Order Granting Rescission and Abeyance Requests (rescinds the order as to the Six Cities and WAPA)
FERC grants the abeyance requests of CAISO, DCR Transmission and the Joint Participating Transmission Owners and rescinds the show cause order against Six Cities and WAPA. The proceeding is held 90 days, with responses now due November 16, 2026.
Applies the abeyance option in the E-10 CAISO show cause order, which allowed up to 90 days for stakeholder work, and moves the 60-day response date from August 17 to November 16, 2026.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- FERC grants the Six Cities and WAPA rescission motions because both are exempt from FERC jurisdiction under FPA section 201(f).
the Show Cause Order is rescinded as against each of the Six Cities and WAPA and the caption of the proceeding has been amended Source text
- CAISO commits to a November 16, 2026 FPA section 205 filing after Board and governing body approval by October 28.
CAISO states it will expedite the process to obtain CAISO Board of Governors and Western Energy Market Governing Body approval as necessary by October 28, 2026 Source text
- The Joint PTOs plan coordinated TO Tariff filings covering study procedures, transparency, cost recovery and financial security.
their filings will present revisions to their TO Tariffs to include study, application, and operational procedures for the interconnection of large loads Source text
- FERC finds the abeyance descriptions meet the show cause order's requirement for a described future filing and a date.
have provided robust descriptions of the FPA section 205 filings they anticipate making by November 16, 2026 Source text
- Responses move to November 16, 2026 and answers to December 16, 2026.
responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
- A respondent that files its section 205 proposal by November 16 has its show cause response suspended.
the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
Topics in the text: Filing procedure · Cost allocation · Connecting load and generation
What the document says
Unpaginated filing
Five of six cases go into 90-day abeyance; responses are due November 16.
Therefore, responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
Unpaginated filing
A timely section 205 filing suspends that respondent's duty to answer the show-cause order.
then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text
Unpaginated filing
FERC granted abeyance because each movant described its coming filing and named a filing date.
CAISO, DCRT, and the Joint PTOs have provided robust descriptions of the FPA section 205 filings they anticipate making by November 16, 2026 Source text
Unpaginated filing
FERC invites each respondent to say which tariff revisions justify ending the show-cause case.
we encourage CAISO and/or Participating Transmission Owners to explain, with specificity, which of their proposed Tariff revisions they believe resolve all or some of the Commission’s preliminary findings in the Show Cause Order Source text
Unpaginated filing
FERC rescinds the CAISO show-cause order for the Six Cities and WAPA.
the Show Cause Order is rescinded as against each of the Six Cities and WAPA and the caption of the proceeding has been amended to reflect their removal from the proceeding Source text
Unpaginated filing
FERC rescinds the CAISO show-cause order for the Six Cities and WAPA.
Six Cities and WAPA, as utilities exempt from Commission jurisdiction under FPA section 201(f), have requested to be removed from this proceeding Source text
Unpaginated filing
Rescission rests on their promise to coordinate with CAISO and file any TO tariff changes needed.
Both Six Cities and WAPA have confirmed that they will continue to coordinate and cooperate with CAISO in responding to the Show Cause Order and will file with the Commission any proposed revisions to their respective TO Tariffs Source text
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Six municipal owners and WAPA distinguished themselves from investor-owned utilities Six Cities and Western Area Power Administration
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
In this order, we grant the Abeyance Motions and hold this proceeding in abeyance for 90 days.Read this passage
Footnotes
Word notes · Topic match: Filing procedure
EL26-71-000 (issued Aug. 4, 2026). [fn:19] Six Cities Motion for Rescission at 4; WAPA Motion for Rescission at 4. [fn:20] Show Cause Order, 195 FERC ¶ 61,214 at P 35. [fn:21] Id. [fn:22] CAISO Abeyance Motion at 4-7. [fn:23] Joint PTOs Abeyance Motion at 3-7. [fn:24] DCRT Abeyance Motion at 4-14.…Read this passage