EL26-67-000 · 2026-08-03 · Constellation Energy Generation, LLC

Answer of Constellation Energy Generation, LLC in support of PJM Interconnection, L.L.C.'s Motion for Abeyance

Read topic-matched comments in EL26-67

Topics in the text: Filing procedure · Connecting load and generation · Reliability and curtailment

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.
Read this passage

ANSWER OF CONSTELLATION ENERGY GENERATION, LLC

PDF bookmark · Topic match: Filing procedure

In the Co-Location proceeding, PJM requests an extension to comply with Commission directives other than “certain defined terms in Tariff, Part I; certain terms for NITS pursuant to Tariff, Part III; additional details regarding the Necessary Study process that will be specified in the manuals; and…
Read this passage Filed comments: Reliability and curtailment

CONCLUSION

PDF bookmark · Topic match: Filing procedure

CONCLUSION For the reasons stated above, Constellation respectfully requests that the Commission grant PJM’s Motion for Abeyance with the clarification that PJM’s obligation in the Co-Location proceeding to file complete provisions on Interim NITS by August 17, 2026, is unchanged. the Tariff…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

PDF bookmark

CERTIFICATE OF SERVICE I hereby certify that I have on this 3rd day of August, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R.…
Read this passage