What the archive covers
All rows in the six show-cause dockets and their -001 subdockets; selected related tariff dockets, and from Nov 15 the related PJM, MISO and ISO-NE dockets listed below. One accession can appear on several sheets. Administrative notices, service changes, withdrawals and intervention-only rows are not counted as policy submissions. Related-docket comments without a local body are identified for follow-up. A captured document is not an endorsement of its contents.
Checked through 2026-11-15. 794 originals in the reading room. PDF page numbers count from the first physical page; Word documents have no fixed pagination.
Docket sheets
- EL26-67-000all rows reconciled · 177 of 177 rows
- EL26-68-000all rows reconciled · 153 of 153 rows
- EL26-69-000all rows reconciled · 105 of 105 rows
- EL26-70-000all rows reconciled · 174 of 174 rows
- EL26-71-000all rows reconciled · 117 of 117 rows
- EL26-72-000all rows reconciled · 111 of 111 rows
- EL26-67-001all rows reconciled · 10 of 10 rows
- EL26-68-001all rows reconciled · 0 of 0 rows
- EL26-69-001all rows reconciled · 3 of 3 rows
- EL26-70-001all rows reconciled · 4 of 4 rows
- EL26-71-001all rows reconciled · 3 of 3 rows
- EL26-72-001all rows reconciled · 4 of 4 rows
- ER26-3380-000all rows reconciled · 156 of 156 rows
- ER26-3552-000all rows reconciled · 53 of 53 rows
- ER27-432-000all rows reconciled · 2 of 2 rows
- ER27-432-001all rows reconciled · 2 of 2 rows
- ER26-3515-000sheet listed in full; 62 rows after Sept 3 not individually reviewed · 162 of 162 rows
- ER26-3650-000all rows reconciled · 72 of 72 rows
- AD26-7-000sheet listed in full; rows not individually reviewed · 150 of 150 rows
- EL25-49-000sheet listed in full; rows not individually reviewed · 303 of 303 rows
- EL25-49-002sheet listed in full; rows not individually reviewed · 34 of 34 rows
- EL26-108-000sheet listed in full; rows not individually reviewed · 42 of 42 rows
- EL27-11-000sheet listed in full; rows not individually reviewed · 36 of 36 rows
- ER26-3380-001sheet listed in full; rows not individually reviewed · 8 of 8 rows
- ER26-3515-001sheet listed in full; rows not individually reviewed · 2 of 2 rows
- ER26-3515-002sheet listed in full; rows not individually reviewed · 2 of 2 rows
- ER27-25-000sheet listed in full; rows not individually reviewed · 74 of 74 rows
- ER27-330-000sheet listed in full; rows not individually reviewed · 31 of 31 rows
- ER27-330-001sheet listed in full; rows not individually reviewed · 19 of 19 rows
- ER27-454-000sheet listed in full; rows not individually reviewed · 14 of 14 rows
- ER27-484-000sheet listed in full; rows not individually reviewed · 5 of 5 rows
- ER27-520-000sheet listed in full on Nov 17; rows not individually reviewed · 4 of 4 rows
- ER27-506-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-517-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-522-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-526-000sheet listed in full on Nov 18; rows not individually reviewed · 7 of 7 rows
- ER27-527-000sheet listed in full on Nov 18; rows not individually reviewed · 8 of 8 rows
- ER27-531-000sheet listed in full on Nov 18; rows not individually reviewed · 4 of 4 rows
- ER26-1479-000sheet listed in full on Nov 18; rows not individually reviewed · 98 of 98 rows
- ER26-1479-001sheet listed in full on Nov 18; rows not individually reviewed · 10 of 10 rows
- ER26-1479-002sheet listed in full on Nov 18; rows not individually reviewed · 7 of 7 rows
- ER27-499-000sheet listed in full on Nov 18; rows not individually reviewed · 3 of 3 rows
- ER27-500-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-501-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-508-000sheet listed in full on Nov 18; rows not individually reviewed · 3 of 3 rows
- ER27-512-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-513-000sheet listed in full on Nov 18; rows not individually reviewed · 3 of 3 rows
- ER27-515-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-518-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-521-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-523-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-528-000sheet listed in full on Nov 18; rows not individually reviewed · 2 of 2 rows
- ER27-529-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-530-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-532-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-533-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-534-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER27-535-000sheet listed in full on Nov 18; rows not individually reviewed · 1 of 1 rows
- ER26-3531-000sheet listed in full on Nov 18; rows not individually reviewed · 13 of 13 rows
- ER26-3537-000sheet listed in full on Nov 18; rows not individually reviewed · 14 of 14 rows
- ER27-559-000sheet listed in full on Nov 21; rows not individually reviewed · 4 of 4 rows
- ER27-577-000sheet listed in full on Nov 21; rows not individually reviewed · 3 of 3 rows
- ER27-578-000sheet listed in full on Nov 21; rows not individually reviewed · 3 of 3 rows
- ER26-3591-000sheet listed in full on Nov 21; rows not individually reviewed · 11 of 11 rows
- ER26-3591-001sheet listed in full on Nov 21; rows not individually reviewed · 2 of 2 rows
Records without a local original
92 listed records. A docket entry establishes that a document was filed; it cannot establish what the document says.
- 20260624-5017 · Comments of Debra Ann Ostroski providing documented correspondence with American Transmission Company re the alternative transmission evaluation for the Large Load Show Cause Proceeding under EL26-70.restricted · FERC labels the only PDF CEII; no public body. The separate public comment is accession 20260624-5016.
- 20260811-4003 · Comments of East Kentucky Power Cooperative re PJM Interconnection’s recent proposals to FERC for addressing capacity needs in the short and long terms under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260817-5042 · Motion to Intervene and Comments of Neil P. Osnato o/b/o Persistence Analytics Group LLC in response to PJM Interconnection, L.L.C.'s 07/31/2026 filing proposing a Reliability Backstop Procurement under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260820-5015 · Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers re PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5090 · Motion to Intervene, Limited Protest, and Request for Clarification of PPL Electric Utilities Corporation under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5105 · Comments of the Solar Energy Industries Association in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5120 · Partial Protest and Comments of Dominion Energy Services, Inc. re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5125 · Comments of Institute for Policy Integrity at New York University School of Law on PJM Interconnection, L.L.C.’s Section 205 filing to implement Reliability Backstop Procurement under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5155 · Comments of Institute for Policy Integrity at New York University School of Law on PJM Interconnection, L.L.C.’s Section 205 filing to implement Reliability Backstop Procurement under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5175 · Motion to Intervene and Comments of Base Power Inc. re PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5192 · Comments of New Jersey Board of Public Utilities in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5197 · Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate re PJM Interconnection, L.L.C.'s 07/31/2026 revisions to the Open Access Transmission Tariff and the Reliability Assurance Agreement under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5206 · Comments of Google LLC re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement Proposal under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5211 · Motion to Intervene and Comments of CPV Power Holdings, LP re PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5215 · Comments of American Municipal Power, Inc. re PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5220 · Comments of Advanced Energy United in response to PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5229 · Motion to Intervene and Request for Clarification of Talen Energy Corporation re the Reliability Backstop Procurement filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5243 · Comments of Equinix Inc. on the PJM Interconnection, LLC filing re Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5263 · Comments of Southern Maryland Electric Cooperative, Inc. re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement filing under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5266 · Limited Protest of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5273 · Limited Protest of the NRG Companies re PJM Interconnection, L.L.C.’s 07/31/2026 filing proposing a Reliability Backstop Procurement under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5274 · Protest of the Indicated PJM Transmission Owners re PJM Interconnection, L.L.C.’s proposed tariff amendment under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5276 · Comments and Protest of FirstEnergy Service Company re PJM Interconnection, L.L.C.'s 07/31/2026 filing proposing to establish a Reliability Backstop Procurement mechanism under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5283 · Limited Protest of American Electric Power Service Corporation to PJM Interconnection, LLC’s proposed revisions to the Open Access Transmission Tariff and Reliability Assurance Agreement Among Load Serving Entities under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5289 · Motion to Intervene and Protest of the Retail Energy Supply Association re PJM Interconnection, LLC's proposed revisions to the Open Access Transmission Tariff under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5290 · Protest of East Kentucky Power Cooperative, Inc. on the 07/31/2026 filing of PJM Interconnection, L.L.C. proposing revisions to the Open Access Transmission Tariff and Reliability Assurance Agreement under ER26-3380. Erroneously filed.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5293 · Motion to Intervene and Initial Comments of Amazon Energy LLC re PJM Interconnection, L.L.C.'s 07/31/2026 filing under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5296 · Comments of Ohio Energy Leadership Council on the Reliability Backstop Procurement proposed by PJM Interconnection, L.L.C. under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5297 · Comments of North Carolina Electric Membership Corporation re PJM Interconnection, L.L.C.'s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5299 · Limited Protest of Vistra Corp. re PJM Interconnection, L.L.C.’s proposed Reliability Backstop Procurement mechanism under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5300 · Comments of Calibrant Energy requesting clarification re the PJM Interconnection, LLC’s proposed revisions to the Open Access Transmission Tariff and the Reliability Assurance Agreement Among Load Serving Entities under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5304 · Comments of Blue Ridge Power Agency re PJM Interconnection, L.L.C.'s Reliability Backstop Procurement proposal under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5307 · Protest of Northern Virginia Electric Cooperative, Inc. to the PJM Reliability Backstop Procurement Proposal under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5313 · Motion to Intervene and Request for Clarification, or in the Alternative, Limited Protest of Tract Holding Company I, LLC re PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5314 · Comments of Old Dominion Electric Cooperative re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement filing under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260821-5318 · Comments of Voltus, Inc. on the PJM Interconnection LLC’s Federal Power Act Section 205 filing requesting the approval of tariff amendments to establish a Reliability Backstop Procurement under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260821-5322 · Protest of East Kentucky Power Cooperative, Inc. to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260824-5017 · Comment, Protest, and Motion for Leave to File One Day Out of Time of E-Cubed Policy Associates, LLC in response to PJM Interconnection, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260902-5075 · Motion for Leave to Answer and Answer of the Attorney General of the Commonwealth of Kentucky to the comments and protests of PJM Interconnections, L.L.C.’s 07/31/2026 filing under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260902-5087 · Supplemental Comments of Persistence Analytics Group LLC re Cost-Causation Revalidation related to PJM Interconnection, L.L.C.’s proposed Reliability Backstop Procurement under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260904-5056 · Motion for Leave to File Limited Answer, and Limited Answer, of East Kentucky Power Cooperative, Inc. in support of Protest filed by American Electric Power Service Corporation et al. under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260908-5260 · Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC to certain comments and protests re the PJM Reliability Backstop Procurement Proposal et al. under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260915-5145 · Motion for Leave to Answer and Answer of PPL Electric Utilities Corporation to the 09/10/2026 Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260917-5316 · Answer of PJM Power Providers Group in response to PJM Interconnection, L.L.C.'s 09/10/2026 Motion for Leave to Answer and Answer under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260918-5364 · Motion For Leave to File Second Limited Answer and Second Limited Answer of East Kentucky Power Cooperative, Inc. under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260918-5413 · Motion for Leave to Answer and Answer of American Electric Power Service Corporation to PJM Interconnection, L.L.C.'s 09/10/2026 Answer under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260921-5148 · Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. filed on 09/10/2026 under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260922-5110 · Motion for Leave to Answer and Answer of Indicated PJM Transmission Owners to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. filed on 09/10/2026 under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260923-5060 · Motion for Leave to Answer and Limited Answer of FirstEnergy Service Company to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. filed on 09/10/2026 under ER26-3380.listed only · The public file list returned metadata, but the normal public download failed.
- 20260923-5149 · Motion for Leave to Answer and Answer of Northern Virginia Electric Cooperative, Inc. to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026 under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260924-5183 · Motion for Leave to Answer and Answer of the New Jersey Board of Public Utilities to the Answer et al. of PJM Interconnection, L.L.C. filed on 09/10/2026 under ER26-3380.listed only · The public file-list endpoint returned HTTP 500.
- 20260929-5071 · Supplemental Comments of Voltus, Inc. in response to PJM Interconnection, L.L.C.'s 09/23/2026 et al. Answers re the Proposal to Establish Interim Resource Adequacy, et al. under ER26-3380 et al.listed only · The public file list returned metadata, but the normal public download failed.
- 20261014-5184 · Answer of Northern Virginia Electric Cooperative, Inc. in Support of PJM Interconnection, L.L.C.’s Motion for Abeyance filed on 10/13/2026 under ER26-3380, et al.listed only · The public file-list endpoint returned HTTP 500.
- 20261020-5159 · Motion to Intervene and Protest of Tesla, Inc. et al. re the Section 206 investigation re PJM Interconnection’s Reliability Backstop Procurement framework under EL26-108.listed only · The public file-list endpoint returned HTTP 500.
- 20260828-5285 · Motion of Michigan Environmental Justice Coalition, et al. for Extension of Time to Submit Comments on the 08/18/2026 filing by the Midcontinent Independent System Operator, Inc. under ER26-3552.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-3033 · Notice Denying Extension of Time re Midcontinent Independent System Operator, Inc. under ER26-3552.listed only · The public file-list endpoint returned HTTP 500.
- 20260908-5257 · Comments of the Solar Energy Industries Association in Support of Midcontinent Independent System Operator, Inc.’s filing proposing revisions to establish the Zero Injection Generator Interconnection Agreement under ER26-3552.listed only · The public file list returned metadata, but the normal public download failed.
- 20260908-5266 · Comments of Google LLC on Midcontinent Independent System Operator Inc.’s Zero Injection Generator Interconnection Agreement proposal under ER26-3552.listed only · The public file list returned metadata, but the normal public download failed.
- 20260908-5321 · Motion to Intervene and Comments of MISO Transmission Owners in support of the 08/18/2026 filing by Midcontinent Independent System Operator, Inc. under ER26-3552.listed only · The public file-list endpoint returned HTTP 500.
- 20260908-5332 · Comments of Advanced Energy United in response to the Midcontinent Independent System Operator’s proposal to establish a Zero Injection Generator Interconnection Agreement framework under ER26-3552.listed only · The public file list returned metadata, but the normal public download failed.
- 20260923-5148 · Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the comments and protests in response to the 08/18/2026 proposed tariff revisions under ER26-3552.listed only · The public file-list endpoint returned HTTP 500.
- 20260814-5009 · Comments of Neil P. Osnato d/b/a Persistence Analytics Group LLC concerning PJM Interconnection, L.L.C.'s 08/13/2026 proposal to establish Interim Resource Adequacy Service and a Large Load Registry under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260820-3043 · Notice Rescinding Prior Notice re PJM Interconnection, L.L.C. under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260831-3082 · Notice Shortening Answer Period re PJM Interconnection, L.L.C. under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260831-5121 · Answer of Google LLC in Support of the Organization of PJM States, Inc.’s 08/28/2026 Motion for Extension of Time under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260901-5250 · Answer of East Kentucky Power Cooperative, Inc. in support of the Organization of PJM States, Inc.’s motion for extension of time to submit comments in response to PJM Interconnection, L.L.C.’s filing under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260902-3019 · Notice Denying Extension of Time re PJM Interconnection, L.L.C. under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260902-5055 · Supplemental Comments of Persistence Analytics Group LLC re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C. under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5020 · Comments of Hans Royal re the Interim Resource Adequacy Service proposed by PJM Interconnection, L.L.C. under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5023 · Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers to PJM Interconnection, L.L.C.'s 08/13/2026 Filing under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5167 · Comments of Tesla, Inc. re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5170 · Supportive Comments and Limited Protest of the New Jersey Board of Public Utilities re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5183 · Motion to Intervene, Protest, and Request for Clarification of PPL Electric Utilities Corporation regarding PJM Interconnection L.L.C.’s Interim Resource Adequacy Service Filing under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5185 · Motion to Intervene and Comments of The Retail Energy Supply Association re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5193 · Motion to Intervene and Comments of Sunrun Inc. in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim Resource Adequacy Service and Large Load Registry under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5195 · Comments of the Chief Energy Officer Josephus M. Allmond et al. of the Commonwealth of Virginia re the PJM Interconnection, L.L.C.'s proposed Interim Resource Adequacy Service Filing under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5197 · Comments of ACORE on PJM Interconnection, L.L.C.'s 08/13/2026 proposal to establish Interim Resource Adequacy Service and a large load registry under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5200 · Motion to Intervene and Protest of Talen Energy Corporation re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5201 · Protest and Comments of Constellation Energy Generation, LLC addressing PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service and Large Load Registry to address System Reliability under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5207 · Limited Protest and Comments of FirstEnergy Service Company et al. in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim Resource Adequacy Service mechanism under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5209 · Comments of Calibrant Energy requesting clarifications of PJM Interconnection, L.L.C.’s proposal filed on 08/13/2026 under ER26-3515.listed only · The public file-list endpoint returned HTTP 500.
- 20260903-5218 · Limited Comments of North Carolina Electric Membership Corporation on PJM Interconnection, L.L.C.’s filing proposing revisions to the Open Access Transmission Tariff et al. under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5221 · Protest of Vistra Corp. regarding PJM Interconnection, L.L.C.’s proposed Interim Resource Adequacy Service filing under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260903-5224 · Comments and Limited Protests of Ohio Energy Leadership Council in response to the Interim Resource Adequacy Service and Large Load Registry proposed by PJM Interconnection, L.L.C. under ER26-3515.listed only · The public file list returned metadata, but the normal public download failed.
- 20260918-5119 · Motion to Intervene and Comments of North American Electric Reliability Corporation et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing under ER26-3650.listed only · The public file-list endpoint returned HTTP 500.
- 20260918-5224 · Motion to Intervene and Comments of the MISO Transmission Owners re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing under ER26-3650.listed only · The public file-list endpoint returned HTTP 500.
- 20260918-5286 · Limited Protest of Entergy Services, LLC re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing under ER26-3650.listed only · The public file-list endpoint returned HTTP 500.
- 20260918-5346 · Joint Comments, Request for Clarification and Limited Protest of Coalition of MISO Transmission Customers et al. to Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing under ER26-3650.listed only · The public file-list endpoint returned HTTP 500.
- 20260918-5386 · Comments of Google LLC on Midcontinent Independent System Operator Inc.’s Interconnection Reliability Requirements for Large Loads Proposal under ER26-3650.listed only · The public file list returned metadata, but the normal public download failed.
- 20260918-5391 · Comments of Verrus LLC in Support of Midcontinent Independent System Operator, Inc.'s proposed Interconnection Reliability Requirements for Large Loads under ER26-3650.listed only · The public file list returned metadata, but the normal public download failed.
- 20260921-5084 · Comments of Rowan Digital Infrastructure, LLC re the 08/28/2026 filing by Midcontinent Independent System Operator, Inc. proposing Interconnection Reliability Requirements for Large Loads under ER26-3650.listed only · The public file list returned metadata, but the normal public download failed.
- 20260924-5153 · Motion for Leave to Answer and Limited Answer of ON Energy Storage, Inc. in response to comments and protests re Midcontinent Independent System Operator, Inc. proposal to establish Interconnection Reliability Requirements for Large Loads under ER26-3650.listed only · The public file-list endpoint returned HTTP 500.