PJM corrects its October backstop transmittal letter
PDF page 1
1200 G Street, N.W., Suite 600
Washington, D.C. 20005-3898
Phone: 202.393.1200
Fax: 202.393.1240
wrightlaw.com
October 30, 2026
Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E., Room 1A
Washington, D.C. 20426
Re:
PJM Interconnection, L.L.C., Docket No. ER27-330-00_
Errata to Metadata Correcting Requested Effective Date and to Clarify that Requested Waiver Includes Tariff, Attachment DD, section 16.3
Dear Secretary Reese:
On October 29, 2026, PJM Interconnection, L.L.C. (“PJM”) submitted, pursuant to Federal Power Act section 205, 16 U.S.C. § 824d, revisions to the PJM Open Access Transmission Tariff (“Tariff”) to update the Reliability Backstop Procurement (“RBP”) rules to address, inter alia, issues identified in the Commission’s September 29 Order1 (“October 29 Filing”).2 In the October 29 Filing, PJM requested that proposed new Tariff, Attachment DD, section 18.3A become effective January 29, 2027, and the remainder of the proposed Tariff revisions become effective February 28, 2027.3 PJM also sought a one-time, prospective waiver of certain requirements under Tariff, Attachment DD, section 16.4
After submitting this filing, PJM discovered that when it entered the metadata for proposed new Tariff, Attachment DD, section 18.3A, PJM incorrectly entered an effective date of January 15, 2027, instead of January 29, 2027. Accordingly, to correct this clerical error, PJM submits a corrected version of the sole affected tariff record, i.e., proposed new Tariff, Attachment DD, section 18.3A only to make the ministerial revision to the metadata, to be effective January 29, 2027, as proposed in the October 29
1 PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026) (“September 29 Order”).2 PJM Interconnection, L.L.C., Proposed Amendments to the Reliability Backstop Procurement Motion for Extended, 32-Day Comment Period Request for Waiver of Tariff Attachment DD, Section 16.2 Requirement to Investigate Capacity Shortfall, Docket No. ER27-330-000 (Oct. 29, 2026). 3 October 29 Filing, Transmittal Letter at 62. 4 Id. at 57-60.
PDF page 2
Debbie-Anne Reese, Secretary
October 30, 2026
Page 2
Filing transmittal letter.5 This correction to the metadata for proposed new Tariff, Attachment DD, section 18.3A does not otherwise change the original October 29 Filing, and the effective dates for all other tariff revisions submitted in the October 29 Filing are not affected by this filing.
In addition, PJM discovered it inadvertently omitted in the October 29 Filing’s
transmittal letter reference to Tariff, Attachment DD, section 16.3 in the caption, the heading to Part IV, and in the text on page 60. Page 3 of the transmittal letter clearly states PJM’s request for waiver includes a requirement in Tariff, Attachment DD,
section 16.3,6 but PJM inadvertently failed to carry through citations to this Tariff section in the caption and Part IV of the transmittal letter. Accordingly, PJM has corrected the caption, the heading to Part IV, and page 60 of the attached transmittal letter to include references to Tariff, Attachment DD, section 16.3. Indeed, page 60 of the corrected transmittal provides that “PJM seeks a one-time waiver of Tariff, Attachment DD,
sections 16.2 and 16.3 upon completion of the 2029/2030 Base Residual Auction in the event such auction clears short.”7 PJM has attached hereto as Attachment A, a revised version of the transmittal letter, reflecting the corrections described above and making no other changes.8
Please contact the undersigned with any questions.
Respectfully,
/s/ Ryan J. Collins
Ryan J. Collins
1200 G Street, NW, Suite 600
Washington, D.C. 20005
(202) 393-1200
collins@wrightlaw.com
Attorney for
PJM Interconnection, L.L.C.
5 Since the record and clean and marked versions of proposed Tariff, Attachment DD, section 18.3A, as Attachments A and B are correct, for purposes of this ministerial supplemental filing, a clean and marked version of Tariff, Attachment DD, section 18.3A are not being filed herewith. 6 See October 29 Filing, Transmittal Letter at 3 (“PJM conditionally requests waiver of the requirement in Tariff, Attachment DD, section 16.3 that PJM ‘declare a capacity shortage and make a filing with FERC for approval to conduct a Reliability Backstop Auction’ following three consecutive Delivery Years in which the Base Residual Auction clears short.”).7 Id. at 60.8 For ease of review of the corrections, a redline of the corrections to the October 29 Filing transmittal letter are attached hereto as Attachment B.
PDF page 3
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 30th day of October 2026.
/s/ Ryan J. Collins
Ryan J. Collins