{"document":{"slug":"rec-20261119-5278","title":"Motion for Leave to Answer and Answer of Southern Minnesota Municipal Power Agency et al. to the 11/09/2026 Motion for Leave to Answer filed by the…","issued":"2026-11-19","accession":"20261119-5278","docket":"ER27-25-000","group":"MISO Large Load Addition Resource Study (LARS)","filer":"Southern Minnesota Municipal Power AgencyWPPI Energy","kind":"answer","file":"sources/filings/text/20261119-5278_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261119-5278","tier":"record","sha256":"a0d14fe34419594a906674df6f55ca562f582bc0ea680e04c80d89695d4f5ca9","pages":12,"tokens":3066,"emptyPages":[],"textThemes":["cost","proximate","study","flex"]},"pages":[{"page":1,"startToken":0,"endToken":261,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nMidcontinent Independent System \nOperator, Inc. \nDocket No.  ER27-25-000 \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER \nOF MIDWEST TDUS \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(“FERC” or “Commission”) Rules of Practice and Procedure,1 Midwest TDUs2 \nrespectfully move for leave to answer and answer the November 9, 2026, Motion for \nLeave to Answer and Answer filed by the Midcontinent Independent System Operator, \nInc. (“MISO”).3 MISO’s Answer responds to, among other things, Midwest TDUs’ \nLimited Protest4 of MISO’s October 2, 2026 filing to revise its Open Access \nTransmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) to establish a \nLarge Load Addition Resource Study (“LARS”) process.5  \nMidwest TDUs previously raised two issues with MISO’s LARS proposal: (1) an \nimportant flaw in MISO’s proposed scope for LARS eligibility that requires correction, \nand (2) the need to ensure that all cost-shifting issues associated with LARS are fully \naddressed in future filing(s). MISO’s Answer resolves neither of these concerns.  \n \n1 18 C.F.R. §§ 385.212, 385.213. \n2 Midwest TDUs consist of Southern Minnesota Municipal Power Agency (“SMMPA”) and WPPI Energy \n(“WPPI”). \n3 Motion for Leave to Answer and Answer of the Midcontinent Independent System Operator, Inc. (Nov. 9, \n2026), eLibrary No. 20261109-5205 (“MISO Answer”). \n4 Motion to Intervene and Limited Protest of Southern Minnesota Municipal Power Agency and WPPI \nEnergy (Oct. 23, 2026), eLibrary No. 20261023-5191 (“Midwest TDUs Limited Protest”). \n5 MISO, Large Load Addition Resource Study Process (Oct. 2, 2026), eLibrary No. 20261002-5074 \n(“MISO Filing”)."},{"page":2,"startToken":261,"endToken":515,"text":"- 2 - \nFirst, Midwest TDUs and others previously protested MISO’s proposal to make \npaired generation and load within the same Local Resource Zone (“LRZ” or “Zone”) \neligible for the expedited LARS process. MISO’s Answer fails to address specific \nproblems raised about this scope. Instead, MISO’s Answer repeats vague assertions about \nidentifying optimized sets of Network Upgrades, which fails to demonstrate that the \nproposed scope for LARS eligibility is just, reasonable, and not unduly discriminatory in \nlight of the problems identified in the Commission’s Show Cause Order.6 \nSecond, MISO’s Answer doubles down on MISO’s contradictory clam that \ncritical cost shifting issues will be addressed in future filing(s), but that the Commission \nshould nevertheless accept LARS independently from those Tariff reforms essential to \nmaking LARS just, reasonable, and not unduly discriminatory or preferential. MISO’s \nargument rests of the false premise that the Commission must choose between timely \nimplementation of LARS or consideration of cost shifting in the context of LARS. Not \nso. The Commission should instead condition any acceptations of MISO’s LARS \nproposal on the Commission finding, in future proceeding(s), that MISO has satisfied its \nobligations with respect to the Show Cause Order’s discussion of cost allocation and \ntransparency as applied to LARS.  \nI. \nMOTION FOR LEAVE TO ANSWER \nThe Commission’s Rules of Practice and Procedure prohibit answers to answers \nunless otherwise authorized by the Commission.7 The Commission, however, has \n \n6 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).   \n7 18 C.F.R. § 385.213(a)(2)."},{"page":3,"startToken":515,"endToken":818,"text":"- 3 - \nauthority to waive this prohibition for good cause,8 and it has found good cause to waive \nthe general prohibition on answers to answers where, among other things, the answer \nwould assist the Commission in its decision-making process.9 Midwest TDUs’ Answer to \nMISO’s Answer will aid the Commission’s understanding of important issues regarding \nthe proposed scope of eligibility for LARS as well as the relationship between MISO’s \nfiling and the critical concerns about cost shifting identified in the Commission’s Show \nCause Order.  \nII. \nANSWER \nA. \nMISO’s Answer fails to justify its proposed geographic scope for \npaired generation and load eligible for LARS. \nAs MISO summarizes in its Answer, “[m]any of the protesters,” including \nMidwest TDUs, challenged MISO’s proposal to allow paired generation and load located \nwithin the same LRZ to be eligible for LARS.10 MISO acknowledges that its proposed \nscope for LARS differs from the Commission-suggested definition of “electrically \nproximate” in the Show Cause Order, but defends its filing by arguing that its proposal \n“provide[s] maximum flexibility for the generation/load pairs.”11 \nThe Commission’s mandate in the Show Cause Order was not to ensure \n“maximum flexibility” to a subset of load and generation that desires to interconnect to \n \n8 Id. § 385.101(e). \n9 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, P 24 (2025) (accepting answers to \nanswers “because they have provided information that assisted us in our decision-making process”). \n10 MISO Answer at 9. \n11 Id. See also id. at 9-10 (“In developing LARS, MISO concluded that defining a maximum distance based \non substations would impede the flexibility of large loads and Interconnection Customers to site their \nprojects in a way that made the most sense for the parties.”), id. at 12 (describing its proposal as “providing \nmaximum flexibility for participants”)."},{"page":4,"startToken":818,"endToken":1134,"text":"- 4 - \nthe transmission system on an expedited basis. Rather, it was to ensure just, reasonable, \nand not unduly discriminatory Commission-jurisdictional rates for all customers, \nparticularly considering the challenges associated with a significant increase in new large \nload interconnections. Specifically, the Commission found that “the status quo may result \nin inefficient and unnecessary development of infrastructure, which leads to \nunnecessarily higher network upgrade costs that may result in unjust and unreasonable \nrates,”12 whereas “electrically proximate” large load and generation may “potentially \nreduc[e] the need for Network Upgrades, which can accelerate the generator \ninterconnection process.”13 Thus, the key to addressing the Show Cause Order’s concern \nis targeting those paired generation and large loads that are sufficiently “electrically \nproximate” to reduce the need for Network Upgrades.14 \nMISO’s Answer fails to show that its proposed zonal approach satisfies the Show \nCause Order’s directive. MISO offers generic statements (with no supporting data or \nexamples) about how studying generation and load together might reduce the need for \nNetwork Upgrades,15 but none of those statements support MISO’s specific proposal to \nallow pairs within the same Zone. In fact, MISO concedes that “adjacent large loads and \nGenerating Facilities may produce the most significant Network Upgrade \n \n12 Show Cause Order P 114.  \n13 Id. P 113.  \n14 For example, the Show Cause Order explains that electrically proximate load and generation have unique \ncharacteristics; “because the generating facility and load are located so closely on the transmission system, \nif the generating facility’s output matches the load’s demand, then the transmission provider would need to \nstudy only the local impacts because the impact on the transmission system of the combination of the \ngenerating facility and the load, with the exception of the transmission facilities between the two, will be \neffectively the same as if they were located at the same substation.” Id. P 113 n.256. \n15 See MISO Answer at 10-11."},{"page":5,"startToken":1134,"endToken":1385,"text":"- 5 - \noptimization.”16 Although MISO claims that more distant pairs may also result in some \nreduction in Network Upgrades (at least over time in the aggregate), it offers no specific \nsupport for a zonal scope.  \nMISO claims that the Commission’s suggested definition of electrically \nproximate (i.e., no more than two substations apart) “would be arbitrary” in the MISO \ncontext,17 but it fails to offer any reasoned basis for an alternative zonal approach. MISO \ndoes not explain why paired generation and load that cross a zonal boundary (even if \nelectrically proximate) will likely require more costly Network Upgrades compared to a \npair anywhere within a Zone (even those not electrically proximate). Nor does MISO \nexplain why paired generation and load hundreds of miles and multiple states apart are \nmore likely to require fewer Network Upgrades just because they are in the same Zone.  \nMISO’s critiques of the Commission’s suggested scope also fail to justify its \nalternative approach. MISO claims that in some instances “two substations could still be \nhundreds of miles apart,”18 but that concern fails to justify a zonal approach that still \nallows pairs of generation and load that are not only hundreds of miles apart but also \nelectrically distant.  \nMISO also claims that in areas of MISO where several substations are in close \nproximity, a two-substation-limit could result in “geographically proximate Generating \nFacility and large load [having] very limited options for interconnection” under LARS.19 \n \n16 Id. at 11. \n17 Id. at 10.  \n18 Id. \n19 Id."},{"page":6,"startToken":1385,"endToken":1705,"text":"- 6 - \nMISO does not explain why this is a problem or contrary to MISO’s stated intent to \ndevelop a “narrowly scoped”20 LARS process. Under MISO’s own proposal, only certain \npairs of generation and large load have access to the expedited LARS process to begin \nwith, and the concern expressed in the Commission’s Show Cause Order was about the \ntimely interconnection of paired generation and load that are uniquely situated to require \nless significant and costly Network Upgrades. MISO has not demonstrated that it is just, \nreasonable, and not unduly discriminatory to extend the expedited treatment provided by \nLARS to pairs that lack these critical characteristics.   \nIn addition, MISO’s Answer fails to address, much less rebut, several key \nproblems with its proposed scope for LARS. Midwest TDUs pointed out that MISO’s \nproposed scope is not only overinclusive (i.e., covering generation/load pairs that are not \nelectrically proximate), but also underinclusive (i.e., excluding pairs that may be in \nseparate Zones but are nevertheless electrically proximate).21 MISO offers no \njustification for excluding electrically proximate loads that happen to fall in different \nZones. MISO also fails to explain how its proposed zonal scope will produce the \noptimized results MISO claims, particularly given the numerous elements of LARS that \nbroaden its scope and require additional studies.22 \n \n20 Id. at 13. \n21 See Midwest TDUs Limited Protest at 5-6.  \n22 See id. at 6-7 (explaining how MISO’s LARS proposal (1) allows generation at multiple Points of \nInterconnection for a single LARS Associated Load, with separate Applications for each Point of \nInterconnection; (2) requires separate, serial studies, even for multiple pairs of generation and load in the \nsame Zone and even for multiple Points of Interconnection for the same load; (3) permits generation to \nreceive NRIS equal to 150% of the LARS Associated Load’s peak demand; and (4) permits retention of \nNRIS for up to a year without paired LARS associated Load)."},{"page":7,"startToken":1705,"endToken":2053,"text":"- 7 - \nFinally, MISO is wrong to suggest that there is no downside to broadening the \nscope to LARS eligibility.23 MISO proposes to limit the number of generation/load pairs \nthat may be studied in each LARS Study Period.24 As a result, the inclusion in LARS of \npairs of generation and load that do not reduce the need for Network Upgrades (e.g., \nthose not electrically proximate) risks crowding out those pairs that do create greater \nefficiencies (e.g., those that are sufficiently electrically proximate such that their impact \non the transmission system is the same as if they were located at the same substation). An \noverbroad scope thus undermines the benefits LARS is intended to achieve. Moreover, to \nbe just, reasonable, and not unduly discriminatory, an expedited interconnection process \nmust be “narrowly tailored to the problem being addressed.”25 Here, MISO has failed to \nshow that a zonal scope for LARS eligibility is responsive to the problem identified in the \nCommission’s Show Cause Order, and MISO has not meet its burden of showing that this \nscope is just, reasonable, and not unduly discriminatory.  \nB. \nMISO fails to show that the Commission can simply ignore cost \nshifting concerns in this proceeding.  \nMidwest TDUs and numerous other participants also identified the shortcoming \nof MISO’s failure to address the Show Cause Order’s cost shifting concerns in its LARS \nproposal. MISO’s Answer reiterates MISO’s plan to address the Show Cause Order’s \n \n23 See MISO Answer at 12 (“It should not be objectionable that LARS provides efficiency benefits in more \nsituations than the smaller subset contemplated by the Show Cause Order.”). \n24 See id. at 7 (“LARS is limited in scope both by its strict eligibility requirements and because only thirty \ngeneration and load pairs may be studied each year.”). \n25 Midcontinent Indep. Sys. Operator, Inc., 194 FERC ¶ 61,050, P 55 (2026) (“In evaluating whether \nproposals by RTOs/ISOs to implement expedited interconnection study processes to address urgent \nresource adequacy needs are reasonable, the Commission has considered factors including whether those \nproposals were narrowly tailored to the problem being addressed.”)."},{"page":8,"startToken":2053,"endToken":2348,"text":"- 8 - \ndirective regarding a pro forma cost recovery agreement and transparency in future \nfilings, but MISO nevertheless argues that its LARS proposal should be accepted without \nany Commission consideration of these critical upcoming reforms.26 MISO’s Answer \nfurther underscores the need for the Commission to condition any acceptations of \nMISO’s LARS proposal on the Commission finding, in future proceeding(s), that MISO \nhas satisfied its obligations with respect to the Show Cause Order’s discussion of cost \nallocation and transparency as applied to LARS. \nMISO’s Answer first points to language in its proposed Tariff it states “assigns \nthe costs of [non-GIP local Transmission Facilities] to the LARS Associated \nTransmission Customer even if the large load is ultimately not built.”27 But in the very \nnext sentence, MISO concedes that the “enforcement mechanism for the obligations of \nTransmission Customers seeking Transmission Service to serve Large Loads” will be \npart of future filings—not the Tariff revisions before the Commission here—and that \nMISO will “integrate” those future reforms “into the LARS process” once those reforms \nare accepted.28  \nAs a result, MISO’s statement that “the LARS proposal includes a Tariff \nmechanism for identifying and assigning any necessary transmission Network Upgrades \n \n26 MISO Answer at 14. After MISO filed its Answer, it submitted two filings on November 16, 2026, in \nresponse to the Commission’s Show Cause Order. In Docket No. ER27-526, MISO filed its “omnibus” \nresponse to the Show Cause Order, which includes (among other things) MISO’s response to the Show \nCause Order’s discussion of transparency requirements and a pro forma cost recovery agreement. In \nDocket No. ER27-527, MISO submitted its Grid Responsive Integration Transmission Service (“GRITS”) \nfiling, which addresses permanent firm and non-firm contract demand-based transmission service options \nfor large loads.  \n27 Id. at 15.  \n28 Id."},{"page":9,"startToken":2348,"endToken":2614,"text":"- 9 - \nassociated with the generation/load pair to the Transmission Customer or the \nInterconnection Customer”29 appears to describe, at best, MISO’s future intent. But \nnothing in the Tariff revisions before the Commission in this proceeding appears to \nactually implement a mechanism that holds the LARS Associated Transmission \nCustomer responsible for identified upgrades even if the LARS Associated Load does not \ncommence service at the expected amount. As a result, the proposed Tariff provisions \nbefore the Commission are incomplete and wrongly suggest a level of protection against \ncost shifting that does not (yet) exist. Conditioning any acceptance of LARS, as described \nabove and in Midwest TDUs’ Limited Protest, would ensure that this protection of other \ncustomers will function as intended.    \nMISO next attempts to dismiss cost shifting concerns by arguing that its LARS \nfiling “is not creating a new cost-allocation problem.”30 That is not the relevant legal \nstandard. Not only does MISO have the burden to demonstrate that its revised Tariff \nlanguage is just, reasonable, and not unduly discriminatory,31 but here MISO is also \nresponding to a Commission Show Cause Order that preliminarily found its existing \nTariff to be unjust and unreasonable.32 MISO has not shown that other customers will be \nprotected against cost shifts associated with the transmission infrastructure built to \ninterconnect LARS projects on an expedited basis. Even assuming this cost shifting risk \nis not new to LARS, that is little comfort to ratepayers that face cost shifting risks under \n \n29 Id. at 5.  \n30 Id. at 16.  \n31 16 U.S.C. § 824d(e).  \n32 Show Cause Order P 113."},{"page":10,"startToken":2614,"endToken":2878,"text":"- 10 - \nunjust and unreasonable Tariff provisions applied to costs incurred to serve projects \ninterconnecting pursuant to a new LARS process.  \nRelatedly, MISO also argues that concerns about cost shifting should not delay \nthe large load-related reforms included in its LARS proposal. This presents the \nCommission with a false choice between protecting against cost shifting and delaying \nimplementation of LARS. Midwest TDUs do not seek to delay LARS, and the \nconditional acceptance we request allows the Commission to facilitate timely \nimplementation of LARS while still fulfilling its statutory mandate to ensure just, \nreasonable, and not unduly discriminatory rates.33  \nFinally, MISO states that “there is nothing in the LARS proposal that would \nprevent a state regulator from allocating costs of a BRP or Other project more granularly \nto a specific retail customer.”34 While true, this statement misses the point. The \nCommission’s Show Cause Order specifically acknowledges the concern that state \nregulators cannot protect all wholesale transmission customers from cost shifting that \noccurs through Commission-jurisdictional transmission rates.35 This Commission is \nstatutorily obligated to address cost shifting that occurs through rates subject to its \njurisdiction. It can do so with respect to costs incurred for LARS projects, while still \nallowing timely implementation of LARS, through the conditional acceptance described \nherein.  \n \n33 Similarly, Google argues that the Commission could “accept and suspend the proposal, until it can be \nevaluated alongside any necessary customer protection measures, including the contemplated pro forma \ncost shifting agreement.” Limited Protest of Google at 3 (Oct. 23, 2026), eLibrary No. 20261023-5177.  \n34 MISO Answer at 18. \n35 Show Cause Order P 79."},{"page":11,"startToken":2878,"endToken":3000,"text":"- 11 - \nCONCLUSION \nFor the reasons discussed above and in Midwest TDUs’ Limited Protest, the \nCommission should (1) reject MISO’s proposed geographic scope for paired generation \nand load eligible for LARS and direct MISO to revise its Tariff language consistent with \nthe Show Cause Order; and (2) condition any acceptance on MISO’s filing in this \nproceeding on the Commission finding, in future proceeding(s), that MISO has satisfied \nits obligations with respect to the Show Cause Order’s discussion of cost allocation and \ntransparency as applied to LARS.   \n \nRespectfully submitted, \n /s/ Cynthia S. Bogorad \nCynthia S. Bogorad \nJeffrey M. Bayne \nAttorneys for Midwest TDUs \nLaw Offices of: \nSpiegel & McDiarmid LLP \n1818 N Street, NW \n8th Floor \nWashington, DC 20036 \n(202) 879-4000 \nNovember 19, 2026"},{"page":12,"startToken":3000,"endToken":3066,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing document to be served \nupon each person designated on the official service list compiled by the Secretary in this \nproceeding. \nDated on this 19th day of November, 2026. \n /s/ Jeffrey M. Bayne \nJeffrey M. Bayne \nLaw Offices of: \n \nSpiegel & McDiarmid LLP \n1818 N Street, NW \n8th Floor \nWashington, DC 20036 \n(202) 879-4000"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1379,"startToken":0,"endToken":464},{"p":2,"at":1379,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":546,"startToken":464,"endToken":599},{"p":3,"at":546,"title":"II. ANSWER","method":"printed heading","endPage":3,"endAt":559,"startToken":599,"endToken":601},{"p":3,"at":559,"title":"A. MISO’s Answer fails to justify its proposed geographic scope for","method":"printed heading","endPage":7,"endAt":1130,"startToken":601,"endToken":1890},{"p":7,"at":1130,"title":"B. MISO fails to show that the Commission can simply ignore cost","method":"printed heading","endPage":11,"endAt":8,"startToken":1890,"endToken":2879},{"p":11,"at":8,"title":"CONCLUSION","method":"printed heading","endPage":12,"endAt":0,"startToken":2879,"endToken":3000},{"p":12,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":12,"endAt":405,"startToken":3000,"endToken":3066}]}