# Sec. 2252. Offshore energy transmission

BAAJA draft released September 30, 2026. AI-assisted analysis; proposed changes.

Saved AI review: 794 supported, 0 flagged, 18 unchecked of 812 statements; checked 2026-10-06; stale: true. Coverage excludes current-law comparison cells and some research paraphrases. Read data/core.json checks for link and quote results and their dates. A stale review does not verify the current wording.

[Official PDF](https://www.epw.senate.gov/public/_cache/files/5/c/5c5f5935-b224-48e7-abea-e60c30e7a4cf/7935BF3C85967B6F56F6F4858FD3221B7E0AEB02D04BE391CAFBD1B884CE3DC5.bipartisan-american-affordability-and-jobs-act-text.pdf) · [Browser section](https://pranava0x0.github.io/permittingreform/#/bill/sec/2252)

## Summary

Directs Interior and Energy to identify preferred routes for offshore transmission cables within 2 years and review them every 3 years. ([p. 367, line 15 to p. 367, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367)) Interior is the lead agency for offshore transmission permitting, and a final rule is required within 2 years. ([p. 369, line 8 to p. 369, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369)) Offshore transmission rights-of-way may be issued competitively or noncompetitively by Interior. ([p. 370, line 8 to p. 370, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370))

## Key points

- Planned offshore transmission routes within 2 years ([p. 367, line 15 to p. 368, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367))
- Interior is lead agency; rights-of-way can be noncompetitive ([p. 369, line 8 to p. 369, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369))

## Selected statutory quotes

> shall identify preferred routes on the outer Continental Shelf for transmission cables and sub-seabed infrastructure

[p. 367, line 22 to p. 367, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367)

Interior and Energy must identify preferred offshore cable routes.

## Comparison notes

- [SPEED Act (H.R. 4776), engrossed in House](https://www.govinfo.gov/content/pkg/BILLS-119hr4776eh/html/BILLS-119hr4776eh.htm)
- [Energy Permitting Reform Act of 2024 (S. 4753), reported in Senate](https://www.govinfo.gov/content/pkg/BILLS-118s4753rs/html/BILLS-118s4753rs.htm)

### Current law

Each offshore transmission line is permitted on its own.

### EPRA 2024 (reported S. 4753)

Not in EPRA 2024, which made offshore lines eligible for FERC backstop siting and cost allocation (kept in section 2101).

### SPEED Act (House-passed H.R. 4776)

Not in the SPEED Act.

## Full statutory text

Extracted from the official PDF; line cites mark paragraph starts. Consult the PDF for exact layout.

[p. 365, line 2](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 1)

(a) DEFINITIONS.—In this section:

[p. 365, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 2)

(1) BACKBONE LINE.—The term “backbone line” means a transmission line that connects multiple offshore transmission substitutions.

[p. 365, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 2)

(2) FEDERAL AUTHORIZATION.—

[p. 365, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 3)

(A) IN GENERAL.—The term “Federal authorization” means any authorization required under Federal law in order to site an offshore transmission facility.

[p. 365, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 3)

(B) INCLUSIONS.—The term “Federal authorization” includes such permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law in order to site an offshore transmission facility.

[p. 365, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 2)

(3) OFFSHORE GENERATION FACILITY.—The term “offshore generation facility” means a facility that—

[p. 365, line 20](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 3)

(A) is located on the outer Continental Shelf; and

[p. 365, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 3)

(B) produces electric energy.

[p. 365, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 2)

(4) OFFSHORE TRANSMISSION FACILITY.—

[p. 365, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=365) (indent level 3)

(A) IN GENERAL.—The term “offshore transmission facility” means a facility, such as a line or cable, and any related infrastructure or equipment, such as a substation or converter station, that is used for the transmission of electric energy—

[p. 366, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 4)

(i) between 2 or more offshore generation facilities, including—

[p. 366, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 5)

(I) offshore generation facilities within a single offshore energy project; and

[p. 366, line 9](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 5)

(II) offshore generation facilities in different offshore energy projects; or

[p. 366, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 4)

(ii) between 1 or more offshore generation facilities and an interconnection with an onshore electric grid.

[p. 366, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 3)

(B) INCLUSIONS.—The term “offshore transmission facility” includes a radial line, a backbone line, and any transmission line.

[p. 366, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 2)

(5) OPTIMAL POINT OF INTERCONNECTION.— The term “optimal point of interconnection” means a point of interconnection that minimizes—

[p. 366, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 3)

(A) delays;

[p. 366, line 22](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 3)

(B) local impacts; and

[p. 366, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 3)

(C) the need for grid updates.

[p. 366, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=366) (indent level 2)

(6) OUTER CONTINENTAL SHELF.—The term “outer Continental Shelf” has the meaning given the term in section 2 of the Outer Continental Shelf Lands Act (43 U.S.C. 1331).

[p. 367, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367) (indent level 2)

(7) RADIAL LINE.—The term “radial line” means a transmission line that is used to link 1 or more offshore energy projects to the bulk-power system (as defined in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a))).

[p. 367, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367) (indent level 2)

(8) SECRETARY.—The term “Secretary” means the Secretary of the Interior.

[p. 367, line 10](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367) (indent level 2)

(9) STATE.—The term “State” has the meaning given the term in section 2 of the Outer Continental Shelf Lands Act (43 U.S.C. 1331).

[p. 367, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367) (indent level 1)

(b) IDENTIFICATION OF PREFERRED ROUTES.—

[p. 367, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367) (indent level 2)

(1) IN GENERAL.—

[p. 367, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=367) (indent level 3)

(A) INITIAL IDENTIFICATION.—Not later than 2 years after the date of enactment of this Act, the Secretary and the Secretary of Energy (referred to in this subsection as the “Secretaries”), in coordination with relevant Federal agencies involved in the permitting of offshore generation facilities and offshore transmission facilities, shall identify preferred routes on the outer Continental Shelf for transmission cables and sub-seabed infrastructure (where such routes have not yet been identified), including—

[p. 368, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 4)

(i) between offshore generation facilities; and

[p. 368, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 4)

(ii) between offshore generation facilities and optimal points of interconnection with onshore electric grids.

[p. 368, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 3)

(B) PERIODIC REVIEW.—Not less frequently than once every 3 years after the initial identification of preferred routes in accordance with subparagraph (A), the Secretaries, in coordination with relevant Federal agencies involved in the permitting of offshore generation facilities and offshore transmission facilities, shall—

[p. 368, line 14](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 4)

(i) determine whether additional preferred routes are needed; and

[p. 368, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 4)

(ii) if applicable, identify any additional preferred routes.

[p. 368, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 2)

(2) CONSIDERATIONS.—In identifying preferred routes under paragraph (1), the Secretaries shall take into account—

[p. 368, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 3)

(A) existing rights-of-way and existing sub-seabed infrastructure;

[p. 368, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=368) (indent level 3)

(B) the optimal points of interconnection between offshore generation facilities and onshore electric grids; and

[p. 369, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369) (indent level 3)

(C) impacts on the marine environment, including critical habitats or protected areas, marine organisms, including protected or endangered species, and other ocean users, including fisheries.

[p. 369, line 6](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369) (indent level 1)

(c) SITING, PERMITTING, AND AUTHORIZATIONS.—

[p. 369, line 7](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369) (indent level 2)

(1) LEAD AGENCY.—With respect to an offshore transmission facility, the Department of the Interior shall act as the lead agency for purposes of coordinating all applicable Federal authorizations and related environmental reviews of the facility.

[p. 369, line 12](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369) (indent level 2)

(2) RULEMAKING.—

[p. 369, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369) (indent level 3)

(A) IN GENERAL.—Not later than 2 years after the date of enactment of this Act, the Secretary, in coordination with other relevant Federal agencies, shall issue, pursuant to section 5 of the Outer Continental Shelf Lands Act (43 U.S.C. 1334), a final rule relating to Federal authorizations for offshore transmission facilities.

[p. 369, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=369) (indent level 3)

(B) CONSIDERATIONS.—In carrying out subparagraph (A), the Secretary shall consider—

[p. 370, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 4)

(i) establishing 1 or more procedures for soliciting information about existing and potential rights-of-way;

[p. 370, line 4](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 4)

(ii) establishing a process for determining interest in the use of 1 or more rights-of-way, including backboned or meshed rights-of-way;

[p. 370, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 4)

(iii) establishing a process for the issuance of rights-of-way, on a competitive or noncompetitive basis, as appropriate, which may include consideration of whether a developer—

[p. 370, line 13](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 5)

(I) has an award from a State via a competitive process;

[p. 370, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 5)

(II) has an existing agreement to interconnect a transmission project; or

[p. 370, line 17](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 5)

(III) has submitted an interconnection request in accordance with the pro forma Large Generator Interconnection Procedures promulgated pursuant to section 35.28(f) of title 18, Code of Federal Regulations (or successor regulations);

[p. 370, line 24](https://pranava0x0.github.io/permittingreform/bill.pdf#page=370) (indent level 4)

(iv) any requirements relating to environmental reviews for—

[p. 371, line 1](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 5)

(I) independent transmission projects; and

[p. 371, line 3](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 5)

(II) transmission projects within existing rights-of-way; and

[p. 371, line 5](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 4)

(v) the requirements described in section 8(p)(4) of the Outer Continental Shelf Lands Act (43 U.S.C. 1337(p)(4)).

[p. 371, line 8](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 2)

(3) AMENDMENT.—Section 8(p)(3) of the Outer Continental Shelf Lands Act (43 U.S.C. 1337(p)(3)) is amended—

[p. 371, line 11](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 3)

(A) by striking “, the Secretary shall issue a lease, easement, or right-of-way” and inserting the following: “(43 U.S.C. 1337 note; Public Law 109–58), the Secretary—

[p. 371, line 15](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 3)

“(A) shall issue a lease or easement”; and

[p. 371, line 16](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 3)

(B) in subparagraph (A) (as so designated)—

[p. 371, line 18](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 4)

(i) by striking “lease, easement, or right-of-way” and inserting “lease or easement”; and

[p. 371, line 21](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 4)

(ii) by striking the period at the end and inserting the following: “; and

[p. 371, line 23](https://pranava0x0.github.io/permittingreform/bill.pdf#page=371) (indent level 3)

“(B) may issue a right-of-way on a competitive or noncompetitive basis, as the Secretary determines to be appropriate.”.