EL26-68-000 · 2026-08-07 · Southwest Power Pool Regional State Committee

Comments of the Southwest Power Pool Regional State Committee in support of Southwest Power Pool, Inc.’s request for an extension of time until 11/20/2026 to respond to the FERC's 06/18/2026 Order to Show Cause

PDF page 1

August 7, 2026

The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426

RE:
Southwest Power Pool Abeyance Request; Docket No. EL26-68-000

Dear Secretary Reese,
The Southwest Power Pool Regional State Committee (RSC) respectfully submits this letter in support of Southwest Power Pool, Inc.’s (SPP) request for an extension of time, until November 20, 2026, to respond to the Commission’s June 18, 2026, Order to Show Cause in the above- referenced proceeding.

The Commission’s order raises significant and complex issues concerning the integration of large loads, including how to mitigate the risk that transmission costs attributable to large-load development may be shifted to other transmission customers. These issues directly implicate the RSC’s responsibility within the SPP regional governance structure for determining regional proposals concerning the allocation of transmission costs.

The RSC, working through SPP’s Cost Control and Allocation Review and Evaluation (CARE) Team, is currently considering potential measures to mitigate cost-shift risks associated with large load customers. Among other matters, the CARE Team is evaluating approaches for assigning or securing responsibility for transmission costs driven by new large loads, particularly when projected load does not materialize as anticipated or does not remain on the system for the period used to justify transmission investment.

The CARE Team expects to develop a recommendation for consideration by the RSC and the SPP Board of Directors during their quarterly business meetings on November 16 and 17, 2026. That recommendation will reflect substantial analysis and regional stakeholder and state-regulatory input regarding matters that are related to the cost-shifting concerns identified in the Commission’s order.

Granting the requested extension would allow the RSC and SPP to complete this established regional process and would enable SPP’s response to more fully reflect the resulting recommendations. It would also promote the development of a thoughtful, durable, and regionally

PDF page 2

The Honorable Debbie-Anne A. Reese
August 7, 2026
Page 2

tailored approach that recognizes the respective roles of SPP, its stakeholders, and state regulatory authorities.

The RSC recognizes the urgency of addressing the challenges presented by rapid large-load growth and does not seek unnecessary delay. Rather, the additional time would support a more comprehensive response and could reduce the need for subsequent revisions or supplemental filings as the CARE Team’s work is completed.

For these reasons, the RSC respectfully supports SPP’s request for an extension of time in Docket No. EL26-68-000.

Respectfully submitted
/s/ Chuck Hutchison
Chuck Hutchison
Chairman, Nebraska Power Review Board
President, Southwest Power Pool Regional State Committee

On Behalf of the Regional State Committee

PDF page 3

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Little Rock, Arkansas, this 7th day of August, 2026.

 /s/ Michelle Harris
Michelle Harris
On Behalf of the
Southwest Power Pool Regional State Committee
201 Worthen Drive
Little Rock, AR 72223-4936
(501) 614-3200