# Sec. 2233. Hydropower maintenance and temporary adjustments

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2233)

## Summary

Bars FERC from requiring license amendments for routine hydropower maintenance, repair or replacement, or for temporary operating variances caused by events outside the licensee's control. ([p. 355, line 8 to p. 355, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355)) FERC must propose a rule within 90 days and finish within a further 180 days defining which alterations are substantial enough to need approval. ([p. 355, line 14 to p. 355, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355)) Dam safety authority is preserved. ([p. 357, line 3 to p. 357, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357))

## Key points

- No FERC approval needed for routine hydropower maintenance ([p. 355, line 8 to p. 355, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355))

## Selected statutory quotes

> The Commission shall not require approval or an amendment to a project license for any routine maintenance, repair, or replacement of any portion of a project works

[p. 355, line 8 to p. 355, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355)

Routine dam maintenance no longer needs FERC sign-off.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

FERC reviews many post-licensing changes individually. It opened an inquiry in November 2025 (Docket RM26-3).

### EPRA 2024 (reported S. 4753)

Not in EPRA 2024.

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 354, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=354) (indent level 1)

(a) ALTERATIONS IN PROJECT WORKS.—Section 10(b) of the Federal Power Act (16 U.S.C. 803(b)) is amended by adding at the end the following: “Except as previously provided in this subsection, the Commission shall require prior approval of a ‘substantial alteration or addition’ to project works or to project operations consisting of any significant modification of the project works or operation of the project that is not in conformity with the project plans previously approved by the Commission. The Commission shall not require approval of any alteration or addition as determined pursuant to regulations promulgated under section 2233(c) of the Bipartisan American Affordability and Jobs Act of 2026 or any temporary variance to the project operations necessitated by circumstances beyond the reasonable control of the licensee, including extreme weather, natural disasters, equipment failures, or other unforeseen circumstances.”.

[p. 355, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355) (indent level 1)

(b) MAINTENANCE AND REPAIR OF PROJECT WORKS.—Section 10(c) of the Federal Power Act (16 U.S.C. 803(c)) is amended by inserting after the first sentence the following: “The Commission shall not require approval or an amendment to a project license for any routine maintenance, repair, or replacement of any portion of a project works necessary to maintain the project works in accordance with this subsection.”.

[p. 355, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355) (indent level 1)

(c) GUIDANCE AND PROCESS.—

[p. 355, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=355) (indent level 2)

(1) GUIDANCE.—Not later than 90 days after the date of enactment of this Act, the Federal Energy Regulatory Commission shall issue a notice of proposed rulemaking proposing a process or considerations for determining a “substantial alteration or addition”, “nonsubstantial alteration or addition”, and “routine maintenance, repair, or replacement” to a hydropower project works based on the results of the Notice of Inquiry of the Federal Energy Regulatory Commission entitled “Authorizations for Certain Post-Licensing Activities at Hydroelectric Projects” (90 Fed. Reg. 53310; Docket No. RM26-3-000) issued on November 20, 2025, initially scheduled to close on January 26, 2026, but extended and officially closed on February 10, 2026.

[p. 356, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=356) (indent level 2)

(2) PROCESS.—Not later than 180 days after the date of the issuance of the notice of proposed rulemaking under paragraph (1), and after public notice and opportunity for comment, the Federal Energy Regulatory Commission shall promulgate a final rule establishing—

[p. 356, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=356) (indent level 3)

(A) standards for determining a “substantial alteration or addition”, “nonsubstantial alteration or addition”, and “routine maintenance, repair, or replacement” to a hydropower project works; and

[p. 356, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=356) (indent level 3)

(B) a formal process, as appropriate, for determining whether a proposed alteration or addition constitutes a “substantial alteration or addition” under the final rule that requires approval of the Federal Energy Regulatory Commission under section 10(b) of the Federal Power Act (16 U.S.C. 803(b)).

[p. 356, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=356) (indent level 2)

(3) EFFECT.—The rule promulgated under paragraph (2) shall establish a process or considerations for determining which licensee-requested project alterations require the approval of the Federal Energy Regulatory Commission.

[p. 357, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357) (indent level 1)

(d) SAVINGS CLAUSE.—Nothing in this section or an amendment made by this section—

[p. 357, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357) (indent level 2)

(1) affects any authority of the Commission—

[p. 357, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357) (indent level 3)

(A) to require notice from a licensee under subsection (a) or (b) of section 10 of the Federal Power Act (16 U.S.C. 803); or

[p. 357, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357) (indent level 3)

(B) to enforce requirements of that section or the terms of a license issued under part I of the Federal Power Act (16 U.S.C. 792 et seq.) with respect to the safety of any dam and appurtenant works and structures; or

[p. 357, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357) (indent level 2)

(2)(A) precludes any prompt, informal consultation between the licensee and the Commission, at the request of the licensee or the Commission, with respect to the safety of any dam and appurtenant works and structures in advance of work to be undertaken under section 10 of the Federal Power Act (16 U.S.C. 803); or

[p. 357, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=357) (indent level 3)

(B) affects any authority of the Commission to require changes in advance of the work described in subparagraph (A) to protect the safety of any dam and appurtenant works and structures.