EL26-67-000 · 2026-07-08 · Global Capacity Alliance

Motion to Intervene and Initial Comments of Global Capacity Alliance in response to FERC's 06/18/2026 Show Cause Order

Read topic-matched comments in EL26-67

Topics in the text: Reliability and curtailment · Cost allocation

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

FERC-001 Version 1.1 0 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Interconnection of Large Loads to the Interstate Transmission System | Docket No.
Read this passage

I. INTRODUCTION AND MOTION TO INTERVENE

printed heading

Accordingly, the GCA respectfully requests the Commission grant it intervenor party status in these proceedings.
Read this passage

II. FRONT-OF-THE-METER NETTING AND THE ATTRIBUTABILITY GAP

printed heading · Topic match: Reliability and curtailment

Because they are treated independently, the resource’s provided mitigation is socialized to the grid, leaving the load still exposed to curtailment even while the paired resource is offsetting its impact, MW for MW.
Read this passage Filed comments: Reliability and curtailment

III. THE TECHNICAL AND COMMERCIAL CORE OF FTM-NETTING

printed heading · Topic match: Reliability and curtailment

While rare, controlled shedding during system emergencies is possible due to on-site backup generation, but frequent rapid curtailment events are technically and commercially unviable.
Read this passage Filed comments: Reliability and curtailment

IV. TRANSMISSION PLANNING ALIGNMENT AND GRID RELIABILITY

printed heading · Topic match: Reliability and curtailment

Reliability Assurance: The Scarcity Release During system-wide emergency conditions, RTOs may require FTM-Netting participants to execute a Scarcity Release, lowering the telemetry shield so both assets see full market dispatch / curtailment.
Read this passage Filed comments: Reliability and curtailment

V. IMPLEMENTATION AND BENEFITS

printed heading · Topic match: Cost allocation

The Externalities of FTM-Netting: A System-Level Assessment By aligning the commercial imperatives of developers with macro-grid operational needs, FTM-Netting delivers compounding system benefits: • Grid Visibility & Reliability: Halts the "BTM Exodus" by keeping new generation visible to RTOs. •…
Read this passage Filed comments: Cost allocation

VI. CONCLUSION AND REQUEST FOR RELIEF

printed heading · Topic match: Cost allocation

CONCLUSION AND REQUEST FOR RELIEF For the foregoing reasons, the GCA respectfully requests that the Commission grant its Motion to Intervene in these consolidated proceedings and accord it full party status with all attendant rights.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated at Austin, Texas this 8th day of July, 2026. ______________________________ Jesse Gossett Jesse Gossett, Interim Executive Director Global Capacity Alliance