# Sec. 2102. Reconductoring and other activities in existing rights-of-way

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2102)

## Summary

Adds Federal Power Act section 216A: work that maintains or increases grid capacity inside an existing right-of-way is categorically excluded from NEPA. ([p. 201, line 23 to p. 202, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201)) Covered work includes reconductoring, higher operating voltage, added circuits, advanced transmission technologies, added storage at an existing facility, and a parallel circuit. ([p. 202, line 16 to p. 202, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202)) Work under section 216A is also not a major federal action and not an undertaking under the National Historic Preservation Act. ([p. 202, line 4 to p. 202, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202)) The bill also amends Natural Gas Act section 7 for repair, replacement, looping, compression and capacity-enhancement of interstate gas pipelines. ([p. 203, line 18 to p. 203, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203)) That work is not a major federal action or a historic-preservation undertaking when it stays inside an existing right-of-way or previously reviewed footprint. ([p. 204, line 14 to p. 204, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204))

## Key points

- Reconductoring and in-corridor grid upgrades exempt from NEPA and NHPA section 106 ([p. 201, line 23 to p. 202, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201))
- Gas pipeline looping and compression in existing corridors exempt from NEPA and NHPA section 106 ([p. 204, line 17 to p. 204, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204))
- Clean Water Act and Clean Air Act requirements for pipelines stay in place ([p. 205, line 1 to p. 205, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205))

## Selected statutory quotes

> Activities to maintain or increase the capacity of the electric grid within a covered area, and any Federal agency action authorizing such activities— “(A) are a category of actions designated as being categorically excluded

[p. 201, line 19 to p. 201, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201)

Grid upgrades inside an existing right-of-way are excluded from NEPA.

> The term ‘covered activity’ means any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation, looping, compression, capacity-enhancement project, or addition to a covered facility.

[p. 203, line 17 to p. 203, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203)

The same exemption for gas pipeline work, including looping and compression.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

DOE and other agencies have administrative categorical exclusions for some reconductoring; there is no statutory exclusion, and pipeline looping and compression get FERC environmental review.

### EPRA 2024 (reported S. 4753)

EPRA 2024 (sec. 209) only told Interior and Agriculture to adopt categorical exclusions for in-corridor grid work, which survives as section 2214. The statutory exemptions here, including the gas pipeline one, are new.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 200, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 1)

(a) CATEGORICAL EXCLUSION FOR RECONDUCTORING.—The Federal Power Act is amended by inserting after section 216 (16 U.S.C. 824p) the following:

[p. 200, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 0)

“SEC. 216A. GRID CAPACITY EXPANSION IN EXISTING RIGHTS-OF-WAY.

[p. 200, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 1)

“(a) DEFINITIONS.—In this section:

[p. 200, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 2)

“(1) APPLICABLE ELECTRICAL STANDARD.— The term ‘applicable electrical standard’ includes—

[p. 200, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 3)

“(A) a reliability standard (as defined in section 215(a)); and

[p. 200, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=200) (indent level 3)

“(B) an applicable standard of the National Electrical Safety Code published by the Institute of Electrical and Electronics Engineers Standards Association.

[p. 201, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 2)

“(2) COVERED AREA.—The term ‘covered area’ means an area—

[p. 201, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 3)

“(A) within an existing right-of-way; or

[p. 201, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 3)

“(B) within the minimum additional area adjacent to an existing right-of-way that is necessary—

[p. 201, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 4)

“(i) to comply with applicable electrical standards; or

[p. 201, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 4)

“(ii) to complete an activity described in subsection (b).

[p. 201, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 2)

“(3) COVERED FACILITY.—The term ‘covered facility’ means an existing electric transmission or distribution facility or associated infrastructure (including an electrical substation) that is located within a covered area.

[p. 201, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 1)

“(b) EXEMPTIONS.—

[p. 201, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 2)

“(1) IN GENERAL.—Activities to maintain or increase the capacity of the electric grid within a covered area, and any Federal agency action authorizing such activities—

[p. 201, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=201) (indent level 3)

“(A) are a category of actions designated as being categorically excluded from the preparation of an environmental assessment or an environmental impact statement under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and

[p. 202, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 3)

“(B) shall not be considered to be—

[p. 202, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 4)

“(i) a major Federal action for purposes of that Act; or

[p. 202, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 4)

“(ii) an undertaking for purposes of section 306108 of title 54, United States Code.

[p. 202, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 2)

“(2) INCLUSIONS.—The activities described in paragraph (1) include—

[p. 202, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 3)

“(A) any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation of, or addition to, a covered facility, including—

[p. 202, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 4)

“(i) reconductoring;

[p. 202, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 4)

“(ii) an increase in operating voltage;

[p. 202, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 4)

“(iii) a circuit addition or adjustment; and

[p. 202, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=202) (indent level 4)

“(iv) installation of advanced transmission technologies (as defined in section 1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 16422(a)));

[p. 203, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 3)

“(B) any minimum widening of an existing right-of-way associated with an activity described in subparagraph (A) that—

[p. 203, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 4)

“(i) is necessary to comply with applicable electrical standards; or

[p. 203, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 4)

“(ii) remains within a covered area;

[p. 203, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 3)

“(C) an addition of energy storage at or near a covered facility; and

[p. 203, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 3)

“(D) the addition of a parallel circuit within an existing right-of-way.”.

[p. 203, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 1)

(b) INTERSTATE NATURAL GAS PIPELINE MODERNIZATION WITHIN EXISTING CORRIDORS.—Section 7 of the Natural Gas Act (15 U.S.C. 717f) is amended by adding at the end the following:

[p. 203, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 4)

“(i) COVERED PIPELINE ACTIVITIES.—

[p. 203, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 2)

“(1) DEFINITIONS.—In this subsection:

[p. 203, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 3)

“(A) COVERED ACTIVITY.—The term ‘covered activity’ means any repair, maintenance, replacement, upgrade, rebuilding, modification, optimization, minor relocation, looping, compression, capacity-enhancement project, or addition to a covered facility.

[p. 203, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 3)

“(B) COVERED AREA.—The term ‘covered area’ means—

[p. 203, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=203) (indent level 4)

“(i) an existing right-of-way; and

[p. 204, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204) (indent level 4)

“(ii) the footprint of original construction previously authorized and environmentally reviewed under this Act, together with any minimum additional area adjacent to an existing right-of-way that is necessary to complete a covered activity.

[p. 204, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204) (indent level 3)

“(C) COVERED FACILITY.—The term ‘covered facility’ means an existing interstate natural gas pipeline or associated infrastructure, including a compressor station, meter station, regulator station, valve site, launcher, receiver, storage-related facility, or similar facility located within a covered area.

[p. 204, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204) (indent level 2)

“(2) ENVIRONMENTAL REVIEW.—A covered activity and any Federal agency action authorizing that covered activity—

[p. 204, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204) (indent level 3)

“(A) shall not be considered a major Federal action under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) if the covered activity remains within a covered area; and

[p. 204, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=204) (indent level 3)

“(B) shall not be considered an undertaking for purposes of section 306108 of title 54, United States Code, if the covered activity remains within a covered area.

[p. 205, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 2)

“(3) RULE OF CONSTRUCTION.—Nothing in this subsection affects the applicability of any requirement under—

[p. 205, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 3)

“(A) the Federal Water Pollution Control Act (33 U.S.C. 1251 et seq.) (commonly known as the ‘Clean Water Act’);

[p. 205, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 3)

“(B) the Clean Air Act (42 U.S.C. 7401 et seq.); or

[p. 205, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 3)

“(C) any other applicable Federal law not expressly addressed by this subsection.”.