# Sec. 2108. Dispatchable energy systems market access

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2108)

## Summary

Opens wholesale markets to aggregations of customer-sited batteries, fuel cells and generators that can respond within 15 minutes (5 kilowatts minimum per device, 100 kilowatts per aggregation). ([p. 240, line 23 to p. 240, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240)) After 18 months, grid operator rules that block them are unjust and unreasonable. ([p. 243, line 13 to p. 243, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243)) Grid operators file compliance tariffs within 180 days. ([p. 244, line 21 to p. 244, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244)) Unless state law or the state regulator provides otherwise, distribution utilities in organized markets must interconnect these resources; for public power utilities and other section 201(f) entities the requirement is voluntary. ([p. 252, line 6 to p. 252, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252)) They must also accept wholesale metering data. ([p. 253, line 7 to p. 253, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253))

A device paid by a state retail program cannot be paid twice for the same service; ([p. 246, line 7 to p. 246, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=246)) FERC orders disgorgement and can impose penalties of up to 3 times the amount for each day it was knowingly kept. ([p. 250, line 16 to p. 250, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250)) The Energy Department runs a voluntary streamlined local permitting program for rooftop solar, batteries and vehicle chargers, with $20 million a year authorized for fiscal years 2026 through 2031. ([p. 259, line 21 to p. 259, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259))

## Key points

- Virtual power plants get statutory wholesale market access ([p. 243, line 20 to p. 243, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243))
- Distribution utilities in organized markets must interconnect behind-the-meter resources ([p. 252, line 9 to p. 252, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252))
- Device-level metering allowed; utilities cannot require their own equipment ([p. 241, line 16 to p. 241, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241))
- Double-payment ban, with penalties of up to 3 times the amount per day ([p. 250, line 16 to p. 250, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250))
- $20 million a year for streamlined local solar and storage permitting ([p. 259, line 22 to p. 259, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259))

## What others say it would do

Outside readings, quoted from their sources. These are claims about effects, not findings of this tracker.

- **Bommarito Consulting** (Think tanks; concerns): Data centers' own gas or diesel generators could access wholesale markets, and states could require new generation of any fuel.
  > A qualifying behind-the-meter “generator” — including a data center's own gas turbines or diesel sets — could gain access to wholesale markets.
  [Bommarito Consulting, 2026-09-30](https://bommaritollc.com/insights/senate-permitting-bill-2026/). On the bill text at [p. 240, line 20 to p. 240, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240).

## Selected statutory quotes

> it shall not be just and reasonable within the meaning of sections 205 and 206 for any Transmission Organization to maintain rates, terms, or conditions of service that, by their terms and to the extent that such rates, terms, and conditions directly affect wholesale rates, prevent the participation of any qualifying BTM DES aggregation

[p. 243, line 15 to p. 243, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243)

Grid operators cannot bar aggregated customer-sited resources from wholesale markets.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

FERC Order No. 2222 (2020) requires aggregation access by rule; implementation has slipped to 2026 and beyond in several regions.

### EPRA 2024 (reported S. 4753)

Not in EPRA 2024.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 240, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240) (indent level 1)

(a) DEFINITIONS.—Section 3 of the Federal Power Act (16 U.S.C. 796) is amended by adding at the end the following:

[p. 240, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240) (indent level 2)

“(30) QUALIFYING BEHIND-THE-METER DISTRIBUTED ENERGY SYSTEM FACILITY; QUALIFYING BTM DES FACILITY.—The term ‘qualifying behind-the-meter distributed energy system facility’ or ‘qualifying BTM DES facility’ means a facility that—

[p. 240, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240) (indent level 3)

“(A) is an energy storage system (including a battery energy storage system), a fuel cell system, a generator, or other resource—

[p. 240, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=240) (indent level 4)

“(i) that can be brought online within 15 minutes of being called on for deployment; and

[p. 241, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 4)

“(ii) the output of which can be dispatched and adjusted at the signal of the system operator;

[p. 241, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 3)

“(B) is located behind the meter of a retail customer of a distribution utility (as defined in section 217(a));

[p. 241, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 3)

“(C) has a rated capacity of not less than 5 kilowatts; and

[p. 241, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 3)

“(D) maintains metering and telemetry capabilities that—

[p. 241, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 4)

“(i) are sufficient to dispatch the facility, account for withdrawals from and injections to the grid, and communicate all relevant operational data from the facility; and

[p. 241, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 4)

“(ii) are not required to include equipment owned or installed by the distribution utility (as so defined), and may include the use of device-level equipment, including inverters.

[p. 241, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=241) (indent level 2)

“(31) QUALIFYING BEHIND-THE-METER DISTRIBUTED ENERGY SYSTEM AGGREGATION; QUALIFYING BTM DES AGGREGATION.—The term ‘qualifying behind-the-meter distributed energy system aggregation’ or ‘qualifying BTM DES aggregation’ means an aggregation of 2 or more qualifying BTM DES facilities—

[p. 242, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 3)

“(A) with a combined capacity of not less than 100 kilowatts; and

[p. 242, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 3)

“(B) that maintains aggregation-level metering and telemetry capabilities sufficient to facilitate the dispatch and market settlement of the aggregation.”.

[p. 242, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 1)

(b) RULE OF CONSTRUCTION.—Section 201 of the Federal Power Act (16 U.S.C. 824) is amended by adding at the end the following:

[p. 242, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 1)

“(h) QUALIFYING BTM DES FACILITIES AND AGGREGATIONS.— The designation of a facility as a qualifying BTM DES facility or an aggregation of 2 or more facilities as a qualifying BTM DES aggregation does not, of itself, subject any of the following to the jurisdiction of the Commission:

[p. 242, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 2)

“(1) The facility or aggregation.

[p. 242, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 2)

“(2) The retail electric service provided to or for the facility or aggregation.

[p. 242, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 2)

“(3) The distribution service on which the facility or aggregation relies.”.

[p. 242, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=242) (indent level 1)

(c) WHOLESALE MARKET ACCESS FOR QUALIFYING BTM DES AGGREGATIONS.—Part II of the Federal Power Act (16 U.S.C. 824 et seq.) (as amended by section 2107(b)) is amended by adding at the end the following:

[p. 243, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243) (indent level 0)

“SEC. 229. WHOLESALE MARKET ACCESS FOR QUALIFYING BTM DES AGGREGATIONS.

[p. 243, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243) (indent level 1)

“(a) DEFINITIONS.—In this section:

[p. 243, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243) (indent level 2)

“(1) COMMISSION.—The term ‘Commission’ means the Federal Energy Regulatory Commission.

[p. 243, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243) (indent level 2)

“(2) DOUBLE COMPENSATION.—The term ‘double compensation’ means payment through or by both a wholesale market and a State-jurisdictional retail market or program for providing the same service during the same time interval.

[p. 243, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=243) (indent level 1)

“(b) JUST AND REASONABLE PRACTICES.—Effective on the date that is 18 months after the date of enactment of this section, it shall not be just and reasonable within the meaning of sections 205 and 206 for any Transmission Organization to maintain rates, terms, or conditions of service that, by their terms and to the extent that such rates, terms, and conditions directly affect wholesale rates, prevent the participation of any qualifying BTM DES aggregation in wholesale energy, capacity, or ancillary services markets administered by the Transmission Organization.

[p. 244, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 1)

“(c) PROHIBITED PRACTICES.—The following practices shall not be considered to be just and reasonable within the meaning of sections 205 and 206:

[p. 244, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 2)

“(1) Imposing metering, telemetry, or equipment requirements that are inconsistent with the definitions of the terms ‘qualifying BTM DES facility’ and ‘qualifying BTM DES aggregation’ in section 3.

[p. 244, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 2)

“(2) Requiring a qualifying BTM DES facility or qualifying BTM DES aggregation to participate in the energy market as a precondition to participating in the capacity market.

[p. 244, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 2)

“(3) Requiring the joint participation with any resource co-located with a Qualifying BTM DES facility as a condition for inclusion in a qualifying BTM DES aggregation.

[p. 244, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 2)

“(4) Any other practice otherwise described in subsection (b).

[p. 244, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 1)

“(d) COMPLIANCE FILINGS.—

[p. 244, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=244) (indent level 2)

“(1) TRANSMISSION ORGANIZATION FILINGS.— Not later than 180 days after the date of enactment of this section, each Transmission Organization that administers a wholesale market subject to the jurisdiction of the Commission shall file with the Commission proposed rates, terms, and conditions of service that comply with the requirements of this section.

[p. 245, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 2)

“(2) COMMISSION ACTION.—Not later than 180 days after the filing of a proposal under paragraph (1), the Commission shall—

[p. 245, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 3)

“(A) approve the proposal if the Commission determines that the proposal complies with this section; or

[p. 245, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 3)

“(B) require or impose such changes as the Commission determines to be just, reasonable, and in compliance with this section.

[p. 245, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 1)

“(e) COMPLAINTS.—

[p. 245, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 2)

“(1) IN GENERAL.—The Commission shall act on the merits of any complaint alleging noncompliance with this section not later than 180 days after the date on which the complaint is filed.

[p. 245, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 2)

“(2) CONSOLIDATION.—To maximize administrative efficiency, the Commission may consolidate and act upon related complaints with respect to a given Transmission Organization.

[p. 245, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 1)

“(f) DUAL PARTICIPATION; PROHIBITION ON DOUBLE COMPENSATION.—

[p. 245, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=245) (indent level 2)

“(1) PRESERVATION OF STATE PROGRAM ELIGIBILITY.— Participation by a qualifying BTM DES facility in a State-jurisdictional retail market or program shall not disqualify the qualifying BTM DES facility from participating in a wholesale market administered by a Transmission Organization, and nothing in this section requires a qualifying BTM DES facility to participate in any wholesale market.

[p. 246, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=246) (indent level 2)

“(2) PROHIBITION ON DOUBLE COMPENSATION.— No qualifying BTM DES facility or qualifying BTM DES aggregation shall receive double compensation.

[p. 246, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=246) (indent level 2)

“(3) QUALIFYING BTM DES RATE FILING.—

[p. 246, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=246) (indent level 3)

“(A) IN GENERAL.—Not later than 180 days after the date of enactment of this section, each Transmission Organization shall file with the Commission under section 205 revisions to its tariff establishing settlement, metering, and telemetry protocols that exclude from wholesale market settlement the quantity of energy, ancillary service, or capacity, evaluated on a service-by-service basis, for which a qualifying BTM DES facility has received or will receive compensation under a State-jurisdictional retail market or program, such that, for example, a BTM DES facility that has earned retail energy credit but not ancillary services or capacity credit may receive wholesale compensation for capacity and ancillary services without receiving any wholesale energy compensation.

[p. 247, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=247) (indent level 3)

“(B) ELECTRIC UTILITIES.—Each public utility that provides distribution service to a qualifying BTM DES facility shall provide to the applicable Transmission Organization and aggregator, in a form and on a schedule established by the Transmission Organization, the interval metering data and program-participation information necessary to implement subparagraph (A), subject to such protections for customer-specific information as the applicable State commission may require.

[p. 247, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=247) (indent level 3)

“(C) CERTIFICATION.—

[p. 247, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=247) (indent level 4)

“(i) IN GENERAL.—Each aggregator shall certify to the applicable Transmission Organization, on a schedule established by the Commission—

[p. 247, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=247) (indent level 5)

“(I) each State-jurisdictional retail market or program from which each qualifying BTM DES facility has received compensation; and

[p. 247, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=247) (indent level 5)

“(II) on the basis of final determinations made by the Commission arising from the proceedings initiated under subparagraph (A), that no qualifying BTM DES facility in its aggregation has retained double compensation during the certification period.

[p. 248, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=248) (indent level 4)

“(ii) TREATMENT.—A certification under this subparagraph shall constitute a statement made to the Commission for purposes of sections 316 and 316A.

[p. 248, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=248) (indent level 2)

“(4) COMPLAINT WITH RESPECT TO DOUBLE COMPENSATION.—

[p. 248, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=248) (indent level 3)

“(A) IN GENERAL.—Any person, electric utility, State, municipality, or State commission aggrieved by alleged double compensation may file a complaint pursuant to section 206.

[p. 248, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=248) (indent level 3)

“(B) PROCEDURE.—In a proceeding initiated pursuant to a complaint under subparagraph (A), if a qualifying BTM DES facility or qualifying BTM DES aggregation that is the subject of the complaint meets the eligibility requirements of both a wholesale market and a State-jurisdictional program, the complainant in that proceeding shall—

[p. 248, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=248) (indent level 4)

“(i) bear the burden of proof before the Commission; and

[p. 249, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 4)

“(ii) demonstrate that—

[p. 249, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 5)

“(I) double compensation has in fact occurred or is imminent; and

[p. 249, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 5)

“(II) such double compensation could not be avoided through reasonable adjustments to—

[p. 249, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 6)

“(aa) wholesale market compensation received by the applicable qualifying BTM DES facility or qualifying BTM DES aggregation; or

[p. 249, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 6)

“(bb) the retail bill associated with the qualifying BTM DES facility or qualifying BTM DES aggregation, using metering and telemetry data that meets the requirements of the wholesale market.

[p. 249, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 3)

“(C) LIMITATION.—A complaint under subparagraph (A) shall be filed not later than 5 years after the date on which the alleged double compensation was received.

[p. 249, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=249) (indent level 2)

“(5) WHOLESALE MARKET COMPENSATION ADJUSTMENT.— If the Commission determines that double compensation could be avoided through an adjustment to a rate, term, or condition of service under the jurisdiction of the Commission pursuant to section 205, the Commission may initiate a proceeding consistent with section 206 to eliminate double compensation.

[p. 250, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250) (indent level 2)

“(6) DISGORGEMENT; PENALTIES.—

[p. 250, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250) (indent level 3)

“(A) DISGORGEMENT.—If the Commission finds that double compensation has occurred, the Commission shall order disgorgement of the full amount of the double compensation received.

[p. 250, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250) (indent level 3)

“(B) PENALTIES.—If the Commission determines that double compensation has been knowingly retained, the Commission may order penalties, which may include—

[p. 250, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250) (indent level 4)

“(i) monetary penalties of up to 3 times the amount of the double compensation received for each day that the double compensation was knowingly retained after the date of receipt, without regard to the limitations described in section 206(b); and

[p. 250, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=250) (indent level 4)

“(ii) suspension or termination of the participation of a qualifying BTM DES facility, qualifying BTM DES aggregation, or aggregator in a wholesale market administered by a Transmission Organization.

[p. 251, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 1)

“(g) ANNUAL REPORTING.—Each qualifying BTM DES facility and qualifying BTM DES aggregation participating in a wholesale market under this section shall submit to the Commission, not later than March 30 of each year, a public report that summarizes and quantifies all services provided by the qualifying BTM DES facility or qualifying BTM DES aggregation during the preceding calendar year to—

[p. 251, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 2)

“(1) wholesale markets subject to the jurisdiction of the Commission; and

[p. 251, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 2)

“(2) State-jurisdictional retail markets and programs within regions subject to the jurisdiction of the Commission.”.

[p. 251, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 1)

(d) DISTRIBUTION UTILITY INTERCONNECTION AND NON-INTERFERENCE.—Part II of the Federal Power Act (16 U.S.C. 824 et seq.) (as amended by subsection (c)) is amended by adding at the end the following:

[p. 251, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 0)

“SEC. 230. DISTRIBUTION UTILITY OBLIGATIONS WITH RESPECT TO QUALIFYING BTM DES FACILITIES AND QUALIFYING BTM DES AGGREGATIONS.

[p. 251, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 1)

“(a) DEFINITIONS.—In this section:

[p. 251, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=251) (indent level 2)

“(1) COMMISSION.—The term ‘Commission’ means the Federal Energy Regulatory Commission.

[p. 252, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252) (indent level 2)

“(2) DISTRIBUTION UTILITY; LOAD-SERVING ENTITY.—The terms ‘distribution utility’ and ‘load-serving entity’ have the meanings given those terms in section 217(a).

[p. 252, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252) (indent level 1)

“(b) INTERCONNECTION OBLIGATION.—

[p. 252, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252) (indent level 2)

“(1) IN GENERAL.—Except as otherwise provided by State law or by the State regulatory authority with jurisdiction over the distribution utility, any distribution utility located within the geographic footprint of an organized wholesale market administered by a Transmission Organization shall interconnect any behind-the-meter resource that is eligible to participate in that wholesale market, including any qualifying BTM DES facility or qualifying BTM DES aggregation, in a timely fashion and with rates, terms, and conditions of service that—

[p. 252, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252) (indent level 3)

“(A) allow the behind-the-meter resource to export energy to the grid, if applicable; and

[p. 252, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252) (indent level 3)

“(B) do not prevent, impede, or unreasonably condition the participation of the behind-the-meter resource in the wholesale market.

[p. 252, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=252) (indent level 2)

“(2) SAVINGS PROVISION.—Nothing in this subsection authorizes the Commission to prescribe the rates, terms, or conditions of distribution-level interconnection service.

[p. 253, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253) (indent level 1)

“(c) ACCEPTANCE OF WHOLESALE MARKET METERING DATA.—

[p. 253, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253) (indent level 2)

“(1) IN GENERAL.—Any distribution utility or load-serving entity providing retail electric service to a customer at whose premises a qualifying BTM DES facility or qualifying BTM DES aggregation is located shall accept the same metering and telemetry data used by the wholesale market for purposes of market participation by that qualifying BTM DES facility or qualifying BTM DES aggregation.

[p. 253, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253) (indent level 2)

“(2) REQUIREMENT.—The manner in which the data described in paragraph (1) is used to adjust the retail bill of a customer, including any adjustment to account for energy exported or withdrawn, shall be determined by the State regulatory authority having jurisdiction over retail rates.

[p. 253, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253) (indent level 1)

“(d) PROHIBITION ON INTERFERENCE.—

[p. 253, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253) (indent level 2)

“(1) IN GENERAL.—No distribution utility shall purposefully use its control over the distribution system or retail sales to prevent any behind-the-meter resource eligible to participate in a wholesale market subject to the jurisdiction of the Commission from participating in such wholesale market.

[p. 253, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=253) (indent level 2)

“(2) CERTAIN ACTIONS.—Nothing in this subsection limits a distribution utility from taking actions reasonably necessary to maintain the safety, reliability, or operations of the distribution system.

[p. 254, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 1)

“(e) COMMISSION ENFORCEMENT.—

[p. 254, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 2)

“(1) IN GENERAL.—The Commission shall have authority to enforce the provisions of this section, and any person may file with the Commission a complaint alleging a violation of this section.

[p. 254, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 2)

“(2) REQUIREMENT.—The Commission shall act on the merits of any complaint filed under paragraph (1) not later than 180 days after the date on which the complaint is filed.

[p. 254, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 1)

“(f) APPLICABILITY TO PUBLIC POWER AND CERTAIN COOPERATIVES.—Except to the extent that compliance is required under State law, the requirements of subsections (b), (c), and (d) shall be voluntary with respect to distribution utilities that are entities described in section 201(f).”.

[p. 254, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 1)

(e) ESTABLISHMENT OF PROGRAM TO FACILITATE VOLUNTARY STREAMLINED PROCESS FOR LOCAL PERMITTING OF QUALIFYING DISTRIBUTED ENERGY SYSTEMS.—

[p. 254, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 2)

(1) DEFINITIONS.—In this subsection:

[p. 254, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=254) (indent level 3)

(A) AUTHORITY HAVING JURISDICTION.— The term “authority having jurisdiction” means any State, county, local, or Tribal office or official with jurisdiction—

[p. 255, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=255) (indent level 4)

(i) to issue permits relating to qualifying distributed energy systems;

[p. 255, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=255) (indent level 4)

(ii) to conduct inspections to enforce the requirements of a relevant code or standard relating to qualifying distributed energy systems; or

[p. 255, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=255) (indent level 4)

(iii) to approve the installation of, or the equipment and materials used in the installation of, qualifying distributed energy systems.

[p. 255, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=255) (indent level 3)

(B) QUALIFYING DISTRIBUTED ENERGY SYSTEM.—The term “qualifying distributed energy system” means any equipment or materials installed in, on, or near a building or premises to support onsite or local energy use, including equipment or materials, the primary function of which is—

[p. 255, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=255) (indent level 4)

(i) to generate electricity from distributed renewable energy sources, including solar photovoltaic systems or similar solar energy technologies;

[p. 256, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=256) (indent level 4)

(ii) to store and discharge electricity from batteries with a capacity of at least 2 kilowatt hours;

[p. 256, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=256) (indent level 4)

(iii) to charge a plug-in electric drive vehicle at a power rate of at least 2 kilowatts; or

[p. 256, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=256) (indent level 4)

(iv) to refuel a hydrogen fuel cell electric vehicle.

[p. 256, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=256) (indent level 3)

(C) SECRETARY.—The term “Secretary” means the Secretary of Energy.

[p. 256, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=256) (indent level 2)

(2) PROGRAM.—Not later than 180 days after the date of enactment of this Act, the Secretary, in consultation with trade associations and other entities representing distributed energy system installers, organizations representing State, local, and Tribal governments engaged in permitting, and other interested stakeholders, shall carry out a program to further develop, expand, and support the adoption of a voluntary streamlined permitting and inspection process for authorities having jurisdiction to use for the permitting of qualifying distributed energy systems.

[p. 256, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=256) (indent level 2)

(3) ACTIVITIES OF THE PROGRAM.—In carrying out the program established under paragraph (2), the Secretary shall—

[p. 257, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 3)

(A) further develop and expand an exemplary streamlined permitting process that includes an online permitting platform—

[p. 257, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 4)

(i) for expediting, standardizing, and streamlining permitting; and

[p. 257, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 4)

(ii) that authorities having jurisdiction may voluntarily use to receive, review, and approve permit applications relating to qualifying distributed energy systems;

[p. 257, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 3)

(B) establish targets for the adoption of a streamlined, expedited permitting process by authorities having jurisdiction;

[p. 257, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 3)

(C) provide technical assistance and training directly or indirectly to authorities having jurisdiction on using and adopting the exemplary streamlined permitting process described in subparagraph (A), including the adoption of any necessary building codes;

[p. 257, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 3)

(D) develop a voluntary inspection protocol and related tools to expedite, standardize, and streamline the inspection of qualifying distributed energy systems, including—

[p. 257, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=257) (indent level 4)

(i) by investigating the potential for using remote inspections;

[p. 258, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=258) (indent level 4)

(ii) by investigating the potential for sample-based inspection for distributed energy system installers with a demonstrated track record of high-quality work; and

[p. 258, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=258) (indent level 4)

(iii) by investigating opportunities to integrate the voluntary inspection protocol into the online permitting platform described in subparagraph (A) and the platforms of government software providers; and

[p. 258, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=258) (indent level 3)

(E) take any other action to expedite, standardize, streamline, or improve the process for permitting, inspecting, or interconnecting qualifying distributed energy systems.

[p. 258, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=258) (indent level 2)

(4) SUPPORT SERVICES.—The Secretary shall—

[p. 258, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=258) (indent level 3)

(A) support the provision of technical assistance to authorities having jurisdiction, any administrator of the online permitting platform described in paragraph (3)(A), government software providers, and any other entity determined appropriate by the Secretary in carrying out the activities described in paragraph (3); and

[p. 258, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=258) (indent level 3)

(B) provide such financial assistance as the Secretary determines appropriate from any funds appropriated to carry out this subsection.

[p. 259, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259) (indent level 2)

(5) AUTHORITY HAVING JURISDICTION CERTIFICATION PROGRAM.—

[p. 259, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259) (indent level 3)

(A) IN GENERAL.—The Secretary may certify authorities having jurisdiction that implement the exemplary streamlined permitting process described in paragraph (3)(A).

[p. 259, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259) (indent level 3)

(B) PROCESS.—The Secretary may confer a certification under subparagraph (A) through existing programs within the Department of Energy.

[p. 259, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259) (indent level 3)

(C) PRIZES.—The Secretary may award prizes to authorities having jurisdiction, using funds appropriated to the Secretary to carry out this subsection, to encourage authorities having jurisdiction to adopt the exemplary streamlined permitting process or the voluntary inspection protocol established under subparagraphs (A) and (D) of paragraph (3), respectively.

[p. 259, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=259) (indent level 2)

(6) AUTHORIZATION OF APPROPRIATIONS.— There is authorized to be appropriated to the Secretary to carry out this subsection $20,000,000 for each of fiscal years 2026 through 2031.