EL26-69-000 · 2026-06-18 · FERC

NYISO show cause order

Contents · 42 sections
  1. D. Extending New Transmission Services to Eligible Customers Taking Service on p. 2
  2. E. Interconnection Customers Serving Electrically Proximate Large Load and Co- p. 2
  3. I. Background p. 7
  4. A. Growth of Large and Co-Located Loads and ANOPR p. 7
  5. B. Recent Proceedings Addressing Large and Co-Located Loads p. 12
  6. 1. PJM Co-Location Proceedings p. 13
  7. 2. SPP High Impact Large Load and High Impact Large Load Generation Assessment Processes p. 14
  8. 3. SPP Conditional High Impact Large Load Service p. 17
  9. II. NYISO’s Existing Processes p. 18
  10. A. Existing Tariff Processes p. 18
  11. 1. Firm Point-to-Point Transmission Service p. 19
  12. 2. NITS p. 21
  13. 3. Load Interconnection Process p. 23
  14. 4. Local Transmission Planning Process p. 25
  15. 5. Generator Interconnection p. 25
  16. 6. Co-Located Load Interconnection Process p. 26
  17. B. Recent Stakeholder Proceedings in NYISO p. 27
  18. III. Discussion p. 29
  19. A. Transmission Service to Eligible Customers on Behalf of Large Loads p. 31
  20. 1. Jurisdiction p. 32
  21. 2. Tariff Provisions p. 35
  22. B. Cost Shifting Risk Among Transmission Customers p. 47
  23. 1. Jurisdiction p. 48
  24. 2. Additional Cost Transparency p. 49
  25. 3. Cost Recovery Agreements p. 53
  26. C. Co-Location Arrangements and Load with Behind the Meter Generation p. 57
  27. 1. Definition p. 58
  28. 2. Jurisdiction p. 59
  29. 3. Tariff Provisions p. 60
  30. D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads p. 65
  31. E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load p. 67
  32. 1. Jurisdiction p. 70
  33. 2. Definitions p. 71
  34. 3. Tariff Provisions p. 72
  35. F. Informational Report p. 77
  36. IV. Briefing Questions p. 78
  37. I. Overview of Today’s Orders p. 109
  38. II. The Commission Needs Good Records to Ensure Reasoned Decision-Making p. 110
  39. III. The Commission Needs to Pursue Meaningful Customer Protection p. 111
  40. IV. The Commission Needs to Understand the Implications of Extending New Transmission Services to Additional Loads and Regions p. 113
  41. V. The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies p. 114
  42. VI. Conclusion p. 114

Topics in the text: Connecting load and generation · Cost allocation · Filing procedure

Elsewhere in the record

Other parties on the same questions, in their own documents.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

195 FERC ¶ 61,216 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on

printed heading

D.
Read this passage

E. Interconnection Customers Serving Electrically Proximate Large Load and Co-

printed heading · Topic match: Connecting load and generation

Over the past year, the Commission has taken action in numerous dockets1 to address issues related to (a) unprecedented increases in requests for transmission service 1 See, e.g., PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (PJM Show Cause Order); PJM Interconnection, L.L.C., 193 FERC ¶…
Read this passage

I. Background

PDF bookmark

I.
Read this passage

A. Growth of Large and Co-Located Loads and ANOPR

PDF bookmark · Topic match: Reliability and curtailment

EL26-69-000 - 10 - notes that there are several challenges with its existing load interconnection process, such as: (1) the large volume of requests may delay the completion of the Load System Impact Study (Load SIS), which already requires approximately nine months to complete;28 (2) resource…
Read this passage

B. Recent Proceedings Addressing Large and Co-Located Loads

PDF bookmark · Topic match: Filing procedure

Representatives November 21 ANOPR Comments at 1. 36 See, e.g., AI Supply Chain Alliance November 21 ANOPR Comments at 2; DCC November 21 ANOPR Comments at 3; ECA November 21 ANOPR Comments at 6; Geronimo November 21 ANOPR Comments at 1-2; Google November 21 ANOPR Comments at 2-3; Verrus December 5…
Read this passage

1. PJM Co-Location Proceedings

PDF bookmark · Topic match: Connecting load and generation

On February 20, 2025, the Commission initiated a show cause proceeding against PJM and the PJM transmission owners regarding the lack of tariff provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements.39 The…
Read this passage

2. SPP High Impact Large Load and High Impact Large Load Generation Assessment Processes

PDF bookmark · Topic match: Connecting load and generation

P 32 (explaining that SPP will grant HILLGA customers a new type of interconnection service, load limited resource interconnection service, which grants limited interconnection service solely to serve the associated HILL). 55 Id.
Read this passage

3. SPP Conditional High Impact Large Load Service

PDF bookmark · Topic match: Reliability and curtailment

SPP Conditional High Impact Large Load Service 18.
Read this passage

II. NYISO’s Existing Processes

PDF bookmark

II.
Read this passage

A. Existing Tariff Processes

PDF bookmark

Eligible Customers may request Firm Point-To-Point Transmission Service68 or NITS.69 Firm Point-To-Point Transmission Service and NITS are available to an Eligible Customer that is willing to pay Congestion Rent associated with its service.70 The charges for transmission services in NYISO (either…
Read this passage

1. Firm Point-to-Point Transmission Service

PDF bookmark · Topic match: Cost allocation

NYISO offers a standard Firm Point-to-Point Service Agreement to an Eligible Customer when it submits a completed application for Firm Point-to-Point Service.75 Firm Point-To-Point Transmission Service does not require NYISO to conduct a System Impact Study (SIS) or Transmission Service Study…
Read this passage

2. NITS

PDF bookmark

NITS requests do not require a NITS Study unless the Eligible Customer specifically requests that NYISO conduct such a study.92 In the event that the Eligible Customer requests a NITS Study, NYISO will coordinate with all affected transmission owners in performing the NITS Study, which will…
Read this passage

3. Load Interconnection Process

PDF bookmark · Topic match: Cost allocation

EL26-69-000 - 24 - data.100 After the Eligible Customer executes a System Impact Study Agreement with the transmission owner whose system the Eligible Customer proposes to interconnect (Connecting Transmission Owner) and submits a $150,000 study deposit, NYISO, in cooperation with the Connecting…
Read this passage

4. Local Transmission Planning Process

PDF bookmark

4.
Read this passage

5. Generator Interconnection

PDF bookmark · Topic match: Connecting load and generation

Pursuant to the Tariff, an interconnection customer may request, and NYISO may provide, provisional interconnection service for limited operation prior to the completion of the cluster study and prior to completion of requisite attachment facilities, distribution upgrades, system upgrade…
Read this passage

6. Co-Located Load Interconnection Process

PDF bookmark · Topic match: Cost allocation

NYISO does not have a process in place to evaluate large load co-located with generating facilities.118 Generator interconnection requests proceed through NYISO’s 113 Id. attach.
Read this passage

B. Recent Stakeholder Proceedings in NYISO

PDF bookmark · Topic match: Connecting load and generation

EL26-69-000 - 28 - and Behind-the-Meter Net Generation programs.123 NYISO explains that its current Behind-the-Meter Net Generation Resource participation is premised on a firm Host Load that does not participate in wholesale markets and is not easily controllable or responsive to market signals,…
Read this passage

III. Discussion

PDF bookmark · Topic match: Filing procedure

We emphasize that we will not grant such abeyances reflexively, that any abeyance will be limited to 90 days, and that we will look with great disfavor toward requests to extend the abeyance period.
Read this passage

A. Transmission Service to Eligible Customers on Behalf of Large Loads

PDF bookmark

It also includes instances where an Eligible Customer requests a new or modified point of delivery to serve a large load, where a large load seeks a new or modified delivery point as an unbundled retail transmission service customer, or where large loads are otherwise included in an Eligible…
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Retail and wholesale authority

Specifically, we find that it is within the Commission’s exclusive authority to ensure that transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers on behalf of large loads interconnecting…
Read this passage

2. Tariff Provisions

PDF bookmark · Topic match: Cost allocation

Lastly, we are concerned that NYISO’s existing Tariff fails to deter speculative or duplicative requests for transmission service by Eligible Customers on behalf of large loads.
Read this passage

B. Cost Shifting Risk Among Transmission Customers

PDF bookmark · Topic match: Cost allocation

Cost Shifting Risk Among Transmission Customers 72.
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Cost allocation

To fulfill its responsibility to ensure that transmission rates are just and reasonable, the Commission must act to address the risk of cost shifting among transmission customers due to (1) the process transmission providers and/or transmission owners use to evaluate the facilities needed, and the…
Read this passage

2. Additional Cost Transparency

PDF bookmark · Topic match: Cost allocation

The speed and scale with which Eligible Customers are seeking transmission service on behalf of large loads makes it difficult for interested parties, including transmission customers and state regulators, to accurately assess which transmission costs are driven by requests for transmission service…
Read this passage

3. Cost Recovery Agreements

PDF bookmark · Topic match: Cost allocation

Several commenters discuss the risk of cost shifting among transmission customers that could result from transmission service requests by Eligible Customers on behalf of large loads.190 Commenters also argue that retail-level large load tariffs do not protect wholesale transmission customers from…
Read this passage

C. Co-Location Arrangements and Load with Behind the Meter Generation

PDF bookmark · Topic match: Connecting load and generation

See infra P 98. 201 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 2; PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at PP 91, 102.
Read this passage

1. Definition

PDF bookmark · Topic match: Connecting load and generation

The Generator of the BTM:NG Resource must be electrically located in the NYCA, have a minimum nameplate rating of 2 MW and a minimum net injection to the NYS Transmission System or distribution system of 1 MW.
Read this passage

2. Jurisdiction

PDF bookmark · Topic match: Connecting load and generation

As we explained in the PJM Co- Location Order, states retain exclusive authority over the specific terms of retail sales and retail rate design, including retail cost allocation to the co-located load; which entities are legally permitted to provide electricity to retail customers in co-location…
Read this passage

3. Tariff Provisions

PDF bookmark · Topic match: Connecting load and generation

We preliminarily find that NYISO’s Tariff appears to be unjust and unreasonable because it lacks sufficient clarity and consistency as to the rates, terms, and conditions of service that apply to interconnection customers serving co-located load, including the scope of the analyses NYISO performs…
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads

PDF bookmark · Topic match: Connecting load and generation

Finally, we note that the Commission has found it just and reasonable that, in order for an Eligible Customer to take interim NITS, firm contract demand transmission service, and non-firm contract demand transmission service, an Eligible Customer must have necessary control technologies and/or…
Read this passage

E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load

PDF bookmark · Topic match: Connecting load and generation

Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 114.
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Connecting load and generation

The Commission has exercised this jurisdiction previously in requiring generator interconnection services that allow certain generating facilities to interconnect more quickly through the use of provisional interconnection service and surplus interconnection service,262 and has approved…
Read this passage

2. Definitions

PDF bookmark

For purposes of this order, it appears to be reasonable to use the term “electrically proximate large load” to mean a large load, as defined in this order,264 that is sufficiently electrically close to the interconnection customer’s requested point of interconnection, such that the impact on the…
Read this passage

3. Tariff Provisions

PDF bookmark · Topic match: Connecting load and generation

EL26-69-000 - 77 - what type of transmission service an Eligible Customer will need to take on behalf of the electrically proximate large load or large co-located load.281 We note that, in the PJM Co-Location Order, the Commission found that the Eligible Customer must take transmission service on…
Read this passage

F. Informational Report

PDF bookmark · Topic match: Reliability and curtailment

The informational report must include a detailed schedule of such initiatives, including timing of the stakeholder process and dates of any anticipated filings with the Commission.
Read this passage

IV. Briefing Questions

PDF bookmark · Topic match: Cost allocation

We find that there may be a variety of possible approaches to protect customers from significant cost shifts associated with Network Upgrades triggered by large loads.
Read this passage

I. Overview of Today’s Orders

PDF bookmark · Topic match: Cost allocation

In each of today’s orders to show cause, the Commission identifies a series of issues raised by the ongoing growth of large loads, directs briefing on whether existing tariffs remain just and reasonable in light of those developments, and describes possible solutions to those issues if the…
Read this passage

II. The Commission Needs Good Records to Ensure Reasoned Decision-Making

PDF bookmark

The Commission Needs Good Records to Ensure Reasoned Decision-Making 4.
Read this passage

III. The Commission Needs to Pursue Meaningful Customer Protection

PDF bookmark · Topic match: Cost allocation

As we develop the new infrastructure, many have raised concerns about whether these costs are being fairly assigned to new and existing customers, whose benefits must be commensurate with the costs they pay.
Read this passage

IV. The Commission Needs to Understand the Implications of Extending New Transmission Services to Additional Loads and Regions

PDF bookmark · Topic match: Cost allocation

While it is important to identify innovative solutions that can adapt to the needs of the system, the Commission and grid operators must also be careful not to implement changes that create unforeseen reliability risks.
Read this passage

V. The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies

PDF bookmark

The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies 12.
Read this passage

VI. Conclusion

PDF bookmark · Topic match: Cost allocation

While this is a long journey, even so, we must continue to move at breakneck pace to win the AI race.
Read this passage