# Sec. 2106. Consolidated planning process

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2106)

## Summary

Requires FERC, within 18 months, to make each planning region file a consolidated interconnection and transmission planning process that looks 20 years ahead. ([p. 224, line 24 to p. 225, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=224)) The process publishes fuel-neutral planned interconnection locations with a fixed per-megawatt cost. ([p. 225, line 8 to p. 225, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225)) A cluster study in the process has one decision point and nonrefundable security to deter speculative projects. ([p. 225, line 13 to p. 225, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225)) Regions file within 2 years and update every 2 years. ([p. 225, line 22 to p. 225, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225))

## Key points

- Generation interconnection and transmission planned together ([p. 225, line 3 to p. 225, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225))
- Published zonal per-megawatt interconnection prices ([p. 225, line 8 to p. 225, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225))
- Nonrefundable deposits and withdrawal penalties for queue entrants ([p. 225, line 13 to p. 225, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225))

## Selected statutory quotes

> routinely identifies and publishes resource and fuel-neutral planned interconnection locations for generating capacity and an upfront, fixed, zonal, per-megawatt cost for each planned interconnection location

[p. 225, line 8 to p. 225, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225)

Published interconnection locations with a fixed per-megawatt cost.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

FERC Order No. 2023 set cluster studies; planning and interconnection remain separate processes.

### EPRA 2024 (reported S. 4753)

Not in EPRA 2024.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 224, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=224) (indent level 0)

Part III of the Federal Power Act is amended by inserting after section 317 (16 U.S.C. 825p) the following:

[p. 224, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=224) (indent level 0)

“SEC. 318. CONSOLIDATED PLANNING PROCESS.

[p. 224, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=224) (indent level 1)

“(a) CONSOLIDATED GENERATION AND TRANSMISSION PLANNING.—Not later than 18 months after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026, the Federal Energy Regulatory Commission (referred to in this section as the ‘Commission’) shall issue a rule requiring each transmission planning region (as defined in section 225(a)) to file a consolidated interconnection and regional transmission planning process that—

[p. 225, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225) (indent level 2)

“(1) jointly evaluates electric transmission facilities and the generating capacity reasonably anticipated to be needed to meet future forecasted demand and forecasted generation over the next 20 years;

[p. 225, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225) (indent level 2)

“(2) routinely identifies and publishes resource and fuel-neutral planned interconnection locations for generating capacity and an upfront, fixed, zonal, per-megawatt cost for each planned interconnection location; and

[p. 225, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225) (indent level 2)

“(3) establishes a streamlined generator cluster study process with a single decision point, meaningful and nonrefundable financial security, and withdrawal penalties sufficient to deter speculative projects.

[p. 225, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225) (indent level 1)

“(b) DEADLINE; UPDATES.—The consolidated interconnection and regional transmission planning process required to be filed with the Commission pursuant to the rule under subsection (a) shall be—

[p. 225, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=225) (indent level 2)

“(1) filed with the Commission not later than 2 years after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026; and

[p. 226, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 2)

“(2) updated not less frequently than once every 2 years.

[p. 226, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 1)

“(c) COMMISSION REVIEW.—The Commission shall—

[p. 226, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 2)

“(1) review each consolidated interconnection and regional transmission planning process filed pursuant to the rule under subsection (a); and

[p. 226, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 2)

“(2) approve the consolidated interconnection and regional transmission planning process if the Commission finds that the process—

[p. 226, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 3)

“(A) ensures that all rates, charges, terms, and conditions will be just and reasonable and not unduly discriminatory or preferential; and

[p. 226, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 3)

“(B) is consistent with the public interest.”.