EL26-67-000 · 2026-07-09 · Individual No Affiliation
Motion to Intervene and Comments of Evan Pierce re the large-load interconnection tariff provisions
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL26-67-000
I. MOTION TO INTERVENE
New Era Energy & Digital Inc. is a data center developer pursuing data center and energy development in the PJM service area. New Era Energy & Digital Inc. is concerned with maintaining transmission reliability and affordability while advancing economic development associated with data centers.
II. COMPLIANCE WITH RULE 203
The exact name of the movant is New Era Energy & Digital Inc. New Era Energy & Digital’s principal place of business is located at 200 N. Loraine Street, Suite 1324, Midland, TX 79701. Service of pleadings, documents, and communications in this proceeding should be made on the following: Evan A. Pierce, Chief Development Officer – evan@newerainfra.ai
III. INTRODUCTION AND RELEVANT BACKGROUND
A. The Commission Opened This Section 206 Proceeding in Response to Rapid
Large-Load Growth and the Need for Tariff-Specific Reforms in PJM.
This proceeding arises from the Commission’s ongoing consideration of the transmission, reliability, affordability, and cost-allocation issues associated with the rapid growth of large loads, namely data centers. On October 23, 2025, the Secretary of Energy issued an advance notice of proposed rulemaking requesting that the Commission consider additional action to address the addition of large and co-located loads to the interstate transmission system.1 The Commission subsequently agreed that large-load growth created an urgent need for reforms to ensure timely, orderly, and non-discriminatory interconnection, concluded that further action was warranted, and announced its intent to act by the end of June 2026.2
On June 18, 2026, the Commission instituted this proceeding under section 206 of the Federal Power Act—a process for examining and potentially fixing unjust or unreasonable tariff rules.3 The Commission preliminarily found that PJM’s Open Access Transmission Tariff—the
1 Ensuring the Timely and Orderly Interconnection of Large Loads, Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (October 2025). 2 Interconnection of Large Loads to the Interstate Transmission Sys., 195 FERC ¶ 61,045, at PP 2–4 (April 2026).3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (June 2026) (“Order Instituting Proceeding Under Section 206 of the Federal Power Act”).
PDF page 2
rulebook governing access to PJM’s transmission system—appears to be unjust, unreasonable, or unduly discriminatory or preferential (the Federal Power Act standard for unlawful tariff terms) because it lacks sufficiently clear and consistent provisions addressing the integration of large loads onto the PJM transmission system.4 The Commission therefore directed PJM and the PJM Transmission Owners to “show cause” why the Tariff remains just and reasonable without such provisions, or to explain what Tariff changes would remedy the Commission’s concerns if the Commission proceeds to establish a replacement Tariff.5
The Commission’s order identifies four categories of tariff issues relevant here: (1) the application process, study procedures, and ongoing operational requirements for Eligible Customers (entities that may request transmission service under PJM’s tariff) seeking transmission service on behalf of large loads; (2) transparency and cost-recovery measures for Network Upgrade costs (the costs of transmission-system improvements needed to accommodate the service) associated with such service; (3) transmission services for flexible large loads that are willing and able to limit their use of the transmission system under certain conditions; and (4) the rates, terms, and conditions applicable to interconnection customers serving co-located load or electrically proximate load (meaning large demand located at or near a generation facility).6 The Commission also directed PJM to file a report explaining how PJM will ensure that adequate generation will be available to serve existing and new large loads.7
B. The Commission Identified PJM-Specific Concerns Regarding Large Loads, Co- Located Generation, Flexible Demand, and Resource Adequacy.
The Commission’s concerns are substantial in PJM. The order notes that PJM’s load forecast predicts peak load growth of 32 GW from 2024 to 2030, with 30 GW of that growth projected to come from data centers.8 The order also identifies comments raising concerns that large-load additions in PJM are contributing to resource-adequacy, reliability, affordability, and interconnection-delay challenges.9 In addition, the Commission summarized concerns that infrastructure costs driven by data center load could be shifted to other transmission customers, including through Network Upgrade costs and transmission costs borne in corresponding PJM zones or, where applicable, the broader PJM region.10
The Commission also emphasized the need for clearer tariff rules governing flexible large loads. The order recognizes that certain large loads may be willing and able to limit their withdrawals from the transmission system under specified conditions, and preliminarily finds that PJM’s
4 Id. PP 3, 35.5 Id. PP 3, 35, Ordering Para. (B).6 Id. PP 3, 35.7 Id. PP 3, 102–104, Ordering Para. (C).8 Id. P 8.9 Id. P 9.10 Id. PP 9–10.
PDF page 3
Tariff appears unjust and unreasonable because it lacks transmission services reflecting those operational characteristics.11 Similarly, the Commission preliminarily found that PJM’s Tariff appears to lack generator interconnection study procedures and services that allow interconnection customers serving electrically proximate large load or large co-located load to obtain interconnection service reflecting the operational dynamics of serving such load. 12 Finally, the Commission identified a related supply-side concern. PJM has undertaken several initiatives to address resource adequacy and large-load growth (whether enough generation will be available to meet demand reliably), including the Reliability Resource Initiative, Expedited Interconnection Track, voluntary “Bring Your Own New Generation” approach, and the connect- and-manage framework.13 The Commission nevertheless expressed concern that these efforts may be insufficient, particularly in light of generator retirements and tightening supply conditions, and directed PJM to file a detailed informational report addressing how adequate generation will be available to serve existing and new large loads.14
The below comments address two issues that fall within the scope of the Commission’s order and should be addressed in PJM’s forthcoming filings: first, the use of “Maximum Net Withdrawal” as a tariff-based mechanism for evaluating large loads paired with dependable nearby generation; and second, fast-track treatment for safe supply additions, including uprates (output increases at existing power plants) and reactivation or reconnection of retired or mothballed capacity (existing power plants or units that are shut down or inactive), as part of PJM’s response to the Commission’s resource-adequacy directive.
IV. LIMITED COMMENTS
New Era Energy & Digital submits these limited comments to identify two issues that PJM should address in its forthcoming filings in this proceeding. These comments are directed to the specific issues raised in the Commission’s June 18, 2026 order: the treatment of generation serving electrically proximate or large co-located load, and PJM’s required report on the availability of adequate generation to serve existing and new large loads.15
A. PJM Should Address Maximum Net Withdrawal as Part of Any Framework for
Generation Serving Electrically Proximate or Large Co-Located Load.
The Commission preliminarily found that PJM’s Tariff appears to be unjust and unreasonable because it lacks generator interconnection study procedures and services allowing an
11 Id. PP 85–87. 12 Id. PP 88–101; id. P 95.13 Id. PP 31–34; id. P 103.14 Id. PP 102–104.15 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 3, 35, 88–104 (2026) (“Order Instituting Proceeding Under Section 206 of the Federal Power Act”).
PDF page 4
interconnection customer to seek generator interconnection service that reflects the operational dynamics of serving electrically proximate large load or large co-located load.16 The Commission also identified potential generator-side approaches under which a generating facility’s output could be limited to match the associated load, existing Energy Resource Interconnection Service or Network Resource Interconnection Service (ERIS and NRIS; two types of generator interconnection service under PJM’s rules) could be used with controls to prevent net injection (power exported onto the transmission system) above the existing interconnection agreement, or a new generator interconnection service could ensure no injection to the transmission system. 17
PJM’s response should address the corresponding load-side issue as well. Where a large load is paired with dependable nearby generation and accepts binding operational limits on its reliance on the transmission system, PJM should evaluate the project based on the facility’s enforceable maximum net withdrawal from the transmission system, rather than assuming the facility will impose its full gross demand (the facility’s total electricity need before accounting for nearby generation) on the grid at all times.
For purposes of these comments, “Maximum Net Withdrawal” means the enforceable upper limit, measured in megawatts at the applicable point of interconnection or delivery point, that the combined load/generation configuration may withdraw from the transmission system. A Maximum Net Withdrawal framework would not replace reliability analysis. Rather, it would provide the correct study assumption where the project’s physical configuration, controls, and service obligations make the net-withdrawal limit operationally enforceable.
Such an approach fits the Commission’s reasoning in this order. The Commission explained that where a generating facility’s output is matched to the demand of electrically proximate large load or large co-located load, or where the generating facility’s output is limited to ensure no new injection, the transmission-system impacts may be limited and may reduce the need for Network Upgrades.18 That same principle supports studying the associated load based on an enforceable cap on net withdrawals where the load and generation are operated as a controlled configuration. PJM should therefore address whether any tariff provisions proposed in response to this order should include: (1) a binding net-withdrawal cap in the relevant service agreement or other tariff- governed arrangement; (2) real-time metering and telemetry (measurement and communications data visible to grid operators) for load, generation, and net withdrawals; (3) operational controls or protection systems sufficient to maintain withdrawals within the approved limit; (4) operator visibility (PJM’s ability to see and manage the facility’s grid impacts in real time) sufficient to
16 Id. P 95. 17 Id. PP 95, 98, 100.18 Id. PP 95–96.
PDF page 5
preserve reliability; and (5) tariff consequences if the facility exceeds its approved Maximum Net Withdrawal.
PJM should also explain what transmission service the Eligible Customer must take for a large load operated subject to an enforceable Maximum Net Withdrawal. The Commission expressly encouraged PJM to consider what type of transmission service an Eligible Customer will need to take on behalf of electrically proximate large load or large co-located load, noting that generator interconnection service does not itself convey transmission service.19 A Maximum Net Withdrawal framework would help answer that question by tying the associated transmission service to the project’s enforceable use of the transmission system, rather than to an assumption that the full gross load must always be served from the grid.
B. PJM’s Resource-Adequacy Report Should Address Fast-Track Treatment for Safe Supply Additions.
The Commission separately directed PJM to file an informational report explaining how PJM intends to ensure that adequate generation will be available to serve existing and new large loads.20 The Commission recognized PJM’s existing efforts, including the Reliability Resource Initiative, Expedited Interconnection Track, voluntary “Bring Your Own New Generation” approach, connect-and-manage framework, and reliability backstop procurement, but stated that those efforts may still fall short in light of generator retirements and tightening supply conditions.21
PJM’s report should address not only how large loads can be served more quickly, but also how additional supply can be brought online more quickly where the system impacts are bounded and can be studied safely. Large-load growth presents a supply problem as well as a load-service problem. A complete response should therefore address whether PJM’s existing tariff and study processes allow expedited treatment for limited, low-risk generation additions that can increase available supply without requiring a full multi-year queue process.
In particular, PJM should address whether its Tariff provides an adequate pathway for expedited treatment of uprates at existing generating facilities. Such treatment should be limited to modifications that rely on existing interconnection facilities, do not involve a change in generation technology or fuel type, can be evaluated independently through existing system models or a limited-scope study (a narrower review focused on the incremental grid impacts), and do not materially affect the cost or timing of lower-queued projects (those that entered the interconnection queue later) or already-interconnected projects. Where those conditions are met,
19 Id. P 101.20 Order, 195 FERC ¶ 61,211 at PP 102–104, Ordering Para. (c).21 Id. P 103.
PDF page 6
the incremental nature of the uprate may warrant a narrower and faster study process while preserving all applicable reliability requirements.
PJM should also address whether its Tariff provides an adequate pathway for expedited reconnection or reactivation of retired or mothballed capacity. Such treatment should be available only where the relevant interconnection facilities remain available or can be safely restored, required permits and operating authorizations remain available or can be obtained, and any reliability impacts can be evaluated through a limited-scope review. The purpose would not be to bypass reliability review, but to avoid subjecting bounded reactivations of existing capacity to procedures designed for wholly new speculative projects.
The Commission has already recognized, in this order and related precedent, that certain forms of generator interconnection service may allow resources to interconnect more quickly where their impacts are limited or where they use existing interconnection capability. PJM’s required resource-adequacy report should therefore identify whether existing PJM processes are adequate to accelerate safe uprates and reconnections, and if not, what tariff changes or stakeholder processes would be needed to create such a pathway.
C. Reservation of Rights
Because the Commission has directed PJM to file a 30-day informational report and a 60-day show-cause response, and has allowed interested entities to respond after those filings, New Era Energy & Digital submits these comments on a limited basis and reserves the right to submit further comments after PJM and the Transmission Owners make their directed filings.22
V. CONCLUSION
For the foregoing reasons, New Era Energy & Digital respectfully requests that the Commission grant its motion to intervene and consider these limited comments in evaluating PJM’s forthcoming filings in this proceeding.
22 Order, 195 FERC ¶ 61,211, Ordering Paras. (B), (C), (E).