EL26-71-000 · 2026-08-03 · Western Area Power Administration

Motion to Rescind Show Cause Order as applied to Western Area Power Administration

The Western Area Power Administration moves to rescind the CAISO show cause order as to it. WAPA is a federal power marketing administration whose only CAISO-controlled asset is its share of the Path 15 Upgrade line.

Asks FERC to: Rescind the June 18, 2026 show cause order against WAPA as a Participating Transmission Owner and waive any notice and comment periods.

Uses the E-10 CAISO show cause order's offer to rescind the order against non-public utilities at their request. FERC granted this motion on August 14, 2026.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. WAPA placed only its Path 15 Upgrade Project interests under CAISO operational control, an 83-mile 500-kilovolt line.
    WAPA only placed under the operational control of the CAISO its rights and interests in the Path 15 Upgrade Project, a single, approximately 83-mile, 500-kilovolt transmission line PDF p. 3
  2. WAPA keeps the right to use its own tariff for interconnections to the Path 15 Upgrade where CAISO provisions are inconsistent.
    including use of its own Tarif or OATT for interconnections to the Path 15 Upgrade to the extent the CAISO provisions are inconsistent. PDF p. 3
  3. WAPA is exempt from FERC jurisdiction under FPA section 201(f) as a federal entity.
    WAPA is a non-public utility that is exempt from the Commission’s jurisdiction pursuant to Section 201(f) of the Federal Power Act. PDF p. 4
  4. WAPA will keep coordinating with CAISO and file tariff revisions if it finds changes are needed.
    WAPA will file proposed revisions to its Tariff with the Commission in due course. PDF p. 4
Contents · 4 sections
  1. I. WAPA Background p. 2
  2. II. relevant background p. 3
  3. III. justification for rescission p. 4
  4. IV. CONCLUSION p. 5

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

- 1 - UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Citizen S-Line Transmission LLC Citizens Sunrise Transmission LLC Citizens Sycamore-Penasquitos Transmission LLC City of Anaheim, California City of Azusa, California…
Read this passage

I. WAPA Background

PDF bookmark

WAPA BACKGROUND WAPA is a power marketing administration of the U.S.
Read this passage

II. relevant background

PDF bookmark

RELEVANT BACKGROUND On June 18, 2026, the Commission issued the Show Cause Order, thereby initiating a proceeding under Section 206 of the Federal Power Act.
Read this passage

III. justification for rescission

PDF bookmark

JUSTIFICATION FOR RESCISSION WAPA is a non-public utility that is exempt from the Commission’s jurisdiction pursuant to Section 201(f) of the Federal Power Act.4 The Commission acknowledged that the Show Cause Order included Participating TOs that are not subject to the Commission’s jurisdiction…
Read this passage

IV. CONCLUSION

PDF bookmark

CONCLUSION WHEREFORE, for the foregoing reasons, WAPA respectfully requests that the Commission rescind the Show Cause Order against WAPA as a non-public utility and ask that the Commission waive any notice and comment periods that might be applicable to this motion.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Ben Summerhays Attorney for Western Area Power Administration Western Area Power Administration 12155 W.