EL26-67-000 · 2026-08-07 · Corporate Energy Buyers Association
Answer of Corporate Energy Buyers Association in support of PJM Interconnection, L.L.C.'s et al. 07/28/2026 Motion for Abeyance
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL26-67-000
ANSWER OF CORPORATE ENERGY BUYERS ASSOCIATION
IN SUPPORT OF THE MOTIONS FOR ABEYANCE
Pursuant to Rule 213 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure,1 Corporate Energy Buyers Association (CEBA) respectfully submits this Answer in support of the motions for abeyance submitted separately by PJM Interconnection, L.L.C. (PJM),2 Indicated PJM Transmission Owners,3 and Silver Run Electric, LLC4 (collectively, Movants). Movants ask the Commission to hold this proceeding in abeyance by 90 days and, in so doing, extend certain deadlines for responding to the June 18, 2026 Order to Show Cause (Show Cause Order).5
The issues raised in the Show Cause Order raise complex and substantial issues that require due consideration to craft solutions that are appropriately tailored to the region. Granting the requested abeyance will promote administrative efficiencies by allowing time for PJM and stakeholders—including CEBA and its members—to work collaboratively, as opposed to a rushed proposal that would unnecessarily shift stakeholder debate to the Commission docket. Lastly, the requested abeyance also strikes an appropriate balance: a 90-day extension would not materially impede the Commission’s objectives for advancing reforms quickly yet offers
1 18 C.F.R. § 385.213.2 PJM July 28, 2026 Motion for Abeyance.3 Indicated PJM Transmission Owners July 28, 2026 Motion for Abeyance. 4 Silver Run Electric, LLC August 3, 2026 Motion for Abeyance.5 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026).
PDF page 2
2
significant benefits in terms of enabling proposals to receive sufficient stakeholder feedback to promote both commercial viability and legal durability of the proposals that PJM and the PJM transmission owners will file in mid-November.
For these reasons, CEBA respectfully requests that the Commission grant these motions in an expedited manner.
Respectfully submitted,
/s/ John Miller___________________
John Miller
Director, Transmission Policy
CEBA
1501 M Street, N.W., Suite 900
Washington, D.C. 20005
(240) 630-2201
jmiller@ceba.org
Bryn Baker
Senior Director, Organized Markets Policy
CEBA
1501 M Street, N.W., Suite 900
Washington, D.C. 20005
bbaker@ceba.org
August 7, 2026
PDF page 3
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.
Dated at Washington, D.C., this 7th day of August 2026.
/s/ John Miller___________________
John Miller
Director, Transmission Policy
CEBA
1501 M Street, N.W., Suite 900
Washington, D.C. 20005
(240) 630-2201
jmiller@ceba.org