Exelon answers PJM’s request for more time on its capacity-auction complaint
Exelon answers PJM's November 4, 2026 request for more time and opposition to fast-track processing in the EL27-11 complaint. Exelon says PJM's requested extension is too long for the narrow legal question, supports a shorter extension, and asks for an order well before the May 2027 auction.
Asks FERC to: Limit the extension to December 7, 2026, and issue an order sufficiently in advance of the May 2027 Base Residual Auction.
A procedural answer in Exelon's section 206 complaint on PJM's capacity auction schedule. It does not cite the show cause orders; the link is the shared PJM resource adequacy question.
E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- Exelon says PJM's proposed extension is excessive for the narrow scope of the allegations it must answer.
the scale of PJM’s proposed extension is excessive for the narrow scope of the allegations it must answer. PDF p. 3
- Exelon says it should not take PJM 48 days to state its view on the narrow legal question.
it should not take PJM 48 days to express its opinion on this narrow legal question. PDF p. 3
- Exelon supports extending the comment period to December 7, 2026, which gives PJM 34 days after the complaint.
Exelon supports an extension of the comment period until December 7, 2026, which will provide PJM with a total of 34 days after Exelon filed the complaint PDF p. 4
- Exelon says the relief it seeks is prospective and can be given only before the auction process moves forward.
the relief Exelon seeks is prospective, and it can be meaningfully provided only before the auction process moves forward. PDF p. 5
Contents · 4 sections
Topics in the text: Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL27-11-000 ) PJM Interconnection, L.L.C., ) ) Respondent ) ) MOTION FOR LEAVE TO ANSWER AND ANSWER OF EXELON CORPORATION Pursuant to Rules 2121 and 2132 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure, Exelon Corporation (“Exelon”) submits this motion…Read this passage
I. MOTION FOR LEAVE TO ANSWER
PDF bookmark · Topic match: Filing procedure
Accordingly, Exelon respectfully requests the Commission grant leave and accept this Answer into the record of this proceeding.Read this passage
II. ANSWER
PDF bookmark
II.Read this passage
A. Exelon Supports an Extension of the Comment Period to December 7, 2026.
printed heading · Topic match: Filing procedure
Fast Track procedures may include expedited action on the pleadings by the Commission, expedited hearing before an ALJ, or expedited action on requests for stay, extension of time, or other relief by the Commission or an ALJ.”). 5 advance of the May 2027 BRA.Read this passage
III. Conclusion
PDF bookmark
CONCLUSION For these reasons, Exelon requests the Commission establish an extended comment date of December 7, 2026, and consider expeditiously the instant complaint so the Commission can act sufficiently in advance of the May 2027 BRA.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 9th day of November 2026. /s/ Thomas S.Read this passage