# Sec. 2107. Ratepayer protection

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2107)

## Summary

Congress finds it is not just and reasonable to charge data center, AI and cryptocurrency loads less than the embedded and incremental cost of the transmission they need. ([p. 226, line 25 to p. 227, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226)) FERC must revise its 1994 transmission pricing policy within 270 days, propose a rule 270 days after that, and finish within a further year. ([p. 229, line 15 to p. 229, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229))

New Federal Power Act section 228 covers data center loads of 20 megawatts or more. ([p. 232, line 9 to p. 232, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232)) None of the incremental cost of serving them (generation, transmission, distribution) may be recovered from other customers. ([p. 234, line 23 to p. 235, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234)) Recovery continues even if the data center leaves, and utilities must collect financial assurance before building upgrades. ([p. 235, line 23 to p. 236, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235))

States may charge these loads more than cost and credit the surplus to other ratepayers. ([p. 236, line 14 to p. 236, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236)) They may run open seasons that award service by ratepayer benefit, whatever the queue order. ([p. 237, line 1 to p. 237, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=237)) They may require the load to bring new generation, require curtailable service, and treat data centers less favorably than other industrial customers. ([p. 237, line 14 to p. 237, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=237)) The section applies to loads interconnecting after enactment. ([p. 240, line 1 to p. 240, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240))

## Key points

- Data centers of 20 MW or more pay the full incremental cost of serving them ([p. 234, line 23 to p. 235, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234))
- Costs follow the data center even after it exits ([p. 235, line 14 to p. 235, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235))
- Up-front financial assurance before upgrades are built ([p. 235, line 23 to p. 236, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235))
- States may auction grid access and require bring-your-own generation ([p. 236, line 23 to p. 237, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236))
- Non-firm service gets a lower transmission price ([p. 230, line 9 to p. 230, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230))
- Standardized study of cost-reduction options to avoid network upgrades ([p. 231, line 5 to p. 231, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=231))
- Incremental revenues credited to prevent double recovery from other ratepayers ([p. 230, line 1 to p. 230, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230))
- Existing approved arrangements grandfathered ([p. 240, line 5 to p. 240, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240))

## What others say it would do

Outside readings, quoted from their sources. These are claims about effects, not findings of this tracker.

- **Bommarito Consulting** (Think tanks; concerns): The data-center cost rule relies on utility cost estimates and adds no public disclosure or contested-hearing requirement.
  > The section adds no public disclosure or contested hearing requirement.
  [Bommarito Consulting, 2026-09-30](https://bommaritollc.com/insights/senate-permitting-bill-2026/).
- **Washington Examiner** (Reporting; explains): Data centers would have to post financial assurances covering project costs before any generation, transmission or distribution facility is built for them.
  > Data centers must also provide utilities with financial assurances or contributions sufficient to cover the cost of the project before construction on a generating, transmission or distribution facility begins.
  [Washington Examiner, 2026-10-01](https://www.washingtonexaminer.com/daily-on-energy/4750722/daily-on-energy-a-baaja-blast-for-data-centers/). On the bill text at [p. 235, line 23 to p. 236, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235).
- **Bipartisan Policy Center** (Think tanks; supports): The exit and up-front payment rules address the risk that a data center closes before the lines and plants built for it are paid off.
  > ensuring that data centers keep paying even if they leave early and must provide financial guarantees before utilities build to serve them
  [Bipartisan Policy Center, 2026-10-02](https://bipartisanpolicy.org/explainer/explaining-the-senate-permitting-bill-the-bipartisan-american-affordability-and-jobs-act). On the bill text at [p. 235, line 18 to p. 235, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235).
- **King & Spalding** (Lawyers and legal scholars; explains): FERC would reprice transmission service so data centers carry embedded as well as incremental costs; developers should compare with the House Ratepayer Protection Act approach.
  > FERC would revise its transmission pricing policy so that data centers pay both the embedded and incremental cost of transmission service.
  [King & Spalding, 2026-10-02](https://www.kslaw.com/Insights/Articles/The-Senate-Permitting-Deal-What-It-Would-Change-and-What-to-Do-Now). On the bill text at [p. 229, line 23 to p. 229, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229).
- **McGuireWoods** (Lawyers and legal scholars; explains): States could place data centers in a separate service class with terms less favorable than other large customers.
  > The rates, terms or service priorities for that class could differ from, and be less favorable than, those for other large commercial and industrial customers.
  [McGuireWoods, 2026-10-02](https://www.mcguirewoods.com/client-resources/alerts/2026/10/bipartisan-american-affordability-and-jobs-act-of-2026-proposes-sweeping-reform-for-energy-and-infrastructure-projects/). On the bill text at [p. 238, line 25 to p. 238, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238).
- **McGuireWoods** (Lawyers and legal scholars; explains): States could ration service among large loads by open season, awarding capacity by benefit to other ratepayers rather than queue order.
  > States could use an open season or competitive process to decide which covered loads receive available electric service, with awards based on the greatest benefit to other ratepayers on a present-value basis rather than the order in which applications are received.
  [McGuireWoods, 2026-10-02](https://www.mcguirewoods.com/client-resources/alerts/2026/10/bipartisan-american-affordability-and-jobs-act-of-2026-proposes-sweeping-reform-for-energy-and-infrastructure-projects/). On the bill text at [p. 236, line 23 to p. 237, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236).
- **Womble Bond Dickinson** (Lawyers and legal scholars; explains): The 20 MW data-center regime would require full incremental-cost recovery even after exit plus up-front financial assurances.
  > It would require full recovery of incremental service costs even after a customer exits, together with financial assurances or contributions before necessary infrastructure construction or upgrades.
  [Womble Bond Dickinson, 2026-10-02](https://www.womblebonddickinson.com/us/node/21451). On the bill text at [p. 235, line 18 to p. 235, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235).
- **Womble Bond Dickinson** (Lawyers and legal scholars; explains): The data-center cost rules could change service agreements, collateral, exit charges and project economics.
  > These provisions could materially affect service agreements, collateral requirements, exit charges, and development economics.
  [Womble Bond Dickinson, 2026-10-02](https://www.womblebonddickinson.com/us/node/21451). On the bill text at [p. 235, line 23 to p. 236, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235).
- **Arushi Sharma Frank** (Commentators; explains): Curtailing only at system peak would not get a data center connected faster, because local contingency limits bind off-peak too; the speed comes from the bill's lower-cost non-firm service and its required analysis of upgrade cost-reduction options.
  > BAAJA’s breakthrough isn't peak shaving; it's codifying "non-firm transmission service".
  [X, 2026-10-04](https://x.com/ArushiSF/status/2106595761748111595). On the bill text at [p. 230, line 9 to p. 230, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230).
- **Bisnow** (Industry; concerns): A data center developer says requiring large loads to pay grid costs that would not exist but for their demand adds speculative upfront capital that smaller developers cannot carry.
  > Any upfront cost that you have to spend before you even know the answer if something is viable will wipe everyone out
  [Bisnow, 2026-10-18](https://www.bisnow.com/news/national/data-center-development/senate-bill-offers-data-centers-a-faster-path-to-power-but-at-a-price). On the bill text at [p. 229, line 19 to p. 229, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229).
- **Heatmap News** (Reporting; explains): FERC would have to require utilities to charge data centers both for new grid upgrades and for ongoing use of the grid.
  > FERC would have to require utilities to charge data centers not only for the costs of new grid upgrades but the charges incurred for using the grid, too.
  [Heatmap News (The Fight), 2026-10-16](https://heatmap.news/plus/the-fight/spotlight/project-jupiter-permitting). On the bill text at [p. 229, line 19 to p. 229, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229).
- **Institute for Progress** (Think tanks; supports): Utilities may not shift a data center's incremental costs to other customers, and the federal floor of 20 MW and up lets states charge more.
  > Utilities may not shift a data center's "incremental cost" to other customers.
  [Institute for Progress, 2026-10-12](https://ifp.org/how-the-permit). On the bill text at [p. 229, line 19 to p. 229, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229).

## Selected statutory quotes

> No portion of the incremental cost may be allocated to, or recovered in the rates of, any customer other than a covered load

[p. 234, line 23 to p. 235, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234)

Other customers cannot be charged the incremental cost of serving a data center.

> A State may treat covered loads as a separate class of service, and may establish rates, charges, terms, conditions, and interconnection or service priorities for covered loads that differ from, and that are less favorable than, those applicable to other large industrial, manufacturing, or commercial loads.

[p. 238, line 24 to p. 239, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238)

States may treat data centers less favorably than other large customers.

> equals or exceeds 20 megawatts or, in the case of data centers or high-density computing facilities developed in phases, is reasonably expected to equal or exceed 20 megawatts at full buildout.

[p. 232, line 9 to p. 232, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232)

The 20-megawatt threshold.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

Cost allocation for large loads is set in individual state proceedings and FERC tariffs. FERC opened a large-load interconnection rulemaking in 2025. There is no federal floor.

### EPRA 2024 (reported S. 4753)

Not in EPRA 2024; data center cost allocation became a central issue in 2025-2026.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 226, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 1)

(a) FERC PRICING POLICY FOR TRANSMISSION SERVICES PROVIDED BY PUBLIC UTILITIES AND TRANSMITTING UTILITIES.—

[p. 226, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 2)

(1) FINDINGS.—Congress finds that—

[p. 226, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=226) (indent level 3)

(A) it is not just and reasonable within the meaning of sections 205 and 206 of the Federal Power Act (16 U.S.C. 824d, 824e) for any public utility or transmitting utility to maintain rates, terms, or conditions of service that, by their terms, charge less than the embedded costs and incremental expansion costs to eligible customers seeking transmission service from computational load owners and computational load operators;

[p. 227, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=227) (indent level 3)

(B) transmission service costs should be fully assigned to computational load owners and computational load operators so as to minimize or avoid the cost burden on other customers; and

[p. 227, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=227) (indent level 3)

(C) computational load owners and computational load operators should incur the full cost of the transmission service they require.

[p. 227, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=227) (indent level 2)

(2) DEFINITIONS.—In this subsection:

[p. 227, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=227) (indent level 3)

(A) 1994 TRANSMISSION PRICING POLICY STATEMENT.—The term “1994 transmission pricing policy statement” means the policy statement issued by the Commission on October 26, 1994, and published in the Federal Register on November 3, 1994, relating to “Inquiry Concerning the Commission’s Pricing Policy for Transmission Services Provided by Public Utilities Under the Federal Power Act; Policy Statement” (59 Fed. Reg. 55031).

[p. 228, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 3)

(B) COMMISSION.—The term “Commission” means the Federal Energy Regulatory Commission.

[p. 228, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 3)

(C) COMPUTATIONAL LOAD OPERATOR.— The term “computational load operator” means the entity that operates a computational load site.

[p. 228, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 3)

(D) COMPUTATIONAL LOAD OWNER.—The term “computational load owner” means the entity that owns a computational load site.

[p. 228, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 3)

(E) COMPUTATIONAL LOAD SITE.—The term “computational load site” means 1 or more buildings, structures, or installations at a single location that—

[p. 228, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 4)

(i) primarily contain information technology infrastructure used for—

[p. 228, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 5)

(I) creating, executing, and delivering software applications and services;

[p. 228, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 5)

(II) artificial intelligence training, deployment, and delivery;

[p. 228, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 5)

(III) cryptocurrency mining; or

[p. 228, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=228) (indent level 5)

(IV) other computational activities at a data center; and

[p. 229, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229) (indent level 4)

(ii) are supplied through electrical equipment that is connected to the bulk-power system (as defined in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a))).

[p. 229, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229) (indent level 3)

(F) PUBLIC UTILITY.—The term “public utility” has the meaning given the term in section 201(e) of the Federal Power Act (16 U.S.C. 824(e)).

[p. 229, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229) (indent level 3)

(G) TRANSMITTING UTILITY.—The term “transmitting utility” has the meaning given the term in section 3 of the Federal Power Act (16 U.S.C. 796).

[p. 229, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229) (indent level 2)

(3) REVISION OF POLICY STATEMENT.—

[p. 229, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229) (indent level 3)

(A) IN GENERAL.—Not later than 270 days after the date of enactment of this Act, the Commission shall revise the 1994 transmission pricing policy statement—

[p. 229, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=229) (indent level 4)

(i) to require public utilities and transmitting utilities to charge eligible customers seeking transmission service on behalf of computational load owners and computational load operators the embedded cost and the incremental cost of transmission service; and

[p. 230, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230) (indent level 4)

(ii) to ensure that any incremental costs paid are credited to the annual transmission revenue requirement of the applicable public utility or transmitting utility to prevent double recovery from other customers.

[p. 230, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230) (indent level 3)

(B) REQUIREMENT.—In revising the 1994 transmission pricing policy statement under subparagraph (A), the Commission shall provide for a lower cost of transmission service for eligible customers seeking transmission service on behalf of computational load owners and computational load operators that elect non-firm transmission service.

[p. 230, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230) (indent level 2)

(4) RULEMAKING.—

[p. 230, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230) (indent level 3)

(A) NOTICE OF PROPOSED RULEMAKING.— Not later than 270 days after the date on which a revised transmission pricing policy statement is published in the Federal Register under paragraph (3), the Commission shall issue a notice of proposed rulemaking requiring public utilities and transmitting utilities—

[p. 230, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=230) (indent level 4)

(i) to establish or revise transmission rates for eligible customers seeking transmission service for computational load owners and computational load operators in accordance with that revised transmission pricing policy statement; and

[p. 231, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=231) (indent level 4)

(ii) to require standardized analysis to identify upgrades for a computational load site and cost reduction options, as the Commission may require by rule.

[p. 231, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=231) (indent level 3)

(B) FINAL RULE.—Not later than 1 year after the date on which the notice of proposed rulemaking described in subparagraph (A) is issued, the Commission shall issue a final rule requiring public utilities and transmitting utilities to establish or revise transmission rates for eligible customers seeking transmission service for computational load owners and computational load operators.

[p. 231, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=231) (indent level 1)

(b) RATEPAYER PROTECTION FOR DATA CENTER AND HIGH-DENSITY COMPUTING LOAD.—Part II of the Federal Power Act (16 U.S.C. 824 et seq.) (as amended by section 2105) is amended by adding at the end the following:

[p. 231, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=231) (indent level 0)

“SEC. 228. RATEPAYER PROTECTION FOR DATA CENTER AND HIGH-DENSITY COMPUTING LOAD.

[p. 231, line 25](https://pranava0x0.github.io/permittingreform/bill.pdf#page=231) (indent level 1)

“(a) DEFINITIONS.—In this section:

[p. 232, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 2)

“(1) COMMISSION.—The term ‘Commission’ means the Federal Energy Regulatory Commission.

[p. 232, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 2)

“(2) COVERED LOAD.—The term ‘covered load’ means electric load that—

[p. 232, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 3)

“(A) is attributable to 1 or more data centers or high-density computing facilities located at a single site, or at multiple sites under common ownership or control; and

[p. 232, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 3)

“(B) equals or exceeds 20 megawatts or, in the case of data centers or high-density computing facilities developed in phases, is reasonably expected to equal or exceed 20 megawatts at full buildout.

[p. 232, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 2)

“(3) DATA CENTER OR HIGH-DENSITY COMPUTING FACILITY.—

[p. 232, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 3)

“(A) IN GENERAL.—The term ‘data center or high-density computing facility’ means a facility, or group of co-located facilities, the primary purpose of which is to house computing, networking, or data storage equipment used to process, store, or transmit digital data, including equipment used for—

[p. 232, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=232) (indent level 4)

“(i) artificial intelligence training or inference;

[p. 233, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=233) (indent level 4)

“(ii) cloud computing or data hosting; or

[p. 233, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=233) (indent level 4)

“(iii) cryptocurrency mining or other distributed-ledger or digital-asset computation.

[p. 233, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=233) (indent level 3)

“(B) EXCLUSION.—The term ‘data center or other high-density computing facility’ does not include computing or data storage equipment that is ancillary to a facility the primary purpose of which is a commercial or industrial activity other than an activity described in subparagraph (A).

[p. 233, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=233) (indent level 2)

“(4) EMBEDDED AVERAGE COST.—The term ‘embedded average cost’ means the average cost of service reflected in the rates otherwise in effect for the customer class that would apply to the applicable covered load.

[p. 233, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=233) (indent level 2)

“(5) INCREMENTAL COST.—The term ‘incremental cost’ means the cost that would be avoided had a specific covered load not been served by the electric utility, including all costs to construct, own, and operate power generation or storage resources and electric transmission and distribution services associated with serving the covered load, based on costs estimated by the electric utility at or around the time that the covered load becomes operational and subject to approval by the Commission or a State, as appropriate.

[p. 234, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 2)

“(6) STATE.—The term ‘State’ includes the applicable State commission and any other State authority having jurisdiction over retail electric service.

[p. 234, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 2)

“(7) TRANSMISSION SERVICE CATEGORY.—The term ‘transmission service category’ means a class of transmission service provided under a tariff on file with the Commission, including—

[p. 234, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 3)

“(A) network integration transmission service;

[p. 234, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 3)

“(B) point-to-point transmission service; and

[p. 234, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 3)

“(C) any interim, non-firm, contract demand, or other service that limits—

[p. 234, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 4)

“(i) the quantity of energy a load may withdraw from the transmission system; or

[p. 234, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 4)

“(ii) the conditions under which the load may withdraw energy from the transmission system.

[p. 234, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 1)

“(b) RATEPAYER PROTECTION FLOOR.—

[p. 234, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=234) (indent level 2)

“(1) NO SUBSIDY OF COVERED LOAD.—No portion of the incremental cost may be allocated to, or recovered in the rates of, any customer other than a covered load, subject to the limitations described in subsection (e).

[p. 235, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235) (indent level 2)

“(2) SURPLUS PERMITTED.—Paragraph (1) does not limit the authority of the Commission or a State under subsection (c) to recover from covered loads amounts in excess of incremental cost and to credit those amounts to other customers as a rebate or a reduction to the utility costs that are used as a basis for the calculation of customer rates.

[p. 235, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235) (indent level 2)

“(3) CONTINUING RECOVERY ON EXIT.—A rate, charge, or agreement for service to a covered load shall be designed to recover from the covered load the full incremental cost of the electric utility, and such recovery shall continue notwithstanding the termination by the covered load of a contract or other agreement pertaining to the sale of electric energy, or the cessation by the covered load of the purchase of electric energy, before that incremental cost has been fully recovered.

[p. 235, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=235) (indent level 2)

“(4) FINANCIAL ASSURANCE.—Before constructing, or making an upgrade to, a generation, transmission, or distribution facility necessary to serve a covered load, an electric utility shall require the covered load to provide financial assurances or contributions sufficient to cover the cost of the facility or upgrade, subject to the condition that any financial assurances or contributions provided by the applicable covered load to a public utility or Transmission Organization for the same facility or upgrade shall be credited against the requirement of this paragraph.

[p. 236, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236) (indent level 1)

“(c) STATE AUTHORITY TO HOLD OPEN SEASONS AND SET COVERED-LOAD RATES.—

[p. 236, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236) (indent level 2)

“(1) IN GENERAL.—Notwithstanding any other provision of this Act or any rule or order of the Commission, and consistent with subsection (b)(3), a State may, with respect to retail electric service to covered loads—

[p. 236, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236) (indent level 3)

“(A) establish rates, charges, or contract terms that recover more than the embedded average cost, and more than the incremental cost, of serving a covered load;

[p. 236, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236) (indent level 3)

“(B) require that revenue collected from a covered load in excess of incremental cost be credited or applied to reduce the rates of other retail customers;

[p. 236, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=236) (indent level 3)

“(C) in effectuating the policy described in this subsection, use an open season or competitive solicitation to allocate among covered loads the opportunity to obtain and contract for retail electric service, making awards in such manner as returns the greatest benefit to other ratepayers on a present value basis, notwithstanding the order in which applications or requests for service are received from covered loads or any other basis for making such awards, subject to the condition that each award under such an open season or competitive solicitation shall specify the maximum quantity of firm demand awarded, in megawatts, and the transmission service category on the basis of which the covered load is to be served;

[p. 237, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=237) (indent level 3)

“(D) condition the provision of retail electric service to a covered load on the procurement, construction, or contracting by the covered load for new generation resources sufficient to serve the demand of the covered load; and

[p. 237, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=237) (indent level 3)

“(E) condition the provision of retail electric service to a covered load on the covered load taking, or agreeing to take, a transmission service category that limits—

[p. 238, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 4)

“(i) the quantity of energy the covered load may withdraw from the transmission system; or

[p. 238, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 4)

“(ii) the conditions under which the covered load may withdraw energy from the transmission system.

[p. 238, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 2)

“(2) PRIORITY OF STATE COMPETITIVE SOLICITATIONS.—

[p. 238, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 3)

“(A) BROAD DISCRETION.—For purposes of an open solicitation, a State shall, with respect to retail electric service to a covered load, be afforded broad discretion to conduct, to authorize an electric utility to conduct, or to require an electric utility to conduct, a competitive solicitation or open season to allocate the opportunity to interconnect, or to obtain service for, a covered load.

[p. 238, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 3)

“(B) ELECTRIC UTILITY FILING.—An electric utility may file to conduct a solicitation or open season described in subparagraph (A).

[p. 238, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 3)

“(C) AUTHORITY TO REQUIRE.—A State may require an electric utility to conduct an open season described in subparagraph (A).

[p. 238, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=238) (indent level 1)

“(d) PROTECTION OF AMERICAN INDUSTRY.—A State may treat covered loads as a separate class of service, and may establish rates, charges, terms, conditions, and interconnection or service priorities for covered loads that differ from, and that are less favorable than, those applicable to other large industrial, manufacturing, or commercial loads.

[p. 239, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 1)

“(e) RULES OF CONSTRUCTION.—

[p. 239, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 2)

“(1) STATE AND FEDERAL AUTHORITY.—Except as expressly provided in subsection (c), nothing in this section expands or diminishes the jurisdiction of the Commission or of any State, including State authority over retail electric service, rate design, and resource planning.

[p. 239, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 2)

“(2) RECOGNITION OF RESERVED STATE AUTHORITY.—

[p. 239, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 3)

“(A) IN GENERAL.—The authority described in subsection (c)(1) is an attribute of the reserved authority of the States over retail electric service.

[p. 239, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 3)

“(B) CLARIFICATION.—This section—

[p. 239, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 4)

“(i) recognizes and confirms the authority described in subparagraph (A); and

[p. 239, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 4)

“(ii) is not the source of that authority.

[p. 239, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=239) (indent level 1)

“(f) APPLICABILITY.—

[p. 240, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240) (indent level 2)

“(1) PROSPECTIVE APPLICATION.—Subsections (b) and (c) apply to a covered load that interconnects on or after the date of enactment of this section.

[p. 240, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240) (indent level 2)

“(2) EXISTING ARRANGEMENTS.—An arrangement to serve a covered load that was approved by the Commission or by a State before the date of enactment of this section shall remain in effect.”.