ER27-454-000 · 2026-11-09 · PJM

Attachment A -Marked Tariff

Contents · 6 sections
  1. Attachment A p. 1
  2. Attachment K-Appendix, section 6.6(c) or the defaults below: p. 27
  3. A. It has a documented plan in place to retire the resource prior to or during the Delivery p. 36
  4. B. Significant physical operational restrictions cause long term or permanent changes to the p. 36
  5. C. The Capacity Market Seller is involved in an ongoing regulatory proceeding (e.g. – p. 36
  6. 18 p. 44

Read the parent filing

Topics in the text: Credit and exit · Cost allocation · Connecting load and generation

What the document says

Seller obligations · PDF pp. 1–43

Marked definitions and auction rules

Attachment A shows edits against the earlier tariff. It reproduces the definitions and auction sections containing the changes, including eligibility and offer obligations. For the proposed wording without deleted text, use Attachment B.

Eligibility for Participation in RPM Auctions PDF p. 33

Cost allocation · PDF pp. 44–51

Marked §18.1–18.3A: costs and the snapshot

The redline locates the new distributor reporting requirement alongside the target calculation, qualifying offsets and allocation rules. Parallel clean language begins at page 45 of Attachment B.

the quantity and identity of incremental Large Load that is supported by an electric service obligation PDF p. 51

Seller obligations · PDF pp. 52–61

Marked §18.4–18.6: the procurement

The marked seller rules cover procurement scope, offers, selection and committed resources' obligations. The clean text distinguishes new conditions from text PJM proposes to delete.

The Reliability Backstop Procurement Process PDF p. 53

Exit liability · PDF pp. 62–68

Marked §18.7–18.8: exit and credit

The redline replaces the exiting transmission owner with the withdrawing load-serving entity as the party responsible for the remaining charges. Section 18.8 then marks the changes to collateral.

such Load Serving Entity shall be responsible for the remainder of the RBP Charges allocated to it PDF p. 62

Elsewhere in the record

Other parties on the same questions, in their own documents.

Source sections

Printed headings where available; page ranges otherwise. Open a heading to read the original passage.