Comments of the Natural Gas Supply Association on the Informational Reports re Resource Adequacy Measures and Proposals, PJM Interconnection L.L.C., et al
Read topic-matched comments in EL26-67
Topics in the text: Reliability and curtailment
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
August 10, 2026 The Honorable Laura Swett, Chairman Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: Informational Reports Regarding Resource Adequacy Measures and Proposals, PJM Interconnection L.L.C., Docket No.Read this passage Filed comments: Reliability and curtailment
I. Natural Gas is Critical to Supporting Large Load Growth
printed heading
Similarly, there has been an incredible shift in MISO, where gas requests have spiked over the last 24 months to now dominate the fast-track Expedited Resource Addition (ERAS) queue, capturing 75% of the new expedited capacity requests.Read this passage
II. Infrastructure Constraints Threaten Reliability Efforts
printed heading · Topic match: Reliability and curtailment
Failing to account for the full energy ecosystem—including necessary pipeline infrastructure—limits the regional operators’ ability to achieve full success in these critical resource adequacy initiatives.Read this passage Filed comments: Reliability and curtailment
III. Conclusion and Specific Request for Supplemental Reporting
printed heading
Conclusion and Specific Request for Supplemental Reporting NGSA does not ask the Commission or RTOs to reprioritize their current, complex workloads regarding large load integration.Read this passage