{"document":{"slug":"rec-20261119-5176","title":"Deficiency Response - Modify the CHILL Policy to Accommodate Planned Outages","issued":"2026-11-19","accession":"20261119-5176","docket":"ER26-3591-001","group":"SPP conditional large-load service credits (CHILLS)","filer":"Southwest Power Pool, Inc.","kind":"tariff filing","file":"sources/filings/text/20261119-5176_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261119-5176","tier":"record","sha256":"84c133175b25609d8dbbb16d8084a589ca3b20f2d22ce5dc7e01cdd2f0097841","pages":9,"tokens":2948,"emptyPages":[],"textThemes":["flex"]},"pages":[{"page":1,"startToken":0,"endToken":265,"text":"November 19, 2026 \n \n \nThe Honorable Debbie-Anne A. Reese \nSecretary  \nFederal Energy Regulatory Commission \n888 First Street NE \nWashington, DC 20426 \n \n \nRE: \nSouthwest Power Pool, Inc., Docket No. ER26-3591-____ \nSubmission of Response to Request for Additional Information \n \nDear Secretary Reese: \n \n \nPursuant to the Federal Energy Regulatory Commission’s (“Commission”) letter \nissued on October 21, 2026,1 in this proceeding, Southwest Power Pool, Inc. (“SPP”) \nsubmits additional information2 concerning the filing it submitted on August 24, 2026, in \nDocket No. ER26-3591-000.3 \n \nI. \nBACKGROUND \n \nIn the August Filing, SPP submitted revisions to the SPP Open Access \nTransmission Tariff 4 to modify the Conditional High Impact Large Load (“CHILL”) \npolicy to accommodate planned Outages. \n \n \n \n1  \nSw. Power Pool, Inc., Deficiency Letter, Docket No. ER26-3591-000 (Oct. 21, \n2026) (“Deficiency Letter”). \n2  \nSPP is attaching one, unmodified tariff record to this filing as required by the \nCommission. Electronic Tariff Filings, 130 FERC ¶ 61,047, at PP 3-8 (2010) \n(stating an amendment filing must include at least one tariff record even though a \ntariff revision might not otherwise be required). \n3  \nSubmission of Tariff Revisions to Modify the Conditional High Impact Large Load \nPolicy to Accommodate Planned Outages of Southwest Power Pool, Inc., Docket \nNo. ER26-3591-00 (Aug. 24, 2026) (“August Filing”). \n4  \nSouthwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised \nVolume No. 1. References in this filing to \"Tariff\" refer to the version of SPP’s \nTariff currently in effect. \"Proposed Tariff\" refers to a version reflecting the \nrevisions proposed in the August Filing. All capitalized terms not otherwise defined \nin this filing shall have the definitions assigned by the Tariff."},{"page":2,"startToken":265,"endToken":659,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 2 \n \nSeveral parties filed motions to intervene.5 No parties filed comments or protests. \n \n \nIn the Deficiency Letter, the Commission directed SPP to provide additional \ninformation required to process the filing. The Commission required responses be \nsubmitted within thirty (30) days of the date of the request for additional information. In \nthis instant filing, SPP submits its responses to the specific questions raised in the \nDeficiency Letter.  \n \nII. \nRESPONSE TO DEFICIENCY LETTER \nQuestion 1:   \n \nSPP explains that, currently, under section 2.22.1(d) of Attachment AE of the \nTariff, a CHILL can be curtailed when the sum of the available capacity of its supporting \nResources is less than the CHILL.6  SPP proposes to revise its Tariff to provide that a \n“CHILL will not be curtailed solely due to supporting Resource insufficiency” when its \nsupporting resource takes a Scheduled Resource Outage that is scheduled at least 14 days \nin advance of the planned start time.7  Please explain whether there are limitations on how \nlong a CHILL can stay online while all or some of its supporting Resources are on a \nScheduled Resource Outage or otherwise unavailable to the SPP Integrated Marketplace. \nResponse: \n \nIf a CHILL participating under Section 2.22.1(d) of Attachment AE of Attachment \nAE (“Option 2 CHILL”) of the Tariff has all or some of its supporting Resources on a \nScheduled Resource Outage submitted at least 14 Calendar Days in advance, the Option 2 \nCHILL is limited in its ability to stay online by the duration of the Outage and the results \nof the system feasibility solve.8  \n \n \n5  \nMotions to Intervene were filed by: American Electric Power Service Corporation; \nEvergy Kansas Central, Inc., Evergy Missouri West, Inc., Evergy Metro, Inc.; Grid \nReform; Kansas Electric Power Cooperative, Inc.; Oklahoma Gas and Electric \nCompany; Solar Energy Industries Association; Sunflower Electric Power \nCooperative; and Western Farmers Electric Cooperative. \n6  \nAugust Filing at 6. \n7  \nProposed Tariff, Att. AE, § 2.22.2 (Resources Supporting a HILL or CHILL). \n8  \nThese limitations are specific to the proposed changes to the Resource sufficiency \ncheck. The Option 2 CHILL could also be curtailed due to transmission limitations, \na Local Reliability Issue, an unfavorable net impact to the Transmission System \nduring system CHILL Curtailments, and Emergency Conditions. See Tariff, \nAttachment AE, Section 2.22.1(d)."},{"page":3,"startToken":659,"endToken":1071,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 3 \nOutages for Resources supporting CHILL(s) must be reviewed and approved or \ndenied by the Transmission Provider.9 An Outage request must be accompanied by a reason \nfor the Outage in addition to the planned start and end times.10 To help evaluate Outage \nrequests, SPP uses the Generator Assessment Process (GAP), which projects the \navailability to schedule generating resource maintenance on an hourly basis.11 Consistent \nwith the treatment of other Resources, SPP did not propose a cap on the maximum length \nof a Scheduled Resource Outage for an Option 2 CHILL supporting Resource, but the \npotential length of a Scheduled Resource Outage would be limited operationally by the \navailable maintenance margin MW. If the nameplate capacity of the supporting Resource \nrequesting an Outage exceeds the projected available margin in any hour during the \nrequested period, the request would be denied. While the maintenance margin will be used \nin evaluating Outages for Option 2 CHILLs supporting Resources, SPP will not consider \ntheir availability when calculating the maintenance margin.12 Resources supporting \nCHILLS do not have a net impact on the system because all Resources supporting CHILLs \nmust only submit Resource Offers sufficient to cover the forecasted withdrawals by the \nCHILL.13 Consistent with reliability needs of the system, SPP may deny an Outage it \npreviously approved.14 Furthermore, the Market Monitoring Unit may request supporting \ndocumentation for the Outage.15 \n  \nSecond, when supporting Resources are not on Outage, to avoid curtailment for \nsupporting Resource insufficiency, Option 2 CHILLs must pass a check which compares \nthe Maximum Economic Operating Limits of its supporting Resources to the CHILL.16 In \ncontrast, CHILLs participating under Section 2.22.1(c) of Attachment AE (“Option 1 \nCHILLs”) of the Tariff do not have designated supporting Resources and instead undergo \n \n \n9  \nTariff, Attachment AE, Section 3.1.5. See also Southwest Power Pool, Inc. Open \nAccess Transmission Tariff Business Practices, Business Practice 10000 Reliability \nCoordinator Outage Coordination Methodology for the RTO Footprint, Section 1.1 \n(“Business Practice 10000”), available at: https://www.spp.org/spp-documents-\nfilings/?id=472252.  \n10  \nBusiness Practice 10000, Section 3.2.   \n  \n11  \nId., Section 3.6.  \n \n12  \nSee id, Section 3.6.  \n13  \nTairff, Attachment AE, Section 2.22.2(2)(b). \n14  \nTariff, Attachment AE, Section 3.1.5.1. \n15  \nTariff, Attachment AG, Sections 4.6.4 and 8.3.  \n16  \nTariff, Attachment AE, Section 2.22.1(d)(1)."},{"page":4,"startToken":1071,"endToken":1465,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 4 \na system feasibility check, where they may be curtailed pro rata if there is insufficient \ncapacity available to serve the CHILL.17 Under the proposed policy, if the supporting \nResources of an Option 2 CHILL are all on a Scheduled Resource Outage submitted at \nleast 14 Calendar Days in advance, the CHILL would functionally be treated as an Option \n1 CHILL by the market clearing engine and included in the system feasibility solve that is \nnot limited to supporting Resources. \n \nIf at least one of the supporting Resources is available (not on a Scheduled Resource \nOutage submitted at least 14 Calendar Days in advance), the Option 2 CHILL must pass \nthe following sufficiency check:18 \n \n𝑆𝑢𝑚(𝐸𝑐𝑜𝑚𝑎𝑥𝑒𝑠 𝑜𝑓 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑠𝑢𝑝𝑝𝑜𝑟𝑡𝑖𝑛𝑔 𝑅𝑒𝑠𝑜𝑢𝑟𝑐𝑒𝑠)    ≥ \n 𝐶𝐻𝐼𝐿𝐿 − 𝑠𝑢𝑚(𝐴𝑐𝑐𝑟𝑒𝑑𝑖𝑡𝑒𝑑 𝑀𝑊 𝑜𝑓 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑖𝑛𝑔 𝑅𝑒𝑠𝑜𝑢𝑟𝑐𝑒𝑠 𝑜𝑛 𝑃𝑙𝑎𝑛𝑛𝑒𝑑 𝑂𝑢𝑡𝑎𝑔𝑒)  \n \nIf the Option 2 CHILL fails this check, the CHILL will be curtailed.  \n \nBelow is an example of potential outcomes of the sufficiency check. Assume there \nis a 100 MW Option 2 CHILL supported by 100 MW of nameplate wind with 20 MW  \n(20%) of accredited value and 100 MW of nameplate gas with 80 MW of accredited value \n(80%). The examples below illustrate the check outcomes when the CHILL is forecasting \n100 MW of consumption while one Resource is on Outage and the other has varying \navailability. For example, in the first row the wind Resource is on Outage, meaning the gas \nResource must make at least 80 MW available to serve the CHILL to avoid curtailment of \nthe CHILL. In this example, the CHILL is curtailed because only 50 MW of the gas \nResource were available, which fails the requirement to be greater than or equal to the \nCHILL less the accredited MW of the supporting wind Resource (100-20=80).  \n \nCHILL \nWithdrawal \nResource on \nOutage  \nAccredited \nMW on \nOutage \nSufficiency \nThreshold  \nAvailable \nResource \nMW  \nOutcome \n100 MW \nWind  \n20 MW \n100-20 = 80 MW \n50 MW \nCHILL \ncurtailed \n100 MW \nWind \n20 MW \n100-20 = 80 MW \n80 MW \nCHILL \nPasses \n100 MW \nGas \n80 MW \n100-80 = 20 MW \n0 MW \nCHILL \ncurtailed \n100 MW \nGas \n80 MW \n100-80 = 20 MW \n30 MW \nCHILL \nPasses  \n \n \n \n17  \nTariff, Attachment AE, Section 2.22.1(c)(2) and Market Protocols, Section 4.1.11.  \n18  \nProposed Tariff, Attachment AE, Section 2.22.2(1)(c)."},{"page":5,"startToken":1465,"endToken":1820,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 5 \nQuestion 2:   \n \nSPP proposes to incentivize Resources supporting CHILLs to be available during \nEmergency Conditions by allowing them to receive compensation for deferring Scheduled \nResource Outages in certain circumstances.19 Specifically, the proposed revisions state that \n“Scheduled Resource Outages for supporting Resources for a [CHILL] . . . are solely \nQualified [for compensation] if, in addition to the criteria in this Section B, the Outage is \nrescheduled at the request of the Transmission Provider to make the Resource available in \nEmergency Conditions . . . and the Resource was made available. . . .”20  SPP contends that \nthis is the same compensation offered to other Resources on approved Scheduled Resource \nOutages.21  \n  \na. Please explain whether and, if so, how SPP will consider whether a Resource is \nsupporting a CHILL in its determination of which approved Scheduled \nResource \nOutage \nit \nwill \nrequest \nto \nbe \nrescheduled.   \n \nb Please describe the circumstances in which SPP will request that “the Resource \n[be made] available in Emergency Conditions.”  For example, please clarify \nwhether a Resource supporting a CHILL would only be eligible for \ncompensation if it rescheduled its approved Scheduled Resource Outage in \nEmergency Conditions. \n \n \nc. Please confirm whether the circumstances in which SPP may offer \ncompensation to a Resource supporting a CHILL are the same as for other \nResources.  If not, please describe and support that difference. \nResponse to 2.a:  \n \n \nOutside of Emergency Conditions, SPP would consider if a Resource is supporting \na CHILL. This matters because requesting that an Option 2 CHILL supporting Resource \nreschedule an Outage has little benefit as the Tariff limits the Resource output to the load \nforecast value of the corresponding CHILL.22 A Resource supporting a CHILL must only \nsubmit a Resource Offer sufficient to cover the forecasted withdrawals of the CHILL.23 An \nOption 2 CHILL may be curtailed if the supporting Resource Offer is less than the \n \n \n19  \nAugust Filing at 8. \n20  \nProposed Tariff, Att. U, § B (Compensation for Generator Owners). \n21  \nAugust Filing at 8.  \n22  \nTariff, Attachment AE, Section 2.22.2(2)(b). \n23  \nTariff, Attachment AE, Section 2.22.2(1)(a)."},{"page":6,"startToken":1820,"endToken":2227,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 6 \nforecasted CHILL withdrawal.24 Furthermore, CHILL supporting Resources are not \nincluded in calculating maintenance margin in the Generator Assessment Process, as \ndescribed above, so requesting that CHILL supporting Resource reschedule an Outage \nwould not help accommodate the Outage of a network Resource.  \n \nDuring Emergency Conditions, SPP would not consider whether a Resource is \nsupporting an Option 2 CHILL in its determination of which Scheduled Resource Outage \nit will request to be rescheduled during Emergency Conditions. In Emergency Conditions, \nSPP may allow the Resource to exceed the forecasted CHILL withdrawal, so there is more \npotential benefit to the reliability for SPP to consider.  \n \nResponse to 2.b:  \n \n \nA supporting Resource for an Option 2 CHILL is only eligible for compensation if \nit rescheduled its approved Scheduled Resource Outage in Emergency Conditions. The \nsupporting Resource must make itself available by self-committing or setting its \ncommitment status to market or reliability and meet the other requirements for Qualified \nOutages in Attachment U, Section B of the Tariff. For example, a Qualified Outage must \nbe submitted at least 60 days prior to the start of the scheduled maintenance.25 This proposal \nonly provides compensation for rescheduled Outages during Emergency Conditions \nbecause, as explained above, CHILL supporting resources do not support the capacity for \nNetwork Resources to take Outages and provides little system reliability benefit outside of \nthose conditions.  \n \nResponse to 2.c:  \n \n \nAll Resources are subject to the criteria in Attachment U, Section B, including \nResources supporting a CHILL. SPP’s proposed Tariff changes specify that the \nrequirements for Resources supporting a CHILL are “in addition to the criteria in this \nSection B.”26 A Resource that is not supporting a CHILL provides two benefits to the \nsystem if it reschedules its Outage: (1) it increases the maintenance margin available for \nother Resources to retain their Scheduled Resource Outage and (2) it is likely to make \nadditional Energy available beyond what would have been available if it had not \nrescheduled its Outage. A Resource that is not supporting a CHILL is likely to make \nadditional Energy available because it is subject to must offer requirements and associated \n \n \n24  \nAttachment AE, Section 2.22.1(d) (“the CHILL must agree to be curtailable (1) \nwhen the sum of the available capacity for the supporting Resources is less than the \nCHILL. . .”). \n25  \nTariff, Attachment U, Section B. \n26   \nProposed Tariff, Attachment U, Section B."},{"page":7,"startToken":2227,"endToken":2653,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 7 \ncharges if the requirements are not satisfied.27 Therefore, the incentive exists for the \nGenerator Owner to offer the Resource to the market. By contrast, outside of Emergency \nConditions, a Resource supporting a CHILL provides neither benefit: it is not included in \nthe maintenance margin calculation and any Energy it produces is offset by the withdrawals \nfrom the CHILL.  \n \nAccordingly, the proposed revisions include two additional conditions for \ncompensation that apply only to Resources supporting a CHILL. A Resource supporting a \nCHILL is only eligible for compensation if it has (1) rescheduled its approved Scheduled \nResource Outage in Emergency Conditions and (2) made itself available. First, as described \nabove, there is little benefit to the system if a Resource supporting a CHILL reschedules \nits Outage because the Outage is not included in the maintenance margin calculation. \nHowever, a Resource supporting a CHILL does provide a benefit to the system when it \ninjects Energy beyond the needs of the CHILL, which may only occur during Emergency \nConditions.  \n \nAs described above, Resources supporting CHILLs must only submit Resource \nOffers sufficient to cover the forecasted withdrawals by the CHILL.28 This limitation exists \nbecause the supporting Resource interconnected through the High Impact Large Load \nGeneration Assessment (HILLGA) and is subject to a High Impact Large Load Generator \nInterconnection Agreement (HILLGIA).29 The HILLGIA provides that the Transmission \nProvider may take whatever actions necessary during Emergency Conditions to \n(i) preserve public health and safety, (ii) preserve the reliability of the Transmission \nSystem or Transmission Owner’s Interconnection Facilities, (iii) limit or prevent damage, \nand (iv) expedite restoration of service.30 The CHILL must also agree to be curtailable in \nthe event of Emergency Conditions.31 Due to the limitations of the HILLGIA, SPP may \nonly request that the Resources supporting CHILLS exceed the forecasted withdrawals by \nthe CHILL during Emergency Conditions. Additionally, Resources supporting Option 2 \nCHILLs may also have Load Limited Resource Interconnection Service, which limits their \noutput to the forecast value of the corresponding CHILL, except when directed by the \n \n \n27  \nTariff, Attachment AF, Section 3.9 \n28  \nTairff, Attachment AE, Section 2.22.2(2)(b). \n29  \nSee Submission of Tariff Revisions to Add the High Impact Large Load Processes \nand High Impact Large Load Generation Assessment of Southwest Power Pool, \nInc., Docket No. ER26-247-000 (October 24, 2025) (“HILL Filing”) for a more \nthorough discussion regarding the HILLGA and HILLGIA. \n30  \nTariff, Attachment BB, Appendix 2, Article 13.5. \n31  \nTariff, Attachment AE, Section 2.22.1(c)."},{"page":8,"startToken":2653,"endToken":2891,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 8 \nTransmission Provider to mitigate Emergency Conditions.32 Because a Resource \nsupporting an Option 2 CHILL with LLRIS is only eligible to produce more than the \nCHILL’s forecasted withdrawals during Emergency Conditions, the Transmission \nProvider may only request that the Resource inject Energy onto the Transmission System \nduring Emergency Conditions. Second, because a Resource supporting a CHILL is not \nsubject to must offer requirements that would normally be relied upon to incent a Market \nParticipant to make a Resource available to the market, SPP requires the Resource \nsupporting a CHILL to be made available to receive compensation. \n \nTherefore, compensation under Attachment U of the Tariff is limited to the \ncircumstances in which a Resource supporting a CHILL provides a benefit to the system.  \nProviding compensation under these parameters provides incentives for the Resource \nsupporting a CHILL to remain available during Emergency Conditions to support system \nreliability while maintaining equitable treatment between Resources supporting CHILLs \nand Resources that are not supporting CHILLs.  \n \nIII. \nCONCLUSION \n \n \nFor all of the reasons discussed in this instant filing, the Commission should accept \nthe Tariff revisions submitted in this proceeding as just and reasonable. \n \nRespectfully submitted, \n \n/s/ Emon Mahony \n \nEmon Mahony \nSenior Attorney \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR  72223-4936 \n(501) 482-2506 \nemahony@spp.org \n \nAttorney for Southwest Power Pool, Inc. \n \n \n \n32  \nTariff, Attachment AE, Section 2.22.2(2)(b)."},{"page":9,"startToken":2891,"endToken":2948,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have on this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \n \n \nDated this 19th day of November, 2026. \n \n \n \n \n \n \n \n/s/ Michelle Harris \n \n \n \n \n \n \n \nMichelle Harris \n \n \n \n \n \n \n \nSouthwest Power Pool, Inc.  \n \n \n \n \n \n \n \n201 Worthen Drive \n \n \n \n \n \n \n \n \nLittle Rock, AR 72223-4936  \n \n \n \n \n \n \n \n(501) 614-3200"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":591,"startToken":0,"endToken":79},{"p":1,"at":591,"title":"I. BACKGROUND","method":"printed heading","endPage":2,"endAt":517,"startToken":79,"endToken":341},{"p":2,"at":517,"title":"II. RESPONSE TO DEFICIENCY LETTER","method":"printed heading","endPage":8,"endAt":1186,"startToken":341,"endToken":2823},{"p":8,"at":1186,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":2823,"endToken":2891},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":465,"startToken":2891,"endToken":2948}]}