# Sec. 2103. Transmission planning

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2103)

## Summary

Adds Federal Power Act sections 224 and 225. ([p. 205, line 12 to p. 205, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205)) The Energy Department studies transmission constraints and congestion every 3 years and may identify constrained geographic areas. ([p. 205, line 15 to p. 205, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205)) FERC must issue a rule within 180 days requiring every planning region to file a regional planning process and joint interregional processes with its neighbors within 2 years, updated every 4 years. ([p. 211, line 11 to p. 211, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211)) The processes must use common assumptions, a fixed list of six benefits, and selection criteria of improved reliability, consumer benefit and public interest. ([p. 213, line 1 to p. 213, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213))

Costs are allocated to beneficiaries roughly commensurate with benefits. ([p. 216, line 12 to p. 216, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=216)) Compliance with the FERC planning orders published on June 11, 2024, December 6, 2024 and April 28, 2025 (Order 1920 and its two rehearing orders) counts as compliance for regional planning. ([p. 217, line 3 to p. 217, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217)) A project selected in a regional or interregional plan is deemed to meet most of the findings for a FERC backstop permit. ([p. 217, line 9 to p. 217, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217)) Approving a planning process is not a major federal action under NEPA. ([p. 218, line 5 to p. 218, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=218))

## Key points

- Requires interregional transmission planning by statute ([p. 211, line 19 to p. 212, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211))
- FERC rule in 180 days; regional filings in 2 years ([p. 211, line 11 to p. 211, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211))
- Compliance with FERC's 2024 and 2025 planning orders (Order 1920) counts for the regional piece ([p. 217, line 1 to p. 217, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217))
- Plan-selected projects get a fast path to a FERC siting permit ([p. 217, line 12 to p. 217, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217))
- Six enumerated benefits; reliability first ([p. 213, line 19 to p. 213, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213))

## What others say it would do

Outside readings, quoted from their sources. These are claims about effects, not findings of this tracker.

- **Grid Strategies** (Think tanks; supports): The transmission title tackles the planning, permitting and cost-allocation barriers together.
  > It addresses the ‘3Ps’ of transmission barriers: planning, permitting, and paying, with targeted improvements in each area.
  [pv magazine USA, 2026-10-01](http://pv-magazine-usa.com/2026/10/01/senate-introduces-landmark-permitting-bill-as-industry-data-and-environmental-groups-clash-over-reforms/).
- **Grid Strategies** (Think tanks; supports): More transmission and better access to low-cost generation would likely lower consumer bills over time.
  > It is very likely that this bill, if passed, would reduce consumer utility bills over time as the transmission system expands and access to low-cost generation improves.
  [pv magazine USA, 2026-10-01](http://pv-magazine-usa.com/2026/10/01/senate-introduces-landmark-permitting-bill-as-industry-data-and-environmental-groups-clash-over-reforms/).

## Selected statutory quotes

> require neighboring transmission planning regions to jointly establish a process for planning interregional transmission facilities in accordance with this section

[p. 211, line 19 to p. 211, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211)

Neighboring regions must plan interregional lines together.

> Compliance with a Commission order or rulemaking effective as of the date of enactment of this section, including orders published in the Federal Register on April 28, 2025, December 6, 2024, and June 11, 2024, shall constitute compliance with the regional transmission planning and cost allocation requirements of this section.

[p. 217, line 1 to p. 217, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217)

Compliance with FERC's existing planning orders counts.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

FERC Orders 1000 and 1920 require regional planning by rule; interregional coordination is weak and there is no statutory requirement. DOE's triennial congestion study exists under section 216(a).

### EPRA 2024 (reported S. 4753)

EPRA 2024 (sec. 402) created the same sections 224 and 225 but required only interregional plans. This bill also requires regional planning processes, deems FERC Order No. 1920 compliance sufficient for the regional piece, and exempts public power and small co-ops unless they opt in. It drops EPRA's 60-day FERC dispute resolution between regions and FERC's power to impose a plan when regions fail to file one; the only consequence left is a 6-month extension.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 205, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 0)

Part II of the Federal Power Act (16 U.S.C. 824 et seq.) is amended by adding at the end the following:

[p. 205, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 0)

“SEC. 224. TRANSMISSION STUDY.

[p. 205, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 1)

“(a) IN GENERAL.—Not later than 1 year after the date of enactment of this section and every 3 years thereafter, the Secretary of Energy (referred to in this section as the ‘Secretary’), in consultation with affected States and Indian Tribes, shall conduct a study of electric transmission capacity constraints and congestion.

[p. 205, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 1)

“(b) REPORT.—

[p. 205, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=205) (indent level 2)

“(1) IN GENERAL.—Not less frequently than once every 3 years, the Secretary shall issue a report based on the study under subsection (a) or other information relating to electric transmission capacity constraints and congestion.

[p. 206, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 2)

“(2) OPPORTUNITY FOR COMMENT.—Before issuing a report under paragraph (1), the Secretary shall—

[p. 206, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 3)

“(A) provide an opportunity for comment to affected States and Indian Tribes; and

[p. 206, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 3)

“(B) take into consideration any comments received under subparagraph (A) in preparing the report.

[p. 206, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 2)

“(3) IDENTIFICATION OF AREAS WITH CAPACITY CONSTRAINTS AND CONGESTION.—After considering alternatives and recommendations from interested parties (including any comments received from affected States and Indian Tribes), the Secretary may identify in a report issued under paragraph (1) any geographic area that—

[p. 206, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 3)

“(A) is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or

[p. 206, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 3)

“(B) is expected to experience such energy transmission capacity constraints or congestion.

[p. 206, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=206) (indent level 1)

“(c) CONSULTATION.—Not less frequently than once every 3 years, the Secretary, in conducting the study under subsection (a) and issuing the report under subsection (b), shall consult with affected transmission planning regions (as defined in section 225(a)) and any appropriate regional entity referred to in section 215.

[p. 207, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 1)

“(d) ALASKA.—The Secretary—

[p. 207, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 2)

“(1) shall, in consultation with the State of Alaska and affected Indian Tribes, consider any intrastate transmission capacity constraints and congestion within the State of Alaska in the study under subsection (a); and

[p. 207, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 2)

“(2) in issuing the report under subsection (b), may, subject to the approval of the Regulatory Commission of Alaska, identify any geographic area in the State of Alaska that—

[p. 207, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 3)

“(A) is experiencing electric energy transmission capacity constraints or congestion that adversely affects consumers; or

[p. 207, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 3)

“(B) is expected to experience such energy transmission capacity constraints or congestion.

[p. 207, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 0)

“SEC. 225. PLANNING FOR TRANSMISSION FACILITIES THAT ENHANCE GRID RELIABILITY, AFFORDABILITY, AND RESILIENCE.

[p. 207, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 1)

“(a) DEFINITIONS.—In this section:

[p. 207, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=207) (indent level 2)

“(1) COMMISSION.—The term ‘Commission’ means the Federal Energy Regulatory Commission.

[p. 208, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 2)

“(2) ERO.—The term ‘ERO’ has the meaning given the term in section 215(a).

[p. 208, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 2)

“(3) EXEMPT TRANSMITTING UTILITY.—The term ‘exempt transmitting utility’ means a transmitting utility that is—

[p. 208, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 3)

“(A) a State or any political subdivision of a State; or

[p. 208, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 3)

“(B) an electric cooperative that sells less than 4,000,000 megawatt hours of electricity per year.

[p. 208, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 2)

“(4) IMPROVED RELIABILITY.—The term ‘improved reliability’ means that, on balance, considering each of the matters described in subparagraphs (A) through (D), reliability is improved in a material manner that benefits customers through at least one of the following:

[p. 208, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 3)

“(A) Facilitating compliance with a mandatory standard for reliability approved by the Commission under section 215.

[p. 208, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 3)

“(B) A reduction in expected unserved energy, loss of load hours, or loss of load probability (as defined by the ERO).

[p. 208, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=208) (indent level 3)

“(C) Facilitating compliance with a tariff requirement or process for resource adequacy on file with the Commission.

[p. 209, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 3)

“(D) Any other similar material improvement, including a reduction in correlated outage risk.

[p. 209, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 2)

“(5) INTERREGIONAL TRANSMISSION FACILITY.— The term ‘interregional transmission facility’ means a transmission facility that—

[p. 209, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 3)

“(A) is located within 2 or more neighboring transmission planning regions; or

[p. 209, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 3)

“(B) significantly impacts the ability of 1 or more transmission planning regions to transmit electric energy among neighboring transmission planning regions.

[p. 209, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 2)

“(6) REGIONAL TRANSMISSION FACILITY.—The term ‘regional transmission facility’ means a transmission facility that—

[p. 209, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 3)

“(A) is located within 1 transmission planning region; and

[p. 209, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 3)

“(B) is not an interregional transmission facility.

[p. 209, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 2)

“(7) TRANSMISSION PLANNING REGION.—

[p. 209, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 3)

“(A) IN GENERAL.—The term ‘transmission planning region’—

[p. 209, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=209) (indent level 4)

“(i) when used in a geographical sense, means a region for which the Commission determines that electric transmission planning is appropriate, such as a region established in accordance with Order No. 1000 of the Commission, entitled ‘Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities’ (76 Fed. Reg. 49842 (August 11, 2011)); and

[p. 210, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=210) (indent level 4)

“(ii) when used in a corporate sense, means the Transmission Organization or other entity responsible for planning or operating electric transmission facilities within a region described in clause (i).

[p. 210, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=210) (indent level 3)

“(B) EXCLUSION.—The term ‘transmission planning region’ does not include the Electric Reliability Council of Texas or the region served by members of the Electric Reliability Council of Texas.

[p. 210, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=210) (indent level 1)

“(b) JURISDICTION.—

[p. 210, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=210) (indent level 2)

“(1) ERCOT.—This section shall not apply within the area referred to in section 212(k)(2)(A).

[p. 210, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=210) (indent level 2)

“(2) OTHER UTILITIES.—

[p. 210, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=210) (indent level 3)

“(A) IN GENERAL.—For the purposes of this section, the Commission shall have jurisdiction over all transmitting utilities, including transmitting utilities described in section 201(f), but excluding any ERCOT utility (as defined in section 212(k)(2)(B)) and any exempt transmitting utility that does not voluntarily subject itself to Commission jurisdiction for the purposes of this section.

[p. 211, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211) (indent level 3)

“(B) CLARIFICATION.—Being subject to Commission jurisdiction for the purposes of this section shall not make an entity described in section 201(f) a public utility for the purposes of section 201(e).

[p. 211, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211) (indent level 1)

“(c) RULEMAKING REQUIREMENT.—Not later than 180 days after the date of enactment of this section, the Commission shall, consistent with the requirements of this section, by rule—

[p. 211, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211) (indent level 2)

“(1) require each transmission planning region to establish a process for planning for regional transmission facilities in accordance with this section;

[p. 211, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211) (indent level 2)

“(2) require neighboring transmission planning regions to jointly establish a process for planning interregional transmission facilities in accordance with this section;

[p. 211, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=211) (indent level 2)

“(3) require each transmission planning region to submit to the Commission for approval—

[p. 212, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=212) (indent level 3)

“(A) a regional transmission planning process; and

[p. 212, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=212) (indent level 3)

“(B) a joint interregional transmission planning process with each of its neighboring transmission planning regions, which requirement may, at the discretion of the transmission planning region, be satisfied through the submission of—

[p. 212, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=212) (indent level 4)

“(i) a separate joint interregional transmission planning process with each of its neighboring transmission planning regions; or

[p. 212, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=212) (indent level 4)

“(ii) 1 or more joint interregional transmission planning processes, any of which may be submitted with any 1 or more of its neighboring transmission planning regions; and

[p. 212, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=212) (indent level 2)

“(4) establish rate treatments for regional and interregional transmission planning and cost allocation.

[p. 212, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=212) (indent level 1)

“(d) TRANSMISSION PLANNING PROCESS ELEMENTS.— The Commission shall require, within the rule under subsection (c), that regional and joint interregional transmission planning processes contain the following elements:

[p. 213, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 2)

“(1) COMPATIBILITY.—A common set of input assumptions and models, on a consistent timeline, that—

[p. 213, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 3)

“(A) allow for the joint identification and selection of specific interregional transmission facilities, and individual identification and selection of specific regional transmission facilities, by transmission planning regions, for construction or modification, including through the use of advanced transmission conductors (including superconductors) and reconductoring;

[p. 213, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 3)

“(B) consider, to the extent reasonable and economical, modifications that maximize the transmission capabilities of existing towers, structures, or rights-of-way; and

[p. 213, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 3)

“(C) consider interactions with existing regional, interregional, and supplemental transmission plans and planning processes.

[p. 213, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 2)

“(2) TRANSMISSION BENEFITS.—A common set of benefits for regional and interregional transmission planning and cost allocation, including—

[p. 213, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 3)

“(A) improved reliability;

[p. 213, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 3)

“(B) reduced congestion;

[p. 213, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=213) (indent level 3)

“(C) reduced power losses;

[p. 214, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 3)

“(D) greater carrying capacity that delivers improved reliability or reductions in the cost of delivered power;

[p. 214, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 3)

“(E) reduced operating reserve requirements; and

[p. 214, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 3)

“(F) improved access to generation that achieves reductions in the cost of delivered power.

[p. 214, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 2)

“(3) SELECTION CRITERIA.—Criteria governing the selection by transmission planning regions, for construction or modification, of regional and interregional transmission facilities that—

[p. 214, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 3)

“(A) provide improved reliability;

[p. 214, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 3)

“(B) protect or benefit consumers; and

[p. 214, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 3)

“(C) are consistent with the public interest.

[p. 214, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 1)

“(e) DEADLINE; UPDATES.—The regional and joint interregional transmission planning processes required to be submitted to the Commission pursuant to the rule under subsection (c) shall be—

[p. 214, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 2)

“(1) submitted to the Commission not later than 2 years after the date of enactment of this section; and

[p. 214, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=214) (indent level 2)

“(2) updated not less frequently than once every 4 years.

[p. 215, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 1)

“(f) COMMISSION REVIEW.—The Commission shall—

[p. 215, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 2)

“(1) review each regional and joint interregional transmission planning process submitted pursuant to the rule under subsection (c); and

[p. 215, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 2)

“(2) approve the regional or joint interregional transmission planning process if the Commission finds that the process—

[p. 215, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 3)

“(A) meets the requirements of subsection (d);

[p. 215, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 3)

“(B) allocates costs in accordance with subsection (g);

[p. 215, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 3)

“(C) ensures that all rates, charges, terms, and conditions will be just and reasonable and not unduly discriminatory or preferential; and

[p. 215, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 3)

“(D) is consistent with the public interest.

[p. 215, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 1)

“(g) COST ALLOCATION.—

[p. 215, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=215) (indent level 2)

“(1) TRANSMISSION TARIFFS.—For the purposes of this section and except as provided in paragraph (2), any transmitting utility that owns, controls, or operates electric transmission facilities constructed or modified as a result of this section shall file a tariff or tariff revision with the Commission pursuant to section 205 and the regulations of the Commission allocating the costs of the new or modified transmission facilities.

[p. 216, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=216) (indent level 2)

“(2) EXCEPTION.—In the case of an exempt transmitting utility that owns, controls, or operates electric transmission facilities described in paragraph (1), the Commission, notwithstanding section 211A(c), shall require the exempt transmitting utility to provide transmission services over such facilities pursuant to section 211A and the regulations of the Commission allocating the costs of the new or modified transmission facilities.

[p. 216, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=216) (indent level 2)

“(3) REQUIREMENT.—The Commission shall require that tariffs or tariff revisions filed under this section are just and reasonable and allocate the costs of providing service to customers that benefit, in accordance with the cost-causation principle and at least roughly commensurate with the benefits, including through the benefits described in subsection (d)(2).

[p. 216, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=216) (indent level 2)

“(4) RATEPAYER PROTECTION.—Customers that receive no benefit, or benefits that are trivial in relation to the costs sought to be allocated, from electric transmission facilities constructed or modified under this section shall not be involuntarily allocated any of the costs of those transmission facilities.

[p. 217, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217) (indent level 1)

“(h) COMPLIANCE.—Compliance with a Commission order or rulemaking effective as of the date of enactment of this section, including orders published in the Federal Register on April 28, 2025, December 6, 2024, and June 11, 2024, shall constitute compliance with the regional transmission planning and cost allocation requirements of this section.

[p. 217, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217) (indent level 1)

“(i) CONSTRUCTION PERMIT.—For the purposes of obtaining a construction permit under section 216(b), a project that is selected by 1 or more transmission planning regions pursuant to a regional or joint interregional transmission plan in accordance with this section shall be considered to satisfy paragraphs (2) through (5) and, if applicable, (6) of that section.

[p. 217, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=217) (indent level 1)

“(j) FAILURE TO SUBMIT PLANNING PROCESS.—In the event that neighboring transmission planning regions (in the case of an interregional planning process) or a single planning region (in the case of a regional planning process) fails to submit to the Commission a regional or joint interregional transmission planning process, as applicable, under this section, the Commission shall, as the Commission determines to be appropriate, grant a request to extend the time for submission of the planning process for not more than 6 months after the deadline the Commission requires for compliance with the rule under subsection (c).

[p. 218, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=218) (indent level 1)

“(k) NEPA.—For purposes of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.)—

[p. 218, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=218) (indent level 2)

“(1) any approval of a regional or joint interregional transmission planning process under subsection (f) shall not be considered a major Federal action; and

[p. 218, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=218) (indent level 2)

“(2) any permit granted under section 216(b) for a project that is selected by transmission planning regions pursuant to a joint interregional transmission plan shall be considered a major Federal action.”.