{"document":{"slug":"rec-20261119-5227","title":"Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs","issued":"2026-11-19","accession":"20261119-5227","docket":"ER27-577-000","group":"SPP large-load tariff revisions","filer":"Southwest Power Pool, Inc.","kind":"tariff filing","file":"sources/filings/text/20261119-5227_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261119-5227","tier":"record","sha256":"a9d06721aaa6c18506f16fdf94be2a484143016f8de7ad23629b192c06fdb244","pages":24,"tokens":9237,"emptyPages":[],"textThemes":["cost","study","credit","procedure"]},"pages":[{"page":1,"startToken":0,"endToken":340,"text":"November 19, 2026 \n \nThe Honorable Debbie-Anne A. Reese \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, D.C.  20426 \n \nRe: \nSouthwest Power Pool, Inc., Docket No. ER27-____-000 \nSubmission of Tariff Revisions to Establish Load Safe Harbor Limit for \nDelivery Point Costs; Related to Docket No. EL26-68-000 \n \nDear Secretary Reese:  \n \n \nPursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, \nand Section 35.13 of the Federal Energy Regulatory Commission’s (“Commission”) \nRegulations, 18 C.F.R. § 35.13, Southwest Power Pool, Inc. (\"SPP\"), as authorized by \nits independent Board of Directors, submits revisions to its Open Access Transmission \nTariff (“Tariff”)1 in response to the Commission’s June 18, 2026, order instituting a \nproceeding under FPA Section 206 in Docket No. EL26-68-000 (“Show Cause \nOrder”).2 The proposed revisions establish a new Load Safe Harbor Limit (“LSHL”) \nfor the costs of Network Upgrades identified through the transmission study processes \noutlined in Attachments AQ, AX, and BA of the Tariff.3 As directed by the Show Cause \nOrder, SPP states explicitly that this proposal is submitted under FPA Section 205, \nexplains which of the Commission’s directives this filing addresses and how it resolves \nthem, explains how the proposal avoids disrupting existing commercial arrangements, \nand identifies a reasonable effective date.4 \nThe revisions in this filing respond directly to the Commission’s preliminary \nfindings that the Tariff should contain mechanisms or provisions that require minimum \n \n1  \nSouthwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume \nNo. 1.  References in this filing to \"Tariff\" refer to the version of SPP’s Tariff currently \nin effect. \"Proposed Tariff\" refers to a version reflecting the revisions proposed in this \nfiling. All capitalized terms not otherwise defined in this filing shall have the \ndefinitions assigned by the Tariff. \n2  \nSw. Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (“Show Cause Order”). \n3  \nThe revisions proposed herein are referred to, for purposes of this transmittal letter, as \nthe “Load Safe Harbor Limit Revisions.” \n4  \nShow Cause Order at P 32."},{"page":2,"startToken":340,"endToken":736,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 2 \n \nfinancial contributions and financial security sufficient to mitigate the risk of cost \nshifting among transmission customers if a large load does not materialize as planned.5 \nSPP respectfully requests that the Commission find the proposed revisions just and \nreasonable and not unduly discriminatory or preferential, accepting them effective \nFebruary 17, 2027, and finding that they resolve the cost-shifting concerns identified \nin the Show Cause Order. \nI. \nSUMMARY OF FILING  \nThe Show Cause Order commended SPP’s “bold and proactive steps” to \nintegrate large loads. It recognized that SPP’s High Impact Large Load (“HILL”) \nprocess already provides an enhanced study framework for Eligible Customers taking \ntransmission service on behalf of large loads.6 Notwithstanding this, the Commission \npreliminarily found “that SPP’s Tariff appears to be unjust and unreasonable because \nit lacks adequate mechanisms to mitigate the risk of cost shifting among transmission \ncustomers, which may result in unjust and unreasonable rates for transmission \nservice.”7 The Commission expressed concern that there is no mechanism to help \nensure that Eligible Customers taking service on behalf of large loads bear the risk and \nare ultimately responsible for costs incurred to provide transmission service, including \nthe cost of Network Upgrades.8  \nTo address this concern, SPP proposes the LSHL for Network Upgrades needed \nto add or modify load delivery points studied under the Tariff. The LSHL mitigates the \nrisk of cost shifting associated with the connection of large loads by requiring the \nTransmission Customer to pay, and to secure with financial security, all delivery point \nNetwork Upgrade costs above a threshold—creating an obligation that correlates \ndirectly with the level of cost resulting from the delivery point request and does not \ndepend on whether, when, or at what level the load materializes. The LSHL preserves \na defined level of rate support for Network Upgrades approved by SPP (i.e., “Base Plan \nfunding”) for load delivery points while directly assigning costs above that level to the \nrequesting Transmission Customer. Because the LSHL operates through the Tariff and \nSPP’s existing Commission-accepted cost allocation framework, it applies uniformly \nto every delivery point request, ties the customer’s obligation to the actual cost of the \nNetwork Upgrades identified in SPP’s studies, and preserves SPP’s existing regional \n \n5  \nId. at PP 59-65. \n6  \nId. at P 2. \n7  \nId. at P 59. \n8  \nId. at P 62."},{"page":3,"startToken":736,"endToken":1072,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 3 \n \ncost allocation methods, which the Show Cause Order expressly did not intend to \ndisturb.9  \nThis filing, which addresses the Commission’s directive regarding mitigation \nof the risk of cost shifting, is one part of SPP’s comprehensive response to the Show \nCause Order. The filings addressing the Show Cause Order’s remaining directives are \nidentified in Section IV.E. \nII. \nBACKGROUND \nA. \nThe HILL Process  \nOn January 14, 2026, the Commission accepted SPP's Tariff revisions \nestablishing the HILL study process in Attachment BA and the High Impact Large \nLoad Generation Assessment (\"HILLGA\") in Attachment BB. Those revisions: (1) \ndefined HILLs as a new category of load; (2) established enhanced study requirements \nfor HILLs, including the HILL Delivery Point Study (\"HDPS\"), to enable SPP to assess \nthe reliability impacts of a HILL on the Transmission System; and (3) imposed ongoing \noperational requirements on HILLs to ensure the continued reliable operation of the \nTransmission System. The Commission found the HILL process to be “a just and \nreasonable approach for integrating transmission customers’ new large loads onto \nSPP’s transmission system in a reliable manner.”10 \nB. \nThe Show Cause Order  \nIn the Show Cause Order, the Commission adopted SPP’s HILL definition as \nits definition of “large load.”11 It then preliminarily found that the Tariff appears unjust \nand unreasonable in four categories. The Commission directed SPP and the \nTransmission Owners either to show cause why the Tariff remains just and reasonable \nor to explain what changes would remedy the identified concerns.12 The Commission \nstrongly encouraged SPP to address these issues through FPA Section 205 filings.13 \nC. \nAbeyance  \nOn August 3, 2026, SPP and the Transmission Owners jointly moved to hold \nDocket No. EL26-68-000 in abeyance through November 20, 2026, so SPP could \n \n9  \nId. at P 63. \n10  \nSw. Power Pool, Inc., 194 FERC ¶ 61,031 at P 61 (2026) (“HILL Order”). \n11  \nShow Cause Order at n.2. \n12  \nId. at P 3. \n13  \nId. at P 32."},{"page":4,"startToken":1072,"endToken":1447,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 4 \n \ndevelop Section 205 filings through its stakeholder process.14 SPP described the \nanticipated content of those filings in its Abeyance Motion, including the revisions \nsubmitted here.15 On August 14, 2026, the Commission granted the Abeyance Motion \nand set a due date of November 20, 2026, for SPP’s response to the Show Cause \nOrder.16  \nD. \nStakeholder Process and Approval  \nThe LSHL revisions were reviewed through SPP’s stakeholder process, \nincluding meetings of the Regional Tariff Working Group (“RTWG”) on September \n24, 2026;17 Cost Allocation Working Group (“CAWG”) on October 1, 2026;18 Cost \nControl and Allocation Review and Evaluation Team (“CARE Team”) on October 7, \n \n14  \nJoint Movants’ Amended Motion to Hold Section 206 Proceeding in Abeyance of \nSouthwest Power Pool, Inc., et al., Docket No. EL26-68-000 (Aug. 3, 2026) \n(“Abeyance Motion”). \n15  \nId. \n16  \nSw. Power Pool, Inc., 196 FERC ¶ 61,128 (2026) (“Abeyance Order”). \n17  \nThe RTWG did not approve the LSHL in its vote dated October 12, 2026. See the votes \nof the RTWG included in the RR814 Recommendation Report  posted at: \nhttps://www.spp.org/Documents/77866/rr814%20(6).zip (contained in zip file \n“RR814 Load Safe Harbor Limit”).  The RTWG develops, implements and oversees \nSPP’s Open Access Transmission Tariff. The RTWG provides input on regulatory or \nimplementation issues not specifically covered by the tariff and issues where there may \nbe conflicting or differing interpretations of the tariff. \n18  \nSee CAWG Meeting Minutes, dated October 1, 2026, at Agenda Item 11 posted at: \nhttps://www.spp.org/documents/77976/cawg%20minutes%2020261001.pdf. \nThe \nCAWG reports to the Regional State Committee and assists the RSC in addressing \nmatters for which the RSC has primary responsibility as defined in Section 7.2 of the \nSPP Bylaws.  In addition, the CAWG will assist the RSC in addressing any other issues \nas requested by the RSC. The CAWG approved a motion which stated “The [CAWG] \nrecommends the Regional State Committee approve RR814 – Load Safe Harbor Limit, \nwhich includes a load safe harbor limit of $21,250,000 for load interconnection of \n50MW or larger.”. The CAWG approved by a vote of six (6) in favor, four (4) against, \nand five (5) abstentions."},{"page":5,"startToken":1447,"endToken":1939,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 5 \n \n2026;19 Markets and Operations Policy Committee (“MOPC”) on October 13, 2026;20 \nand Regional State Committee (“RSC”) on November 16, 2026.21  \n \n19  \nSee CARE Team Meeting Minutes, dated October 7, 2026, at Agenda Item 7 posted \nat: \nhttps://www.spp.org/documents/78112/care%20team%20minutes%2020261007.pdf. \nThe CARE Team serves as a cross-functional leadership body to review, evaluate, \nassess, and recommend refinements or alternatives to the current transmission cost \ncontrols and cost allocation methodologies. The CARE Team’s recommendations are \nintended to increase confidence that SPP’s processes produce efficient cost-effective \nresults and that costs are equitably allocated commensurate with expected benefits \nreceived, while maintaining fiscal discipline necessary to support infrastructure \ninvestment that meet regional reliability needs. The CARE Team approved the \nfollowing motion by a vote of fourteen (14) in favor and two (2) abstentions: the CARE \nTeam approves RR814 – Load Safe Harbor Limit, as presented, and with the following \nchanges: Make the Load Safe Harbor Limit applicable only to delivery point additions \nor modifications that are requested for study on or after the Tariff effective date \nestablished by FERC; and limit direct assignment resulting from the Load Safe Harbor \nLimit to no more than 20 years, with recovery of the revenue requirement subsequently \nreverting to Base Plan Upgrade cost allocation.” \n20  \nSee MOPC Meeting Minutes, dated October 22, 2026, at Agenda Item 3(d) \nposted \nat: \nhttps://www.spp.org/Documents/78127/MOPC%20Mtg%20Minutes%20and\n%20Ballots%2020261014.zip. The MOPC is responsible, through its \ndesignated Organizational Groups, for developing and recommending policies \nand procedures related to the technical operations for the company in \naccordance with its scope as approved by the Board of Directors. The MOPC \nfailed to pass any motion related to the LSHL. \n21  \nSee RSC Meeting Materials, dated November 16, 2026, at Agenda Item 7A posted at: \nhttps://spp.org/spp-documents-filings/?id=20623. The meeting minutes will be posted \nthat this location when they become available.   The RSC provides collective state \nregulatory agency input on matters of regional importance related to the development \nand operation of bulk electric transmission. The SPP RSC is comprised of retail \nregulatory commissioners from agencies in Arkansas, Arizona, Colorado, Iowa, \nKansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North \nDakota, Oklahoma, South Dakota, Texas, Utah and Wyoming. The RSC approved the \nfollowing motion by a vote of fourteen (14) in favor, one (1) against, and one (1) \nabstention: “The Regional State Committee approves RR814 - Load Safe Harbor Limit \nconsistent with the CARE Team recommendation, as amended. The RSC further \nadopts an action item for the Cost Allocation Working Group to review the Load Safe \nHarbor Limit amounts annually and report to the RSC if the CAWG recommends that \na prospective adjustment of the limits be filed with FERC. The period for direct \nassignment of costs in excess of the Load Safe Harbor Limit shall not exceed forty (40) \nyears.”"},{"page":6,"startToken":1939,"endToken":2309,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 6 \n \nSPP’s Commission-approved Bylaws expressly recognize state regulatory \nauthority and assign the RSC specific responsibilities within SPP. Section 7.1 of the \nSPP Bylaws provides that “[n]othing in the formation or operation of SPP as a FERC-\nrecognized regional transmission organization is in any way intended to diminish \nexisting state regulatory jurisdiction and authority.”22 The SPP Bylaws specifically \ngrant the RSC authority over cost allocation proposals in SPP.  The Bylaws state, “[t]he \nRSC has primary responsibility for determining regional proposals and the transition \nprocess in the following areas: (a) whether and to what extent participant funding will \nbe used for transmission enhancements… [.]”23 In turn, as the RSC reaches decisions \non cost allocation methodologies, SPP will make the requisite filings at the \nCommission. 24 Because the LSHL determines the extent to which delivery point \nNetwork Upgrade costs are directly assigned versus being regionally allocated, it falls \nsquarely within the RSC’s authority. \n \nIn recognition of the RSC authorities under Section 7.2 of the SPP Bylaws, the \nSPP Board of Directors appropriately approved the filing of these Tariff revisions, as \napproved by the RSC, to create the LSHL.25 \nIII. \nCURRENT \nCOST \nALLOCATION \nFOR \nDELIVERY \nPOINT \nNETWORK \nUPGRADES \nAND \nEXISTING \nSAFE \nHARBOR \nPROVISIONS \nA. \nSPP Transmission Service Process  \nAs described in Section II.A above, the Commission accepted SPP’s HILL and \nHILLGA Tariff revisions on January 14, 2026.26 SPP processes all load additions and \nmodifications for long-term firm SPP transmission service, including HILLs, using its \nexisting Attachment AQ and/or Attachment AX study processes.27 However, for \n \n22  \nSee Bylaws at Section 7.1. \n23  \nSee Bylaws at Section 7.2. \n24  \nId. \n25  \nSee Board of Directors & Members Committee Meeting Materials, dated November \n17, 2026, at Agenda Item 3.2.1 posted at:   https://www.spp.org/spp-documents-\nfilings/?id=18449. The meeting minutes will be posted that this location when they \nbecome available.    \n26  \nSee HILL Order. \n27  \nThrough Attachment AQ, any existing customers with a sufficient level of existing \nDesignated Resources may obtain firm transmission service for the modification of an \nexisting delivery point or for the creation of a new delivery point. Under Attachment"},{"page":7,"startToken":2309,"endToken":2732,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 7 \n \nHILLs, SPP and the applicable Transmission Owner(s) simultaneously conduct \nadditional studies under Attachment BA to ensure that the unique operational \ncharacteristics of HILLs are considered when evaluating the addition of a HILL to the \nTransmission System, and that SPP has mechanisms in place to maintain reliable \noperation of the Transmission System.28 These ongoing operational requirements under \nAttachment BA, including the addition of certain equipment, ensure that SPP can \ncontinue to manage the Transmission System while accommodating the unique \noperational demands and characteristics of HILLs.29  \nNetwork Upgrades identified as necessary to accommodate load additions or \nmodifications through Attachment AQ are Base Plan Upgrades, meaning that their \ncosts are allocated through rolled-in regional, subregional, and/or zonal rates among \nSPP Transmission Customers pursuant to the criteria in the Tariff (“Base Plan \nFunded”).30 Network Upgrades identified in the Attachment AX process are directly \nassigned to the Transmission Customer until it receives Long-Term Service for the \nplanned generation studied under Attachment AX, at which point the remaining costs \nare Base Plan Funded.31  Thus, the Commission has already accepted direct assignment \nas a just and reasonable means to protect other customers from delivery point Network \nUpgrade costs while load-related uncertainty persists. Currently, there is no limit to the \namount of Network Upgrade costs, quantified as either dollars per megawatt (“MW”) \nor total cost, that can be Base Plan Funded for a delivery point request, regardless of \nthe costs relative to the load requested or whether the load materializes. This is \nprecisely the gap the Show Cause Order identified. \nB. \nOriginal Safe Harbor Provisions \nSPP’s original cost allocation methodology, which the Commission accepted in \n2005 (“Base Plan Funding Order”),32 included the Safe Harbor Provisions33 to limit the \n \nAX, existing customers may receive provisional study of a new or modified delivery \npoint using planned generation, instead of existing Designated Resources.  \n28  \nTariff, Attachment BA, Sections 2.1.3.4 and 2.1.3.5. \n29  \nTariff, Attachment BA, Section 2.2. \n30  \nTariff, Attachment J, Section III.A.  \n31  \nTariff, Attachment J, Section V.F; Sw. Power Pool, Inc., 193 FERC ¶ 61,018 (2025). \n32  \nSee Sw. Power Pool, Inc., 111 FERC ¶ 61,118, order on reh’g, 112 FERC ¶ 61,319 \n(2005). \n33  \nAs used herein, the term “Safe Harbor Provisions” refers to the criteria set forth in \nTariff Attachment J, Section III.B, which identify the conditions for Network Upgrade \ncosts associated with Designated Resources to be classified as Base Plan Upgrade costs"},{"page":8,"startToken":2732,"endToken":3255,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 8 \n \nNetwork Upgrade costs allocated to the SPP Region. Specifically, the Safe Harbor \nProvisions relate to costs for Network Upgrades associated with designating a \ngeneration resource.34 Under the currently applicable set of Safe Harbor Provisions, \nany Network Upgrades identified as needed because of the designation of a resource \nare eligible to be Base Plan funded if the following conditions are met: (1) the \nTransmission Customer’s commitment to the Designated Resource has a duration of at \nleast five years; (2) the new and existing Designated Resources of the Transmission \nCustomer do not exceed the higher of (a) 125% or (b) the sum of 110% and the current \nPlanning Reserve Margin percentage set forth in the SPP Planning Criteria;35 and (3) if \nthe new Designated Resource is a wind generation plant, the sum of the requested \ncapacity for the new wind Designated Resource and the reserved capacity for the \nTransmission Customer’s existing wind Designated Resources do not exceed 20% of \nthe customer’s projected system peak responsibility (“Wind/Load Condition”).36 If the \nconditions above are met, or a waiver is requested and received pursuant to Section \nIII.C of Attachment J, aggregate costs for Network Upgrades associated with \ndesignating a generation resource that are less than or equal to $180,000 per MW (“Safe \nHarbor Cost Limit”) are eligible for Base Plan funding (i.e., rolled into generally \napplicable rates under Schedule 11 of the Tariff). The Safe Harbor Cost Limit was \ndesigned to provide a check on the level of investment required to support the \ntransmission service request. This limitation provides an incentive to locate generation \ncloser to load and closer to adequate network transmission infrastructure. \nIn the Base Plan Funding Order, the Commission approved the Safe Harbor \nProvisions, but the Commission directed SPP to assess average costs of all Network \nUpgrades as part of its biennial planning process and work with stakeholders and the \nRSC to evaluate the effectiveness and accuracy of the $180,000 per MW Safe Harbor \n \neligible for cost allocation.  These conditions include the Safe Harbor Cost Limit of \n$180,000 per MW, which is specified in Section B.1.d.i and Section B.3 of Attachment \nJ. \n34  \nSafe Harbor Provisions are not applicable to transmission upgrades approved for \npurposes other than resource designation.   \n35  \nThe “higher of (a) 125% or (b) the sum of 110% and the current Planning Reserve \nMargin percentage set forth in the SPP Planning Criteria” was not part of the original \nSafe Harbor Provisions accepted by the Commission in the Base Plan Funding Order. \nThe cap originally accepted in 2005 was “125% of the Transmission Customer’s \nprojected system peak responsibility” and the cap was subsequently expanded to its \nabove form by the Commission in 2024. Sw. Power Pool, Inc., 188 FERC ¶ 61,213 \n(2024). \n36  \nThis Wind/Load Condition was not included in Safe Harbor Provisions accepted by \nthe Commission in the Base Plan Funding Order.  It was subsequently added to the \nSafe Harbor Provisions and approved by the Commission in 2009. See Sw. Power Pool, \nInc., 127 FERC ¶ 61,283 (2009)."},{"page":9,"startToken":3255,"endToken":3596,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 9 \n \nCost Limit.37 The Commission directed SPP to file an annual report to include: (1) \naverage costs of new Network Upgrades and the effectiveness of the Safe Harbor Cost \nLimit threshold; (2) an “unintended consequences” review (now addressed every six \nyears as a consideration in a broad cost allocation review); and (3) SPP’s disposition \nof requests for waiver of the Base Plan funding eligibility conditions and the Safe \nHarbor Cost Limit in the Safe Harbor Provisions.38 Since 2006, SPP has complied with \nthis yearly filing requirement.39 \nThe Load Safe Harbor Limit proposed in this filing is modeled after the current \nSafe Harbor Cost Limit. The Load Safe Harbor Limit, if approved, establishes a direct \nlink to cost causation, with the entity for whom the Network Upgrades were built \nbearing any excess costs.  \nIV. \nDESCRIPTION OF AND JUSTIFICATION FOR THE LOAD SAFE \nHARBOR LIMIT REVISIONS \nA. \nShow Cause Order Requirements \nAs noted above, the Show Cause Order preliminarily found “that SPP’s Tariff \nappears to be unjust and unreasonable because it lacks adequate mechanisms to \nmitigate the risk of cost shifting among transmission customers, which may result in \nunjust and unreasonable rates for transmission service.”40 The Commission further \npreliminarily found that the minimum contribution required of Transmission \nCustomers on behalf of large loads “should be based on the level of jurisdictional \ntransmission service (in MW) requested...”41 The Commission also preliminarily found \nthat the cost recovery mechanism should “include a credit support (or other financial \nsecurity) requirement sufficient to secure the obligations of the Eligible Customer \ntaking transmission service on behalf of a large load to pay the amounts owed…”42 \nB. \nLoad Safe Harbor Limit Proposal \nSPP proposes to establish a LSHL for Network Upgrades needed to add or \nmodify load delivery points studied under Attachment AQ, Attachment AX, or \n \n37  \nBase Plan Funding Order at P 51. \n38  \nId. \n39  \nSee Docket No. ER05-652-000. \n40  \nShow Cause Order at P 59. \n41  \nId. at P 65. \n42  \nId."},{"page":10,"startToken":3596,"endToken":3964,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 10 \n \nAttachment BA of the Tariff.43 The LSHL will require Transmission Customers to pay \nfor any Network Upgrade costs identified in the SPP transmission service process that \nexceed the lesser of $25 million or $500,000 per MW of transmission service \nrequested.44 Zonal Reliability Upgrades, which are not Base Plan Upgrades, are \nexcluded. Any cost above the LSHL will be directly assigned to the Transmission \nCustomer that requested the delivery point addition or modification.45 The directly \nassigned amount will be recovered as a Transmission Owner-calculated revenue \nrequirement, based on the Transmission Owner’s standard revenue requirement \nmethodology, for no more than forty (40) years.46 Thereafter, any remaining revenue \nrequirement will be allocated as a Base Plan Upgrade.47 The LSHL will apply to \ndelivery point addition or modification requests submitted under Attachments AQ, AX, \nor BA on or after the effective date accepted by the Commission.48 \nAny Transmission Customer responsible for directly assigned Network \nUpgrade costs through application of the LSHL will be required to provide financial \nsecurity.49 The level of required security will be tied to the amount of direct assignment \nand will be reduced as the associated Network Upgrade assets depreciate.50 A claim on \nthe financial security will be necessary only if the entity paying the direct assignment \ndefaults.51 The period over which the security will be held is the term of payment for \nthe directly assigned cost.52 Therefore, the financial security arrangements to protect \nagainst the risk of cost shifting will have clearly defined parameters for amount, \nduration, and trigger of any potential claim on the security. This type of financial \nsecurity arrangement is administered under the Tariff for existing forms of direct \nassignment, such as charges for Service Upgrades and Sponsored Upgrades.53 \n \n43  \nProposed Tariff, Attachment J, Section V.G. \n44  \nId. \n45  \nId. \n46  \nProposed Tariff, Attachment J, Sections V.F and V.G. \n47  \nId. \n48  \nProposed Tariff, Attachment J, Section V.G. \n49  \nProposed Tariff, Attachment AQ, Section 4.0 and Attachment AX, Section 3.0. \n50  \nId. \n51  \nId. \n52  \nId. \n53  \nTariff, Attachment J, Section V and Attachment Z1, Section III."},{"page":11,"startToken":3964,"endToken":4505,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 11 \n \nThe Commission’s large load Show Cause Order emphasizes mitigation of the \nrisk of cost shifting, including a specified minimum financial contribution and \nsufficient financial security to reduce cost shifting risk when forecasted load does not \ndevelop as planned. This proposal directly addresses those concerns by retaining a basic \nlevel of load interconnection service that is funded by the SPP Region and directly \nassigning costs exceeding that level, backed by financial security, to the customer \nwhose transmission service request causes the upgrades. This proposal establishes a \ndirect link to cost causation, with the entity for whom the Network Upgrades were built \nbearing any excess costs.  \nThe proposed limit of $500,000 per MW is informed by two data sets, which \nare attached to this transmittal letter as Exhibit 1 and Exhibit 2. Exhibit 1 is an affidavit \nfrom Natasha Henderson with an attached spreadsheet outlining the upgrade costs \nresulting from Notifications to Construct (“NTCs”) that have been issued by SPP \nthrough its delivery point study processes from 2012 to 2026, which includes for each \nload request (1) the load amount; (2) the total cost of the Network Upgrades identified; \n(3) the cost per MW of load requested; (4) the approximate date when the Network \nUpgrades are put into service; and (5) the cost per MW percentile compared to the other \nrequests included on Exhibit 1. Exhibit 2 is an affidavit from Don Frerking with an \nattached spreadsheet that includes transmission gross and net plant values, both in total \nand on a per-MW basis, for the SPP Region. The transmission plant per-MW values \nwere derived from: (1) gross and net plant values in individual Transmission Owner \nformula rate template updates (effective as of August 2026); and (2) transmission \nrevenue requirement and zonal load information sourced from the August 2026 \nRevenue Requirements and Rates (“RRR”) file.54 \nHistorical delivery point studies requiring Network Upgrades showed \napproximate costs of $177,000 per MW at the median, $378,000 per MW at the 75th \npercentile, and $1.018 million per MW at the 95th percentile. The estimated investment \nin transmission facilities across the entire SPP Region is approximately $422,000 per \nMW on a net plant basis (reduced for depreciation) and $572,000 per MW on a gross \nplant basis. The value of the proposed per-MW limit falls between those system-wide \ninvestment measures and between the historical 75th and 95th percentiles for delivery \npoint requests. The percentiles from this history of requests that required Network \nUpgrades suggest that the majority of future delivery point requests requiring such \nupgrades will remain under the proposed per-MW cost cap, thereby resulting in full \nBase Plan funding at an average cost level for delivery points which are not HILLs. \nAlso, it should be noted that a large majority of delivery point requests do not require \nissuance of a Notification to Construct for any Network Upgrade. In addition to \nprotecting the region from bearing excess costs associated with load interconnection \nrequests, the proposed per-MW limit provides an incentive for the requesting \nTransmission Customer to select cost effective interconnection locations, which is \n \n54  \nThe SPP RRR files can be found at the following link: https://www.spp.org/spp-\ndocuments-filings/?id=18251."},{"page":12,"startToken":4505,"endToken":5031,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 12 \n \nconsistent with emphasis in the Show Cause Order on cost-effective solutions.55 For \nload requests that are smaller than the 50 MW threshold for a HILL connecting above \n69 kV, these limits will ensure that new load receives Base Plan funding beyond the \nmedian level of transmission investment for adding or modifying delivery points, while \nany costs above the $500,000 per MW level are assigned to the requesting \nTransmission Customer. For delivery point requests smaller than 50 MW, only those \nentailing excessive per-MW cost (i.e., above roughly the 85th percentile level) are \ncharged a direct assignment. Although upgrade costs, transmission rates, and \ntransmission rate impacts vary significantly between SPP pricing Zones due to \ndifferences among Schedule 9 and Schedule 11 zonal revenue requirements, the \nproposed limit value of $500,000 per MW is a level that can be supported from an \noverall system average rate perspective. With this limit in place, Network Upgrades for \ndelivery points can be added without putting a substantial amount of upward pressure \non average transmission service rates due to the delivery point changes alone.56 Further, \nthe fact that this proposed limit exceeds the system-wide net transmission plant value \nof $422,000 per MW provides allowance for some escalation in the system-wide \naverage due to inflation between the date of application of the LSHL in the Attachment \nAQ or AX study and the actual in-service date of the upgrade(s) when the cost effect \nwill be realized in transmission rates.       \nThe proposed framework of a per-MW limit coupled with an aggregate limit \nensures that the focus is on mitigation of cost risk. An aggregate cap is needed because \na per-MW limit alone could leave the SPP Region, and its ratepayers, potentially \nexposed to very large cost burdens. For example, with a $500,000 per MW limit, a \n1,000 MW request could qualify for $500 million of Base Plan funding if there were \nno aggregate cap. Further, a per-MW limit without an aggregate limit could incentivize \nthe submission of inflated delivery point load amounts in some situations.  \nThe proposed $25 million aggregate cap for the LSHL is calculated using the \n50 MW HILL definition threshold57 for interconnections above 69 kV (i.e., 50 MW \nmultiplied by $500,000) and provides a meaningful, regional funding level. Tying to \nthe Tariff’s HILL definition (and to the Show Cause Order’s adopted large load \n \n55  \nSee generally, Show Cause Order at PP 44-45. \n56  \nAlthough this filing is focused on cost responsibility for Network Upgrades resulting \nfrom delivery point changes, it should be noted that long-term incremental costs \nassociated with load growth are broad and are driven through additional planning \nprocesses including consolidated planning, generator interconnection, and \ntransmission service.  Through the CARE Team, SPP and its stakeholders worked for \nthe past year on development of multiple policy-level proposals to adjust SPP’s cost \nallocation framework in view of rapid load growth. These proposals will be further \nrefined in coming months through SPP’s stakeholder processes.    \n57  \nSee generally, Show Cause Order at P 16 (the Commission points out its previous \napproval of the HILL definition)."},{"page":13,"startToken":5031,"endToken":5425,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 13 \n \ndefinition) by means of an aggregate cost cap, rather than linking applicability of the \nlimit mechanism strictly to a load threshold (e.g., 50 MW), is a structure that avoids \nincentivizing Transmission Customers to submit delivery point requests below such a \nMW threshold regardless of the amount of load actually anticipated. \nTable 1 below outlines an example of how the Load Safe Harbor Limit would \nbe applied to Network Upgrades identified under Attachment AX, Attachment AQ, or \nAttachment BA. \nTable 1: \n \n \nThe proposed LSHL results in a division of cost responsibility for the delivery \npoint end of a transmission service path between a portion subject to regional cost \nallocation and a portion directly assigned to the requesting Transmission Customer. \nThis is generally consistent with the Tariff’s current treatment of the resource end of \nthe transmission service path (i.e., the existing Safe Harbor Provisions), which \nincorporates a division of cost responsibility between a portion subject to regional cost \nallocation and a portion assigned to the requesting Transmission Customer by means \nof the Safe Harbor Cost Limit and other qualifying criteria for regional funding as set \nforth in Section III.B of Attachment J. This is a means to recognize the benefits that \nNetwork Upgrades can provide to other Transmission Customers in the Zone, \nSubregion, or even across the SPP Region while still applying the cost-causation \nprinciple through direct assignment of any cost above the LSHL.   \nThose Transmission Customers who bear directly assigned costs for delivery \npoint Network Upgrades as a result of the Load Safe Harbor Limit will be eligible for \ncompensation through allocation of Candidate Incremental Long-Term Congestion \nRights, as provided under Attachment Z2 of the Tariff.     \nC. \nThe Load Safe Harbor Limit Resolves the Show Cause Order’s Cost \nRecovery Directive \nAs required by the Show Cause Order, the proposed LSHL specifically \nmitigates the cost risks to existing Transmission Customers by requiring a minimum \ncontribution by Transmission Customers taking transmission service on behalf of the \nlarge loads that impose costs above the LSHL. The per-MW component of the proposed \nLSHL is based on the level of SPP transmission service that is requested by the \nTransmission Customer and the aggregate cap component of the proposed LSHL is \nbased on an amount corresponding to the 50 MW threshold for a HILL. As a result, the"},{"page":14,"startToken":5425,"endToken":5866,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 14 \n \namount of potential contribution for large loads varies directly with the cost created by \nthe load request, a cost level which is driven primarily by the MW amount requested.58 \nThe proposed framework also requires Transmission Customers taking transmission \nservice on behalf of large loads to  provide a sufficient contribution to ensure that large \nloads interconnecting to the SPP Transmission System are not unduly burdening other \nTransmission Customers with costs caused by such interconnection.59 Lastly, the Load \nSafe Harbor Limit Revisions require the Transmission Customer taking service on \nbehalf of a large load to provide sufficient security to back its obligation to pay the \namounts that are owed.60 The directly assigned obligation is a fixed payment that does \nnot depend on whether, when, or at what level the load is energized. Payments begin \nwhen the Transmission Owner establishes a revenue requirement for the upgrade, \naddressing the timing concern in Paragraph 65 of the Show Cause Order; and directly \nassigned amounts are excluded from the Base Plan Upgrade revenue requirements \ncharged to other customers. This is the kind of “other just and reasonable method[]” \nthe Commission invited.61 \nUnder FPA Section 205, SPP must show that its proposal is just and reasonable. \nIt need not show that the proposal is the only reasonable approach or that it is more \nreasonable than the alternatives.62 The LSHL meets this burden. As described above, \nthe LSHL provides for a just and reasonable, and not unduly discriminatory, approach \nfor satisfying the Commission’s concern outlined in the Show Cause Order, and the \nCommission should accept it.  \nD. \nAnnual Load Safe Harbor Limit Annual Filing \nAs described above in Section III.B, the Commission, in the Base Plan Funding \nOrder, directed SPP to assess average costs of all Network Upgrades as part of its \nbiennial planning process and work with stakeholders and the RSC to evaluate the \neffectiveness and accuracy of the $180,000 per MW Safe Harbor Cost Limit.63 The \nCommission directed SPP to file an annual report to include: (1) average costs of new \nNetwork Upgrades and the effectiveness of the Safe Harbor Cost Limit threshold; (2) \nan “unintended consequences” review (now addressed every six years as a \nconsideration in a broad cost allocation review); and (3) SPP’s disposition of requests \n \n58  \nId. at P 65. \n59  \nId.  \n60  \nId. \n61  \nId. \n62  \nSee, e.g., Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984); OXY USA, \nInc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995). \n63  \nBase Plan Funding Order at P 51."},{"page":15,"startToken":5866,"endToken":6254,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 15 \n \nfor waiver of the Base Plan Funding eligibility conditions and the Safe Harbor Cost \nLimit in the Safe Harbor Provisions.64  \nIf directed by the Commission to do so here, SPP is willing to annually assess \nthe average costs of all Network Upgrades from SPP’s delivery point studies and \naverage costs from SPP Region transmission plant values and to work with the RSC \nand stakeholders to evaluate the effectiveness and accuracy of the proposed LSHL. SPP \nwould also be willing to add this updated information regarding average costs of all \nNetwork Upgrade from SPP’s delivery point studies and average costs from SPP \nRegion transmission plant values to its annual Safe Harbor Cost Limit filing for \ninformational purposes.  \nAdditionally, as part of the RSC’s approval of the LSHL, the RSC directed the \nCAWG to review the Load Safe Harbor Limit amounts annually and report to the RSC if the \nCAWG recommends that a prospective adjustment of the limits be filed with the Commission. \nThis is a similar action item that the CAWG currently has for its annual review of the designated \nresource Safe Harbor Cost Limit. \nE. \nDirectives Addressed in Separate Filings  \nThis filing does not address the remaining Show Cause Order directives. SPP \nis addressing them in the following separate filings:  \n• HILL Transmission Service Revisions and Non-Transmission Facility \nRevisions (the “Combined Filing”);  \n• Price Adaptive Load Service (PALS); and \n• SPP’s response to the Show Cause Order in Docket No. EL26-68-000, \nwhich addresses, among other things, transmission and ancillary service \nrates for co-located load. \n \n \nSPP respectfully requests that the Commission consider this filing together with \nthe above filings as SPP’s response to the Show Cause Order. \nV. \nPROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS  \nThe Show Cause Order directs that any Section 205 filing explain how the \nproposal will avoid disrupting existing commercial arrangements and identify a \nreasonable effective date.65 The proposed LSHL provisions are designed to apply only \nto delivery point requests submitted for study on or after the effective date accepted by \nthe Commission. This will allow Transmission Customers and their large load \ncustomers sufficient time to incorporate and appropriately reference the impacts of the \nLSHL provisions in their agreements prior to finalization. The LSHL will not affect \n \n64  \nId. \n65  \nShow Cause Order at PP 5, 32, 92."},{"page":16,"startToken":6254,"endToken":6744,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 16 \n \nexisting commercial arrangements that are based on currently ongoing or past delivery \npoint studies. \nVI. \nPROPOSED TARIFF CHANGES AND JUSTIFICATIONS \nA. \nPart I, Section 1, Definitions \nSPP proposes to modify two existing definitions and add a new definition to \nPart I, Section 1 of the Tariff as follows: \n \ni. \n1 Definitions B \n \nBase Plan Upgrades:  Those upgrades included in and constructed pursuant to \nthe SPP Transmission Expansion Plan in order to ensure the reliability of the \nTransmission System.  Base Plan Upgrades shall also include: (i) those Service \nUpgrades required for new or changed Designated Resources to the extent \nallowed for in Attachment J to this Tariff, (ii) to the extent allowed in Sections \nV.F and V.G of Attachment J, Network Upgrades required pursuant to the study \nresults under Attachment AQ to this Tariff or required pursuant to Attachment \nAX of this Tariff after the planned generation has been included as a Designated \nResource in the applicable Transmission Customer’s Network Integration \nTransmission Service Agreement or Service Agreement for Long-Term Firm \nPoint-To-Point Transmission Service, (iii) ITP Upgrades that are approved for \nconstruction by the SPP Board of Directors, (iv) CPP Upgrades that are \napproved for construction by the SPP Board of Directors or authorized under a \nCPP GIA and that have a portion of cost allocated pursuant to Section III of \nAttachment J to this Tariff and recovered under Schedule 11 to this Tariff, (v) \nhigh priority upgrades, excluding Balanced Portfolios, that are approved for \nconstruction by the SPP Board of Directors, (vi) Network Upgrades due to the \nretirement of a Resource in accordance with Attachment AB to this Tariff; and \n(vii) to the extent allowed in Section III.B of Attachment J, Qualifying NRIS \nUpgrades.  For Zones 1 through 15, all such upgrades shall specifically exclude \nplanned Transmission System facilities identified in the SPP Transmission \nExpansion Plan that are: (i) placed in service during the 2005 calendar year or \n(ii) required to be in service to meet the SPP Criteria and the NERC Reliability \nStandards for the summer of 2005.  For Zones 16, 17, and 18, all such upgrades \nshall specifically exclude planned Transmission System facilities in those zones \nidentified in the SPP Transmission Expansion Plan Report (2009 – 2018) that \nare required to be in service to meet the SPP Criteria and the NERC Reliability \nStandards for the summer of 2008 or which are in operation prior to January 1, \n2009, except for those upgrades that are in service prior to January 1, 2009 and \nare components of Phase 1 of the NPPD 345kV Norfolk to Lincoln (ETR) \nproject or OPPD Sub 1255/3455 Transformer project.   Network Upgrades that \nare components of Phase 1 of the NPPD 345kV Norfolk to Lincoln (ETR) \nproject or OPPD Sub 1255/3455 Transformer project that are in service prior to \nJanuary 1, 2009 will be Base Plan Upgrades, however, the Zonal component of"},{"page":17,"startToken":6744,"endToken":7147,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 17 \n \nthe costs shall be 100% allocated to the respective host zone. The Base Plan \nUpgrades in Zones 1 through 18 identified by the Transmission Provider with \na need date prior to October 1, 2015 shall not be allocable to Zone 19.  The \nupgrades in Zone 19 identified by the Transmission Provider with a need date \nprior to October 1, 2015, shall not constitute Base Plan Upgrades. The facilities \nidentified in Schedule 2 to Attachment J are expressly deemed to be Base Plan \nUpgrades pursuant to Attachment J, Section III.A.2.66 \n \nThis proposed revision is necessary to reference the portion of any Network \nUpgrade cost that does not exceed the LSHL, which remains a Base Plan Upgrade cost \nallocated under Section III.A of Attachment J.  \n \n \nii. \n1 Definitions D \nDirectly Assigned Upgrade Costs:  An Eligible Customer’s share of the cost \nof a Service Upgrade or Network Upgrade, or a Project Sponsor’s share of the \ncost of a Sponsored Upgrade, determined in accordance with Attachments J, V, \nZ1, and AX, which includes any Network Upgrade costs that are (i) directly \nassigned to an Eligible Customer for a Service Upgrade in excess of the \nnormally applicable transmission access charges for the associated transmission \nservice; (ii) directly assigned to an Eligible Customer that are in excess of the \nSafe Harbor Cost Limit for Service Upgrades associated with new or changed \nDesignated Resource; (iii) directly assigned to a Project Sponsor for a \nSponsored Upgrade; (iv) directly assigned to a Generation Interconnection  \nCustomer resulting from a request for generation interconnection; or (v) directly \nassigned to a Transmission Customer for a Network Upgrade when the \nTransmission Customer has not been granted Long-Term Service for the \nplanned generation that was submitted in accordance with Attachment AX; or \n(vi) directly assigned to a Transmission Customer for the Network Upgrade(s) \nrequired pursuant to a study conducted under Attachment AQ, Attachment AX, \nor Attachment BA to add or modify a delivery point when the applicable \nNetwork Upgrade costs exceed the Load Safe Harbor Limit specified in Section \nV.G of Attachment J.67 \nThis proposed revision is necessary to reference the portion of any Network \nUpgrade cost that exceeds the Load Safe Harbor Limit and is directly assigned to the \nTransmission Customer. \n \n66  \nProposed Tariff, Part I, Section 1 Definitions B. \n67  \nProposed Tariff, Part I, Section 1 Definitions D."},{"page":18,"startToken":7147,"endToken":7472,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 18 \n \n \niii. \n1 Definitions L \nLoad Safe Harbor Limit:  The maximum amount of Base Plan Upgrade cost \neligible for cost allocation, as specified in Section V.G of Attachment J, for \neach request studied pursuant to Attachment AQ, Attachment AX, or \nAttachment BA to add or modify a delivery point, which is applicable to the \nNetwork Upgrade(s) authorized for construction under such a study other than \nZonal Reliability Upgrades.68 \n \nThis proposed revision is needed to specifically define the LSHL, including the \nclarification that Zonal Reliability Upgrades, which are not Base Plan Upgrades, are \nnot subject to the cost limitation on rate funding. \n \nB. \nPart III Section 31.2 \n \n \ni. \nSection 31.2c \n \nSPP proposes to modify Section 31.2c to include a reference to Attachment AX \nof the Tariff as a governing attachment for requests for modification of delivery \npoints.69 This edit is simply a clean-up revision necessary to appropriately reference \nAttachment AX, along with Attachment AQ, as one of the attachments used to modify \ndelivery points. \n \n \nii. \nSection 31.2d \nSPP proposes to modify Section 31.2d to remove the reference to Section III of \nAttachment J and replace it with a reference to Section V.G of Attachment J of the \nTariff as the section governing funding for Network Upgrades identified under \nAttachment AQ.70 \nThis proposed revision is necessary as the appropriate reference should be to the new \nLSHL section, as that section describes how Network Upgrades identified in the \nAttachment AQ load addition or modification study processes will be allocated. \n \n \nC. \nAttachment J \n \n \ni. \nSection V.F \n \nSPP proposes to modify Section V.F of Attachment J to remove language \nstating that Network Upgrades are to be allocated pursuant to Section III.A of \n \n68  \nProposed Tariff, Part I, Section 1 Definitions L. \n69  \nProposed Tariff, Part III, Section 31.2c. \n70  \nProposed Tariff, Part III, Section 31.2d."},{"page":19,"startToken":7472,"endToken":7999,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 19 \n \nAttachment J upon the Transmission Customer receiving Long-Term Service for the \nplanned generation that was studied in accordance with Attachment AX. SPP proposes \nrevisions to replace the removed language with language stating that Network \nUpgrades are to be allocated in accordance with Section III.A of Attachment J for \namounts of cost less than or equal to the LSHL and direct assignment for any amount \nin excess of the LSHL. Under Attachment AX, the full term of directly assigned costs \nfor Network Upgrades, including both the period before Long-Term Service is received \nand the period after Long-Term Service is received, will not exceed forty (40) years. \nSubsequent to the termination date of direct assignment payments, the remaining \nrevenue requirements will be allocated in accordance with Section III.A of Attachment \nJ.71 \n \nThis proposed modification to Section V.F of Attachment J is necessary to \ndescribe how Network Upgrades identified in the Provisional Load Process \n(Attachment AX) will be Base Plan funded or directly assigned using the LSHL.  \n \n \nii. \nSection V.G \n \nSPP proposes to add a new subsection V.G of Attachment J for Network \nUpgrades required by SPP to add or modify a delivery point. SPP proposes revisions \nto state that cost up to the LSHL will be allocated in accordance with Section III.A of \nAttachment J for Affected Network Upgrades. “Affected Network Upgrades” are \ndefined as all Network Upgrade(s), other than any Zonal Reliability Upgrade(s), \nresulting from a request that is studied under Attachment AQ, Attachment AX, or \nAttachment BA to add or modify a delivery point. For the aggregate cost of Affected \nNetwork Upgrades under each study request, the LSHL is defined as the lesser of:  a) \n$500,000 per MW multiplied by the MW amount of requested change in delivery point \nload, or b) $25,000,000. The LSHL is applicable for load service requests submitted to \nSPP under Attachment AQ, Attachment AX, or Attachment BA on or after the effective \ndate established by the Commission for these Tariff changes. The aggregate amount of \nthe directly assigned cost for each delivery point request will be apportioned to the \nAffected Network Upgrade(s) in a manner that will minimize the number of such \nupgrades for which directly assigned cost will be charged, which is consistent with \ntreatment of Service Upgrades as provided in Section V.c of Tariff Attachment Z1 and \nreduces long-term administrative cost connected with directly assigned upgrades. The \nmonthly amount of directly assigned costs shall be the monthly revenue requirement of \nthe constructing Transmission Owner(s), with the revenue requirement amount based \non the portion of cost of the Affected Network Upgrade that is directly assigned and \ncalculated in a manner consistent with the revenue requirements of Network \nUpgrade(s) recovered by the Transmission Owner(s) under Schedule 9 or Schedule 11 \nof this Tariff. The term of each Affected Network Upgrade’s set of direct assignment \npayments will extend forty (40) years unless the Transmission Owner’s revenue \nrequirement for the Affected Network Upgrade is terminated at an earlier date. \n \n71  \nProposed Tariff, Attachment J, Section V.F."},{"page":20,"startToken":7999,"endToken":8346,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 20 \n \nSubsequent to the termination date of the directly assigned cost, any remaining revenue \nrequirements will be allocated in accordance with Section III.A of Attachment J.72 \n \nThis proposed new Section V.G of Attachment J is needed to describe how \nNetwork Upgrades identified in SPP’s transmission study processes for delivery point \nadditions and modifications will be Base Plan funded or directly assigned using the \nLSHL. \n \nD. \nAttachment Y \n \n \nSPP proposes revisions to Section I.1(a) of Attachment Y to be clear that \nNetwork Upgrades identified under Attachment AQ that have no directly assigned costs \nwill be eligible for the specified process under Section III of Attachment Y, subject to \nmeeting the remaining eligibility criteria.73  \n \nE. \nAttachment AQ \n \nSPP proposes to add language in Section 4.0 of Attachment AQ to state that \nresponsibility for the costs of facilities required under the Delivery Point Network \nStudy (“DPNS”) shall be as described in proposed Section V.G of Attachment J of the \nTariff. The Transmission Customer will maintain financial security, in an amount \ncorresponding to the engineering and construction costs associated with any direct \nassignment obligation for Network Upgrades identified for construction under the \nDPNS. The security requirement may be reduced annually or waived by SPP pursuant \nto specifications detailed in the proposed revisions.74 \n \nThese edits are necessary to describe the financial obligations of those \nTransmission Customers that are directly assigned Network Upgrade costs through the \nAttachment AQ study process. \n \nF. \nAttachment AX \n \n \ni. \nSection 3.0 \nSPP proposes to add language in Section 3.0 of Attachment AX to state that \nresponsibility for the costs of facilities required under the Provisional Load Process \nStudy (“PLPS”) shall be as described in proposed Section V.F of Attachment J of the \nTariff. The Transmission Customer will maintain financial security, in an amount \ncorresponding to the engineering and construction costs associated with any direct \n \n72  \nProposed Tariff, Attachment J, Section V.G. \n73  \nProposed Tariff, Attachment Y, Section 1. \n74  \nProposed Tariff, Attachment AQ, Section 4.0."},{"page":21,"startToken":8346,"endToken":8725,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 21 \n \nassignment obligation for Network Upgrades identified for construction under the \nPLPS. The security requirement may be reduced annually or waived by SPP pursuant \nto specifications detailed in the proposed revisions.75 \nThese edits are necessary to describe the financial obligations of those \nTransmission Customers that are directly assigned Network Upgrade costs through the \nAttachment AX study process. \n \nii. \nAddendum 2  \n \nSPP proposes revisions to Addendum 2 of Attachment AX to remove the \nreference to Schedule 11 and add that the remaining costs of Network Upgrade(s) shall \nbe recovered through allocation in accordance with Section III.A of Attachment J of \nthe Tariff and through direct assignment of any amount in excess of the LSHL, as \nspecified in Sections V.F and V.G of Attachment J.76 This revision is necessary \nbecause, under the LSHL, a portion of the remaining Network Upgrade costs may be \ndirectly assigned rather than recovered entirely under Schedule 11. \n \n \niii. \nAddendum 3 \n \nSPP also proposes revisions to Addendum 3 of Attachment AX to remove the \nreference to Schedule 11 and add that the remaining costs of Network Upgrade(s) shall \nbe recovered through allocation in accordance with Section III.A of Attachment J of \nthe Tariff and through direct assignment of any amount in excess of the LSHL, as \nspecified in Sections V.F and V.G of Attachment J.77 This revision is necessary \nbecause, under the LSHL, a portion of the remaining Network Upgrade costs may be \ndirectly assigned rather than recovered entirely under Schedule 11. \n \nG. \nAttachment BA \n \nSPP proposes revisions to Section 2.1.3.6 of Attachment BA to include \nlanguage specifying that the responsibility for cost of facilities required under the \nHDPS shall be as described in Sections V.F and V.G of Attachment J of the Tariff.78 \nThis revision is necessary to ensure that Network Upgrades identified through the \nHDPS are subject to the same LSHL cost responsibility as those identified under \nAttachments AQ and AX. \n \n75  \nProposed Tariff, Attachment AX, Section 3.0. \n76  \nProposed Tariff, Attachment AX, Addendum 2, Section 10.0. \n77  \nProposed Tariff, Attachment AX, Addendum 3, Section 10.0. \n78  \nProposed Tariff, Attachment BA, Section 2.1.3.6."},{"page":22,"startToken":8725,"endToken":8970,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 22 \n \nVII. \nEFFECTIVE DATE  \n \nFor all the reasons discussed in this transmittal letter, SPP requests that the \nCommission accept the proposed revisions to the Tariff to become effective February \n17, 2027, which is not more than 120 days after, and not fewer than 60 days after, the \nfiling date, consistent with the Commission’s regulations.79 This effective date provides \na reasonable implementation period that accommodates existing commercial \narrangements, as discussed in Section V. \nVIII. ADDITIONAL INFORMATION \nA. \nDocuments submitted with this filing: \nIn addition to this Transmittal Letter, SPP provides with this filing Clean \nand Redlined Tariff revisions under the Sixth Revised Volume No. 180;  \nExhibit No. SPP-0001: Affidavit of Natasha Henderson; and  \nExhibit No. SPP-0002: Affidavit of Don Frerking. \nB. \nService: \nSPP has electronically served a copy of this filing on all its Members, \nTransmission Customers and Market Participants. A complete copy of \nthis filing will be posted on the SPP website, www.spp.org, and is also \nbeing served on all affected state commissions. \nC. \nRequisite agreements: \nThere are none.  \n \n79  \n18 C.F.R. § 35.3(a)(1). \n80  \nCertain tariff records contained in this filing include language in italics indicating \nrevisions pending before the Commission in the following proceedings: ER6-2796-000 \nand ER27-559-000. In the event that revisions in any of these proceedings are not \naccepted by the Commission, SPP commits to submit a clean-up filing to remove the \nlanguage from the Tariff."},{"page":23,"startToken":8970,"endToken":9120,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 23 \n \nD. \nCommunications \nCorrespondence and communications with respect to this filing should \nbe sent to, and SPP requests the Secretary to include on the official \nservice list, the following:81 \nJustin A. Hinton \nSenior Attorney \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR 72223 \nTelephone: (501) 482-2468 \njhinton@spp.org \n \nMeredith Powell \nSenior Attorney \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR 72223 \nTelephone: (501) 482-2507 \nmpowell@spp.org \n \nTessie Kentner \nDirector & Associate General Counsel \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR 72223 \nTelephone: (501) 688-1782 \ntkentner@spp.org  \n \n \n81  \nPursuant to Commission Rule 101(e), 18 C.F.R. § 385.101(e), SPP requests waiver of \nRule 203(b)(3), 18 C.F.R. § 385.203(b)(3), in order to permit more than two persons \nto be included on the service list."},{"page":24,"startToken":9120,"endToken":9237,"text":"The Honorable Debbie-Anne A. Reese \nNovember 19, 2026 \nPage 24 \n \nIX. \nCONCLUSION \n \nFor the foregoing reasons, SPP respectfully requests that the Commission \naccept the Load Safe Harbor Limit Revisions, effective February 17, 2027. SPP further \nrequests that the Commission find that the Load Safe Harbor Limit Revisions are just \nand reasonable and not unduly discriminatory or preferential and resolve the cost \nrecovery directive in Paragraphs 59 through 65 of the Show Cause Order, such that no \nfurther action is required in Docket No. EL26-68-000 with respect to that directive. \n \nRespectfully submitted, \n \n/s/ Justin A. Hinton \n \n  \nJustin A. Hinton \nMeredith Powell \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR  72223-4936 \n  \nAttorneys for  \nSouthwest Power Pool, Inc."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":524,"startToken":0,"endToken":415},{"p":2,"at":524,"title":"I. SUMMARY OF FILING","method":"printed heading","endPage":3,"endAt":437,"startToken":415,"endToken":803},{"p":3,"at":437,"title":"II. BACKGROUND","method":"printed heading","endPage":3,"endAt":454,"startToken":803,"endToken":805},{"p":3,"at":454,"title":"A. The HILL Process","method":"printed heading","endPage":3,"endAt":1260,"startToken":805,"endToken":926},{"p":3,"at":1260,"title":"B. The Show Cause Order","method":"printed heading","endPage":3,"endAt":1781,"startToken":926,"endToken":1008},{"p":3,"at":1781,"title":"C. Abeyance","method":"printed heading","endPage":4,"endAt":405,"startToken":1008,"endToken":1137},{"p":4,"at":405,"title":"D. Stakeholder Process and Approval","method":"printed heading","endPage":6,"endAt":1323,"startToken":1137,"endToken":2139},{"p":6,"at":1323,"title":"III. CURRENT","method":"printed heading","endPage":6,"endAt":1438,"startToken":2139,"endToken":2153},{"p":6,"at":1438,"title":"A. SPP Transmission Service Process","method":"printed heading","endPage":7,"endAt":1826,"startToken":2153,"endToken":2577},{"p":7,"at":1826,"title":"B. Original Safe Harbor Provisions","method":"printed heading","endPage":9,"endAt":889,"startToken":2577,"endToken":3399},{"p":9,"at":889,"title":"IV. DESCRIPTION OF AND JUSTIFICATION FOR THE LOAD SAFE","method":"printed heading","endPage":9,"endAt":970,"startToken":3399,"endToken":3411},{"p":9,"at":970,"title":"A. Show Cause Order Requirements","method":"printed heading","endPage":9,"endAt":1831,"startToken":3411,"endToken":3537},{"p":9,"at":1831,"title":"B. Load Safe Harbor Limit Proposal","method":"printed heading","endPage":13,"endAt":1884,"startToken":3537,"endToken":5319},{"p":13,"at":1884,"title":"C. The Load Safe Harbor Limit Resolves the Show Cause Order’s Cost","method":"printed heading","endPage":14,"endAt":1742,"startToken":5319,"endToken":5698},{"p":14,"at":1742,"title":"D. Annual Load Safe Harbor Limit Annual Filing","method":"printed heading","endPage":15,"endAt":1186,"startToken":5698,"endToken":6061},{"p":15,"at":1186,"title":"E. Directives Addressed in Separate Filings","method":"printed heading","endPage":15,"endAt":1833,"startToken":6061,"endToken":6150},{"p":15,"at":1833,"title":"V. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS","method":"printed heading","endPage":16,"endAt":169,"startToken":6150,"endToken":6278},{"p":16,"at":169,"title":"VI. PROPOSED TARIFF CHANGES AND JUSTIFICATIONS","method":"printed heading","endPage":16,"endAt":218,"startToken":6278,"endToken":6284},{"p":16,"at":218,"title":"A. Part I, Section 1, Definitions","method":"printed heading","endPage":18,"endAt":719,"startToken":6284,"endToken":7260},{"p":18,"at":719,"title":"B. Part III Section 31.2","method":"printed heading","endPage":18,"endAt":1657,"startToken":7260,"endToken":7413},{"p":18,"at":1657,"title":"C. Attachment J","method":"printed heading","endPage":20,"endAt":494,"startToken":7413,"endToken":8075},{"p":20,"at":494,"title":"D. Attachment Y","method":"printed heading","endPage":20,"endAt":817,"startToken":8075,"endToken":8126},{"p":20,"at":817,"title":"E. Attachment AQ","method":"printed heading","endPage":20,"endAt":1665,"startToken":8126,"endToken":8251},{"p":20,"at":1665,"title":"F. Attachment AX","method":"printed heading","endPage":21,"endAt":1639,"startToken":8251,"endToken":8610},{"p":21,"at":1639,"title":"G. Attachment BA","method":"printed heading","endPage":22,"endAt":66,"startToken":8610,"endToken":8735},{"p":22,"at":66,"title":"VII. EFFECTIVE DATE","method":"printed heading","endPage":22,"endAt":552,"startToken":8735,"endToken":8807},{"p":22,"at":552,"title":"VIII. ADDITIONAL INFORMATION","method":"printed heading","endPage":22,"endAt":582,"startToken":8807,"endToken":8810},{"p":22,"at":582,"title":"A. Documents submitted with this filing:","method":"printed heading","endPage":22,"endAt":884,"startToken":8810,"endToken":8854},{"p":22,"at":884,"title":"B. Service:","method":"printed heading","endPage":22,"endAt":1161,"startToken":8854,"endToken":8900},{"p":22,"at":1161,"title":"C. Requisite agreements:","method":"printed heading","endPage":23,"endAt":66,"startToken":8900,"endToken":8980},{"p":23,"at":66,"title":"D. Communications","method":"printed heading","endPage":24,"endAt":66,"startToken":8980,"endToken":9130},{"p":24,"at":66,"title":"IX. CONCLUSION","method":"printed heading","endPage":24,"endAt":799,"startToken":9130,"endToken":9237}]}