Addition Resource Study \nProcess (Oct. 2, 2026) (“LARS Filing”).  \n5 MISO Answer at 3."},{"page":2,"startToken":360,"endToken":645,"text":"2 \n \nefforts to address this challenge, but raised critical questions regarding whether MISO’s proposed \nLARS process would in fact achieve MISO’s goals while remaining consistent with open access \nprinciples.6  MISO’s Answer fails to meaningfully respond to the concerns raised by Geronimo \nPower.  Accordingly, Geronimo Power urges the Commission to reject LARS without prejudice \nto MISO submitting a revised proposal that addresses the significant issues identified by Geronimo \nPower and other parties in this proceeding. \nA. \nMISO Has Not Addressed The Arbitrary And Unduly Discriminatory \nLimitations LARS Places On Eligible Agreements And Co-Location \nArrangements \n \nGeronimo Power demonstrated that the current design of LARS appears to limit the use of \nthis process by large loads and generation resources that are pursuing certain supply arrangements \nthat support resource adequacy and protect ratepayers.  For instance, Geronimo Power noted that \nMISO’s proposed tariff language appears to preclude interconnection customers that have entered \ninto a virtual power purchase agreement (“PPA”) from submitting an application into the LARS \nprocess.7  Geronimo Power’s comments also questioned whether co-location arrangements would \nbe eligible for LARS given MISO’s statements suggesting that co-location arrangements could \nonly be pursued through MISO’s Zero Injection Generator Interconnection Agreement \nframework.8  MISO’s Answer provides no response or clarification to these issues.    \nThe only response offered in MISO’s Answer is a generic assertion that the agreement \nrequirement is “flexible enough for projects with commercial certainty to participate” and that the \n“agreement requirement should not be made more flexible to allow in projects that do not meet the \n \n6 Midcontinent Indep. Sys. Operator, Inc., Docket No. ER27-25-000, Motion to Intervene and Comments of \nGeronimo Power, LLC at 2-5 (Oct. 23, 2026) (“Geronimo Comments”). \n7 Id. at 14-16. \n8 Id. at 16-17."},{"page":3,"startToken":645,"endToken":1100,"text":"3 \n \nhigh hurdle that LARS is designed to maintain.”9  But Geronimo Power is not arguing for MISO \nto relax its standards.  A long-term virtual PPA provides the same level of commercial certainty \nas a long-term physical PPA and allowing this arrangement to qualify for LARS would in no way \nlower the bar MISO has set.  MISO’s restrictions on virtual PPAs and other supply arrangements \narbitrarily prevent customers that are pursuing supply arrangements that are consistent with the \nobjectives underlying LARS and the Show Cause Order from accessing the LARS process.10  \nVirtual PPAs increasingly are being used by large loads to support the construction of the \nnew generation needed to meet their demand.11  Virtual PPAs accomplish exactly what MISO says \nLARS is intended to encourage: they de-risk new generation, support the entry of the capacity \nneeded to offset the resource adequacy requirements of new large loads, and place the cost of \nresources on the large loads they will serve rather than on retail customers.12  Indeed, MISO’s own \nexplanation of LARS confirms that allowing physical PPAs to qualify for LARS while excluding \nvirtual PPAs makes little sense.  Specifically, MISO concedes that LARS does not require the \n \n9 MISO Answer at 25. \n10 See Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 113 (2026) (“Show Cause Order”). \n11 See, e.g., Zachary Skidmore, Google Signs vPPA with Cypress Creek for 2.45 GW Solar Project in \nArkansas – Report, Data Center Dynamics (July 14, 2026), https://www.datacenterdynamics.com/en/news/google-\nsigns-vppa-with-cypress-creek-for-245gw-solar-project-in-arkansas-report (reporting that Google signed a long-term \nvirtual PPA for the full output of the Steel River Energy Center, a 2.45 GW solar plus storage facility in Mississippi \nCounty, Arkansas and that the revenue commitment allowed the developer “to commence construction of the \nproject”); EDP Global, EDP Renewables North America Delivers Three Additional Renewable Energy Projects for \nMicrosoft (Feb. 10, 2025), https://edp.com/en/north-america/na/media/edp-renewables-north-america-delivers-three-\nadditional-renewable-energy (noting that Microsoft “agreed to purchase 389 MW of electricity and renewable energy \ncredits (RECs) from the projects [in Illinois and Texas] through long-term virtual power purchase agreements \n(VPPAs)”); Sustainability Roundtable, Inc., Akamai Technologies, Teradyne, and Wayfair Partner to Purchase Solar \nEnergy in Champaign County, Ill. Through the Net Zero Consortium for Buyers, GlobeNewswire (Sept. 26, 2024), \nhttps://www.globenewswire.com/news-release/2024/09/26/2953870/0/en/Akamai-Technologies-Teradyne-and-\nWayfair-Partner-to-Purchase-Solar-Energy-in-Champaign-County-Ill-Through-the-Net-Zero-Consortium-for-\nBuyers.html (describing an “aggregated virtual power purchase agreement” for the 135 MWac Prairie Solar project in \ndevelopment in the MISO region of Illinois).  See also Brian Martucci, Meta-Constellation virtual PPA could be first \nof \nmany \ndeals \nfor \nexisting \nreactor \noutput: \nexperts, \nUtilityDive \n(June \n12, \n2025), \nhttps://www.utilitydive.com/news/meta-constellation-ppa-could-be-first-of-many-deals-for-existing-\nreactors/750567/. \n12 Geronimo Comments at 15-16."},{"page":4,"startToken":1100,"endToken":1441,"text":"4 \n \noutput of the generating facility to match the demand of load because that “is not the mechanism \nLARS uses to create value and potential savings.”13  If the physical delivery of energy to the load \nis irrelevant to the goal LARS is intended to achieve, there is no basis for excluding resources that \nare financially, rather than physically, committed to serving that load.  And while load-serving \nentities (“LSE”) and Alternative Retail Electric Suppliers have the option of obtaining LARS \neligibility through “other types of agreements” that would allow for a wider range of commercial \narrangements, this option is not available to independent power producers (“IPP”) and large \nloads14—a distinction that is unduly discriminatory and for which MISO has failed to provide any \njustification. \n  MISO has similarly failed to justify excluding co-located load and generation from the \nLARS process.  Co-located load and generation supported by a long-term PPA or similar \narrangement are similarly situated to electrically proximate pairs in every respect relevant to \nLARS: both pairings are based on a binding agreement between the two entities, are located in the \nsame local resource zone, are studied together for their combined system impacts, and are intended \nto bring new generation online to serve a specific load.15  Indeed, co-location arrangements are \nbetter situated to achieve the goals of LARS because they are less likely to trigger transmission \nupgrades relative to generation that is merely “electrically proximate” to the load.  And the \nCommission’s Show Cause Order also made no distinction between these two arrangements.16  Yet \nMISO has refused to clarify that co-located load and generation will be eligible for LARS. \n \n13 MISO Answer at 10.  See also id. at 24 (“MISO is not requiring a generating facility’s output to be matched \nto the demand of the electrically proximate large load.”). \n14 LARS Filing, Proposed Tariff, Att. X § 3.12.2(i)(c); LARS Filing, Tab C, Prepared Direct Testimony of \nChristina Drake at 31-32. \n15 See Geronimo Comments at 17-18 (citing Show Cause Order at P 113).  \n16 Id. at 16-18."},{"page":5,"startToken":1441,"endToken":1749,"text":"5 \n \nMISO does not dispute Geronimo Power’s arguments that there is no reason to exclude co-\nlocation arrangements from LARS.  In fact, MISO concedes that “adjacent large loads and \nGenerating Facilities may produce the most significant Network Upgrade optimization” and touts \nLARS as an “electrically proximate plus” construct that encourages generation and load to site “as \nclose together as is practical.”17  Despite these concessions, MISO has offered no clarification that \nco-location arrangements are eligible for LARS.  MISO should not be permitted to design LARS \naround the electrical proximity of load and generation and then exclude the very pairings that have \nthe closest electrical proximity and that it acknowledges will produce the greatest benefits.  \nB. \nMISO’s Answer Fails To Meaningfully Address The Unduly Discriminatory \nComponents Of LARS  \n \nUnder the LARS process, a generation resource may enter into an agreement to serve a \nlarge load and otherwise meet all the criteria to participate in LARS but will nevertheless be \nineligible unless a transmission customer—which MISO concedes will often be an LSE—agrees \nto submit a LARS application on its behalf.18  Moreover, this same generation resource and large \nload pairing will be ineligible for the LARS process unless the transmission owner of the system \nthey are interconnecting to agrees to a proposed point of interconnection.19  These components of \nLARS effectively give incumbent utilities, in the form of LSEs and transmission owners, the \nability to prevent otherwise viable generation and load pairings from accessing LARS. \nAlthough MISO says that it disagrees with commenters’ characterization of the LARS \nprocess as placing LSEs in a gatekeeper role,20 it does not offer any arguments or evidence to rebut \ncommenters’ characterization.  MISO instead defends the gatekeeping role LSEs and transmission \n \n17 MISO Answer at 11-12. \n18 LARS Filing, Transmittal Letter at 6.  \n19 Id. at 8. \n20 MISO Answer at 20."},{"page":6,"startToken":1749,"endToken":2065,"text":"6 \n \nowners will be permitted to play in the LARS process on the grounds that, like its Expedited Project \nReview process, “LARS is a load-driven process, and an Interconnection Customer cannot require \na Transmission Customer to scope their Transmission Service request around a generator they have \nnot chosen to pair with.”21  MISO’s defense is flawed for numerous reasons. \nTo begin with, MISO’s argument on this point is circular.  To the extent that LARS is a \nload-driven process, that is only because MISO designed it as such.  It does not, however, absolve \nMISO of its obligation to demonstrate that the process it has designed is consistent with the Federal \nPower Act’s (“FPA”) prohibition on undue discrimination.  Indeed, if MISO’s rationale were to \nhold, public utilities would be permitted to adopt any unduly discriminatory interconnection \npolicies so long as the design of the policies was intended to accomplish the utilities’ stated goals.   \nMISO similarly dismisses the fact that Southwest Power Pool, Inc.’s (“SPP”) High Impact \nLarge Load Generation Assessment (“HILLGA”) process provides generation resources with a \nnon-discriminatory pathway to interconnect and serve electrically proximate large loads on the \ngrounds that it is a “generator-driven process.”22  But MISO’s claim that LARS is a load-driven \nprocess ignores that LARS is not simply a load study; it is also a generator interconnection process \nthat results in a resource obtaining a Large Load Generator Interconnection Agreement (“LLGIA”) \nand Network Resource Interconnection Service.23  Indeed, the key components of LARS are \nfocused on the interconnection of a generation resource and the interconnection customer’s \nresulting interconnection rights.  MISO’s own filing, for instance, defines a LARS Application as \n“a form of Interconnection Request.”24  And under MISO’s proposal, the interconnection \n \n21 Id.  \n22 Id. at 21. \n23 LARS Filing, Tab C, Prepared Direct Testimony of Christina Drake at 12-13; id., Transmittal Letter at 6. \n24 Id., Transmittal Letter at 7, n.29."},{"page":7,"startToken":2065,"endToken":2462,"text":"7 \n \ncustomer—not the transmission customer or transmission owner—completes the generation \nportion of the application, satisfies the Attachment X requirements, posts the required security, \nexecutes the LLGIA, and bears responsibility for network upgrades.25  In contrast, MISO’s filing \nis largely devoid of explanation as to how a transmission customer is to obtain transmission service \nfor a LARS Associated Load.    \nEven if the LARS process were accurately characterized as a load-driven process, MISO \nfails to justify requiring a commercially viable large load and its paired generation resource to \nobtain the support and consent of LSEs and transmission owners to access the process.  MISO \nasserts that so long as an interconnection customer and load can obtain the agreement of a \ntransmission customer to initiate the LARS application, there is no barrier to them entering the \nLARS process and without such agreement “the pairing of load and generation in a coordinated \nstudy process would be premature and speculative.”26  MISO does not explain, however, why the \nability of a generation resource to obtain the agreement of an incumbent utility to submit an \napplication is a reasonable benchmark for commercial viability.  A generation developer only \nwould be able to enter LARS if it has an executed long-term agreement with the entity that owns \nor controls the LARS Associated Load or the LARS Associated Transmission Customer already, \n100% site control, and deposits in hand.  These measures already are sufficient to deter speculative \nrequests and ensure the commercial viability of a proposed resource.  Requiring a generation \ndeveloper and large load to obtain the agreement of the incumbent utility to submit the LARS \n \n25 MISO has also failed to address discrepancies in its tariff that create ambiguity regarding the entity that is \neligible to submit a LARS Application.  As Geronimo Power explained in its comments, although MISO states that a \nLARS Application may only be initiated by the LARS Associated Transmission Customer, proposed Section 3.12.1 \nof Attachment X states that “[p]rior to the applicable Transmission Owner submitting a LARS Application, the \npotential LARS Interconnection Customer and the Transmission Owner shall meet and agree on a definitive Point of \nInterconnection for the LARS Generating Facility.”  Geronimo Comments at 7, n.16 (emphasis added).  MISO’s \nAnswer fails to clarify that the LARS Associated Transmission Customer is responsible for submitting the LARS \napplication rather than the transmission owner.  \n26 MISO Answer at 20."},{"page":8,"startToken":2462,"endToken":2752,"text":"8 \n \napplication merely creates opportunities for undue discrimination that incumbent utilities can use \nto create barriers to entry without any corresponding benefit.  \nMISO’s defense of the requirement that the transmission owner pre-approve a project’s \npoint of interconnection before a LARS application may be submitted is equally unsupported.  \nMISO states that LARS “has stricter site control requirements such that the Transmission Owner \nmust agree on the POI at the time of application submission” to ensure that only shovel-ready \nprojects participate.27  But site control and a transmission owner veto are different things.  An \ninterconnection customer can demonstrate site control and identify a point of interconnection \nwithout having to await the interconnecting transmission owner’s approval.  Indeed, in the \ngenerator interconnection context, no transmission owner consent to a point of interconnection is \nrequired, yet evidence of site control is still provided.28  And requiring transmission owner \napproval also does not provide meaningful protection against the risk that technical issues could \narise that could lead the transmission owner or MISO to request a change in the point of \ninterconnection during the study process.29 \nMISO also does not demonstrate that it is just and reasonable to require interconnection \ncustomers to bear the risk of a transmission owner-initiated change to the point of interconnection \nthat occurs during the study process.  As Geronimo Power pointed out in its comments, MISO’s \nproposal not only requires the transmission owner to agree to the point of interconnection in order \nfor a customer to enter the LARS process, but proposes language that would deem a customer’s \nrequest withdrawn if the transmission owner later changes its mind and proposes to modify the \n \n27 Id. at 21. \n28 See MISO Tariff, Att. X § 7.2.1(ii).  \n29 Geronimo Comments at 12-13."},{"page":9,"startToken":2752,"endToken":3162,"text":"9 \n \npoint of interconnection.30  The result is that the transmission owner holds not only an up-front \nveto over a project’s entry into LARS but also a continuing ability to remove the project from the \nprocess after the fact, and MISO offers no justification for placing the consequences of that \nunilateral decision on the interconnection customer rather than on the party that made it. \nUltimately, MISO’s defense of the gatekeeping role that LSEs and transmission owners \nwill be permitted to play for LARS appears to hinge on a fundamental misunderstanding of the \nFPA’s prohibition on undue discrimination and the Commission’s open access principles.  MISO \nappears to believe that so long as its proposal does not expressly prohibit IPPs from accessing \nLARS, it is not unduly discriminatory.31  But that is not how courts or the Commission evaluate \nwhether a proposal is unduly discriminatory and consistent with open access.  The Commission \nhas repeatedly rejected proposals that provide the mere opportunity for undue discrimination by \nincumbent utilities.32  Moreover, whether a proposal is facially neutral—as MISO claims LARS \nis—has no bearing on whether its effect is unduly discriminatory and unlawful under the FPA.33   \n \n30 Id. at 13, n.31 (citing LARS Filing, Proposed Tariff, Att. X § 3.12.9). \n31 MISO Answer at 20 (“LARS does not prevent Independent Power Producers (‘IPPs’) from competing to \nsupply energy to large loads under applicable state and or [sic] utility-led RFP processes.”).  See also id. at 22 (“If an \nIPP has a generation project that is better, more cost effective, or otherwise preferable to alternatives, nothing in the \nLARS process stops the IPP from bringing this project forward for consideration and entering into a pairing \narrangement with a LARS Transmission Customer.”). \n32 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ \n61,103, at PP 11, 696 (2003), order on reh’g, Order No. 2003‐A, 106 FERC ¶ 61,220 (2004), order on reh’g, Order \nNo. 2003‐B, 109 FERC ¶ 61,287 (2005), order on reh’g, Order No. 2003‐C, 111 FERC ¶ 61,401 (2005), aff’d sub \nnom., National Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007) (“The Commission would \nfind any policy that creates opportunities for such discriminatory behavior to be unacceptable.”). \n33 See Xcel Energy Servs. v. FERC, 41 F.4th 548, 559-60 (D.C. Cir. 2022) (quoting Pub. Serv. Co. of Colo., \n172 FERC ¶ 61,297, at P 13 (2020))."},{"page":10,"startToken":3162,"endToken":3281,"text":"10 \n \nII. \nCONCLUSION \nGeronimo Power respectfully requests that the Commission issue an order consistent with \nits filings in this proceeding and reject LARS without prejudice to MISO submitting a revised \nproposal that addresses the significant issues identified by Geronimo Power and other parties in \nthis proceeding.  \nRespectfully submitted, \n \n/s/ Stephen J. Hug \nMatthew Morais \nSenior Director, Policy \nKurt Rempe \nAssistant General Counsel \nGERONIMO POWER, LLC \n8400 Normandale Lake Blvd., Ste. 1200 \nBloomington, MN 55437 \nmmorais@geronimopower.com  \nkrempe@geronimopower.com  \n  \nStephen J. Hug \nBen N. Reiter \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \nTel: (202) 887-4084 \nshug@akingump.com \nbreiter@akingump.com   \nOn behalf of Geronimo Power \nDated: November 18, 2026"},{"page":11,"startToken":3281,"endToken":3345,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have caused the foregoing document to be served upon the individuals \ndesignated on the Commission’s official service list for this proceeding. \nDated at Washington, D.C., this 18th day of November 2026. \n \n \n/s/ Stephen J. Hug \n \nStephen J. Hug \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \n(202) 887-4084"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":624,"startToken":0,"endToken":87},{"p":1,"at":624,"title":"I. ANSWER","method":"printed heading","endPage":2,"endAt":528,"startToken":87,"endToken":435},{"p":2,"at":528,"title":"A. MISO Has Not Addressed The Arbitrary And Unduly Discriminatory","method":"printed heading","endPage":5,"endAt":772,"startToken":435,"endToken":1555},{"p":5,"at":772,"title":"B. MISO’s Answer Fails To Meaningfully Address The Unduly Discriminatory","method":"printed heading","endPage":10,"endAt":6,"startToken":1555,"endToken":3163},{"p":10,"at":6,"title":"II. CONCLUSION","method":"printed heading","endPage":11,"endAt":0,"startToken":3163,"endToken":3281},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":393,"startToken":3281,"endToken":3345}]}