Motion for Abeyance and Request for Shortened Answer Period and Expedited Treatment of LS Power Grid New York Corporation I and New York Transco LLC
LS Power Grid New York Corporation I and New York Transco LLC, the Non-Incumbent TOs, move for a 90-day abeyance of the EL26-69 show cause response to November 16, 2026, with a five-day answer period and an order by August 13.
Asks FERC to: Hold the proceeding in abeyance for 90 days from August 17, extend the response deadline to November 16, 2026, shorten the answer period to five days, and rule by August 13.
Uses the abeyance option in the E-12 NYISO order to defer the 60-day response on the study-window, cost, co-location, flexible-load and proximate-generation findings until November 16, 2026.
E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Timely study window (P 44, p. 31)
Key points
- The NTOs seek a 90-day full abeyance to prepare a section 205 filing alongside NYISO and stakeholders.
The NTOs seek a 90-day full abeyance of the current 60-day deadline to respond to all issues raised in the Show Cause Order PDF p. 1
- They expect the filing to cover large load definition, alternative transmission technologies, a pro forma service agreement, and cost recovery with financial security.
the definition of a large load; readiness and information requirements; the PDF p. 5
- They say their section 205 filing depends on NYISO's stakeholder process because NTOs run no stakeholder process of their own.
NTOs do not administer a stakeholder process of their own through which the issues raised in the Show Cause Order could be resolved independently. PDF p. 8
- Without a shortened answer period, FERC could not rule before the August 17 response deadline.
If the ordinary fifteen-day answer period applies, the Commission will not be in a position to rule on this Motion until after NTOs' response is already due. PDF p. 7
Contents · 6 sections
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-69-000 MOTION FOR ABEYANCE AND REQUEST FOR SHORTENED ANSWER PERIOD AND EXPEDITED TREATMENT OF LS POWER GRID NEW YORK CORPORATION I AND NEW YORK TRANSCO LLCRead this passage
I. INTRODUCTION
PDF bookmark · Topic match: Filing procedure
The NTOs believe the potential tariff changes discussed in the Show Cause Order may provide opportunities for the NYISO and the transmission owning members of NYISO (“NYISO TOs”) to integrate large loads efficiently and further protect ratepayers across the NYISO region from transmission-related…Read this passage
II. ARGUMENT
PDF bookmark · Topic match: Filing procedure
ARGUMENT In the Show Cause Order, the Commission states that it will consider requests for abeyances of up to 90 days, which should include both (1) a robust description of the content of a potential future filing under FPA section 205 and (2) a reasoned and specific explanation of when such a…Read this passage
A. Proposed Tariff Revisions
PDF bookmark · Topic match: Connecting load and generation
NYISO-specific regional differences must also be considered.Read this passage
B. Briefing Questions
PDF bookmark · Topic match: Filing procedure
Briefing Questions The Commission also identifies several issues for further briefing.15 The NTOs understand that, if the Commission grants the requested full abeyance, the deadline to respond to the briefing questions will likewise be held in abeyance.16 The NTOs believe an abeyance is appropriate…Read this passage
III. request for shortened answer period and expedited treatment
PDF bookmark · Topic match: Filing procedure
The Commission directed that requests for a full or partial abeyance be submitted "within 45 days of issuance of this order, to allow time for the Commission to act on the abeyance request." Id. 21 Five days from the August 3, 2026 filing date is Saturday, August 8, 2026, which Rule 2007 moves to…Read this passage
IV. Conclusion
PDF bookmark · Topic match: Filing procedure
CONCLUSION For the reasons described above, the NTOs respectfully request that the Commission (i) grant this Motion and hold this proceeding in abeyance for 90 days beginning August 17, 2026, and extend NTOs’ deadline to respond in full to the Show Cause Order to November 16, 2026; (ii) shorten the…Read this passage
CERTIFICATE OF SERVICE
printed heading · Topic match: Filing procedure
Dated at Silver Spring, Maryland, this 3rd day of August 2026. /s/ Seth Yeazel Seth Yeazel Associate Regulatory Counsel LS Power Development, LLC 16150 Main Circle Drive, Suite 310 Chesterfield, MO 63017 Tel: (240) 904-5109 syeazel@lspower.comRead this passage