Motion for Abeyance of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period
Read topic-matched comments in EL26-67
Topics in the text: Filing procedure · Cost allocation · Connecting load and generation
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-67-000 MOTION FOR ABEYANCE OF THE INDICATED PJM TRANSMISSION OWNERS AND REQUEST FOR EXPEDITED ACTION AND SHORTENED COMMENT PERIOD Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”),1 the Indicated PJM Transmission…Read this passage
I. BACKGROUND
printed heading
I.Read this passage
BACKGROUND
printed heading · Topic match: Filing procedure
BACKGROUND On June 18, 2026, the Commission issued a show cause order under section 206 of the FPA to PJM, together with its transmission owners, directing PJM and the PJM Transmission Owners to justify or reform the tariff provisions governing how large loads connect to and receive service from…Read this passage Filed comments: Connecting load and generation
II. MOTION TO HOLD DEADLINE TO RESPOND IN ABEYANCE
printed heading · Topic match: Filing procedure
The PJM Transmission Owners have already begun these efforts in earnest, but a 90-day abeyance is necessary to allow the PJM Transmission Owners sufficient time not only to develop these PJM Tariff provisions, but to also provide PJM and PJM stakeholders an adequate opportunity to review these…Read this passage
A. Development of a Pro Forma Cost Recovery Agreement
printed heading · Topic match: Cost allocation
Development of a Pro Forma Cost Recovery Agreement In the Show Cause Order, the Commission preliminarily found that PJM’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers.14 The Commission indicated…Read this passage Filed comments: Cost allocation
B. Rate Design Related to Transmission Services for Large Loads
printed heading · Topic match: Connecting load and generation
Rate Design Related to Transmission Services for Large Loads In the Show Cause Order, the Commission preliminarily found that the PJM Tariff appears to be unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking transmission service on behalf…Read this passage Filed comments: Connecting load and generation
C. Transparency Obligations Related to Network Upgrades Needed for Large
printed heading · Topic match: Cost allocation
Under the CTOA, the PJM Transmission Owners retain their rights with respect to local transmission planning matters.29 If the PJM Transmission Owners determine that revisions to the PJM Tariff are needed with respect to local planning matters, such as the provisions of PJM Attachment M-3, the PJM…Read this passage Filed comments: Cost allocation
III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED
printed heading · Topic match: Filing procedure
REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED COMMENT PERIOD The PJM Transmission Owners respectfully request expedited consideration of this motion for abeyance and request that the Commission issue an order granting the motion no later than August 10, 2026.Read this passage
IV. CONCLUSION
printed heading
IV.Read this passage
CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the reasons set forth above, the PJM Transmission Owners’ request that the Commission establish a five (5) day comment period for answers to this motion and issue, on or before August 10, 2026, an order granting the PJM Transmission Owners’ request to hold the deadline to respond in…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 28th day of July 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005Read this passage