EL26-67-000 · 2026-08-14 · FERC

Letter order granting the PJM, Indicated PJM Transmission Owners and Silver Run Electric abeyance motions

Read topic-matched comments in EL26-67

Topics in the text: Filing procedure · Cost allocation · Connecting load and generation

What the document says

Unpaginated filing

Five of six cases go into 90-day abeyance; responses are due November 16.

Therefore, responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text

Unpaginated filing

A timely section 205 filing suspends that respondent's duty to answer the show-cause order.

then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text

Unpaginated filing

FERC granted abeyance because each movant described its coming filing and named a filing date.

PJM, Indicated PJM TOs, and Silver Run have provided robust descriptions of the filings they anticipate making, provided a date by which they intend to make such filings Source text

Unpaginated filing

FERC wants the tariff changes in fast, with an effective date that respects existing deals.

we encourage PJM and/or Transmission Owners to propose an effective date that takes into account the necessary time to implement the proposed Tariff revisions and accommodate existing commercial arrangements Source text

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

In this order, we grant the Abeyance Motions filed by PJM, Indicated PJM TOs, and Silver Run, and hold this proceeding in abeyance for 90 days.
Read this passage Filed comments: Cost allocation

Footnotes

Word notes · Topic match: Filing procedure

PP 35, 37. [fn:5] 18 C.F.R. § 385.212 (2025). [fn:6] The Indicated PJM TOs include: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power…
Read this passage