UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
Docket No. ER26-3650-000
MOTION TO INTERVENE AND COMMENTS OF
CENTRAL MUNICIPAL POWER
AGENCY/SERVICES, INDIANA MUNICIPAL
POWER AGENCY, MISSOURI JOINT MUNICIPAL
ELECTRIC UTILITY COMMISSION, AND WPPI
ENERGY
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s
(the “Commission”) Rules of Practice and Procedure,1 and the Commission’s August 31,
2026 Combined Notice of Filings #1,2 Central Municipal Power Agency/Services
(“CMPAS”), Indiana Municipal Power Agency (“IMPA”), Missouri Joint Municipal
Electric Utility Commission (“MJMEUC”), and WPPI Energy (“WPPI”) (collectively,
“Midwest TDUs”) each moves to intervene in this proceeding and together comment on
Midcontinent Independent System Operator, Inc.’s (“MISO”) August 28, 2026 filing to
revise its Open Access Transmission, Energy, and Operating Reserve Markets Tariff
(“Tariff”) to implement Interconnection Reliability Requirements for Large Loads.3
Midwest TDUs recognize the reliability challenges posed by the influx of new
large loads seeking to interconnect to the MISO Transmission System4 and appreciate
1 18 C.F.R. §§ 385.212 and 385.214.
2 eLibrary No. 20260831-3080.
3 MISO, Interconnection Reliability Requirements for Large Loads (Aug. 28, 2026), eLibrary
No. 20260828-5278 (“MISO Filing”).
4 Unless otherwise noted, capitalized terms in these comments refer to the terms as defined in the MISO
Tariff, including terms that would be defined under the Tariff revisions MISO has filed in this proceeding.
PDF page 2
- 2 -
MISO taking swift action to address these challenges. At the same time, addressing these
complex challenges must be done in a way consistent with the Show Cause Order the
Commission issued to MISO5 and that avoids unintended adverse consequences.
Midwest TDUs therefore seek clarification on two issues:
• That MISO’s proposed Interconnection Reliability Requirements for
Large Loads apply to those Large Loads interconnected to the MISO
Transmission System (and not to loads interconnected at to the distribution
system). This scope of applicability is consistent with MISO’s explanation
of its filing and the Commission’s Show Cause Order, but Midwest TDUs
seek clarification to avoid any potential confusion on this key point.
• That implementation of these requirements will not unduly burden
Transmission Customers. Midwest TDUs appreciate that MISO proposes
to allow Transmission Customers to demonstrate their ability to comply
with these requirements through agreements with a Large Load—as
ultimately Large Loads create the reliability risks at issue, and those risks
can only be avoided with the cooperation of Large Loads. But additional
clarity is needed to ensure that Transmission Customers can rely on these
agreements to avoid undue burdens. In addition, MISO should confirm
that it will play a central role in communication and educating Large
Loads about these requirements, because otherwise important details
needed to ensure reliability may get lost in translation, frustrating the
intended reliability purpose.
To the extent that MISO does not clarify these issues on its own, the Commission
should direct it to do so in a deficiency letter. And if MISO’s proposed Tariff language
does not clearly reflect these clarifications, the Commission should order MISO to make
further revisions to the Tariff language to do so.6
5 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“MISO Show Cause Order”).
6 Because addressing these discrete issues would not result in an “entirely different rate design” (or even
change the substance of the requirements posed by MISO) the Commission has authority to require MISO
to address them without rejecting the filing. Cal. Indep. Sys. Operator Corp., 178 FERC ¶ 61,182, P 30
nn.43-44 (2022) (quoting NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 115 (D.C. Cir. 2017)); see also
El Paso Nat. Gas Co. v. FERC, 966 F.3d 842, 863 (D.C. Cir. 2020) (explaining that under an analogous
provision of the Natural Gas Act “[i]f the rate imposed by FERC ‘differs significantly’ from the rate
proposed by the pipeline, it can no longer be attributed to the pipeline or qualify for Section 4 treatment,”
PDF page 3
- 3 -
I.
MOTION TO INTERVENE
Each Midwest TDU (described in Attachment A hereto) moves to intervene with
full rights as parties to this proceeding. As market participants, load-serving entities, and
customers under MISO’s Tariff, Midwest TDUs will be directly affected by MISO’s
proposed Tariff revisions. They each have clear and substantial interests in this
proceeding that cannot be represented by any other party, and their participation would be
in the public interest. Midwest TDUs should therefore each be granted intervention.
Communications regarding this proceeding should be directed to the following:7
Cynthia S. Bogorad
Jeffrey M. Bayne
SPIEGEL & MCDIARMID LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
Phone: (202) 879-4000 (Phone)
Fax: (202) 393-2866 (Fax)
Email: cynthia.bogorad@spiegelmcd.com
jeffrey.bayne@spiegelmcd.com
CMPAS:
Jay Anderson, Chief Executive Officer
CENTRAL MUNICIPAL POWER
AGENCY/SERVICES
7550 Corporate Way
Suite 100
Eden Prairie, MN 55344
Phone: (888) 970-8267
Email: jaya@cmpas.org
but “[u]nder this Court’s precedents, FERC can alter a proposed rate and remain in a Section 4 proceeding
as long as its change represents ‘at least partial approval of the change’ for which the pipeline itself
petitioned” (emphasis added) (first quoting W. Res., Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993); and
then quoting Pub. Serv. Comm’n of N.Y. v. FERC, 642 F.2d 1335, 1345 (D.C. Cir. 1980))).
7 Midwest TDUs request waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure,
18 C.F.R. § 385.203(b)(3), so as to permit more than two entries on the official service list in order to
enable Midwest TDUs to promptly receive all communications in the proceeding.
PDF page 4
- 4 -
IMPA:
Peter J. Prettyman
Indiana Municipal Power Agency
11610 North College Avenue
Carmel, IN 46032
Phone: (317) 575-3870
Fax: (317) 575-3372
Email: pprettyman@impa.com
WPPI:
Tom Hanrahan, General Counsel
WPPI ENERGY
1425 Corporate Center Drive
Sun Prairie, WI 53590-9109
Phone: (608) 834-4556
Email: thanrahan@wppienergy.org
MJMEUC:
Steve Stodden, President and CEO
MISSOURI JOINT MUNICIPAL ELECTRIC
UTILITY COMMISSION
2200 Maguire Blvd.
Columbia, MO 65201
Phone: (573) 445-3279
Fax: (573) 445-0680
Email: sstodden@mpua.org
Terry M. Jarrett, General Counsel
MISSOURI JOINT MUNICIPAL ELECTRIC
UTILITY COMMISSION
2200 Maguire Blvd.
Columbia, MO 65201
Phone: 573-445-3279
Fax: (573) 445-0680
Email: tjarrett@mpua.org
II.
COMMENTS
A.
Midwest TDUs seek confirmation that the proposed requirements
apply only to those Large Loads directly connected to the MISO
Transmission System.
MISO should confirm that its proposed requirements apply only to those Large
Loads directly connected to the MISO Transmission System. To the extent MISO’s
proposed Tariff language does not clearly impose this limit, the Commission should
direct MISO to revise its proposed Tariff language to do so.
MISO’s filing appears to impose the proposed Large Loads Interconnection
Reliability Requirements on only those Large Loads that are interconnected to the MISO
Transmission System, and there is no indication that MISO intends to extend these
requirements to any loads interconnected to distribution facilities. There is no mention of
distribution-level interconnection in MISO’s transmittal letter, proposed Tariff revisions,
or supporting testimony.
PDF page 5
- 5 -
Indeed, MISO witness Beibei Li describes the scope of MISO’s filing as
“propos[ing] reliability requirements and a reliability-based framework applicable to
Transmission Customers taking Transmission Service on behalf of Large Load
interconnected to the MISO Transmission System.”8 And although MISO’s proposed
definition of Large Load does not expressly refer to interconnections to the MISO
Transmission System,9 other Tariff language in MISO’s filing does explicitly refer to
interconnections to the Transmission System. For example, “Large Load Equipment” is
defined as “[a]ny of the facilities, devices, or equipment that constitutes a part of a Large
Load, or are used to interconnect the Large Load to the Transmission System.”10 And the
Large Load Ride-Through Requirement states that it is designed to “ensur[e] that the
Computational Load remains connected to the Transmission System and continue
operation during voltage and frequency disturbances within the performance criteria
established by the Transmission Provider in the Business Practices Manual for Large
Load.”11
In addition, MISO’s filing is in response to the Commission’s MISO Show Cause
Order,12 which specifically focused on large load interconnections to the transmission
8 MISO Filing, Tab C, Prepared Direct Testimony of Beibei Li Senior Manager of Strategic Assessment at
15 (“Li Test.”) (emphasis added).
9 The MISO Tariff defines the “Transmission System” as “[t]he transmission facilities owned or controlled
by Transmission Owners that have conveyed functional control to the Transmission Provider, and are used
to provide Transmission Service under Module B of this Tariff…,” and the Tariff specifically states that
Distribution Facilities are “not part of the Transmission System.” MISO Tariff § 1.T. (Note, the language
quoted above is only part of the definition of Transmission System, not the complete definition.)
10 MISO Filing, Tab A, Redlined Tariff § 1.L (“Redlined Tariff”).
11 Id. § 37A.6.
12 MISO Filing, Transmittal Letter at 1 (“Transmittal”) (“The [Interconnection Reliability Requirements]
Proposal is responsive to several of the concerns raised by the Commission in the Order Instituting
PDF page 6
- 6 -
system. For example, the Commission’s suggested “reasonable” definition of a large load
is one that “interconnects to the transmission system at a voltage level greater than 69
kV,”13 and the MISO Show Cause Order repeatedly refers to the interconnection of large
loads to the transmission system.14
Consistent with the MISO Show Cause Order, MISO’s intent appears to be that
these requirements are specifically for Large Loads interconnected to the MISO
Transmission System. MISO’s proposed definition of Large Load, however, lacks the
explicit language suggested in the Show Cause Order regarding transmission-level
interconnection. MISO defines a Large Load as one “located at a single substation behind
one or more Point(s) of Withdrawal from the Transmission System,”15 with “Point(s) of
Withdrawal” defined as “[t]he point(s) where a non-transmission facility that is used to
Proceeding Under Section 206 of the Federal Power Act4 in Docket No. EL26-70-000 . . . .” (footnote
omitted)).
13 MISO Show Cause Order, P 58 (emphasis added). The MISO Show Cause Order similar indicates that it
would be “reasonable” to define co-located loads “as a configuration that refers to end-use customer load
that is physically connected to the facilities of an existing or planned generating facility on the generator
interconnection customer’s side of the point of interconnection to the RTO/ISO’s transmission system.” Id.
P 89 (emphasis added).
14 See, e.g., id. P 1 (explaining that “stakeholders have expressed concerns that large loads are not
efficiently and appropriately integrated onto the transmission system”); id. P 12 (“There is also broad
support for rules that help to ensure that other transmission customers are not unfairly burdened with
additional costs or reliability impacts as large and co-located loads interconnect to the transmission
system.”); P 42 (“At the outset, we clarify the principles relating to the Commission’s jurisdiction over the
matters relevant to the integration of large loads onto the transmission system and the impacts of large
loads on the transmission system.”); P 45 (“As applied to large load additions to the transmission system,
these principles mean that the Commission has exclusive jurisdiction over the rates, terms, and conditions
of interstate transmission service to Eligible Customers on behalf of large loads connecting to the
transmission system, and the practices directly affecting the provision of such interstate transmission of
electricity.”); P 123 (“We also understand that large loads and Eligible Customers taking transmission
service on behalf of large loads are negotiating, entering into, and/or have executed various agreements
related to interconnecting to the transmission system and/or the provision of transmission service.”).
15 Redline Tariff § 1.L (proposed definition of Large Load) (emphasis added).
PDF page 7
- 7 -
withdraw Energy from the Transmission System to serve Load connects to the
Transmission System.”16
While MISO’s reference to Point(s) of Withdrawal from the Transmission System
strongly suggests loads interconnected at the distribution level are not covered by the
definition of Large Load, the term “behind” could potentially be read broadly to
encompass anything behind such Point(s) of Withdrawal (such as also behind a
distribution transformer)—not just what is directly behind such points and connected at
transmission voltages. There is additional potential ambiguity because the term “non-
transmission facility” used in the definition of Point(s) of Withdrawal is not defined.17
Midwest TDUs believe that MISO’s intent to limit Large Loads to those
connected to the MISO Transmission System should be clear for the reasons stated
above. But to avoid any potential confusion, MISO should confirm the scope of its
Interconnection Reliability Requirements for Large Loads. To the extent that MISO’s
proposed Tariff language is not clear on this point, the Commission should direct MISO
to revise the definition of Large Load to include more explicit language on the
requirement that Large Loads are those directly interconnected to the MISO
Transmission System.
To the extent that MISO disagrees and argues that its new requirements should
apply to loads interconnected to the distribution system (i.e., behind the transmission-to-
16 Id. § 1.P (proposed definition of Point(s) of Withdrawal).
17 Although this term is undefined, Midwest TDUs believe it to be referring to facilities used to
interconnect the large load to the MISO Transmission System (consistent with the proposed definition of
Large Load Equipment), not a limitless term that could apply to any facility that is not considered
transmission.
PDF page 8
- 8 -
distribution substation), the Commission should find that MISO has not justified that
scope as just and reasonable and require MISO to revise its filing to apply only to Large
Loads interconnected to the MISO Transmission System. Nothing in MISO’s filing
addresses distribution-level interconnections, much less satisfies MISO’s burden under
Federal Power Act (“FPA”) section 20518 to demonstrate the justness and reasonableness
of encompassing distribution-level interconnections.
Moreover, imposing requirements on distribution-level interconnections would go
far beyond the careful and deliberate approach taken in the Commission’s Show Cause
Order—particularly with respect to jurisdictional issues.19 Similarly, while MISO
supports its filing by citing to reliability concerns raised by North American Electric
Reliability Corporation (“NERC”),20 extending MISO’s proposed reliability requirements
to Large Loads connected at the distribution level would be inconsistent with actions
NERC itself is taking. In response to the Commission’s recent directive that NERC
propose reliability standards and propose registry criteria to “address reliability risks to
the Bulk-Power System associated with the integration of computational loads,”21 NERC
is focusing on large computational loads interconnected to the transmission system. For
18 16 U.S.C. § 824d.
19 See, e.g., MISO Show Cause Order, P 43 (“As discussed below, however, certain aspects of the process
for integrating large loads onto the transmission system fall squarely within the Commission’s exclusive
jurisdiction. Specifically, we find that it is within the Commission’s exclusive authority to ensure that
transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions
governing how transmission service to Eligible Customers on behalf of large loads interconnecting to the
transmission system will be studied . . . .” (emphasis added)); id. P 44 (“As part of its transmission
authority, the Commission has exercised jurisdiction over the terms of certain interconnections to the
transmission system as an element of transmission service, including the interconnection of wholesale load
to the transmission system.” (footnote omitted) (emphasis added)).
20 Transmittal at 7.
21 Reliability Standard(s) Pertaining to Computational Load Integration, 196 FERC ¶ 61,031, P 1 (2026).
PDF page 9
- 9 -
example, NERC’s currently proposed revised draft registry criteria for Computational
Load Owner and Operator, as posted on August 19, 2026 for industry comment (due
September 18, 2026), are limited to such loads of at least 50 MW connected to
transmission facilities of at least 100 kV.22 The associated Updated Technical Reasoning,
also posted on August 19, describes the technical basis and analyses supporting these
thresholds.23
In short, both the legal and factual basis of MISO’s filing are targeted toward
large loads interconnected to Commission-jurisdictional transmission facilities. MISO’s
proposed Tariff language should match that scope.
B.
MISO’s new requirements must be implemented in a way that
does not unduly burden Transmission Customers and advances
their reliability purpose.
Although MISO refers to its newly proposed reliability requirements as “Large
Load Reliability Requirements,” MISO proposes to make “[t]he Transmission Customer
taking Transmission Service on behalf of a Large Load . . . responsible for complying
22 NERC, Draft Rules of Procedure Appendix 5B, Statement of Compliance Registry Criteria Revision 9
§ III(c) Computational Load Owner or Operator (Aug. 19, 2026), https://www.nerc.com/globalassets/who-
we-are/rules-of-procedure/proposed/appendix-5b-clean---august-2026-posting.pdf:
III.c.1 Computational Load Owner of a Computational Load Site with a total connected
Load greater than or equal to 50 MW that is supplied through electrical equipment
connected at a voltage level greater than or equal to 100 kV from one or more points of
connection.
III.c.2 Computational Load Operator of a Computational Load Site with a total connected
Load greater than or equal to 50 MW that is supplied through electrical equipment
connected at a voltage level greater than or equal to 100 kV from one or more points of
connection.
23 NERC, Technical Reasoning Update, Proposed Computational Load Owner and Computational Load
Operator at 3-4 (Aug. 19, 2026), https://www.nerc.com/globalassets/who-we-are/rules-of-
procedure/proposed/august-posting-technical-reasoning.pdf.
PDF page 10
- 10 -
with each of the requirements.”24 In other words, the Transmission Customer—not the
Large Load—would be responsible for the proposed visibility requirements, phasor
measurement unit requirements, ramp requirements, and ride-through requirements.
These requirements would impose significant burdens on Transmission Customers,
particularly smaller municipal utilities, if they are forced to be the middlemen between
MISO and the Large Loads that are best positioned to implement the proposed
requirements to achieve their reliability purposes.
For example, while direct implementation of the proposed Large Load
requirements may pose challenges for all load-serving entities, requiring small utilities
that serve Large Loads to add the necessary technology and infrastructure needed to
directly meet MISO’s proposed Large Load requirements (including the additional
requirements applicable to Computational Loads) would impose a disproportionate
financial and administrative burden. Smaller utilities are unable to spread the significant
costs and personnel needed to perform these specialized tasks in a rapidly evolving
terrain. Thus, requiring small Transmission Customers to directly perform the primary
role in complying with the proposed Large Load reliability requirements would impose a
particularly heavy and undue burden on municipal and consumer-owned electric systems
and their often rural customers.
Midwest TDUs are particularly concerned with excessive burdens on
Transmission Customers given that, as MISO’s filing itself makes clear, the reliability
24 Redline Tariff § 37A(I) (emphasis added). See Li Test. at 17 (explaining the definition of the term
“Transmission Customer,” which “include[s] customers receiving Transmission Service under Module B of
[the MISO] Tariff”).
PDF page 11
- 11 -
risks at issue are those posed by Large Loads themselves—not the Transmission
Customer. MISO explains that “the increasing size, concentration, and changing
characteristics of Large Loads create a need for greater consistency in the information,
visibility, and performance expectation necessary to reliably plan and operate the
Transmission System.”25 MISO also emphasizes “the increased operational risk
Computational Loads place on the Transmission System.”26 In explaining why MISO
proposes to make the Transmission Customer responsible for compliance with these
requirements, MISO does not claim that Transmission Customers are causing reliability
risks; rather, it states that the “ultimate owner of a Large Load may not participate
directly in MISO’s markets or otherwise have contractual privity to MISO.”27
Midwest TDUs do not oppose, per se, requiring Transmission Customers to be
responsible for compliance with these new requirements based on privity concerns. But
to be just and reasonable, and not unduly discriminatory or preferential, compliance
responsibility for the new requirements must be implemented in a manner that does not
impose undue burdens on Transmission Customers, especially small utilities, for actions
taken by the Large Loads they serve, and that facilitates achievement of MISO’s stated
objective of ensuring grid reliability.
MISO’s filing includes some language to reasonably limit the burden on
Transmission Customers, but additional clarity is needed. Significantly, MISO’s
proposed Tariff revisions expressly permit a Transmission Customer to demonstrate its
25 Li Test. at 7 (emphasis added).
26 Id. at 17.
27 Id. at 18.
PDF page 12
- 12 -
ability to effectuate compliance with these requirements with “applicable agreement(s), if
any, between the Transmission Customer and the entity or entities that own, operate or
use the Large Load.”28 This language appropriately recognizes that compliance with
these requirements ultimately depends on actions taken by the Large Load itself.
Midwest TDUs support this provision allowing Transmission Customers to
demonstrate compliance through agreements with the Large Loads. Because Large Loads
are best positioned to ensure compliance with these new requirements, it is critical that
Transmission Customers can enter into agreements that assign Large Loads the primary
role for actually complying with the new requirements. But to ensure that Transmission
Customers can rely on such agreements with Large Loads to ensure compliance without
undue burdens, MISO should confirm or clarify the following issues. To the extent MISO
does do so on its own, the Commission should issue a deficiency letter asking MISO to
address these issues and require revisions to the Tariff language consistent with the points
below.
First, MISO should confirm that it will accept agreements that assign Large
Loads the duty to comply with one or more of these new requirements as a sufficient
demonstration of a Transmission Customers’ ability to effectuate compliance. Such
confirmation will clarify the intent behind the language in proposed section 37A(I)
quoted above and the types of agreements that will be acceptable for this purpose.29
28 Redline Tariff § 37A(I).
29 It may be beneficial for MISO to develop a standardized means for Transmission Customers to indicate
that they have assigned compliance roles to a Large Load, so that this provision can be efficiently and
consistently implemented. Midwest TDUs encourage MISO to work with stakeholders to do so.
PDF page 13
- 13 -
Second, MISO should clarify the full scope of potential consequences for non-
compliance with these new requirements, particularly for Transmission Customers that
have entered into agreements with Large Loads to effectuate compliance. Proposed
section 37A(I) states that “[f]ailure to comply with the requirements established in this
Section 37A may result in a delayed Service Commencement Date, a period of time
needed for corrective action, operational limitations, or other remediation action(s) by
Transmission Provider as may be necessary to maintain Transmission System
reliability.”30 It is appropriate for the consequences for non-compliance to be tailored to
address and prevent the reliability risks posed by Large Loads. Indeed, that should be the
guiding principle for implementing these requirements. In contrast, it would be
inappropriate to impose additional consequences or other unduly punitive penalties (such
as financial penalties) on the Transmission Customer if these requirements are not met by
the Large Load assigned responsibility for complying with these requirements under an
agreement.
Accordingly, MISO should clarify that the scope of “other remedial action(s)” is
limited to actions that address the reliability impacts caused by Large Loads assigned
compliance responsibility under their agreement with the Transmission Customer (rather
than punitive measures against the Transmission Customer). Thus, the remedial actions
should be targeted to measures that impact the Large Load that is in the best position to
effectuate compliance. In addition, MISO should confirm that this language establishes
the exclusive list of consequences for a Transmission Customer’s failure to comply with
30 Id.
PDF page 14
- 14 -
the Interconnection Reliability Requirements for Large Loads where the Transmission
Customer has by contract assigned the primary compliance role to the Large Load best
positioned to perform that role. Doing so will ensure that the focus in the event of non-
compliance is on ensuring reliability, not penalizing Transmission Customers for actions
beyond their reasonable control.
Third, where a Transmission Customer demonstrates its ability to effectuate
compliance with these requirements through an agreement with a Large Load, MISO
should cooperate to ensure that compliance can be accomplished in an efficient manner
consistent with such an agreement. For example, where appropriate and consistent with
the terms of the agreement between the Large Load and Transmission Customer, MISO
should accept information provided directly by the Large Load to MISO and the
Transmission Customer, rather than rigidly requiring all information to pass through the
Transmission Customer (or its equipment) as a middleman.
Fourth, MISO should also provide educational and ongoing support to Large
Loads themselves to ensure that they fully understand these new requirements. Although
MISO’s proposed Tariff language makes the Transmission Customer responsible for
compliance with these requirements, MISO cannot ignore that it is the actions taken by
the Large Loads themselves that are the source of the reliability risks that need to be
addressed. MISO has developed these new requirements to protect the MISO
Transmission System against the impact of new Large Load interconnections, and MISO
should play a central role in making sure that Large Loads fully comprehend these
requirements and are well positioned to act consistently with them.
PDF page 15
- 15 -
It would not be just and reasonable for MISO to avoid any direct interactions with
these Large Loads and instead solely rely on Transmission Customers to communicate
these requirements to the Large Load to which responsibility is assigned by agreement.
MISO, which developed these requirements for the stated purpose of protecting the
Transmission System from reliability risks posed by Large Loads, should not by limit
communications about these requirements to a game of telephone where all information
must be conveyed through the Transmission Customer.31 Doing so could risk critical
details getting lost in translation, undermining the reliability protection these
requirements are meant to provide. The support MISO provides Transmission Customers
and other stakeholders—such as service representatives, the MISO Help Center, and
Customer and System Operator Training—should also be made directly available to
Large Loads to facilitate compliance with these requirements, as Large Loads are best
positioned to address reliability risks upon receipt of MISO’s guidance.
31 A standardized means for Transmission Customers to indicate that they have assigned compliance roles
to a Large Load, as noted above in footnote 29, would also allow MISO to more easily and accurately
identify the particular Large Loads that have agreed to play a primary role in ensuring compliance with
these requirements.
PDF page 16
- 16 -
CONCLUSION
For the reasons discussed above, the Commission should (1) grant CMPAS,
IMPA, MJMEUC, and WPPI intervention in this proceeding; and (2) ensure that the
issues above are adequately clarified by MISO and order further Tariff revisions to the
extent that MISO’s proposed language is not clear on these issues.
Respectfully submitted,
/s/ Cynthia S. Bogorad
Cynthia S. Bogorad
Jeffrey M. Bayne
Attorneys for Midwest TDUs
Law Offices of:
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
(202) 879-4000
September 18, 2026
PDF page 18
A-1
ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS
Central Minnesota Municipal Power Agency d/b/a Central Municipal Power
Agency/Services (“CMPAS”) is a public power joint action agency organized under
Minnesota law. CMPAS operates as a project-oriented agency. CMPAS and certain of its
members own and operate transmission assets which have been turned over to the
functional control of MISO.
The Indiana Municipal Power Agency (“IMPA”) is a body corporate and
politic, and a political subdivision of the State of Indiana. IMPA was created in 1980,
under the provisions of Indiana Code § 8-1-2.2, by a group of municipalities for the
purpose of jointly financing, developing, owning, and operating electric generation and
transmission facilities which are appropriate to the current and projected electric power
needs of such municipalities. IMPA became an operating utility in 1983, when it began
to sell electric power to its member utilities under power sales contracts. IMPA’s
members currently comprise 60 Indiana cities and towns and one Ohio Village.
IMPA is a member of Midcontinent Independent System Operator, Inc. (MISO).
IMPA has ownership interests in generation resources within MISO, including co-
ownership with Duke Energy Indiana and Wabash Valley Power Alliance in the Gibson
Station Unit 5, ownership interest in the Prairie State Energy Campus, ownership interest
in Trimble County Units 1 and 2, and ownership of natural gas combustion turbine
peaking units. IMPA, Duke Energy Indiana, and the Wabash Valley Power Alliance
have entered into a joint ownership agreement of the Joint Transmission System (JTS) in
PDF page 19
Attachment A
A-2
Indiana. Access to the JTS transmission facilities is administered by MISO pursuant to
its tariff.
The Missouri Joint Municipal Electric Utility Commission (“MJMEUC”) is a
joint action agency and a body corporate and politic of the State of Missouri authorized
by legislation to construct, operate and maintain jointly owned transmission and
generation facilities for the production and transmission of electric power for its
members, to purchase and sell electric power and energy, and to enter into agreements
with any person for transmission of electric power. It is organized on a statewide basis to
promote efficient wheeling, pooling, generation, and transmission arrangements to meet
the power and energy requirements of municipal utilities in the state. MEC membership
is comprised of 72 municipal utility members and 4 advisory members. Together,
MEC’s members serve some 347,000 retail customers, with a combined peak load of
approximately 2,600 MW.
Since January 1, 2000, pursuant to its authority under state law, MEC has been
administering a power pool formed by some of MEC’s members. The Missouri Public
Energy Pool #1 (“MoPEP”) currently has 35 members, whose 2024 summer peak load
was approximately 528 MW. MoPEP is the full-requirements supplier for its members,
and meets their capacity and energy requirements through generating and purchased-
power resources contributed by the pool members, and through additional resources
arranged for by MoPEP. MoPEP has pool loads and/or resources located within the
transmission systems of several members of MISO and SPP. In addition, as of June 1,
2020, MEC administers, pursuant to its state law authority, a full-requirements power
pool formed by two of MEC’s members (with a third taking supply starting in June 2025)
PDF page 20
Attachment A
A-3
with a 2024 summer peak load of 58 MW, titled the Southwest Missouri Public Energy
Pool (“SWMPEP”). This pool was formed to collectively purchase power at wholesale
costs to serve its members’ load. MEC has load in multi-owner transmission pricing
zones in SPP.
WPPI Energy (“WPPI”) is a municipal electric company formed pursuant to
Wis. Stat. § 66.0825. WPPI provides bulk power and other services to its 51 members
(50 municipalities and one cooperative), each of which operates a distribution utility and
sells electricity at retail to the residences, businesses, and industries in and around its
municipality. These members are located within the Wisconsin, Michigan, and/or Iowa
service territories of four large investor-owned utilities: Northern States Power-
Wisconsin (Xcel Energy (“Xcel”)), WEC Energy Group (Wisconsin Electric Power
Company (“WEPCO”) and Wisconsin Public Service Corp. (“WPS”)), Upper Peninsula
Power Co., and Alliant Energy (Wisconsin Power & Light Co. (“WP&L”) and Interstate
Power and Light Co.). The bulk of WPPI’s load is on the American Transmission
Company LLC (“ATCLLC”), Xcel, or ITC Midwest transmission systems, although
some of WPPI’s resources are located in other transmission zones in MISO, as well as in
PJM Interconnection, L.L.C. WPPI supplies the bulk power and energy requirements of
its members from generation resources owned by WPPI and through purchased power
contracts.
WPPI is a longstanding member of MISO, with both generation and load within
the MISO footprint, and owns portions of transmission projects. WPPI also is a
participating owner of ATCLLC, a MISO Transmission Owner which was formed
pursuant to 1999 Wisconsin Act 9 with WPPI’s support.
PDF page 21
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing document to be served
upon each person designated on the official service list compiled by the Secretary in this
proceeding.
Dated on this 18th day of September, 2026.