Letter order granting the NYISO, New York Transmission Owners and Non-Incumbent Transmission Owners abeyance motions
FERC grants the abeyance motions of NYISO, the New York Transmission Owners and the Non-Incumbent Transmission Owners and holds the EL26-69 show cause proceeding for 90 days, moving responses to November 16, 2026 and answers to December 16, 2026.
Moves the E-12 NYISO 60-day show cause response from August 17 to November 16, 2026, using the 90-day abeyance option the June 18 order offered for stakeholder-developed section 205 filings.
E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: 30-day report on serving large loads with adequate generation (p. 7)
Key points
- FERC grants all three abeyance motions filed August 3 and holds the proceeding for 90 days.
we grant the Abeyance Motions filed by NYISO, NYTOs, and Non-Incumbent TOs and hold this proceeding in abeyance for Source text
- NYISO plans a Management Committee vote on October 28 and a section 205 filing on November 16, 2026.
with the final proposal presented to the Management Committee on October 28, 2026. Source text
- FERC finds the movants met the order's test of describing the future filing and giving a date.
have provided a robust description of the filings they anticipate making, provided a date by which they intend to make such filings, and described the on-going stakeholder process Source text
- New due dates are November 16, 2026 for responses and December 16, 2026 for answers.
responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
- A timely section 205 filing suspends the filer's duty to respond, and the proceeding stays in abeyance.
the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
Topics in the text: Filing procedure · Cost allocation · Connecting load and generation
What the document says
Unpaginated filing
Five of six cases go into 90-day abeyance; responses are due November 16.
Therefore, responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
Unpaginated filing
A timely section 205 filing suspends that respondent's duty to answer the show-cause order.
then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
Unpaginated filing
FERC granted abeyance because each movant described its coming filing and named a filing date.
NYISO, NYTOs, and Non-Incumbent TOs have provided a robust description of the filings they anticipate making, provided a date by which they intend to make such filings Source text
Unpaginated filing
FERC invites each respondent to say which tariff revisions justify ending the show-cause case.
we encourage NYISO and/or Transmission Owners to explain, with specificity, which of their proposed Tariff revisions they believe resolve all or some of the Commission’s preliminary findings in the Show Cause Order Source text
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
In this order, we grant the Abeyance Motions filed by NYISO, NYTOs, and Non-Incumbent TOs and hold this proceeding in abeyance for 90 days.Read this passage
Footnotes
Word notes · Topic match: Filing procedure
PP 38, 40. [fn:5] 18 C.F.R. § 385.212 (2025). [fn:6] NYTOs include: Central Hudson Gas & Electric Corporation; Consolidated Edison Company of New York, Inc.; New York State Electric & Gas Corporation; Niagara Mohawk Power Corp.; Orange and Rockland Utilities, Inc.; and Rochester Gas and Electric…Read this passage