EL26-71-000 · 2026-07-31 · Six Cities CA

Motion to Rescind Show Cause Order on behalf of the Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California

The Cities of Anaheim, Azusa, Banning, Colton, Pasadena and Riverside move to rescind the CAISO show cause order as to each of them. They say they are exempt from FERC jurisdiction under FPA section 201(f).

Asks FERC to: Rescind the June 18, 2026 show cause order against each of the Six Cities as Participating Transmission Owners and waive any notice and comment periods.

Uses the E-10 CAISO show cause order's offer to rescind the order against non-public utilities at their request. FERC granted this motion on August 14, 2026.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. Each city runs a municipal system inside CAISO's area and depends on CAISO and SCE to deliver most of its resources.
    the Cities are dependent upon the CAISO and SCE for the delivery of the majority of these resources. PDF p. 2
  2. The cities are non-public utilities exempt under FPA section 201(f), the ground the show cause order named for rescission on request.
    Each of the Six Cities is a non-public utility that is exempt from the Commission’s jurisdiction pursuant to Section 201(f) of the Federal Power Act. PDF p. 3
  3. The cities promise to coordinate with CAISO on the response and on their TO Tariff load interconnection provisions.
    the Six Cities will coordinate and cooperate with the CAISO in responding to the Show Cause Order, to the extent that the CAISO requests assistance from the Six Cities PDF p. 4
  4. CAISO supports the motion, and each city will file its own TO Tariff changes if needed.
    The Six Cities have conferred with the CAISO and are authorized to state that the CAISO supports this motion. PDF p. 4
Contents · 4 sections
  1. I. DESCRIPTION OF THE SIX CITIES p. 2
  2. II. RELEVANT BACKGROUND p. 3
  3. III. JUSTIFICATION FOR RESCISSION p. 3
  4. IV. CONCLUSION p. 5

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

- 1 - UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Citizen S-Line Transmission LLC Citizens Sunrise Transmission LLC Citizens Sycamore-Penasquitos Transmission LLC City of Anaheim, California City of Azusa, California…
Read this passage

I. DESCRIPTION OF THE SIX CITIES

printed heading

DESCRIPTION OF THE SIX CITIES Each of the Six Cities operates a municipal electric system that is located within the CAISO Balancing Authority Area.
Read this passage

II. RELEVANT BACKGROUND

printed heading

RELEVANT BACKGROUND On June 18, 2026, the Commission issued the Show Cause Order, thereby initiating a proceeding under Section 206 of the Federal Power Act.
Read this passage

III. JUSTIFICATION FOR RESCISSION

printed heading

In requesting recission of the Show Cause Order, the Six Cities will coordinate and cooperate with the CAISO in responding to the Show Cause Order, to the extent that the CAISO requests assistance from the Six Cities and with respect to provisions in the Cities’ TO Tariffs that pertain to load…
Read this passage

IV. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, the Six Cities respectfully request that the Commission rescind the Show Cause Order against each of the Cities as non-public utilities and ask that the Commission waive any notice and comment periods that might be applicable to this motion.