Upper Missouri Zone
Rate Sheet for Point-To-Point Transmission Service
The currently effective rates for Point-To-Point Transmission Service in the Upper Missouri (“UMZ”) rate zone are set forth in the “UMZ PTP Rate Att T” tab of the Revenue Requirements and Rates File (“RRR File”) posted on the SPP website. Transmission Owners that have Commission approved rate(s) in the UMZ rate zone are: Basin Electric Power Cooperative (“Basin Electric”); Heartland Consumers Power District (“Heartland”); Missouri River Energy Services (“MRES”); East River Electric Power Cooperative, Inc. (“East River”); Corn Belt Power Cooperative (“Corn Belt”); NorthWestern Energy Public Service Corporation (“NWPS”); Northwest Iowa Power Cooperative (“NIPCO”); Harlan Municipal Utilities (“HMU”); Western Area Power Administration, Upper Great Plains Region (“Western-UGP”); Central Electric Power Cooperative, Inc. (“Central Power”); Mountrail-Williams Electric Cooperative (“Mountrail- Williams”); Mor-Gran-Sou Electric Cooperative, Inc. (“Mor-Gran-Sou”); Roughrider Electric Cooperative, Inc. (“Roughrider”); L and O Power Cooperative (“LOPC”); and Upper Missouri G. & T. Electric Cooperative, Inc (“UMGT”).
Balanced Portfolio Reallocation Adjustment of Point-To-Point Rates
Rates for Point-To-Point Transmission Service specified in this Attachment T shall be adjusted to reflect any amount reallocated from the Zonal Annual Transmission Revenue Requirement in accordance with Section IV.A of Attachment J. The rates, including any applicable reallocation adjustment, shall be set forth in the RRR File posted on the SPP website.
Revenue Crediting for Point-To-Point Rates
Rates for Point-To-Point Transmission Service under this Attachment T shall reflect any adjustments for Schedules 7, 8, 14, and 15 revenues, Incremental Market Efficiency Use revenues, and revenues distributed and allocated under Attachment AU, implemented in accordance with Section 34.1(2) of this Tariff. The rates, including any applicable adjustments for Schedules 7, 8, 14, and 15 revenues, Incremental Market Efficiency Use revenues, and revenues distributed and allocated under Attachment AU, shall be set forth in the RRR File.
PDF page 2
Firm Point-To-Point Transmission Service
The Transmission Customer shall compensate the Transmission Provider each month for Reserved Capacity at the sum of the applicable charges based upon the rates set forth in the RRR File, calculated pursuant to the formula rates of Basin Electric, Heartland, MRES, MRES Members (includes Moorhead Public Service; Orange City Municipal Utilities; City of Pierre, South Dakota; City of Sioux Center, Iowa; Watertown Municipal Utility Department; Denison Municipal Utilities; and Vermillion Light & Power), East River, Corn Belt, NWPS, NIPCO, HMU, Western- UGP, Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC, and UMGT including any ATRR associated with facility credits provided in the UMZ rate zone, set forth in Attachment H, Addendums 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 37, 40, 41, 42, 45, 47, 49, and 53 (list appropriate addendums, respectively) of the Tariff, and as described below:
1. Yearly delivery: the UMZ Monthly delivery rate multiplied by 12 months.
2. Monthly delivery: the sum of the Basin Electric, Heartland, MRES, MRES
Members, East River, Corn Belt, NWPS, NIPCO, HMU, Western-UGP,
Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC,
and UMGT Annual Transmission Revenue Requirements determined under
these entities’ formula rates, including any ATRR associated with facility
credits provided in the UMZ rate zone, divided by the UMZ total load
estimate and divided by 12 months.
3. Weekly delivery: the UMZ Yearly delivery rate divided by 52.
4. Daily delivery: the UMZ Weekly delivery rate divided by 7.
Non-Firm Point-To-Point Transmission Service
The Transmission Customer shall compensate the Transmission Provider for Non-Firm Point-To-Point Transmission Service up to the sum of the applicable charges based upon the rates set forth in the RRR File, calculated pursuant to the formula rates of Basin Electric, Heartland, MRES, MRES Members, East River, Corn Belt, NWPS, NIPCO, HMU, Western-UGP, Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC, and UMGT including any ATRR associated with facility credits provided in the UMZ rate zone, and as described below:
1. Monthly delivery: the sum of the Basin Electric, Heartland, MRES, MRES
Members, East River, Corn Belt, NWPS, NIPCO, HMU, Western-UGP,
PDF page 3
Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC, and UMGT Annual Transmission Revenue Requirements determined under these entities’ formula rates, including any ATRR associated with facility credits provided in the UMZ rate zone, divided by the UMZ total load estimate and divided by 12 months.
2. Weekly delivery: the UMZ Monthly delivery rate multiplied by 12 and divided by 52.
3. Daily delivery: the UMZ Weekly delivery rate divided by 7.
4. Hourly delivery: the UMZ Monthly delivery rate divided by 730 hours per month.