EL26-70-000 · 2026-06-24 · Individual No Affiliation

Comments of Debra Ann Ostroski providing documented correspondence with American Transmission Company re the alternative transmission evaluation for the Large Load Show Cause Proceeding

Read topic-matched comments in EL26-70

Topics in the text: Cost allocation

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Page 1

page range · Topic match: Cost allocation

As a local concerned citizen regarding the Viridon WISE project in Wisconsin, I formally asked ATC to evaluate upgrading their existing infrastructure (such as reconductoring) as a cheaper, ratepayer-protective alternative to Viridon's $350 million greenfield transmission line.
Read this passage Filed comments: Cost allocation