# Sec. 2101. Transmission permitting

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2101)

## Summary

Overhauls FERC's backstop siting authority under Federal Power Act section 216. ([p. 185, line 11 to p. 185, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185)) FERC must issue a construction or modification permit for an interstate line of 230 kilovolts or more, or an advanced-conductor line at a voltage FERC sets, when it makes the required findings. ([p. 189, line 17 to p. 189, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189)) The line no longer has to sit in a national interest corridor designated by the Energy Department. ([p. 199, line 11 to p. 199, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199)) The state's clock for deciding now starts on the date the application is filed with the state. ([p. 189, line 2 to p. 189, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189))

FERC must find the line is in the public interest, protects or benefits consumers, and improves reliability. ([p. 189, line 14 to p. 189, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189)) For lines of 345 kilovolts or more the developer may file at FERC at the same time as at the state. ([p. 191, line 20 to p. 191, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=191)) FERC must take landowner input, consider the state record, and give a 45-day comment period. ([p. 188, line 11 to p. 188, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188))

Costs go only to customers who benefit, in line with cost causation, and customers with no or trivial benefit cannot be charged involuntarily. ([p. 194, line 13 to p. 194, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194)) Clean Water Act section 401 certifications and other state approvals under federal law become 'Federal authorizations' coordinated by FERC as lead agency (Interior for offshore), with challenges heard in the courts of appeals. ([p. 195, line 10 to p. 195, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195)) ERCOT is excluded. ([p. 198, line 17 to p. 198, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198))

## Key points

- No more national interest corridor prerequisite for FERC backstop siting ([p. 199, line 15 to p. 199, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199))
- The state's clock starts on the date the application is filed with the state ([p. 189, line 2 to p. 189, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189))
- 230 kV threshold; simultaneous state and FERC filing at 345 kV and above ([p. 189, line 17 to p. 189, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189))
- Cost allocation limited to beneficiaries; no involuntary charges for trivial benefits ([p. 194, line 13 to p. 194, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194))
- State 401 certifications for transmission folded into FERC-led federal authorization schedule ([p. 195, line 10 to p. 195, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195))
- ERCOT excluded; public power and small co-ops only if they opt in ([p. 198, line 24 to p. 199, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198))

## What others say it would do

Outside readings, quoted from their sources. These are claims about effects, not findings of this tracker.

- **Bommarito Consulting** (Think tanks; concerns): Landowners get a consultation duty but no obligation on FERC to change a route, and condemnation shifts to federal rules.
  > FERC must “take into account landowner input,” but nothing requires it to accept a requested route change.
  [Bommarito Consulting, 2026-09-30](https://bommaritollc.com/insights/senate-permitting-bill-2026/). On the bill text at [p. 187, line 17 to p. 187, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187).
- **Grid Strategies** (Think tanks; supports): The transmission title tackles the planning, permitting and cost-allocation barriers together.
  > It addresses the ‘3Ps’ of transmission barriers: planning, permitting, and paying, with targeted improvements in each area.
  [pv magazine USA, 2026-10-01](http://pv-magazine-usa.com/2026/10/01/senate-introduces-landmark-permitting-bill-as-industry-data-and-environmental-groups-clash-over-reforms/).
- **Grid Strategies** (Think tanks; supports): More transmission and better access to low-cost generation would likely lower consumer bills over time.
  > It is very likely that this bill, if passed, would reduce consumer utility bills over time as the transmission system expands and access to low-cost generation improves.
  [pv magazine USA, 2026-10-01](http://pv-magazine-usa.com/2026/10/01/senate-introduces-landmark-permitting-bill-as-industry-data-and-environmental-groups-clash-over-reforms/).
- **Grid Strategies** (Think tanks; supports): The FERC backstop would work partly as a threat that pushes developers and states toward approvable routes.
  > the threat of the FERC decision leads to changes in routes or configuration of the proposals to get to yes at the state and local level.
  [The Hill, 2026-10-01](https://thehill.com/policy/energy-environment/6124792-bipartisan-permitting-reform-data-centers-energy-projects/). On the bill text at [p. 188, line 14 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).
- **McGuireWoods** (Lawyers and legal scholars; explains): FERC-permitted lines would carry a cost-causation guardrail: non-beneficiaries cannot be involuntarily charged.
  > Customers who receive no benefit, or only a trivial one, could not be involuntarily charged.
  [McGuireWoods, 2026-10-02](https://www.mcguirewoods.com/client-resources/alerts/2026/10/bipartisan-american-affordability-and-jobs-act-of-2026-proposes-sweeping-reform-for-energy-and-infrastructure-projects/). On the bill text at [p. 194, line 9 to p. 194, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194).
- **Niskanen Center** (Think tanks; supports): The backstop would work like FERC's gas pipeline approvals and give stalled interstate lines a path.
  > This is much closer to how FERC approves natural gas pipelines and would provide a solution for stalled interstate projects that currently have no viable path forward.
  [Niskanen Center, 2026-10-02](https://www.niskanencenter.org/the-bipartisan-american-affordability-and-jobs-act-of-2026-4-ways-the-new-permitting-package-gets-transmission-policy-right/). On the bill text at [p. 188, line 14 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).
- **Third Way** (Think tanks; supports): The federal backstop would make the federal government the decision-maker when states cannot agree on long-distance lines.
  > If states cannot agree where to build essential long-distance transmission lines, BAAJA would make the federal government the backstop decision-maker.
  [Third Way, 2026-10-02](https://www.thirdway.org/blog/one-baaja-blast-please). On the bill text at [p. 188, line 14 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).
- **Womble Bond Dickinson** (Lawyers and legal scholars; mixed): Broader federal siting helps transmission developers, but federal siting still requires meeting the statutory triggers tied to state action or inaction.
  > These measures could improve development prospects, although access to federal siting would still depend on satisfying the applicable statutory conditions.
  [Womble Bond Dickinson, 2026-10-02](https://www.womblebonddickinson.com/us/node/21451). On the bill text at [p. 188, line 14 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).
- **Oklahoma Gas & Electric** (Industry; opposes): The utility says the state referral process in 2104 would put local planning decisions, which state commissions have overseen, under federal investigation and federal penalties.
  > Although a referral would be initiated by a state, the result would be to place local planning decisions, which have historically been overseen by state commissions, under federal investigation and federal penalties.
  [Energy and Policy Institute, 2026-10-20](https://energyandpolicy.org/oge-baaja-transmission-reforms-lobbying/). On the bill text at [p. 220, line 6 to p. 220, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=220).
- **Earthjustice** (Environmental groups; supports): The guide says the stronger FERC backstop siting authority could help resolve conflicts and delays from state permitting of large multi-state transmission lines.
  > Strengthens the Federal Energy Regulatory Commission’s (FERC) backstop permitting authority, which could help resolve conflicts and delays arising from state permitting processes
  [Earthjustice, 2026-10-26](https://earthjustice.org/feature/bipartisan-american-affordability-and-jobs-act-2026-impact-guide). On the bill text at [p. 188, line 13 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).
- **Columbia University Center on Global Energy Policy** (Think tanks; explains): CGEP's replay of past transmission cases finds the transmission archetype saves 64 months up to the federal decision.
  > The bill reduces the timeline to the federal decision by 64 months in the archetype, compared with 60.7 months in the largest replay (Bordertown to California, a 10-mile, 120 kV line).
  [Columbia University Center on Global Energy Policy, 2026-10-21](https://www.energypolicy.columbia.edu/wp-content/uploads/2026/10/baaja-timelines-v6.html). On the bill text at [p. 48, line 17 to p. 48, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=48).
- **Columbia University Center on Global Energy Policy** (Think tanks; explains): State siting and the FERC backstop account for most of the transmission archetype's 96-month timeline, and the replays exclude them.
  > The replays therefore exclude state siting and the FERC backstop permit (Sec. 2101), which account for most of the transmission archetype's 96-month timeline.
  [Columbia University Center on Global Energy Policy, 2026-10-21](https://www.energypolicy.columbia.edu/wp-content/uploads/2026/10/baaja-timelines-v6.html). On the bill text at [p. 188, line 13 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).
- **The Abundant Future** (Commentators; supports): Brown reads BAAJA as letting federal regulators approve interstate lines after states have a year to act.
  > BAAJA lets federal regulators approve interstate transmission lines after states have had a year to act.
  [The Abundant Future, 2026-10-05](https://theabundantfuture.substack.com/p/the-senate-permitting-deal-is-abundance). On the bill text at [p. 188, line 13 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188).

## Selected statutory quotes

> the Commission shall, after notice and an opportunity for hearing, including a public comment period of at least 45 days, issue one or more permits to individual or joint applicants for the construction or modification of electric transmission facilities necessary in the national interest

[p. 188, line 10 to p. 188, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188)

FERC 'shall' issue the permit once it makes the findings.

> Customers that receive no benefit, or benefits that are trivial in relation to the costs sought to be allocated, from electric transmission facilities constructed or modified under this section shall not be involuntarily allocated any of the costs of those transmission facilities

[p. 194, line 9 to p. 194, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194)

Customers with no or trivial benefit cannot be charged.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

Section 216 (2005, amended 2021) says FERC 'may' site lines, and only inside National Interest Electric Transmission Corridors designated by the Energy Department. FERC can step in where a state lacks siting authority, has not decided within 1 year, has denied the application, or has set conditions that make the line uneconomic. Those grounds stay. The cost allocation and lead-agency changes are new.

### EPRA 2024 (reported S. 4753)

EPRA 2024 (sec. 401) made the same core change: FERC backstop siting without corridor designation, FERC action once a state has had 1 year, beneficiary-pays cost allocation and the trivial-benefit protection.

Differences: EPRA said FERC 'may' issue a permit after a 60-day comment period and set the floor at 100 kilovolts. This bill says 'shall' after 45 days and sets the floor at 230 kilovolts. It drops EPRA's findings that a line 'significantly reduce transmission congestion' and be 'consistent with sound national energy policy'. It adds simultaneous state and FERC filing at 345 kilovolts, the state record, an opt-in for public power and small co-ops, FERC-led coordination of state water certifications, and review of all related permits in the courts of appeals.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act, which amended only NEPA.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 185, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 1)

(a) DEFINITIONS.—Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (a) and inserting the following:

[p. 185, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 1)

“(a) DEFINITIONS.—In this section:

[p. 185, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 2)

“(1) AFFECTED LANDOWNER.—The term ‘affected landowner’ includes each owner of a property interest in affected property, including—

[p. 185, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 3)

“(A) the Federal Government;

[p. 185, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 3)

“(B) a State or local government; and

[p. 185, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 3)

“(C) each owner noted in the most recent county or city tax record as receiving the relevant tax notice with respect to that interest.

[p. 185, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=185) (indent level 2)

“(2) AFFECTED PROPERTY.—The term ‘affected property’ means any land or other property—

[p. 186, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 3)

“(A) that is or will be crossed by the energy transmission facility proposed to be constructed or modified under the applicable permit under subsection (b);

[p. 186, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 3)

“(B) that is or will be used as a facility site with respect to the energy transmission facility proposed to be constructed or modified under the applicable permit under subsection (b);

[p. 186, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 3)

“(C) that abuts any boundary of an existing right-of-way or other facility site that—

[p. 186, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 4)

“(i) is owned by an electric utility; and

[p. 186, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 4)

“(ii) is located not more than 500 feet from the energy transmission facility to be constructed or modified under the applicable permit under subsection (b);

[p. 186, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 3)

“(D) that abuts the boundary of a proposed facility site for the energy transmission facility to be constructed or modified under the applicable permit under subsection (b);

[p. 186, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=186) (indent level 3)

“(E) that is crossed by, or abuts any boundary of, an existing or proposed right-of-way that—

[p. 187, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 4)

“(i) will be used for the energy transmission facility to be constructed or modified under the applicable permit under subsection (b); and

[p. 187, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 4)

“(ii) is located not more than 500 feet from the proposed location of that energy transmission facility; or

[p. 187, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 3)

“(F) on which a residence is located not more than 500 feet from the boundary of any right-of-way for that energy transmission facility.

[p. 187, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 2)

“(3) COMMISSION.—The term ‘Commission’ means the Federal Energy Regulatory Commission.

[p. 187, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 2)

“(4) IMPROVED RELIABILITY.—The term ‘improved reliability’ has the meaning given the term in section 225(a).

[p. 187, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 2)

“(5) LANDOWNER INPUT.—The term ‘landowner input’ means input received—

[p. 187, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 3)

“(A) by the Commission;

[p. 187, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 3)

“(B) from affected landowners, such as farmers and ranchers, in the path of the proposed construction or modification of an electric transmission facility; and

[p. 187, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=187) (indent level 3)

“(C) pursuant to notification provided to, and consultation with, those affected landowners, farmers, and ranchers by the Commission.

[p. 188, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 2)

“(6) SECRETARY.—The term ‘Secretary’ means the Secretary of Energy.”.

[p. 188, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 1)

(b) CONSTRUCTION PERMIT.—Section 216(b) of the Federal Power Act (16 U.S.C. 824p(b)) is amended—

[p. 188, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 2)

(1) in the matter preceding paragraph (1), by striking “Except” and all that follows through “finds that” and inserting “Except as provided in subsections (d)(1) and (i), the Commission shall, after notice and an opportunity for hearing, including a public comment period of at least 45 days, issue one or more permits to individual or joint applicants for the construction or modification of electric transmission facilities necessary in the national interest if the Commission finds that”;

[p. 188, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 2)

(2) in paragraph (1)—

[p. 188, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 3)

(A) in subparagraph (A)(i), by inserting “or modification” after “siting”; and

[p. 188, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 3)

(B) in subparagraph (C)—

[p. 188, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 4)

(i) in the matter preceding clause (i), by inserting “or modification” after “siting”; and

[p. 188, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=188) (indent level 4)

(ii) in clause (i), by striking “the later of” in the matter preceding subclause (I) and all that follows through the semicolon at the end of subclause (II) and inserting “the date on which the application was filed with the State commission or other entity;”; and

[p. 189, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189) (indent level 2)

(3) by striking paragraphs (2) through (6) and inserting the following:

[p. 189, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189) (indent level 2)

“(2) the proposed facilities will be used for the transmission of electric energy in interstate commerce (including transmission from the outer Continental Shelf to a State) or foreign commerce;

[p. 189, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189) (indent level 2)

“(3) the proposed construction or modification is consistent with the public interest;

[p. 189, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189) (indent level 2)

“(4) the proposed construction or modification will protect or benefit consumers and provide improved reliability;

[p. 189, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189) (indent level 2)

“(5) the electric transmission facilities are capable of transmitting electric energy at a voltage of not less than 230 kilovolts or, in the case of facilities that include advanced transmission conductors (including superconductors), as defined by the Commission, voltages determined to be appropriate by the Commission; and

[p. 189, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=189) (indent level 2)

“(6) if applicable, the proposed modification (including reconductoring) will maximize, to the extent reasonable and economical, the transmission capabilities of existing towers, structures, or rights-of-way.”.

[p. 190, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=190) (indent level 1)

(c) STATE SITING AND CONSULTATION.—Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (d) and inserting the following:

[p. 190, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=190) (indent level 1)

“(d) STATE SITING AND CONSULTATION.—

[p. 190, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=190) (indent level 2)

“(1) PRESERVATION OF STATE SITING AUTHORITY.— The Commission shall have no authority to issue a permit under subsection (b) for the construction or modification of an electric transmission facility within a State except as provided in paragraph (1) of that subsection.

[p. 190, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=190) (indent level 2)

“(2) CONSULTATION.—In any proceeding before the Commission under subsection (b), the Commission shall afford each State in which a transmission facility covered by the permit is or will be located, each affected Federal agency and Indian Tribe, private property owners, and other interested persons, a reasonable opportunity to present their views and recommendations with respect to the need for and impact of a facility covered by the permit.

[p. 190, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=190) (indent level 2)

“(3) LANDOWNER INPUT.—In authorizing the construction or modification of an electric transmission facility under subsection (b), the Commission shall take into account landowner input.

[p. 191, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=191) (indent level 2)

“(4) STATE RECORD.—In any proceeding before the Commission under subsection (b), each State in which a transmission facility covered by the permit is or will be located may file with the Commission, and the Commission shall consider, any part of the State record, if applicable, that the State finds to be relevant to the determination of the Commission.

[p. 191, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=191) (indent level 2)

“(5) PRE-FILING PROCESSES.—Any Commission-related pre-filing processes relating to an application submitted under subsection (c) may commence before, but shall commence no later than, an application is submitted to the applicable State commission or other entity that has authority to approve the siting of the applicable facility.

[p. 191, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=191) (indent level 2)

“(6) SIMULTANEOUS PROCESSING.—In the case of transmission facilities that are capable of transmitting electric energy at a voltage of not less than 345 kilovolts, an application under subsection (c) shall be submitted to the Commission simultaneously with, or any time after, the submission of an application to the applicable State commission or other entity that has authority to approve the siting of the applicable facility, and the Commission shall commence a proceeding under subsection (b).

[p. 192, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=192) (indent level 2)

“(7) LIMITATIONS.—Simultaneous processing under paragraph (6) is subject to the condition that the Commission shall not issue a permit under subsection (b) unless the Commission first makes a finding described in subparagraph (A), (B), or (C) of subsection (b)(1) with respect to the applicable electric transmission facility.”.

[p. 192, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=192) (indent level 1)

(d) RIGHTS-OF-WAY.—Section 216(e)(3) of the Federal Power Act (16 U.S.C. 824p(e)(3)) is amended by striking “shall conform” and all that follows through the period at the end and inserting “shall be in accordance with rule 71.1 of the Federal Rules of Civil Procedure.”.

[p. 192, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=192) (indent level 1)

(e) COST ALLOCATION.—

[p. 192, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=192) (indent level 2)

(1) IN GENERAL.—Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (f) and inserting the following:

[p. 192, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=192) (indent level 1)

“(f) COST ALLOCATION.—

[p. 192, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=192) (indent level 2)

“(1) TRANSMISSION TARIFFS.—For the purposes of this section and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities that the Commission finds to be consistent with the findings under paragraphs (2) through (5) and, if applicable, (6) of subsection (b) shall file a tariff or tariff revision with the Commission pursuant to section 205 and the regulations of the Commission allocating the costs of the new or modified transmission facilities.

[p. 193, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=193) (indent level 2)

“(2) EXCEPTION.—In the case of an exempt transmitting utility (as defined in section 225(a)) that owns, controls, or operates electric transmission facilities described in paragraph (1), the Commission, notwithstanding section 211A(c), shall require the exempt transmitting utility to provide transmission services over such facilities pursuant to section 211A and the regulations of the Commission allocating the costs of the new or modified transmission facilities.

[p. 193, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=193) (indent level 2)

“(3) TRANSMISSION BENEFITS.—The Commission shall require that tariffs or tariff revisions filed under this section are just and reasonable and allocate the costs of providing service to customers that benefit, in accordance with the cost-causation principle and at least roughly commensurate with the benefits, including through—

[p. 193, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=193) (indent level 3)

“(A) improved reliability;

[p. 193, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=193) (indent level 3)

“(B) reduced congestion;

[p. 193, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=193) (indent level 3)

“(C) reduced power losses;

[p. 194, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194) (indent level 3)

“(D) greater carrying capacity that delivers improved reliability or reductions in the cost of delivered power;

[p. 194, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194) (indent level 3)

“(E) reduced operating reserve requirements; and

[p. 194, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194) (indent level 3)

“(F) improved access to generation that achieves reductions in the cost of delivered power.

[p. 194, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194) (indent level 2)

“(4) RATEPAYER PROTECTION.—Customers that receive no benefit, or benefits that are trivial in relation to the costs sought to be allocated, from electric transmission facilities constructed or modified under this section shall not be involuntarily allocated any of the costs of those transmission facilities, provided, however, that nothing in this section shall prevent a transmitting utility from recovering such costs through voluntary agreement with its customers.”.

[p. 194, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=194) (indent level 2)

(2) SAVINGS PROVISION.—If the Federal Energy Regulatory Commission finds that the considerations under paragraphs (1) through (5) and, if applicable, (6) of section 216 of the Federal Power Act (16 U.S.C. 824p) (as amended by subsection (b)) are met, nothing in this section or the amendments made by this section shall be construed to exclude transmission facilities located on the outer Continental Shelf from being eligible for cost allocation established under subsection (f)(1) of that section (as amended by paragraph (1)).

[p. 195, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195) (indent level 1)

(f) COORDINATION OF FEDERAL AUTHORIZATIONS FOR TRANSMISSION FACILITIES.—Section 216(h) of the Federal Power Act (16 U.S.C. 824p(h)) is amended—

[p. 195, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195) (indent level 2)

(1) in paragraph (1), by adding at the end the following:

[p. 195, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195) (indent level 3)

“(C) The term ‘Federal authorization’ includes a certification under section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341) from a certifying authority (as defined in subsection (h) of that section) and any other permit, license, concurrence, or approval of a State administrative agency required under Federal law, other than the Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.), in order to site a transmission facility.”;

[p. 195, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195) (indent level 2)

(2) in paragraph (2), by striking the period at the end and inserting the following: “, except that—

[p. 195, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195) (indent level 3)

“(A) the Commission shall act as the lead agency in the case of facilities permitted under subsection (b) or section 225; and

[p. 195, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=195) (indent level 3)

“(B) the Department of the Interior shall act as the lead agency in the case of facilities located on a lease, easement, or right-of-way granted by the Secretary of the Interior under section 8(p)(1)(C) of the Outer Continental Shelf Lands Act (43 U.S.C. 1337(p)(1)(C)).”;

[p. 196, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=196) (indent level 2)

(3) in each of paragraphs (3), (4)(B), (4)(C), (5)(B), (6)(A), (7)(A), (7)(B)(i), (8)(A)(i), and (9), by striking “Secretary” each place it appears and inserting “lead agency”;

[p. 196, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=196) (indent level 2)

(4) in paragraph (4)(A), by striking “As head of the lead agency, the Secretary” and inserting “The lead agency”;

[p. 196, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=196) (indent level 2)

(5) in paragraph (5)(A), by striking “As lead agency head, the Secretary” and inserting “The lead agency”;

[p. 196, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=196) (indent level 2)

(6) in paragraph (7)—

[p. 196, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=196) (indent level 3)

(A) in subparagraph (A), by striking “18 months after the date of enactment of this section” and inserting “18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026”; and

[p. 196, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=196) (indent level 3)

(B) in subparagraph (B)(i), by striking “1 year after the date of enactment of this section” and inserting “18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026”; and

[p. 197, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 2)

(7) by adding at the end the following:

[p. 197, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 2)

“(10) Any order or action of a Federal agency or State administrative agency acting pursuant to Federal law to issue, condition, or deny a Federal authorization shall be subject to judicial review in the same courts in which an order of the Commission is subject to judicial review under section 313, and a court shall have jurisdiction over the action in accordance with the third sentence of subsection (b) of that section, the courts described in that section having original and exclusive jurisdiction over such actions.”.

[p. 197, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 1)

(g) INTERSTATE COMPACTS.—Section 216(i) of the Federal Power Act (16 U.S.C. 824p(i)) is amended—

[p. 197, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 2)

(1) in paragraph (3), by striking “, including facilities in national interest electric transmission corridors”; and

[p. 197, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 2)

(2) in paragraph (4)—

[p. 197, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 3)

(A) in subparagraph (A), by striking “; and” and inserting a period;

[p. 197, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 3)

(B) by striking subparagraph (B); and

[p. 197, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=197) (indent level 3)

(C) by striking “in disagreement” in the matter preceding subparagraph (A) and all that follows through “(A) the” in subparagraph (A) and inserting “unable to reach an agreement on an application seeking approval by the”.

[p. 198, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 1)

(h) TRANSMISSION INFRASTRUCTURE INVESTMENT.— Section 219(b)(4) of the Federal Power Act (16 U.S.C. 824s(b)(4)) is amended—

[p. 198, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 2)

(1) in subparagraph (A), by striking “and” after the semicolon at the end;

[p. 198, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 2)

(2) in subparagraph (B), by striking the period at the end and inserting “; and”; and

[p. 198, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 2)

(3) by adding at the end the following:

[p. 198, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 3)

“(C) all prudently incurred costs associated with payments to jurisdictions impacted by electric transmission facilities developed pursuant to section 216 or 225.”.

[p. 198, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 4)

(i) JURISDICTION.—Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (k) and inserting the following:

[p. 198, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 1)

“(k) JURISDICTION.—

[p. 198, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 2)

“(1) ERCOT.—This section shall not apply within the area referred to in section 212(k)(2)(A).

[p. 198, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 2)

“(2) OTHER UTILITIES.—

[p. 198, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=198) (indent level 3)

“(A) IN GENERAL.—For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including transmitting utilities described in section 201(f), but excluding any ERCOT utility (as defined in section 212(k)(2)(B)) and any exempt transmitting utility that does not voluntarily subject itself to Commission jurisdiction for the purposes of this section.

[p. 199, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199) (indent level 3)

“(B) CLARIFICATION.—Being subject to Commission jurisdiction for the purposes of this section shall not make an entity described in section 201(f) a public utility for the purposes of section 201(e).”.

[p. 199, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199) (indent level 1)

(j) CONFORMING AMENDMENTS.—

[p. 199, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199) (indent level 2)

(1) Section 50151(b) of Public Law 117–169 (42 U.S.C. 18715(b)) is amended by striking “facilities designated by the Secretary to be necessary in the national interest under section 216(a) of the Federal Power Act (16 U.S.C. 824p(a))” and inserting “facilities in a geographic area identified under section 224 of the Federal Power Act”.

[p. 199, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199) (indent level 2)

(2) Section 1222 of the Energy Policy Act of 2005 (42 U.S.C. 16421) is amended—

[p. 199, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199) (indent level 3)

(A) in subsection (a)(1)(A), by striking “in a national interest electric transmission corridor designated under section 216(a)” and inserting “in a geographic area identified under section 224”; and

[p. 199, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=199) (indent level 3)

(B) in subsection (b)(1)(A), by striking “in an area designated under section 216(a)” and inserting “in a geographic area identified under section 224”.

[p. 200, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 2)

(3) Section 40106(h)(1)(A) of the Infrastructure Investment and Jobs Act (42 U.S.C. 18713(h)(1)(A)) is amended by striking “in an area designated as a national interest electric transmission corridor pursuant to section 216(a) of the Federal Power Act 16 U.S.C. 824p(a)” and inserting “in a geographic area identified under section 224 of the Federal Power Act”.