EL26-67-000 · 2026-08-03 · PJM Industrial Customer Coalition

Answer in Support of the PJM Industrial Customer Coalition to the Motions for Extension and Abeyance by PJM Interconnection, L.L.C

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)

Docket No. EL25-49-002
)

Docket No. EL25-49-000

)
Large Loads Co-Located at Generating Facilities
)

Docket No. AD24-11-001

)
Constellation Energy Generation, LLC

)

v.

)

Docket No. EL25-20-001
PJM Interconnection, L.L.C.

)

(Consolidated)

)
PJM Interconnection, L.L.C.

)

Docket No. ER26-1479-000

)
PJM Interconnection, L.L.C.

)

Docket No. EL26-67-000

ANSWER IN SUPPORT OF
THE PJM INDUSTRIAL CUSTOMER COALITION
TO THE MOTIONS FOR EXTENSION AND ABEYANCE
BY PJM INTERCONNECTION, L.L.C.

Pursuant to Rule 213 of the Federal Energy Regulatory Commission (“Commission”) Rules of Practice and Procedure and the requests for a shortened answer period of PJM Interconnection, L.L.C. (“PJM”),1 PJM Industrial Customer Coalition (“PJMICC”) hereby files this Answer in support of PJM’s Motion for Extension of Time for Specified Compliance Requirements and Request for Expedited Treatment of PJM Interconnection, L.L.C. in Docket No. EL25-49, et al. (“Co-Located Load Extension Motion”) and Motion of PJM Interconnection, L.L.C. to Hold Proceeding in Abeyance and Request For Shortened Answer Period and Expedited Treatment in Docket No. EL26-67 (“Large Load Abeyance Motion”), both of which were filed on

1 See 18 C.F.R. § 385.213.

PDF page 2

- 2 -
July 28, 2026.2 These Motions both request that the Commission extend certain PJM filing deadlines by 90 days.

In its Co-Located Load Extension Motion, PJM explains: “The compliance changes
directed in this proceeding significantly relate to or overlap with the directives in the Large Load Order in three major areas: expansion of new transmission services, study procedures, and operational requirements.”3 To facilitate the stakeholder process and to allow for coordination on the Co-Located Load docket and the Large Load docket, PJM seeks a parallel ninety-day extension for both proceedings, which will result in filings by mid-November.4

PJM further states:
Given the interrelated nature of a number of the other requirements in the
Compliance Order and Large Load Order, a coordinated approach on the
remaining compliance matters is appropriate for consistency and efficiency.
As noted above, both orders require PJM to propose Tariff changes to address the
study procedures to interconnect Co-Located/Large Loads, make new transmission
services available for customers that are willing and able to limit their withdrawals, and specify operational requirements for Co-Located/Large Loads. PJM proposes

to address these interrelated requirements in a suite of filings to be submitted by
early to mid-November following a period of intensive stakeholder engagement and
feedback.5

PJMICC agrees with PJM’s proposed approach, which facilitates administrative
efficiencies and helps consolidate stakeholder and party resources and work efforts.6 PJMICC

2 Also on July 28, 2026, certain PJM Transmission Owners (“Indicated Transmission Owners”) filed parallel pleadings: (1) Motion for Extension of Compliance Deadline of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period in Docket No. EL25-49, et al.; and (2) Motion for Abeyance of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period in Docket No. EL26-67. PJMICC also supports the requests of the Indicated Transmission Owners for extension and abeyance, respectively, until November 16, 2026.

3 Co-Located Load Extension Motion at 4 (emphasis added).
4 Id. at 6. PJM also pledges to complete a partial compliance filing by August 17, 2026. Id.
5 Id. at 7-8 (emphasis added).
6 See Motion for Extension of Compliance Deadline of the Indicated PJM Transmission Owners, Docket No. EL25- 49 et al., at 7 (emphasizing the importance of coordination to ensure Commission review of proposed reforms “in a coherent and administratively efficient fashion.”).

PDF page 3

- 3 -
believes that such a 90-day time frame is proportionate to the reforms the Commission is pursuing. The Commission, PJM, and many stakeholders have been working hard to ensure all stakeholder voices and perspectives are considered. Many of these participants have raised nuanced but important issues that include significant downstream effects of the Commission’s major orders in these dockets. To execute on the Commission’s reforms in a logical, coherent, and durable manner, these nuanced issues must be addressed thoroughly and carefully in a coordinated fashion. In summary, PJMICC agrees with PJM that the above-captioned proceedings raise

complex issues that are necessarily interrelated and that require significant analysis. In pursuit of durable final orders that provide the industry with regulatory stability and clear direction toward investment, growth, and resource adequacy, PJM’s plan to ensure robust discussion within the PJM stakeholder process—and adequate time to ensure both proceedings are complementing and not contradicting one another—is reasonable. Even a 90-day extension is still potentially an aggressive timeline, but it better strikes the balance between the FERC’s urgent call for reforms and the need for time to create a durable compliance filing. PJMICC therefore respectfully requests that the Commission grant PJM’s Co-Located Load Extension Motion and Large Load Abeyance Motion.

PDF page 4

- 4 -
WHEREFORE, the PJM Industrial Customer Coalition supports PJM Interconnection, L.L.C.’s Co-Located Load Extension Motion and Large Load Abeyance Motion and respectfully requests that the Commission grant those Motions in an expedited fashion.

Respectfully submitted,
McNEES WALLACE & NURICK LLC
/s/  Matthew L. Garber
By______________________________
Susan E. Bruce
Kenneth R. Stark
Matthew Garber
McNees Wallace & Nurick LLC
100 Pine Street
Harrisburg, PA 17101
Phone/Fax:  (717) 237-5254
E-mail:  sbruce@mcneeslaw.com
              kstark@mcneeslaw.com
              mgarber@mcneeslaw.com

Counsel to PJM Industrial Customer Coalition

Dated:  August 3, 2026

PDF page 5

CERTIFICATE OF SERVICE

I hereby certify that I have this day served, via first-class mail, electronic transmission, or hand-delivery, the foregoing upon each person designated on the official service list compiled by the Secretary in this proceeding.  Dated this 3rd day of August 2026.

/s/ Matthew Garber

Matthew Garber
McNees Wallace & Nurick LLC
100 Pine Street
Harrisburg, PA 17101
Phone/Fax: (717) 237-5433
E-mail:  mgarber@mcneeslaw.com