# Sec. 2223. Geothermal leasing reform

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2223)

## Summary

Requires geothermal lease sales every year instead of every 2 years, with a replacement sale in the same year if one is cancelled, and sets 30-day completeness and 30-day decision deadlines for geothermal drilling permits. ([p. 329, line 18 to p. 329, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329))

## Key points

- Annual geothermal lease sales ([p. 329, line 18 to p. 329, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329))
- 30-day drilling permit clocks ([p. 330, line 3 to p. 330, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330))

## Selected statutory quotes

> If a lease sale under paragraph (1) for a year is cancelled or delayed, the Secretary shall conduct a replacement sale during the same year.

[p. 329, line 18 to p. 329, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329)

A cancelled lease sale must be replaced the same year.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

Lease sales at least every 2 years; no permit deadlines.

### EPRA 2024 (reported S. 4753)

Carried over from EPRA 2024 (sec. 208(b) and (c)), with the completeness check lengthened from 10 to 30 days and a hard 10-day deadline added for deferred decisions.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 329, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329) (indent level 1)

(a) ANNUAL LEASING.—Section 4(b) of the Geothermal Steam Act of 1970 (30 U.S.C. 1003(b)) is amended—

[p. 329, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329) (indent level 2)

(1) in paragraph (2), by striking “2 years” and inserting “year”;

[p. 329, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329) (indent level 2)

(2) by adding at the end the following:

[p. 329, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329) (indent level 2)

“(5) REPLACEMENT SALES.—If a lease sale under paragraph (1) for a year is cancelled or delayed, the Secretary shall conduct a replacement sale during the same year.”.

[p. 329, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=329) (indent level 1)

(b) DEADLINES FOR CONSIDERATION OF GEOTHERMAL DRILLING PERMITS.—Section 4 of the Geothermal Steam Act of 1970 (30 U.S.C. 1003) is amended by adding at the end the following:

[p. 330, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 1)

“(h) DEADLINES FOR CONSIDERATION OF GEOTHERMAL DRILLING PERMITS.—

[p. 330, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 2)

“(1) NOTICE.—Not later than 30 days after the date on which the Secretary receives an application for any geothermal drilling permit, the Secretary shall—

[p. 330, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 3)

“(A) provide written notice to the applicant that the application is complete; or

[p. 330, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 3)

“(B) notify the applicant that information is missing and specify any information that is required to be submitted for the application to be complete.

[p. 330, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 2)

“(2) ISSUANCE OR DEFERRAL.—

[p. 330, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 3)

“(A) IN GENERAL.—Not later than 30 days after the Secretary has provided written notice to an applicant for a geothermal drilling permit that the application for such permit is complete pursuant to paragraph (1)(A), the Secretary shall—

[p. 330, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=330) (indent level 4)

“(i) issue the permit, if the requirements under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and other applicable law have been completed within the timeframe; or

[p. 331, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=331) (indent level 4)

“(ii) defer the decision on the permit and provide to the applicant a notice—

[p. 331, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=331) (indent level 5)

“(I) that specifies any steps that the applicant could take for the permit to be issued; and

[p. 331, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=331) (indent level 5)

“(II) that includes a list of actions that need to be taken by the agency to comply with applicable law, together with timelines and deadlines for taking those actions, which shall not exceed the deadlines specified in section 107(g) of the National Environmental Policy Act of 1969 (42 U.S.C. 4336a(g)).

[p. 331, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=331) (indent level 3)

“(B) DEADLINE FOR DEFERRED DECISIONS.— If the Secretary defers a decision on a permit under subparagraph (A)(ii), the Secretary shall issue a decision on the permit not later than 10 days after—

[p. 331, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=331) (indent level 4)

“(i) the applicant takes any steps specified under subparagraph (A)(ii)(I); and

[p. 331, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=331) (indent level 4)

“(ii) the agency takes the actions described in subparagraph (A)(ii)(II) in accordance with any applicable timelines and deadlines.”.