# Sec. 2214. Electric grid projects

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2214)

## Summary

Directs Interior and Agriculture to adopt, within 180 days, categorical exclusions for placing power lines in approved corridors. ([p. 304, line 23 to p. 305, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304)) Another exclusion covers upgrades and reconductoring of existing lines in existing rights-of-way or on previously disturbed land. ([p. 305, line 14 to p. 305, line 19](https://pranava0x0.github.io/permittingreform/bill.pdf#page=305)) A third exclusion covers battery storage on previously disturbed land. ([p. 305, line 20 to p. 305, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=305))

## Key points

- Categorical exclusions for grid work on federal land within 180 days ([p. 304, line 23 to p. 305, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304))

## Selected statutory quotes

> Construction, operation, upgrade, or decommissioning of a battery or other energy storage technology on previously disturbed or developed land.

[p. 305, line 20 to p. 305, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=305)

Battery storage on disturbed federal land gets a categorical exclusion.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

Agencies have partial administrative exclusions; no statutory mandate.

### EPRA 2024 (reported S. 4753)

Carried over from EPRA 2024 (sec. 209, electric grid projects).

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 304, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304) (indent level 1)

(a) DEFINITION OF PREVIOUSLY DISTURBED OR DEVELOPED.— In this section, the term “previously disturbed or developed” has the meaning given the term in section 1021.410(g)(1) of title 10, Code of Federal Regulations (or successor regulations).

[p. 304, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=304) (indent level 1)

(b) RULEMAKING.—Not later than 180 days after the date of enactment of this Act, to facilitate timely permitting, the Secretary of the Interior and the Secretary of Agriculture shall each develop or adopt 1 or more categorical exclusions, including allowing for extraordinary circumstances under which the categorical exclusion shall not be available, under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for the following activities:

[p. 305, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=305) (indent level 2)

(1) Placement of an electric transmission or distribution facility in an approved right-of-way corridor, including a corridor designated under section 368 of the Energy Policy Act of 2005 (42 U.S.C. 15926).

[p. 305, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=305) (indent level 2)

(2) Any repair, maintenance, replacement, upgrade, modification, optimization, or minor relocation of, or addition to, an existing electric transmission or distribution facility or associated infrastructure, including electrical substations, within an existing right-of-way or on otherwise previously disturbed or developed land, including reconductoring and installation of grid-enhancing technologies.

[p. 305, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=305) (indent level 2)

(3) Construction, operation, upgrade, or decommissioning of a battery or other energy storage technology on previously disturbed or developed land.