Motion to Hold Filing Obligation in Abeyance of DCR Transmission, L.L.C
DCR Transmission, owner of the 125-mile Ten West Link line between Arizona and California, asks FERC to hold the show cause proceeding in abeyance until November 16, 2026. It previews the section 205 tariff revisions it expects to propose.
Asks FERC to: Hold the proceeding, including the briefing question deadline, in abeyance for 90 days through November 16, 2026.
Requests the up-to-90-day abeyance option in the E-10 CAISO show cause order and previews tariff changes on the study process, cost transparency and the cost recovery agreement. FERC granted it August 14, 2026.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25)
Key points
- DCRT owns the 125-mile, 500 kV Ten West Link, about 100 miles of it in Arizona but all inside the CAISO balancing authority area.
DCRT owns and manages the 125-mile, 500 kilovolt Ten West Link Transmission Line PDF p. 2
- As a transmission-only company with no load or network customers, DCRT says franchised-utility tariff provisions do not fit it.
DCRT is not a Load Serving Entity (“LSE”), has no network customers, and every mile of its transmission facility is part of the CAISO controlled grid PDF p. 3
- A large load withdrawing near the Arizona end would run against the line's prevailing westbound flows.
a large load withdrawing energy at or near the Arizona portion of the line would run counter to those prevailing flows. PDF p. 4
- DCRT questions whether the 50 MW large load threshold suits its system.
it is not clear to DCRT that a 50 MW threshold is appropriate. PDF p. 8
- DCRT plans a single-location cost data posting and a pro forma cost recovery agreement, and must resolve California and Arizona jurisdiction over construction.
DCRT must resolve the state-level issue of which entity will have the right to construct assets interconnecting with DCRT’s line PDF p. 11
- DCRT's filing would track the CAISO proposal, which the CAISO Board takes up October 28, 2026.
DCRT’s proposed November 16, 2026 filing will address each of the OSC’s directives that implicates DCRT’s TO Tariff, based on the CAISO proposal then before the Commission. PDF p. 14
- DCRT asks that the briefing question deadline also be tolled for 90 days.
DCRT requests that the deadline to respond to the briefing questions also be tolled for 90 days. PDF p. 14
Contents · 9 sections
- I. BACKGROUND
- II. MOTION FOR ABEYANCE
- A. The OSC Requires Substantial Coordination by Multiple Stakeholders and
- III. PROPOSED TO TARIFF REVISIONS
- A. Transmission Service to Eligible Customers on Behalf of Large Loads
- B. Cost Shifting Risk Among Transmission Customers
- C. Co-Location Arrangements; Flexible Transmission Services; Electrically
- D. Briefing Questions
- IV. CONCLUSION
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Pursuant to Rules 206, 212, and 213 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure,1 DCR Transmission, L.L.C. (“DCRT”) respectfully submits this motion for abeyance of the above-captioned proceeding established by the Commission’s June 18,…Read this passage
I. BACKGROUND
printed heading · Topic match: Reliability and curtailment
It does mean, however, that the potential tariff provisions DCRT develops in response to the OSC may not necessarily be adapted from the integrated-utility model; they must be drafted for the transmission-only context, and this distinction is what primarily drives DCRT’s requested abeyance.Read this passage
II. MOTION FOR ABEYANCE
printed heading · Topic match: Filing procedure
MOTION FOR ABEYANCERead this passage
A. The OSC Requires Substantial Coordination by Multiple Stakeholders and
printed heading · Topic match: Filing procedure
DCRT therefore respectfully requests an abeyance until November 16, 2026, so that DCRT can conduct the process described above thoughtfully and thoroughly, yet with “all due deliberate haste,”6 to promote cost-effective economic growth in DCRT’s footprint.Read this passage
III. PROPOSED TO TARIFF REVISIONS
printed heading
PROPOSED TO TARIFF REVISIONS The following subsections describe the content DCRT anticipates proposing in its section 205 filing to address each of the Commission’s preliminary findings.Read this passage
A. Transmission Service to Eligible Customers on Behalf of Large Loads
printed heading
DCRT will define “Large Load” when developing potential tariff revisions; however, it is not clear to DCRT that a 50 MW threshold is appropriate.18 DCRT’s proposed revisions will outline the transmission service application process, study procedures, and ongoing operational requirements that the…Read this passage
B. Cost Shifting Risk Among Transmission Customers
printed heading · Topic match: Cost allocation
As stated above, DCRT is a single-asset Transco that crosses state lines; it must also consider federal-state jurisdictional cost-allocation issues when interconnecting large loads.Read this passage
C. Co-Location Arrangements; Flexible Transmission Services; Electrically
printed heading · Topic match: Connecting load and generation
Based on the CAISO’s stakeholder process timeline, revisions to the CAISO Tariff will likely not be finalized until close to the requested November 16 filing deadline if the CAISO is granted an abeyance.Read this passage
D. Briefing Questions
printed heading · Topic match: Filing procedure
Briefing Questions The Commission also identifies several issues for further briefing. 37 DCRT requests that the deadline to respond to the briefing questions also be tolled for 90 days. 38 DCRT so requests because the briefing questions are inextricably linked with the issues to be addressed in…Read this passage
IV. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION DCRT respectfully requests that the Commission grant this Motion for Abeyance and extend DCRT’s deadline to respond in full to the OSC to November 16, 2026, for the reasons described above.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 3rd day of August 2026.Read this passage