# Sec. 2213. Accelerating renewable energy permitting

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2213)

## Summary

Interior or the Forest Service must tell an eligible-project applicant within 30 days whether its right-of-way application is complete. ([p. 299, line 11 to p. 299, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299)) If an EIS is needed, the agency has 90 days after finding the application complete to issue a notice of intent. ([p. 300, line 6 to p. 300, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=300)) Within 30 days after a complete application is submitted, it must issue any required cost-recovery agreement and grant, deny or defer the application. ([p. 300, line 13 to p. 300, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=300)) Deferral requires notice of remaining steps and agency timelines. ([p. 301, line 12 to p. 301, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301))

Within 180 days, both departments must develop or adopt categorical exclusions for listed low-disturbance renewable activities, with extraordinary-circumstances exceptions. ([p. 301, line 24 to p. 302, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301)) The list includes previously analyzed disturbances under 5 acres, certain repeat activities, small solar projects, surveys and meteorological towers. ([p. 302, line 11 to p. 302, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=302)) BLM must issue standard renewable review standards within 2 years. ([p. 304, line 12 to p. 304, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304))

## Key points

- 30-day completeness and decision clocks for renewable rights-of-way on public land ([p. 299, line 11 to p. 299, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299))
- Categorical exclusions for small solar, met towers and geotechnical work within 180 days ([p. 301, line 22 to p. 301, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301))
- Storage added to the definition of an eligible renewable project ([p. 303, line 22 to p. 303, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303))

## Selected statutory quotes

> The installation, modification, operation, or removal of commercially available solar photovoltaic systems located on— (i) a building or other structure (such as a rooftop, parking lot, or facility, or mounted to signage, lighting, gates, or fences); or (ii) previously disturbed or developed land comprising less than 10 acres.

[p. 303, line 4 to p. 303, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303)

Small solar installations are to be excluded from NEPA review.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

No statutory deadlines for renewable right-of-way applications; Interior's July 2025 policy sent wind and solar decisions to the Secretary's office for sign-off.

### EPRA 2024 (reported S. 4753)

Carried over from EPRA 2024 (secs. 206 and 207): the right-of-way clocks, the low-disturbance exclusions, storage as an eligible project, and the BLM review standards. EPRA's national goal of at least 50 gigawatts of renewable energy authorized on federal land by 2030 is not in this bill.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 298, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=298) (indent level 1)

(a) DEFINITIONS.—In this section:

[p. 298, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=298) (indent level 2)

(1) ELIGIBLE PROJECT.—The term “eligible project” has the meaning given the term in section 3101 of the Energy Act of 2020 (43 U.S.C. 3001) (as amended by subsection (d)).

[p. 299, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299) (indent level 2)

(2) PREVIOUSLY DISTURBED OR DEVELOPED.— The term “previously disturbed or developed” has the meaning given the term in section 1021.410(g)(1) of title 10, Code of Federal Regulations (as in effect on July 2, 2025).

[p. 299, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299) (indent level 1)

(b) DEADLINE FOR CONSIDERATION OF APPLICATIONS FOR RIGHTS-OF-WAY.—

[p. 299, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299) (indent level 2)

(1) COMPLETENESS OF REVIEW.—

[p. 299, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299) (indent level 3)

(A) IN GENERAL.—Not later than 30 days after the date on which the Secretary of the Interior or the Secretary of Agriculture, as applicable, receives an application for a right-of-way under section 501 of the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1761) for an eligible project, the applicable Secretary shall—

[p. 299, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299) (indent level 4)

(i) notify the applicant that the application is complete; or

[p. 299, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=299) (indent level 4)

(ii) notify the applicant that information is missing from the application and specify any information that is required to be submitted for the application to be complete.

[p. 300, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=300) (indent level 3)

(B) ENVIRONMENTAL IMPACT STATEMENT.— For an eligible project that requires an environmental impact statement for an application submitted under subparagraph (A), the Secretary of the Interior or the Secretary of Agriculture, as applicable, shall issue a notice of intent not later than 90 days after the date on which the applicable Secretary determines that an application is complete under subparagraph (A).

[p. 300, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=300) (indent level 2)

(2) COST RECOVERY AND ISSUANCE OR DEFERRAL.—

[p. 300, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=300) (indent level 3)

(A) IN GENERAL.—Not later than 30 days after the date on which an applicant submits a complete application for a right-of-way under paragraph (1), the Secretary of the Interior or the Secretary of Agriculture, as applicable, shall, if a cost recovery agreement is required under section 2804.14 of title 43, Code of Federal Regulations (or successor regulations), or section 251.58 of title 36, Code of Federal Regulations (or successor regulations), issue a cost recovery agreement.

[p. 300, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=300) (indent level 3)

(B) DECISION.—Not later than 30 days after the date on which an applicant submits a complete application for a right-of-way under paragraph (1), the Secretary of the Interior or the Secretary of Agriculture, as applicable, shall—

[p. 301, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301) (indent level 4)

(i) grant or deny the application, if the requirements under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and any other applicable law have been completed; or

[p. 301, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301) (indent level 4)

(ii) defer the decision on the application and provide to the applicant notice—

[p. 301, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301) (indent level 5)

(I) that specifies steps that the applicant can take for the decision on the application to be issued; and

[p. 301, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301) (indent level 5)

(II) of a list of actions that need to be taken by the agency in order to comply with applicable law, and timelines and deadlines for completing those actions.

[p. 301, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301) (indent level 1)

(c) LOW DISTURBANCE ACTIVITIES FOR RENEWABLE ENERGY PROJECTS.—

[p. 301, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=301) (indent level 2)

(1) IN GENERAL.—Not later than 180 days after the date of enactment of this Act, to facilitate timely permitting of eligible projects, the Secretary of the Interior and the Secretary of Agriculture shall each develop or adopt 1 or more categorical exclusions, including allowing for extraordinary circumstances under which the categorical exclusion shall not be available, under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for low disturbance activities necessary for renewable energy projects.

[p. 302, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=302) (indent level 2)

(2) ACTIVITIES DESCRIBED.—Low disturbance activities referred to in paragraph (1) are the following:

[p. 302, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=302) (indent level 3)

(A) Individual surface disturbances of less than 5 acres that have undergone site-specific analysis in a document prepared pursuant to the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) that has been previously completed.

[p. 302, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=302) (indent level 3)

(B) Activities at a location at which the same type of activity has previously occurred within 5 years prior to the date of commencement of the activity.

[p. 302, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=302) (indent level 3)

(C) Activities on previously disturbed or developed land for which an approved land use plan or any environmental document prepared pursuant to the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) analyzed such activity as reasonably foreseeable, so long as such plan or document was approved within 5 years prior to the date of the activity.

[p. 303, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 3)

(D) The installation, modification, operation, or removal of commercially available solar photovoltaic systems located on—

[p. 303, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 4)

(i) a building or other structure (such as a rooftop, parking lot, or facility, or mounted to signage, lighting, gates, or fences); or

[p. 303, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 4)

(ii) previously disturbed or developed land comprising less than 10 acres.

[p. 303, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 3)

(E) Maintenance of a minor activity, other than any construction or major renovation, or a building or facility.

[p. 303, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 3)

(F) Preliminary geotechnical investigations.

[p. 303, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 3)

(G) The construction and removal of meteorological evaluation towers.

[p. 303, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=303) (indent level 1)

(d) DEFINITION OF ELIGIBLE PROJECT.—Paragraph (4) of section 3101 of the Energy Act of 2020 (43 U.S.C. 3001) is amended by inserting “or store” after “generate”.

[p. 304, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304) (indent level 1)

(e) RENEWABLE ENERGY PROJECT REVIEW STANDARDS.— Section 3102 of the Energy Act of 2020 (43 U.S.C. 3002) is amended—

[p. 304, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304) (indent level 2)

(1) by redesignating subsection (f) as subsection (g); and

[p. 304, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304) (indent level 2)

(2) by inserting after subsection (e) the following:

[p. 304, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304) (indent level 1)

“(f) RENEWABLE ENERGY PROJECT REVIEW STANDARDS.— Not later than 2 years after the date of enactment of the Bipartisan American Affordability and Jobs Act of 2026, for the purpose of encouraging standardized reviews and facilitating the permitting of eligible projects, the National Renewable Energy Coordination Office of the Bureau of Land Management shall promulgate renewable energy project review standards to be adopted by regional renewable energy coordination offices.”.